3.8.42 The Ground Hazard Risk Assessment Report

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.42 The Ground Hazard Risk Assessment Report

The Ground Hazard Risk Assessment Report is the form the EIC takes to the site. It records what is found there, frames up to three stabilization alternatives, and rates the site as it stands and after each alternative. It is issued to the railroad the same day as a field copy draft, followed by a formal report within one week.

3.8.42.1 What Has Changed in the Form

The previous worksheet was a single page that began with general site information. The desktop study was handed over as a separate package, and the EIC had to carry the preliminary scores, thresholds and questions on other sheets or from memory. The reworked report is three sheets, and the first is new:

  • Sheet 1, Block A — Desktop Study Summary. Every metric determined before the visit is printed on the form: the network screening value and entry route, the driving mechanism, the situational likelihood (L1 to L5) and consequence (C1 to C5) scores, the trigger and trigger rating T, the instability attribute (L6), the geospatial frequency Fg and defect rating D, the preliminary Fp, Sp and static rating, the H&H thresholds, the live rating on the day of the visit, and the questions for the field. Each value has a field column beside it, so the EIC confirms it with a check or writes the revised value.
  • Sheet 2, Blocks 1 to 3 keep the content of the previous worksheet, with two check rows added: whether the exposure seen on site agrees with the consequence scores, and whether the failure type agrees with the desk driving mechanism.
  • Sheet 3, Blocks 4 to 6 keep the stabilization items, services and costs, and the risk rating. Block 6 now places the preliminary and live ratings beside the field and alternative ratings, and asks for the reason whenever the field rating differs from the preliminary rating by more than one level.

The result is that the engineer arrives with the desk’s reasoning in hand, the field evidence is recorded against it item by item, and every difference between desk and field is written down where it can later be used to calibrate the desk scores and thresholds.

3.8.42.2 Reading the Form and Workflow

Cell shading and text styles show where each entry comes from and when it is made.

Blue: desktop study values, printed before mobilizing (Block A; preliminary and live columns of Block 6).
Yellow: from the railroad’s request and track data, before the visit (Block 1).
White: recorded on site.
Gray: rating outputs and totals.
Green: block titles and headings; do not write in them.

Red text marks entries that must be confirmed with the railroad contact before the form is issued (the number of tracks and which is higher, and any railroad workload conflict). Blue italic marks the measurement and frequency of each reported geometry defect. In the checklist blocks, mark (✓ or X) every item that applies and leave the rest blank; a blank means the item was looked for and not found. Write photo numbers, dimensions or a short note beside each marked item.

Table 3.8-85. Blocks of the Ground Hazard Risk Assessment Report
SheetBlockWhat is recordedQuestion it answersSection
1A. Desktop study summaryNetwork screening, driving mechanism, situational and instability scores, static rating, H&H thresholds, live rating at visit, questionsWhat did the desk find, and what does the field need to check?3.8.42.3 (from 3.8.23 to 3.8.26)
21. General site informationClient, contacts, location, track and traffic data, protection, site settingWhere is the site, and what does the railroad have at stake?3.8.42.4
22. Site conditionsIndicators on the left embankment, between the rails and on the right embankmentWhat is the ground telling us?3.8.24.4
23. Site instabilitiesMajor element affected, construction constraints, estimated failure typeWhat is failing, and what limits the fix?3.8.24.5
34. Recommended stabilization itemsEngineering, drainage, earthwork and structural measures, by alternativeWhat would fix it?3.8.42.6
35. Additional servicesExploration, field testing and engineering by alternative, with low and high costWhat is needed to confirm and design the fix, and what will it cost?3.8.42.6
36. Risk ratingF, S, R and rating: preliminary, live, current and each alternativeHow much risk is there now, and how much does each alternative remove?3.8.42.7

Workflow.

  1. Before the visit. Print Sheet 1 with Block A filled from the desktop study, and fill the yellow cells of Block 1 from the railroad’s request and track data. On the day of the visit, print or write the live readings in A7. Arrange on-site protection and identify the place of safety.
  2. On site. Hold the job briefing, then walk the site before writing. Complete the white cells of Block 1, then Block 2 looking up station, then Block 3. Work through the field column of Block A and the questions in A8 as you go. Photograph each marked indicator.
  3. Before leaving. Check Block 4 and frame up to three alternatives. Assign the current rating in Block 6 while the evidence is in front of you. If the site is Severe or High, tell the railroad contact before leaving.
  4. After the visit. Complete the Block 5 costs and the ratings for each alternative, write the alternative notes and issue the field copy draft. The formal report follows within one week.

Download the blank report form (PDF, three sheets) for printing. Each sheet is shown under the description of its blocks below; click a sheet to zoom and pan.

3.8.42.3 Block A — Desktop Study Summary

Block A carries the desk’s findings into the field. It is prepared by whoever completed the desktop study and checked by the EIC before mobilizing. The sheet is shown in Figure 3.8-48. Its eight parts follow the order of Sections 3.8.23 to 3.8.26:

  • A1 Static network screening: the segment ID, its CHI value or network rank, the segment event count where available, and the route by which the site entered the program (Section 3.8.25.1).
  • A2 Driving mechanism and trigger: primary and contributing mechanism, with the weighted attribute; the primary trigger, its response level, the trigger rating T and the trigger narrative (Section 3.8.18; Section 3.8.23.3).
  • A3 Situational likelihood: L1 to L5 with weights, basis and LS (Section 3.8.23.4).
  • A4 Consequence: C1 to C5, C with the floor rule, and Sp (Sections 3.8.23.5 and 3.8.23.6).
  • A5 Instability rating: L6, the reported defects and whether they recur, the last slow order, L, Fg, the desk defect rating D and Fp (Section 3.8.24), with cells for the field D from Table 3.8-27 and the field Fc from Table 3.8-11.
  • A6 Static (preliminary) rating: Fp, Sp, Rp, the rating, priority and level of effort (Section 3.8.25).
  • A7 H&H thresholds and live rating: the paired gauge and its action and moderate stages, the toe and damage stages, the site rainfall, culvert capacity and antecedent thresholds, thaw history, and the live readings and live rating on the day of the visit (Sections 3.8.23.7 and 3.8.26).
  • A8 Questions for the field: every attribute scored 3 for lack of data, every feature seen in lidar or imagery that needs checking, and the culverts and outlets to find and measure, with space for the answer and photo number.
Ground Hazard Risk Assessment Report, Sheet 1: Block A Desktop Study Summary (blank)
Figure 3.8-48. Report Sheet 1, Block A — Desktop Study Summary. New in this edition. Every metric from Sections 3.8.23 to 3.8.26 is printed here before mobilizing, with a field column beside it so the EIC can confirm or revise each value on site. Blocks A5 and A6 follow the method of Sections 3.8.18 to 3.8.21: trigger rating, geospatial frequency, defect rating and preliminary current risk.

Using the field column. Confirm each value with a check, or write the revised value. Revise a desk score only on evidence seen at the site, and note the evidence. The EIC does not recompute LS, L or C in the field: the field rating in Block 6 is set from the field defect rating, the confirmed trigger and the desk Fg (Table 3.8-27 and Table 3.8-11) and from the exposure (Table 3.8-15). The revised attribute scores are returned to the desk after the visit, where they update the site record and calibrate later desk studies. The toe, culvert outlet and culvert elevations checked in A7 are the first refinement of the H&H thresholds.

The desktop package still includes the site map or KMZ, the site history summary and, where prepared, the Site Background Report. Mark which are attached at the foot of Block A.

3.8.42.4 Block 1 — General Site Information

Block 1 identifies the site and records what the railroad has at risk. Most entries come from the railroad before the visit; the rest are recorded on site. Block 1 is on Sheet 2 with Blocks 2 and 3, shown in Figure 3.8-49.

Ground Hazard Risk Assessment Report, Sheet 2: Blocks 1 to 3 (blank)
Figure 3.8-49. Report Sheet 2: Block 1 General Site Information, Block 2 Site Conditions and Block 3 Site Instabilities. Blocks 2 and 3 record the field instability evidence of Section 3.8.24; new check rows tie Block 1 and Block 3 back to the desktop values on Sheet 1.
Table 3.8-86. General site information
GroupFields
Client and contactsClient; railroad subdivision; project number; railroad contact and phone; EIC and phone
Location and protectionMilepost; from MP and to MP; on-site protection type (for example foul time, track and time, or a watchman/lookout); place of safety; date
OperationsOperational characteristic (main line, siding, yard or industry; freight, passenger or mixed; hazardous materials); average daily train traffic; number of tracks (and which is higher, or whether they are at the same elevation); normal speed; slow order speed; date of last issue
Affected lengthAffected track length (ft), measured on site
Site settingCurrent weather; geologic setting; track cross section (cut or fill); alignment (tangent, inside or outside of curve); track setting (marsh, valley, or slope: top, mid or bottom); population density factor

Why it matters. Train traffic, normal speed, the number of tracks, train type and the population density factor are the exposure that sets the hazard severity. They were scored at the desk as C1 to C5 (Block A4); Block 1 confirms them on site. If they disagree, mark the check row and revise S in Block 6. An error here changes the rating. The slow order speed and the date of the last issue show how the railroad is already managing the hazard. The affected track length scales every cost in Block 5 and should be stated with each alternative.

3.8.42.5 Blocks 2 and 3 — Site Conditions and Site Instabilities

Blocks 2 and 3 are the field half of the instability rating. How to orient the form, walk the site, record defects with their measurement and frequency, and read the pattern of indicators is described in Section 3.8.24.4; the major element, construction constraints and failure type in Section 3.8.24.5. Two points apply to the reworked form:

  • Compare the indicators with the desk L6 and defect history in Block A5, and record the field defect rating D from Table 3.8-27 and the field Fc from Table 3.8-11 in A5. Fc goes to the current column of Block 6.
  • Compare the estimated failure type in Block 3 with the desk driving mechanism in A2, and complete the check row at the foot of Block 3. A changed mechanism changes the weighted attribute, the H&H thresholds that matter and the live indicators that apply; return it to the desk.

3.8.42.6 Blocks 4 and 5 — Stabilization Items, Services and Cost

Block 4 lists the measures that could stabilize the site, grouped by discipline. Mark every item that belongs in at least one alternative and write the alternative number(s) beside it; this is what links Block 4 to the three alternative columns of Blocks 5 and 6. Blocks 4 and 5 are on Sheet 3 with Block 6, shown in Figure 3.8-50.

Ground Hazard Risk Assessment Report, Sheet 3: Blocks 4 to 6 (blank)
Figure 3.8-50. Report Sheet 3: Block 4 Recommended Stabilization Items, Block 5 Additional Services by alternative with cost range, and Block 6 Risk Rating. Block 6 places the preliminary and live ratings beside the field rating and each alternative’s risk reduction ratings (solution, design, construction stage and post-stabilization), so the change from desk to field to residual risk is visible on one sheet.
Table 3.8-87. Recommended stabilization items
Engineering studiesEngineering disciplinesDrainageEarthworkStructural
Site monitoring: track forcesHydraulics and hydrology (H&H)DewaterGradingLoad transfer
Site monitoring: instrumentationGeotechnicalRemove obstructionStiffen subgradeEarth retention
H&H studyStructuralDitchingRemove and replaceRepair
Geotechnical explorationCivilErosion controlCounter (toe) bermReplace

Order of preference. Follow the risk control hierarchy of Section 1.1.9: remove the cause first (water is the most common one: dewater, remove the obstruction, ditch), then reduce the load or driving force (grading), then add resistance (counter berm, stiffen subgrade, earth retention, load transfer). Use monitoring and operating restrictions to manage the remaining risk while the permanent fix is designed and built. The driving mechanism in Block A2 usually points to the first measure. A useful set of alternatives is often a quick, low-cost measure (Alternative 1), a medium measure (Alternative 2) and the long-term structural answer (Alternative 3). Monitoring and instrumentation are covered in Chapter 5.3, earth retention in Chapter 7.1, and ground improvement in Chapter 7.2 and its technology library (Section 7.2.16).

Ground improvement level. An earlier version of the worksheet carried three levels of ground improvement. They remain a useful shorthand when an alternative depends on ground improvement: low for drainage-led and surface measures; medium for local treatment such as lateral drains, a toe berm or compaction grouting; and robust for structural or deep measures such as soldier piles and lagging, deep mixing or track realignment.

Block 5 turns the recommendation into a scope. For each service, mark (or enter a quantity, such as the number of borings or inclinometers) under each alternative that needs it, and give a low and high estimated cost, so the railroad sees a range rather than a single number that looks more precise than it is.

Table 3.8-88. Additional services recommended, by alternative
Service groupItemsRecorded for each item
Subsurface explorationSurveying; soil survey borings; modified SPT soil survey borings; SPT boringsAlternatives 1–3 that need it; estimated cost, low and high
Field testingDynamic cone penetrometer (DCP); field CBR; inclinometer; piezometer; lateral trench test pit; ground penetrating radar (GPR)Alternatives 1–3 that need it; estimated cost, low and high
EngineeringLaboratory testing; geotechnical analysis; structural analysis; design bid package; construction monitoringAlternatives 1–3 that need it; estimated cost, low and high

Each service ties to a chapter of this manual: exploration planning to Chapter 3.9; borings and SPT to Chapter 4.1; DCP, field CBR and GPR to Chapter 5.1; piezometers to Chapter 2.8; inclinometers to Section 5.3.8; laboratory testing to Chapter 5.2; and slope analysis to Chapter 6.3. Field testing on an operating railroad is done in work windows, so note when each test can be done. The level of effort set by the static rating (Table 3.8-29) is a guide to how much exploration to scope.

Alternative notes. On Sheet 3, write a short paragraph for each alternative: what it consists of, the services it needs, how long it will take (Table 3.8-90), and the risk rating expected once it is built. These notes become the alternatives section of the formal report (Chapter 8.4).

3.8.42.7 Block 6 — Ground Hazard Risk Rating

Block 6 rates the site using the scales and matrix of Section 3.8.22. It has six columns:

  • Preliminary and Live at visit (blue): copied from Blocks A6 and A7 before the visit. They are the desk’s expectation and the conditions the site was seen in.
  • Current (field): the trigger narrative and T, Fg, the field D and Fc (Table 3.8-27 and Table 3.8-11), and S from the exposure confirmed in Block 1. Compute R = F × S, read the rating from Table 3.8-16 and circle it. Write a one-line reason for each level.
  • Alternatives 1 to 3: the solution rating for each alternative (Section 3.8.22.7), with its design, construction-stage and post-stabilization ratings added as the alternative is designed, built and verified (Sections 3.8.37 to 3.8.39).

If the live rating at the visit was above the static rating, judge whether the indicators seen are those of the event or of the site’s usual state, and say so in the reason. Record any one-level adjustment (Section 3.8.22.6) and, where the field rating differs from the preliminary rating by more than one level, the reason.

Severe or High now? A Severe rating calls for on-site protection, operating restrictions and immediate stabilization; tell the railroad contact before leaving the site rather than waiting for the field copy, and record who was told and when.

3.8.42.8 Stabilization Methods: Analysis, Testing, Quality Control, Cost and Time

When an alternative includes ground improvement or another stabilization method, the report’s companion sheet sets the analysis it needs, the field and laboratory testing that support the analysis, and the quality control that shows the method worked. The field testing column also records when the test can be done around traffic.

Table 3.8-89. Stabilization methods: analysis, testing and quality control
MethodAnalysis requiredField testingLaboratory testing (standard)Quality control
Preloading and surchargingConsolidation analysisSPT during off-peak hoursTriaxial compression (ASTM D4767-11(2020))Pore pressure measurement
Sand drainsConsolidation analysisCPT coordinated with rail operationsUnconfined compression (ASTM D2166/D2166M-24)Settlement monitoring
Vibro-compactionShear strength analysisSPT during off-peak hoursConsolidation (ASTM D2435)Pore pressure measurement
Deep mixingShear strength analysisCPT coordinated with rail operationsTriaxial compression (ASTM D4767-11(2020))Settlement monitoring
GroutingLiquefaction analysisSPT or CPT with minimal disturbanceUnconfined compression (ASTM D2166/D2166M-24)Pore pressure measurement and settlement monitoring
Compaction grouting (low-mobility grout to 20 ft below toe of slope)Ground stabilization analysisSPT or CPT to verify treatment; GPRCompressive strength (ASTM C39/C39M-26)Ground movement monitoring
Ballast removal and replacementMaterial contamination analysisSPT or CPT during maintenance windowsParticle size distribution (ASTM D6913; D422 was withdrawn in 2016)Track settlement monitoring
Lateral drainsSeepage analysisSPT or CPT with piezometer installation; GPRPermeability (ASTM D5084-24)Pore pressure and water table monitoring
Toe bermSlope stability analysisSPT or CPT at the berm location; GPRDirect shear (ASTM D3080/D3080M-23)Slope monitoring
Embankment wideningLateral stability analysisSPT or CPT along the embankment; GPRCompaction (ASTM D1557) and shear strengthLateral movement monitoring
Soldier piles and laggingStructural stability analysisSPT or CPT at pile locations; GPRLoad test (ASTM D1143 axial; ASTM D3966 lateral)Structural monitoring
Track realignment away from top of slopeTrack stability analysisGPR; SPT or CPT during off-peak hoursCompaction (ASTM D698 or D1557)Track alignment monitoring

The standards and editions are those listed on the worksheet. Confirm the current edition, and that the standard fits the test intended, when the testing program is written. Method descriptions, design procedures and acceptance criteria are in Chapter 7.2; monitoring methods and trigger levels are in Chapter 5.3.

When alternatives are first framed in the field, before quantities exist, a relative ranking of cost and time is enough to tell a quick, inexpensive fix from a long capital project. Table 3.8-90 lists the methods in the same order as Table 3.8-89. Completion time is scored from 1 to 5; the scores used are 2 (about 1 week), 3 (about 3 months) and 5 (over 1 year).

Table 3.8-90. Relative cost and completion time of stabilization methods
MethodRelative costCompletion time (score)
Preloading and surchargingLowOver 1 year (5)
Sand drainsMediumAbout 3 months (3)
Vibro-compactionHighAbout 3 months (3)
Deep mixingHighAbout 3 months (3)
GroutingHighAbout 3 months (3)
Compaction grouting (low-mobility grout to 20 ft below toe of slope)HighAbout 3 months (3)
Ballast removal and replacementMediumOver 1 year (5)
Lateral drainsMediumAbout 1 week (2)
Toe bermMediumAbout 3 months (3)
Embankment wideningMediumOver 1 year (5)
Soldier piles and laggingHighOver 1 year (5)
Track realignment away from top of slopeHighOver 1 year (5)

Use the ranking with the risk ratings. Lateral drains, a medium-cost method installed in about a week, can move a Forming, Critical site (R = 12, High) to Inactive (R = 4, Guarded). That may be the right first step even where a high-cost structural fix is the long-term answer.

3.8.42.9 Field Copy Draft and Formal Report

Before the form leaves your hands, check that every block has been completed or marked “N/A”, that each Block A value has been confirmed or revised, that the photo numbers are recorded and that the red-text entries were confirmed with the railroad. Date the form, send it to a senior technical manager for review and issue it to the railroad as the field copy draft, so operating decisions are not held up while the report is written. The statement printed at the foot of Sheet 3 must stay on every copy:

FIELD COPY DRAFT – THIS DOCUMENT IS TO BE CONSIDERED A DRAFT. IT HAS ALSO BEEN SUBMITTED TO A SENIOR TECHNICAL MANAGER FOR REVIEW. THIS DOCUMENT IS SUBJECT TO EDITS, REMOVALS AND ADDITIONS. THE FORMAL REPORT WILL BE SUBMITTED WITHIN 1 WEEK OF THIS DRAFT SUBMITTAL.

The formal report follows within one week. It carries the three sheets forward with photographs, a site plan, the desk-to-field comparison from Block A, the reasoning behind the failure type, the F and S levels and the rating, and the recommended alternative with its scope, cost range and expected rating. Report format and content are covered in Chapter 8.4.

3.8.42.10 Ground Hazard Risk Assessment Checklist

  • Network screening value and entry route recorded (Section 3.8.25.1)
  • Situational rating complete: data sources, setting and construction history, driving mechanism, L1 to L5, C1 to C5, Sp (Section 3.8.23)
  • H&H thresholds set: paired gauge, toe and damage stage, culvert capacity storm, rainfall and antecedent thresholds (Section 3.8.23.7)
  • Trigger and instability rating complete: trigger narrative and T, instability record, L6, defect rating D, Fg and Fp (Section 3.8.24)
  • Static (preliminary) rating, priority and level of effort assigned (Section 3.8.25)
  • Water-sensitive sites paired with a gauge or rainfall trigger; static F and S and thresholds loaded for the live rating (Section 3.8.26)
  • Block A printed; questions for the field written; site map or KMZ in hand; live readings for the day of the visit entered (Section 3.8.42.3)
  • Railroad contact, protection type and place of safety confirmed before going on track
  • Milepost limits, affected track length, and track and traffic data recorded; exposure checked against C1 to C5 (Section 3.8.42.4)
  • Site walked; conditions recorded looking up station: left embankment, between the rails, right embankment (Section 3.8.24.4)
  • Each checked indicator photographed with scale and milepost; photo numbers noted
  • Reported geometry defects recorded with measurement and frequency
  • Major element, construction constraints and estimated failure type selected; failure type compared with the desk mechanism (Section 3.8.24.5)
  • Each Block A value confirmed or revised; questions answered
  • Stabilization items checked and assembled into up to three alternatives (Section 3.8.42.6)
  • Exploration, field testing and engineering services marked by alternative, with low and high cost
  • F, S, R and rating recorded, with reasons, for the current condition and each alternative; any one-level adjustment explained; differences of more than one level from the preliminary rating explained (Section 3.8.42.7)
  • Railroad told before leaving if the site is Severe or High
  • Alternative notes written; field copy draft issued and sent for senior review (Section 3.8.42.9)
  • Formal report scheduled within one week; revised attribute scores and thresholds returned to the desk