Chapter 3.9 — Geotechnical Investigation Planning and Scope

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel

Primary Source: USACE EM 1110-1-1804, Geotechnical Investigations, 1 January 2001; AREMA Manual for Railway Engineering (MRE), Chapter 1 — Roadway and Ballast; client-specific railroad engineering standards as cited.

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Property and test variability to guide the number of borings and tests, and what failure case histories say about investigation scope. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Why geotechnical failures happen and what investigation is worth (6 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Primary cause of geotechnical failure (share of cases)Shortcomings in designISSMGE TC302 Task Force 10, ~100 case histories45%FGE text, p.278
Primary cause of geotechnical failure (share of cases)Inadequate site investigationISSMGE TC302 Task Force 10, ~100 case histories20%FGE text, p.278
Primary cause of geotechnical failure (share of cases)Unforeseen phenomena and occurrencesISSMGE TC302 Task Force 10, ~100 case histories20%FGE text, p.278
Primary cause of geotechnical failure (share of cases)Shortcomings in constructionISSMGE TC302 Task Force 10, ~100 case histories14%FGE text, p.274
Site investigation spend worth makingProject costU.S. study (Threadgold 2002)3% of project costFGE text, p.272
Site investigation spend on projects with > 50% cost overrunOutturn project costUK projects (Clayton 2001)2.5% of project costFGE text, p.272
Open this set in the database ↗
Inherent variability of soil and rock properties (38 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of variationNatural moisture contentMean, without outliers17.7%LOOK T10.2, p.137
Coefficient of variationLiquid limitMean, without outliers11.1%LOOK T10.2, p.137
Coefficient of variationPlastic limitMean, without outliers11.3%LOOK T10.2, p.137
Coefficient of variationInitial void ratioMean, without outliers19.8%LOOK T10.2, p.137
Coefficient of variationUnit weightMean, without outliers7.1%LOOK T10.2, p.137
Coefficient of variationRock unconfined compressive strengthMean, without outliers23%LOOK T10.2, p.137
Coefficient of variationEffective friction angleMean, without outliers12.6%LOOK T10.2, p.137
Coefficient of variationTangent of friction angleMean, without outliers11.3%LOOK T10.2, p.137
Coefficient of variationUndrained shear strengthMean, without outliers33.8%LOOK T10.2, p.137
Coefficient of variationCompression indexMean, without outliers37%LOOK T10.2, p.137
Coefficient of variation – inherent variabilityFine-grained soils – Unit weightML-CHKulhawy et al. (2000), 14 data groups27.820%FGE T31.3, p.479
Coefficient of variation – inherent variabilityFine-grained soils – Natural moisture contentML-CHKulhawy et al. (2000), 40 data groups718.146%FGE T31.3, p.479
Coefficient of variation – inherent variabilityFine-grained soils – Plastic limitML-CHKulhawy et al. (2000), 23 data groups615.734%FGE T31.3, p.479
Coefficient of variation – inherent variabilityFine-grained soils – Liquid limitML-CHKulhawy et al. (2000), 38 data groups718.139%FGE T31.3, p.479
Coefficient of variation – inherent variabilityFine-grained soils – all data – Plasticity indexML-CHKulhawy et al. (2000), 33 data groups929.557%FGE T31.3, p.479
Coefficient of variation – inherent variabilityFine-grained soils, PI ≤ 20% – Plasticity indexML-CLKulhawy et al. (2000), 13 data groups163557%FGE T31.3, p.479
Coefficient of variation – inherent variabilityFine-grained soils, PI > 20% – Plasticity indexCL-CHKulhawy et al. (2000), 20 data groups92640%FGE T31.3, p.479
Coefficient of variation – inherent variabilityRock – Unit weightKulhawy et al. (2000), 42 data groups0.10.93%FGE T31.3, p.479
Coefficient of variation – inherent variabilityRock – PorosityKulhawy et al. (2000), 25 data groups325.971%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand and clay – Effective friction angleKulhawy et al. (2000), 48 data groups413.950%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand – Effective friction angleSW-SMKulhawy et al. (2000), 32 data groups4915%FGE T31.3, p.479
Coefficient of variation – inherent variabilityClay – Effective friction angleCL-CHKulhawy et al. (2000), 16 data groups1023.550%FGE T31.3, p.479
Coefficient of variation – inherent variabilityClay – Undrained shear strengthCL-CHKulhawy et al. (2000), 100 data groups631.580%FGE T31.3, p.479
Coefficient of variation – inherent variabilityRock – Rock unconfined compressive strengthKulhawy et al. (2000), 184 data groups0.314.261%FGE T31.3, p.479
Coefficient of variation – inherent variabilityRock – Brazilian tensile strengthKulhawy et al. (2000), 74 data groups216.658%FGE T31.3, p.479
Coefficient of variation – inherent variabilityRock – Tangent modulus at 50% strengthKulhawy et al. (2000), 32 data groups730.763%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand and clay – CPT cone resistanceKulhawy et al. (2000), 65 data groups1036.681%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand – CPT cone resistanceSW-SMKulhawy et al. (2000), 54 data groups1038.281%FGE T31.3, p.479
Coefficient of variation – inherent variabilityClay – CPT cone resistanceCL-CHKulhawy et al. (2000), 11 data groups1628.440%FGE T31.3, p.479
Coefficient of variation – inherent variabilityClay – CPT corrected cone resistanceCL-CHKulhawy et al. (2000), 9 data groups27.917%FGE T31.3, p.479
Coefficient of variation – inherent variabilityClay – Vane shear strengthCL-CHKulhawy et al. (2000), 26 data groups1325.336%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand and clay – SPT blow countKulhawy et al. (2000), 23 data groups193862%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand and clay – DMT A and B readingsKulhawy et al. (2000), 56 data groups1227.959%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand – DMT A and B readingsSW-SMKulhawy et al. (2000), 30 data groups1334.859%FGE T31.3, p.479
Coefficient of variation – inherent variabilityClay – DMT A and B readingsCL-CHKulhawy et al. (2000), 26 data groups1219.938%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand (without outliers) – DMT material indexSW-SMKulhawy et al. (2000), 29 data groups837.766%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand (without outliers) – DMT horizontal stress indexSW-SMKulhawy et al. (2000), 29 data groups1537.667%FGE T31.3, p.479
Coefficient of variation – inherent variabilitySand (without outliers) – DMT modulusSW-SMKulhawy et al. (2000), 30 data groups741.169%FGE T31.3, p.479
Open this set in the database ↗
Measurement error of lab and in situ tests (25 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of variation of in situ testStandard penetration testEquipment + procedure + random153045%LOOK T10.3, p.137
Coefficient of variation of in situ testMechanical cone penetration testEquipment + procedure + random152025%LOOK T10.3, p.137
Coefficient of variation of in situ testSelf-boring pressuremeterEquipment + procedure + random152025%LOOK T10.3, p.137
Coefficient of variation of in situ testVane shear testEquipment + procedure + random101520%LOOK T10.3, p.137
Coefficient of variation of in situ testPressuremeter, preboredEquipment + procedure + random101520%LOOK T10.3, p.137
Coefficient of variation – lab measurement errorClay, silt – Undrained strength, triaxial compression su(TC)CL-MLPhoon & Kulhawy (1999a)81938%FGE T31.4, p.480
Coefficient of variation – lab measurement errorClay, silt – Undrained strength, direct shear su(DS)CL-MLPhoon & Kulhawy (1999a)192020%FGE T31.4, p.480
Coefficient of variation – lab measurement errorClay – Undrained strength, lab vane su(LV)CL-CHPhoon & Kulhawy (1999a)51337%FGE T31.4, p.480
Coefficient of variation – lab measurement errorClay, silt – Friction angle, triaxial φ′(TC)CL-MLPhoon & Kulhawy (1999a)72456%FGE T31.4, p.480
Coefficient of variation – lab measurement errorClay, silt – Friction angle, direct shear φ′(DS)CL-MLPhoon & Kulhawy (1999a)31329%FGE T31.4, p.480
Coefficient of variation – lab measurement errorSand – Friction angle, direct shear φ′(DS)SW-SMPhoon & Kulhawy (1999a)131414%FGE T31.4, p.480
Coefficient of variation – lab measurement errorSand, silt – tan φ′, triaxialSM-MLPhoon & Kulhawy (1999a)2822%FGE T31.4, p.480
Coefficient of variation – lab measurement errorClay – tan φ′, direct shearCL-CHPhoon & Kulhawy (1999a)61422%FGE T31.4, p.480
Coefficient of variation – lab measurement errorFine-grained soils – Natural moisture content wnML-CHPhoon & Kulhawy (1999a)6812%FGE T31.4, p.480
Coefficient of variation – lab measurement errorFine-grained soils – Liquid limit wLML-CHPhoon & Kulhawy (1999a)3711%FGE T31.4, p.480
Coefficient of variation – lab measurement errorFine-grained soils – Plastic limit wPML-CHPhoon & Kulhawy (1999a)71018%FGE T31.4, p.480
Coefficient of variation – lab measurement errorFine-grained soils – Plasticity index PIML-CHPhoon & Kulhawy (1999a)52451%FGE T31.4, p.480
Coefficient of variation – lab measurement errorFine-grained soils – Total unit weight γML-CHPhoon & Kulhawy (1999a)112%FGE T31.4, p.480
Coefficient of variation of in situ test – measurement errorStandard penetration test (SPT)Total probable range153045%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorMechanical cone (MCPT)Total probable range151525%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorElectric cone (ECPT)Total probable range5715%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorVane shear test (VST)Total probable range101420%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorDilatometer (DMT)Total probable range51115%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorPressuremeter, prebored (PMT)Total probable range101620%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorSelf-boring pressuremeter (SBPMT)Total probable range151925%FGE T31.5, p.480
Open this set in the database ↗
Design parameter variability (20 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of variation – design parameter (point)Clay – Undrained strength su(UC)CL-CHDirect (lab)2037.555%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(UU)CL-CHDirect (lab)1022.535%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(CIUC)CL-CHDirect (lab)2032.545%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(field)CL-CHVane shear1532.550%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(UU)CL-CHFrom CPT qT303540%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(CIUC)CL-CHFrom CPT qT3542.550%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(UU)CL-CHFrom SPT N405060%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength suCL-CHFrom DMT KD3042.555%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Undrained strength su(field)CL-CHFrom PI3042.555%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay, sand – Effective friction angle φ′Direct (lab)713.520%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Sand – Effective friction angle φ′(TC)SW-SMFrom CPT qT1012.515%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Constant-volume friction angle φ′cvCL-CHFrom PI1517.520%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – At-rest coefficient K0CL-CHDirect (SBPMT)2032.545%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Sand – At-rest coefficient K0SW-SMDirect (SBPMT)254055%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – At-rest coefficient K0CL-CHFrom DMT KD3542.550%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – At-rest coefficient K0CL-CHFrom SPT N4057.575%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Sand – Pressuremeter modulus EPMTSW-SMDirect (PMT)204570%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Sand – Dilatometer modulus EDSW-SMDirect (DMT)1542.570%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Clay – Pressuremeter modulus EPMTCL-CHFrom SPT N859095%FGE T31.7, p.485
Coefficient of variation – design parameter (point)Silt – Dilatometer modulus EDMLFrom SPT N405060%FGE T31.7, p.485
Open this set in the database ↗
Scale of fluctuation (sets boring and test spacing) (28 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Vertical scale of fluctuationClay – suLab testing2.615.428.2ftFGE T31.6, p.484
Vertical scale of fluctuationClay – suVane shear6.613.420.3ftFGE T31.6, p.484
Horizontal scale of fluctuationClay – suVane shear150.9173.9196.9ftFGE T31.6, p.484
Vertical scale of fluctuationSand, clay – qcCPT0.35.059.8ftFGE T31.6, p.484
Horizontal scale of fluctuationSand, clay – qcCPT9.8136.2262.5ftFGE T31.6, p.484
Vertical scale of fluctuationOffshore soils – qcCPT11.151.3ftFGE T31.6, p.484
Horizontal scale of fluctuationOffshore soils – qcCPT45.985.3124.7ftFGE T31.6, p.484
Vertical scale of fluctuationClay – qtCPTu0.71.151.6ftFGE T31.6, p.484
Horizontal scale of fluctuationClay – qtCPTu75.5146216.5ftFGE T31.6, p.484
Vertical scale of fluctuationCohesive-behavior soils – qc1NCPT0.31.152ftFGE T31.6, p.484
Vertical scale of fluctuationIntermediate-behavior soils – qc1NCPT12.153.3ftFGE T31.6, p.484
Vertical scale of fluctuationCohesionless-behavior soils – qc1NCPT1.32.453.6ftFGE T31.6, p.484
Vertical scale of fluctuationSand – fsCPT4.3ftFGE T31.6, p.484
Vertical scale of fluctuationCohesive-behavior soils – IcCPT0.71.151.6ftFGE T31.6, p.484
Vertical scale of fluctuationIntermediate-behavior soils – IcCPT2ftFGE T31.6, p.484
Vertical scale of fluctuationCohesionless-behavior soils – IcCPT12.453.9ftFGE T31.6, p.484
Vertical scale of fluctuationSand – NSPT7.9ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – wLab testing5.223.541.7ftFGE T31.6, p.484
Horizontal scale of fluctuationClay, loam – wLab testing557.8ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – wLLab testing5.216.928.5ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – γLab testing7.916.925.9ftFGE T31.6, p.484
Vertical scale of fluctuationOrganic silty clay – eLab testing9.8ftFGE T31.6, p.484
Vertical scale of fluctuationOrganic silty clay – σ′pLab testing2ftFGE T31.6, p.484
Horizontal scale of fluctuationOrganic silty clay – σ′pLab testing590.6ftFGE T31.6, p.484
Vertical scale of fluctuationSand – ln(Dr)SPT12.1ftFGE T31.6, p.484
Horizontal scale of fluctuationSand – ln(Dr)SPT219.8ftFGE T31.6, p.484
Vertical scale of fluctuationSand – n–21.3ftFGE T31.6, p.484
Horizontal scale of fluctuationSand – n–10.8ftFGE T31.6, p.484
Open this set in the database ↗
References (2)
  1. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
  2. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
Executive Summary

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project. Planning errors — insufficient boring depths, wrong spacing, missing laboratory tests — cannot be corrected during analysis; they produce reports that fail engineering review, delay project schedules, and increase total project cost. This chapter establishes the systematic planning process we apply on every railroad geotechnical program, from the first desktop review through final boring layout approval. Key outputs of the planning phase are: a boring location plan dimensioned in feet and referenced to railroad mileposts, a boring depth matrix derived from stress influence calculations in English units, a laboratory testing assignment sheet linked to the specific design questions the investigation must answer, and a project-specific health and safety plan that satisfies the host railroad's Right-of-Way Protection (RWP) requirements.

Railroad client references: AREMA MRE Ch. 1, Parts 1 and 2 (Roadbed; Ballast); the owner railroad's current engineering standards (confirm the edition when the work is scoped).

Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
IS-01SPT energy & procedure correctionN₆₀
RK-10UCS from point load indexσ꜀
IS-02SPT overburden normalization (sands)(N₁)₆₀
IX-01Compression index from liquid limit (undisturbed)C꜀
RK-01Rock Mass Rating (RMR₈₉)RMR
3.9.1 Background — Why Planning is a Billable Deliverable

Planning a geotechnical investigation for a railroad client is not overhead — it is a professional service that prevents costly scope errors and keeps the investigation aligned with the design question the railroad's engineering department needs answered. On railroad programs that operate under Professional Services Agreements (PSA), planning is typically the first deliverable under a task order: a written Investigation Plan or Boring Plan memorandum that the railroad project manager reviews and approves before field work begins.

Importance of Geotechnical Investigation
Importance of Geotechnical Investigation

USACE EM 1110-1-1804 §2-1 defines the objective of a geotechnical investigation as obtaining information that permits design of a safe and economic structure. This definition translates directly to railroad practice: every boring, every sample, and every laboratory test must be traceable to a specific design parameter needed by the railroad's engineering team.

The most common planning failure in railroad geotechnical work is designing the investigation around what is convenient to access rather than what the design requires. A convenient boring is one that can be reached with standard drill rig access from a paved road or an open field. But the critical foundation condition for a railroad bridge abutment, retaining wall, or track embankment is often in a location that requires a track window, specialty equipment, or an ROW access permit — not a convenient open-field location. We plan investigations around the design question first; we solve the access problem second.

Supplemental reference

What an investigation costs relative to the work

Table 5-S3. Site investigation cost as a percentage of project cost (Rowe, 1972, in Look, 2007)

Type of work% of capital cost% of earthworks & foundation cost
Earth dams0.89–3.301.14–5.20
Railways0.60–2.003.5
Roads0.20–1.551.60–5.67
Bridges0.12–0.500.26–1.30
Embankments0.12–0.190.16–0.20
Overall mean0.71.5

Railways sit near the top of the range. Look recommends budgeting no less than 0.2% of capital cost, notes that laboratory testing is typically only 10–20% of investigation cost, and warns against the competitive-bid trend of cutting lab testing and inferring design parameters from field classification alone. In Look’s relative risk ranking, rail embankments and railway bridges are rated higher-risk developments than road embankments and highway bridges.

Source: Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis

Case study: 3.9.14.1 No investigation: “the site across the road is the same” (Look 2023), in §5.14 Case Studies.

Project management · Miller (2009)

Deliverable-Oriented Breakdown of a Geotechnical Investigation Scope

Miller argues that a project plan should be organized around deliverables rather than activities, because the client cares about what the project hands over, not the list of tasks performed. Deliverables are written as nouns. They are arranged in a product breakdown structure (PBS), the top component of the WBS, drawn either as an organization chart or as an indented outline. The single topmost deliverable is level zero; each lower level is produced by successive decomposition of the level above.

A complete PBS holds three kinds of deliverables:

  • Client deliverables – items the client must furnish (documents, site access, facilities, funding). Miller shows them on their own leg so they are not forgotten.
  • Process deliverables – the “glue” (plans, specifications, inventories, strategies) that the client may never see but without which the project deliverables cannot be produced. They can amount to roughly a quarter of the workload and are easiest to find when grouped on one leg.
  • Project deliverables – the items promised to the client.

The fourth level is usually enough detail to control the work. Go deeper where a deliverable is subcontracted (the subcontractor defines two further levels below it), where the deliverable is unfamiliar to the team, or where a team member is unknown to the manager. Miller rejects arbitrary rules such as “no activity longer than 40 hours”; each lowest-level deliverable should define one complete activity. His worked example decomposes a one-day recognition event for 400 employees through Events → Children’s Program → Rides → individual rides.

Successive decomposition of a top-level deliverable down to the fourth level, which Miller treats as the manager’s level of control.
Figure 5-PM1. Successive decomposition of a top-level deliverable down to the fourth level, which Miller treats as the manager’s level of control. Source: Miller (2009), Figure 7.1.

For railroad work: make level zero the thing the railroad is buying, for example “Geotechnical data report and repair recommendations, embankment at MP 112.4.” Level 1 legs might be Field Data, Laboratory Data, Analyses, Reports, Process Deliverables and Client Deliverables. Put the railroad’s obligations on the client leg: right-of-entry and track-access approval, track time and flagging or other roadway worker protection, utility and signal cable records, as-built drawings and the slow-order and maintenance history of the site. Group the safety plan, job-briefing plan, boring location plan, drilling subcontract and chain-of-custody procedure on the process leg. Because drilling is normally subcontracted, have the driller break the drilling deliverable into two more levels (mobilization, each boring log with its sample set, grouting records). A PBS of this kind also makes a clear scope exhibit for the proposal and shows the client exactly what each fee line produces.

Source: Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group), pp. 23–25, 31–33, 45–49. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Oberlender (2000)

Influence Curve and Front-End Scope Definition

Oberlender frames every project as passing through owner’s study, preliminary engineering, detailed design, procurement and construction. His central argument, shown as two opposing curves, is that the ability to influence quality, cost and schedule is highest at the start and falls steadily, while the cost of implementing a change is lowest at the start and rises steeply once procurement and construction begin. Savings are made early, not at the start of construction.

Opposing curves showing that the ability to influence quality, cost and schedule is greatest during project definition, while the cost of making changes climbs through design, procurement and construction.
Figure 5-PM2. Opposing curves showing that the ability to influence quality, cost and schedule is greatest during project definition, while the cost of making changes climbs through design, procurement and construction. Source: Oberlender (2000), Figure 3-3.
The four basic contracting arrangements in simplest form: design/bid/build, design/build, construction management, and owner/agent (force account).
Figure 5-PM3. The four basic contracting arrangements in simplest form: design/bid/build, design/build, construction management, and owner/agent (force account). Source: Oberlender (2000), Figure 3-1.

From this he draws several working rules:

  • The owner’s study must end with stated objectives, minimum quality and performance requirements, an approved maximum budget and a required completion date. If any one of these is missing, the project starts in the wrong direction.
  • Separate what is needed from what is wanted. The best source for needs is the people who will operate the finished facility.
  • Scope comes first; the budget and schedule are then built to match it. A scope checklist (his Table 2.1-1 lists site access, soils and bearing, permits and environmental constraints, among other items) keeps the definition from being a one-line description.
  • When work is requested before it is defined, either do it on a time-and-materials basis until scope can be fixed, or define an assumed scope with a matching budget and schedule, and re-price any deviation before proceeding.
Geotechnical Site Investigation Checklist
Geotechnical Site Investigation Checklist

He also cites the Construction Industry Institute’s Project Definition Rating Index (PDRI): 70 scope elements, each rated 1 (complete) to 5 (poor), weighted to a maximum of 1,000 points. In the CII study, projects that scored below 200 performed significantly better than those that scored above 200.

Construction Rarely Fails at the Point of Failure
Construction Rarely Fails at the Point of Failure

For railroad work: The geotechnical investigation sits at the high-influence end of the curve. Boring locations, depths and lab assignments are fixed while the repair concept (undercut and blanket, shear key, wall, ground improvement or culvert replacement) is still open. Once a track window is booked and materials are ordered, changing direction costs track time as well as money. Before mobilizing a drill rig, confirm with the railroad’s project engineer the purpose of the work, the performance target (for example, removing a slow order or meeting a settlement tolerance), the access and work-window constraints, and the not-to-exceed budget. Record any assumptions in the scope letter so that a later change, such as adding a culvert crossing or extending the limits after a new slip, is visibly a change and is priced as one.

Source: Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill, pp. 33–41, 119–121. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Cretu et al. (2011)

Estimate Range Versus Design Maturity — Why Early Investigation Narrows the Upper Tail

Cretu, Stewart and Berends describe four estimate levels (planning, scoping, design, and final/letting), each with its own purpose, method and expected accuracy. The accuracy range narrows as design matures, but it is not symmetrical: the upper end sits much farther above the baseline than the lower end sits below it, and the upper end moves toward the baseline faster as project-specific information is gained. The authors read this as evidence that economic and political pressures push early numbers down, and they warn reviewers to watch for it. They place reasonably firm project definition at roughly 30 percent design. Before that point the estimate range is driven mostly by scope uncertainty; after it, by unit-cost and market uncertainty plus discrete risk events.

Asymmetric estimate range plotted against percent design completion for a project whose final cost is $100 million, showing the upper end converging on the baseline as design advances.
Figure 5-PM4. Asymmetric estimate range plotted against percent design completion for a project whose final cost is $100 million, showing the upper end converging on the baseline as design advances. Source: Cretu et al. (2011), Figure 2.2.

Their illustration uses a project that ends up costing $100 million. Read from their chart, the plausible range at about 2 percent design runs from roughly $50 million to $300 million, tightens to about $70–150 million at 30 percent, and is close to $95–110 million at letting. In the same way, the “miscellaneous item allowance” that covers undefined scope typically falls from 30–50 percent at planning, to 20–30 percent at scoping, to 10–20 percent during design, and to zero at letting, when every item should be defined. The authors also call for a written basis of estimate (BOE) that records scope, exclusions, assumptions, data sources and the threats and opportunities known when the estimate was made. They urge reporting early estimates as ranges, because the first number given is the one everyone remembers.

For railroad work: On subgrade rehabilitation, slide repair and culvert replacement projects, the upper tail of the estimate is driven mainly by ground conditions: depth to competent material, soft or organic foundation soils, groundwater, and the extent of fouled ballast or a failed subgrade layer. That makes the investigation the main way to pull the upper end down before the railroad sets a capital budget. When scoping a program, show the client the current estimate range, identify which geotechnical unknowns control its upper end, and describe how the proposed borings, CPT soundings or GPR would narrow it. Record the geotechnical assumptions behind each estimate in a BOE-style note, such as an assumed undercut depth, assumed rock line or assumed drainage outfall, so that later changes can be traced to new subsurface data rather than read as estimating error.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 18–25. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

3.9.2 Desktop Review — The Essential First Step

Every railroad geotechnical investigation begins with a desktop review before a single boring is planned. The desktop review assembles all available prior subsurface and surface information for the project corridor and produces a preliminary geologic model that frames the entire investigation strategy.

3.9.2.1 Sources of Prior Information

Existing boring data: Railroad clients maintain subsurface databases of varying quality. Owner railroads maintain central engineering databases that may contain prior boring logs for the project corridor. The railroad's engineering department archives prior geotechnical reports and can provide boring logs for Class I network segments. The railroad's engineering group maintains a GIS-based boring database for capital projects. For short-line subsidiary networks, prior subsurface data is often sparse or held at the subsidiary level — contact the short-line corporate engineering group early to determine what is available.

Published geologic maps: USGS 7.5-minute quadrangle maps and state geologic surveys provide bedrock and surficial geology. The USGS National Geologic Map Database is the primary digital resource. Specific attention: karst terrain (Missouri, Indiana, Kentucky — Class I railroad corridors), residual soil from granitic gneiss (Virginia, North Carolina, Georgia — Class I railroad corridors), loess deposits (Mississippi Valley — Class I railroad corridors), expansive clay (Gulf Coast, Texas — Class I railroad corridors).

Engineering Geology
Engineering Geology
Geology vs. Geotechnical Engineering
Geology vs. Geotechnical Engineering

USDA Web Soil Survey: Provides surficial soil mapping at 1:24,000 scale. Useful for preliminary identification of potentially soft or problematic subgrades along new alignment corridors.

FEMA Flood Insurance Rate Maps (FIRM): Identify flood-prone zones and potential high-water conditions for bridge approaches, embankments, and drainage structures on owner railroads' corridors.

Aerial photographs and satellite imagery: Historical aerial photograph archives (USGS EarthExplorer) reveal past land use, former fill areas, evidence of slope movement, and changes in drainage patterns that may not appear in current satellite imagery.

LiDAR digital elevation models: State and federal LiDAR datasets provide 1- to 2-ft contour resolution suitable for preliminary slope geometry characterization and drainage analysis. Most state DOTs and USGS provide free LiDAR downloads.

Prior geotechnical reports: Obtain all prior geotechnical reports for the project corridor, including reports prepared for adjacent projects on the same railroad. For the owner railroads, prior reports may reside in the railroad's internal engineering archive rather than with the geotechnical consultant.

Maintenance records are investigation data

Change in track geometry under traffic comes from one of two sources: cumulative deformation of the ballast and subballast, or movement of the subgrade. Field observation combined with maintenance records at chronic spots tells the two apart. Frequent resurfacing at the same location, when it traces to the subgrade, points to low bearing capacity. Ask the client for:

  • Surfacing and tamping history.
  • Geometry-car trends.
  • Slow-order records.

Build up a district file of soil and geology maps that later projects can reuse. A deterioration rate that rises from one maintenance cycle to the next is a useful trigger for a substructure investigation.

After Selig & Waters (1994), chs. 4, 10 and 15. Full reference under Supplemental References.

3.9.2.2 Desktop Review Memorandum

The desktop review culminates in a written memorandum — typically 3 to 8 pages — that the railroad project manager can review before authorizing field work. The memorandum covers:

  1. Preliminary geologic model: formation names, anticipated stratigraphy, depth to bedrock estimate, groundwater depth estimate
  2. Identified geotechnical risk areas: soft ground, karst, landslide-prone slopes, high water table, expansive soils, liquefiable materials
  3. Gaps in prior data that the proposed investigation must fill
  4. Preliminary recommendation for investigation type and approximate scope
  5. Access and scheduling considerations specific to the railroad's ROW procedures
Supplemental reference

Flagging environmental conditions during the desktop review

Yards, fueling facilities, former industrial spurs and sidings next to waste sites often put a geotechnical boring inside an environmental compliance or remediation footprint. Repetto (2003) groups these projects as waste disposal (landfills, lagoons, tailings), compliance at active facilities, and remediation at closed facilities; the containment systems used are liners, low-permeability covers and slurry-wall cut-offs. When the desktop review identifies one of these, the plan should:

GIS in the Environmental Impact Assessment Process
GIS in the Environmental Impact Assessment Process
  • Coordinate with the railroad’s environmental group before drilling, and treat drill cuttings and water as potentially regulated waste.
  • Avoid penetrating a liner, cap or slurry wall; locate existing containment features on the boring plan.
  • Recognize that regulatory barrier layers typically require k ≤ 3 × 10−4 ft/day, and that a slurry wall must be keyed into a continuous low-permeability stratum — borings near such walls may be asked to confirm that stratum.
  • Budget a separate geo-environmental sampling scope (Look notes it is costed separately from the geotechnical investigation).

Source: Repetto, P. C. (2003). “Geo-Environment,” Ch. 26 in The Civil Engineering Handbook, 2nd ed. CRC Press

Desk study, route stages and mapping scales

Profillidis starts every geotechnical investigation with available documents (topographic, geologic and hydrogeologic maps, aerial photographs, historical investigation records) and a site reconnaissance, to understand the likely problems and to plan the main study. For new-line design he ties the investigation to the design stages:

Historical vs New Site Boreholes
Historical vs New Site Boreholes
Table 3.9-4. Design stages and mapping for a new railway line
StageMapping scaleScope
Preliminary design1:50,000 or 1:25,000, aerial / satellite imagery2–4 possible routes; horizontal and longitudinal profiles; major structures, utilities and first cost estimate
Outline design1:5,000; cross-sections every 330 ft2–3 routes within a corridor 164 ft wide (flat terrain) to 1.2 mi or more (mountains); subgrade and drainage, bridges and tunnels, construction planning
Final design1:2,000–1:1,000 (difficult terrain); 1:1,000–1:500 (urban)Balance of speed, curvature, gradient and soil-mechanics constraints; minimize future maintenance
Figure 3.9-9. Alluvial (debris) fan below a mountain drainage basin.
Figure 3.9-9. Alluvial (debris) fan below a mountain drainage basin.

For existing lines built decades ago, he notes that a full analytical survey is usually not needed, but a general knowledge of the subgrade’s basic mechanical behavior is essential.

After Profillidis (2014), §9.2.2, §9.3, §14.13–14.14, Fig. 14.12. Full reference under Supplemental References.

Read the landform to predict the soil

Similar landforms are built the same way and contain similar materials. Identify the landform and you can predict the material and how it will behave. Almost all railway terrain has published geologic and soil mapping, and cross-referencing problem sites against it is a useful desktop habit.

  • Glacial till was compressed beneath the ice and performs almost like rock; eskers are meltwater channels full of sand and gravel (good borrow); moraines, kames and drumlins each have characteristic materials.
  • Sensitive (Champlain Sea) clay in the St. Lawrence Lowlands can hold a steep slope undisturbed but flows when remolded. Treat any movement in mapped areas as an escalation trigger.
  • River terraces attracted early builders because they are flat benches above the channel. They contain silts and clays in low-energy settings and sands and gravels in high-energy ones, are consistent along a valley, and are still active.
  • Alluvial fans grade from coarse at the apex to finer and better-sorted outward. Dunes are mainly a sand-encroachment nuisance.
Figure 3.9-5. Glacial landforms: esker, moraine, drumlins, kames, till plain.
Figure 3.9-5. Glacial landforms: esker, moraine, drumlins, kames, till plain.
Figure 3.9-6. Mapped extent of the Champlain Sea sensitive clay, St. Lawrence Lowlands.
Figure 3.9-6. Mapped extent of the Champlain Sea sensitive clay, St. Lawrence Lowlands.
Figure 3.9-7. A glacial valley filling with sediment and building terraces.
Figure 3.9-7. A glacial valley filling with sediment and building terraces.
Figure 3.9-8. Track built along a river terrace.
Figure 3.9-8. Track built along a river terrace.
Figure 3.9-10. Terrace slope: fill over clayey till with seepage toward the river.
Figure 3.9-10. Terrace slope: fill over clayey till with seepage toward the river.

After Geotechnology for Railroaders Program, Module 2; §02–06. Full reference under Supplemental References.

Traffic and load data to collect before scoping

Traffic type and volume drive the track structure, the number and length of yard and support tracks, and the terminal layout. Collect the traffic basis during the desktop review and have the client confirm it in writing. Only then set the investigation scope and the design loads. Cover both existing traffic and foreseeable growth, including surge or peak periods.

Figure 3.9-4. Track layout of a new line designed with computer-aided design software. Profillidis Fig. 14.12.
Figure 3.9-4. Track layout of a new line designed with computer-aided design software. Profillidis Fig. 14.12.
Table 5-S4. Traffic and load data checklist
ItemWhat to obtainWhy it matters
Traffic typeCommodities handled; car types and sizes; loading and unloading method; height and width of loads on open cars (flats, gondolas); special handling or restrictions, especially hazardous materialsLoading facility type, clearances, special containment
Traffic volumeMaximum cars of each type on site at one time, including empties; maximum cars of all types; longest train into or out of the site; maximum cars each loading facility handles in one cycleNumber and length of tracks, yard and terminal capacity
Wheel loadsHeaviest loaded car in common use on each track; heaviest locomotive (owner’s and serving railroad’s)Design wheel load (Chapter 2.3, Table 2-S8) and subgrade stress
Locomotive tractive effortTractive effort curve, or locomotive weight and horsepower if no curve is availableTrain size versus ruling grade and curvature
SourcesClient operating and transportation staff, shippers, the serving railroad, existing capacity studiesTraceable basis for the design

After UFC 4-860-01FA (2004), ch. 2, §§1–3, 5 and 7. Adapted from military installation practice to railroad and industrial clients by the authors. Full reference under Supplemental References.

Case study: 3.9.14.2 A buried creek the ground model missed: deep basement dewatering (Look 2023), in §5.14 Case Studies.

3.9.3 Regulatory and Client-Standard Requirements That Frame the Investigation

Before finalizing boring locations and depths, we confirm which standards govern the investigation. Railroad clients do not all use the same standards; mixing them up is a professional error that creates review problems and can require costly revisions.

OSHA Top 10 Violations 2023–2026
OSHA Top 10 Violations 2023–2026

AREMA MRE Chapter 1 — Roadway and Ballast is the common technical baseline for subgrade-related investigations on owner railroads. AREMA MRE Chapter 1, Part 2 (Section 3.10) sizes the ballast and subballast from the strength and gradation of the subgrade, so the subgrade must be characterized before those thicknesses are set. AREMA MRE Chapter 8 — Structures governs foundation design for bridges, retaining walls, and culverts using Cooper E-80 design live load.

Each owner railroad also has its own engineering standards, and they differ in boring spacing and depth, log format, sample retention, review and track-access requirements. Obtain the current edition from the owner railroad when the work is scoped, record which edition was used, and follow it where it is stricter than the published guidance in this manual.

Supplemental reference

Utility and pipeline crossings — Class I railroad occupancy requirements

Pipeline and utility crossings are a frequent small task order, and the railroad’s occupancy specification — not the utility owner’s design standard — sets the investigation scope. The railroad's Pipeline Occupancies specification (rev. 2018) requires:

  • When borings are required: for every crossing with a casing 48 in. or larger under track; at the railroad's discretion for smaller casings and other right-of-way facilities.
  • Location: one boring each side of the track(s), on the pipe centerline and as close to track as practicable, with a scaled plan showing borings relative to track and pipe. A Right of Entry permit is needed before drilling.
  • Sampling: ASTM D1586 SPT, continuous from ground surface to 5 ft below the proposed invert. Rock is cored with an M-series double-tube diamond barrel (≥ 1⅝ in. core), runs ≤ 5 ft. Auger-cutting or washwater samples are not acceptable.
  • Closure: record groundwater, then grout the full depth with 4-3-1 bentonite–cement–sand grout.
  • Cover: casing under track ≥ 5.5 ft base of rail to top of pipe; uncased gas lines ≥ 10 ft. Longitudinal lines within 50 ft of centerline need 4 ft cover (non-flammable) or 6 ft (flammable).
  • Methods: bore-and-jack is standard; HDD is a variance considered only with ≥ 15 ft cover or in rock; open cut is not permitted under mainline, heavy-tonnage or passenger tracks.

Table 5-S1. Class I railroad live load on buried structures, Cooper E-80 including impact

Cover (ft)234568101216202530
Load (psf)3,8003,1502,8502,5502,2501,7001,3001,000625400250150

For lateral surcharge on sheet piling or pits beside the track, the railroad specifies a Boussinesq strip load 8.5 ft wide (tie length) with q = 80,000 / (8.5 × 5) = 1,882 psf per E-80 axle. Expect pushback on casings from pipeline owners: Miesner and Leffler explain that the industry has moved away from cased road and railroad crossings because the carrier must be electrically insulated from the casing to prevent galvanic corrosion, and shorted casings are a chronic corrosion problem. That is the reason owners ask for uncased crossings — which the railroad allows for gas lines only at 10 ft or more below base of rail.

Source: A Class I railroad (2018). Design and Construction Standard Specifications — Pipeline Occupancies. Office of VP–Engineering, Jacksonville, FL (rev. June 5, 2018) · Miesner, T. O. and Leffler, W. L. (2006). Oil and Gas Pipelines in Nontechnical Language. PennWell

Supplemental reference

Under-track culverts — Class I railroad criteria that drive the geotechnical scope

  • Design for Cooper E-80 and the 100-year storm; headwater limited to HW/D = 1.5 (inlet control) provided high water stays below the toe of ballast and the fill resists short-term infiltration.
  • Minimum culvert size 36 in.; Rational Method for basins under 500 acres, SCS unit hydrograph or regression methods for larger basins.
  • Coating selection follows soil and water pH: aluminized/bituminous galvanized for pH 5–8; fiber-bonded or plastic-coated where fertilizer runoff, acidic coal-field drainage, salt marsh or heavy-metal soils are present — so plan pH, resistivity and sulfate testing at culvert borings.
  • Smooth-wall casing by jack-and-bore where traffic prevents open cut or fill exceeds 10 ft; tunnel liner plate where diameter, length or rock make jacking impractical.
  • Precast or concrete pipe culverts are not permitted under railroad-owned track without Chief Engineer approval, because of differential settlement and joint separation.

Source: A Class I railroad. Guidelines for Under Track Culverts

3.9.4 Boring Location Planning — Criteria by Project Type

The following boring spacing criteria are taken from published sources in the library; Section 3.9.5.3 sets out the sources, the depth criteria and the planner.

Table 3.9-1: Recommended Boring Spacing by Railroad Project Type
Project TypeSpacing or numberNotesSource
New main, siding or track extensionOne per 500 ft (high-strength soil), 200 ft (medium), 100 ft (low)Add borings at drainage crossings and cut-fill transitionsLi and others (2016), Table 8.1
Existing line, cut and fillSeries of 3 (shoulder, midslope, ditch at toe) about every 1,320 ftA railroad minimum; tighten for the groundA Class I railroad's public projects requirements
Embankment80 to 165 ft at critical areas; 330 ft or more elsewhereShoulder and toe borings at each stationLook, Table 1.8
Cut slope80 to 165 ft (H over 16 ft); 165 to 330 ft (lower cuts)Boring atop the cut and at the toeLook; A Class I railroad's public projects requirements
BridgeEach pier and abutment; one may do for a short bridge in uniform geologyToe of embankment, away from the track, where practicalA Class I railroad's bridge requirements; Look
Retaining wallAt each wall; 50 to 100 ft along the lineDenser in variable groundA Class I railroad's public projects requirements; spacing is practice
CulvertUnder 66 ft: 1; 66 to 130 ft: each end; longer: each end and every 66 ftEach end of a culvert to be extendedLook; A Class I railroad's public projects requirements
Pipeline crossingOne each side of the track on the pipe centerlineContinuous samplingA Class I railroad's pipeline occupancy specification
Yard or intermodal pavementGrid over the paved areaGrid spacing is practice; denser under crane railsEM 1110-1-1804, Table 2-4 (roads)
Slope failureAt least 3 borings or test pits on the critical sectionHead scarp, middle and toeLook, Table 1.8
Subgrade failure or mud boil2 to 4 borings straddling the failureAdd test pits or trenches across the trackPractice

Section 3.9.5.3 gives the full criteria, depths and the planner calculator.

Milepost referencing: All boring locations must be described in terms of railroad mileposts and offset from track centerline (in feet, left or right, looking in the direction of increasing milepost). GPS coordinates (NAD 83, decimal degrees or State Plane in feet) are required in addition to milepost references. Railroad mileposts are the primary location reference for all railroad engineering documents.

Supplemental reference

New alignments and crossing structures that carry wildlife

New alignments and major culvert or bridge replacements increasingly include wildlife passage as a permit condition. The FHWA Wildlife Crossing Structure Handbook gives recommended dimensions for eleven crossing types (overpasses, open-span bridges, large culverts, etc.); most overpasses are under 230–260 ft long, but landscape bridges spanning roads and a railway can be much longer. When a crossing structure is in the scope, add borings at both abutments/footings of the wildlife structure and at the approach fills, and confirm the clear-opening dimensions with the environmental permit before setting foundation boring depths.

Geotechnical Investigation for Bridges
Geotechnical Investigation for Bridges
Landscape bridge near Hilversum, The Netherlands, about 2,600 ft long, spanning two roads and a railroad (photo credit in source: Goois Natuurreservaat / W. Metz).
Supplemental Figure 5-S1. Landscape bridge near Hilversum, The Netherlands, about 2,600 ft long, spanning two roads and a railroad (photo credit in source: Goois Natuurreservaat / W. Metz). Source: Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003, p. 60.

Source: Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003

What the investigation must answer, and in what stages

No new line can be designed correctly or built economically unless the soils and hydrogeology along the route are known in detail. Profillidis lists what the investigation must establish:

  • whether fill material is available on site or must be imported;
  • appropriate slopes for embankments and cuts;
  • whether loosening or densification of soil may occur;
  • where weak ground needs treatment before filling;
  • where groundwater will cause problems;
  • measures for long-term stability of earthwork slopes;
  • where cuts need special drainage or protection;
  • what planting suits the cut and fill slopes.

Because investigation is costly, run it in stages: assemble existing information; reconnaissance (geologic and topographic maps, aerial photos, water and oil well logs, hydrologic data, state soil manuals); a preliminary site investigation with a few borings or test pits to establish stratification, soil types and groundwater; then the detailed investigation. The program should yield strength, deformation and hydraulic properties at the least cost. Techniques fall into geophysical (seismic, magnetic, gravimetric, resistivity), physical (borings, test pits), mechanical (pressuremeter, penetrometer, laboratory) and hydrogeological (piezometers) methods.

Foundation Soil Investigation
Foundation Soil Investigation
Soil Investigation Before Construction
Soil Investigation Before Construction

After Profillidis (2014), §9.2.1–9.2.4. Full reference under Supplemental References.

What the subgrade investigation must deliver for track design

Before the track structure is designed, the investigation along the alignment should establish, at a minimum:

  • Soil type and classification
  • Strength and bearing capacity
  • Groundwater levels
  • Natural water content (the UFC bearing check in Chapter 1.4, Table 2-S9 uses qu at natural water content)
  • Compaction characteristics of soils that will form or be reused in the subgrade

Add borings, laboratory testing and analysis at bridges and other special structures. AREMA Chapter 1, Part 1 gives the base recommendations, and the spacing in Table 3.9-1 applies. Where chemical stabilization is under consideration in a frost area, include frost-susceptibility and freeze–thaw durability testing in the laboratory program.

After UFC 4-860-01FA (2004), ch. 6, §8b and §8e. Full reference under Supplemental References.

Investigating the trackbed itself

Do not judge the trackbed from the surface. Clean ballast at the surface may be only one particle thick. Selig and Waters recommend the following, in order of effort:

  • Shoulder pits to about 3 ft below the subgrade surface, with the shoulder ballast removed to expose the ballast and subballast.
  • Cross trenches (full or half track width) to at least 4 ft below top of tie. Use them to find ballast pockets and depressions in the subgrade surface.
  • BALCON-type pits. Describe the site and delineate layers by color and gradation. Describe samples to ASTM D2488, with pits 1–2 ft or more below the tie. Many sites can be logged per day. Because layers are usually horizontal, one pit often represents a section. From the gradations, plot the percentage of reclaimable stone against undercut depth. The breaks in slope mark the layer boundaries and set the cutting depth.
  • Rail-mounted boring machine (British Rail). It has a center unit plus two side units that swing out to 10.8 ft from centerline. It drills 6.2 ft below the rail head as standard and up to 16.4 ft, and the core is viewed through a slot in the tube. An intact blanket with no subgrade fouling marks a good candidate for cleaning.
  • Deeper work. Use hollow-stem auger borings with SPT, rock coring and CPT.

Depth. Traffic stress is significant to about 16 ft below the tie, and rail deflection 80 in. down is still about half the surface value. CPT for track-modulus back-analysis should reach at least 16 ft below the tie.

After Selig & Waters (1994), chs. 2, 5, 10, 14 and 16. Full reference under Supplemental References.

3.9.5 Boring Depth Planning — Criteria and Equations (English Units)

Boring depth must be sufficient to characterize all soil and rock materials that will influence the performance of the planned structure or earthwork. Minimum boring depths for each project type are set by the applicable stress influence criterion, the structure geometry, and the owner railroad's requirements.

3.9.5.1 Stress Influence Criterion — 2:1 Method

For footings and other structures, Das gives the ASCE (1972) rule: the minimum boring depth is the smaller of D1, where the stress increase falls to 10% of the applied pressure, and D2, where it falls to 5% of the effective overburden stress. The rule is for structures, not embankments (Section 3.9.5.3.3). Using the 2:1 stress distribution approximation:

Equation 3.9-1: Stress Increase at Depth z Below a Loaded Area B × L (English units)
Δσz = Q(B + z)(L + z)

Where:

  • Δσ_z = stress increase at depth z (psf)
  • Q = total applied load (lb)
  • B = footing width or embankment base width (ft)
  • L = footing length or embankment base length (ft)
  • z = depth below the base of the loaded area (ft)

Minimum boring depth condition (ASCE 1972, in Das):

D1: Δσz = 0.10 q;   D2: Δσz = 0.05 σ'v0;   minimum depth = smaller of D1 and D2

Where σ'_v₀ is the effective overburden stress at depth z (psf), computed as:

σ'v0 = γ' × z

with γ' = effective unit weight (pcf), typically 55–65 pcf (buoyant) below the water table, or 100–125 pcf (total) above it.

Inputs: where each value comes from (6)
SymbolWhat it isComes fromHow to get itTypical range
Qtotal applied load (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Bfooting width or embankment base width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Lfooting length or embankment base length (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
zdepth below the base of the loaded area (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
σ'v0vertical stress / pore pressure = γ' × zAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
γ'buoyant unit weightAnother equationγ' = γsat − γw (γw = 62.4 pcf). Use below the water table.50–75 pcf for most mineral soils · by USCS group
Important Foundation Levels
Important Foundation Levels
Equation 3.9-2: Minimum Boring Depth for a Square Footing (B × B)

For a square footing with total applied stress q (psf) over area B²:

D1 = (√10 − 1) B ≈ 2.16 B;   D2: q B² / (B + z)² = 0.05 σ'v0(z), solved by trial

D1 has a closed form for a square footing; D2 does not, because σ'v0 grows with z. The investigation planner (Section 3.9.5.3) solves both.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
γ'buoyant unit weightAnother equationγ' = γsat − γw (γw = 62.4 pcf). Use below the water table.50–75 pcf for most mineral soils · by USCS group
3.9.5.2 Minimum Boring Depths by Project Type (English Units)
Minimum boring depths by project type
Project TypeMinimum Boring Depth (ft)Source
Track subgrade, new or existing10 to 15 ft below proposed grade; stop at rock or 5 ft into dense or very stiff soilLi and others (2016)
Embankment fill0.5 to 2 times the fill height below original ground, and through compressible soilDas (2010); Look, Table 1.8
Cut slopeTop of cut: to 5 ft below the proposed ditch flowline; toe: 16 ft or 10 ft into rock, whichever is shallowerA Class I railroad's public projects requirements; Look
Bridge, spread footingAbout 2 B below the base, and the ASCE stress depth; Look gives 4 B to 5 BA Class I railroad's bridge requirements; Das; Look
Bridge, piles or shafts10 ft below the estimated tip, or 10 pile diameters in competent strataA Class I railroad's bridge requirements; Look
Bridge pier in a waterwayBelow the estimated scour depth as well as the foundation criterionScour estimate (FHWA HEC-18 methods)
Retaining wallAbout 2 to 2.5 times the retained height for a cantilever soldier pile wall; into rock or a firm layerPractice
Culvert2 B to 4 B below the invert, and below compressible soilLook, Table 1.8
Slope failure investigationBelow the slide zone: as a guide 2 times the slope height or the width of the moving zoneLook, Table 1.8
Rock coringAbout 10 ft into rock to prove it is not a boulderLook, Table 1.8

Values not supported by the sources in the library were removed in the November 2026 fact check (Table 3.9-8).

Supplemental reference

Railroad-bridge boring depth rules of thumb

The railroad's bridge investigation requirements (Ruel, 2003) follow AREMA and add practical limits: borings extend below the depth significantly affected by the loads, river scour or deep shear — about twice the anticipated spread-footing width, or 10 ft below the estimated pile tip from a preliminary static analysis. One boring can be sufficient for a short bridge replacement in uniform, well-mapped geology; where practical, drill at the toe of the embankment rather than on the track. A railroad Bridges & Structures representative accompanies the crew.

The railroad also asks the geotechnical engineer for: allowable pile load vs. depth for each pile type (typical working load about 160 kips for a 14-in. H-pile), DRIVEN static capacity (compression and uplift), GRLWEAP driving criteria and maximum blows/in., p–y curves, and a linear lateral spring constant K per stratum for pile deflection up to about ½ in. at the bridge seat — so SPT, strength and unit-weight data must be sufficient for LPILE input in every stratum.

Table 5-S2. Guideline to extent of investigation (Look, 2007, Table 1.8, abridged)

DevelopmentTest spacingApproximate depth
BridgesEach pier4B–5B for shallow footings; 10 pile diameters in competent strata; in bedrock, ≥ 10 ft of coring and 3 pile diameters below founding level (RQD > 50%, moderately weathered or better)
Buildings65–165 ft2B–4B for pads/strips; 10 ft or 3 diameters below pile toe
Embankments80–165 ft at critical areas; 330–1,650 ft elsewhereBeyond base of compressible alluvium at critical or suspect areas

Source: Ruel, M. and KRK (2003). General Requirements for Geotechnical Investigations for the railroad's Bridge Construction Projects and “A Practical Approach to Lateral Loading on Piles for Railroad Bridge Design on Class I railroad Projects.” a Class I railroad · Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis

Geotechnical Investigation
Geotechnical Investigation
3.9.5.3 Required Boring Spacing and Depth

No single code fixes how many borings a railroad project needs or how deep they go. The criteria in the library come from four kinds of source, and they do not all agree: a Class I railroad's own requirements (public projects, bridge foundations and pipeline occupancy), a railway geotechnics text that ties boring spacing along the track to soil strength (Li and others), general investigation guides (Look's Table 1.8, USACE EM 1110-1-1804 Table 2-4 and a short course on site investigation), and the stress rule for structures given by Das. This section sets them side by side, fact-checks the spacing and depth values used elsewhere in this manual against them, and gives the planner that applies them. Use the railroad's requirement as the minimum, then tighten spacing and extend depth for the ground: weak, variable or suspect soil governs over any table.

3.9.5.3.1 Spacing

Table 3.9-5. Boring spacing and number by feature, with sources
FeatureSpacing or numberSource
Track corridor (new siding, second main, extension)One boring every 500 ft in high-strength soil, 200 ft in medium, 100 ft in low-strength soilLi and others (2016), Table 8.1
Existing line, cut and fill (public projects)A series of three borings (on the track grade at the shoulder, at midslope, and in the ditch at the toe) about every quarter mile (1,320 ft), sited to represent the prevailing cut or fillA Class I railroad's public projects requirements
Embankments80 to 165 ft at critical or suspect areas; 330 ft or more elsewhere, as for roadsLook, Table 1.8
Cut slopes80 to 165 ft where H exceeds 16 ft; 165 to 330 ft where H is under 16 ftLook, Table 1.8
Landslide or slope failureAt least three borings or test pits along the critical sectionLook, Table 1.8
BridgesAt each pier and abutment; one boring can be enough for a short bridge in uniform, mapped geologyLook, Table 1.8; EM 1110-1-1804, Table 2-4; a Class I railroad's bridge requirements
CulvertsUnder 66 ft long: one; 66 to 130 ft: one at each end; longer: each end and between, at most 66 ft apart. A boring at each end of a culvert to be extendedLook, Table 1.8; a Class I railroad's public projects requirements
Pipeline crossing under trackOne on each side of the track on the pipe centerline, as close to the track as practicableA Class I railroad's pipeline occupancy specification
Retaining wallsAt each wall; 50 to 100 ft along the wall lineA Class I railroad's public projects requirements (at each wall); spacing is practice
Light towers, signal masts, catenary polesAt each foundationLook, Table 1.8 (monopoles and towers)
Roads and yard pavementOne per 490 ft of centerline for a two-lane road (245 ft multilane); a grid over yards (practice)EM 1110-1-1804, Table 2-4

Look's metric values are converted (25 m = 82 ft, rounded to 80; 50 m = 165 ft). Spacing tightens wherever the ground changes between borings, and test pits, probes or geophysics can fill the gaps.

3.9.5.3.2 Depth

Table 3.9-6. Minimum boring depth by feature, with sources
FeatureMinimum depthExtend whenSource
Track subgrade10 to 15 ft below proposed gradePoor soil is known or suspected; stop at rock or 5 ft into dense or very stiff soilLi and others (2016)
Embankment0.5 to 2 times the embankment height below original ground; beyond the base of compressible soil at critical areasSoft, organic or compressible soil continuesDas (2010); Look, Table 1.8
Cut slopeCut height to 5 ft below the proposed ditch flowline (top-of-cut boring); 16 ft below the toe or 10 ft into rock, whichever is shallowerWater-bearing or weak layers below the cutA Class I railroad's public projects requirements; Look, Table 1.8
LandslideBelow the slide zone: as a guide 2 times the slope height or the width of the moving zone, and 16 ft below the toe or 10 ft into rockThe slip surface is not foundLook, Table 1.8
Bridge, spread footingsAbout 2 B below the base (1.5 B to 2 B); Look gives 4 B to 5 B for bridge footingsCompressible layers within the stress zone; scour depthA Class I railroad's bridge requirements; short course; Look, Table 1.8
Bridge, piles or shafts10 ft below the estimated tip; 10 pile diameters in competent strataWeak layer below the tipA Class I railroad's bridge requirements; Look, Table 1.8
RockAbout 10 ft of core, to show that rock is not a boulder; for bridge piles, 3 diameters below founding levelVoids, clay seams or weathered zonesLook, Table 1.8
Culvert2 B to 4 B below the invert (B = span), and below compressible soilHigh fill over soft groundLook, Table 1.8
Pipeline crossingContinuous sampling to 5 ft below the proposed invert; rock cored–A Class I railroad's pipeline occupancy specification
Light tower or pole15 ft for poles up to 66 ft high, rising to about 49 ft for 230 to 260 ft towers; less in hard ground, 30% more in softLoose sand or soft clayLook, Table 1.8
Road or yard pavement10 ft below finished grade (6.5 ft below formation in Look)Organic or soft fill continuesEM 1110-1-1804, Table 2-4; Look, Table 1.8

Every boring that ends in soft, organic or loose soil, uncontrolled fill, or rock that could be a boulder is extended, whatever the table says.

3.9.5.3.3 The stress rule for structures

For footings and other structures, Das gives the rule recommended by the American Society of Civil Engineers (1972). Find the depth D1 at which the stress increase from the structure falls to 10% of the applied pressure, and the depth D2 at which it falls to 5% of the effective overburden stress. The approximate minimum boring depth is the smaller of the two. The short course gives the same picture from elastic theory: under a square footing the stress increase is about 15% of the applied pressure at 1.5 B and 10% at 2 B, but under a long strip it is still 40% and 30% at those depths, so strips need deeper borings.

Equation 3.9-3. ASCE (1972) boring depth rule, with the 2:1 stress distribution

Δσ(z) = q B L / [(B + z)(L + z)];   D1: Δσ = 0.10 q;   D2: Δσ = 0.05 σ'v0;   minimum depth below the base = smaller of D1 and D2

z is measured below the footing base; σ'v0 is the effective overburden stress at that depth, with the buoyant unit weight below the water table.

The rule was written for buildings and does not work for embankments. Under a strip as wide as a railroad fill, D1 is about 9 times the base width, which is why Das gives a separate range for embankments (one-half to two times the height) and why this manual no longer applies the stress check to fills.

Table 3.9-7. Checks of the planner against the sources
CheckSourcePlanner
Square footing, depth where Δσ = 10% of qAbout 2 B (short course, elastic); 2.16 B (2:1 closed form)2.17 B (B = 10 ft, D1 = 21.7 ft)
Long strip, depth where Δσ = 10% of qWell beyond 2 B (short course: 30% at 2 B); 9 B (2:1 closed form)8.9 B
Track corridor in medium soil, 6,500 ftOne boring every 200 ft (Li and others)34 borings, 510 ft
Culvert 150 ft longEach end and between, at most 66 ft apart (Look)4 borings
Pipeline crossing, invert 9 ft below the trackEach side, to 5 ft below the invert (a Class I railroad's specification)2 borings to 14 ft, rounded to 15 ft

3.9.5.3.4 What the fact check changed

Table 3.9-8. Earlier values in this manual and the published criteria
Earlier valueWherePublished criterionNow
Track subgrade borings every 500 to 1,000 ftTable 3.3-2100 to 500 ft by soil strength (Li and others); quarter-mile series as a railroad minimum100 to 500 ft; quarter-mile series as the floor
New sidings: 3 borings up to 5,000 ft; 1 per 2,500 ft beyondTable 3.9-1As aboveSpacing by soil strength
Embankment over 10 ft: 1.5 times the base width deepSection 3.9.5.20.5 to 2 times the height (Das)0.5 to 2 H, through compressible soil
Depth where Δσ = 10% of σ'v0Section 3.9.5.1Smaller of D1 (10% of q) and D2 (5% of σ'v0), for structures only (ASCE, in Das)Equation 3.9-3
Culvert: one diameter below the invertTable 3.3-32 B to 4 B below the invert (Look)2 B to 4 B
Rock core 5 to 10 ftTable 3.3-3About 10 ft (Look)10 ft
Pile-supported abutment: 20 ft below the tipSection 3.9.5.210 ft below the tip (a Class I railroad's bridge requirements); 10 pile diameters (Look)10 ft or 10 diameters

3.9.5.3.5 Worked examples

Slope repair. A 600-ft embankment repair with 20-ft slopes in medium-strength soil, with the railroad's three-boring series (shoulder, midslope and toe) at each station. At the 165-ft spacing Look gives for critical areas the planner places 5 stations and 15 borings: the shoulder borings go through the fill and one fill height below original ground (40 ft), the midslope and toe borings to 30 ft. That is 500 ft of drilling, about 6.1 days at 90 ft/day including half a day to set up, and a standby allowance of 24.5 hr at 3.5 hr/day.

New siding. A 6,500-ft siding on medium-strength soil needs about 34 borings at 200-ft spacing, each 15 ft deep (510 ft). The railroad's quarter-mile series would give 6 stations and 18 borings; the soil-strength spacing governs here, and the railroad minimum governs only in strong, uniform ground.

Bridge footing. A 10-ft-square pier footing with its base 6 ft deep, bearing 4,000 psf, groundwater at 10 ft: D1 = 21.7 ft and D2 = 38.8 ft below the base, so the stress rule gives 21.7 ft. The railroad's 2 B gives 20 ft. The planner takes the deeper, 21.7 ft, and adds the 6-ft embedment: borings about 30 ft deep at each support.

Write the basis of every boring depth into the boring plan (the rule, its source and the dimension used), and give the driller the instruction to extend any boring that ends in soft or organic soil, fill or possible boulders. A boring stopped at a table depth in the wrong material is the most common reason a second mobilization is needed.

Open the investigation planner calculator →
Boring number, spacing and depth for eleven railroad features from the published criteria above, the ASCE stress check for footings, soil and core footage, drilling days and train standby.

3.9.5.3.6 Sources in the library

These documents are in the reference library. Summaries are paraphrased and metric values converted to English units. Individual railroads are not named.

  • A Class I railroad's public projects geotechnical requirements, 16 Railroad, Carriers folder: quarter-mile boring series, cut and culvert borings.Find source ↗
  • A Class I railroad's general requirements for geotechnical investigations for bridge construction projects (2003), Site Investigation folder: one boring for short bridges, 2 B or 10 ft below the pile tip.Find source ↗
  • A Class I railroad's pipeline occupancy specification (2018), Carriers folder: borings each side of the track to 5 ft below the invert.Find source ↗
  • D. Li, J. Hyslip, T. Sussmann and S. Chrismer, Railway Geotechnics (2016), Section 8.1.2 and Table 8.1: spacing by soil strength, depth 10 to 15 ft below grade.Find source ↗
  • B. G. Look, Handbook of Geotechnical Investigation and Design Tables (2007), Table 1.8: guideline to extent of investigation.Find source ↗
  • USACE, EM 1110-1-1804 Geotechnical Investigations (2001), Table 2-4: suggested boring programs (after Dunlap 1980).Find source ↗
  • B. M. Das, Principles of Geotechnical Engineering, 7th edition, Section 18.1: boring spacing, building depth rules and the ASCE (1972) stress rule; embankments 0.5 to 2 H.Find source ↗
  • A Short Course in Geotechnical Site Investigation, Chapter 1: borehole depth of 1.5 B to 2 B and the stress increase under square and strip footings.Find source ↗
3.9.6 Worked Calculation Examples
The three examples set boring depth for an embankment and a bridge abutment, and build a boring scope for a yard. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 3.9-1: Boring Depth for a New Siding Embankment

A new 4,800-ft siding needs a 12-ft fill. Boring depth for an embankment is often set with the stress rule written for structures, and the example shows why that gives an absurd answer for a wide fill, and what to use instead.

Residual sandy clay, γ = 118 pcfFill 12 ft, γ = 125 pcfB = 80 ftGWT 15 ftD1, D2 = ?Boring depth = ?14-ft track centersGivenH = 12 ft; γfill = 125 pcfB = 80 ft; 2H:1V; two tracksClay γ = 118 pcf; GWT 15 ftD1: Δσ = 10% qD2: Δσ = 5% σ′v Das, Li et al., Look rulesRequiredStress-rule depths D1 and D2 Recommended centerline depthBlack = given; red = required
Given and required for Example 3.9-1.

Given

VariableValueDescription
H12 ftEmbankment height
γfill125 pcfCompacted granular fill (assumed)
B80 ftBase width; 2H:1V slopes, two tracks at 14-ft centers
γ118 pcfResidual sandy clay
zw15 ftDepth to water; γ′ = 55.6 pcf below it
CriteriaSection 3.9.5.3.3Stress rule (D1: Δσ = 10% q; D2: Δσ = 5% σ′v); embankment rules of Das (0.5 to 2H), Li et al. (10 to 15 ft) and Look (through compressible soil)

Required

  • Stress-rule depths D1 and D2
  • Recommended centerline boring depth

Equations

  1. Eq. 1: q = γfill H — applied stress
  2. Eq. 2: Δσz = q B / (B + z) — 2:1 method, strip
  3. Eq. 3: D1: B/(B + z) = 0.10; D2: q B/(B + z) = 0.05 σ′v(z) — stress rule

Steps

Step 1 · Applied stress (Eq. 1)
125 × 12
q = 1,500 psf
↓
Step 2 · D1 (Eq. 3)
80/(80 + z) = 0.10
z = 720 ft
↓
Step 3 · D2 (Eq. 3)
120,000/(80 + z) = 0.05[1,770 + 55.6(z − 15)]
z ≈ 162 ft
Spot check: At 162 ft: Δσ = 120,000/242 = 496 psf; 5% of (1,770 + 55.6 × 147) = 5% of 9,943 = 497 psf.
↓
Step 4 · Embankment criteria
Das: 0.5H to 2H = 6 to 24 ft; Li et al.: 10 to 15 ft; Look: through compressible soil
About 25 ft (2H), extended through any soft soil
↓
Solution
Drill about 25 ft below grade, deeper through any soft soil.

Solution

The stress rule gives 162 ft, which no one would drill for a 12-ft fill. Take the centerline boring to about 25 ft below existing ground (2H) and extend it through any soft or compressible soil found.

The stress rule was written for structures with modest footprints; under an 80-ft-wide strip the stress decays so slowly that the rule runs to absurd depths. For embankments the published embankment criteria govern. Record the basis of the depth in the boring plan, so the reviewer sees it was chosen, not guessed.

Example 3.9-2: Boring Depth for a Pile-Supported Bridge Abutment

A bridge replacement on a Class I railroad main line needs a new pile-supported abutment. Old borings show where the existing piles stopped, which is the best first guess at where the new ones will.

Soil Exploration and Foundation Basics
Soil Exploration and Foundation Basics

Given

VariableValueDescription
Refusal (1962 borings)45 ftExisting HP piles assumed to stop near here
New pile tip40 to 55 ftRange for the new load
Rule20 ft below the estimated pile tipSection 3.9.5.2
Owner rule (assumed)At least 20 ft into competent bearing material, or refusal, whichever is deeperConfirm with the railroad’s engineer

Required

  • Minimum boring depth

Equations

  1. Eq. 1: D = deepest estimated tip + 20 ft — Section 3.9.5.2

Steps

Step 1 · Deepest estimated tip
Upper end of 40 to 55 ft
55 ft
↓
Step 2 · Depth (Eq. 1)
55 + 20
75 ft
↓
Step 3 · Owner rule
Also 5 ft below the first refusal horizon, if that is deeper
↓
Solution
75 ft, or 5 ft below first refusal, whichever is deeper.

Solution

Drill to at least 75 ft, or 5 ft below the first refusal horizon, whichever is deeper.

Using the deep end of the tip range protects against a second mobilization if the design load pushes the piles deeper than the old ones. Refusal in 1962 may have been on a boulder or a hard layer over softer soil, so the new borings should core or sample through it rather than stop.

Example 3.9-3: Preliminary Boring Scope for an Intermodal Yard

A first-pass boring count and footage for a new intermodal yard expansion, built up zone by zone. The total drives the drilling budget in Chapter 3.7.

Yard plan: 2,200 ft × 800 ft3 crane rails, 2,100 ft: borings at 200 ft, 65 ft deepPavement 20 ac: 1 per 2 ac, 20 ftBuildingAcres = ? Boring count and total footage = ?GivenFootprint 2,200 × 800 ftCranes: 3 rails × 2,100 ft; 200-ft spacing, 65 ftPavement 20 ac: 1 per 2 ac, 20 ftBuilding 100 × 200 ft: 5 borings, 60 ftOther: 6 borings, 15 ftRequiredFootprint in acresBoring count and total footageBlack = given; red = required
Given and required for Example 3.9-3.

Given

VariableValueDescription
Footprint2,200 ft × 800 ftYard area
Cranes3 parallel crane rails, each 2,100 ftBorings at 200-ft spacing, 65 ft deep (20 ft below a 45-ft pile tip)
Pavement20 acres1 boring per 2 acres, 20 ft deep
Building100 ft × 200 ft4 corners + center, 60 ft deep (piles assumed)
OtherDrainage, gate, utilities6 borings, 15 ft deep

Required

  • Footprint in acres
  • Boring count and total footage

Equations

  1. Eq. 1: A = L W / 43,560 — acres
  2. Eq. 2: N = L / s + 1 — borings along a line
  3. Eq. 3: Footage = Σ Ni Di

Steps

Step 1 · Area (Eq. 1)
2,200 × 800 / 43,560
40.4 acres
↓
Step 2 · Crane borings (Eq. 2)
3 × (2,100/200 + 1) = 3 × 11.5, rounded to 11 per line
33
↓
Step 3 · Count
33 + 10 + 5 + 6
54 borings
↓
Step 4 · Footage (Eq. 3)
33(65) + 10(20) + 5(60) + 6(15) = 2,145 + 200 + 300 + 90
2,735 ft
↓
Solution
54 borings, 2,735 ft.

Solution

About 54 borings totaling 2,735 linear feet.

The crane rails take over three-quarters of the footage, because their pile foundations need deep borings at close spacing. That is where scope negotiation should focus: if the crane design allows 300-ft spacing, the count drops by about 10 borings and 650 ft.

3.9.7 Laboratory Testing Assignment Matrix

Laboratory testing must be assigned during planning — not after borings are complete. The testing matrix is organized by project feature, governing design calculation, and required test data.

Table 3.9-2: Laboratory Testing Assignment by Design Feature (English Units)
FeatureDesign CalculationRequired TestsTypical Quantity
Track subgrade — embankmentSettlement, bearing capacityMC, Atterberg limits, USCS classification, consolidation1 consolidation per soft layer identified
Track subgrade — cutSlope stability, shrink/swellMC, Atterberg limits, unconfined compression (q_u), direct shear2–3 q_u per cut
Bridge abutment — spread footingBearing capacity, settlementMC, Atterberg limits, consolidation, unconfined compressionFull suite per 5 ft depth change in critical strata
Bridge abutment — pileSkin friction, end bearingMC, Atterberg limits, triaxial UU (φ, c), grain sizePer critical layer
Intermodal pavementPavement subgrade designMC, Atterberg, CBR (ASTM D1883), M_r (AASHTO T 307)1 CBR per lift zone
Crane rail foundationSettlement, bearing capacityMC, Atterberg, consolidation, triaxial CUFull suite per 10 ft in critical zone
Retaining wallEarth pressure, stabilityMC, Atterberg, direct shear (φ', c'), unit weight1 direct shear per soil unit
Slope stabilityShear strengthTriaxial CU + CD, direct shear (residual φ_r for existing landslides)3+ per failure surface soil unit
Ground improvementSettlement after treatmentMC, Atterberg, consolidation, grain size for PVD drain designFull suite per 5 ft in soft zone
Rock core (all structures)Rock quality, bearing capacityPoint load (q_u conversion), core description (RQD), petrographic1 point load per 5 ft of core
Tests for Soil
Tests for Soil
Rock Tests
Rock Tests
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • RK-10 UCS from point load index σ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).
3.9.8 Representative Boring Log — Sample Format

BORING LOG — PROJECT: [Railroad] [Project Name] [Milepost]

Pile Boring Log
Pile Boring Log

Boring No.: B-1 Date Drilled: [Date] Sheet: 1 of 1

Location: STA 10+50 (MP 347.2 + 0.05 mi), 12 ft Right of CL, Looking Incr. MP

Ground Surface Elevation: 342.4 ft (NAVD 88) Drill Rig: CME-75 Track-Mounted

Drilling Method: Hollow Stem Auger (HSA) 3.25-in. ID Hammer: Auto SPT, 140 lb

Driller: [Name], Certified Class I railroad RWP Logger: [PE Name], PE

DEPTH SAMPLE BLOW DESCRIPTION

(ft) TYPE COUNT (USCS — ASTM D2488/D 2487)

----------------------------------------------------------------------

0-2 - - Fill: silty CLAY, gray-brown, soft, moist

(CL per USCS, AASHTO A-6)

2-5 SPT-1 3/5/7 CLAY, gray-brown, soft to medium, wet

N = 12 (field) MC = 38%

5-10 ST-1 - Shelby Tube (undisturbed sample for consolidation)

CLAY, gray, soft, wet; slight organic odor

MC = 44%, LL = 62, PI = 34 (CH)

10-15 SPT-3 2/4/4 CLAY, gray, soft; N₆₀ = 8; MC = 46%

15-20 SPT-4 4/5/6 CLAY, gray-tan, medium; N₆₀ = 11

20-25 SPT-5 6/8/10 CLAY, tan, medium-stiff; N₆₀ = 18

25-30 SPT-6 8/12/15 Transition to Sandy CLAY (SC); N₆₀ = 27

30-35 SPT-7 11/15/18 SAND, fine, silty, tan (SM); N₆₀ = 33

35-40 SPT-8 15/22/28 SAND, fine-medium, tan-gray (SP-SM); N₆₀ = 50

40 --- --- End of boring at 40 ft (No rock encountered)

Water Level: 6.2 ft below ground surface (measured 24 hr after drilling)

Casing: 3.25-in. HSA, pulled and abandoned

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
3.9.9 Representative Lab Test Data Table — Soil Classification Parameters
Table 3.9-3: Boring B-1 — Laboratory Summary (English Units)
SampleDepth (ft)USCS SymbolLLPLPIMC (%)γ_t (pcf)q_u (tsf)Notes
SPT-12–4CL48222638113—Jar sample
ST-15–7CH622834441080.42Consolidation test specimen
SPT-310–12CH64293546107—Jar sample
SPT-520–22CL422022291170.78q_u by UUC
SPT-730–32SMNPNPNP14124—Grain size analysis
SPT-835–37SP-SMNPNPNP12127—Grain size analysis

LL = Liquid Limit; PL = Plastic Limit; PI = Plasticity Index; MC = Natural Moisture Content; γ_t = Total Unit Weight; q_u = Unconfined Compressive Strength (UUC); NP = Non-Plastic

Soil Index Properties
Soil Index Properties
3.9.10 Reference Photographs
BOREHOLE DRILLING EXPLAINED
BOREHOLE DRILLING EXPLAINED
Tunnel Boring Machine
Tunnel Boring Machine
Groundwater flow systems in hummocky terrain
Groundwater flow systems in hummocky terrain
3.9.11 Investigation Planning Checklist

Checklist · Part V · Subsurface Exploration

Investigation Planning Checklist

Use this checklist to verify planning completeness before submitting the Investigation Plan memorandum to the railroad client for approval.

Desktop Review0 of 6
Boring Layout0 of 5
Laboratory Testing0 of 4
Health and Safety / ROW Access0 of 6
Client Communication0 of 3

Reference graphics

Levy (2010) recommends that owners prequalify contractors through a request for qualifications (RFQ) before bidding. His RFQ checklist asks for, among other things, years in business and any former company names, current backlog, three years of revenue, the largest recent projects, bonding capacity and insurance limits, projects not completed and why, any debarment, an attached quality control program, an attached safety program, and reportable accidents and OSHA violations for the past year. He recommends requesting the past five-year safety record and workers’ compensation experience modification rate (EMR), treating a rate below 1.0 as acceptable, and noting that a poor record takes about three years to work off. He also suggests calling past owners beyond the references listed, and asking them for other owners to contact.

For testing and inspection, Levy advises that certain inspections be contracted directly by the owner so the firm is impartial and works only for the owner. His list starts with inspecting soils before foundations are placed, inspecting compaction, and load testing piles. The testing RFQ should describe the project and schedule, list the services required, give an order-of-magnitude scope so firms can price it, and request hourly rates by staff level (regular and overtime) and unit prices for estimated test quantities.

At the preconstruction conference, the owner’s team should confirm the notice-to-proceed date, introduce the day-to-day staff, set communication channels and meeting protocol, verify insurance certificates for the contractor and each subcontractor, set procedures for questions and proposed change orders, and set the deadline for a baseline schedule and its update interval.

For railroad work: Add these points to the investigation planning checklist: confirm that the drilling subcontractor has railroad right-of-way experience, current contractor right-of-entry insurance, a safety program addressing roadway worker protection, and an acceptable EMR and OSHA history; confirm the testing laboratory’s accreditation and that acceptance testing during construction is contracted so that it reports to the railroad. Hold a short kickoff with the railroad’s representative to fix track access procedures, flagging requests, and the schedule for boring logs and lab data.

Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 21–24, 28–29, 113–116. Summarized and paraphrased. Full reference under Supplemental References.

Cretu et al. treat risk identification as a short, facilitated, multidiscipline session. One to two hours is usually enough on an ordinary project. It is best run with a risk breakdown structure (RBS) as a checklist so that no category is skipped. Their construction RBS has seven top-level branches: design, environmental, real estate, economic, schedule, contracting and construction. Each branch breaks down into items such as design coordination, resource agency reviews, utility issues, impacts to existing operations and force majeure. The facilitator records every idea where the whole group can see it and holds back editing until later. The facilitator draws out risks with Socratic questions. One of the authors’ own examples is “Did we run into geotechnical problems at this location when the original foundations were installed?” A SWOT framing (internal strengths and weaknesses, external opportunities and threats) is offered as an alternative prompt.

The results go into a risk register with these fields: ID, RBS category, threat or opportunity, short title, description, trigger, probability (initially high >75%, medium ≈50%, low <25%), impact description, owner, response strategy and status. Each description should be specific, measurable, attributable, relevant and time-bound (SMART). The register is then vetted. Duplicates are merged, and many small related items, such as several minor geotechnical uncertainties, may be grouped into one risk for management. Black-swan events are noted, but they are not modeled. The authors’ list of workshop questions includes several on ground conditions: what geotechnical work has been done, what is assumed for cut/fill reuse and haul, what is assumed for stability of cuts and temporary support, and whether perched water or dewatering permits are involved.

For railroad work: Hold this session during investigation planning, before the boring layout is fixed. Add railroad-specific branches to the RBS: track access and work windows, flagging and protection, slow-order or traffic interruption exposure, signal and communication cable conflicts, and right-of-way or permit-to-enter limits. Then trace every high or medium geotechnical risk to a specific exploration, test or monitoring item in the scope, or record it as a risk the client accepts. The register then becomes the written basis for the scope and fee, and it carries forward into the report and the construction documents.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 237–244, 249–250. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Ticks are saved in this browser.
Plain text version

Use this checklist to verify planning completeness before submitting the Investigation Plan memorandum to the railroad client for approval.

Desktop Review:

  • [ ] USGS 7.5-minute geologic map obtained and reviewed
  • [ ] USDA Web Soil Survey surficial map reviewed
  • [ ] FEMA FIRM reviewed; flood zone designations noted
  • [ ] All prior boring logs and geotechnical reports for the corridor obtained and reviewed
  • [ ] LiDAR or topographic data obtained; preliminary slope angles computed
  • [ ] Historical aerial photographs reviewed for evidence of prior land use, fills, or slope movement

Boring Layout:

  • [ ] Boring locations determined by project type (Table 3.9-1) and the owner railroad's engineering standard
  • [ ] All boring locations dimensioned by milepost and offset (ft right/left of CL)
  • [ ] GPS coordinates (NAD 83, State Plane in ft) assigned to each boring
  • [ ] Boring depths computed per Section 3.9.5 and the owner railroad's requirements; documented in the boring log
  • [ ] Rock coring specified at borings where rock is anticipated at depth

Laboratory Testing:

  • [ ] Testing assignment matrix completed (Table 3.9-2) — every boring has at least one test assigned
  • [ ] Consolidation testing specified for every identified soft cohesive layer
  • [ ] Shear strength testing specified for every slope stability critical layer
  • [ ] CBR or M_r testing specified for pavement subgrade investigations

Health and Safety / ROW Access:

  • [ ] Host railroad RWP training confirmed current for all field personnel (within 12–24 months per railroad)
  • [ ] RWIC/Flagman arranged through railroad's flagging coordinator
  • [ ] Track window schedule confirmed with Railroad Roadmaster and Division Engineer
  • [ ] Job Safety Briefing form prepared (to be executed at site before ROW entry)
  • [ ] Utility locates (811/One-Call) ordered with the notice the state law requires (commonly 2 to 3 business days)
  • [ ] Private utility locates ordered for railroad-owned infrastructure (signal cables, communication conduits, fuel lines) — do not rely on 811 for railroad-owned utilities
Top 5 Geo Site Red Flags
Top 5 Geo Site Red Flags

Client Communication:

  • [ ] Investigation Plan memorandum drafted, PE-reviewed, and issued to railroad project manager for approval
  • [ ] Railroad project manager confirmed approval in writing before field work begins
  • [ ] Daily summary protocol communicated to field team lead
Daily Site Inspection Checklist
Daily Site Inspection Checklist
3.9.12 Practical Recommendations
  1. Always obtain the railroad's current RWP certification requirements before scheduling field crews. Certification requirements change, and an expired RWP certificate discovered at the gate means a wasted mobilization and rescheduled track window. Call the railroad's RWP coordinator the week before mobilization to verify.
  2. Plan conservative boring depths and trim in the field if warranted. It is far less expensive to terminate a boring 10 ft early because you have already encountered competent material than it is to mobilize a second boring campaign because the first borings were too shallow.
  3. Treat the 2:1 stress method result as a minimum, not a target. Client engineering standards frequently require depths that exceed the stress influence calculation, particularly for Class I railroad mainline bridge and embankment projects. Check the applicable engineering standard before finalizing depths.
  4. Do not skip the planning memorandum on emergency response projects. Even on emergency task orders, document your boring plan — locations, depths, and rationale — in writing before drilling begins. This documentation protects both the firm and the client if the design is ever challenged.
  5. Coordinate boring locations with railroad signal engineering. Signal cables, transponders, and grade crossing detection circuits are buried within the railroad ROW and are not reliably located by 811 locates. Request the railroad's signal department to mark signal infrastructure locations before drilling within 30 ft of the track centerline.
  6. High-speed passenger corridor projects: Passenger corridor track windows are extremely constrained. Plan boring access for overnight possession windows (typically 11 PM to 5 AM); portable drill rigs that can be assembled and removed within 1 hour are required. Coordinate with the railroad's Capital Engineering a minimum of 6 weeks before field mobilization to secure track window scheduling.
Risk Management in Construction
Risk Management in Construction
Project management · Seeley (1993)

Structuring an Investigation Fee So It Reprices Fairly: Count, Depth and Sample Items

Seeley explains how the civil engineering method of measurement (CESMM3, Class B) breaks a ground investigation into separately priced items, and why. Every group of test pits or borings generates at least two items: the number of holes and the aggregate depth. Costs that follow the number of holes (moving and setting up the rig at each location) are therefore kept apart from costs that follow footage. Further items cover depth in rock versus other material, hole support or backfill, samples by type and class, removal of obstructions (paid by the hour), and pumping (paid by the hour at a stated minimum extraction rate). Hand-dug pits are itemized separately because they cost more. The rate covers preparing and submitting records and results, but not their analysis, which is paid separately.

His sample bill (converted to US units) shows the pattern: 34 trial pits 10–16 ft deep with a minimum base area of about 24 ft², 446 ft of pit depth, 446 ft of backfill, 15 hours of obstruction removal and 30 hours of pumping at a minimum 35 gpm; 14 rotary core holes (4-in. minimum core), 367 ft of cored depth in holes 16–33 ft deep, 367 ft of grout backfill and 28 core boxes 10 ft long; 102 disturbed bag samples of at least 11 lb; and 56 thin-wall tube samples 4 in. × 24 in.

For railroad work: build the cost estimate and the scope of services the same way, so that a change in the number of borings or their depth reprices on its own rather than becoming a negotiation. Typical line items are: mobilization to the subdivision (fixed); moves between holes, priced per hole and split between hi-rail or on-track access and off-track access on the right-of-way; drilling footage in soil and rock in depth bands; coring footage; SPT and thin-wall tube samples counted separately; grouted abandonment per foot; standby hours for flagging delays or train traffic; and per-day items for flagging protection and roadway worker protection briefings where the railroad bills them. Keep laboratory testing and engineering analysis out of the field unit rates, as Class B does, so that adding borings at a growing slide does not quietly use up the analysis budget. A table set up like this also gives the client a clear, auditable invoice against the work authorization.

Field Investigation of Soil
Field Investigation of Soil

Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 80–81. Summarized and paraphrased. Full reference under Supplemental References.

3.9.13 Practice Questions
Each question is worked in the same five parts as the examples. Questions 3.9-3 and 3.9-5 are planning questions, so their steps are a chain of reasoning rather than equations.
Question 3.9-1: Boring Count and Depth for a New Siding

Problem Statement

A Class I railroad located in the Mississippi Delta plans a 6,500-ft siding on flat alluvial ground, built on a 6-ft fill with a 60-ft base. The railroad’s standard (assumed here) calls for one boring per 1,500 ft and a 25-ft minimum depth. The geotechnical engineer must set the number and depth of borings for the proposal and show whether the owner’s minimum or the published embankment criteria govern.

Alluvium: silty clay and fine sandSiding L = 6,500 ft6-ft fill, 60-ft base; owner: 1 per 1,500 ft, 25 ft min.Number = ? Depth = ? Which governs?GivenL = 6,500 ft1 boring per 1,500 ft (owner)25 ft minimum depth (owner)H = 6 ft; B = 60 ftSilty clay and fine sand alluviumRequired(a) Number of borings(b) Depth from embankment criteria(c) Which governsBlack = given; red = required
Given and required for Question 3.9-1.

Given

VariableValueDescription
L6,500 ftSiding length
Spacing1 boring per 1,500 ft (owner minimum, assumed)
Owner depth25 ft minimum (assumed)
H, B6 ft; 60 ftFill height and base width
SoilSilty clay and fine sand alluvium

Required

  • (a) Number of borings
  • (b) Depth from the embankment criteria
  • (c) Which governs

Equations

  1. Eq. 1: N = L / s, rounded up, + 1

Steps

Step 1 · (a) Count
6,500 / 1,500 = 4.33 → 5 spaces
6 borings, one at each end
↓
Step 2 · (b) Embankment criteria
Das 0.5H to 2H = 3 to 12 ft; Li et al. 10 to 15 ft
12 to 15 ft
↓
Step 3 · (c) Compare
Owner 25 ft > 15 ft
Owner minimum governs: 25 ft, deeper through soft soil
↓
Step 4 · Spacing check
Li et al., about 200 ft on medium alluvium: 6,500/200 + 1
About 34 borings
↓
Solution
6 borings minimum, 25 ft deep.

Solution

(a) 6 borings. (b) 12 to 15 ft from the embankment criteria. (c) The owner’s 25-ft minimum governs.

The published spacing guidance would call for about 34 borings, so the owner’s 1,500-ft spacing is a floor, not a target. Where the first borings show variable alluvium, add borings rather than defend the minimum.

Question 3.9-2: Rock Coring for Drilled Shafts

Problem Statement

A railroad bridge over a creek is being replaced, and the new spans will sit on drilled shafts socketed into rock. The only record at the site is a 1967 boring that found weathered granite at 18 ft and auger refusal at 22 ft. The engineer must specify how deep the new borings go and what rock data the coring must deliver for socket design.

OverburdenWeathered granite (1967 log)010203040Depth (ft)Rock at 18 ftAuger refusal 22 ftDepth = ? Rock data?Creek bridge, drilled shaft socketsGivenWeathered granite at 18 ftRefusal at 22 ft (1967 log)Drilled shafts socketed in rock≥ 20 ft of core below rock surfaceRequiredMinimum boring depthRock data the coring must provideBlack = given; red = required
Given and required for Question 3.9-2.

Given

VariableValueDescription
RockWeathered granite at 18 ft; refusal at 22 ft1967 boring log
FoundationDrilled shafts
RuleAt least 20 ft of core below the rock surfaceCommon practice for shaft sockets

Required

  • Minimum boring depth
  • Rock data the coring must provide

Equations

  1. Eq. 1: D = rock surface + 20 ft of core

Steps

Step 1 · Depth (Eq. 1)
22 + 20
At least 42 ft, with 20 ft of NX or NQ core
↓
Step 2 · Data (USACE EM 1110-1-1804)
RQD (ASTM D6032), core recovery, qu (laboratory or point load), weathering, fracture frequency, infilling and orientation
↓
Step 3 · Data for socket design (AREMA Chapter 8)
qu and joint condition, frequency and weathering grade
↓
Solution
At least 42 ft, with 20 ft of core and full rock logging.

Solution

At least 42 ft, including 20 ft of NX or NQ core below the rock surface, logged for RQD, recovery, strength, weathering and jointing.

A common criterion before calling a horizon competent bearing is at least 10 ft of core with RQD of 50% or more and recovery of 80% or more. Refusal at 22 ft may be a boulder or a weathered zone, which is why coring, not refusal, defines the top of rock.

Question 3.9-3: Expired Roadway Worker Certificates in an Emergency

Problem Statement

At 10:00 PM the railroad calls: a cut slope has failed onto a main track and it needs a geotechnical crew on site by 6:00 AM. Of the four available staff, two hold current roadway worker protection certificates and two let theirs lapse four months ago. The project manager must decide who can go onto the right-of-way and how to staff the response.

Main track blocked10:00 PM call → on site 6:00 AM2 current RWP, 2 expired 4 monthsEscort allowed? Course of action?GivenCrew of 4: 2 current RWP2 expired 4 months agoOn site 6:00 AM (now 10:00 PM)Rule: everyone on right-of-way must hold current certificateRequiredCan expired staff enter under escort?Correct course of actionBlack = given; red = required
Given and required for Question 3.9-3.

Given

VariableValueDescription
Crew4; 2 with current RWP, 2 expired 4 months ago
DeadlineOn site by 6:00 AM; now 10:00 PM
RuleEach person who enters the right-of-way must hold a current certificateRailroad RWP program

Required

  • Whether the expired personnel can enter under escort
  • The correct course of action

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Can escort substitute for certification?
No. Escort covers visitors, not technical staff doing work on the right-of-way.
↓
Step 2 · Who mobilizes?
The two certified staff, immediately, as a two-person crew.
↓
Step 3 · What else?
Ask the railroad’s RWP coordinator whether an emergency process exists; enroll the other two in the next class; document the limitation in the project file.
↓
Solution
No: send the two certified staff, and fix the lapse.

Solution

No. Only the two staff with current certificates may enter the right-of-way. They mobilize now; the other two stay off the right-of-way.

Contact the railroad’s RWP training coordinator about any emergency provision, enroll the two in the next class, and record in the project file how the crew was deployed. A certificate should never be allowed to lapse during an active contract; track expiry dates with the project schedule.

Question 3.9-4: Borings Beyond the Toe for an Embankment Widening

Problem Statement

A Class I railroad is adding a second main track by widening a 20-ft embankment 12 ft on each side and raising it 4 ft. Existing borings are on the centerline only and reach 45 ft. Before the scope is priced, the engineer must decide whether borings are needed outside the existing toe and, if so, where they should go.

CL boring 45 ftold toenew toeslip surfaces 0.5H–1.0H beyond toeBorings beyond toe? Where?GivenH = 20 ft; raise 4 ftWiden 12 ft each sideToe ~60 ft → ~72 ft from CLCenterline borings to 45 ftSlip surfaces 0.5H–1.0H past toeRequiredAre borings beyond the toe needed?Where to put themBlack = given; red = required
Given and required for Question 3.9-4.

Given

VariableValueDescription
H20 ft existing; 4-ft raiseEmbankment
Widening12 ft each side
Existing toeAbout 60 ft from centerlineNew toe about 72 ft out
BoringsCenterline to 45 ftExisting data
RuleCritical slip surfaces extend about 0.5H to 1.0H beyond the toeSection 6.3

Required

  • Whether borings beyond the toe are needed, and where

Equations

  1. Eq. 1: x = new toe + (0.5 to 1.0) H — reach of the critical slip surface
  2. Eq. 2: q = γ H — load at the new toe area

Steps

Step 1 · Where is the new load?
Under the widening, outside the old toe, on ground that has never been loaded or sampled.
↓
Step 2 · Reach of the slip surface (Eq. 1)
72 + (10 to 20)
About 80 to 90 ft from centerline
↓
Step 3 · Data needed there
Strength of the natural foundation soil, which the centerline borings do not sample.
↓
Solution
Yes: borings about 20 to 30 ft beyond the new toe.

Solution

Yes. Place borings about 20 to 30 ft beyond the new toe, roughly 80 to 100 ft from centerline.

The centerline borings describe soil that has carried the embankment for decades and has consolidated under it; the soil under the widening has not. The stability of the widened slope depends on that unloaded soil, so without borings there the factor of safety is undocumented (AREMA Chapter 1, Part 1).

Question 3.9-5: Investigating Beside a High-Speed Passenger Corridor

Problem Statement

A signal bridge on a passenger corridor operated at FRA Class 7 (125 mph) is to be replaced. The engineer has scoped many freight bridge investigations on Class 4 track but none on a high-speed line. Before writing the work plan, the engineer must identify what makes this investigation different and list the planning requirements that follow.

Signal bridge (replace)FRA Class 7, 125 mphFive planning requirements that differ = ?Compared with: Class 4 freight bridgeGivenFRA Class 7, 125 mph49 CFR 213, Subpart GSignal bridge replacementComparison: Class 4 freight bridgeRequiredFive planning requirements that distinguish this investigationBlack = given; red = required
Given and required for Question 3.9-5.

Given

VariableValueDescription
TrackFRA Class 7, 125 mph49 CFR 213, Subpart G
WorkSignal bridge replacement
ComparisonClass 4 freight bridge

Required

  • Five planning requirements that distinguish the investigation

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Track time
Short overnight possessions; equipment that sets up and clears quickly; possession requests weeks ahead.
↓
Step 2 · Geometry tolerances
Class 7 limits (49 CFR 213.331) are tighter than Class 4 (213.63): 1 in. against 1¼ in. cross level, 1 in. against 2 in. profile on a 62-ft chord. Settlement must be predicted to that standard.
↓
Step 3 · Review
Formal owner review of 60% and 100% submissions; more documentation.
↓
Step 4 · Signals and power
Clearance from signal circuits for each boring near the track, and electrical clearance from the overhead catenary for the drill mast.
↓
Solution
Track time, tighter tolerances, owner review, signal clearance, catenary clearance.

Solution

The five are: short track possessions, Class 7 geometry tolerances, formal owner peer review, signal circuit clearance, and catenary electrical clearance.

The tolerances drive the technical scope: settlement predictions compared with a 1-in. limit usually need consolidation tests on every soft layer, not only the worst one. The other four drive cost and schedule and belong in the investigation plan memorandum before a price is given.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • RK-10 UCS from point load index σ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).
Cross-References
Related TopicChapter
SPT corrections, sampling methods, boring log formatChapter 4.1
CPT, VST, PMT, and geophysical methods for site characterizationChapter 5.1
Soil and rock classification — USCS, AASHTO, AREMA MRE Ch. 1 categoriesChapter 2.2
Groundwater characterization, piezometers, permeability testingChapter 2.8
Bearing capacity calculations — Cooper E-80 loading, AREMA MRE Ch. 8Chapter 6.1
Settlement analysis — consolidation, time rate, FRA and client geometry tolerancesChapter 6.2
Slope stability — AREMA MRE Ch. 1 embankment design; USACE EM 1110-2-1902Chapter 6.3
Ground improvement — PVD spacing, preloading, schedule implicationsChapter 7.2
Report preparation — investigation plan format per client requirementsChapter 8.4
Lab testing program — test standards, minimum quantities, acceptance criteriaChapter 5.2
I.8 Emergency Response — Client-Specific Protocols (continued)

Table 1.0-3: Emergency Response Contact Structure by Railroad Client (completed)

Landslides After Rain
Landslides After Rain

These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.

We establish and document these contact chains at the beginning of every PSA engagement — not when the emergency occurs. The geotechnical firm's project manager and the on-call geotechnical engineer must have direct mobile phone numbers for every contact in the chain. We verify these contacts annually and update them when railroad personnel change roles.

I.8.1 Emergency Response Timeline — Standard for All Railroad Clients

The following timeline applies to all railroad emergency geotechnical response, regardless of client. Individual client protocols may require faster response on specific corridors or for specific event types.

Hour 0 — Notification Received:

  • Geotechnical firm's on-call engineer accepts the call and confirms they will mobilize
  • Contacts the firm's emergency response coordinator to arrange field technician and equipment
  • Confirms RWP certification currency for all personnel being mobilized
  • Contacts railroad flagging coordinator to arrange RWIC for site entry

Hour 0–4 — Mobilization and Site Arrival:

  • Licensed geotechnical engineer and field technician on site
  • All personnel hold current RWP certification for the host railroad
  • Job Safety Briefing completed before entering the ROW
  • Field assessment of failure mechanism, extent, and movement status begins immediately

Hour 1–4 — First Professional Recommendation:

  • Verbal recommendation delivered to railroad operating officer while on site or immediately upon departure
  • Recommendation covers: track restriction (closure, slow order with mph basis, or flag-and-proceed), specific technical basis, and re-inspection interval
  • Confirmation of recommendation in writing by email within 2 hours of leaving the site

Day 1–5 — Emergency Investigation:

  • Drill rig mobilized under emergency track window scheduling within 24–48 hours
  • Three to five targeted borings at 15–25 ft depth
  • Expedited laboratory testing: 48-hour turnaround on moisture content, Atterberg limits, unconfined compression, and USCS classification
  • Written emergency recommendations issued in letter report format within 48–72 hours of completing field work

Month 1–6 — Permanent Repair:

  • Formal signed-and-sealed geotechnical report and construction documents produced following standard design-phase process
  • Geotechnical Special Provisions included in permanent repair bid package
I.8.2 Emergency Repair Guidance by Failure Type

We use the following framework when formulating emergency repair recommendations. Recommendations must be tailored to the specific conditions observed; this table provides starting points, not substitutes for engineering judgment.

Failure TypeAREMA MRE ReferenceTypical Emergency Repair Approach
Shallow slope failure (H < 10 ft)MRE Ch. 1, Section 1.4.3 (Maintenance of Earth Slopes)Slope regrading to stable angle; rock buttress at toe; surface drainage improvement; erosion control blanket
Deep slope failure (H > 10 ft)MRE Ch. 1, Section 1.4.3; MRE Ch. 8, Part 5 (Retaining Walls)Staged material removal; soldier pile wall; concrete block or gabion buttress; soil nail wall with geogrid facing
Embankment settlement or sinkholeMRE Ch. 1, Section 1.4.1 (Maintenance of Roadbed)Compaction grouting; flowable fill void filling; temporary timber cribbing or bridging between ties
Bridge scour — abutment or pierMRE Ch. 1, Part 3 (Natural Waterways); FHWA HEC-23Emergency riprap placement; geotextile bag placement; temporary sheet pile or H-pile; flow diversion
Subgrade failure or mud boilMRE Ch. 1, Section 1.4.1 (Maintenance of Roadbed)Undercutting and replacement with granular fill; ballast injection; geotextile/geogrid installation under ballast
Retaining wall distressMRE Ch. 8, Part 5 (Retaining Walls, Abutments and Piers)Temporary rock buttress at wall base; sheet pile wall parallel to track; soil anchor installation
Debris Flow Landslide
Debris Flow Landslide
Project management · Hutchings (2004)

Sustained Overtime, Productivity Loss and Acceleration During Extended Emergency Work

Hutchings summarizes research on scheduled overtime. In the first few weeks, total output per worker rises, though not in proportion to the added hours. After about 7 to 9 consecutive 50- or 60-hour weeks, weekly output falls to roughly what the same crew produces in a 40-hour week. After about eight more weeks, the losses cancel the early gains, so the whole overtime period produces no more work, and possibly less, than a normal schedule would have. Combined with premium pay, the productive value per wage dollar after several weeks drops below about 75% for five 10-hour days, below about 62% for six 10-hour days and below about 40% for seven 12-hour days. Productivity per hour recovers sharply when the crew returns to a 40-hour week. In his example claim on a public works job, lost labor productivity (about $2.4 million) was the largest single component of a total claim of about $7.4 million.

He distinguishes directed acceleration, where the owner orders the work sped up, from constructive acceleration. The latter requires an excusable delay, a request for an extension, refusal of the request, an order to finish on the original date anyway, and actual acceleration by the contractor. When a contractor is simply behind, he advises against an acceleration order. Instead, give written notice that the contract date will be enforced and ask for a revised schedule showing how the contractor will meet it. Means and methods, and responsibility for them, then stay with the contractor.

For railroad work: round-the-clock effort is appropriate in the first days of a slide or washout response, when restoring service drives every decision. Once the response becomes a permanent repair lasting weeks, plan for a sustainable pace: rotating crews, a defined second shift, or more equipment, rather than the same people working seven 12-hour days. Fatigue affects geotechnical observers as much as operators. Missed seepage, tension cracks or compaction problems late in a long shift carry a real cost. When the railroad sets a restoration date that cannot be met at normal production, record the instruction, any request for more time and the response, because those records determine later whether the extra cost was acceleration or part of the original scope.

Source: Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc., pp. 273–277. Summarized and paraphrased. Full reference under Supplemental References.

I.9 Communicating with Railroad Clients — Standards and Professional Obligations

Technical quality is necessary but not sufficient for a successful railroad geotechnical practice. How we communicate — the speed, format, and clarity of our client communications — determines whether the railroad can actually use our work in their decision process. Different railroad clients have different communication cultures; we adapt to each.

I.9.1 Real-Time Field Communication Standards

When we encounter a significant finding in the field — an unexpected organic layer at a structure location, rock at a depth that contradicts a prior boring, artesian groundwater conditions, or a condition that materially changes the geotechnical risk picture — we communicate it to the railroad project manager the same day, not in the formal report.

Routing findings to the owner railroad: Railroads differ in how field findings should reach them. Some expect a short, direct email to the Division Engineer or Roadmaster (three to five sentences: what was found, at what depth and location, what it means for the project, and what we recommend next). Others route findings through a designated project engineer or project manager, who passes them to track, structures or environmental reviewers, and prefer a formal preliminary memorandum for significant findings. Large networks often assign findings to a regional or division engineer for the territory rather than a central contact. Passenger railroads also need findings that affect train operations sent to operations management. On short lines, the subsidiary's general manager often needs to be copied, because track restrictions, crew deployments and customer notices are decided there. Confirm the communication chain at project initiation and record it in the project plan.

I.9.2 Daily Field Summary Standard

At the end of each day of field investigation work, we send a brief daily summary to the railroad project manager. This is non-negotiable professional practice on all railroad geotechnical programs, regardless of whether the client has specifically requested it. The daily summary is a single paragraph or a short bulleted list containing:

  • Borings completed today: boring numbers, depths, and locations (milepost reference)
  • Samples obtained: number of SPT samples and Shelby tubes recovered
  • Significant observations: any condition that departs from prior expectations — unexpected soft layers, groundwater higher than assumed, refusal on possible rock at shallow depth, organic odor, or artesian conditions
  • Track windows used: duration, any anomalies during window operations
  • Tomorrow's planned work and any access or scheduling issues anticipated

The daily summary is not a formal document and does not carry a PE seal. It is a professional service communication that keeps the client informed and demonstrates that our investigation is progressing as planned.

I.9.3 Budget Status Communication

We notify the railroad project manager by email when we reach 75% of the not-to-exceed (NTE) budget on any task order. The notification states: the current budget, the amount expended to date, the work remaining, our current estimate of total cost at completion, and our recommendation for how to proceed — either confirm that remaining work will be completed within the current NTE, or request authorization to increase the NTE.

We do not wait for the client to ask about budget status. We do not complete work beyond the NTE without prior written authorization. These are fundamental PSA disciplines that the railroad client's accounts payable and capital program management departments enforce regardless of how important the additional work is technically.

Project management · CIOB (2014)

A Formal Change-Control Procedure and Change Register

The CIOB Code defines change broadly: anything that affects the scope or brief, cost (including whole-life cost), time milestones, risk allocation, the working of the team, or any project process. It sets out a single route for every change:

  1. A change request is made, and the requirement is clarified and documented.
  2. The project team reports the technical, health-and-safety, schedule and cost consequences, each assessed by the appropriate specialist.
  3. The project manager reports to the client. If the consequences are not accepted, the change is reviewed and modified, and the loop repeats.
  4. Formal authorization is obtained, the change order is issued by the contract administrator, and the change is entered in the master schedule and cost plan.
Change-control flowchart running from change request through consequence report, client acceptance or review loop, formal authorization, issue of the change order, and update of the master schedule and cost plan.
Figure 5-PM6. Change-control flowchart running from change request through consequence report, client acceptance or review loop, formal authorization, issue of the change order, and update of the master schedule and cost plan. Source: CIOB (2014), Figure 4.4.

Supporting tools:

  • Change order register. Records what the change is, who raised it, why, whether it is discretionary or not, its cost and time implications, the date by which a client decision is needed, and the decision.
  • Design development control sheet. Records the issue, the options considered, the recommendation, the affected cost-plan item, and any transfer of client contingency.
  • Delegated financial limits. Instructions below an agreed value can be given without going back to the client each time. Above that limit, the client must be consulted.
  • One source of instructions. All instructions go to the contractor in writing from a single source, and nothing is valued without one. The register is cross-referenced to RFIs and claims and reported to the client at regular intervals.

The Code stresses that controlling change during design is far more effective than during construction, and that time is often more expensive than the material change itself.

For railroad work: On consulting assignments for a railroad, agree at the kick-off:

  • Who on the railroad side can authorize added borings, added lab testing or an extended limit of investigation, and up to what value.
  • How fast a decision is needed so the drill crew and flagger are not left standing.

Keep a simple change register on the project. Log each scope change (a new boring offset because of a signal cable, a CPT replaced by a boring because of refusal, an added cross-section after a new tension crack) with its cost and schedule effect. Send the register with each progress report. The railroad then sees the cumulative effect before the invoice does.

Source: Chartered Institute of Building (2014). Code of Practice for Project Management for Construction and Development, 5th ed. Chichester, UK: John Wiley & Sons, pp. 184–186, 236–238. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

I.10 Data Management for the Railroad Client
I.10.1 Deliverable File Format Requirements by Client

These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.

All boring logs must be delivered in both signed-and-sealed PDF and the native project file format (gINT project file, Log*Plot project file). Electronic data files allow the railroad's engineering team and future consultants to access and extend the boring database without re-entering data — a significant long-term value that distinguishes a professional deliverable from a mere PDF.

I.10.2 Sample and Core Retention — Client Requirements

Physical sample and core retention requirements vary by client. The following represents minimum standards; client-specific requirements in the task order govern when they differ from these minimums:

These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.

Storage of Samples
Storage of Samples

Core photography requirement: All rock core must be photographed in boxes before disposal, regardless of retention period. Core photographs, stored as high-resolution JPEG files with metadata tags identifying project, boring number, box number, and depth range, must be delivered to the railroad client at project closeout and retained in our project archive indefinitely.

I.11 Quality Assurance — Peer Review Requirements by Deliverable and Client

Every signed-and-sealed geotechnical deliverable for any railroad client is subject to independent peer review before issuance. The standard for "independent" is clear: the reviewer had no involvement in the investigation, analysis, or previous drafts of the document being reviewed.

Table 1.0-4: Peer Review Requirements by Deliverable Type
DeliverableMinimum Reviewer QualificationReview Level RequiredPre-issuance Client Review
Desktop Review MemorandumSenior PE, same firm acceptableInternal QC checkNot required
Assessment ReportSenior PE, same firm acceptableInternal QC checkNot required
Reconnaissance ReportSenior PE, same firm acceptableInternal QC checkNot required
Preliminary Geotechnical ReportIndependent PE, 10 yr railroad GT experienceFull independent reviewRecommended
30% Geotechnical Design MemoIndependent PE, 10 yr railroad GT experienceFull independent review; signed seal requiredRequired — railroad engineering Dept.
60% Geotechnical Design ReportIndependent PE, 10 yr railroad GT experienceFull independent review; signed seal requiredRequired — railroad engineering Dept.
100% Final Geotechnical ReportIndependent PE, 10 yr railroad GT experienceFull independent review; signed seal requiredRequired — railroad engineering approval
Emergency Phase 2 Letter ReportSenior PE, same firm acceptableReview within 24 hours of issueNotify only; no formal approval
Permanent Emergency Repair ReportIndependent PE, 10 yr railroad GT experienceFull independent reviewRequired — railroad engineering Dept.

Client-specific peer review considerations:

  • A Class I railroad: The railroad's engineering department department conducts its own independent technical review of all 60% and 100% submissions. Our independent peer review must be completed and all comments resolved before we issue to a Class I railroad; do not submit a document to Class I railroad review with known open peer review comments.
  • High-speed passenger corridor: The railroad's engineering department conducts a formal technical review of all 60% and 100% submissions under the railroad's Quality Management Program. The passenger railroad applies its own criteria in that review, so the peer reviewer must know them.
  • Class I railroad operations located in Canada: TC RSA-regulated projects in Canada may require TC review of geotechnical findings that affect safety-critical infrastructure. The railroad's engineering department coordinates TC filings; our role is to provide technically complete documentation that supports the railroad's regulatory submission.
  • A Class I railroad: Post-merger the railroad is developing harmonized review processes. Confirm the current 60% and 100% review process with the railroad's engineering group at the beginning of each project.
  • A Class I railroad: Some railroads have internal review requirements for capital projects above set thresholds; confirm the current process with the owner railroad when the work is scoped. We confirm the railroad's current internal review process with the railroad's regional engineer at project initiation.
Project management · ASCE (2012)

When and How to Commission a Project Peer Review

ASCE (2012) defines peer review as an independent assessment by experienced professionals who have not worked on the project or organization being reviewed. It distinguishes organizational reviews (how faithfully a firm or agency follows its own policies; usually confidential and often oral) from project reviews, which examine the technical results of a project at its current stage and are reported in writing. Peer reviewers are advisory; they identify gaps and do not direct changes, and the original engineer keeps full legal responsibility. A peer review is also not value engineering: VE asks whether the right overall solution has been chosen, while design peer review asks whether the chosen solution is engineered correctly.

Engineering Ethics — Integrity, Responsibility, Public Trust
Engineering Ethics — Integrity, Responsibility, Public Trust

The Manual lists circumstances that suggest a project review: a project larger or more complex than the team usually handles; new technology; difficulties on similar past projects; changed objectives or disputes; many offices or organizations; a fast-track schedule; limited budgets; staffing concerns or recent departure of key people; large potential liability or unusual public risk; uncertain status of work to date; and special environmental concerns. Typical scope items are design assumptions and criteria, applicable codes, spot-checks of calculations, clarity and completeness of reports, alternatives considered, judgment, constructability, proposed construction means and methods, and prospects of meeting objectives.

The process has six steps: request, scoping, reviewer selection, preliminary document review, on-site document review and confidential interviews, and reporting, followed by follow-up actions with measurable goals. Reviews held at earlier milestones usually yield more benefit than a review only at final design. A project review report typically covers scope and limits, schedule and status, phase reviewed, needed corrective actions, and issues for further evaluation. The EJCDC publishes a standard agreement for independent project peer review.

For railroad work: Several of the Manual’s triggers are common on railroad ground-hazard projects: emergency slide repairs designed on a compressed schedule, novel stabilization methods, high consequence of failure under traffic, and work spread across several offices. For such deliverables, set the peer review scope at the concept stage (failure mechanism, design parameters, analysis method) rather than only at final plans, and keep reviewer comments and their disposition in the project file.

Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 213–222. Summarized and paraphrased. Full reference under Supplemental References.

I.12 Scope of Services Matrix by Project Phase and Client Type
Table 1.0-5: Minimum Geotechnical Services by Phase and Railroad Client Category
PhaseClass I FreightPassengerShort-line Short Line / Regional
Desktop ReviewRequired — all projectsRequired — all projectsRequired — recommended even for small projects
AssessmentRequired if no prior dataRequired — all projectsRequired — client often has minimal prior data
ReconnaissanceRequired for new alignments and facilitiesRequired — all projectsMay combine with design investigation
Study / Prelim. Eng.Required for new facilities; alternatives analysisRequired — all projectsGrant-funded projects require study level
30% DesignRequiredRequired — owner railroad's process governsRequired
60% DesignRequiredRequired — owner railroad's process governsRequired
100% DesignRequiredRequired — owner railroad's process governsRequired
Construction ServicesRequired on significant capital; recommended on allRequired — continuous inspection on passenger corridorRequired on embankment and structure work
Project management · Skill Right (2013)

Statement of Work: Deliverables as Nouns, SMART Success Indicators and If–Then Risk Plans

The course presents the statement of work (SOW) as the document that defines scope, sets the customer’s expectations and can serve as the contract. A good SOW answers: what the purpose is and why the project is being done; who the immediate customer and the end user are; what the deliverables are and what support they need; and what the budget, final date, success measures, customer support and contingency plans are. Its generic contents are:

  • Background – history and justification. Every claim made here must be backed up later by a success indicator.
  • Deliverables – written as nouns, with quantities stated, because vague deliverables create wrong expectations.
  • Measurable success indicators – written to the SMART test: Specific, Measurable, Agreed upon, Realistic, and Time- and cost-framed. Overall schedule and budget are the two most important, and key milestone dates should be listed.
  • Customer support – what the customer must provide (drawings, subject-matter experts, equipment).
  • Risk plans – written as “If ___, then ___” statements covering what is most likely to go wrong and what would have the most impact.

For railroad work: a culvert replacement investigation SOW might be built as follows (values illustrative):

  • Background – the pipe’s condition and any slow order, sinkhole or overtopping history that justifies the work.
  • Deliverables – “six borings, two at each headwall and two through the embankment crest; boring logs; a laboratory summary; a geotechnical report with foundation and installation-method recommendations.”
  • Success indicators – “draft report within 30 calendar days of the last boring; within the authorized fee; no unplanned track occupancy.”
  • Customer support – right-of-entry, track time and roadway worker protection, utility and signal-cable locates, and existing drawings and inspection reports.
  • Risk plans – “If track time is cancelled, then perform the toe borings and off-track soundings first.” “If refusal occurs above the planned invert depth, then core at least to the depth needed for the foundation recommendation.”

Writing the client’s obligations into the SOW makes them visible when the schedule slips for reasons outside the consultant’s control.

Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 26–35. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Oberlender (2000)

Work Breakdown Structure, Work Packages and the Kick-Off Meeting

Oberlender calls the work breakdown structure (WBS) the cornerstone of the work plan: to manage the whole project, you manage each of its parts. The WBS divides a project into levels (major facilities, sub-facilities, work items, tasks), and the lowest level is the work package, defined well enough to be measured, budgeted, scheduled and controlled. Code numbers link each package to the organizational breakdown structure (who does it), the cost breakdown structure (which account pays for it) and the CPM schedule (when it happens).

Five-level work breakdown structure descending from the project to major facilities, sub-facilities, work items, tasks and finally work packages.
Figure 5-PM7. Five-level work breakdown structure descending from the project to major facilities, sub-facilities, work items, tasks and finally work packages. Source: Oberlender (2000), Figure 6-6.

His procedure for building the plan:

  1. Initial review. The project manager reads the owner’s study and the contract and asks scope, budget and schedule questions. What is missing? How and when was the budget prepared? How firm is the completion date?
  2. Preliminary WBS. The project manager drafts the major tasks before forming the team, because the team cannot be selected until the work is known.
  3. Kick-off meeting. This is an orientation, not a design meeting. Review goals, scope, the approved budget and milestones. Then assign each member to return work packages (who, what, when, how much) within two weeks.
  4. Work packages. Each package has three parts. Scope states what is included and what is explicitly done by others. Budget gives work-hours, computer time, travel and reproduction against a cost code. Schedule lists tasks, the responsible person and dates.
  5. Reconcile. If the packages total more than the budget or run past the required date, resolve it inside the team. If that fails, take it to the owner while there are still choices.
Team member’s work package form with scope (including work by others), budget by cost code, and schedule by responsible person.
Figure 5-PM8. Team member’s work package form with scope (including work by others), budget by cost code, and schedule by responsible person. Source: Oberlender (2000), Figure 6-7.

The “not included / performed by others” lines on the work package are what prevent the same work from being done twice, or not at all.

For railroad work: A typical geotechnical scope breaks down cleanly. Level I covers desktop review, field exploration, laboratory testing, analysis, and reporting/GSPs. Level II splits field exploration into utility locates and railroad permits, flagging requests, drilling, in situ testing, and piezometer installation. Write a work package for each discipline lead and subconsultant (driller, lab, surveyor). Spell out in each package who requests and pays for flagging, who obtains right-of-entry, and who supplies track charts and as-built drawings. Hold the kick-off before the first track-time request, so that the two-week package return lines up with the railroad’s advance notice for work windows.

Source: Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill, pp. 99–115. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Kelly et al. (2004)

Value Opportunity Points and the Lever of Value

From an international benchmarking study, Kelly, Male and Graham identify standard value opportunity points where a value study can be inserted in the project life cycle. These are a strategic briefing study (why invest, why now, for what purpose), a project briefing study (translating the business need into performance requirements), a concept design workshop, a detail design workshop and an operations workshop; a single charrette can take the place of some of the early studies. Each study has three phases. The orientation and diagnostic phase covers interviews, document review and a site tour. The workshop phase is typically half a day to a day within a four- to seven-day effort for a strategic study. The implementation phase, which the benchmarking found to be the most common point of failure, requires a named action plan. Their lever of value makes the timing point: effort spent at the strategy and objectives stages moves value far more than the same effort at the design or operations stage, and by final design the project’s value system is effectively locked. Two simple workshop tools support this. A time–cost–quality triangle has the team place one dot showing which of the three governs. A risk ranking from A to F combines high or low probability with consequence levels of “blocking force,” “turbulence” and “noise”; A–C risks go forward to analysis automatically.

Lever of value showing that interventions at the project strategy and objectives stages yield far more value than the same effort at the functionality or operation stages.
Figure 5-PM9. Lever of value showing that interventions at the project strategy and objectives stages yield far more value than the same effort at the functionality or operation stages. Source: Kelly et al. (2004), Fig. 7.3.

For railroad work: Map these points onto the scope-of-services matrix. A short value and risk session at the concept or alternatives stage, before the boring program and the remedy type are fixed, is where the geotechnical engineer has the most leverage. It is the point to question whether the slide needs a wall or a drainage-and-buttress fix, or whether a culvert should be lined or replaced. Use the time–cost–quality dot to record whether track time or capital cost governs. On emergency slide work it is almost always time. On planned subgrade programs, cost and long-term performance often govern. Record the answer in the scope so that later choices about investigation depth and remedy are judged against the same priorities.

Source: Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science, pp. 102–109, 173, 299–302, 307. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Rad (2002)

Estimate Accuracy by Phase, Contingency and Range Estimating

Rad treats an estimate as a forecast whose accuracy depends on how much is known about the project. Late in a project, with full information, estimates are seldom better than about ±3–4%. At inception, with little project-specific data, an order-of-magnitude estimate may end anywhere from about 30% to 330% of final cost. He cites professional-society guidance that the first formal published estimate should be within −40%/+100%. On that basis, a $100 estimate implies a final cost between $60 and $200.

The cheapest point to change a project comes early, while uncertainty is still high. Estimates refine progressively down the WBS: level 0 first, then level 1, and so on. Each refinement is an enhancement of the original estimate, not a new one, which makes variances easier to explain.

Bar chart of how knowledge of project details grows across the conceive, plan, implement and deliver phases; Figure 3.8-28 on the same page shows uncertainty and risk falling over the same phases.
Figure 5-PM10. Bar chart of how knowledge of project details grows across the conceive, plan, implement and deliver phases; Figure 3.8-28 on the same page shows uncertainty and risk falling over the same phases. Source: Rad (2002), Figure 4-1.

He separates three kinds of money that are often combined:

  • Allowance: a lump sum for a cost that is known to occur but is not worth detailing. Use it sparingly and only for small items.
  • Contingency: money for estimating inaccuracy caused by uncertain project details. Traditionally 10–50%, depending on how much information exists. It is not meant to cover design errors, omissions or scope changes.
  • Client reserve: held outside the contract budget for changes in the owner’s objectives or environment. Also 10–50%, depending on how much innovation is involved.

For early estimates he recommends range estimating. Each element gets optimistic, most-likely and pessimistic values, combined as (O + 4M + P)/6. In his example, values of 5, 8 and 35 give 12, not 8. This shows how a single-point “most likely” figure sits close to the optimistic end when the downside is long. When single-point estimates are rolled up they tend to understate cost, because estimators are optimistic.

For railroad work: The scope-of-services matrix should label each phase’s construction cost opinion with its expected accuracy, so that a desktop-stage figure for a slide repair is not taken as a budget. Carry contingency for geotechnical uncertainty, such as undercut depth, rock, groundwater and slide limits, separately from any railroad-held reserve for scope growth, for example added track miles or a changed alignment. Where data are sparse, give three-point ranges for the dominant quantities. As borings and lab results come in, reduce the contingency and record why it was reduced.

Source: Rad, P. F. (2002). Project Estimating and Cost Management. Vienna, VA: Management Concepts, pp. 43–49, 62–64, 111–112. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

I.13 Practice Questions

Q1. You are providing geotechnical services to the railroad's project manager for a new intermodal yard expansion in the Texas Gulf Coast region. Your investigation reveals a 12-ft-thick soft marine clay deposit at 15 to 27 ft depth. Your consolidation test results show C_c = 0.72 and c_v = 4.8 ft²/year. The railroad's project manager tells you that the crane rail foundations must be ready for concrete placement in 16 months. Which owner railroad provisions govern your response, and what is your professional obligation to the project manager before the formal report is issued?

A: The governing documents are the owner railroad's structures standards for crane rail foundation design, supplemented by AREMA MRE Chapter 8 for foundation bearing capacity and settlement criteria. The governing performance criterion for crane rail differential settlement is contained in the railroad's intermodal facility design guidance, which specifies maximum differential rail settlement of ¼ in. per 50 ft — a tolerance far tighter than standard embankment subgrade requirements.

Our professional obligation to the railroad's project manager before the formal report is issued: Communicate the settlement timeline problem immediately — within 48 hours of receiving the consolidation test results. The calculation is straightforward: 90% primary consolidation of a 12-ft layer (single drainage assumed) with c_v = 4.8 ft²/year occurs at t₉₀ = 0.848 × H_dr² / c_v = 0.848 × 144 / 4.8 = 25.4 years without treatment. Even with PVD drains at 4-ft triangular spacing, achieving 90% consolidation in 16 months requires that surcharge loading must begin within weeks, not months, of our report issuance. We issue a preliminary technical memorandum — not a formal report — within 48 hours of receiving the consolidation data, clearly stating the schedule implication and recommending an immediate scope addition for a ground improvement feasibility study. We copy the railroad's Division Engineer and the railroad's Capital Engineering project manager.

Q2. A short-line subsidiary railroad in Louisiana is pursuing FRA CRISI grant funding for a 12,000-ft new siding on their network. The short-line corporate engineering group asks your firm to develop the geotechnical investigation scope. The subsidiary's General Manager suggests that the railroad's prior inspection of the alignment is sufficient and no borings are needed. Explain your response, referencing applicable standards.

A: We respectfully decline to endorse a scope that eliminates borings for a 12,000-ft new siding on an FRA CRISI grant-funded project. Our response to the General Manager, coordinated through the short-line corporate engineering group, covers three points:

First, regulatory requirement: FRA CRISI grant funding requires that design be supported by site-specific subsurface investigation meeting applicable professional engineering standards. AREMA MRE Chapter 1, Part 2 (Section 3.10) bases subballast design on the subgrade's strength and gradation, so subgrade quality must be measured before blanket thickness and compaction requirements can be set. A visual inspection does not produce the quantitative data required by AREMA MRE or by the FRA grant program's technical standards.

Second, professional liability: Signing a geotechnical report that supports a design without performing a defensible investigation creates direct professional liability for the engineer of record. If the siding subgrade fails after construction — due to soft soils, high water table, or organic deposits that a visual inspection would not detect — the geotechnical consultant and the short-line railroad share liability for the design deficiency.

Third, practical cost argument: The cost of a minimum reconnaissance investigation for a 12,000-ft siding — approximately $60,000 to $90,000 — is 0.5 to 0.75% of a typical siding construction cost of $12 million to $15 million. Discovery of soft soils requiring ground improvement during construction routinely costs $500,000 to $1,500,000 in change orders. The investigation is not an optional expense; it is risk management that the FRA grant program explicitly expects.

Q3. Your firm holds a PSA with a Class I railroad and is executing a task order for a bridge replacement investigation on a Class I railroad subdivision. The 60% GDR is 80% complete when the railroad issues a revised edition of its engineering standards. The revision changes the minimum pile embedment depth requirement for the pile type you have already designed. What are your obligations, and what do you tell the client?

A: We notify the railroad's project manager immediately — the same day we learn of the revised edition — that a revision has been issued that affects our current design. We do not complete and issue the 60% GDR under the superseded standard without first confirming with the railroad's engineering group how to proceed.

Our specific obligations: (1) Obtain the revised standards from the railroad; confirm which edition and effective date apply to this project. (2) Review our pile embedment calculations against the new minimum depth requirement. If our calculations already meet or exceed the new minimum, document that compliance explicitly in the revised 60% GDR and reference the new edition. (3) If our calculated pile embedment is less than the new minimum, we must revise our pile design recommendations before issuing the 60% GDR — we cannot issue a document that we know conflicts with the current version of the applicable standard. (4) If the revised minimum depth requires additional borings to confirm competent material at the new depth, we prepare a supplemental boring scope for Class I railroad authorization before proceeding.

We tell the client: directly, transparently, and without delay. We do not quietly revise the document and hope the client does not notice which edition of the standards we applied. Professional integrity and our PSA obligation require full transparency about standards changes that affect our work.

Q4. You are providing emergency geotechnical response to a Class I railroad for a slope failure at milepost 347.2 on the Class I railroad Southern subdivision. After your site assessment, you determine that the failure is a shallow rotational failure with H = 8 ft, and the slope is currently stabilized with no active movement observed. Track geometry indicates a surface deviation of 1.8 in. over 31 ft at the slide location. The current Class I track classification is Class 4 freight at 60 mph. What is your track restriction recommendation, and what is your technical basis?

A: FRA Track Safety Standards (49 CFR 213.63) limit the deviation from uniform profile at the mid-ordinate of a 62-ft chord to 2 in. on Class 4 track and 2¾ in. on Class 2. A deviation measured on a 31-ft chord cannot be scaled to the 62-ft chord, so have the track inspector measure it on the 62-ft chord. Whether or not it exceeds the Class 4 limit, a 1.8-in. deviation at a slide shows that the failure has reached the track, so we apply engineering judgment.

Our recommendation: Reduce operating speed to 25 mph (Class 2 restriction) over the affected 300-ft zone while emergency investigation and repair proceed. Technical basis: (1) The 1.8-in. surface deviation indicates the failure has affected the track structure, justifying an operational restriction. (2) The slope is currently stabilized with no active movement, justifying a slow order rather than a full closure. (3) Class 2 at 25 mph reduces dynamic wheel loads (DLF from ~1.4 to ~1.15), reducing the cyclic stress on the unstable subgrade by approximately 20%, reducing risk of renewed movement while the emergency investigation is underway. (4) We specify the railroad's Roadmaster re-inspection every 12 hours until emergency repairs are in place.

We communicate this recommendation verbally to the railroad's Division Engineer during the site visit and follow up with a written email to the railroad's Division Engineer and Roadmaster within 2 hours of leaving the site, citing the FRA 49 CFR Part 213 surface deviation criteria and our AREMA MRE Chapter 1 slope stability assessment as the technical basis.

Q5. The railroad asks your firm to prepare a preliminary geotechnical report for a section of the passenger corridor between Baltimore and Philadelphia where recurring track geometry deviations have been observed in the passenger track geometry car data for three consecutive measurement runs. The track is designated Class 7 (125 mph passenger operations). You find organic clay at 8 to 18 ft depth in your borings with natural moisture content w_n = 78% and liquid limit LL = 82%. What criteria govern your settlement analysis, and what preliminary finding must you communicate to the railroad's project manager before the formal report is issued?

A: The governing criteria for this analysis are: the passenger railroad's track subgrade and earthwork standards for subgrade performance criteria; AREMA MRE Chapter 5 and 49 CFR Part 213 Subpart G for Class 7 track geometry tolerances (FRA deviation from zero crosslevel of 1 in. and profile deviation of 1 in. on a 62-ft chord, 49 CFR 213.331; the railroad's own limits may be tighter); and its bridge and structures standards for any settlement analysis at bridge approaches within the affected zone.

The organic clay condition (w_n/LL = 78/82 = 0.95 — natural moisture nearly at the liquid limit) indicates a soil at or near the liquid state with essentially zero effective stress margin. This material is under active consolidation and is the almost certain cause of the recurring track geometry deviations in the passenger geometry car data.

Preliminary finding to communicate to the railroad's project manager before the formal report: The preliminary finding is that the track geometry deviations are caused by ongoing primary consolidation settlement of a normally consolidated or lightly underconsolidated organic clay deposit at 8 to 18 ft depth. The settlement is ongoing — not a historical, completed event. Without intervention, the settlement will continue and the geometry deviations will worsen. For Class 7 passenger corridor operations with a cross-level tolerance of ½ in., the expected differential settlement rate — even if only 0.1 to 0.2 in. per year — will require more frequent maintenance surfacing than is sustainable for high-speed passenger operations on the passenger corridor. We communicate this finding in a preliminary technical memorandum within 48 hours of receiving the first laboratory test results, recommend that railroad engineering evaluate whether the current maintenance cycle is sustainable while geotechnical remediation options are evaluated, and request authorization to expand our investigation scope to include ground improvement feasibility assessment.

I.14 Cross-References to Technical Chapters
TopicChapter
Investigation planning — boring layout, depths, AREMA MRE Chapter 1.1 complianceChapter 3.9
Drilling, sampling, SPT corrections, boring logs in client-required formatsChapter 4.1
In situ testing — CPT, VST, PMT, MASW for soft ground characterizationChapter 5.1
Soil and rock classification — USCS, AASHTO, AREMA MRE Chapter 1.1 subgrade categoriesChapter 2.2
Groundwater — piezometers, permeability, seepage, dewatering for constructionChapter 2.8
Bearing capacity — Cooper E-80 loading, spread footings, piles, drilled shafts per AREMA MRE Ch. 8Chapter 6.1
Settlement — consolidation time rate; comparison to FRA and client geometry tolerancesChapter 6.2
Slope stability — AREMA MRE Chapter 1.1 embankment design, USACE EM 1110-2-1902Chapter 6.3
Seismic hazard and liquefaction — ASCE 7 site class; CPT and SPT methodsChapter 6.5
Pavement subgrade — CBR, resilient modulus, AASHTO 1993 design for yard pavingChapter 7.3
Ground improvement — preloading, PVDs, stone columns, DSM; client schedule implicationsChapter 7.2
Retaining structures — earth pressure, wall types, drainage; AREMA MRE Chapter 2.2Chapter 7.1
Railroad track subgrade — AREMA MRE Chapter 1.1 loading, subgrade failure modes, ballast designChapter 2.3
Construction monitoring — compaction acceptance, pile driving, instrumentationChapter 5.3
Report preparation — format by client, GSPsChapter 8.4
Laboratory testing program — test standards, testing plan, acceptance criteriaChapter 5.2

Chapter 3.9 — Geotechnical Investigation Planning and Scope

Primary Source: USACE EM 1110-1-1804, Geotechnical Investigations, 1 January 2001; AREMA Manual for Railway Engineering (MRE), Chapter 1 — Roadway and Ballast; client-specific railroad engineering standards as cited.

3.9.14 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental References.

Case Study 3.9.14.1 — No investigation: “the site across the road is the same”
Case study · Look (2023) §2.5

Related section: 3.9.1 Background — Why Planning is a Billable Deliverable

In this 1988 case a developer sold apartments “off the plan” on one site founded on high-level weathered rock (shallow footings, 4,200 psf allowable bearing). When a second lot of similar size came up across the road, less than 66 ft away, the developer duplicated the project and skipped a site investigation, citing “experience” from next door.

The second site sat over a buried alluvial channel. A backhoe test pit to 10 ft, then borings to 20 ft and 49 ft, showed rock dropping to about 39 ft with compressible alluvium above. Shallow foundations were no longer viable and piles were required. The added cost cancelled the project about three weeks after start, and every purchaser’s deposit was returned.

For railroad work: the same assumption appears when a siding, second main or bridge replacement is designed from borings taken for the adjacent structure. Ground can change completely within a few track lengths, especially where a line crosses a filled valley or old stream course. The cost of the investigation is small next to the cost of finding this out during construction.

Two sites less than 66 ft apart: high-level rock under the first, a buried alluvial channel with rock at about 39 ft under the second.
Figure 5-LK1. Two sites less than 66 ft apart: high-level rock under the first, a buried alluvial channel with rock at about 39 ft under the second. Source: Look (2023), Figure 2.5-1, p. 67.
Time line from the decision to skip the investigation to project cancellation and refund of deposits.
Figure 5-LK2. Time line from the decision to skip the investigation to project cancellation and refund of deposits. Source: Look (2023), Figure 2.5-2, p. 69.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §2.5, pp. 66–68. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 3.9.14.2 — A buried creek the ground model missed: deep basement dewatering
Case study · Look (2023) §1.7

Related section: 3.9.2 Desktop Review — The Essential First Step

A deep basement was designed from a seepage model built on in-situ permeability tests, particle-size estimates and a sensitivity check of upper-95% flow rates. Access limits put every boring and CPT outside the building footprint, so the model was effectively two-dimensional. Extraction wells in the middle of the site then pumped far more water than predicted, while flows at the corners stayed manageable. Undersized pumps cost construction time, because a pump of the right capacity is seldom an off-the-shelf item.

Wall type, toe level and an underlying gravel layer were all examined and none explained the flows. Forensic data-gathering did: historical records showed a creek crossing the middle of the site 150 years earlier, infilled in the late nineteenth century and left undeveloped for another 50 years. That paleochannel, filled with loose sand, was the governing feature. Additional borings in detailed design had hinted at local loose sand, but the preliminary parameters were carried forward with only “minor” adjustments.

Look’s lesson is that each model (geological, geotechnical, analytical, design, construction) inherits the errors of the one before it, and the construction model is two steps removed from the analysis. The geological model has to envelop the others.

For railroad work: old valuation maps, historical aerials and early topographic sheets belong in the desktop review for the same reason. Filled creeks, ponds and borrow pits under an embankment or a new structure are the features a two-dimensional boring line along the track will not find.

Geological model rebuilt from site history: an 1846 creek, infilled by 1865, lies under the 2014 basement footprint.
Figure 5-LK3. Geological model rebuilt from site history: an 1846 creek, infilled by 1865, lies under the 2014 basement footprint. Source: Look (2023), Figure 1.6-2, p. 29.
Geology, geotechnical and analytical models developed in the forensic stage to explain the basement inflows.
Figure 5-LK4. Geology, geotechnical and analytical models developed in the forensic stage to explain the basement inflows. Source: Look (2023), Figure 1.7-2, p. 31.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §1.7, pp. 28–30. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

3.9.15 Selecting Design Parameters and Estimating Probability of Failure

An investigation ends with a number chosen for each property, and the scatter in the data is as important as the average. The FHWA's Evaluation of Soil and Rock Properties (GEC 5) sets out a three-step selection. First, judge the data and remove values that reflect disturbance or a different material. Second, estimate variability, either from the tests themselves, from published coefficients of variation (Duncan 2000), or from the three-sigma rule using the highest and lowest conceivable values. Third, test the design at the mean and at the mean minus one standard deviation. Duncan, Wright and Brandon carry this to the probability that the factor of safety is less than 1.0 by the Taylor series method. One railroad's investigation requirements ask for the same end product: design strength parameters for every layer, from borings placed off the track where possible, preferably at the embankment toe.

3.9.15.1 Variability and the Taylor series method

Table 3.9-9. Coefficients of variation (Duncan 2000, in GEC 5 Table 52)
PropertyCOV (%)PropertyCOV (%)
Unit weight3 to 7Compression index10 to 37
Effective friction angle2 to 13Preconsolidation stress10 to 35
Undrained shear strength13 to 40Coefficient of consolidation33 to 68
Undrained strength ratio5 to 15Hydraulic conductivity, saturated clay68 to 90
SPT blow count15 to 45Electric CPT qc5 to 15
Vane shear strength10 to 20Mechanical CPT qc15 to 37

Equation 3.9-4. Standard deviation, reliability index and probability of failure

s = (HCV − LCV)/6  (three-sigma rule)

σF = √Σ[(Fi+ − Fi−)/2]²;   COVF = σF/FMLV
β = (FMLV − 1)/σF (normal);   βLN = ln[FMLV/√(1 + COVF²)]/√ln(1 + COVF²) (lognormal)

Fi+ and Fi− come from rerunning the stability analysis (for example with the Chapter 6.3 Bishop calculator) with one parameter at a time raised and lowered by one standard deviation. The probabilities agree with Duncan, Wright and Brandon's Tables 13.5 and 13.6. At FMLV = 1.5 and COVF = 20%, the calculator gives 4.8% (normal) and 2.6% (lognormal), against the tabulated 4.8% and 3%. At 1.2 and 10%, it gives 4.8% and 3.8%, against 4.8% and 4%.

3.9.15.2 Worked example

GEC 5's Piedmont example has a mean friction angle of 35.2°, a highest conceivable value of 53.8° and a lowest of 27.3°. The three-sigma rule gives s = 4.42, a COV of 12.5% (at the top of the published 2 to 13% range), and a mean minus one standard deviation of 30.78°. For an illustrative slope with FMLV = 1.5 and four uncertain parameters, the Taylor series gives COVF = 16.5% and a probability of failure of 2.18% (normal) or 0.84% (lognormal). The clay's undrained strength contributes most of the variance, so more strength testing of the clay is the investigation money best spent.

Engineers almost always set the highest and lowest conceivable values too close together. Widen them deliberately. Report the probability of failure alongside the factor of safety in the risk assessment (Chapter 3.8), and judge it against the consequence, not against a fixed number.

Open the design parameter reliability calculator →
Mean, standard deviation and COV from tests or the three-sigma rule, comparison with published COV ranges, mean minus one standard deviation, and probability of failure by the Taylor series method.

3.9.15.3 Using probability of failure in a decision

Duncan, Wright and Brandon show why a probability of failure can say more than a factor of safety. Two slope designs are compared. Design A has steep slopes, costs $100,000 for construction and land, and has Pf = 0.1. Design B has flatter slopes, costs $400,000, and has Pf = 0.01. If either failure would cost $5 million in primary and secondary consequences, the expected total cost is $100,000 + 0.1 × $5,000,000 = $600,000 for A and $400,000 + 0.01 × $5,000,000 = $450,000 for B. The design that costs more to build is cheaper overall. They also note that most people understand "1 chance in 10" against "1 chance in 100" more readily than 1.3 against 1.5. Putting a probability in front of an owner also makes clear that no factor of safety above 1.0 guarantees the slope will stand. The same arithmetic underlies the life-cycle comparison in Chapter 3.8.

Table 3.9-10. Expected total cost of two slope designs (Duncan, Wright and Brandon, Section 13.5.5)
DesignConstruction and landPfExpected failure cost ($5 million consequence)Expected total
A, steep slopes$100,0000.10$500,000$600,000
B, flatter slopes$400,0000.01$50,000$450,000

3.9.15.4 Checks against the published tables

The calculator's lognormal probabilities match Duncan, Wright and Brandon's Table 13.6, which is rounded, at the combinations below. Read across a row and the probability rises steeply with COVF. Reducing uncertainty through more testing can lower Pf as much as a higher factor of safety does.

Table 3.9-11. Probability that F < 1, lognormal distribution: published (Table 13.6) / calculated
FMLVCOVF = 10%COVF = 20%COVF = 30%
1.30.5% / 0.49%11% / 11.01%23% / 22.75%
1.50.00% / 0.00%3% / 2.57%11% / 10.85%
2.00.00% / 0.00%0.03% / 0.03%1.3% / 1.34%
11.522.501020304050Most likely factor of safetyProbability of failure (%), lognormalCOVF = 10%COVF = 20%COVF = 30%
Figure 3.9-11. Probability of failure against the most likely factor of safety for three coefficients of variation of F. The grey line marks 1%.

3.9.15.5 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • P.J. Sabatini and others, Evaluation of Soil and Rock Properties, FHWA Geotechnical Engineering Circular No. 5: selection of design parameters, variability, Table 52 and the Piedmont exampleFind source ↗Library entry
  • J.M. Duncan, S.G. Wright and T.L. Brandon, Soil Strength and Slope Stability, 2nd edition: Chapter 13, reliability, the Taylor series method and probability tablesFind source ↗
  • N. Simons, B. Menzies and M. Matthews, A Short Course in Geotechnical Site Investigation: the value of site investigationFind source ↗
  • U.S. Army Corps of Engineers, Geotechnical Investigations, EM 1110-1-1804 (2001): investigation planningOfficial page ↗
  • A Class I railroad's general requirements for geotechnical investigations for bridge projects: boring location, depth and reporting of design parametersFind source ↗

Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

Supplemental references

  • A Class I railroad (2018). Design and Construction Standard Specifications — Pipeline Occupancies. Office of VP–Engineering, Jacksonville, FL (rev. June 5, 2018)Find source ↗
  • A Class I railroad. Guidelines for Under Track CulvertsFind source ↗
  • Ruel, M. and KRK (2003). General Requirements for Geotechnical Investigations for the railroad's Bridge Construction Projects and “A Practical Approach to Lateral Loading on Piles for Railroad Bridge Design on Class I railroad Projects.” a Class I railroadFind source ↗
  • Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & FrancisFind source ↗
  • Repetto, P. C. (2003). “Geo-Environment,” Ch. 26 in The Civil Engineering Handbook, 2nd ed. CRC PressFind source ↗Library entry
  • Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003Find source ↗
  • Miesner, T. O. and Leffler, W. L. (2006). Oil and Gas Pipelines in Nontechnical Language. PennWellFind source ↗
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §1.7, §2.5Find source ↗Library entry

File locations for these documents are listed under Supplemental References.

Project management sources

  • Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group)Find source ↗
  • Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-HillFind source ↗
  • Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & SonsFind source ↗
  • Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier)Find source ↗
  • Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan PressFind source ↗
  • Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc.Find source ↗
  • Chartered Institute of Building (2014). Code of Practice for Project Management for Construction and Development, 5th ed. Chichester, UK: John Wiley & SonsFind source ↗
  • American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCEFind source ↗
  • Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]Find source ↗
  • Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell ScienceFind source ↗
  • Rad, P. F. (2002). Project Estimating and Cost Management. Vienna, VA: Management ConceptsFind source ↗
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After UFC 4-860-01FA (2004)” draw on item S10 and are rewritten for railroad clients. Blocks marked “After Selig & Waters (1994)” summarize item S11 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S12 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. A Class I railroad (2018). Design and Construction Standard Specifications — Pipeline Occupancies. Office of VP–Engineering, Jacksonville, FL (rev. June 5, 2018)Find source ↗
  2. A Class I railroad. Guidelines for Under Track CulvertsFind source ↗
  3. Ruel, M. and KRK (2003). General Requirements for Geotechnical Investigations for the railroad's Bridge Construction Projects and “A Practical Approach to Lateral Loading on Piles for Railroad Bridge Design on Class I railroad Projects.” a Class I railroadFind source ↗
  4. Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & FrancisFind source ↗
  5. Repetto, P. C. (2003). “Geo-Environment,” Ch. 26 in The Civil Engineering Handbook, 2nd ed. CRC PressFind source ↗Library entry
  6. Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003Find source ↗
  7. Miesner, T. O. and Leffler, W. L. (2006). Oil and Gas Pipelines in Nontechnical Language. PennWellFind source ↗
  8. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  9. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  10. U.S. Army Corps of Engineers, Naval Facilities Engineering Command and Air Force Civil Engineer Support Agency (2004). UFC 4-860-01FA, Railroad Design and Rehabilitation. Unified Facilities Criteria, 16 January 2004 (supersedes TI 850-02, 1 March 2000); approved for public release, distribution unlimited. Used on this page: ch. 2 and ch. 6 (§8)Find source ↗Library entry
  11. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 2, 4, 5, 10, 14, 15 and 16Find source ↗Library entry
  12. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §1.7, §2.5Find source ↗Library entry
  13. Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group). Used on this page for project-management materialFind source ↗
  14. Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill. Used on this page for project-management materialFind source ↗
  15. Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons. Used on this page for project-management materialFind source ↗
  16. Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier). Used on this page for project-management materialFind source ↗
  17. Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press. Used on this page for project-management materialFind source ↗
  18. Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc.. Used on this page for project-management materialFind source ↗
  19. Chartered Institute of Building (2014). Code of Practice for Project Management for Construction and Development, 5th ed. Chichester, UK: John Wiley & Sons. Used on this page for project-management materialFind source ↗
  20. American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE. Used on this page for project-management materialFind source ↗
  21. Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]. Used on this page for project-management materialFind source ↗
  22. Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science. Used on this page for project-management materialFind source ↗
  23. Rad, P. F. (2002). Project Estimating and Cost Management. Vienna, VA: Management Concepts. Used on this page for project-management materialFind source ↗