3.8.5 Subsidence and Collapse Mechanisms

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.5 Subsidence and Collapse Mechanisms

Chapter 1.1 separates progressive settlement from sudden collapse. The mechanisms below produce sudden collapse. They are the most dangerous for train operations because warning time is short.

MechanismProcessWhere to Expect It
Karst sinkholesSoil ravels into solution cavities in limestone, dolomite or gypsum until the overlying arch collapses (cover-collapse) or sags (cover-subsidence)Karst regions; often triggered by water-table changes or concentrated drainage
Mine subsidenceCollapse of underground workings producing troughs (sag) or pitsAbandoned coal and mineral mining districts
HydrocollapseLow-density, dry soils lose their bonding and compress when first wettedLoess and some arid-region alluvium; triggered by new drainage or leaks
Culvert and pipe failureBackfill lost through corroded or separated barrels leaves voids that collapseAging metal culverts; clay tile and masonry drains
Decay of buried timberRotting of buried trestles and cribbing leaves voids in the fillFills built over or around former timber structures
Leaking utilitiesWater and sewer leaks wash fines into the pipe or away along the trenchUtility crossings (Chapter 2.1, Section 2.1.9)
Burrowing animalsBurrows provide seepage paths and voids in embankmentsEmbankments near water; flood-control levee analogs