3.8.10 Failure Mechanisms of Old Railroad Earthworks

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.10 Failure Mechanisms of Old Railroad Earthworks

Most railroad embankments and cuts were built long before the slopes were designed. Before the 1930s nearly all fills were end-dumped without systematic compaction, at slopes set by experience, and they settled heavily soon after construction. They now carry heavier and more frequent traffic at lower factors of safety than a new earthwork would be given. UK rail and highway owners, who manage the oldest large earthwork network, group the ways these earthworks fail into the mechanisms in Table 3.8-7. Each has its own trigger and season, so the mechanism decides what to inspect, when, and which analysis applies.

Table 3.8-7. Failure mechanisms of existing earthworks and their triggers
MechanismTypical depthTrigger and seasonWhat the track inspector seesAnalysis in this manual
Shallow translational or circular slip3 to 5 ft; survey range 0.7 to 8 ftHeavy rain after a dry season; drainage that is blocked or absentBulging or slumped slope, debris at toe; track usually unaffectedCh 6.3; Ch 6.4.11
Deep-seated first-time or delayed failureDeeper than 3 to 7 ft; may pass through the foundationSlow rise of pore pressure in stiff, high-plasticity clay over years to decades; progressive loss of strengthCrest cracking, track drop and line, toe heaveCh 6.3.6; Ch 2.5
Slide on an old shear surfaceAlong the pre-existing surfaceWet season; repairs that left the old surface in placeRecurring movement at a known slipCh 6.3.6 (residual strength)
Seasonal shrink–swell with ratchetingUpper 3 to 13 ft of clay fillDry summers under high-water-demand trees, then winter wetting; outward movement does not fully recoverSummer settlement and winter heave of track; slow net outward creepCh 2.5; Ch 3.8
Shoulder instabilityCrest and shoulderSteep upper slope, train vibration, fine ash or ballast that dries and runsNarrowing shoulder, ballast loss, tie ends unsupportedSection III (Ch 2.1)
Flooding and toe scourToe and lower slopeHigh stream or river levels beside or through the embankmentToe loss, sudden deep slip after the floodCh 2.8; Ch 6.3
Flow failure in cuttingsShallow, rapidShort, intense rain on permeable soil with run-off concentrated at the crestDebris flow onto the track at the toe of a cutCh 6.4.11; LS-series equations
Frost shattering of rock cutsFace of the cutFreeze–thaw in porous or jointed rock (chalk is especially prone)Debris at the toe; loosened trees fallingCh 2.7

After McGinnity and Saffari (2012), ICE Manual Vol. II, Section 71.2.1, pp. 1069–1073; shallow failure depths from the UK highway survey reported by Nowak (2012), Section 70.1.4, p. 1050. Depths converted from metres.

What the UK network data show. A study of train delays from geotechnical causes on the UK network in 2000–2003 put their cost at about £26 million, concentrated where high-plasticity clays occur. About 80% of the delay time came from about 20% of the incidents. In high-plasticity clay, delays in dry summers were of the same order as those in wet winters. Of 95 ultimate failures recorded later, about half were deep-seated through the crest; the rest were local crest failures, unravelling of oversteepened ash and ballast at the shoulder (mostly in summer), and shallow translational slides. Delayed deep failures were usually on slopes with grass or small shrubs; excessive track movement was usually where large trees grew on the slope (O'Brien, 2013, p. 20).

Progressive failure. In brittle, overconsolidated clay the strength along a developing slip surface drops unevenly from peak toward residual. Skempton's back-analysis of long-term failures in five cuttings in weathered London Clay gave an operating friction angle of about 20° with an average pore pressure ratio ru of 0.25 to 0.35, against laboratory peak values of φ′ = 20°, c′ = 145 psf and residual φ′r = 13°, c′r = 20 psf (McGinnity and Saffari, 2012, p. 1070). The operating strength lies between peak and residual, which is why a peak-strength analysis of an old clay slope overstates its safety.

Name the mechanism before choosing the analysis. A limit-equilibrium factor of safety with a hydrostatic water table answers the deep-seated question only; it says nothing about seasonal track movement, shoulder loss or flow failure, which are the more frequent causes of slow orders on old earthworks.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • McGinnity, B. T. and Saffari, N. (2012). Earthworks asset management and remedial design. Chapter 71 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1067–1086Find source ↗Library entry
  • Nowak, P. A. (2012). Design of new earthworks. Chapter 70 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1047–1066Find source ↗Library entry
  • O'Brien, A. S. (2013). The assessment of old railway embankments – time for a change? In Gallipoli (ed.), Partial Saturation in Compacted Soils, pp. 19–32. ICE PublishingFind source ↗