3.8.3 Embankment and Slope Failure Mechanisms

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.3 Embankment and Slope Failure Mechanisms

Classify slope movements by material (rock, debris, earth) and movement type (fall, topple, slide, spread, flow), following Cruden and Varnes (1996) as adopted in Chapter 1.1. The mechanism determines the analysis method (Chapter 6.3) and the likely warning time.

MechanismTypical Railroad SettingWarning SignsWarning Time
Rotational slide (slump)Embankments and cuts in clay; river-bank fillsCrest cracks parallel to track, back-tilted blocks, bulging toeDays to months; often progressive
Translational slideFill over sloping bedrock or weak planar layer; colluviumTension cracks upslope, displaced ditch, leaning polesHours to weeks
Earthflow and retrogressive slideSensitive and quick clays in river valleysOften little; small initial slide at the bankMinutes to hours once started
Lateral spreadSensitive clay or liquefiable layers near free facesGround cracking, bulging toward channelRapid
Debris flowSteep channels above track; source areas often out of sightAccumulated debris in upper channel, burn scars, intense rainMinutes; can reach track 1–2 miles from source (Chapter 1.1)
Rockfall and toppleRock cuts and natural rock facesFresh debris in ditch, open joints, freeze-thaw season activitySeconds
CreepClay slopes and colluviumCurved tree trunks, slow drift of track alignment and structuresYears; may accelerate to sliding
Shallow sloughing and surface erosionSteep, unvegetated fill slopesRills and gullies, slumped surface layerStorm-dependent
Embankment spreading or foundation squeezeEmbankment on soft foundationToe heave, lateral displacement, crest settlementWeeks to months
Figure 3.8-2. Rotational and translational slides, block slide, rockfall, topple, debris flow, debris avalanche, earthflow, creep and lateral spread.
Figure 3.8-2. Rotational and translational slides, block slide, rockfall, topple, debris flow, debris avalanche, earthflow, creep and lateral spread.

Mass-movement types and internal-erosion collapse

Mass movements are classified by rate against water content, from extremely slow dry creep through earthflows and rotational or translational slides to extremely rapid rockfalls, debris flows and debris avalanches in saturated ground. An earthflow has a characteristic hourglass shape. Creep is spotted by its effects: curved trunks, bent fences and tilted poles.

Figure 3.8-3. Mass-movement classification: rate of movement vs. water content.
Figure 3.8-3. Mass-movement classification: rate of movement vs. water content.

Embankment collapse by internal erosion (rated Severe) is the hidden mode. Water moves through the fill or overflows through buried rock drains, carrying soil out and leaving voids until the surface collapses. In one case a culvert roof failed about 45 ft inside the fill and produced a sink hole up to 70 ft deep. In another, a 6.5-ft multi-plate culvert with a rusted-out invert let water erode beneath it, causing outlet and toe scour, an over-steepened slope, head-scarp cracks, 14 in. of mainline settlement and 2 in. of lateral deflection.

Figure 3.8-4. Montmagny, mile 115.53: settlement from a culvert collapse.
Figure 3.8-4. Montmagny, mile 115.53: settlement from a culvert collapse.
Figure 3.8-5. Sink hole over a failed culvert (illustrative risk rating: Severe).
Figure 3.8-5. Sink hole over a failed culvert (illustrative risk rating: Severe).
Figure 3.8-6. A sink hole forming under the track from internal erosion.
Figure 3.8-6. A sink hole forming under the track from internal erosion.

After Geotechnology for Railroaders Program, Module 5; §05, §09, §14. Full reference under Supplemental References.

Case study: 3.8.45.1 Slope failures whose consequences left the site (Look 2023), in §4.18 Case Studies.