3.8.14 Monitoring and Early-Warning Indicators

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.14 Monitoring and Early-Warning Indicators

Monitoring converts an unknown mechanism into a measured one. It also provides warning where mitigation cannot be built right away. Instrument selection, installation and reading frequency are covered in Chapter 5.3.

Figure 3.8-30. Signs-of-instability job aid.
Figure 3.8-30. Signs-of-instability job aid.
IndicatorInstrument or Data SourceMechanism Monitored
Subsurface displacementInclinometers (ASTM D6230), shape arrays, TDR cableSlides, creep, spreading
Pore pressureVibrating-wire piezometers, observation wellsSlides, consolidation, rapid drawdown
SettlementSettlement plates, survey monuments, track geometry-car trendsConsolidation, cumulative deformation, sinkholes
Ground surface changeLiDAR change detection, InSAR, UAV photogrammetrySlides, subsidence, erosion
Track bed conditionGPR surveys (Chapter 2.3, Section 2.3.9)Fouling, ballast pockets, wet subgrade
Rockfall and slide detectionSlide fences and detector wires tied to signalsRockfall, debris flow
Rainfall and stream stageRain gauges, stream gauges, weather servicesAll water-triggered mechanisms (Section 3.8.12)

Track-recording data as an early-warning stream

Recording cars run at fixed intervals: about 3 times a year on main routes, twice a year on intermediate routes and once a year on branch lines. They measure longitudinal, transverse and horizontal defects on a base of about 33 ft and twist on 8–10 ft. At low and medium speeds the absolute (peak and mean) values govern. At higher speeds the standard deviation over 660–980 ft is used as the quality index. Results are ranked by severity and compared with earlier runs and with the limits.

Figure 3.8-31. Longitudinal defects as recorded. Profillidis Fig. 16.6.
Figure 3.8-31. Longitudinal defects as recorded. Profillidis Fig. 16.6.

Defects grow quickly until about 2 million tons after maintenance, then slowly and roughly with log T:

me(T) = a1 + a0 · log(T / Tr),    Tr = 2.2×106 tons

Here a1 is the mean settlement at Tr and a0 is the settlement rate per log cycle, 0.079–0.24 in. per decade, depending mainly on subgrade quality (a0/a1 = 0.25–0.70). The standard deviation of longitudinal defects follows the same form with c0 ≈ 0.0039–0.0079 in. per decade. A segment whose fitted a0 or c0 drifts above its neighbors is a candidate for substructure investigation. The sensitive period (about 1–4 months on a UIC group 4 line, 15–40 days on groups 1–3) is when monitoring after a repair matters most.

Figure 3.8-32. Mean track settlement me(T) vs. log of traffic since maintenance. Profillidis Fig. 16.8.
Figure 3.8-32. Mean track settlement me(T) vs. log of traffic since maintenance. Profillidis Fig. 16.8.

After Profillidis (2014), §16.5, §16.7, §16.10, Eqs. 16.3–16.5, Figs. 16.5, 16.6, 16.8. Full reference under Supplemental References.

Figure 3.8-33. Chord-type track recording car (French railways) and its measurement bases. Profillidis Fig. 16.5.
Figure 3.8-33. Chord-type track recording car (French railways) and its measurement bases. Profillidis Fig. 16.5.

Signs of instability job aid and field reporting

Warning signs appear in a predictable order: unusual high water on one side, seepage at the downhill toe, tension cracks along the shoulder (often hidden in ballast), a bulging toe and a small sand fan, increasingly dirty or milky seepage, trees leaning in different directions, and finally settlement or cross-level change in the track. Test hidden cracks with a lining bar; it meets little resistance over a fissure. Paint reference marks to see whether cracks widen. Walk down to the base of the fill when checking culverts, because much of this cannot be seen from the track. If movement is large and accelerating, take the track out of service and restore drainage urgently.

Figure 3.8-34. Testing a suspected tension crack in the field.
Figure 3.8-34. Testing a suspected tension crack in the field.
Figure 3.8-35. Paint marks used to monitor crack widening.
Figure 3.8-35. Paint marks used to monitor crack widening.
Figure 3.8-36. Leaning trees: a subtle sign of slope movement.
Figure 3.8-36. Leaning trees: a subtle sign of slope movement.

Moisture clues: groundwater discharge in depressions, wet zones or salt stains in cut ditches, frost boils, ice at culvert sides, moisture-loving plants (cattails, willows), and sudden lush vegetation on a slope. Report every natural-hazard incident, including rock found in a ditch, on the Natural Hazard Incident Report. It records site and weather (at the time and over the prior 24 h), a rockfall section, a mass-movement and washout section, and consequences (damage, delays, slow orders). The data is used to deploy rock gangs and maintenance crews.

Figure 3.8-37. Natural Hazard Incident Report, rockfall section.
Figure 3.8-37. Natural Hazard Incident Report, rockfall section.
Figure 3.8-38. Natural Hazard Incident Report, mass movement, washout and consequence sections.
Figure 3.8-38. Natural Hazard Incident Report, mass movement, washout and consequence sections.

After Geotechnology for Railroaders Program, Module 5, Module 7.1, Module 4, Module 6.4; Module 5 §11; Module 7.1 §05; Module 4 §10; Module 6.4 §05. Full reference under Supplemental References.

Project management · Skill Right (2013)

RASIC Responsibility Matrix for Monitoring and Alarm Response

A responsibility assignment matrix (RAM) makes sure every task has an owner and shows how deeply each person is involved. Tasks are listed as rows and roles as columns. The course uses the RASIC code:

Example responsibility assignment matrix that assigns R, A, S, I and C codes to each task and each project role.
Figure 4-PM1. Example responsibility assignment matrix that assigns R, A, S, I and C codes to each task and each project role. Source: Skill Right (2013), Slide: Responsibility Assignment Matrix (RASIC Method).
  • R – Responsible: makes sure the work is completed and delivered.
  • A – Approve: confirms the work meets the requirements.
  • S – Support: does the work and is committed to completing it.
  • I – Inform: kept up to date on status; makes no decisions.
  • C – Consult: gives input before the work is done.

The course example assigns codes for a marketing study (identify market, develop and test the survey, collect and analyze the data, report) across project manager, customer, team members, senior management and support staff.

For railroad work: an early-warning system is only as good as the chain from instrument reading to train movement decision, and that chain crosses organizations. A RASIC matrix agreed before the instruments are installed removes ambiguity at 2 a.m. The illustrative example below must be adapted to each railroad’s own operating rules and authority for slow orders and track removal from service.

Table 4-PM1. Illustrative RASIC matrix for an instrumented slide (adapted from the course method)

TaskGeotech consultantRailroad engineeringTrack supervisorOperations / dispatch
Set alert and action thresholdsR/SACI
Read and reduce instrumentsR/SII–
Threshold exceedance noticeR/SIII
Field inspection of track and slopeSAR/SI
Speed restriction or removal from serviceCAR/SS
Return to normal operationCARI

Keep one Approve per row so that the decision has a single owner. Put named people and phone numbers, with alternates, in the monitoring plan, and review the matrix whenever staff or thresholds change.

Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 45–47. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.