3.8.2 Track Substructure Failure Mechanisms

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.2 Track Substructure Failure Mechanisms

These mechanisms act within the ballast, subballast and subgrade (Chapter 2.3) and the upper part of the embankment (Chapter 2.1). They account for most of what track patrols encounter day to day: the "subsidence" category of Chapter 1.1.

MechanismWhat HappensSusceptible ConditionsField IndicatorsSee
Ballast degradation and foulingParticle breakage and abrasion, plus infiltration of fines, fill voids and reduce drainage and strengthWeak or soft aggregate, heavy tonnage, tamping cycles, wind-blown or spilled finesFouled shoulders, reduced voids, geometry loss after surfacingChapter 2.3, Section 2.3.7
Subgrade attrition and mud pumpingWater plus cyclic loading at the ballast–subgrade contact produces a slurry that is pumped into the ballastPlastic fine-grained subgrade, no or inadequate subballast, poor drainageMud at tie ends and in cribs, "white spots" on shoulders, rapid surface defectsChapter 2.3, Section 2.3.5
Progressive shear failureRepeated stress near the subgrade strength remolds the soil and squeezes it laterally beneath the tiesSoft, wet fine-grained subgrade; thin granular layerHeave of the ballast shoulder or ditch side ("subgrade squeeze"), ties hanging, recurring cross-level defectsChapter 2.3, Section 2.3.5
Excessive cumulative plastic deformationGradual accumulation of permanent strain under millions of load cycles forms ballast pockets and troughsFine-grained subgrade with moderate strength; heavy axle loadsBallast pockets in trench sections; gradual long-wave settlementChapter 2.3, Section 2.3.5
Consolidation settlementVolume decrease of saturated clay and organic soil under sustained loadSoft clay or peat foundations; new fill, raises or a second trackLong-wave settlement, often continuing for years after constructionChapter 6.2
Frost heave and thaw weakeningIce lens growth heaves track in winter; excess water on thaw softens the subgradeFrost-susceptible silts and silty clays, available water, freezing climateSeasonal differential heave, spring pumping and soft spotsChapter 2.3, Section 2.3.5; Chapter 7.3
Swell and shrinkageMoisture change in expansive clay causes volume changeHigh-plasticity clay, clay shale in cuts, seasonal wetting and dryingSeasonal geometry cycling, shoulder cracking in dry periodsChapters 2.1, 2.2
Cyclic softening ("subgrade dynamic liquefaction")Pore pressure buildup under repeated loading in saturated low-plasticity silt causes loss of strengthSaturated silts, poor drainageSudden loss of support in wet periods, mud boilsChapters 1.1, 6.5
Foundation Failure
Foundation Failure
Foundation Failure — Excessive Settlement
Foundation Failure — Excessive Settlement
Dynamic Soil and Liquefaction
Dynamic Soil and Liquefaction

Reading the substructure through maintenance demand

Profillidis uses a maintenance coefficient k = I / Im, where I is the annual number of maintenance sessions on a section and Im the average for track of the same age, UIC group and axle load. k = 1 is average; k = 0.5 is good; on poor subgrade k can reach 10. Maintenance hours rise steeply with k and with years since renewal (Figure 3.8-1). He uses k to judge whether the track bed is adequately sized:

Figure 3.8-1. Manual maintenance hours H per km and annual number of maintenance sessions I vs. years since renewal, for maintenance coefficients k = 0.3 to 10 (UIC groups 1–3). Profillidis Fig. 9.6.
Figure 3.8-1. Manual maintenance hours H per km and annual number of maintenance sessions I vs. years since renewal, for maintenance coefficients k = 0.3 to 10 (UIC groups 1–3). Profillidis Fig. 9.6.
Table 3.8-2. Assessment of track-bed sizing from the maintenance coefficient k
kAssessment
k < 1Correct dimensioning
1 < k < 2.5Track-bed structures slightly under-dimensioned
2.5 < k < 5Track-bed structures under-dimensioned; poor functioning of drainage
k > 5Renewal and strengthening of track-bed structures necessary

When I passes a threshold, geometry can no longer be held by surfacing alone and the remedy is to reduce k, mainly by thickening the track bed. Applied with Dormon’s rule, subgrade stress also depends on maintenance: traffic between sessions scales with T/k, so tracks with different k values load the subgrade differently. For a ground-hazard program the practical point is that a segment needing repeated spot surfacing (high k) is evidence of a substructure mechanism, and that evidence lives in maintenance records.

After Profillidis (2014), §9.9, Table 9.5, Fig. 9.6. Full reference under Supplemental References.

Ballast or subgrade: which one sets the maintenance cycle?

Short-term versus long-term settlement. On most track, ballast causes most of the settlement between surfacings, both average and differential. This is the short-term component. The subgrade adds a long-term component that builds slowly over decades of traffic. Ballast governs only when three conditions hold:

  • A filter or separation layer is present.
  • The subgrade is strong enough.
  • Surface drainage is good.

If any of these is missing, the subgrade dictates the maintenance cycle.

Why track subgrade fails by creep, not by sudden collapse. Train loading on the subgrade does not reverse the direction of shear stress. Under that kind of loading, pore pressure rises to a limit and failure comes as permanent strain accumulating at an increasing rate. Cyclic strain stays small. Two factors make it worse:

  • Static shear stress, such as beneath an embankment shoulder or slope, magnifies the plastic strain caused by traffic.
  • Subgrade saturation changes with the seasons, so the same section can perform differently in spring and in autumn.

After Selig & Waters (1994), chs. 3, 4 and 8. Full reference under Supplemental References.