Most ground hazard data are counts and extremes: rockfalls per mile per year, washouts per decade, the largest daily rainfall or river stage in each year. Each kind of data has a distribution that fits it and a way of turning the record into the annual probabilities used in the ratings. Table 3.8-63 lists the distributions that cover nearly all ground hazard work.
| Distribution | Use in risk assessment | Mean; variance | Notes |
|---|---|---|---|
| Normal (Gaussian) | Sums of many small effects: factor of safety from many parameters; averages of test results | μ; σ² | Can go negative, so a poor model for strengths with high COV |
| Lognormal | Strengths, permeability, settlement; any positive quantity that is a product of factors | exp(λ + ζ²/2); see Eq. 3.9-4 | Used for the lognormal reliability index in Section 3.9.15 |
| Binomial | Number of years with an event in n years; number of sites that fail out of a group | np; np(1 − p) | The 1 − (1 − p)n form of Section 3.8.30 |
| Poisson | Number of events in a time or length: rockfalls, washouts, sinkholes per mile per year | λt; λt | Mean equals variance; check for clustering (variance much larger than the mean) |
| Exponential | Time between Poisson events; time to the next failure | 1/λ; 1/λ² | Memoryless: a long quiet period does not make the next event “due” |
| Gumbel (Extreme Value Type I) | Annual maximum rainfall, flood flow or stage | u + 0.5772/α; 1.645/α² | Basis of the frequency factor in Appendix F; Eq. 3.8-10 |
| Weibull (Extreme Value Type III) | Minimum values and lifetimes: weakest link, time to deterioration of an asset | depends on shape k | Shape k < 1: early failures; k > 1: wear-out |
| Beta | Bounded quantities: a probability or proportion estimated from judgment; PERT cost and duration | depends on two shape parameters | Three-point (low, most likely, high) estimates of cost and duration |
Equation 3.8-9. Poisson distribution of event counts
λ = rate (events per year, or per mile per year with t in mile-years); k = number of events. The same form applies along the track: with λ per mile, t becomes the length of track considered. Events must be independent; storms that cause several rockfalls at once break this assumption, so count storm events rather than individual rocks if they cluster.
A record of N events in t years gives λ ≈ N/t. A short record gives a rough rate: for N = 3 the 90% confidence range on the true rate is about 0.8/t to 7.8/t, so three events in ten years is consistent with anything from one in twelve years to almost one a year. Report the range, not just the point value, and see Section 3.8.33 for the case of no events at all.
Equation 3.8-10. Gumbel (Extreme Value Type I) distribution of annual maxima
x̄ and s are the mean and standard deviation of the annual maxima (method of moments). xT is the value with return period T. The constants 1.2825 = π/√6 and 0.4500 = 0.5772/1.2825 come from the Euler constant 0.5772. For flood flows at a gauge, USGS Bulletin 17C (Log-Pearson Type III) is the standard (Section 3.5.12); Gumbel is a quick check and suits rainfall depths and river stages.
For example, 25 years of annual maximum 24-hour rainfall at a gauge near a cut with mean 3.2 in. and standard deviation 0.9 in. give α = 1.425 in.−1 and u = 2.80 in., so the 25-year value is 2.80 + 3.20/1.425 = 5.0 in. If the cut has responded at 4.5 in. (its response level, Section 3.8.23), that depth has a return period of about 12 years and the trigger rates T = 3 (Table 3.8-9).
A Class I railroad located in Pennsylvania has a 6-mile segment of rock cuts along a river. The maintenance records show 14 rockfalls that reached the track in the last 10 years, 6 of them in mile 3 (Figure 3.8-44). The segment is being rated for a rockfall program. The engineer must turn the counts into annual probabilities, decide whether mile 3 is genuinely worse than the rest or just unlucky, and assign the frequency index F of Table 3.8-14.
| Variable | Value | Description |
|---|---|---|
| N | 14 rockfalls | Rockfalls onto the track in the record |
| t | 10 years | Length of the record |
| L | 6 miles | Segment length |
| N3 | 6 rockfalls | Rockfalls in mile 3 |
| Model | Poisson | Rockfalls independent and random in time and along the segment |
The segment averages 1.4 rockfalls a year (75% chance of at least one in any year). Mile 3 rates F = 4 and the rest F = 3, provided field mapping confirms a physical reason for mile 3.
The counts show a real hazard with a 75% annual chance of rock on the track somewhere in the segment, and about one year in six with three or more. Mile 3 stands out, but six events in one of six miles would happen by chance about one time in five, so the statistics alone cannot justify spending the program on it. The decision should rest on the field evidence: if mile 3 has an adverse joint set, overhangs, a steeper or higher face, or a ditch too narrow to catch what falls (Section 3.8.29), the split rating of F = 4 for mile 3 and F = 3 for the rest is justified and mile 3 goes first. If the cuts look alike, rate the segment uniformly and keep counting; another five years of records will separate a real hot spot from a run of bad luck. Rates per mile also suit the exposure calculations of Section 3.8.30: the Poisson form there (Pn ≈ 1 − e−n/T) is Eq. 3.8-9 with k = 0.
Open the hazard event rate and hot spot (Poisson) calculator →
For railroad work: Keep the incident log by milepost and date, and record each rockfall, washout or sinkhole even when it causes no delay; without that log the frequency index is a guess. Count storm events where events cluster, compare each mile with the segment average before declaring a hot spot, and check the statistics against the field evidence before moving money. Convert rates to the band levels of Tables 3.8-9 and 3.8-14 with the arithmetic of Section 3.8.30.
Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 6 (Poisson distribution, including spatial distributions), Ch. 7 (exponential, lognormal, beta and extreme-value distributions); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (binomial, normal and Poisson distributions).