3.8.34 Semi-Quantitative Landslide Risk Scores as a Cross-Check

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.34 Semi-Quantitative Landslide Risk Scores as a Cross-Check

Sections 3.8.19 to 3.8.21 rank sites by R = F × S. Hearn's Slope Engineering for Mountain Roads sets out two published semi-quantitative systems for road slopes that do the same job and make a useful cross-check. Both follow the definitions of Varnes and of the Australian Geomechanics Society. Risk combines the hazard (its magnitude and probability) with the value of the assets exposed and their vulnerability, the degree of loss if the hazard occurs. The GHRM severity S folds value and vulnerability into one scale. Hearn keeps them separate, so a site where the rankings disagree usually points to a judgment about consequence that deserves a second look. Hearn is explicit that neither system gives absolute risk; they are for recording slopes and putting stabilization work in order.

3.8.34.1 Method

Table 3.8-65. Table A4.1 relative risk (after Hearn, developed for mountain roads in Laos)
Component0123
Magnitude M–Small: shallow, up to about 650 cu ydModerateLarge: deep, about 6,500 cu yd or more
Probability in a 20-year design life PNot expectedPossibleExpectedDefinite
Value of elements at risk Va–Slope works and ditchSlope works, ditch and up to half the formation widthWhole formation and adjacent structures
Vulnerability VuNo effectDeformation or blockagePartial lossTotal loss

Relative risk R = M × P × Va × Vu, 0 to 81. Hearn's road terms (side drain, carriageway) are given here as their track equivalents.

Table 3.8-66. Table D1.3 prioritization (after Hearn and Hunt)
Asset value classVulnerability highModerateLow
1: heavy traffic, strategic access, buildings in the hazard area, or access lost over 3 days543
2: moderate traffic or access, buildings on the margin, access lost 1 to 3 days432
3: light traffic, network only, access lost under 1 day321

Entries are the loss value. Risk number = loss value × probability level: 5 high (active indicators, or occurrence at least every 2 years), 3 moderate (landslide morphology or previous movement; periodic, every 2 to 5 years), 1 low (no evidence of movement). Ranks: 20 to 25 Very High, preventative works immediately; 10 to 15 High, preventative works in the following dry season; 5 to 9 Moderate, monitoring; 1 to 4 Low, no action.

3.8.34.2 Worked example

Example 3.8-11: Two Slides Ranked with Hearn's Relative Risk Score

Hearn's own illustration of Table A4.1 compares two slides on one road. Put in railroad terms, a small slide below the track is undermining a retaining wall, and a large slide above the track could bury it. The cross-check asks which carries more risk, and whether the answer agrees with the F × S ranking.

TrackSlide 1: small, below the track,undermining a wall: M1 P2 Va3 Vu3Slide 2: large, above the track:M3 P1 Va3 Vu1R = ?GivenSlide 1: M = 1, P = 2, Va = 3, Vu = 3Slide 2: M = 3, P = 1, Va = 3, Vu = 1Scores from Hearn Table A4.1RequiredRelative risk of each slideWhich ranks higher, and whyAgreement with F × S rankingBlack = given; red = required
Given and required for Example 3.8-11.

Given

VariableValueDescription
M1 (slide 1); 3 (slide 2)Magnitude of the failure
P2; 1Probability of failure
Va3; 3Value of the asset affected
Vu3; 1Vulnerability: 3 where support is removed, 1 where the track is only blocked

Required

  • Relative risk score of each slide
  • Which ranks higher and why
  • Whether the order agrees with the GHRM severity rules

Equations

  1. Eq. 1: RH = M × P × Va × Vu — Hearn's relative risk, Table A4.1

Steps

Step 1 · Slide 1, below the track (Eq. 1)
Uses: M, P, Va, Vu
RH = 1 × 2 × 3 × 3
RH = 18
Spot check: Matches Hearn's published 18 (Table 3.8-67).
↓
Step 2 · Slide 2, above the track (Eq. 1)
Uses: M, P, Va, Vu
RH = 3 × 1 × 3 × 1
RH = 9
Spot check: Matches Hearn's published 9.
↓
Step 3 · Compare
Uses: Steps 1 and 2
18 / 9
Slide 1 carries twice the relative risk
Spot check: Vulnerability alone accounts for the ratio: 3/1 = 3, offset in part by magnitude 1/3 and probability 2/1.
↓
Solution
Slide 1 (18) outranks slide 2 (9).

Solution

The small slide below the track scores 18 and the large slide above it scores 9: the smaller failure carries twice the risk, because it removes support while the larger one only has to be cleared.

The same reasoning runs through Table 3.8-15, which places loss of track support among the most severe consequences, and through the rule of Section 3.8.20 that the consequence governs. In Hearn's field example, cutting a failed slope back to the dip of the bedding lowered its score from 18 to 12, not lower, because bedding-plane sliding was still possible and tension cracks were still opening.

The three scenarios Hearn uses for Table D1.3 reproduce in the calculator: a moderately likely slide above a busy road scores 15 (High); a wall being undermined by seepage on the only access to a hospital scores 25 (Very High); and a debris flow with buildings in its path but no sign of activity scores 5 (Moderate).

Run both systems on the same sites when a program is being set. Where Hearn's order and the F × S order disagree, find out why before accepting either: the usual cause is a consequence judgment, such as a failure below the track rated as a minor blockage, or a probability scored on morphology alone. Record the reason in the rationale (Section 3.8.43).

Open the landslide risk score calculator →
Hearn's Table A4.1 relative risk (magnitude, probability, value and vulnerability) and Table D1.3 risk number with its rank and action, for any number of sites, sorted for comparison with the F × S ranking.

3.8.34.3 Verification against the published examples

Table 3.8-67. Published and calculated scores
ExampleHearnCalculator
Table A4.1: small slide undermining wall foundations1818
Table A4.1: large slide blocking the road from above99
Table D1.5 scenario 1: slide above a road carrying over 800 vehicles a day15, High15, High
Table D1.5 scenario 2: retaining wall failure, access to a hospital25, Very High25, Very High
Table D1.5 scenario 3: debris flow, buildings in the hazard area5, Low (as printed)5, Moderate

Hearn's Table D1.5 lists scenario 3 as Low, but a risk number of 5 falls in the 5 to 9 Moderate range of Table D1.3; the calculator follows Table D1.3.

3.8.34.4 How the scales compare

Table 3.8-68. Hearn's probability levels beside the GHRM frequency index
Hearn (Table D1.3)DescriptionClosest GHRM level (Table 3.8-14)
High (5)Adverse structure, seepage, toe erosion, fresh scarps, bulges or cracks; occurrence at least every 2 yearsF = 4 or 5 (Emerging or Occurring)
Moderate (3)Landslide morphology but no visible movement; previous movement; periodic occurrence every 2 to 5 yearsF = 2 by evidence (Dormant); F = 4 by frequency
Low (1)No evidence of movement, no sources, stable founding conditionsF = 1 (Inactive)

Hearn's moderate level mixes evidence of past movement with a frequency of 2 to 5 years, which the GHRM scales keep apart. A site rated by frequency and one rated by morphology can therefore land in the same Hearn level but in different F levels.

3.8.34.5 Sources in the library

Paraphrased from these documents in the reference library.

  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section A4 (G.J. Hearn), landslide susceptibility, hazard and risk, Table A4.1 and Figure A4.1Find source ↗Library entry
  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section D1 (G.J. Hearn and T. Hunt), slope management, Tables D1.3 to D1.5Find source ↗Library entry