Primary Source: USACE EM 1110-1-1804, Geotechnical Investigations, 1 January 2001; AREMA Manual for Railway Engineering (MRE), Chapter 1 — Roadway and Ballast; client-specific railroad engineering standards as cited.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Property and test variability to guide the number of borings and tests, and what failure case histories say about investigation scope. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Primary cause of geotechnical failure (share of cases) | Shortcomings in design | ISSMGE TC302 Task Force 10, ~100 case histories | 45 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Inadequate site investigation | ISSMGE TC302 Task Force 10, ~100 case histories | 20 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Unforeseen phenomena and occurrences | ISSMGE TC302 Task Force 10, ~100 case histories | 20 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Shortcomings in construction | ISSMGE TC302 Task Force 10, ~100 case histories | 14 | % | FGE text, p.274 | |||
| Site investigation spend worth making | Project cost | U.S. study (Threadgold 2002) | 3 | % of project cost | FGE text, p.272 | |||
| Site investigation spend on projects with > 50% cost overrun | Outturn project cost | UK projects (Clayton 2001) | 2.5 | % of project cost | FGE text, p.272 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Coefficient of variation | Natural moisture content | Mean, without outliers | 17.7 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Liquid limit | Mean, without outliers | 11.1 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Plastic limit | Mean, without outliers | 11.3 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Initial void ratio | Mean, without outliers | 19.8 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Unit weight | Mean, without outliers | 7.1 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Rock unconfined compressive strength | Mean, without outliers | 23 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Effective friction angle | Mean, without outliers | 12.6 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Tangent of friction angle | Mean, without outliers | 11.3 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Undrained shear strength | Mean, without outliers | 33.8 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation | Compression index | Mean, without outliers | 37 | % | LOOK T10.2, p.137 | |||
| Coefficient of variation – inherent variability | Fine-grained soils – Unit weight | ML-CH | Kulhawy et al. (2000), 14 data groups | 2 | 7.8 | 20 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Fine-grained soils – Natural moisture content | ML-CH | Kulhawy et al. (2000), 40 data groups | 7 | 18.1 | 46 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Fine-grained soils – Plastic limit | ML-CH | Kulhawy et al. (2000), 23 data groups | 6 | 15.7 | 34 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Fine-grained soils – Liquid limit | ML-CH | Kulhawy et al. (2000), 38 data groups | 7 | 18.1 | 39 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Fine-grained soils – all data – Plasticity index | ML-CH | Kulhawy et al. (2000), 33 data groups | 9 | 29.5 | 57 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Fine-grained soils, PI ≤ 20% – Plasticity index | ML-CL | Kulhawy et al. (2000), 13 data groups | 16 | 35 | 57 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Fine-grained soils, PI > 20% – Plasticity index | CL-CH | Kulhawy et al. (2000), 20 data groups | 9 | 26 | 40 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Rock – Unit weight | Kulhawy et al. (2000), 42 data groups | 0.1 | 0.9 | 3 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Rock – Porosity | Kulhawy et al. (2000), 25 data groups | 3 | 25.9 | 71 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand and clay – Effective friction angle | Kulhawy et al. (2000), 48 data groups | 4 | 13.9 | 50 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand – Effective friction angle | SW-SM | Kulhawy et al. (2000), 32 data groups | 4 | 9 | 15 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – Effective friction angle | CL-CH | Kulhawy et al. (2000), 16 data groups | 10 | 23.5 | 50 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – Undrained shear strength | CL-CH | Kulhawy et al. (2000), 100 data groups | 6 | 31.5 | 80 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Rock – Rock unconfined compressive strength | Kulhawy et al. (2000), 184 data groups | 0.3 | 14.2 | 61 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Rock – Brazilian tensile strength | Kulhawy et al. (2000), 74 data groups | 2 | 16.6 | 58 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Rock – Tangent modulus at 50% strength | Kulhawy et al. (2000), 32 data groups | 7 | 30.7 | 63 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand and clay – CPT cone resistance | Kulhawy et al. (2000), 65 data groups | 10 | 36.6 | 81 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand – CPT cone resistance | SW-SM | Kulhawy et al. (2000), 54 data groups | 10 | 38.2 | 81 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – CPT cone resistance | CL-CH | Kulhawy et al. (2000), 11 data groups | 16 | 28.4 | 40 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – CPT corrected cone resistance | CL-CH | Kulhawy et al. (2000), 9 data groups | 2 | 7.9 | 17 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – Vane shear strength | CL-CH | Kulhawy et al. (2000), 26 data groups | 13 | 25.3 | 36 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Sand and clay – SPT blow count | Kulhawy et al. (2000), 23 data groups | 19 | 38 | 62 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand and clay – DMT A and B readings | Kulhawy et al. (2000), 56 data groups | 12 | 27.9 | 59 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand – DMT A and B readings | SW-SM | Kulhawy et al. (2000), 30 data groups | 13 | 34.8 | 59 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – DMT A and B readings | CL-CH | Kulhawy et al. (2000), 26 data groups | 12 | 19.9 | 38 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Sand (without outliers) – DMT material index | SW-SM | Kulhawy et al. (2000), 29 data groups | 8 | 37.7 | 66 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Sand (without outliers) – DMT horizontal stress index | SW-SM | Kulhawy et al. (2000), 29 data groups | 15 | 37.6 | 67 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Sand (without outliers) – DMT modulus | SW-SM | Kulhawy et al. (2000), 30 data groups | 7 | 41.1 | 69 | % | FGE T31.3, p.479 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Coefficient of variation of in situ test | Standard penetration test | Equipment + procedure + random | 15 | 30 | 45 | % | LOOK T10.3, p.137 | |
| Coefficient of variation of in situ test | Mechanical cone penetration test | Equipment + procedure + random | 15 | 20 | 25 | % | LOOK T10.3, p.137 | |
| Coefficient of variation of in situ test | Self-boring pressuremeter | Equipment + procedure + random | 15 | 20 | 25 | % | LOOK T10.3, p.137 | |
| Coefficient of variation of in situ test | Vane shear test | Equipment + procedure + random | 10 | 15 | 20 | % | LOOK T10.3, p.137 | |
| Coefficient of variation of in situ test | Pressuremeter, prebored | Equipment + procedure + random | 10 | 15 | 20 | % | LOOK T10.3, p.137 | |
| Coefficient of variation – lab measurement error | Clay, silt – Undrained strength, triaxial compression su(TC) | CL-ML | Phoon & Kulhawy (1999a) | 8 | 19 | 38 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay, silt – Undrained strength, direct shear su(DS) | CL-ML | Phoon & Kulhawy (1999a) | 19 | 20 | 20 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay – Undrained strength, lab vane su(LV) | CL-CH | Phoon & Kulhawy (1999a) | 5 | 13 | 37 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay, silt – Friction angle, triaxial φ′(TC) | CL-ML | Phoon & Kulhawy (1999a) | 7 | 24 | 56 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay, silt – Friction angle, direct shear φ′(DS) | CL-ML | Phoon & Kulhawy (1999a) | 3 | 13 | 29 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Sand – Friction angle, direct shear φ′(DS) | SW-SM | Phoon & Kulhawy (1999a) | 13 | 14 | 14 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Sand, silt – tan φ′, triaxial | SM-ML | Phoon & Kulhawy (1999a) | 2 | 8 | 22 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay – tan φ′, direct shear | CL-CH | Phoon & Kulhawy (1999a) | 6 | 14 | 22 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Fine-grained soils – Natural moisture content wn | ML-CH | Phoon & Kulhawy (1999a) | 6 | 8 | 12 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Fine-grained soils – Liquid limit wL | ML-CH | Phoon & Kulhawy (1999a) | 3 | 7 | 11 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Fine-grained soils – Plastic limit wP | ML-CH | Phoon & Kulhawy (1999a) | 7 | 10 | 18 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Fine-grained soils – Plasticity index PI | ML-CH | Phoon & Kulhawy (1999a) | 5 | 24 | 51 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Fine-grained soils – Total unit weight γ | ML-CH | Phoon & Kulhawy (1999a) | 1 | 1 | 2 | % | FGE T31.4, p.480 |
| Coefficient of variation of in situ test – measurement error | Standard penetration test (SPT) | Total probable range | 15 | 30 | 45 | % | FGE T31.5, p.480 | |
| Coefficient of variation of in situ test – measurement error | Mechanical cone (MCPT) | Total probable range | 15 | 15 | 25 | % | FGE T31.5, p.480 | |
| Coefficient of variation of in situ test – measurement error | Electric cone (ECPT) | Total probable range | 5 | 7 | 15 | % | FGE T31.5, p.480 | |
| Coefficient of variation of in situ test – measurement error | Vane shear test (VST) | Total probable range | 10 | 14 | 20 | % | FGE T31.5, p.480 | |
| Coefficient of variation of in situ test – measurement error | Dilatometer (DMT) | Total probable range | 5 | 11 | 15 | % | FGE T31.5, p.480 | |
| Coefficient of variation of in situ test – measurement error | Pressuremeter, prebored (PMT) | Total probable range | 10 | 16 | 20 | % | FGE T31.5, p.480 | |
| Coefficient of variation of in situ test – measurement error | Self-boring pressuremeter (SBPMT) | Total probable range | 15 | 19 | 25 | % | FGE T31.5, p.480 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UC) | CL-CH | Direct (lab) | 20 | 37.5 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UU) | CL-CH | Direct (lab) | 10 | 22.5 | 35 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(CIUC) | CL-CH | Direct (lab) | 20 | 32.5 | 45 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(field) | CL-CH | Vane shear | 15 | 32.5 | 50 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UU) | CL-CH | From CPT qT | 30 | 35 | 40 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(CIUC) | CL-CH | From CPT qT | 35 | 42.5 | 50 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UU) | CL-CH | From SPT N | 40 | 50 | 60 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su | CL-CH | From DMT KD | 30 | 42.5 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(field) | CL-CH | From PI | 30 | 42.5 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay, sand – Effective friction angle φ′ | Direct (lab) | 7 | 13.5 | 20 | % | FGE T31.7, p.485 | |
| Coefficient of variation – design parameter (point) | Sand – Effective friction angle φ′(TC) | SW-SM | From CPT qT | 10 | 12.5 | 15 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Constant-volume friction angle φ′cv | CL-CH | From PI | 15 | 17.5 | 20 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – At-rest coefficient K0 | CL-CH | Direct (SBPMT) | 20 | 32.5 | 45 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Sand – At-rest coefficient K0 | SW-SM | Direct (SBPMT) | 25 | 40 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – At-rest coefficient K0 | CL-CH | From DMT KD | 35 | 42.5 | 50 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – At-rest coefficient K0 | CL-CH | From SPT N | 40 | 57.5 | 75 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Sand – Pressuremeter modulus EPMT | SW-SM | Direct (PMT) | 20 | 45 | 70 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Sand – Dilatometer modulus ED | SW-SM | Direct (DMT) | 15 | 42.5 | 70 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Pressuremeter modulus EPMT | CL-CH | From SPT N | 85 | 90 | 95 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Silt – Dilatometer modulus ED | ML | From SPT N | 40 | 50 | 60 | % | FGE T31.7, p.485 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Vertical scale of fluctuation | Clay – su | Lab testing | 2.6 | 15.4 | 28.2 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Clay – su | Vane shear | 6.6 | 13.4 | 20.3 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Clay – su | Vane shear | 150.9 | 173.9 | 196.9 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Sand, clay – qc | CPT | 0.3 | 5.05 | 9.8 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Sand, clay – qc | CPT | 9.8 | 136.2 | 262.5 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Offshore soils – qc | CPT | 1 | 1.15 | 1.3 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Offshore soils – qc | CPT | 45.9 | 85.3 | 124.7 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Clay – qt | CPTu | 0.7 | 1.15 | 1.6 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Clay – qt | CPTu | 75.5 | 146 | 216.5 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Cohesive-behavior soils – qc1N | CPT | 0.3 | 1.15 | 2 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Intermediate-behavior soils – qc1N | CPT | 1 | 2.15 | 3.3 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Cohesionless-behavior soils – qc1N | CPT | 1.3 | 2.45 | 3.6 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Sand – fs | CPT | 4.3 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Cohesive-behavior soils – Ic | CPT | 0.7 | 1.15 | 1.6 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Intermediate-behavior soils – Ic | CPT | 2 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Cohesionless-behavior soils – Ic | CPT | 1 | 2.45 | 3.9 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Sand – N | SPT | 7.9 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Clay, loam – w | Lab testing | 5.2 | 23.5 | 41.7 | ft | FGE T31.6, p.484 | |
| Horizontal scale of fluctuation | Clay, loam – w | Lab testing | 557.8 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Clay, loam – wL | Lab testing | 5.2 | 16.9 | 28.5 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Clay, loam – γ | Lab testing | 7.9 | 16.9 | 25.9 | ft | FGE T31.6, p.484 | |
| Vertical scale of fluctuation | Organic silty clay – e | Lab testing | 9.8 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Organic silty clay – σ′p | Lab testing | 2 | ft | FGE T31.6, p.484 | |||
| Horizontal scale of fluctuation | Organic silty clay – σ′p | Lab testing | 590.6 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Sand – ln(Dr) | SPT | 12.1 | ft | FGE T31.6, p.484 | |||
| Horizontal scale of fluctuation | Sand – ln(Dr) | SPT | 219.8 | ft | FGE T31.6, p.484 | |||
| Vertical scale of fluctuation | Sand – n | – | 21.3 | ft | FGE T31.6, p.484 | |||
| Horizontal scale of fluctuation | Sand – n | – | 10.8 | ft | FGE T31.6, p.484 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
A well-planned geotechnical investigation is the foundation of every successful railroad engineering project. Planning errors — insufficient boring depths, wrong spacing, missing laboratory tests — cannot be corrected during analysis; they produce reports that fail engineering review, delay project schedules, and increase total project cost. This chapter establishes the systematic planning process we apply on every railroad geotechnical program, from the first desktop review through final boring layout approval. Key outputs of the planning phase are: a boring location plan dimensioned in feet and referenced to railroad mileposts, a boring depth matrix derived from stress influence calculations in English units, a laboratory testing assignment sheet linked to the specific design questions the investigation must answer, and a project-specific health and safety plan that satisfies the host railroad's Right-of-Way Protection (RWP) requirements.
Railroad client references: AREMA MRE Ch. 1, Parts 1 and 2 (Roadbed; Ballast); the owner railroad's current engineering standards (confirm the edition when the work is scoped).
The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.
| ID | Correlation | Gives |
|---|---|---|
| IS-01 | SPT energy & procedure correction | N₆₀ |
| RK-10 | UCS from point load index | σ꜀ |
| IS-02 | SPT overburden normalization (sands) | (N₁)₆₀ |
| IX-01 | Compression index from liquid limit (undisturbed) | C꜀ |
| RK-01 | Rock Mass Rating (RMR₈₉) | RMR |
Planning a geotechnical investigation for a railroad client is not overhead — it is a professional service that prevents costly scope errors and keeps the investigation aligned with the design question the railroad's engineering department needs answered. On railroad programs that operate under Professional Services Agreements (PSA), planning is typically the first deliverable under a task order: a written Investigation Plan or Boring Plan memorandum that the railroad project manager reviews and approves before field work begins.

USACE EM 1110-1-1804 §2-1 defines the objective of a geotechnical investigation as obtaining information that permits design of a safe and economic structure. This definition translates directly to railroad practice: every boring, every sample, and every laboratory test must be traceable to a specific design parameter needed by the railroad's engineering team.
The most common planning failure in railroad geotechnical work is designing the investigation around what is convenient to access rather than what the design requires. A convenient boring is one that can be reached with standard drill rig access from a paved road or an open field. But the critical foundation condition for a railroad bridge abutment, retaining wall, or track embankment is often in a location that requires a track window, specialty equipment, or an ROW access permit — not a convenient open-field location. We plan investigations around the design question first; we solve the access problem second.
Table 5-S3. Site investigation cost as a percentage of project cost (Rowe, 1972, in Look, 2007)
| Type of work | % of capital cost | % of earthworks & foundation cost |
|---|---|---|
| Earth dams | 0.89–3.30 | 1.14–5.20 |
| Railways | 0.60–2.00 | 3.5 |
| Roads | 0.20–1.55 | 1.60–5.67 |
| Bridges | 0.12–0.50 | 0.26–1.30 |
| Embankments | 0.12–0.19 | 0.16–0.20 |
| Overall mean | 0.7 | 1.5 |
Railways sit near the top of the range. Look recommends budgeting no less than 0.2% of capital cost, notes that laboratory testing is typically only 10–20% of investigation cost, and warns against the competitive-bid trend of cutting lab testing and inferring design parameters from field classification alone. In Look’s relative risk ranking, rail embankments and railway bridges are rated higher-risk developments than road embankments and highway bridges.
Source: Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis
Case study: 3.9.14.1 No investigation: “the site across the road is the same” (Look 2023), in §5.14 Case Studies.
Miller argues that a project plan should be organized around deliverables rather than activities, because the client cares about what the project hands over, not the list of tasks performed. Deliverables are written as nouns. They are arranged in a product breakdown structure (PBS), the top component of the WBS, drawn either as an organization chart or as an indented outline. The single topmost deliverable is level zero; each lower level is produced by successive decomposition of the level above.
A complete PBS holds three kinds of deliverables:
The fourth level is usually enough detail to control the work. Go deeper where a deliverable is subcontracted (the subcontractor defines two further levels below it), where the deliverable is unfamiliar to the team, or where a team member is unknown to the manager. Miller rejects arbitrary rules such as “no activity longer than 40 hours”; each lowest-level deliverable should define one complete activity. His worked example decomposes a one-day recognition event for 400 employees through Events → Children’s Program → Rides → individual rides.

For railroad work: make level zero the thing the railroad is buying, for example “Geotechnical data report and repair recommendations, embankment at MP 112.4.” Level 1 legs might be Field Data, Laboratory Data, Analyses, Reports, Process Deliverables and Client Deliverables. Put the railroad’s obligations on the client leg: right-of-entry and track-access approval, track time and flagging or other roadway worker protection, utility and signal cable records, as-built drawings and the slow-order and maintenance history of the site. Group the safety plan, job-briefing plan, boring location plan, drilling subcontract and chain-of-custody procedure on the process leg. Because drilling is normally subcontracted, have the driller break the drilling deliverable into two more levels (mobilization, each boring log with its sample set, grouting records). A PBS of this kind also makes a clear scope exhibit for the proposal and shows the client exactly what each fee line produces.
Source: Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group), pp. 23–25, 31–33, 45–49. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Oberlender frames every project as passing through owner’s study, preliminary engineering, detailed design, procurement and construction. His central argument, shown as two opposing curves, is that the ability to influence quality, cost and schedule is highest at the start and falls steadily, while the cost of implementing a change is lowest at the start and rises steeply once procurement and construction begin. Savings are made early, not at the start of construction.


From this he draws several working rules:
He also cites the Construction Industry Institute’s Project Definition Rating Index (PDRI): 70 scope elements, each rated 1 (complete) to 5 (poor), weighted to a maximum of 1,000 points. In the CII study, projects that scored below 200 performed significantly better than those that scored above 200.
For railroad work: The geotechnical investigation sits at the high-influence end of the curve. Boring locations, depths and lab assignments are fixed while the repair concept (undercut and blanket, shear key, wall, ground improvement or culvert replacement) is still open. Once a track window is booked and materials are ordered, changing direction costs track time as well as money. Before mobilizing a drill rig, confirm with the railroad’s project engineer the purpose of the work, the performance target (for example, removing a slow order or meeting a settlement tolerance), the access and work-window constraints, and the not-to-exceed budget. Record any assumptions in the scope letter so that a later change, such as adding a culvert crossing or extending the limits after a new slip, is visibly a change and is priced as one.
Source: Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill, pp. 33–41, 119–121. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Cretu, Stewart and Berends describe four estimate levels (planning, scoping, design, and final/letting), each with its own purpose, method and expected accuracy. The accuracy range narrows as design matures, but it is not symmetrical: the upper end sits much farther above the baseline than the lower end sits below it, and the upper end moves toward the baseline faster as project-specific information is gained. The authors read this as evidence that economic and political pressures push early numbers down, and they warn reviewers to watch for it. They place reasonably firm project definition at roughly 30 percent design. Before that point the estimate range is driven mostly by scope uncertainty; after it, by unit-cost and market uncertainty plus discrete risk events.

Their illustration uses a project that ends up costing $100 million. Read from their chart, the plausible range at about 2 percent design runs from roughly $50 million to $300 million, tightens to about $70–150 million at 30 percent, and is close to $95–110 million at letting. In the same way, the “miscellaneous item allowance” that covers undefined scope typically falls from 30–50 percent at planning, to 20–30 percent at scoping, to 10–20 percent during design, and to zero at letting, when every item should be defined. The authors also call for a written basis of estimate (BOE) that records scope, exclusions, assumptions, data sources and the threats and opportunities known when the estimate was made. They urge reporting early estimates as ranges, because the first number given is the one everyone remembers.
For railroad work: On subgrade rehabilitation, slide repair and culvert replacement projects, the upper tail of the estimate is driven mainly by ground conditions: depth to competent material, soft or organic foundation soils, groundwater, and the extent of fouled ballast or a failed subgrade layer. That makes the investigation the main way to pull the upper end down before the railroad sets a capital budget. When scoping a program, show the client the current estimate range, identify which geotechnical unknowns control its upper end, and describe how the proposed borings, CPT soundings or GPR would narrow it. Record the geotechnical assumptions behind each estimate in a BOE-style note, such as an assumed undercut depth, assumed rock line or assumed drainage outfall, so that later changes can be traced to new subsurface data rather than read as estimating error.
Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 18–25. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Every railroad geotechnical investigation begins with a desktop review before a single boring is planned. The desktop review assembles all available prior subsurface and surface information for the project corridor and produces a preliminary geologic model that frames the entire investigation strategy.
Existing boring data: Railroad clients maintain subsurface databases of varying quality. Owner railroads maintain central engineering databases that may contain prior boring logs for the project corridor. The railroad's engineering department archives prior geotechnical reports and can provide boring logs for Class I network segments. The railroad's engineering group maintains a GIS-based boring database for capital projects. For short-line subsidiary networks, prior subsurface data is often sparse or held at the subsidiary level — contact the short-line corporate engineering group early to determine what is available.
Published geologic maps: USGS 7.5-minute quadrangle maps and state geologic surveys provide bedrock and surficial geology. The USGS National Geologic Map Database is the primary digital resource. Specific attention: karst terrain (Missouri, Indiana, Kentucky — Class I railroad corridors), residual soil from granitic gneiss (Virginia, North Carolina, Georgia — Class I railroad corridors), loess deposits (Mississippi Valley — Class I railroad corridors), expansive clay (Gulf Coast, Texas — Class I railroad corridors).
USDA Web Soil Survey: Provides surficial soil mapping at 1:24,000 scale. Useful for preliminary identification of potentially soft or problematic subgrades along new alignment corridors.
FEMA Flood Insurance Rate Maps (FIRM): Identify flood-prone zones and potential high-water conditions for bridge approaches, embankments, and drainage structures on owner railroads' corridors.
Aerial photographs and satellite imagery: Historical aerial photograph archives (USGS EarthExplorer) reveal past land use, former fill areas, evidence of slope movement, and changes in drainage patterns that may not appear in current satellite imagery.
LiDAR digital elevation models: State and federal LiDAR datasets provide 1- to 2-ft contour resolution suitable for preliminary slope geometry characterization and drainage analysis. Most state DOTs and USGS provide free LiDAR downloads.
Prior geotechnical reports: Obtain all prior geotechnical reports for the project corridor, including reports prepared for adjacent projects on the same railroad. For the owner railroads, prior reports may reside in the railroad's internal engineering archive rather than with the geotechnical consultant.
Change in track geometry under traffic comes from one of two sources: cumulative deformation of the ballast and subballast, or movement of the subgrade. Field observation combined with maintenance records at chronic spots tells the two apart. Frequent resurfacing at the same location, when it traces to the subgrade, points to low bearing capacity. Ask the client for:
Build up a district file of soil and geology maps that later projects can reuse. A deterioration rate that rises from one maintenance cycle to the next is a useful trigger for a substructure investigation.
After Selig & Waters (1994), chs. 4, 10 and 15. Full reference under Supplemental References.
The desktop review culminates in a written memorandum — typically 3 to 8 pages — that the railroad project manager can review before authorizing field work. The memorandum covers:
Yards, fueling facilities, former industrial spurs and sidings next to waste sites often put a geotechnical boring inside an environmental compliance or remediation footprint. Repetto (2003) groups these projects as waste disposal (landfills, lagoons, tailings), compliance at active facilities, and remediation at closed facilities; the containment systems used are liners, low-permeability covers and slurry-wall cut-offs. When the desktop review identifies one of these, the plan should:
Source: Repetto, P. C. (2003). “Geo-Environment,” Ch. 26 in The Civil Engineering Handbook, 2nd ed. CRC Press
Profillidis starts every geotechnical investigation with available documents (topographic, geologic and hydrogeologic maps, aerial photographs, historical investigation records) and a site reconnaissance, to understand the likely problems and to plan the main study. For new-line design he ties the investigation to the design stages:
| Stage | Mapping scale | Scope |
|---|---|---|
| Preliminary design | 1:50,000 or 1:25,000, aerial / satellite imagery | 2–4 possible routes; horizontal and longitudinal profiles; major structures, utilities and first cost estimate |
| Outline design | 1:5,000; cross-sections every 330 ft | 2–3 routes within a corridor 164 ft wide (flat terrain) to 1.2 mi or more (mountains); subgrade and drainage, bridges and tunnels, construction planning |
| Final design | 1:2,000–1:1,000 (difficult terrain); 1:1,000–1:500 (urban) | Balance of speed, curvature, gradient and soil-mechanics constraints; minimize future maintenance |

For existing lines built decades ago, he notes that a full analytical survey is usually not needed, but a general knowledge of the subgrade’s basic mechanical behavior is essential.
After Profillidis (2014), §9.2.2, §9.3, §14.13–14.14, Fig. 14.12. Full reference under Supplemental References.
Similar landforms are built the same way and contain similar materials. Identify the landform and you can predict the material and how it will behave. Almost all railway terrain has published geologic and soil mapping, and cross-referencing problem sites against it is a useful desktop habit.





After Geotechnology for Railroaders Program, Module 2; §02–06. Full reference under Supplemental References.
Traffic type and volume drive the track structure, the number and length of yard and support tracks, and the terminal layout. Collect the traffic basis during the desktop review and have the client confirm it in writing. Only then set the investigation scope and the design loads. Cover both existing traffic and foreseeable growth, including surge or peak periods.

| Item | What to obtain | Why it matters |
|---|---|---|
| Traffic type | Commodities handled; car types and sizes; loading and unloading method; height and width of loads on open cars (flats, gondolas); special handling or restrictions, especially hazardous materials | Loading facility type, clearances, special containment |
| Traffic volume | Maximum cars of each type on site at one time, including empties; maximum cars of all types; longest train into or out of the site; maximum cars each loading facility handles in one cycle | Number and length of tracks, yard and terminal capacity |
| Wheel loads | Heaviest loaded car in common use on each track; heaviest locomotive (owner’s and serving railroad’s) | Design wheel load (Chapter 2.3, Table 2-S8) and subgrade stress |
| Locomotive tractive effort | Tractive effort curve, or locomotive weight and horsepower if no curve is available | Train size versus ruling grade and curvature |
| Sources | Client operating and transportation staff, shippers, the serving railroad, existing capacity studies | Traceable basis for the design |
After UFC 4-860-01FA (2004), ch. 2, §§1–3, 5 and 7. Adapted from military installation practice to railroad and industrial clients by the authors. Full reference under Supplemental References.
Case study: 3.9.14.2 A buried creek the ground model missed: deep basement dewatering (Look 2023), in §5.14 Case Studies.
Before finalizing boring locations and depths, we confirm which standards govern the investigation. Railroad clients do not all use the same standards; mixing them up is a professional error that creates review problems and can require costly revisions.
AREMA MRE Chapter 1 — Roadway and Ballast is the common technical baseline for subgrade-related investigations on owner railroads. AREMA MRE Chapter 1, Part 2 (Section 3.10) sizes the ballast and subballast from the strength and gradation of the subgrade, so the subgrade must be characterized before those thicknesses are set. AREMA MRE Chapter 8 — Structures governs foundation design for bridges, retaining walls, and culverts using Cooper E-80 design live load.
Each owner railroad also has its own engineering standards, and they differ in boring spacing and depth, log format, sample retention, review and track-access requirements. Obtain the current edition from the owner railroad when the work is scoped, record which edition was used, and follow it where it is stricter than the published guidance in this manual.
Pipeline and utility crossings are a frequent small task order, and the railroad’s occupancy specification — not the utility owner’s design standard — sets the investigation scope. The railroad's Pipeline Occupancies specification (rev. 2018) requires:
Table 5-S1. Class I railroad live load on buried structures, Cooper E-80 including impact
| Cover (ft) | 2 | 3 | 4 | 5 | 6 | 8 | 10 | 12 | 16 | 20 | 25 | 30 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Load (psf) | 3,800 | 3,150 | 2,850 | 2,550 | 2,250 | 1,700 | 1,300 | 1,000 | 625 | 400 | 250 | 150 |
For lateral surcharge on sheet piling or pits beside the track, the railroad specifies a Boussinesq strip load 8.5 ft wide (tie length) with q = 80,000 / (8.5 × 5) = 1,882 psf per E-80 axle. Expect pushback on casings from pipeline owners: Miesner and Leffler explain that the industry has moved away from cased road and railroad crossings because the carrier must be electrically insulated from the casing to prevent galvanic corrosion, and shorted casings are a chronic corrosion problem. That is the reason owners ask for uncased crossings — which the railroad allows for gas lines only at 10 ft or more below base of rail.
Source: A Class I railroad (2018). Design and Construction Standard Specifications — Pipeline Occupancies. Office of VP–Engineering, Jacksonville, FL (rev. June 5, 2018) · Miesner, T. O. and Leffler, W. L. (2006). Oil and Gas Pipelines in Nontechnical Language. PennWell
Source: A Class I railroad. Guidelines for Under Track Culverts
The following boring spacing criteria are taken from published sources in the library; Section 3.9.5.3 sets out the sources, the depth criteria and the planner.
| Project Type | Spacing or number | Notes | Source |
|---|---|---|---|
| New main, siding or track extension | One per 500 ft (high-strength soil), 200 ft (medium), 100 ft (low) | Add borings at drainage crossings and cut-fill transitions | Li and others (2016), Table 8.1 |
| Existing line, cut and fill | Series of 3 (shoulder, midslope, ditch at toe) about every 1,320 ft | A railroad minimum; tighten for the ground | A Class I railroad's public projects requirements |
| Embankment | 80 to 165 ft at critical areas; 330 ft or more elsewhere | Shoulder and toe borings at each station | Look, Table 1.8 |
| Cut slope | 80 to 165 ft (H over 16 ft); 165 to 330 ft (lower cuts) | Boring atop the cut and at the toe | Look; A Class I railroad's public projects requirements |
| Bridge | Each pier and abutment; one may do for a short bridge in uniform geology | Toe of embankment, away from the track, where practical | A Class I railroad's bridge requirements; Look |
| Retaining wall | At each wall; 50 to 100 ft along the line | Denser in variable ground | A Class I railroad's public projects requirements; spacing is practice |
| Culvert | Under 66 ft: 1; 66 to 130 ft: each end; longer: each end and every 66 ft | Each end of a culvert to be extended | Look; A Class I railroad's public projects requirements |
| Pipeline crossing | One each side of the track on the pipe centerline | Continuous sampling | A Class I railroad's pipeline occupancy specification |
| Yard or intermodal pavement | Grid over the paved area | Grid spacing is practice; denser under crane rails | EM 1110-1-1804, Table 2-4 (roads) |
| Slope failure | At least 3 borings or test pits on the critical section | Head scarp, middle and toe | Look, Table 1.8 |
| Subgrade failure or mud boil | 2 to 4 borings straddling the failure | Add test pits or trenches across the track | Practice |
Section 3.9.5.3 gives the full criteria, depths and the planner calculator.
Milepost referencing: All boring locations must be described in terms of railroad mileposts and offset from track centerline (in feet, left or right, looking in the direction of increasing milepost). GPS coordinates (NAD 83, decimal degrees or State Plane in feet) are required in addition to milepost references. Railroad mileposts are the primary location reference for all railroad engineering documents.
New alignments and major culvert or bridge replacements increasingly include wildlife passage as a permit condition. The FHWA Wildlife Crossing Structure Handbook gives recommended dimensions for eleven crossing types (overpasses, open-span bridges, large culverts, etc.); most overpasses are under 230–260 ft long, but landscape bridges spanning roads and a railway can be much longer. When a crossing structure is in the scope, add borings at both abutments/footings of the wildlife structure and at the approach fills, and confirm the clear-opening dimensions with the environmental permit before setting foundation boring depths.

Source: Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003
No new line can be designed correctly or built economically unless the soils and hydrogeology along the route are known in detail. Profillidis lists what the investigation must establish:
Because investigation is costly, run it in stages: assemble existing information; reconnaissance (geologic and topographic maps, aerial photos, water and oil well logs, hydrologic data, state soil manuals); a preliminary site investigation with a few borings or test pits to establish stratification, soil types and groundwater; then the detailed investigation. The program should yield strength, deformation and hydraulic properties at the least cost. Techniques fall into geophysical (seismic, magnetic, gravimetric, resistivity), physical (borings, test pits), mechanical (pressuremeter, penetrometer, laboratory) and hydrogeological (piezometers) methods.


After Profillidis (2014), §9.2.1–9.2.4. Full reference under Supplemental References.
Before the track structure is designed, the investigation along the alignment should establish, at a minimum:
Add borings, laboratory testing and analysis at bridges and other special structures. AREMA Chapter 1, Part 1 gives the base recommendations, and the spacing in Table 3.9-1 applies. Where chemical stabilization is under consideration in a frost area, include frost-susceptibility and freeze–thaw durability testing in the laboratory program.
After UFC 4-860-01FA (2004), ch. 6, §8b and §8e. Full reference under Supplemental References.
Do not judge the trackbed from the surface. Clean ballast at the surface may be only one particle thick. Selig and Waters recommend the following, in order of effort:
Depth. Traffic stress is significant to about 16 ft below the tie, and rail deflection 80 in. down is still about half the surface value. CPT for track-modulus back-analysis should reach at least 16 ft below the tie.
After Selig & Waters (1994), chs. 2, 5, 10, 14 and 16. Full reference under Supplemental References.
Boring depth must be sufficient to characterize all soil and rock materials that will influence the performance of the planned structure or earthwork. Minimum boring depths for each project type are set by the applicable stress influence criterion, the structure geometry, and the owner railroad's requirements.
For footings and other structures, Das gives the ASCE (1972) rule: the minimum boring depth is the smaller of D1, where the stress increase falls to 10% of the applied pressure, and D2, where it falls to 5% of the effective overburden stress. The rule is for structures, not embankments (Section 3.9.5.3.3). Using the 2:1 stress distribution approximation:
Where:
Minimum boring depth condition (ASCE 1972, in Das):
Where σ'_v₀ is the effective overburden stress at depth z (psf), computed as:
with γ' = effective unit weight (pcf), typically 55–65 pcf (buoyant) below the water table, or 100–125 pcf (total) above it.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Q | total applied load (lb) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| B | footing width or embankment base width (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| L | footing length or embankment base length (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| z | depth below the base of the loaded area (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| σ'v0 | vertical stress / pore pressure = γ' × z | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
| γ' | buoyant unit weight | Another equation | γ' = γsat − γw (γw = 62.4 pcf). Use below the water table. | 50–75 pcf for most mineral soils · by USCS group |
For a square footing with total applied stress q (psf) over area B²:
D1 has a closed form for a square footing; D2 does not, because σ'v0 grows with z. The investigation planner (Section 3.9.5.3) solves both.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| γ' | buoyant unit weight | Another equation | γ' = γsat − γw (γw = 62.4 pcf). Use below the water table. | 50–75 pcf for most mineral soils · by USCS group |
| Project Type | Minimum Boring Depth (ft) | Source |
|---|---|---|
| Track subgrade, new or existing | 10 to 15 ft below proposed grade; stop at rock or 5 ft into dense or very stiff soil | Li and others (2016) |
| Embankment fill | 0.5 to 2 times the fill height below original ground, and through compressible soil | Das (2010); Look, Table 1.8 |
| Cut slope | Top of cut: to 5 ft below the proposed ditch flowline; toe: 16 ft or 10 ft into rock, whichever is shallower | A Class I railroad's public projects requirements; Look |
| Bridge, spread footing | About 2 B below the base, and the ASCE stress depth; Look gives 4 B to 5 B | A Class I railroad's bridge requirements; Das; Look |
| Bridge, piles or shafts | 10 ft below the estimated tip, or 10 pile diameters in competent strata | A Class I railroad's bridge requirements; Look |
| Bridge pier in a waterway | Below the estimated scour depth as well as the foundation criterion | Scour estimate (FHWA HEC-18 methods) |
| Retaining wall | About 2 to 2.5 times the retained height for a cantilever soldier pile wall; into rock or a firm layer | Practice |
| Culvert | 2 B to 4 B below the invert, and below compressible soil | Look, Table 1.8 |
| Slope failure investigation | Below the slide zone: as a guide 2 times the slope height or the width of the moving zone | Look, Table 1.8 |
| Rock coring | About 10 ft into rock to prove it is not a boulder | Look, Table 1.8 |
Values not supported by the sources in the library were removed in the November 2026 fact check (Table 3.9-8).
The railroad's bridge investigation requirements (Ruel, 2003) follow AREMA and add practical limits: borings extend below the depth significantly affected by the loads, river scour or deep shear — about twice the anticipated spread-footing width, or 10 ft below the estimated pile tip from a preliminary static analysis. One boring can be sufficient for a short bridge replacement in uniform, well-mapped geology; where practical, drill at the toe of the embankment rather than on the track. A railroad Bridges & Structures representative accompanies the crew.
The railroad also asks the geotechnical engineer for: allowable pile load vs. depth for each pile type (typical working load about 160 kips for a 14-in. H-pile), DRIVEN static capacity (compression and uplift), GRLWEAP driving criteria and maximum blows/in., p–y curves, and a linear lateral spring constant K per stratum for pile deflection up to about ½ in. at the bridge seat — so SPT, strength and unit-weight data must be sufficient for LPILE input in every stratum.
Table 5-S2. Guideline to extent of investigation (Look, 2007, Table 1.8, abridged)
| Development | Test spacing | Approximate depth |
|---|---|---|
| Bridges | Each pier | 4B–5B for shallow footings; 10 pile diameters in competent strata; in bedrock, ≥ 10 ft of coring and 3 pile diameters below founding level (RQD > 50%, moderately weathered or better) |
| Buildings | 65–165 ft | 2B–4B for pads/strips; 10 ft or 3 diameters below pile toe |
| Embankments | 80–165 ft at critical areas; 330–1,650 ft elsewhere | Beyond base of compressible alluvium at critical or suspect areas |
Source: Ruel, M. and KRK (2003). General Requirements for Geotechnical Investigations for the railroad's Bridge Construction Projects and “A Practical Approach to Lateral Loading on Piles for Railroad Bridge Design on Class I railroad Projects.” a Class I railroad · Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis
No single code fixes how many borings a railroad project needs or how deep they go. The criteria in the library come from four kinds of source, and they do not all agree: a Class I railroad's own requirements (public projects, bridge foundations and pipeline occupancy), a railway geotechnics text that ties boring spacing along the track to soil strength (Li and others), general investigation guides (Look's Table 1.8, USACE EM 1110-1-1804 Table 2-4 and a short course on site investigation), and the stress rule for structures given by Das. This section sets them side by side, fact-checks the spacing and depth values used elsewhere in this manual against them, and gives the planner that applies them. Use the railroad's requirement as the minimum, then tighten spacing and extend depth for the ground: weak, variable or suspect soil governs over any table.
| Feature | Spacing or number | Source |
|---|---|---|
| Track corridor (new siding, second main, extension) | One boring every 500 ft in high-strength soil, 200 ft in medium, 100 ft in low-strength soil | Li and others (2016), Table 8.1 |
| Existing line, cut and fill (public projects) | A series of three borings (on the track grade at the shoulder, at midslope, and in the ditch at the toe) about every quarter mile (1,320 ft), sited to represent the prevailing cut or fill | A Class I railroad's public projects requirements |
| Embankments | 80 to 165 ft at critical or suspect areas; 330 ft or more elsewhere, as for roads | Look, Table 1.8 |
| Cut slopes | 80 to 165 ft where H exceeds 16 ft; 165 to 330 ft where H is under 16 ft | Look, Table 1.8 |
| Landslide or slope failure | At least three borings or test pits along the critical section | Look, Table 1.8 |
| Bridges | At each pier and abutment; one boring can be enough for a short bridge in uniform, mapped geology | Look, Table 1.8; EM 1110-1-1804, Table 2-4; a Class I railroad's bridge requirements |
| Culverts | Under 66 ft long: one; 66 to 130 ft: one at each end; longer: each end and between, at most 66 ft apart. A boring at each end of a culvert to be extended | Look, Table 1.8; a Class I railroad's public projects requirements |
| Pipeline crossing under track | One on each side of the track on the pipe centerline, as close to the track as practicable | A Class I railroad's pipeline occupancy specification |
| Retaining walls | At each wall; 50 to 100 ft along the wall line | A Class I railroad's public projects requirements (at each wall); spacing is practice |
| Light towers, signal masts, catenary poles | At each foundation | Look, Table 1.8 (monopoles and towers) |
| Roads and yard pavement | One per 490 ft of centerline for a two-lane road (245 ft multilane); a grid over yards (practice) | EM 1110-1-1804, Table 2-4 |
Look's metric values are converted (25 m = 82 ft, rounded to 80; 50 m = 165 ft). Spacing tightens wherever the ground changes between borings, and test pits, probes or geophysics can fill the gaps.
| Feature | Minimum depth | Extend when | Source |
|---|---|---|---|
| Track subgrade | 10 to 15 ft below proposed grade | Poor soil is known or suspected; stop at rock or 5 ft into dense or very stiff soil | Li and others (2016) |
| Embankment | 0.5 to 2 times the embankment height below original ground; beyond the base of compressible soil at critical areas | Soft, organic or compressible soil continues | Das (2010); Look, Table 1.8 |
| Cut slope | Cut height to 5 ft below the proposed ditch flowline (top-of-cut boring); 16 ft below the toe or 10 ft into rock, whichever is shallower | Water-bearing or weak layers below the cut | A Class I railroad's public projects requirements; Look, Table 1.8 |
| Landslide | Below the slide zone: as a guide 2 times the slope height or the width of the moving zone, and 16 ft below the toe or 10 ft into rock | The slip surface is not found | Look, Table 1.8 |
| Bridge, spread footings | About 2 B below the base (1.5 B to 2 B); Look gives 4 B to 5 B for bridge footings | Compressible layers within the stress zone; scour depth | A Class I railroad's bridge requirements; short course; Look, Table 1.8 |
| Bridge, piles or shafts | 10 ft below the estimated tip; 10 pile diameters in competent strata | Weak layer below the tip | A Class I railroad's bridge requirements; Look, Table 1.8 |
| Rock | About 10 ft of core, to show that rock is not a boulder; for bridge piles, 3 diameters below founding level | Voids, clay seams or weathered zones | Look, Table 1.8 |
| Culvert | 2 B to 4 B below the invert (B = span), and below compressible soil | High fill over soft ground | Look, Table 1.8 |
| Pipeline crossing | Continuous sampling to 5 ft below the proposed invert; rock cored | – | A Class I railroad's pipeline occupancy specification |
| Light tower or pole | 15 ft for poles up to 66 ft high, rising to about 49 ft for 230 to 260 ft towers; less in hard ground, 30% more in soft | Loose sand or soft clay | Look, Table 1.8 |
| Road or yard pavement | 10 ft below finished grade (6.5 ft below formation in Look) | Organic or soft fill continues | EM 1110-1-1804, Table 2-4; Look, Table 1.8 |
Every boring that ends in soft, organic or loose soil, uncontrolled fill, or rock that could be a boulder is extended, whatever the table says.
For footings and other structures, Das gives the rule recommended by the American Society of Civil Engineers (1972). Find the depth D1 at which the stress increase from the structure falls to 10% of the applied pressure, and the depth D2 at which it falls to 5% of the effective overburden stress. The approximate minimum boring depth is the smaller of the two. The short course gives the same picture from elastic theory: under a square footing the stress increase is about 15% of the applied pressure at 1.5 B and 10% at 2 B, but under a long strip it is still 40% and 30% at those depths, so strips need deeper borings.
Equation 3.9-3. ASCE (1972) boring depth rule, with the 2:1 stress distribution
z is measured below the footing base; σ'v0 is the effective overburden stress at that depth, with the buoyant unit weight below the water table.
The rule was written for buildings and does not work for embankments. Under a strip as wide as a railroad fill, D1 is about 9 times the base width, which is why Das gives a separate range for embankments (one-half to two times the height) and why this manual no longer applies the stress check to fills.
| Check | Source | Planner |
|---|---|---|
| Square footing, depth where Δσ = 10% of q | About 2 B (short course, elastic); 2.16 B (2:1 closed form) | 2.17 B (B = 10 ft, D1 = 21.7 ft) |
| Long strip, depth where Δσ = 10% of q | Well beyond 2 B (short course: 30% at 2 B); 9 B (2:1 closed form) | 8.9 B |
| Track corridor in medium soil, 6,500 ft | One boring every 200 ft (Li and others) | 34 borings, 510 ft |
| Culvert 150 ft long | Each end and between, at most 66 ft apart (Look) | 4 borings |
| Pipeline crossing, invert 9 ft below the track | Each side, to 5 ft below the invert (a Class I railroad's specification) | 2 borings to 14 ft, rounded to 15 ft |
| Earlier value | Where | Published criterion | Now |
|---|---|---|---|
| Track subgrade borings every 500 to 1,000 ft | Table 3.3-2 | 100 to 500 ft by soil strength (Li and others); quarter-mile series as a railroad minimum | 100 to 500 ft; quarter-mile series as the floor |
| New sidings: 3 borings up to 5,000 ft; 1 per 2,500 ft beyond | Table 3.9-1 | As above | Spacing by soil strength |
| Embankment over 10 ft: 1.5 times the base width deep | Section 3.9.5.2 | 0.5 to 2 times the height (Das) | 0.5 to 2 H, through compressible soil |
| Depth where Δσ = 10% of σ'v0 | Section 3.9.5.1 | Smaller of D1 (10% of q) and D2 (5% of σ'v0), for structures only (ASCE, in Das) | Equation 3.9-3 |
| Culvert: one diameter below the invert | Table 3.3-3 | 2 B to 4 B below the invert (Look) | 2 B to 4 B |
| Rock core 5 to 10 ft | Table 3.3-3 | About 10 ft (Look) | 10 ft |
| Pile-supported abutment: 20 ft below the tip | Section 3.9.5.2 | 10 ft below the tip (a Class I railroad's bridge requirements); 10 pile diameters (Look) | 10 ft or 10 diameters |
Slope repair. A 600-ft embankment repair with 20-ft slopes in medium-strength soil, with the railroad's three-boring series (shoulder, midslope and toe) at each station. At the 165-ft spacing Look gives for critical areas the planner places 5 stations and 15 borings: the shoulder borings go through the fill and one fill height below original ground (40 ft), the midslope and toe borings to 30 ft. That is 500 ft of drilling, about 6.1 days at 90 ft/day including half a day to set up, and a standby allowance of 24.5 hr at 3.5 hr/day.
New siding. A 6,500-ft siding on medium-strength soil needs about 34 borings at 200-ft spacing, each 15 ft deep (510 ft). The railroad's quarter-mile series would give 6 stations and 18 borings; the soil-strength spacing governs here, and the railroad minimum governs only in strong, uniform ground.
Bridge footing. A 10-ft-square pier footing with its base 6 ft deep, bearing 4,000 psf, groundwater at 10 ft: D1 = 21.7 ft and D2 = 38.8 ft below the base, so the stress rule gives 21.7 ft. The railroad's 2 B gives 20 ft. The planner takes the deeper, 21.7 ft, and adds the 6-ft embedment: borings about 30 ft deep at each support.
Open the investigation planner calculator →
Boring number, spacing and depth for eleven railroad features from the published criteria above, the ASCE stress check for footings, soil and core footage, drilling days and train standby.
These documents are in the reference library. Summaries are paraphrased and metric values converted to English units. Individual railroads are not named.
A new 4,800-ft siding needs a 12-ft fill. Boring depth for an embankment is often set with the stress rule written for structures, and the example shows why that gives an absurd answer for a wide fill, and what to use instead.
| Variable | Value | Description |
|---|---|---|
| H | 12 ft | Embankment height |
| γfill | 125 pcf | Compacted granular fill (assumed) |
| B | 80 ft | Base width; 2H:1V slopes, two tracks at 14-ft centers |
| γ | 118 pcf | Residual sandy clay |
| zw | 15 ft | Depth to water; γ′ = 55.6 pcf below it |
| Criteria | Section 3.9.5.3.3 | Stress rule (D1: Δσ = 10% q; D2: Δσ = 5% σ′v); embankment rules of Das (0.5 to 2H), Li et al. (10 to 15 ft) and Look (through compressible soil) |
The stress rule gives 162 ft, which no one would drill for a 12-ft fill. Take the centerline boring to about 25 ft below existing ground (2H) and extend it through any soft or compressible soil found.
The stress rule was written for structures with modest footprints; under an 80-ft-wide strip the stress decays so slowly that the rule runs to absurd depths. For embankments the published embankment criteria govern. Record the basis of the depth in the boring plan, so the reviewer sees it was chosen, not guessed.
A bridge replacement on a Class I railroad main line needs a new pile-supported abutment. Old borings show where the existing piles stopped, which is the best first guess at where the new ones will.
| Variable | Value | Description |
|---|---|---|
| Refusal (1962 borings) | 45 ft | Existing HP piles assumed to stop near here |
| New pile tip | 40 to 55 ft | Range for the new load |
| Rule | 20 ft below the estimated pile tip | Section 3.9.5.2 |
| Owner rule (assumed) | At least 20 ft into competent bearing material, or refusal, whichever is deeper | Confirm with the railroad’s engineer |
Drill to at least 75 ft, or 5 ft below the first refusal horizon, whichever is deeper.
Using the deep end of the tip range protects against a second mobilization if the design load pushes the piles deeper than the old ones. Refusal in 1962 may have been on a boulder or a hard layer over softer soil, so the new borings should core or sample through it rather than stop.
A first-pass boring count and footage for a new intermodal yard expansion, built up zone by zone. The total drives the drilling budget in Chapter 3.7.
| Variable | Value | Description |
|---|---|---|
| Footprint | 2,200 ft × 800 ft | Yard area |
| Cranes | 3 parallel crane rails, each 2,100 ft | Borings at 200-ft spacing, 65 ft deep (20 ft below a 45-ft pile tip) |
| Pavement | 20 acres | 1 boring per 2 acres, 20 ft deep |
| Building | 100 ft × 200 ft | 4 corners + center, 60 ft deep (piles assumed) |
| Other | Drainage, gate, utilities | 6 borings, 15 ft deep |
About 54 borings totaling 2,735 linear feet.
The crane rails take over three-quarters of the footage, because their pile foundations need deep borings at close spacing. That is where scope negotiation should focus: if the crane design allows 300-ft spacing, the count drops by about 10 borings and 650 ft.
Laboratory testing must be assigned during planning — not after borings are complete. The testing matrix is organized by project feature, governing design calculation, and required test data.
| Feature | Design Calculation | Required Tests | Typical Quantity |
|---|---|---|---|
| Track subgrade — embankment | Settlement, bearing capacity | MC, Atterberg limits, USCS classification, consolidation | 1 consolidation per soft layer identified |
| Track subgrade — cut | Slope stability, shrink/swell | MC, Atterberg limits, unconfined compression (q_u), direct shear | 2–3 q_u per cut |
| Bridge abutment — spread footing | Bearing capacity, settlement | MC, Atterberg limits, consolidation, unconfined compression | Full suite per 5 ft depth change in critical strata |
| Bridge abutment — pile | Skin friction, end bearing | MC, Atterberg limits, triaxial UU (φ, c), grain size | Per critical layer |
| Intermodal pavement | Pavement subgrade design | MC, Atterberg, CBR (ASTM D1883), M_r (AASHTO T 307) | 1 CBR per lift zone |
| Crane rail foundation | Settlement, bearing capacity | MC, Atterberg, consolidation, triaxial CU | Full suite per 10 ft in critical zone |
| Retaining wall | Earth pressure, stability | MC, Atterberg, direct shear (φ', c'), unit weight | 1 direct shear per soil unit |
| Slope stability | Shear strength | Triaxial CU + CD, direct shear (residual φ_r for existing landslides) | 3+ per failure surface soil unit |
| Ground improvement | Settlement after treatment | MC, Atterberg, consolidation, grain size for PVD drain design | Full suite per 5 ft in soft zone |
| Rock core (all structures) | Rock quality, bearing capacity | Point load (q_u conversion), core description (RQD), petrographic | 1 point load per 5 ft of core |


Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
BORING LOG — PROJECT: [Railroad] [Project Name] [Milepost]

Boring No.: B-1 Date Drilled: [Date] Sheet: 1 of 1
Location: STA 10+50 (MP 347.2 + 0.05 mi), 12 ft Right of CL, Looking Incr. MP
Ground Surface Elevation: 342.4 ft (NAVD 88) Drill Rig: CME-75 Track-Mounted
Drilling Method: Hollow Stem Auger (HSA) 3.25-in. ID Hammer: Auto SPT, 140 lb
Driller: [Name], Certified Class I railroad RWP Logger: [PE Name], PE
DEPTH SAMPLE BLOW DESCRIPTION
(ft) TYPE COUNT (USCS — ASTM D2488/D 2487)
----------------------------------------------------------------------
0-2 - - Fill: silty CLAY, gray-brown, soft, moist
(CL per USCS, AASHTO A-6)
2-5 SPT-1 3/5/7 CLAY, gray-brown, soft to medium, wet
N = 12 (field) MC = 38%
5-10 ST-1 - Shelby Tube (undisturbed sample for consolidation)
CLAY, gray, soft, wet; slight organic odor
MC = 44%, LL = 62, PI = 34 (CH)
10-15 SPT-3 2/4/4 CLAY, gray, soft; N₆₀ = 8; MC = 46%
15-20 SPT-4 4/5/6 CLAY, gray-tan, medium; N₆₀ = 11
20-25 SPT-5 6/8/10 CLAY, tan, medium-stiff; N₆₀ = 18
25-30 SPT-6 8/12/15 Transition to Sandy CLAY (SC); N₆₀ = 27
30-35 SPT-7 11/15/18 SAND, fine, silty, tan (SM); N₆₀ = 33
35-40 SPT-8 15/22/28 SAND, fine-medium, tan-gray (SP-SM); N₆₀ = 50
40 --- --- End of boring at 40 ft (No rock encountered)
Water Level: 6.2 ft below ground surface (measured 24 hr after drilling)
Casing: 3.25-in. HSA, pulled and abandoned
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Sample | Depth (ft) | USCS Symbol | LL | PL | PI | MC (%) | γ_t (pcf) | q_u (tsf) | Notes |
|---|---|---|---|---|---|---|---|---|---|
| SPT-1 | 2–4 | CL | 48 | 22 | 26 | 38 | 113 | — | Jar sample |
| ST-1 | 5–7 | CH | 62 | 28 | 34 | 44 | 108 | 0.42 | Consolidation test specimen |
| SPT-3 | 10–12 | CH | 64 | 29 | 35 | 46 | 107 | — | Jar sample |
| SPT-5 | 20–22 | CL | 42 | 20 | 22 | 29 | 117 | 0.78 | q_u by UUC |
| SPT-7 | 30–32 | SM | NP | NP | NP | 14 | 124 | — | Grain size analysis |
| SPT-8 | 35–37 | SP-SM | NP | NP | NP | 12 | 127 | — | Grain size analysis |
LL = Liquid Limit; PL = Plastic Limit; PI = Plasticity Index; MC = Natural Moisture Content; γ_t = Total Unit Weight; q_u = Unconfined Compressive Strength (UUC); NP = Non-Plastic



Checklist · Part V · Subsurface Exploration
Use this checklist to verify planning completeness before submitting the Investigation Plan memorandum to the railroad client for approval.
Reference graphics
Levy (2010) recommends that owners prequalify contractors through a request for qualifications (RFQ) before bidding. His RFQ checklist asks for, among other things, years in business and any former company names, current backlog, three years of revenue, the largest recent projects, bonding capacity and insurance limits, projects not completed and why, any debarment, an attached quality control program, an attached safety program, and reportable accidents and OSHA violations for the past year. He recommends requesting the past five-year safety record and workers’ compensation experience modification rate (EMR), treating a rate below 1.0 as acceptable, and noting that a poor record takes about three years to work off. He also suggests calling past owners beyond the references listed, and asking them for other owners to contact.
For testing and inspection, Levy advises that certain inspections be contracted directly by the owner so the firm is impartial and works only for the owner. His list starts with inspecting soils before foundations are placed, inspecting compaction, and load testing piles. The testing RFQ should describe the project and schedule, list the services required, give an order-of-magnitude scope so firms can price it, and request hourly rates by staff level (regular and overtime) and unit prices for estimated test quantities.
At the preconstruction conference, the owner’s team should confirm the notice-to-proceed date, introduce the day-to-day staff, set communication channels and meeting protocol, verify insurance certificates for the contractor and each subcontractor, set procedures for questions and proposed change orders, and set the deadline for a baseline schedule and its update interval.
For railroad work: Add these points to the investigation planning checklist: confirm that the drilling subcontractor has railroad right-of-way experience, current contractor right-of-entry insurance, a safety program addressing roadway worker protection, and an acceptable EMR and OSHA history; confirm the testing laboratory’s accreditation and that acceptance testing during construction is contracted so that it reports to the railroad. Hold a short kickoff with the railroad’s representative to fix track access procedures, flagging requests, and the schedule for boring logs and lab data.
Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 21–24, 28–29, 113–116. Summarized and paraphrased. Full reference under Supplemental References.
Cretu et al. treat risk identification as a short, facilitated, multidiscipline session. One to two hours is usually enough on an ordinary project. It is best run with a risk breakdown structure (RBS) as a checklist so that no category is skipped. Their construction RBS has seven top-level branches: design, environmental, real estate, economic, schedule, contracting and construction. Each branch breaks down into items such as design coordination, resource agency reviews, utility issues, impacts to existing operations and force majeure. The facilitator records every idea where the whole group can see it and holds back editing until later. The facilitator draws out risks with Socratic questions. One of the authors’ own examples is “Did we run into geotechnical problems at this location when the original foundations were installed?” A SWOT framing (internal strengths and weaknesses, external opportunities and threats) is offered as an alternative prompt.
The results go into a risk register with these fields: ID, RBS category, threat or opportunity, short title, description, trigger, probability (initially high >75%, medium ≈50%, low <25%), impact description, owner, response strategy and status. Each description should be specific, measurable, attributable, relevant and time-bound (SMART). The register is then vetted. Duplicates are merged, and many small related items, such as several minor geotechnical uncertainties, may be grouped into one risk for management. Black-swan events are noted, but they are not modeled. The authors’ list of workshop questions includes several on ground conditions: what geotechnical work has been done, what is assumed for cut/fill reuse and haul, what is assumed for stability of cuts and temporary support, and whether perched water or dewatering permits are involved.
For railroad work: Hold this session during investigation planning, before the boring layout is fixed. Add railroad-specific branches to the RBS: track access and work windows, flagging and protection, slow-order or traffic interruption exposure, signal and communication cable conflicts, and right-of-way or permit-to-enter limits. Then trace every high or medium geotechnical risk to a specific exploration, test or monitoring item in the scope, or record it as a risk the client accepts. The register then becomes the written basis for the scope and fee, and it carries forward into the report and the construction documents.
Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 237–244, 249–250. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Use this checklist to verify planning completeness before submitting the Investigation Plan memorandum to the railroad client for approval.
Desktop Review:
Boring Layout:
Laboratory Testing:
Health and Safety / ROW Access:

Client Communication:
Seeley explains how the civil engineering method of measurement (CESMM3, Class B) breaks a ground investigation into separately priced items, and why. Every group of test pits or borings generates at least two items: the number of holes and the aggregate depth. Costs that follow the number of holes (moving and setting up the rig at each location) are therefore kept apart from costs that follow footage. Further items cover depth in rock versus other material, hole support or backfill, samples by type and class, removal of obstructions (paid by the hour), and pumping (paid by the hour at a stated minimum extraction rate). Hand-dug pits are itemized separately because they cost more. The rate covers preparing and submitting records and results, but not their analysis, which is paid separately.
His sample bill (converted to US units) shows the pattern: 34 trial pits 10–16 ft deep with a minimum base area of about 24 ft², 446 ft of pit depth, 446 ft of backfill, 15 hours of obstruction removal and 30 hours of pumping at a minimum 35 gpm; 14 rotary core holes (4-in. minimum core), 367 ft of cored depth in holes 16–33 ft deep, 367 ft of grout backfill and 28 core boxes 10 ft long; 102 disturbed bag samples of at least 11 lb; and 56 thin-wall tube samples 4 in. × 24 in.
For railroad work: build the cost estimate and the scope of services the same way, so that a change in the number of borings or their depth reprices on its own rather than becoming a negotiation. Typical line items are: mobilization to the subdivision (fixed); moves between holes, priced per hole and split between hi-rail or on-track access and off-track access on the right-of-way; drilling footage in soil and rock in depth bands; coring footage; SPT and thin-wall tube samples counted separately; grouted abandonment per foot; standby hours for flagging delays or train traffic; and per-day items for flagging protection and roadway worker protection briefings where the railroad bills them. Keep laboratory testing and engineering analysis out of the field unit rates, as Class B does, so that adding borings at a growing slide does not quietly use up the analysis budget. A table set up like this also gives the client a clear, auditable invoice against the work authorization.
Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 80–81. Summarized and paraphrased. Full reference under Supplemental References.
A Class I railroad located in the Mississippi Delta plans a 6,500-ft siding on flat alluvial ground, built on a 6-ft fill with a 60-ft base. The railroad’s standard (assumed here) calls for one boring per 1,500 ft and a 25-ft minimum depth. The geotechnical engineer must set the number and depth of borings for the proposal and show whether the owner’s minimum or the published embankment criteria govern.
| Variable | Value | Description |
|---|---|---|
| L | 6,500 ft | Siding length |
| Spacing | 1 boring per 1,500 ft (owner minimum, assumed) | |
| Owner depth | 25 ft minimum (assumed) | |
| H, B | 6 ft; 60 ft | Fill height and base width |
| Soil | Silty clay and fine sand alluvium |
(a) 6 borings. (b) 12 to 15 ft from the embankment criteria. (c) The owner’s 25-ft minimum governs.
The published spacing guidance would call for about 34 borings, so the owner’s 1,500-ft spacing is a floor, not a target. Where the first borings show variable alluvium, add borings rather than defend the minimum.
A railroad bridge over a creek is being replaced, and the new spans will sit on drilled shafts socketed into rock. The only record at the site is a 1967 boring that found weathered granite at 18 ft and auger refusal at 22 ft. The engineer must specify how deep the new borings go and what rock data the coring must deliver for socket design.
| Variable | Value | Description |
|---|---|---|
| Rock | Weathered granite at 18 ft; refusal at 22 ft | 1967 boring log |
| Foundation | Drilled shafts | |
| Rule | At least 20 ft of core below the rock surface | Common practice for shaft sockets |
At least 42 ft, including 20 ft of NX or NQ core below the rock surface, logged for RQD, recovery, strength, weathering and jointing.
A common criterion before calling a horizon competent bearing is at least 10 ft of core with RQD of 50% or more and recovery of 80% or more. Refusal at 22 ft may be a boulder or a weathered zone, which is why coring, not refusal, defines the top of rock.
At 10:00 PM the railroad calls: a cut slope has failed onto a main track and it needs a geotechnical crew on site by 6:00 AM. Of the four available staff, two hold current roadway worker protection certificates and two let theirs lapse four months ago. The project manager must decide who can go onto the right-of-way and how to staff the response.
| Variable | Value | Description |
|---|---|---|
| Crew | 4; 2 with current RWP, 2 expired 4 months ago | |
| Deadline | On site by 6:00 AM; now 10:00 PM | |
| Rule | Each person who enters the right-of-way must hold a current certificate | Railroad RWP program |
No equation is needed; the answer follows from the criteria listed under Given.
No. Only the two staff with current certificates may enter the right-of-way. They mobilize now; the other two stay off the right-of-way.
Contact the railroad’s RWP training coordinator about any emergency provision, enroll the two in the next class, and record in the project file how the crew was deployed. A certificate should never be allowed to lapse during an active contract; track expiry dates with the project schedule.
A Class I railroad is adding a second main track by widening a 20-ft embankment 12 ft on each side and raising it 4 ft. Existing borings are on the centerline only and reach 45 ft. Before the scope is priced, the engineer must decide whether borings are needed outside the existing toe and, if so, where they should go.
| Variable | Value | Description |
|---|---|---|
| H | 20 ft existing; 4-ft raise | Embankment |
| Widening | 12 ft each side | |
| Existing toe | About 60 ft from centerline | New toe about 72 ft out |
| Borings | Centerline to 45 ft | Existing data |
| Rule | Critical slip surfaces extend about 0.5H to 1.0H beyond the toe | Section 6.3 |
Yes. Place borings about 20 to 30 ft beyond the new toe, roughly 80 to 100 ft from centerline.
The centerline borings describe soil that has carried the embankment for decades and has consolidated under it; the soil under the widening has not. The stability of the widened slope depends on that unloaded soil, so without borings there the factor of safety is undocumented (AREMA Chapter 1, Part 1).
A signal bridge on a passenger corridor operated at FRA Class 7 (125 mph) is to be replaced. The engineer has scoped many freight bridge investigations on Class 4 track but none on a high-speed line. Before writing the work plan, the engineer must identify what makes this investigation different and list the planning requirements that follow.
| Variable | Value | Description |
|---|---|---|
| Track | FRA Class 7, 125 mph | 49 CFR 213, Subpart G |
| Work | Signal bridge replacement | |
| Comparison | Class 4 freight bridge |
No equation is needed; the answer follows from the criteria listed under Given.
The five are: short track possessions, Class 7 geometry tolerances, formal owner peer review, signal circuit clearance, and catenary electrical clearance.
The tolerances drive the technical scope: settlement predictions compared with a 1-in. limit usually need consolidation tests on every soft layer, not only the worst one. The other four drive cost and schedule and belong in the investigation plan memorandum before a price is given.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Related Topic | Chapter |
|---|---|
| SPT corrections, sampling methods, boring log format | Chapter 4.1 |
| CPT, VST, PMT, and geophysical methods for site characterization | Chapter 5.1 |
| Soil and rock classification — USCS, AASHTO, AREMA MRE Ch. 1 categories | Chapter 2.2 |
| Groundwater characterization, piezometers, permeability testing | Chapter 2.8 |
| Bearing capacity calculations — Cooper E-80 loading, AREMA MRE Ch. 8 | Chapter 6.1 |
| Settlement analysis — consolidation, time rate, FRA and client geometry tolerances | Chapter 6.2 |
| Slope stability — AREMA MRE Ch. 1 embankment design; USACE EM 1110-2-1902 | Chapter 6.3 |
| Ground improvement — PVD spacing, preloading, schedule implications | Chapter 7.2 |
| Report preparation — investigation plan format per client requirements | Chapter 8.4 |
| Lab testing program — test standards, minimum quantities, acceptance criteria | Chapter 5.2 |
Table 1.0-3: Emergency Response Contact Structure by Railroad Client (completed)

These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.
We establish and document these contact chains at the beginning of every PSA engagement — not when the emergency occurs. The geotechnical firm's project manager and the on-call geotechnical engineer must have direct mobile phone numbers for every contact in the chain. We verify these contacts annually and update them when railroad personnel change roles.
The following timeline applies to all railroad emergency geotechnical response, regardless of client. Individual client protocols may require faster response on specific corridors or for specific event types.
Hour 0 — Notification Received:
Hour 0–4 — Mobilization and Site Arrival:
Hour 1–4 — First Professional Recommendation:
Day 1–5 — Emergency Investigation:
Month 1–6 — Permanent Repair:
We use the following framework when formulating emergency repair recommendations. Recommendations must be tailored to the specific conditions observed; this table provides starting points, not substitutes for engineering judgment.
| Failure Type | AREMA MRE Reference | Typical Emergency Repair Approach |
|---|---|---|
| Shallow slope failure (H < 10 ft) | MRE Ch. 1, Section 1.4.3 (Maintenance of Earth Slopes) | Slope regrading to stable angle; rock buttress at toe; surface drainage improvement; erosion control blanket |
| Deep slope failure (H > 10 ft) | MRE Ch. 1, Section 1.4.3; MRE Ch. 8, Part 5 (Retaining Walls) | Staged material removal; soldier pile wall; concrete block or gabion buttress; soil nail wall with geogrid facing |
| Embankment settlement or sinkhole | MRE Ch. 1, Section 1.4.1 (Maintenance of Roadbed) | Compaction grouting; flowable fill void filling; temporary timber cribbing or bridging between ties |
| Bridge scour — abutment or pier | MRE Ch. 1, Part 3 (Natural Waterways); FHWA HEC-23 | Emergency riprap placement; geotextile bag placement; temporary sheet pile or H-pile; flow diversion |
| Subgrade failure or mud boil | MRE Ch. 1, Section 1.4.1 (Maintenance of Roadbed) | Undercutting and replacement with granular fill; ballast injection; geotextile/geogrid installation under ballast |
| Retaining wall distress | MRE Ch. 8, Part 5 (Retaining Walls, Abutments and Piers) | Temporary rock buttress at wall base; sheet pile wall parallel to track; soil anchor installation |

Hutchings summarizes research on scheduled overtime. In the first few weeks, total output per worker rises, though not in proportion to the added hours. After about 7 to 9 consecutive 50- or 60-hour weeks, weekly output falls to roughly what the same crew produces in a 40-hour week. After about eight more weeks, the losses cancel the early gains, so the whole overtime period produces no more work, and possibly less, than a normal schedule would have. Combined with premium pay, the productive value per wage dollar after several weeks drops below about 75% for five 10-hour days, below about 62% for six 10-hour days and below about 40% for seven 12-hour days. Productivity per hour recovers sharply when the crew returns to a 40-hour week. In his example claim on a public works job, lost labor productivity (about $2.4 million) was the largest single component of a total claim of about $7.4 million.
He distinguishes directed acceleration, where the owner orders the work sped up, from constructive acceleration. The latter requires an excusable delay, a request for an extension, refusal of the request, an order to finish on the original date anyway, and actual acceleration by the contractor. When a contractor is simply behind, he advises against an acceleration order. Instead, give written notice that the contract date will be enforced and ask for a revised schedule showing how the contractor will meet it. Means and methods, and responsibility for them, then stay with the contractor.
For railroad work: round-the-clock effort is appropriate in the first days of a slide or washout response, when restoring service drives every decision. Once the response becomes a permanent repair lasting weeks, plan for a sustainable pace: rotating crews, a defined second shift, or more equipment, rather than the same people working seven 12-hour days. Fatigue affects geotechnical observers as much as operators. Missed seepage, tension cracks or compaction problems late in a long shift carry a real cost. When the railroad sets a restoration date that cannot be met at normal production, record the instruction, any request for more time and the response, because those records determine later whether the extra cost was acceleration or part of the original scope.
Source: Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc., pp. 273–277. Summarized and paraphrased. Full reference under Supplemental References.
Technical quality is necessary but not sufficient for a successful railroad geotechnical practice. How we communicate — the speed, format, and clarity of our client communications — determines whether the railroad can actually use our work in their decision process. Different railroad clients have different communication cultures; we adapt to each.
When we encounter a significant finding in the field — an unexpected organic layer at a structure location, rock at a depth that contradicts a prior boring, artesian groundwater conditions, or a condition that materially changes the geotechnical risk picture — we communicate it to the railroad project manager the same day, not in the formal report.
Routing findings to the owner railroad: Railroads differ in how field findings should reach them. Some expect a short, direct email to the Division Engineer or Roadmaster (three to five sentences: what was found, at what depth and location, what it means for the project, and what we recommend next). Others route findings through a designated project engineer or project manager, who passes them to track, structures or environmental reviewers, and prefer a formal preliminary memorandum for significant findings. Large networks often assign findings to a regional or division engineer for the territory rather than a central contact. Passenger railroads also need findings that affect train operations sent to operations management. On short lines, the subsidiary's general manager often needs to be copied, because track restrictions, crew deployments and customer notices are decided there. Confirm the communication chain at project initiation and record it in the project plan.
At the end of each day of field investigation work, we send a brief daily summary to the railroad project manager. This is non-negotiable professional practice on all railroad geotechnical programs, regardless of whether the client has specifically requested it. The daily summary is a single paragraph or a short bulleted list containing:
The daily summary is not a formal document and does not carry a PE seal. It is a professional service communication that keeps the client informed and demonstrates that our investigation is progressing as planned.
We notify the railroad project manager by email when we reach 75% of the not-to-exceed (NTE) budget on any task order. The notification states: the current budget, the amount expended to date, the work remaining, our current estimate of total cost at completion, and our recommendation for how to proceed — either confirm that remaining work will be completed within the current NTE, or request authorization to increase the NTE.
We do not wait for the client to ask about budget status. We do not complete work beyond the NTE without prior written authorization. These are fundamental PSA disciplines that the railroad client's accounts payable and capital program management departments enforce regardless of how important the additional work is technically.
The CIOB Code defines change broadly: anything that affects the scope or brief, cost (including whole-life cost), time milestones, risk allocation, the working of the team, or any project process. It sets out a single route for every change:

Supporting tools:
The Code stresses that controlling change during design is far more effective than during construction, and that time is often more expensive than the material change itself.
For railroad work: On consulting assignments for a railroad, agree at the kick-off:
Keep a simple change register on the project. Log each scope change (a new boring offset because of a signal cable, a CPT replaced by a boring because of refusal, an added cross-section after a new tension crack) with its cost and schedule effect. Send the register with each progress report. The railroad then sees the cumulative effect before the invoice does.
Source: Chartered Institute of Building (2014). Code of Practice for Project Management for Construction and Development, 5th ed. Chichester, UK: John Wiley & Sons, pp. 184–186, 236–238. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.
All boring logs must be delivered in both signed-and-sealed PDF and the native project file format (gINT project file, Log*Plot project file). Electronic data files allow the railroad's engineering team and future consultants to access and extend the boring database without re-entering data — a significant long-term value that distinguishes a professional deliverable from a mere PDF.
Physical sample and core retention requirements vary by client. The following represents minimum standards; client-specific requirements in the task order govern when they differ from these minimums:
These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.

Core photography requirement: All rock core must be photographed in boxes before disposal, regardless of retention period. Core photographs, stored as high-resolution JPEG files with metadata tags identifying project, boring number, box number, and depth range, must be delivered to the railroad client at project closeout and retained in our project archive indefinitely.
Every signed-and-sealed geotechnical deliverable for any railroad client is subject to independent peer review before issuance. The standard for "independent" is clear: the reviewer had no involvement in the investigation, analysis, or previous drafts of the document being reviewed.
| Deliverable | Minimum Reviewer Qualification | Review Level Required | Pre-issuance Client Review |
|---|---|---|---|
| Desktop Review Memorandum | Senior PE, same firm acceptable | Internal QC check | Not required |
| Assessment Report | Senior PE, same firm acceptable | Internal QC check | Not required |
| Reconnaissance Report | Senior PE, same firm acceptable | Internal QC check | Not required |
| Preliminary Geotechnical Report | Independent PE, 10 yr railroad GT experience | Full independent review | Recommended |
| 30% Geotechnical Design Memo | Independent PE, 10 yr railroad GT experience | Full independent review; signed seal required | Required — railroad engineering Dept. |
| 60% Geotechnical Design Report | Independent PE, 10 yr railroad GT experience | Full independent review; signed seal required | Required — railroad engineering Dept. |
| 100% Final Geotechnical Report | Independent PE, 10 yr railroad GT experience | Full independent review; signed seal required | Required — railroad engineering approval |
| Emergency Phase 2 Letter Report | Senior PE, same firm acceptable | Review within 24 hours of issue | Notify only; no formal approval |
| Permanent Emergency Repair Report | Independent PE, 10 yr railroad GT experience | Full independent review | Required — railroad engineering Dept. |
Client-specific peer review considerations:
ASCE (2012) defines peer review as an independent assessment by experienced professionals who have not worked on the project or organization being reviewed. It distinguishes organizational reviews (how faithfully a firm or agency follows its own policies; usually confidential and often oral) from project reviews, which examine the technical results of a project at its current stage and are reported in writing. Peer reviewers are advisory; they identify gaps and do not direct changes, and the original engineer keeps full legal responsibility. A peer review is also not value engineering: VE asks whether the right overall solution has been chosen, while design peer review asks whether the chosen solution is engineered correctly.
The Manual lists circumstances that suggest a project review: a project larger or more complex than the team usually handles; new technology; difficulties on similar past projects; changed objectives or disputes; many offices or organizations; a fast-track schedule; limited budgets; staffing concerns or recent departure of key people; large potential liability or unusual public risk; uncertain status of work to date; and special environmental concerns. Typical scope items are design assumptions and criteria, applicable codes, spot-checks of calculations, clarity and completeness of reports, alternatives considered, judgment, constructability, proposed construction means and methods, and prospects of meeting objectives.
The process has six steps: request, scoping, reviewer selection, preliminary document review, on-site document review and confidential interviews, and reporting, followed by follow-up actions with measurable goals. Reviews held at earlier milestones usually yield more benefit than a review only at final design. A project review report typically covers scope and limits, schedule and status, phase reviewed, needed corrective actions, and issues for further evaluation. The EJCDC publishes a standard agreement for independent project peer review.
For railroad work: Several of the Manual’s triggers are common on railroad ground-hazard projects: emergency slide repairs designed on a compressed schedule, novel stabilization methods, high consequence of failure under traffic, and work spread across several offices. For such deliverables, set the peer review scope at the concept stage (failure mechanism, design parameters, analysis method) rather than only at final plans, and keep reviewer comments and their disposition in the project file.
Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 213–222. Summarized and paraphrased. Full reference under Supplemental References.
| Phase | Class I Freight | Passenger | Short-line Short Line / Regional |
|---|---|---|---|
| Desktop Review | Required — all projects | Required — all projects | Required — recommended even for small projects |
| Assessment | Required if no prior data | Required — all projects | Required — client often has minimal prior data |
| Reconnaissance | Required for new alignments and facilities | Required — all projects | May combine with design investigation |
| Study / Prelim. Eng. | Required for new facilities; alternatives analysis | Required — all projects | Grant-funded projects require study level |
| 30% Design | Required | Required — owner railroad's process governs | Required |
| 60% Design | Required | Required — owner railroad's process governs | Required |
| 100% Design | Required | Required — owner railroad's process governs | Required |
| Construction Services | Required on significant capital; recommended on all | Required — continuous inspection on passenger corridor | Required on embankment and structure work |
The course presents the statement of work (SOW) as the document that defines scope, sets the customer’s expectations and can serve as the contract. A good SOW answers: what the purpose is and why the project is being done; who the immediate customer and the end user are; what the deliverables are and what support they need; and what the budget, final date, success measures, customer support and contingency plans are. Its generic contents are:
For railroad work: a culvert replacement investigation SOW might be built as follows (values illustrative):
Writing the client’s obligations into the SOW makes them visible when the schedule slips for reasons outside the consultant’s control.
Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 26–35. Summarized and paraphrased. Full reference under Supplemental References.
Oberlender calls the work breakdown structure (WBS) the cornerstone of the work plan: to manage the whole project, you manage each of its parts. The WBS divides a project into levels (major facilities, sub-facilities, work items, tasks), and the lowest level is the work package, defined well enough to be measured, budgeted, scheduled and controlled. Code numbers link each package to the organizational breakdown structure (who does it), the cost breakdown structure (which account pays for it) and the CPM schedule (when it happens).

His procedure for building the plan:

The “not included / performed by others” lines on the work package are what prevent the same work from being done twice, or not at all.
For railroad work: A typical geotechnical scope breaks down cleanly. Level I covers desktop review, field exploration, laboratory testing, analysis, and reporting/GSPs. Level II splits field exploration into utility locates and railroad permits, flagging requests, drilling, in situ testing, and piezometer installation. Write a work package for each discipline lead and subconsultant (driller, lab, surveyor). Spell out in each package who requests and pays for flagging, who obtains right-of-entry, and who supplies track charts and as-built drawings. Hold the kick-off before the first track-time request, so that the two-week package return lines up with the railroad’s advance notice for work windows.
Source: Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill, pp. 99–115. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
From an international benchmarking study, Kelly, Male and Graham identify standard value opportunity points where a value study can be inserted in the project life cycle. These are a strategic briefing study (why invest, why now, for what purpose), a project briefing study (translating the business need into performance requirements), a concept design workshop, a detail design workshop and an operations workshop; a single charrette can take the place of some of the early studies. Each study has three phases. The orientation and diagnostic phase covers interviews, document review and a site tour. The workshop phase is typically half a day to a day within a four- to seven-day effort for a strategic study. The implementation phase, which the benchmarking found to be the most common point of failure, requires a named action plan. Their lever of value makes the timing point: effort spent at the strategy and objectives stages moves value far more than the same effort at the design or operations stage, and by final design the project’s value system is effectively locked. Two simple workshop tools support this. A time–cost–quality triangle has the team place one dot showing which of the three governs. A risk ranking from A to F combines high or low probability with consequence levels of “blocking force,” “turbulence” and “noise”; A–C risks go forward to analysis automatically.

For railroad work: Map these points onto the scope-of-services matrix. A short value and risk session at the concept or alternatives stage, before the boring program and the remedy type are fixed, is where the geotechnical engineer has the most leverage. It is the point to question whether the slide needs a wall or a drainage-and-buttress fix, or whether a culvert should be lined or replaced. Use the time–cost–quality dot to record whether track time or capital cost governs. On emergency slide work it is almost always time. On planned subgrade programs, cost and long-term performance often govern. Record the answer in the scope so that later choices about investigation depth and remedy are judged against the same priorities.
Source: Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science, pp. 102–109, 173, 299–302, 307. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Rad treats an estimate as a forecast whose accuracy depends on how much is known about the project. Late in a project, with full information, estimates are seldom better than about ±3–4%. At inception, with little project-specific data, an order-of-magnitude estimate may end anywhere from about 30% to 330% of final cost. He cites professional-society guidance that the first formal published estimate should be within −40%/+100%. On that basis, a $100 estimate implies a final cost between $60 and $200.
The cheapest point to change a project comes early, while uncertainty is still high. Estimates refine progressively down the WBS: level 0 first, then level 1, and so on. Each refinement is an enhancement of the original estimate, not a new one, which makes variances easier to explain.

He separates three kinds of money that are often combined:
For early estimates he recommends range estimating. Each element gets optimistic, most-likely and pessimistic values, combined as (O + 4M + P)/6. In his example, values of 5, 8 and 35 give 12, not 8. This shows how a single-point “most likely” figure sits close to the optimistic end when the downside is long. When single-point estimates are rolled up they tend to understate cost, because estimators are optimistic.
For railroad work: The scope-of-services matrix should label each phase’s construction cost opinion with its expected accuracy, so that a desktop-stage figure for a slide repair is not taken as a budget. Carry contingency for geotechnical uncertainty, such as undercut depth, rock, groundwater and slide limits, separately from any railroad-held reserve for scope growth, for example added track miles or a changed alignment. Where data are sparse, give three-point ranges for the dominant quantities. As borings and lab results come in, reduce the contingency and record why it was reduced.
Source: Rad, P. F. (2002). Project Estimating and Cost Management. Vienna, VA: Management Concepts, pp. 43–49, 62–64, 111–112. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Q1. You are providing geotechnical services to the railroad's project manager for a new intermodal yard expansion in the Texas Gulf Coast region. Your investigation reveals a 12-ft-thick soft marine clay deposit at 15 to 27 ft depth. Your consolidation test results show C_c = 0.72 and c_v = 4.8 ft²/year. The railroad's project manager tells you that the crane rail foundations must be ready for concrete placement in 16 months. Which owner railroad provisions govern your response, and what is your professional obligation to the project manager before the formal report is issued?
A: The governing documents are the owner railroad's structures standards for crane rail foundation design, supplemented by AREMA MRE Chapter 8 for foundation bearing capacity and settlement criteria. The governing performance criterion for crane rail differential settlement is contained in the railroad's intermodal facility design guidance, which specifies maximum differential rail settlement of ¼ in. per 50 ft — a tolerance far tighter than standard embankment subgrade requirements.
Our professional obligation to the railroad's project manager before the formal report is issued: Communicate the settlement timeline problem immediately — within 48 hours of receiving the consolidation test results. The calculation is straightforward: 90% primary consolidation of a 12-ft layer (single drainage assumed) with c_v = 4.8 ft²/year occurs at t₉₀ = 0.848 × H_dr² / c_v = 0.848 × 144 / 4.8 = 25.4 years without treatment. Even with PVD drains at 4-ft triangular spacing, achieving 90% consolidation in 16 months requires that surcharge loading must begin within weeks, not months, of our report issuance. We issue a preliminary technical memorandum — not a formal report — within 48 hours of receiving the consolidation data, clearly stating the schedule implication and recommending an immediate scope addition for a ground improvement feasibility study. We copy the railroad's Division Engineer and the railroad's Capital Engineering project manager.
Q2. A short-line subsidiary railroad in Louisiana is pursuing FRA CRISI grant funding for a 12,000-ft new siding on their network. The short-line corporate engineering group asks your firm to develop the geotechnical investigation scope. The subsidiary's General Manager suggests that the railroad's prior inspection of the alignment is sufficient and no borings are needed. Explain your response, referencing applicable standards.
A: We respectfully decline to endorse a scope that eliminates borings for a 12,000-ft new siding on an FRA CRISI grant-funded project. Our response to the General Manager, coordinated through the short-line corporate engineering group, covers three points:
First, regulatory requirement: FRA CRISI grant funding requires that design be supported by site-specific subsurface investigation meeting applicable professional engineering standards. AREMA MRE Chapter 1, Part 2 (Section 3.10) bases subballast design on the subgrade's strength and gradation, so subgrade quality must be measured before blanket thickness and compaction requirements can be set. A visual inspection does not produce the quantitative data required by AREMA MRE or by the FRA grant program's technical standards.
Second, professional liability: Signing a geotechnical report that supports a design without performing a defensible investigation creates direct professional liability for the engineer of record. If the siding subgrade fails after construction — due to soft soils, high water table, or organic deposits that a visual inspection would not detect — the geotechnical consultant and the short-line railroad share liability for the design deficiency.
Third, practical cost argument: The cost of a minimum reconnaissance investigation for a 12,000-ft siding — approximately $60,000 to $90,000 — is 0.5 to 0.75% of a typical siding construction cost of $12 million to $15 million. Discovery of soft soils requiring ground improvement during construction routinely costs $500,000 to $1,500,000 in change orders. The investigation is not an optional expense; it is risk management that the FRA grant program explicitly expects.
Q3. Your firm holds a PSA with a Class I railroad and is executing a task order for a bridge replacement investigation on a Class I railroad subdivision. The 60% GDR is 80% complete when the railroad issues a revised edition of its engineering standards. The revision changes the minimum pile embedment depth requirement for the pile type you have already designed. What are your obligations, and what do you tell the client?
A: We notify the railroad's project manager immediately — the same day we learn of the revised edition — that a revision has been issued that affects our current design. We do not complete and issue the 60% GDR under the superseded standard without first confirming with the railroad's engineering group how to proceed.
Our specific obligations: (1) Obtain the revised standards from the railroad; confirm which edition and effective date apply to this project. (2) Review our pile embedment calculations against the new minimum depth requirement. If our calculations already meet or exceed the new minimum, document that compliance explicitly in the revised 60% GDR and reference the new edition. (3) If our calculated pile embedment is less than the new minimum, we must revise our pile design recommendations before issuing the 60% GDR — we cannot issue a document that we know conflicts with the current version of the applicable standard. (4) If the revised minimum depth requires additional borings to confirm competent material at the new depth, we prepare a supplemental boring scope for Class I railroad authorization before proceeding.
We tell the client: directly, transparently, and without delay. We do not quietly revise the document and hope the client does not notice which edition of the standards we applied. Professional integrity and our PSA obligation require full transparency about standards changes that affect our work.
Q4. You are providing emergency geotechnical response to a Class I railroad for a slope failure at milepost 347.2 on the Class I railroad Southern subdivision. After your site assessment, you determine that the failure is a shallow rotational failure with H = 8 ft, and the slope is currently stabilized with no active movement observed. Track geometry indicates a surface deviation of 1.8 in. over 31 ft at the slide location. The current Class I track classification is Class 4 freight at 60 mph. What is your track restriction recommendation, and what is your technical basis?
A: FRA Track Safety Standards (49 CFR 213.63) limit the deviation from uniform profile at the mid-ordinate of a 62-ft chord to 2 in. on Class 4 track and 2¾ in. on Class 2. A deviation measured on a 31-ft chord cannot be scaled to the 62-ft chord, so have the track inspector measure it on the 62-ft chord. Whether or not it exceeds the Class 4 limit, a 1.8-in. deviation at a slide shows that the failure has reached the track, so we apply engineering judgment.
Our recommendation: Reduce operating speed to 25 mph (Class 2 restriction) over the affected 300-ft zone while emergency investigation and repair proceed. Technical basis: (1) The 1.8-in. surface deviation indicates the failure has affected the track structure, justifying an operational restriction. (2) The slope is currently stabilized with no active movement, justifying a slow order rather than a full closure. (3) Class 2 at 25 mph reduces dynamic wheel loads (DLF from ~1.4 to ~1.15), reducing the cyclic stress on the unstable subgrade by approximately 20%, reducing risk of renewed movement while the emergency investigation is underway. (4) We specify the railroad's Roadmaster re-inspection every 12 hours until emergency repairs are in place.
We communicate this recommendation verbally to the railroad's Division Engineer during the site visit and follow up with a written email to the railroad's Division Engineer and Roadmaster within 2 hours of leaving the site, citing the FRA 49 CFR Part 213 surface deviation criteria and our AREMA MRE Chapter 1 slope stability assessment as the technical basis.
Q5. The railroad asks your firm to prepare a preliminary geotechnical report for a section of the passenger corridor between Baltimore and Philadelphia where recurring track geometry deviations have been observed in the passenger track geometry car data for three consecutive measurement runs. The track is designated Class 7 (125 mph passenger operations). You find organic clay at 8 to 18 ft depth in your borings with natural moisture content w_n = 78% and liquid limit LL = 82%. What criteria govern your settlement analysis, and what preliminary finding must you communicate to the railroad's project manager before the formal report is issued?
A: The governing criteria for this analysis are: the passenger railroad's track subgrade and earthwork standards for subgrade performance criteria; AREMA MRE Chapter 5 and 49 CFR Part 213 Subpart G for Class 7 track geometry tolerances (FRA deviation from zero crosslevel of 1 in. and profile deviation of 1 in. on a 62-ft chord, 49 CFR 213.331; the railroad's own limits may be tighter); and its bridge and structures standards for any settlement analysis at bridge approaches within the affected zone.
The organic clay condition (w_n/LL = 78/82 = 0.95 — natural moisture nearly at the liquid limit) indicates a soil at or near the liquid state with essentially zero effective stress margin. This material is under active consolidation and is the almost certain cause of the recurring track geometry deviations in the passenger geometry car data.
Preliminary finding to communicate to the railroad's project manager before the formal report: The preliminary finding is that the track geometry deviations are caused by ongoing primary consolidation settlement of a normally consolidated or lightly underconsolidated organic clay deposit at 8 to 18 ft depth. The settlement is ongoing — not a historical, completed event. Without intervention, the settlement will continue and the geometry deviations will worsen. For Class 7 passenger corridor operations with a cross-level tolerance of ½ in., the expected differential settlement rate — even if only 0.1 to 0.2 in. per year — will require more frequent maintenance surfacing than is sustainable for high-speed passenger operations on the passenger corridor. We communicate this finding in a preliminary technical memorandum within 48 hours of receiving the first laboratory test results, recommend that railroad engineering evaluate whether the current maintenance cycle is sustainable while geotechnical remediation options are evaluated, and request authorization to expand our investigation scope to include ground improvement feasibility assessment.
| Topic | Chapter |
|---|---|
| Investigation planning — boring layout, depths, AREMA MRE Chapter 1.1 compliance | Chapter 3.9 |
| Drilling, sampling, SPT corrections, boring logs in client-required formats | Chapter 4.1 |
| In situ testing — CPT, VST, PMT, MASW for soft ground characterization | Chapter 5.1 |
| Soil and rock classification — USCS, AASHTO, AREMA MRE Chapter 1.1 subgrade categories | Chapter 2.2 |
| Groundwater — piezometers, permeability, seepage, dewatering for construction | Chapter 2.8 |
| Bearing capacity — Cooper E-80 loading, spread footings, piles, drilled shafts per AREMA MRE Ch. 8 | Chapter 6.1 |
| Settlement — consolidation time rate; comparison to FRA and client geometry tolerances | Chapter 6.2 |
| Slope stability — AREMA MRE Chapter 1.1 embankment design, USACE EM 1110-2-1902 | Chapter 6.3 |
| Seismic hazard and liquefaction — ASCE 7 site class; CPT and SPT methods | Chapter 6.5 |
| Pavement subgrade — CBR, resilient modulus, AASHTO 1993 design for yard paving | Chapter 7.3 |
| Ground improvement — preloading, PVDs, stone columns, DSM; client schedule implications | Chapter 7.2 |
| Retaining structures — earth pressure, wall types, drainage; AREMA MRE Chapter 2.2 | Chapter 7.1 |
| Railroad track subgrade — AREMA MRE Chapter 1.1 loading, subgrade failure modes, ballast design | Chapter 2.3 |
| Construction monitoring — compaction acceptance, pile driving, instrumentation | Chapter 5.3 |
| Report preparation — format by client, GSPs | Chapter 8.4 |
| Laboratory testing program — test standards, testing plan, acceptance criteria | Chapter 5.2 |
Chapter 3.9 — Geotechnical Investigation Planning and Scope
Primary Source: USACE EM 1110-1-1804, Geotechnical Investigations, 1 January 2001; AREMA Manual for Railway Engineering (MRE), Chapter 1 — Roadway and Ballast; client-specific railroad engineering standards as cited.
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental References.
Related section: 3.9.1 Background — Why Planning is a Billable Deliverable
In this 1988 case a developer sold apartments “off the plan” on one site founded on high-level weathered rock (shallow footings, 4,200 psf allowable bearing). When a second lot of similar size came up across the road, less than 66 ft away, the developer duplicated the project and skipped a site investigation, citing “experience” from next door.
The second site sat over a buried alluvial channel. A backhoe test pit to 10 ft, then borings to 20 ft and 49 ft, showed rock dropping to about 39 ft with compressible alluvium above. Shallow foundations were no longer viable and piles were required. The added cost cancelled the project about three weeks after start, and every purchaser’s deposit was returned.
For railroad work: the same assumption appears when a siding, second main or bridge replacement is designed from borings taken for the adjacent structure. Ground can change completely within a few track lengths, especially where a line crosses a filled valley or old stream course. The cost of the investigation is small next to the cost of finding this out during construction.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §2.5, pp. 66–68. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 3.9.2 Desktop Review — The Essential First Step
A deep basement was designed from a seepage model built on in-situ permeability tests, particle-size estimates and a sensitivity check of upper-95% flow rates. Access limits put every boring and CPT outside the building footprint, so the model was effectively two-dimensional. Extraction wells in the middle of the site then pumped far more water than predicted, while flows at the corners stayed manageable. Undersized pumps cost construction time, because a pump of the right capacity is seldom an off-the-shelf item.
Wall type, toe level and an underlying gravel layer were all examined and none explained the flows. Forensic data-gathering did: historical records showed a creek crossing the middle of the site 150 years earlier, infilled in the late nineteenth century and left undeveloped for another 50 years. That paleochannel, filled with loose sand, was the governing feature. Additional borings in detailed design had hinted at local loose sand, but the preliminary parameters were carried forward with only “minor” adjustments.
Look’s lesson is that each model (geological, geotechnical, analytical, design, construction) inherits the errors of the one before it, and the construction model is two steps removed from the analysis. The geological model has to envelop the others.
For railroad work: old valuation maps, historical aerials and early topographic sheets belong in the desktop review for the same reason. Filled creeks, ponds and borrow pits under an embankment or a new structure are the features a two-dimensional boring line along the track will not find.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §1.7, pp. 28–30. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
An investigation ends with a number chosen for each property, and the scatter in the data is as important as the average. The FHWA's Evaluation of Soil and Rock Properties (GEC 5) sets out a three-step selection. First, judge the data and remove values that reflect disturbance or a different material. Second, estimate variability, either from the tests themselves, from published coefficients of variation (Duncan 2000), or from the three-sigma rule using the highest and lowest conceivable values. Third, test the design at the mean and at the mean minus one standard deviation. Duncan, Wright and Brandon carry this to the probability that the factor of safety is less than 1.0 by the Taylor series method. One railroad's investigation requirements ask for the same end product: design strength parameters for every layer, from borings placed off the track where possible, preferably at the embankment toe.
| Property | COV (%) | Property | COV (%) |
|---|---|---|---|
| Unit weight | 3 to 7 | Compression index | 10 to 37 |
| Effective friction angle | 2 to 13 | Preconsolidation stress | 10 to 35 |
| Undrained shear strength | 13 to 40 | Coefficient of consolidation | 33 to 68 |
| Undrained strength ratio | 5 to 15 | Hydraulic conductivity, saturated clay | 68 to 90 |
| SPT blow count | 15 to 45 | Electric CPT qc | 5 to 15 |
| Vane shear strength | 10 to 20 | Mechanical CPT qc | 15 to 37 |
Equation 3.9-4. Standard deviation, reliability index and probability of failure
σF = √Σ[(Fi+ − Fi−)/2]²; COVF = σF/FMLV
β = (FMLV − 1)/σF (normal); βLN = ln[FMLV/√(1 + COVF²)]/√ln(1 + COVF²) (lognormal)
Fi+ and Fi− come from rerunning the stability analysis (for example with the Chapter 6.3 Bishop calculator) with one parameter at a time raised and lowered by one standard deviation. The probabilities agree with Duncan, Wright and Brandon's Tables 13.5 and 13.6. At FMLV = 1.5 and COVF = 20%, the calculator gives 4.8% (normal) and 2.6% (lognormal), against the tabulated 4.8% and 3%. At 1.2 and 10%, it gives 4.8% and 3.8%, against 4.8% and 4%.
GEC 5's Piedmont example has a mean friction angle of 35.2°, a highest conceivable value of 53.8° and a lowest of 27.3°. The three-sigma rule gives s = 4.42, a COV of 12.5% (at the top of the published 2 to 13% range), and a mean minus one standard deviation of 30.78°. For an illustrative slope with FMLV = 1.5 and four uncertain parameters, the Taylor series gives COVF = 16.5% and a probability of failure of 2.18% (normal) or 0.84% (lognormal). The clay's undrained strength contributes most of the variance, so more strength testing of the clay is the investigation money best spent.
Open the design parameter reliability calculator →
Mean, standard deviation and COV from tests or the three-sigma rule, comparison with published COV ranges, mean minus one standard deviation, and probability of failure by the Taylor series method.
Duncan, Wright and Brandon show why a probability of failure can say more than a factor of safety. Two slope designs are compared. Design A has steep slopes, costs $100,000 for construction and land, and has Pf = 0.1. Design B has flatter slopes, costs $400,000, and has Pf = 0.01. If either failure would cost $5 million in primary and secondary consequences, the expected total cost is $100,000 + 0.1 × $5,000,000 = $600,000 for A and $400,000 + 0.01 × $5,000,000 = $450,000 for B. The design that costs more to build is cheaper overall. They also note that most people understand "1 chance in 10" against "1 chance in 100" more readily than 1.3 against 1.5. Putting a probability in front of an owner also makes clear that no factor of safety above 1.0 guarantees the slope will stand. The same arithmetic underlies the life-cycle comparison in Chapter 3.8.
| Design | Construction and land | Pf | Expected failure cost ($5 million consequence) | Expected total |
|---|---|---|---|---|
| A, steep slopes | $100,000 | 0.10 | $500,000 | $600,000 |
| B, flatter slopes | $400,000 | 0.01 | $50,000 | $450,000 |
The calculator's lognormal probabilities match Duncan, Wright and Brandon's Table 13.6, which is rounded, at the combinations below. Read across a row and the probability rises steeply with COVF. Reducing uncertainty through more testing can lower Pf as much as a higher factor of safety does.
| FMLV | COVF = 10% | COVF = 20% | COVF = 30% |
|---|---|---|---|
| 1.3 | 0.5% / 0.49% | 11% / 11.01% | 23% / 22.75% |
| 1.5 | 0.00% / 0.00% | 3% / 2.57% | 11% / 10.85% |
| 2.0 | 0.00% / 0.00% | 0.03% / 0.03% | 1.3% / 1.34% |
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.
Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.
Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.
Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.
File locations for these documents are listed under Supplemental References.
Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After UFC 4-860-01FA (2004)” draw on item S10 and are rewritten for railroad clients. Blocks marked “After Selig & Waters (1994)” summarize item S11 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S12 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.