3.8.28 Vegetation, Fill Plasticity and Permeability as Likelihood Modifiers

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.28 Vegetation, Fill Plasticity and Permeability as Likelihood Modifiers

The ratings in Sections 3.8.18 to 3.8.27 are unchanged. The factors below come from UK monitoring of old clay embankments and cut slopes. Record them in the rating justification, and where several point the same way, use the higher end of the existing likelihood band for the element being rated. They apply to clay fills and clay cuts; they do not apply to rock cuts or granular fills.

Table 3.8-54. Site factors that raise or lower the likelihood of earthwork failure (guidance; ratings unchanged)
FactorPoints to lower likelihoodPoints to higher likelihoodMechanism affectedSource
Vegetation on the slopeGrass or small shrubsLarge high-water-demand trees (oak, poplar)Grass: delayed deep failure in wet winters. Trees: summer track settlement and shoulder lossO'Brien (2013), pp. 20–22
Recent tree removal on clay fillNone in the last few yearsClearance within the last one to three wintersWetting-up, swelling and outward movement in the following winterO'Brien (2013), p. 22
Plasticity of clay fillPI below about 20PI above about 30 (intermediate PI 30–35, high PI 45–50 in the UK studies)Seasonal shrink–swell and progressive failureO'Brien (2013), pp. 20, 29
Bulk permeability of clay fillAbout 0.0003 ft/day (10−9 m/s) or lessAbout 0.014 to 0.14 ft/day (5 × 10−8 to 5 × 10−7 m/s)Winter rain infiltrates fast enough to raise pore pressureO'Brien (2013), pp. 25, 27
Soft alluvium or topsoil left under the fillFill placed on firm groundSoft or organic layer at the baseDelayed deep failure through the foundationO'Brien (2013), Table 3
Ash or ballast at the shoulderShoulder flatter than about 1.5H:1V, well vegetatedOversteepened, dry fine ash at the crestShoulder unravelling under traffic, mostly in summerMcGinnity and Saffari (2012), p. 1071

Permeability converted from m/s to ft/day (1 m/s = 283,000 ft/day). Tree water demand classes follow the UK NHBC (2003) system with oak and poplar placed in a “very high” class, as in the monitoring studies.

Vegetation cuts both ways. Trees that cause summer track movement may also be what keeps a clay embankment from a winter failure, so a rating that improves the serviceability score by clearing trees should be re-checked for the deep-seated case (Chapter 2.5, Section 2.5.18).

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • O'Brien, A. S. (2013). The assessment of old railway embankments – time for a change? In Gallipoli (ed.), Partial Saturation in Compacted Soils, pp. 19–32. ICE PublishingFind source ↗
  • McGinnity, B. T. and Saffari, N. (2012). Earthworks asset management and remedial design. Chapter 71 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1067–1086Find source ↗Library entry