3.8.20 Severity

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.20 Severity

Severity (S) is the consequence if the failure happens, scored 1 to 5 from Table 3.8-15: what the track carries (traffic, speed, passenger and hazardous materials trains), the number of tracks and redundancy of the route, the size of the failure, and what lies below and beside the track. Severity is a property of the site, not of the trigger or the state of the ground; it does not change during a live event. The consequence elements and their levels are in Section 3.8.27.6.

Two rules carry the extra weight on consequence called for in Section 1.1.2: where the consequence and the typical setting point to different levels, the consequence governs; and the engineer may raise the rating one level where the matrix understates the risk (Section 3.8.22.6), but never lower it. Severity changes in a risk reduction only where the solution changes what a failure would reach (Section 3.8.37.3).

When severity changes, and when it does not

Because severity belongs to the site and what it carries, it is rescored when the line changes, not when the ground or the weather does.

  • S rises when passenger service or hazardous materials routing is added, when traffic or speed increases materially, when development appears below or beside the fill (a road, homes, a water intake), or when a detour is lost.
  • S falls when the line is downgraded or taken out of main-line service, when the track is realigned away from the slope, when a protective structure is built between the hazard and the track, or when a detour becomes available.
  • S does not change during a storm or a flood (the live rating raises F only), when a stabilization lowers the chance of failure, or when monitoring is installed. The one exception is detection tied to an operating response, which may lower S by one level, and only while the response is in force (Table 3.8-80).

A quick check before a severity is recorded: name the train that would meet the failure, what it is carrying and at what speed; say where a derailed train would go (into a creek, onto a road, against a building); and say how long the line would be out and whether traffic can be detoured. If those answers point to different levels, the consequence governs. The same 15-ft slump below the track is Critical or Catastrophic under a main line with hazardous materials traffic over a stream, and Minor under a yard track with a parallel lead.