3.8.27 Rated Elements and Rating Criteria

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.27 Rated Elements and Rating Criteria

Sections 3.8.18 to 3.8.39 define each rating by its levels. This section breaks every rating into the elements that are actually looked at, at the desk or on site, and states for each element what places it at 1, 2, 3, 4 or 5. The tables are the working detail behind Tables 3.8-9, 3.8-10, 3.8-80 to 3.8-82 and Tables 3.8-20, 3.8-21 and 3.8-24; they do not change those tables, the equations or the risk matrix. They make the choice of level repeatable: two engineers looking at the same evidence should land on the same score, and the one-line reason required by Section 3.8.43 can be taken straight from the cell that was matched.

This section is the working detail behind the ratings, so its element tables are folded. Open the group you need; each lists what places an element at 1 to 5.
  • 3.8.27.2 Trigger Rating Elements (T) (Tables 3.8-34 to 3.8-38)
  • 3.8.27.3 Situational Attribute Elements (L1 to L5) (Tables 3.8-39 to 3.8-43)
  • 3.8.27.4 Historic Instability Elements (L6) (Table 3.8-44)
  • 3.8.27.5 Defect Rating Elements (D) (Tables 3.8-45 to 3.8-47)
  • 3.8.27.6 Consequence Elements (C1 to C5) and Severity (S) (Table 3.8-48)
  • 3.8.27.7 Solution Elements (Table 3.8-49)
  • 3.8.27.8 Design and Construction Elements (Tables 3.8-50 to 3.8-51)
  • 3.8.27.9 Post-Stabilization Elements (Table 3.8-52)
  • 3.8.27.10 Example: Element Scores Behind the Worked Example (Table 3.8-53)
  • 3.8.27.11 Basis and Limits of the Element Criteria

3.8.27.1 How the Element Tables Work

Table 3.8-33. Ratings, the elements that feed them and how the elements combine
RatingElement tablesHow the element scores give the ratingSection
Trigger rating TTables 3.8-34 to 3.8-38 (T1 to T19)T is the highest score among the trigger elements that can, on their own, bring the site to its response level. Where two triggers act only in sequence (a flood that scours the toe, then drawdown), score the sequence by the frequency of the event that starts it. Where the response level is unknown, T is not lower than 3.3.8.18.3
Situational attributes L1 to L5Tables 3.8-39 to 3.8-43Each attribute is the highest score among its elements that have data. Elements without data are left blank, not scored. An attribute with no data at all is scored 3 and flagged for the field visit (Section 3.8.22.1). The attributes are then weighted and averaged as before (Section 3.8.23.4).3.8.19.1; 3.8.23.4
Historic instability L6Table 3.8-44The highest score among its elements that have data.3.8.24.2
Defect rating DTables 3.8-45 to 3.8-47The higher of (a) the highest score among the record and measurement elements D1 to D4 and D15, and (b) the highest score shown by two or more of the field indicators D5 to D14. Check the result against the level descriptions of Table 3.8-10.3.8.19.2
Consequence attributes C1 to C5, and severity STable 3.8-48Each attribute is the highest score among its elements. C is the average of C1 to C5, with the floor of Section 3.8.23.6 (a 5 on C2 or C3 sets C at 4 or more), rounded half up to give S. The consequence governs, and the engineer may raise S one level (Section 3.8.20).3.8.20; 3.8.23.5 and 3.8.23.6
Solution ratingTable 3.8-49The element scores do not average into a rating. Each one sets a limit on, or a condition for, the credit the solution can take, as stated in the last column.3.8.37
Design and construction-stage ratingsTables 3.8-50 and 3.8-51Design elements give Fdes through Table 3.8-81; construction-stage elements decide Fcon and any one-level reduction in S for the stage.3.8.38
Post-stabilization ratingTable 3.8-52The elements decide whether Fpost is provisional (Fdes + 1), verified (Fdes) or reverts to the current-risk process.3.8.39
Why the highest element governs. A slope fails through its weakest layer, a culvert overtops at its smallest capacity, and a fill moves where its toe is wettest. Averaging the elements of one attribute would let good conditions in one place hide the condition that controls. The same rule is already used for slope geometry (score height and steepness separately and use the higher, Section 3.8.23.4). The weighting and averaging that follow, across attributes, are unchanged.

Reading the tables. Every table runs from 1 (lowest risk) to 5 (highest), the same direction as every other scale in the manual. For the solution, design and post-stabilization elements, 1 means the stage leaves the least risk. Where the evidence falls between two descriptions, choose the higher until the field visit or the record settles it, and say so in the reason. Numeric thresholds are indicative values from common practice; where a railroad has its own standard for an element (defect limits, culvert design events, monitoring alarm levels), use the railroad standard and record it.

3.8.27.2 Trigger Rating Elements (T)

The trigger elements are grouped by the kind of event. Their levels use the five annual frequency bands of Table 3.8-9, so the score of the element is the trigger rating it would give. Score only the elements that can act on the site’s driving mechanism (Table 3.8-8); the rest are left blank.

Table 3.8-34. Hydrologic and hydraulic trigger elements
IDElement and what is measured1 Remote: less than 1 in 100 years, or none2 Rare: 1 in 25 to 1 in 100 years3 Occasional: 1 in 5 to 1 in 25 years4 Frequent: 1 in 1 to 1 in 5 years5 Acting now: once a year or moreSources
T1Storm rainfall: return period of the storm at which the site has responded (defects, slow orders, movement, overtopping)No response to rainfall on record, or responds only to storms rarer than the 100-year eventResponds to 25- to 100-year stormsResponds to 5- to 25-year stormsResponds to 1- to 5-year storms (for example the 2-year, 24-hour depth)Responds in most wet seasons, to storms smaller than the 1-year eventNOAA Atlas 14; event and defect history; Section 3.8.23.7
T2Antecedent wetness: how often soil moisture or 30-day rainfall reaches the level that preceded past failures (default: 80th soil moisture percentile)No link between wet periods and the site’s responseOnly in exceptionally wet yearsIn wet years, about 1 in 5 to 1 in 25In most wet seasonsEvery wet season; the site is wet enough to respond for part of every yearSoil moisture percentile; antecedent rainfall; Section 3.8.23.7
T3Flood stage at the toe: return period, or gauge stage, at which water reaches the toe (toe stage)No water body within reach of the toe, or toe stage above the 100-year floodWater reaches the toe only in 25- to 100-year floodsWater reaches the toe in 5- to 25-year floodsWater reaches the toe in most high-water years (for example at minor flood stage)Toe in water at normal high water, or every yearNWS and USGS gauges; FEMA flood profiles; lidar; high-water marks
T4Scour and channel migration: how often flows erode the bank or toeNo channel within reach, or bank in rockArmored or straight reach; erosion only in floods rarer than 1 in 25 yearsOutside of a bend or below a constriction; bank loss in 5- to 25-year floodsBank retreating toward the toe in most high-water years; undercutting seenChannel migrating into the fill; toe lost in recent eventsHistoric aerials; lidar comparison; gauges; field reconnaissance
T5Rapid drawdown: how often water stands against the slope and falls faster than the fill can drainNo ponded or flood water against the slopeWater against the slope only in rare floods; slow recessionWater against the slope in 5- to 25-year floods; recession over daysWater against the slope most years; recession within a dayRoutine drawdown against the slope (reservoir, tide or controlled release)Gauge hydrographs; dam operator data
T6Snowmelt and rain-on-snow: how often melt runoff reaches the site at the response levelNegligible snowpackSnowpack present; rain-on-snow only in rare yearsRain-on-snow or rapid melt about 1 in 5 to 1 in 25 yearsRain-on-snow or rapid melt most yearsMelt runoff over frozen ground reaches the site every spring, and the site has failed in the melt seasonNOAA snow data; SNOTEL; Section 3.8.7.8
Table 3.8-35. Drainage and groundwater trigger elements
IDElement and what is measured1 Remote: less than 1 in 100 years, or none2 Rare: 1 in 25 to 1 in 100 years3 Occasional: 1 in 5 to 1 in 25 years4 Frequent: 1 in 1 to 1 in 5 years5 Acting now: once a year or moreSources
T7Culvert capacity exceedance: return period of the storm the culvert passes without heading up against the fill (culvert capacity storm)No concentrated flow, or the culvert passes the 100-year eventCapacity 25- to 100-yearCapacity 5- to 25-yearCapacity 1- to 5-yearHeads up or overtops every yearStreamStats or lidar drainage area; culvert inventory; Section 3.5.10
T8Blockage events: how often debris, sediment, beavers or ice block the inlet, outlet or ditchNo blockage on record; inlet protected; no debris sourceBlockage on record only once, long agoBlocked in some years; debris or sediment source upstreamBlocked most years; beaver activity in the reachBlocked now, or every year; active beaver dam at the inletMaintenance records; imagery sequence; field reconnaissance
T9Seasonal groundwater rise: how often groundwater reaches the critical zone of the slope or subgradeGroundwater well below any critical surface in all seasonsReaches the critical zone only in exceptionally wet yearsApproaches the critical zone about 1 in 5 to 1 in 25 yearsWithin the critical zone in most wet seasons; perched water on low-permeability layersAt or near the surface every year, or artesian or persistent perched waterPiezometers; boring water levels; seepage; Chapter 2.8
Table 3.8-36. Climatic and cyclic trigger elements
IDElement and what is measured1 Remote: less than 1 in 100 years, or none2 Rare: 1 in 25 to 1 in 100 years3 Occasional: 1 in 5 to 1 in 25 years4 Frequent: 1 in 1 to 1 in 5 years5 Acting now: once a year or moreSources
T10Frost and thaw weakening of the subgrade: how often frost reaches frost-susceptible soil with water availableFrost does not reach frost-susceptible soil, or the subgrade is non-frost-susceptibleReaches it only in extreme wintersReaches it in cold winters, about 1 in 5 to 1 in 25Reaches it in most wintersEvery winter, with heave or thaw softening recordedFrost depth and freezing index; USACE frost groups (Table 3.8-39); Section 3.8.8
T11Freeze-thaw, root wedging and intense rain on rock faces: how often these are followed by fallsNo falls on record after these events, or massive rockFalls only after extreme winters or stormsFalls after some winters or stormsFalls after most winters or stormsFalls every freeze-thaw season or storm seasonRock fall records; freeze-thaw cycle counts; rainfall intensity; Section 3.8.29
T12Wet-dry cycles in plastic clay (shrink-swell): how often desiccation cracking and re-wetting soften the slope or shoulderNon-plastic soils, or no seasonal moisture change in the active zoneCracking only in severe droughtsCracking in dry years, about 1 in 5 to 1 in 25Cracking in most dry seasonsDeep cracks open every dry season and soften on re-wettingPlasticity (Table 3.8-39); drought records; Chapter 2.5
Table 3.8-37. Loading, land-use and seismic trigger elements
IDElement and what is measured1 Remote or none2 Rare3 Occasional4 Frequent or planned5 Acting nowSources
T13Change in traffic loading: tonnage or axle load increase relative to what the subgrade has carriedNo change; traffic within what the subgrade has carriedIncrease unlikely within 25 yearsIncrease possible within 5 to 25 yearsIncrease planned within 5 yearsIncrease in the last few years, and the subgrade is responding (pumping, ballast pockets)Traffic and tonnage records; Chapter 2.3
T14Surcharge at the crest: stockpiles, spoil, new fill, added track or structuresNone, and none crediblePossible but unlikely; the land use controls itOccasional temporary stockpiles or spoil within twice the slope height of the crestA second track, siding or structure planned within 5 years, or recurring stockpilingSurcharge at the crest nowField reconnaissance; aerials; railroad plans
T15Excavation at or below the toe, or other removal of supportNone, and none credibleUnlikely; the land below is controlledPossible; the land below is open to developmentExcavation planned or permittedExcavation under way or recent, with distressField reconnaissance; aerials; permits
T16Upslope development and drainage changes: runoff redirected toward the right-of-wayNoneMinor development, no change in drainageIncreased runoff, managed by drainage worksRunoff concentrated toward the right-of-wayUncontrolled discharge onto the slope or fill nowAerials; county GIS; field reconnaissance
T17Vegetation loss and wildfire upslope or on the slopeDense, healthy coverGood cover with minor gapsSparse cover, or an older burn upslopeRecent clearing or loggingBurned within the last two years with a storm season aheadAerials; fire perimeter data; post-fire debris flow hazard maps
T18Earthquake shaking: return period of the ground motion at which the site fails or liquefies (Chapter 6.5)More than 100 years (most sites)25 to 100 years5 to 25 years1 to 5 yearsOnce a year or more (induced seismicity only)USGS hazard tools; Chapter 6.5

Seismic triggers rarely score above 2 on an annual scale. That does not make them unimportant: the screening elements of Table 3.8-38 decide whether the seismic case must be analyzed and designed for, whatever T is.

Table 3.8-38. Seismic screening elements
IDElement and what is measured12345Sources
T19aDesign ground motion: peak ground acceleration for the 2,475-year return period, site-adjustedLess than 0.05 g0.05 to 0.10 g0.10 to 0.20 g0.20 to 0.40 gMore than 0.40 gUSGS seismic design maps; Chapter 6.5
T19bLiquefaction: factor of safety against liquefaction of saturated loose sands and silts (Chapter 6.5)No liquefiable soil, or above the water tableFS more than 1.3 in all layersFS 1.1 to 1.3, or isolated thin loose layersFS 1.0 to 1.1 in a continuous layer, or FS below 1.0 in isolated layersFS below 1.0 in a continuous layer, with a free face or sloping ground (lateral spread)Borings and CPT; Chapter 6.5; Chapter 2.4

A score of 4 or 5 on either screening element requires the seismic case in the analysis (Chapter 6.5) and in the design factor of safety element DC2 (Table 3.8-50). Record shaking as a secondary trigger in the narrative.

3.8.27.3 Situational Attribute Elements (L1 to L5)

Each table refines one attribute of Table 3.8-20. The 1, 3 and 5 descriptions of Table 3.8-20 and the 2 and 4 descriptions of Table 3.8-76 are carried into the elements of each attribute, so a desk rating made from Table 3.8-20 alone still agrees with these tables. The other elements are used when the data exist.

Table 3.8-39. L1 Surficial soils: elements
IDElement and what is measured12345Sources
L1.1Soil type of the fill, the cut face or the foundation (USCS, ASTM D2487)Rock, or clean, well-drained sand and gravelSand and gravel with some fines; well drainedSilty or clayey sand, low-plasticity silt or clay; moderately drainedLean clay or silt that softens when wet; poorly drained in placesHigh-plasticity or organic clay, peat, loess, sensitive or collapsible soil; poorly drainedSoil survey; geologic map; boring logs; Chapters 2.2 and 2.4 to 2.7
L1.2Consistency of cohesive soil: undrained shear strength suVery stiff to hard: more than 2,000 psfStiff: 1,000 to 2,000 psfMedium stiff: 500 to 1,000 psfSoft: 250 to 500 psfVery soft: less than 250 psf, or sensitive clayBorings, vane, CPT, lab tests; Appendix D
L1.3Density of granular soil: SPT N60Dense to very dense: more than 30Medium dense: 10 to 30Loose: 4 to 10Very loose: less than 4Very loose, saturated fine sand or silt prone to flowBorings and CPT; Appendix D
L1.4Fill type and placementEngineered, compacted granular fillOlder granular fill with a good recordMixed fill with some finesCinders, end-dumped or loose fillEnd-dumped fill over soft ground, with debris or organicsValuation maps; construction records; borings
L1.5Frost susceptibility of the subgrade (USACE frost group)Non-frost-susceptible (NFS)F1F2F3F4Gradation and plasticity tests; Chapter 7.3
L1.6Plasticity of clay in the active zone: plasticity index PINon-plastic, or PI less than 10PI 10 to 20PI 20 to 35PI 35 to 50PI more than 50, with seasonal desiccation crackingAtterberg limits (Chapter 5.2); Chapter 2.5

At the desk L1.1 is usually the only element with data. L1.5 applies to subgrade-driven sites and L1.6 to sites in plastic clay; leave them blank elsewhere.

Table 3.8-40. L2 Geologic setting: elements
IDElement and what is measured12345Sources
L2.1Overburden over rock: depth and type of the materials below the fill or cutCompetent rock at or near the surfaceWeathered rock over competent rock at shallow depthWeathered rock or till at moderate depthThick till, colluvium or weak shaleDeep weak overburden or colluvium, or a mapped landslide-prone formationGeologic map; boring logs; lidar
L2.2Landslide susceptibility of the mapped unitLow or noneLow to moderateModerateHighVery high, or the site sits in a mapped landslide-prone formation with deep colluviumState and USGS landslide susceptibility maps
L2.3Karst and underminingNo soluble rock and no miningSoluble rock at depth, no features within about half a mileSinkholes or mine workings mapped within about half a mileKarst or mine workings mapped nearby but not under the trackKarst features or mine workings under the trackKarst and mine maps; state geological survey; lidar closed depressions
L2.4Rock mass structure in cuts: discontinuities relative to the faceNo rock cut, or massive rock, or joints dipping into the faceFavorable joints; slight weatheringRandom or some adverse joints; moderate weatheringAdverse joints daylighting in the faceDaylighting planes or wedges with past failures, toppling, or clay-filled jointsGeologic mapping of the cut; Section 3.8.29
Table 3.8-41. L3 Slope geometry: elements
IDElement and what is measured12345Sources
L3.1Height of the fill or cutUnder 10 ftHeight alone does not give 210 to 30 ftHeight alone does not give 4Over 30 ftLidar; track charts
L3.2Steepness of the steepest representative slopeFlatter than 3H:1V2.5H:1V to 3H:1VAbout 2H:1V (2H:1V to 2.5H:1V)Steeper than 2H:1V but not steeper than 1.5H:1VSteeper than 1.5H:1VLidar sections; field measurement
L3.3Distance from the end of the ties to the crest of the slopeMore than 10 ft6 to 10 ft3 to 6 ft1 to 3 ftLess than 1 ft, or the crest is in the ballast shoulderLidar; field measurement
L3.4Setting: what the fill or cut sits onFill or cut on level groundLow sidehill, natural ground flatter than 5H:1VSidehill bench on natural ground of 5H:1V to 3H:1VCut with natural ground steeper than 3H:1V above itSidehill fill on natural ground steeper than 3H:1V, or a fill across a hollow or old channelLidar; valuation and historic maps; Section 3.8.23.2

Height keeps the three bands of Table 3.8-20, so the intermediate scores 2 and 4 come from steepness, crest distance and setting. Use the highest element, as Section 3.8.23.4 requires for height and steepness.

Table 3.8-42. L4 Hydrology: elements
IDElement and what is measured12345Sources
L4.1Water against or near the toeNo contributing flow; no water body within about 500 ftIntermittent ditch flow away from the toe, or a water body 200 to 500 ft awayDitch or small-stream flow along the toe, or a water body 50 to 200 ft awayStream within about 50 ft of the toeStream or river against the toe, or convergent flow or ponding against the fillAerials; National Hydrography Dataset; lidar
L4.2Mapped flood hazard (FEMA zone)Outside mapped flood hazard areas (Zone X, unshaded), no flow toward the fillOutside the 500-year floodplain, local ponding possibleIn or near the 500-year floodplain (Zone X, shaded)In the 100-year floodplain (Zone A or AE) without flow against the fillIn the 100-year floodplain with flow against the fill, in a regulatory floodway, or in a coastal high hazard area (Zone VE)FEMA National Flood Hazard Layer
L4.3Channel position and flow attackNo channelStraight reach, flow parallel to an armored or vegetated bankFlow along the toe in a straight reachOutside of a bend, or below a constriction or a bridgeFlow impinging directly on the fillAerials; lidar; field reconnaissance
Table 3.8-43. L5 Drainage condition: elements
IDElement and what is measured12345Sources
L5.1Culvert condition and blockageClear and soundMinor debris, sediment or corrosion; full functionAging; some section loss or partial blockageAbout half blocked, damaged, separated joints, or capacity unknownMostly blocked, collapsed, or failed and directing water into the fillCulvert inspections; field reconnaissance
L5.2Culvert size relative to the design flowPasses the design flow without heading up against the fillAdequate, but aging or with little marginCapacity not knownUndersized for the design flowUndersized, with a record of overtopping or ponding against the fillCulvert inventory; StreamStats; Section 3.5.10 (the frequency itself is T7)
L5.3Ditches and outletsFree-draining, with outlet controlMinor sediment or vegetationPartly obstructed; some sedimentDitch holding water; outlet eroded or undefinedDitch blocked or missing; water directed onto the slope; no outlet controlImagery sequence; field reconnaissance; maintenance records
L5.4Track and subsurface drainage: subdrains, underdrains and drainage of the track sectionSection drains freely; subdrains workingMinor fouling; subdrains workingFouled shoulders or subdrain condition unknownWater trapped in the section; subdrain outlets buriedBathtub section or failed subdrains holding water under the trackField reconnaissance; GPR; Chapter 2.3
L5.5Beaver activity and debris sourcesNoneOld evidence onlyBeaver or debris source in the drainage upstreamActive beaver activity in the reachActive dam at or near the inlet, or debris jam at the structureImagery sequence; field reconnaissance; maintenance records

L5 records the condition of the drainage. How often the drainage is exceeded is the trigger element T7; the two are scored separately, as Section 3.8.37.1 requires when a solution changes both.

3.8.27.4 Historic Instability Elements (L6)
Table 3.8-44. L6 Historic instability: elements
IDElement and what is measured12345Sources
L6.1Recorded failures and repairs at the siteNoneNo record at the site; landslide-prone formation mapped (L2.2 of 4 or more)A past repair at the site (berm, drains, riprap, wall)A documented failure at the site within about 20 yearsRepeated documented failures, or repairs that have not heldRailroad records; interviews with track forces
L6.2Geomorphic evidence in lidar and on siteNoneSubdued features that may be old movementOld lobes or hummocky ground near the siteAn old scarp visible in lidar at the siteFresh or repeated scarps at the siteLidar hillshade and slope maps; field reconnaissance
L6.3Mapped instability near the siteNone within about a mileDistant mapped slidesMapped slides within about half a mile, or instability mapped nearbyA mapped slide adjacent to the right-of-wayA mapped active landslide crossing the right-of-wayUSGS landslide inventory; state geological survey
L6.4Slow orders for a geotechnical cause, more than 12 months agoNoneOne, more than 10 years agoOne or two in the last 10 yearsThree to five in the last 10 yearsMore than five in the last 10 yearsSlow order history
L6.5Measured past movementNone measuredMovement measured once, since stoppedIntermittent movement after past eventsMeasured movement in recent yearsContinuing measured movementInSAR; survey; inclinometer records

Slow orders in the last 12 months and standing slow orders are scored in the defect rating (D3), not here, so the same order is not counted twice.

3.8.27.5 Defect Rating Elements (D)

The defect elements follow the levels of Table 3.8-10: 1 None, 2 Historic, 3 Present, 4 Recurring, 5 Active. The record and measurement elements (D1 to D4 and D15) are direct evidence of what the track and the ground are doing, so any one of them can set D. The field indicators are read as a pattern (Section 3.8.24.4): D is set at the highest level shown by at least two of them. Each defect is entered with its measurement and its frequency.

Table 3.8-45. Track defect and slow order elements
IDElement and what is measured12345Sources
D1Recurrence of geometry defects at the site (cross level, profile, alignment, warp)No defects in the recordA single defect in the record, not repeatedDefects reported more than once, but not returning between surfacing cyclesThe same defect returns between surfacing cycles (surfaced two or more times in 12 months at the same location)Defects return within weeks of surfacingGeometry car and inspection records; surfacing records
D2Size of the worst defect relative to the limitsNoneWithin the railroad’s maintenance toleranceBeyond the maintenance tolerance but within the FRA limit for the track classBeyond the FRA limit for the track class; remedial action required under 49 CFR Part 213Beyond the limits for any class the line can be reduced to; track removed from serviceGeometry car data; 49 CFR Part 213
D3Slow orders in the last 12 months for a geotechnical causeNoneA slow order more than 12 months ago, lifted after repair, nothing sincePrecautionary slow orders during high water or storms, without defectsA slow order for a defect within the last 12 monthsStanding slow order, or track removed from serviceSlow order history
D4Trend of defects over successive geometry runs or inspectionsNo defectsDecreasingSteadyIncreasingAccelerating, or recurring after each surfacingGeometry car data

These elements record the evidence behind the defect rating. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.

Table 3.8-46. Field indicator elements: slope and ground
IDElement and what is measured12345Sources
D5Tension cracks and scarpsNoneOld, healed or vegetated cracks or scarps onlyOpen cracks with weathered edges, no sign of progressFresh cracks with clean edges, or a continuous scarp with a small offsetCracks widening between visits, or cracks through the shoulder or ballastField reconnaissance; photographs with scale (Section 3.8.24.4)
D6Bulges and toe heaveNoneOld lobes with no fresh disturbanceNoticeable bulge, no fresh disturbanceDistinct or growing bulge, or fresh toe heaveActive toe heave, a slumped mass, or a bulge advancingField reconnaissance
D7Displaced trees, poles, fences and structuresNoneIsolated old tilted trees with recovered growthSeveral curved (pistol-butt) treesRecently tilted poles or fences, cracked headwallsStructures being displaced now, or broken utilitiesField reconnaissance
D8Settlement, sags and ballast pocketsNoneMinor shoulder irregularityA low spot that recurs, with no recent changeRepeated surfacing; ballast pocketsRapid settlement; track hung or voids under the tiesField reconnaissance; track forces; GPR
D9Seepage, piping and water at the toeNoneDamp areas onlySeepage or standing water at the toe; clear waterPersistent seepage carrying finesActive piping, sinkholes or sand boilsField reconnaissance; seasonal re-inspection
D10Erosion and undercutting at the face or toeNoneMinor rillsGullies, or minor undercuttingSignificant undercutting; slope oversteepenedToe lost; erosion reaching the shoulderField reconnaissance; aerials
D11Loss of shoulder or sectionFull shoulderSlightly narrowed shoulderNarrowed shoulder, stableShoulder narrower than 12 in., with recent lossTie ends unsupportedField reconnaissance; Table 3.8-25
Table 3.8-47. Field indicator elements: track section, protection and structures, and monitoring
IDElement and what is measured12345Sources
D12Fouled ballast, water between the cribs and pumpingNoneIsolatedRecurring after stormsPersistent pumping; fouled ballastContinuous pumping, with geometry defects returningField reconnaissance; GPR; Chapter 2.3
D13Scour protection (riprap or revetment) conditionIntact, or not neededMinor displacementGaps, or undersized stoneSignificant loss of protectionProtection failed, or absent where flow attacks the toeField reconnaissance; underwater or low-water inspection
D14Retaining structures (soldier pile and lagging and other walls)None needed, or in good conditionMinor deteriorationModerate deterioration, minor tiltLagging loss, significant tilt or bulgingWall failing or failedField reconnaissance; Chapter 7.1
D15Monitoring trend: inclinometers, survey, extensometers or InSARNo movement beyond instrument precision over at least a year of readingsMovement after a past event that has since stoppedPossible slow movement, less than about 0.1 in. per year, not yet confirmed by successive readingsConfirmed steady movement, about 0.1 to 2 in. per yearMore than about 2 in. per year, or acceleratingInstrument and survey records; InSAR; Chapter 5.3

D15 is a measurement element and can set D on its own. The movement rates are indicative; where the railroad or the design sets alarm levels for the instruments, the alarm levels govern.

3.8.27.6 Consequence Elements (C1 to C5) and Severity (S)

The consequence elements refine Tables 3.8-21 and 3.8-76. Each attribute is the highest of its elements; C1 to C5 are averaged with the floor of Section 3.8.23.6, and the result is the hazard severity S of Table 3.8-15. For cuts and natural slopes above the track, C4 is judged from the volume that would reach the track rather than the fill height.

Table 3.8-48. Consequence attribute elements
IDElement and what is measured12345Sources
C1.1Line and track: what the track is used forIndustry, yard or out-of-service trackLightly used branch line or sidingMain line with light traffic, or a busy sidingMain line with moderate trafficMain line with heavy tonnage or high speed; multiple main tracksRailroad network data; timetable
C1.2Track class: FRA class of the track at the siteExcepted track or Class 1Class 2Class 3Class 4Class 5 or higherTimetable; 49 CFR Part 213
C2.1Train type: passenger and hazardous materials trafficNo passenger or hazardous materials trafficNo passenger trains; hazardous materials limited to infrequent carsOccasional hazardous materialsRegular hazardous materials traffic, or occasional passenger trainsPassenger trains, or a key route for hazardous materials (AAR Circular OT-55)Railroad traffic data
C3.1People and property below and beside the trackOpen land on railroad propertyRailroad or private land with minor drainageA road or farmlandA local road, or a few dwellings within reachA highway, dwellings, occupied buildings, utilities or a critical facilityAerials; county GIS
C3.2Water and the environment below and beside the trackNoneMinor drainageA small stream or wetlandA stream with fisheries value, or other regulated waterA river, a drinking-water supply or protected habitatNational Wetlands Inventory; state environmental data
C4.1Size of failure: fill height, or volume reaching the track from aboveFill under 5 ft; a failure would be shallowFill 5 to 10 ftFill 10 to 20 ftFill 20 to 30 ftFill over 30 ft, or a culvert or structure under high fillLidar; track charts
C5.1Redundancy: route around the siteA parallel route on the same corridorA parallel route nearby, with minor delayA detour is availableOnly a long detourNo detourRailroad network data
C5.2Recovery: time to restore service, including accessWithin a shiftWithin a dayDaysAbout a weekMore than a week, or access is difficultAccess study (Chapter 3.6); repair experience

The floor applies through C2 and C3: a 5 on C2.1, C3.1 or C3.2 sets C at no less than 4, because a failure that can reach passengers, a hazardous materials release or the public governs regardless of the other attributes.

3.8.27.7 Solution Elements

The solution is rated by rescoring T, L1 to L5 and D as the site would be once the solution works (Section 3.8.37.2). The elements below do not change that arithmetic; they decide how much of it can be credited. A score of 1 means the solution leaves the least risk.

Table 3.8-49. Solution elements and their effect on the solution rating
IDElement12345Effect on the rating
SOL1Mechanism match: does the solution act on the primary trigger, or on the susceptibility it exploits?Acts on the primary and all contributing mechanismsActs fully on the primary mechanismActs on part of the primary mechanismActs on a contributing mechanism onlyDoes not act on the primary mechanism1 or 2: full rescoring. 3: Fsol no more than one level below Fc. 4 or 5: no reduction in F (Fsol = Fc); only S can change, under Table 3.8-80.
SOL2Way of reducing risk (Table 3.8-79)Removes the trigger and increases resistanceRemoves or controls the triggerIncreases resistance onlyReduces exposure only (detection linked to operating rules)Monitoring without an operating response1 to 3: rescore T and L as the solution changes them. 4: S may drop one level while the response is in force; F unchanged. 5: no credit.
SOL3Investigation behind the solutionSubsurface investigation, laboratory testing, analysis and instrumentationSubsurface investigation, laboratory testing and analysis at the design sectionsLimited borings, no analysisField reconnaissance onlyDesk study onlyCaps from Table 3.8-80. 1 or 2: full credit. 3 or 4: at most two levels. 5: at most one level.
SOL4Dependence on maintenanceNo maintenance needed to keep workingRoutine inspection onlyPeriodic maintenance (drainage cleaning, vegetation)Frequent maintenance; works fail if it lapsesWorks fail within a season without maintenance3 to 5: full credit only with a maintenance plan in force (Table 3.8-80); otherwise the rating stays provisional (Table 3.8-82).
SOL5Design life against the planning horizonMore than 50 years30 to 50 years15 to 30 years5 to 15 yearsLess than 5 years4 or 5: record the date the credit expires and re-rate before it; carry the replacement cost into the life-cycle cost (Section 3.8.40). A solution that leaves the site at High or above is interim either way.
SOL6Constructability and permittingNo permits; easy access; work outside the trackMinor permits; good accessStandard permits; limited access or track timeMajor permits; difficult access; long track windowsPermits uncertain; access needs a new road or bargeNot a rating input. 4 or 5: check the construction-stage rating (Table 3.8-51) and the duration before the solution is preferred.
3.8.27.8 Design and Construction Elements
Table 3.8-50. Design elements and the design frequency index Fdes
IDElement12345Effect on the rating
DC1Investigation adequacy at the design stageFull investigation with instrumentationBorings and laboratory tests at the design sectionsLimited boringsDesk study and reconnaissance onlyNo site-specific data1 or 2: full design credit. 3: Fdes no lower than 2. 4 or 5: no design credit beyond the caps of Table 3.8-80.
DC2Slope design factor of safety for the governing condition (Chapter 6.3)FS of 1.5 or more static, and the required factors of safety met for rapid drawdown and seismic cases where they applyFS of 1.5 or more static; other cases not applicable or not yet checkedFS 1.3 to under 1.5FS 1.1 to under 1.3FS under 1.1Fdes 1, 1 (2 if a required case is unchecked), 2, 3, no credit (Table 3.8-81).
DC3Hydraulic design event for culverts, channels and scour countermeasures100-year or larger, with scour checked at the 500-year event25- to 100-year10- to 25-year5- to 10-yearUnder 5-yearFdes 1, 2, 3, 3, no credit (Table 3.8-81).
DC4Subgrade and track section design (Chapter 2.3)Meets the criteria for the traffic with margin, with drainageMeets the criteria, but depends on drainage maintenanceMeets bearing criteria; drainage not addressedPartly meets the criteriaNo subgrade designFdes 1, 2, then no design credit for 3 to 5.
DC5Rock and debris, or subsidence, treatmentAll mapped blocks stabilized and catchment verified; or track bridged or relocated over the voidsScaling, bolting or catchment designed for the design block size and energy; or voids treated and verifiedCatchment for smaller blocks than the design block; or voids treated but not verifiedScaling only; or partial treatmentNoneFdes 1, 2, 3, then no credit for 4 and 5 (Table 3.8-81).
DC6Construction quality assurance planned for the works (Chapter 5.3)Full-time inspection, testing and as-built recordsRegular inspection and testingPeriodic inspectionContractor quality control onlyNo inspection1 or 2: the works can be accepted (Table 3.8-82). 3: acceptable for maintenance-level work only. 4 or 5: works cannot be accepted; Fpost not credited below Fc until inspection or testing confirms them.

Where several mechanisms apply, Fdes is the highest among them (Section 3.8.38.1).

Table 3.8-51. Construction-stage elements
IDElement12345Effect on the rating
CS1Temporary loss of resistance or added load during the workNone; the work is away from the slope and the toeMinor and brief (light equipment, short trenches outside the slope)Excavation or equipment within the slope or at the toe, stage designedTrench through the fill or excavation at the toe, stage checked only by judgmentExcavation or loading on a slope already moving1 or 2: Fcon = Fc. 3 to 5: Fcon = Fc + 1, to a maximum of 5 (Equation 3.8-15).
CS2Protection of operations during the stageTrack out of service for the stageSlow order with monitoring, and temporary support designed for the stageSlow order onlyInspection onlyNone1 or 2: S may be lowered one level for the stage (Table 3.8-80). 3 to 5: S unchanged. A stage rated Severe requires 1.
CS3Duration of the work relative to the trigger seasonDays, outside the trigger seasonWeeks, outside the trigger seasonOne seasonThrough a trigger seasonMore than a year4 or 5: the construction-stage rating applies through a triggering season; show it on the schedule and in the rating record.
3.8.27.9 Post-Stabilization Elements
Table 3.8-52. Post-stabilization elements and the post-stabilization frequency index Fpost
IDElement12345Effect on the rating
POST1Acceptance of the works: as-built quality assurance and quality control (Chapter 5.3)Accepted on full records and testsAccepted on regular inspection and testingAccepted on periodic inspectionContractor records onlyNo records1 to 3: Fpost = Fdes + 1, provisional. 4 or 5: not accepted; Fpost not credited below Fc.
POST2Performance monitoring after constructionAutomated, alarmed and reviewedPeriodic instrument readingsPeriodic survey or engineer’s inspectionVisual by track forces, with geometry recordsNone1 to 4: can verify the rating. 5: the rating stays provisional.
POST3Testing by a trigger since completionTwo or more triggering seasons, or events at or above the response level, with no movementOne triggering season or event at or above the response level, with no movementA full season, but the response level was not reachedLess than one seasonNone1 or 2 (with POST2 of 1 to 4): verified, Fpost = Fdes. 3 to 5: provisional, Fdes + 1.
POST4Maintenance plan for drainage, vegetation and protectionScheduled and funded, with recordsScheduledAs needed, from inspectionReactive onlyNoneDrainage-dependent works need 1 or 2 to be verified; otherwise they stay provisional (Table 3.8-82).
POST5Defects and indicators after stabilizationNoneRare, maintenance-levelOccasionalSimilar to before stabilizationIncreasing1 or 2: supports verification. 3: hold the rating provisional and find the cause. 4 or 5: recompute Fc from the new D (Section 3.8.19).
3.8.27.10 Example: Element Scores Behind the Worked Example

The ratings of the worked example in Section 3.8.41 are rebuilt below from the element tables. The element scores reproduce the attribute scores of Table 3.8-83.

Table 3.8-53. Worked example: element scores and the ratings they give
RatingElements scoredRating givenReason
TT7 = 4 (ponding against the fill recorded about every 3 years)4Primary trigger; no other trigger element scores higher
L1L1.1 = 4 (lean clay fill that softens when wet); no data for L1.2 to L1.64Highest element with data
L2L2.1 = 3 (weathered rock or till at moderate depth, assumed)3
L3L3.1 = 3 (22-ft fill); L3.2 = 3 (slopes about 2H:1V, assumed)3
L4L4.1 = 4 (creek within about 50 ft of the toe); L4.2 = 4 (100-year floodplain, no flow against the fill)4
L5L5.1 = 4 (culvert partly blocked); L5.2 = 5 (ponding against the fill on record)5Weight 2 (drainage-driven)
L6L6.1 = 3 (berm placed 15 years ago)3
L and Fg(4 + 3 + 3 + 4 + 2 × 5 + 3) / 7 = 3.86, rounded to 4; lesser of L and TFg = 4Equation 3.8-2
DD1 = 4 (surfaced twice in 12 months); D6 = 4 (bulge forming on the downstream slope)4Record element at 4, confirmed by a field indicator
Fc, S and RcFc from Table 3.8-11; S = 4 as in Table 3.8-83Fc = 4; Rc = 16, HighSame result as Table 3.8-83
3.8.27.11 Basis and Limits of the Element Criteria

Soil consistency and density bands follow the conventional classes used on boring logs (Appendix D). The frost groups are the USACE groups, F4 being the most frost-susceptible. The track class bands are the FRA classes of 49 CFR Part 213. The flood zones are FEMA’s. The trigger bands are the annual frequency bands of Table 3.8-9 and Table 3.8-14, and the design bands are those of Table 3.8-81. The remaining thresholds (distances, crest offsets, movement rates, plasticity bands and design life) are indicative values chosen to separate the five levels; they are starting points to be calibrated, like the H&H thresholds of Section 3.8.23.7, as each site’s record grows.

The elements are evidence for a rating, not a rating in themselves. Where the element scores and the trigger narrative disagree, one of them is wrong (Section 3.8.18.4): resolve it and write down why. A rating may always be raised one level on engineering judgment (Section 3.8.22.6); it is never lowered below what the element tables give without a written reason.