Most railroad embankments and cuts were built long before the slopes were designed. Before the 1930s nearly all fills were end-dumped without systematic compaction, at slopes set by experience, and they settled heavily soon after construction. They now carry heavier and more frequent traffic at lower factors of safety than a new earthwork would be given. UK rail and highway owners, who manage the oldest large earthwork network, group the ways these earthworks fail into the mechanisms in Table 3.8-7. Each has its own trigger and season, so the mechanism decides what to inspect, when, and which analysis applies.
| Mechanism | Typical depth | Trigger and season | What the track inspector sees | Analysis in this manual |
|---|---|---|---|---|
| Shallow translational or circular slip | 3 to 5 ft; survey range 0.7 to 8 ft | Heavy rain after a dry season; drainage that is blocked or absent | Bulging or slumped slope, debris at toe; track usually unaffected | Ch 6.3; Ch 6.4.11 |
| Deep-seated first-time or delayed failure | Deeper than 3 to 7 ft; may pass through the foundation | Slow rise of pore pressure in stiff, high-plasticity clay over years to decades; progressive loss of strength | Crest cracking, track drop and line, toe heave | Ch 6.3.6; Ch 2.5 |
| Slide on an old shear surface | Along the pre-existing surface | Wet season; repairs that left the old surface in place | Recurring movement at a known slip | Ch 6.3.6 (residual strength) |
| Seasonal shrink–swell with ratcheting | Upper 3 to 13 ft of clay fill | Dry summers under high-water-demand trees, then winter wetting; outward movement does not fully recover | Summer settlement and winter heave of track; slow net outward creep | Ch 2.5; Ch 3.8 |
| Shoulder instability | Crest and shoulder | Steep upper slope, train vibration, fine ash or ballast that dries and runs | Narrowing shoulder, ballast loss, tie ends unsupported | Section III (Ch 2.1) |
| Flooding and toe scour | Toe and lower slope | High stream or river levels beside or through the embankment | Toe loss, sudden deep slip after the flood | Ch 2.8; Ch 6.3 |
| Flow failure in cuttings | Shallow, rapid | Short, intense rain on permeable soil with run-off concentrated at the crest | Debris flow onto the track at the toe of a cut | Ch 6.4.11; LS-series equations |
| Frost shattering of rock cuts | Face of the cut | Freeze–thaw in porous or jointed rock (chalk is especially prone) | Debris at the toe; loosened trees falling | Ch 2.7 |
After McGinnity and Saffari (2012), ICE Manual Vol. II, Section 71.2.1, pp. 1069–1073; shallow failure depths from the UK highway survey reported by Nowak (2012), Section 70.1.4, p. 1050. Depths converted from metres.
What the UK network data show. A study of train delays from geotechnical causes on the UK network in 2000–2003 put their cost at about £26 million, concentrated where high-plasticity clays occur. About 80% of the delay time came from about 20% of the incidents. In high-plasticity clay, delays in dry summers were of the same order as those in wet winters. Of 95 ultimate failures recorded later, about half were deep-seated through the crest; the rest were local crest failures, unravelling of oversteepened ash and ballast at the shoulder (mostly in summer), and shallow translational slides. Delayed deep failures were usually on slopes with grass or small shrubs; excessive track movement was usually where large trees grew on the slope (O'Brien, 2013, p. 20).
Progressive failure. In brittle, overconsolidated clay the strength along a developing slip surface drops unevenly from peak toward residual. Skempton's back-analysis of long-term failures in five cuttings in weathered London Clay gave an operating friction angle of about 20° with an average pore pressure ratio ru of 0.25 to 0.35, against laboratory peak values of φ′ = 20°, c′ = 145 psf and residual φ′r = 13°, c′r = 20 psf (McGinnity and Saffari, 2012, p. 1070). The operating strength lies between peak and residual, which is why a peak-strength analysis of an old clay slope overstates its safety.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.