This section moves from water flowing around and through the embankment to water freezing inside it. Frost hazards belong to the subsidence category of Chapter 1.1 (Keegan 2007). Unlike slope and hydraulic hazards, they start within the soil mass, driven by temperature gradients and the freezing and thawing of pore water. Frost heave and thaw softening from freeze-thaw cycles degrade track geometry, change the vertical force at the wheel-rail interface, and can affect operating safety (Roghani 2021; Roghani, Caldwell et al. 2021; Roghani, Liu and Burgess 2021). In early spring they bring frequent tamping and surfacing and temporary slow orders.
These hazards are deceptive. They develop slowly over weeks, out of sight, and then appear as differential track lift, soft track, cross-level defects or shoulder failures. Because the mechanisms are not intuitive, the warning signs are easy to misread and remedies often treat the symptom rather than the cause. Source material: Ruel (2026b), Part II; see also Selig and Waters (1994), Li et al. (2016) and Ruel (2024).
Differential frost heave is the uneven upward movement of the ground surface caused by ice lenses forming and growing in freezing soil. Water expands about 9% when it freezes; where that expansion is uniform along the track it does little harm. Heave becomes a problem when the ground does not freeze uniformly.
Damaging heave needs three conditions at once (Figure 3.8.8-1):

Remove any one and damaging lenses are unlikely to form. Every remedy in Section 3.8.8.6 works by removing one of the three.
Ice lenses. As the freezing front moves down, freezing creates suction that draws water up from the unfrozen soil and the water table. The water freezes at the front as discrete lenses that grow and push the soil apart, heaving the surface. As the front goes deeper, successive lenses form and the heave accumulates (Figure 3.8.8-2).

Why silt. Frost susceptibility depends on the balance between capillarity and permeability. Silt pores are small enough to produce strong capillary suction yet large enough to move water quickly to the freezing front; water can rise 3 to 7 ft above the water table in silt by capillarity alone. Clean sand has pores too large to sustain much capillary rise. Clay has strong capillarity but is too impermeable to feed lenses fast enough.
Subgrade conditions change quickly along a line, and silt and water are rarely uniform, so heave is not uniform either. Severe heave concentrates in short spots, often only 13 to 33 ft long, where enough silt and water coincide. The track is lifted more in some places than others, producing a rough surface and abrupt changes in elevation at the transitions (Figures 3.8.8-3 and 3.8.8-6).


The thaw is the most dangerous period of the year for track-bed bearing capacity and surface defects (Figure 3.8.8-5):

Highway agencies apply the same principle through spring load-restriction periods. The hazard depends on where the thaw front is relative to the remaining frost, so monitoring both is valuable. The worst heave occurs at maximum frost depth, around the start of surface melt; the worst bearing capacity occurs after moderate thaw, when a soft saturated layer sits on a still-frozen base. Conditions return to normal only when the thaw front reaches the bottom of the frost and the trapped water can drain. Because the loss is predictable and seasonal, it can be managed administratively by reducing axle loads or speeds over vulnerable sections until the subgrade recovers.

Silt liquefaction is the most severe form of the spring loss of bearing capacity. The top of a soft, wet silt layer thaws over hard, still-frozen ground. Heavy, vibrating trains cycle load onto the saturated silt while the frozen base prevents drainage. Pore pressure builds with each load cycle until the silt loses its strength and liquefies. The silt-water mixture is squeezed up and out at the embankment shoulder, leaving voids beneath the track (Figure 3.8.8-7).

Signs.


Silt liquefaction causes differential settlement, a weakened subgrade and shoulder, and hidden voids, and it is a recognized cause of spring derailments. It resolves on its own once the frost is fully out and the trapped water drains, so the danger is confined to the thaw window, but within that window it is acute.
Frost depth controls it. Liquefaction occurs when the thaw front reaches the top of the silt while the silt below is still frozen, which is possible only when frost has penetrated deep into the silt (Figure 3.8.8-10). If the silt did not freeze deeply, it drains and keeps its strength. Evaluate frost depth at locations with a history of silt boils: after a mild winter the risk is low; after a cold winter, inspectors must watch closely for early signs in the spring.


Because frost heave needs silt, water and freezing, every remedy removes one of them. Table 3.8.8-1 lists the measures in broad order of value, starting with drainage.
| Priority | Measure | Condition removed | Key points |
|---|---|---|---|
| 1 | Drainage and subdrainage | Water | The first line of defense and the most cost-effective. Poorly maintained ditches cause roughly three-quarters of frost heave problems, and poor ballast or subballast drainage most of the rest. Clear ditches and daylight the ballast at the shoulder; where water is trapped below the surface, install subdrains (Figure 3.8.8-12). |
| 2 | Marking and salting | Freezing | The most practical treatment for recurring heave spots; reduces differential heave by about 70% for two to three years. |
| 3 | Shimming | None (compensates) | The most common spring response; smooths the surface without disturbing frozen ballast. |
| 4 | Excavate and replace silty soil | Soil | Replace only 50 to 60% of the frost depth, with flat transitions. |
| 5 | Insulation | Freezing | Attenuates heave to match the adjacent track; tapered ends are essential. |
| 6 | Injection or soil treatment | Soil | Cement or chemical mixing, or cement or urethane injection from the surface. |

To stabilize a silt-liquefaction zone, relieve the water pressure at the silt-frost interface while containing the silt. The proven technique is a lateral trench drain that also acts as a reinforcing shear key (Figure 3.8.8-13):


In an emergency, even clean crushed rock without geotextile improves conditions by draining water faster, although silt will slowly migrate into the voids.
Salt lowers the freezing point of the soil moisture, slowing the freezing front and limiting ice lenses (Figure 3.8.8-14).

Shimming compensates for heave rather than curing it. A heave bump produces an abrupt surface change that trains cannot cross safely at normal speed, and severe temporary slow orders, down to 10 mph (16 km/h), may be needed until the surface improves. Tamping is not practical in winter because the ballast is frozen. Shims of different thicknesses placed between rail and tie smooth the transition and gradually raise the track over the heave (Figure 3.8.8-15), following the railway’s track standards. All shims must be removed once the frost bumps go down. Installing them in spring and removing them in summer is slow and labor-intensive, but it remains the most common way of dealing with heave bumps.

Where drainage has been tried and shimming has become too labor-intensive at a chronic location, more disruptive and costly measures may be justified. Replacing the frost-susceptible silt with dry, non-frost-susceptible granular fill fixes the local bump, but the ground on either side keeps heaving slightly, so the repaired zone can become a winter dip that is as hazardous as the bump it replaced. This was common where a culvert was replaced and new granular fill placed over it.

Where the soil or the water cannot be removed, the freezing can be. Rigid extruded polystyrene insulation (Type IV or HI) on a firm granular base beneath the subballast can greatly reduce heave (Figure 3.8.8-17). The aim is to attenuate heave so the insulated zone behaves like the adjacent uninsulated track, not to stop all frost penetration. Tapered transitions at both ends are essential; without them, abrupt differential heave develops exactly where the insulation ends. A designer experienced with thermal insulation should be involved.

Mixing the existing soil with cement or other chemicals, either by excavation and in-place mixing or by injecting cement or urethane through drill holes from the surface, has also been successful (Figure 3.8.8-18; Chapter 7.2).