3.8.24 Instability Ratings: Evidence That the Ground Is Moving

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.24 Instability Ratings: Evidence That the Ground Is Moving

The situational rating says what a site could do. The instability rating says what it has done and is doing: past failures and repairs, track geometry defects that keep coming back, and the cracks, bulges, seeps and voids that the engineer sees on the ground. Past movement is the best single predictor of future movement, and present movement is direct proof that the frequency index is high. The instability rating therefore governs the frequency index: it supplies the defect rating D that, with the geospatial frequency, sets the current frequency index (Table 3.8-11) at the desk and in the field.

The instability rating is assembled in two passes. The desk pass reads the railroad’s records and the public event and movement data (Section 3.8.24.1 to 3.8.24.3). The field pass is made by the EIC on site, in Blocks 2 and 3 of the report (Sections 3.8.24.4 and 3.8.24.5), and turns what is seen into the field frequency index (Section 3.8.24.6).

3.8.24.1 Instability Record

Continue the site history begun in Section 3.8.23.2, still oldest first, with the record of what has gone wrong:

  1. Instability record. Past slides, washouts, repairs, berms, riprap, drains and slow orders. Lidar hillshade often shows old scarps and lobes that never made it into the records, and InSAR, where available, shows whether the ground has moved since 2016.
  2. Defect record. Geometry exceptions (cross level, profile, alignment, warp) at the site, their frequency, and whether they return between surfacing cycles.
  3. Triggering events. Match the dates of failures and defects against rainfall, flood stage, snowmelt and freeze-thaw. A site that fails after every high-water event has a different driving mechanism, and a different fix, from one that fails after long wet spells. These matches also calibrate the H&H thresholds of Section 3.8.23.7.

3.8.24.2 Historic Instability (L6) and Defect History

The instability record is scored on one attribute, L6, using the same 1-to-5 convention as the situational attributes, and the defect history is scored as the defect rating D of Chapter 3.8.

Table 3.8-24. Instability attribute and defect rating
ItemScore 1 / no changeScore 3Score 5 / raise one levelMain sources
L6 Historic instabilityNo evidence of movementPast repair at the site, or mapped instability nearbyRepeated documented failure, a scarp visible in lidar, or measured movementRailroad records, lidar, landslide inventory, InSAR
Defect rating D1: no defects in the record and no indicators3: defects reported more than once but not returning between cycles, or indicators without progress5: defects returning within weeks of surfacing; standing slow order. 4: the same defect returns between surfacing cycles, or a slow order in the last 12 months (Table 3.8-10)Track geometry exception reports, slow order history, surfacing records

This table scores the defect rating at the desk from the records. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.

Scores of 2 and 4 for L6 are described in Table 3.8-76. Defects are scored as a separate rating rather than as an attribute because they are direct evidence that the ground is moving now; they outweigh what the terrain alone suggests, so they act on the frequency index through Table 3.8-11 instead of being diluted in the average.

3.8.24.3 Preliminary Frequency Index (Fp)

The preliminary frequency index combines the situational likelihood with the instability attribute. L6 carries a weight of 1 and is added to the weighted situational attributes:

L = [ Σ (wi · Li)i = 1 to 5 + L6 ] / [ Σ wi + 1 ]

Round L half up (2.5 becomes 3) to the nearest whole number, then bound it by the trigger rating to give the geospatial frequency Fg = the lesser of L and T (Equation 3.8-2). The preliminary frequency index Fp is read from Table 3.8-11 using Fg and the defect rating D scored from the railroad's records. The situational and instability contributions (LS, L6, L), T and D are kept separately so they can be seen, and printed, on the report.

Susceptibility is not activity. Fg comes mostly from susceptibility, while D describes activity. Without defects or indicators (D of 1 or 2), Fp cannot exceed Forming (3), however susceptible the site; a high Fg with no defects is a reason to visit early, not evidence that the ground is moving.

3.8.24.4 Field Indicators of Instability (Report Block 2)

On site, the instability rating is completed from what the ground and the track are showing. Block 2 of the report is a checklist of indicators, recorded separately for the left embankment, the track between the rails and the right embankment. The embankment lists are the same on both sides. The between-rails list records the track geometry defects and track structure symptoms that brought the engineer to the site.

Table 3.8-25. Field indicators of instability
Left and right embankmentBetween the rails
Upper slope bulge, tension crack or seepageReported cross level (measurement and frequency)
Mid-slope bulge, tension crack or seepageReported profile (measurement and frequency)
Lower slope bulge, tension crack or seepageReported alignment (measurement and frequency)
Standing water in ditch or at toe of slopeReported warp (measurement and frequency)
Obstruction in ditchFouled ballast or water between cribs
Culvert dry, obstructed or damagedTie shift
Water level higher than on the opposite sideVoids between cribs
ErosionShoulder narrower than 12 in.

Orient and walk the site. Stand on the track centerline facing up station (increasing milepost); the left embankment column is on your left and the right on your right, so “left” and “right” mean the same thing to everyone who reads the form. Walk each embankment from the top of slope to the toe, then check the ditch and toe, each culvert, the water level against the opposite embankment, and erosion. Between the rails, enter each reported defect with its measurement (the defect value, in inches, from the geometry car or track inspector) and its frequency (how often it has been reported or corrected, for example “surfaced 3 times since May”), then mark the track structure symptoms you can see. Photograph every marked indicator with a scale and the milepost in the frame, and write the photo number beside the entry.

Read the pattern, not the item. A single indicator rarely decides the case; the combination does. Typical patterns are:

  • Upper slope tension cracks with a mid- or lower slope bulge on one side, and recurring cross level and alignment defects: rotational or translational slope movement through the embankment or its foundation (Section 6.3.2).
  • Seepage on the slope, standing water at the toe and a higher water level on one side: a drainage or seepage problem, often a blocked or undersized culvert ponding water against the embankment (Chapter 2.8; Section 3.8.4).
  • Fouled ballast, water between the cribs, voids and profile defects with no slope indicators: a track substructure problem such as subgrade pumping, ballast pockets or poor drainage within the section (Chapter 2.3).
  • A shoulder narrower than 12 in., erosion and tie shift: loss of lateral support at the edge of the section.

Defect frequency is the best single field measure of how fast the condition is developing, and it is the main evidence for the field frequency index. Record it exactly as the railroad reports it.

3.8.24.5 Site Instabilities (Report Block 3)

Block 3 records what is failing, what will make it hard to fix, and how it is expected to fail.

Table 3.8-26. Site instabilities
Major elementConstruction constraintEstimated failure type
BallastAccess and mobilityBearing capacity
SubgradeRailroad workload conflictSlope
ForeslopePropertySettlement
BackslopeMaterialWashout
Bridge abutmentUnderground obstructionsSubsidence
CulvertWater sourceSurface erosion
DitchPermitStream and wave erosion
Adjacent propertyEnvironmentalUnderground flow erosion

Major element is the part of the roadbed or structure whose failure threatens the track. More than one may apply; number them with the governing element as 1.

Estimated failure type is the engineer’s field judgment of the mechanism. Mark one as primary; a second may be marked as contributing. Compare it with the driving mechanism assigned at the desk (printed in the Desktop Study Summary of the report) and note any change. The exploration and analysis scoped in Block 5 confirm or revise it, and it sets which analyses are required (Section 3.8.42.8). Section 3.8.13 shows how to work from the symptom back to the mechanism.

Construction constraints are not part of the rating, but they are recorded here, while the access, the right-of-way and the utilities are in view, because they often decide which alternative is practical. Equipment access, track time (railroad workload conflict, confirmed with the railroad contact), right-of-way and adjacent property, the supply of fill and aggregate, buried utilities, a construction water source, permits and environmental restrictions can each rule out an otherwise sound fix. A toe berm that needs property the railroad does not own, or a sheet pile wall that needs a crane on a single-track main line with no work windows, is not a practical alternative.

3.8.24.6 Setting the Field Frequency Index

In the field the EIC does not recompute L. The EIC confirms the trigger and T, sets the field defect rating D from the instability evidence (Table 3.8-27, which matches Table 3.8-10), and reads the current frequency index Fc from Table 3.8-11 using the geospatial frequency Fg printed on the report. Fc is the field F. The preliminary Fp is printed beside it as a check.

Table 3.8-27. Instability evidence and the field defect rating
Instability evidence (Blocks 2 and 3, desk record)Field defect rating D
Active movement, settlement or erosion affecting the track now; repeated slow orders or surfacing; defects recurring faster than surfacing can hold5 Active
Fresh tension cracks or a growing bulge; geometry defects that return between surfacing cycles; the track still runs at or near normal speed4 Recurring
No sign of movement, but the conditions for it are present: water ponded against the fill, seepage, a blocked culvert, an over-steepened or eroding slope3 Present
Old scarps, past repairs or a documented failure (L6 of 3 or more), but no fresh indicators and no recurring defects2 Historic
No indicators, no instability record, or the cause has been removed1 None

This table sets the defect rating in the field from what is seen. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.

Where the field F differs from Fp by more than one level, write the reason on the report. Those notes are how the desktop attributes and thresholds are calibrated over time.

3.8.24.7 Example: Instability Rating

Example 3.8-5: Culvert Fill Site, Part 3: Instability Rating

Continuing Example 3.8-4: the site's record of past movement and its track defects are added to its situation, first at the desk and then on the field visit.

Main track36-in. culvert, half blockedponded water (left)seepagetension cracks25 ftGivenWeighted sum of L1–L5 = 23 (weights 6)Shoulder slump repaired 12 yr ago4 cross level exceptions, returning between cyclesTrigger T = 4Field: seepage, cracks, track at normal speedRequiredL6 and overall LF​g, desk D and F​pField D and F​cBlack = given; red = required
Given and required for Example 3.8-5.

Given

VariableValueDescription
ΣwiLi, Σwi23; 6From Example 3.8-4
Repair recordShoulder slump repaired with fill and riprap 12 years agoEvidence for L6
Geometry recordFour cross level exceptions since the last slow order, returning between surfacing cyclesDesk evidence for D
T4Storm exceeding the half-blocked culvert ponds water in most wet years
Field findingsSeepage at mid-slope; water 3 ft higher on the left; culvert half blocked; fresh tension cracks; track at normal speed, no slow orderField evidence for D

Required

  • The instability attribute L6 and the overall likelihood L
  • The geospatial frequency Fg, the desk defect rating and the preliminary Fp
  • The field defect rating and Fc

Equations

  1. Eq. 1: L = (ΣwiLi + L6) / (Σwi + 1) — overall likelihood (Equation 3.8-2)
  2. Eq. 2: Fg = lesser of (L, T) — geospatial frequency bounded by the trigger
  3. Eq. 3: Fc from Fg and D — Table 3.8-11 (Equation 3.8-3)

Steps

Step 1 · Historic instability
Uses: Repair record
A documented failure within about 20 years
L6 = 4
Spot check: A single repaired slump is 4, not 5; 5 needs repeated failure or measured movement (Table 3.8-24).
↓
Step 2 · Overall likelihood (Eq. 1)
Uses: ΣwiLi, L6
L = (23 + 4) / (6 + 1) = 27 / 7
L = 3.86 → 4
Spot check: Adding a 4 to an average of 3.83 can only move it toward 4.
↓
Step 3 · Geospatial frequency (Eq. 2)
Uses: L, T
Fg = lesser of (4, 4)
Fg = 4
Spot check: The trigger does not cap it here, because T = L.
↓
Step 4 · Desk defect rating and Fp (Eq. 3)
Uses: Geometry record
Recurring defects in the records: D = 4; Table 3.8-11, row 4, column 4
Fp = 4
Spot check: D = Fg, so the defects govern without amplification.
↓
Step 5 · Field defect rating and Fc (Eq. 3)
Uses: Field findings
Fresh cracks and recurring defects confirm D = 4; no slow order yet, so not 5
Fc = 4, Emerging, the same as Fp
Spot check: D = 5 needs a standing slow order or defects returning within weeks (Table 3.8-10).
↓
Solution
Fp = Fc = 4 (Emerging).

Solution

L6 = 4; L = 3.86 → 4; Fg = 4; D = 4 at the desk and in the field; Fp = Fc = 4, Emerging. The desk rating predicted the field rating: the records already showed the recurring defects that the visit confirmed.

The site now has a situational severity and an instability-based frequency index. Section 3.8.25 combines them into the static rating that ranks the site under usual conditions.