The Ground Hazard Risk Assessment Report is the form the EIC takes to the site. It records what is found there, frames up to three stabilization alternatives, and rates the site as it stands and after each alternative. It is issued to the railroad the same day as a field copy draft, followed by a formal report within one week.
The previous worksheet was a single page that began with general site information. The desktop study was handed over as a separate package, and the EIC had to carry the preliminary scores, thresholds and questions on other sheets or from memory. The reworked report is three sheets, and the first is new:
The result is that the engineer arrives with the desk’s reasoning in hand, the field evidence is recorded against it item by item, and every difference between desk and field is written down where it can later be used to calibrate the desk scores and thresholds.
Cell shading and text styles show where each entry comes from and when it is made.
Red text marks entries that must be confirmed with the railroad contact before the form is issued (the number of tracks and which is higher, and any railroad workload conflict). Blue italic marks the measurement and frequency of each reported geometry defect. In the checklist blocks, mark (✓ or X) every item that applies and leave the rest blank; a blank means the item was looked for and not found. Write photo numbers, dimensions or a short note beside each marked item.
| Sheet | Block | What is recorded | Question it answers | Section |
|---|---|---|---|---|
| 1 | A. Desktop study summary | Network screening, driving mechanism, situational and instability scores, static rating, H&H thresholds, live rating at visit, questions | What did the desk find, and what does the field need to check? | 3.8.42.3 (from 3.8.23 to 3.8.26) |
| 2 | 1. General site information | Client, contacts, location, track and traffic data, protection, site setting | Where is the site, and what does the railroad have at stake? | 3.8.42.4 |
| 2 | 2. Site conditions | Indicators on the left embankment, between the rails and on the right embankment | What is the ground telling us? | 3.8.24.4 |
| 2 | 3. Site instabilities | Major element affected, construction constraints, estimated failure type | What is failing, and what limits the fix? | 3.8.24.5 |
| 3 | 4. Recommended stabilization items | Engineering, drainage, earthwork and structural measures, by alternative | What would fix it? | 3.8.42.6 |
| 3 | 5. Additional services | Exploration, field testing and engineering by alternative, with low and high cost | What is needed to confirm and design the fix, and what will it cost? | 3.8.42.6 |
| 3 | 6. Risk rating | F, S, R and rating: preliminary, live, current and each alternative | How much risk is there now, and how much does each alternative remove? | 3.8.42.7 |
Workflow.
Download the blank report form (PDF, three sheets) for printing. Each sheet is shown under the description of its blocks below; click a sheet to zoom and pan.
Block A carries the desk’s findings into the field. It is prepared by whoever completed the desktop study and checked by the EIC before mobilizing. The sheet is shown in Figure 3.8-48. Its eight parts follow the order of Sections 3.8.23 to 3.8.26:

Using the field column. Confirm each value with a check, or write the revised value. Revise a desk score only on evidence seen at the site, and note the evidence. The EIC does not recompute LS, L or C in the field: the field rating in Block 6 is set from the field defect rating, the confirmed trigger and the desk Fg (Table 3.8-27 and Table 3.8-11) and from the exposure (Table 3.8-15). The revised attribute scores are returned to the desk after the visit, where they update the site record and calibrate later desk studies. The toe, culvert outlet and culvert elevations checked in A7 are the first refinement of the H&H thresholds.
The desktop package still includes the site map or KMZ, the site history summary and, where prepared, the Site Background Report. Mark which are attached at the foot of Block A.
Block 1 identifies the site and records what the railroad has at risk. Most entries come from the railroad before the visit; the rest are recorded on site. Block 1 is on Sheet 2 with Blocks 2 and 3, shown in Figure 3.8-49.

| Group | Fields |
|---|---|
| Client and contacts | Client; railroad subdivision; project number; railroad contact and phone; EIC and phone |
| Location and protection | Milepost; from MP and to MP; on-site protection type (for example foul time, track and time, or a watchman/lookout); place of safety; date |
| Operations | Operational characteristic (main line, siding, yard or industry; freight, passenger or mixed; hazardous materials); average daily train traffic; number of tracks (and which is higher, or whether they are at the same elevation); normal speed; slow order speed; date of last issue |
| Affected length | Affected track length (ft), measured on site |
| Site setting | Current weather; geologic setting; track cross section (cut or fill); alignment (tangent, inside or outside of curve); track setting (marsh, valley, or slope: top, mid or bottom); population density factor |
Why it matters. Train traffic, normal speed, the number of tracks, train type and the population density factor are the exposure that sets the hazard severity. They were scored at the desk as C1 to C5 (Block A4); Block 1 confirms them on site. If they disagree, mark the check row and revise S in Block 6. An error here changes the rating. The slow order speed and the date of the last issue show how the railroad is already managing the hazard. The affected track length scales every cost in Block 5 and should be stated with each alternative.
Blocks 2 and 3 are the field half of the instability rating. How to orient the form, walk the site, record defects with their measurement and frequency, and read the pattern of indicators is described in Section 3.8.24.4; the major element, construction constraints and failure type in Section 3.8.24.5. Two points apply to the reworked form:
Block 4 lists the measures that could stabilize the site, grouped by discipline. Mark every item that belongs in at least one alternative and write the alternative number(s) beside it; this is what links Block 4 to the three alternative columns of Blocks 5 and 6. Blocks 4 and 5 are on Sheet 3 with Block 6, shown in Figure 3.8-50.

| Engineering studies | Engineering disciplines | Drainage | Earthwork | Structural |
|---|---|---|---|---|
| Site monitoring: track forces | Hydraulics and hydrology (H&H) | Dewater | Grading | Load transfer |
| Site monitoring: instrumentation | Geotechnical | Remove obstruction | Stiffen subgrade | Earth retention |
| H&H study | Structural | Ditching | Remove and replace | Repair |
| Geotechnical exploration | Civil | Erosion control | Counter (toe) berm | Replace |
Order of preference. Follow the risk control hierarchy of Section 1.1.9: remove the cause first (water is the most common one: dewater, remove the obstruction, ditch), then reduce the load or driving force (grading), then add resistance (counter berm, stiffen subgrade, earth retention, load transfer). Use monitoring and operating restrictions to manage the remaining risk while the permanent fix is designed and built. The driving mechanism in Block A2 usually points to the first measure. A useful set of alternatives is often a quick, low-cost measure (Alternative 1), a medium measure (Alternative 2) and the long-term structural answer (Alternative 3). Monitoring and instrumentation are covered in Chapter 5.3, earth retention in Chapter 7.1, and ground improvement in Chapter 7.2 and its technology library (Section 7.2.16).
Ground improvement level. An earlier version of the worksheet carried three levels of ground improvement. They remain a useful shorthand when an alternative depends on ground improvement: low for drainage-led and surface measures; medium for local treatment such as lateral drains, a toe berm or compaction grouting; and robust for structural or deep measures such as soldier piles and lagging, deep mixing or track realignment.
Block 5 turns the recommendation into a scope. For each service, mark (or enter a quantity, such as the number of borings or inclinometers) under each alternative that needs it, and give a low and high estimated cost, so the railroad sees a range rather than a single number that looks more precise than it is.
| Service group | Items | Recorded for each item |
|---|---|---|
| Subsurface exploration | Surveying; soil survey borings; modified SPT soil survey borings; SPT borings | Alternatives 1–3 that need it; estimated cost, low and high |
| Field testing | Dynamic cone penetrometer (DCP); field CBR; inclinometer; piezometer; lateral trench test pit; ground penetrating radar (GPR) | Alternatives 1–3 that need it; estimated cost, low and high |
| Engineering | Laboratory testing; geotechnical analysis; structural analysis; design bid package; construction monitoring | Alternatives 1–3 that need it; estimated cost, low and high |
Each service ties to a chapter of this manual: exploration planning to Chapter 3.9; borings and SPT to Chapter 4.1; DCP, field CBR and GPR to Chapter 5.1; piezometers to Chapter 2.8; inclinometers to Section 5.3.8; laboratory testing to Chapter 5.2; and slope analysis to Chapter 6.3. Field testing on an operating railroad is done in work windows, so note when each test can be done. The level of effort set by the static rating (Table 3.8-29) is a guide to how much exploration to scope.
Alternative notes. On Sheet 3, write a short paragraph for each alternative: what it consists of, the services it needs, how long it will take (Table 3.8-90), and the risk rating expected once it is built. These notes become the alternatives section of the formal report (Chapter 8.4).
Block 6 rates the site using the scales and matrix of Section 3.8.22. It has six columns:
If the live rating at the visit was above the static rating, judge whether the indicators seen are those of the event or of the site’s usual state, and say so in the reason. Record any one-level adjustment (Section 3.8.22.6) and, where the field rating differs from the preliminary rating by more than one level, the reason.
When an alternative includes ground improvement or another stabilization method, the report’s companion sheet sets the analysis it needs, the field and laboratory testing that support the analysis, and the quality control that shows the method worked. The field testing column also records when the test can be done around traffic.
| Method | Analysis required | Field testing | Laboratory testing (standard) | Quality control |
|---|---|---|---|---|
| Preloading and surcharging | Consolidation analysis | SPT during off-peak hours | Triaxial compression (ASTM D4767-11(2020)) | Pore pressure measurement |
| Sand drains | Consolidation analysis | CPT coordinated with rail operations | Unconfined compression (ASTM D2166/D2166M-24) | Settlement monitoring |
| Vibro-compaction | Shear strength analysis | SPT during off-peak hours | Consolidation (ASTM D2435) | Pore pressure measurement |
| Deep mixing | Shear strength analysis | CPT coordinated with rail operations | Triaxial compression (ASTM D4767-11(2020)) | Settlement monitoring |
| Grouting | Liquefaction analysis | SPT or CPT with minimal disturbance | Unconfined compression (ASTM D2166/D2166M-24) | Pore pressure measurement and settlement monitoring |
| Compaction grouting (low-mobility grout to 20 ft below toe of slope) | Ground stabilization analysis | SPT or CPT to verify treatment; GPR | Compressive strength (ASTM C39/C39M-26) | Ground movement monitoring |
| Ballast removal and replacement | Material contamination analysis | SPT or CPT during maintenance windows | Particle size distribution (ASTM D6913; D422 was withdrawn in 2016) | Track settlement monitoring |
| Lateral drains | Seepage analysis | SPT or CPT with piezometer installation; GPR | Permeability (ASTM D5084-24) | Pore pressure and water table monitoring |
| Toe berm | Slope stability analysis | SPT or CPT at the berm location; GPR | Direct shear (ASTM D3080/D3080M-23) | Slope monitoring |
| Embankment widening | Lateral stability analysis | SPT or CPT along the embankment; GPR | Compaction (ASTM D1557) and shear strength | Lateral movement monitoring |
| Soldier piles and lagging | Structural stability analysis | SPT or CPT at pile locations; GPR | Load test (ASTM D1143 axial; ASTM D3966 lateral) | Structural monitoring |
| Track realignment away from top of slope | Track stability analysis | GPR; SPT or CPT during off-peak hours | Compaction (ASTM D698 or D1557) | Track alignment monitoring |
The standards and editions are those listed on the worksheet. Confirm the current edition, and that the standard fits the test intended, when the testing program is written. Method descriptions, design procedures and acceptance criteria are in Chapter 7.2; monitoring methods and trigger levels are in Chapter 5.3.
When alternatives are first framed in the field, before quantities exist, a relative ranking of cost and time is enough to tell a quick, inexpensive fix from a long capital project. Table 3.8-90 lists the methods in the same order as Table 3.8-89. Completion time is scored from 1 to 5; the scores used are 2 (about 1 week), 3 (about 3 months) and 5 (over 1 year).
| Method | Relative cost | Completion time (score) |
|---|---|---|
| Preloading and surcharging | Low | Over 1 year (5) |
| Sand drains | Medium | About 3 months (3) |
| Vibro-compaction | High | About 3 months (3) |
| Deep mixing | High | About 3 months (3) |
| Grouting | High | About 3 months (3) |
| Compaction grouting (low-mobility grout to 20 ft below toe of slope) | High | About 3 months (3) |
| Ballast removal and replacement | Medium | Over 1 year (5) |
| Lateral drains | Medium | About 1 week (2) |
| Toe berm | Medium | About 3 months (3) |
| Embankment widening | Medium | Over 1 year (5) |
| Soldier piles and lagging | High | Over 1 year (5) |
| Track realignment away from top of slope | High | Over 1 year (5) |
Use the ranking with the risk ratings. Lateral drains, a medium-cost method installed in about a week, can move a Forming, Critical site (R = 12, High) to Inactive (R = 4, Guarded). That may be the right first step even where a high-cost structural fix is the long-term answer.
Before the form leaves your hands, check that every block has been completed or marked “N/A”, that each Block A value has been confirmed or revised, that the photo numbers are recorded and that the red-text entries were confirmed with the railroad. Date the form, send it to a senior technical manager for review and issue it to the railroad as the field copy draft, so operating decisions are not held up while the report is written. The statement printed at the foot of Sheet 3 must stay on every copy:
The formal report follows within one week. It carries the three sheets forward with photographs, a site plan, the desk-to-field comparison from Block A, the reasoning behind the failure type, the F and S levels and the rating, and the recommended alternative with its scope, cost range and expected rating. Report format and content are covered in Chapter 8.4.