3.8.30 Return Period, Exposure and the Trigger and Frequency Bands

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.30 Return Period, Exposure and the Trigger and Frequency Bands

The trigger rating T (Table 3.8-9) and the frequency index F (Table 3.8-14) are both defined by annual frequency: 1 in 5, 1 in 25 and 1 in 100 years mark the band edges. Programming decisions, however, are made over a period: a five-year capital plan, a 50-year service life. The conversion between the two is the probability of at least one event in n independent years. It is the same arithmetic behind the seismic design levels quoted in the library. Duncan, Wright and Brandon tabulate peak rock accelerations for a 10% chance of exceedance in 50 years (the 500-year level) and a 2% chance (the 2,500-year level). The Navy's soil dynamics handbook uses a 10% chance in 100 years (950 years). Hearn's semi-quantitative risk matrix (Section 3.8.34) rates the probability of a landslide over a 20-year road design life, and the GEO factors of safety in Look (Section 3.8.35) are set for a 10-year return period rainfall. Each ties its probability to a stated period or return period, and a rating should do the same.

3.8.30.1 Method

Equation 3.8-6. Annual probability, exposure and design return period

p = 1/T;   Pn = 1 − (1 − p)n ≈ 1 − e−n/T;   expected number of events = n/T

Tdesign = 1 / [1 − (1 − Ptarget)1/n];   several independent sites or triggers: P = 1 − Π(1 − pi)n

T is the return period (average recurrence interval) and n the exposure period in years. The binomial form treats each year as one independent trial; the Poisson form treats events as random in time. They agree closely once T is more than a few years. The calculator also gives the chance of exactly 0, 1, 2, 3 or 4 events and the band level for the trigger or failure frequency.

Table 3.8-59. Chance of at least one event at the band edges of Tables 3.8-9 and 3.8-14, from the calculator
Band edge, T / F levelsIn 1 yearIn 5 yearsIn 25 yearsIn 50 years
5 / 4 (1 per year or more)100.0%100.0%100.0%100.0%
4 / 3 (1 in 5)20.0%67.2%99.6%100.0%
3 / 2 (1 in 25)4.0%18.5%64.0%87.0%
2 / 1 (1 in 100)1.0%4.9%22.2%39.5%

An event at the 1-in-5 edge is about 67% likely within a five-year program; one at the 1-in-100 edge is still about 40% likely within a 50-year life.

Table 3.8-60. Check against design levels quoted in the library
Design levelReturn period as quotedCalculator
10% in 50 years (Duncan, Wright and Brandon, Table 10.2)500-year475 years
2% in 50 years (same table)2,500-year2,475 years
10% in 100 years (Navy MIL-HDBK-1007/3)950-year950 years

The quoted values are the rounded forms of the exact 475, 2,475 and 950 years.

3.8.30.2 Worked example

Example 3.8-7: What the Trigger Rating Means over a Program and a Service Life

The site of Section 3.8.41 rated its trigger T = 4 because water has ponded against the fill about every 3 years. Alternative A replaces the culvert with one sized for the 100-year event. The question is what those return periods mean over the periods that matter: a five-year program for ranking the site, and a 50-year service life for the new culvert.

ponding about every 3 years5-yr program50-yr service life of new culvertP = ?GivenPonding return period T = 3 yr (trigger T = 4)Program n = 5 yr; service life N = 50 yrNew culvert sized for the 100-yr eventResidual storm checked: 10-yr eventRequiredP(ponding) in 5 yr; expected numberP(new culvert exceeded) in 50 yrP(10-yr storm) in 5 yr; meaning for TBlack = given; red = required
Given and required for Example 3.8-7.

Given

VariableValueDescription
Tpond3 yearsReturn period of ponding against the fill (trigger T = 4, Table 3.8-9)
n5 yearsProgram cycle used for ranking
Tdes, N100 years; 50 yearsDesign event and service life of the new culvert
T1010 yearsA storm in the level 3 trigger band, still able to reach the site

Required

  • Chance of at least one ponding event in the program, and the expected number
  • Chance that the new culvert's capacity is exceeded in its service life
  • Chance of a 10-year storm in a program, and what the three results mean for T

Equations

  1. Eq. 1: p = 1/T — annual probability
  2. Eq. 2: Pn = 1 − (1 − p)n — chance of at least one event in n years (Equation 3.8-6)
  3. Eq. 3: E = n/T — expected number of events in n years

Steps

Step 1 · Ponding in the program (Eq. 1, 2, 3)
Uses: Tpond, n
p = 1/3 = 0.3333; P5 = 1 − 0.66675 = 1 − 0.1317; E = 5/3
P5 = 86.8%; E = 1.67 events
Spot check: 0.6667² = 0.444, &sup4; = 0.198, × 0.6667 = 0.132.
↓
Step 2 · New culvert over its life (Eq. 1, 2)
Uses: Tdes, N
p = 0.01; P50 = 1 − 0.9950 = 1 − 0.605
P50 = 39.5%
Spot check: e−50/100 = 0.607 gives 39.3%, within the approximation error of Section 3.8.40.
↓
Step 3 · 10-year storm in a program (Eq. 1, 2)
Uses: T10, n
p = 0.1; P5 = 1 − 0.95 = 1 − 0.590
P5 = 41.0%
Spot check: 0.9² = 0.81, 0.81² = 0.656, × 0.9 = 0.590.
↓
Solution
86.8% now; 39.5% over the new culvert's life; 41.0% for a 10-year storm in any program.

Solution

The ponding trigger has an 86.8% chance of reaching the site in a five-year program (1.67 events expected); a 100-year culvert still has a 39.5% chance of being exceeded in 50 years; and a 10-year storm has a 41.0% chance in any program.

The first result is what Table 3.8-9 means by a trigger the site will meet before most programs could fix it. The new culvert lowers T to 1 but does not remove the trigger, and storms of the level 3 band still arrive often enough that drainage maintenance remains part of the rating (Section 3.8.39).

A T-year event is not one that happens once every T years. Over an exposure equal to T its chance is about 63%. State the exposure period with every probability in a rating: the program cycle when ranking sites, the service life when sizing works. Return periods of rare events estimated from short gauge or defect records are uncertain; use agency frequency analyses where they exist.

Open the trigger probability calculator →
Annual probability, chance of one or more events in an exposure period, the number of events, the return period for a target chance in a design life, and the band level of Tables 3.8-9 and 3.8-14.

3.8.30.3 Many sites, one program

A single Forming site (1 in 25 years) has an 18% chance of failing within a five-year program. A subdivision with many such sites is a different matter. If their failures are independent, the chance that at least one of them fails in the program rises quickly with the number of sites. This is why corridor budgets need a reserve for emergency repairs even when every individual site is rated Forming or below. The corridor screening calculator (Section 1.1.15) applies the same rule to a hazard register.

Table 3.8-61. Chance that at least one of N independent sites fails in a five-year program
Sites NEach 1 in 25 years (F = 3 edge)Each 1 in 100 years (F = 2 edge)
118.5%4.9%
564.0%22.2%
1087.0%39.5%
2098.3%63.4%

Sites that share a trigger (one storm over the whole subdivision) are not independent; their failures cluster in the same event, so the chance of several failures together is higher than this table implies.

3.8.30.4 How the chance grows with exposure

The figure plots the chance of at least one event against the exposure period for the three band edges. The curves rise steeply over the first few years and then flatten. Most of the benefit of fixing a Frequent or Emerging site is gained by fixing it soon.

020406080100020406080100Exposure period (years)Chance of at least one event (%)5-year event25-year event100-year event
Figure 3.8-42. Chance of at least one event against exposure period for 5-, 25- and 100-year events, the edges of the trigger and frequency bands.

3.8.30.5 Sources in the library

Paraphrased from these documents in the reference library.

  • J.M. Duncan, S.G. Wright and T.L. Brandon, Soil Strength and Slope Stability, 2nd edition: Table 10.2, peak rock accelerations for 10% and 2% probability of exceedance in 50 yearsFind source ↗
  • U.S. Navy, Soil Dynamics and Special Design Aspects, MIL-HDBK-1007/3: response spectrum for 10% exceedance in 100 years (950-year average return period) (Cancelled in 2006; current Department of Defense criteria are in UFC 3-220-01, Geotechnical Engineering, 2012 with Change 3, 2025. The 950-year return period quoted here is a historical example.)Find source ↗
  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section A4, probability of a landslide during a 20-year design lifeFind source ↗Library entry
  • B.G. Look, Handbook of Geotechnical Investigation and Design Tables (2007): Tables 14.5 and 14.6, factors of safety for a 10-year return period rainfall (Current edition: 2nd edition, CRC Press, 2014; this section cites the edition held in the library.)Find source ↗

Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.

← Previous · 3.0 Risk Management Chapter 3.7 — Cost Estimates
Next · 3.0 Risk Management → Chapter 3.9 — Geotechnical Investigation Planning and Scope