[ ] Preparatory factors identified and, where possible, stopped
[ ] Relevant triggers listed with site-specific thresholds where applicable
[ ] Factor of safety estimated for current and triggered conditions
[ ] Monitoring installed where the mechanism is uncertain or mitigation is deferred
[ ] Operating protocol (patrol, slow order, warning system) defined for residual risk
[ ] Mitigation selected to address the mechanism, not only the trigger (Chapter 1.1, Section 1.1.9)
[ ] Spring readiness: critical culverts inspected and cleared of ice before the melt; differential water levels and seepage checked from the ground, not the hi-rail (Section 3.8.7)
[ ] Embankments that were submerged kept under observation for 24 to 48 hours after any rapid drop in water level (Section 3.8.7.5)
[ ] Frost heave and silt-boil locations marked on the ties and logged in the registry; remedy chosen to remove water, silt or freezing (Section 3.8.8)