Chapter 7.2 — Ground Improvement Methods

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel

Primary Reference: USACE EM 1110-1-1804, Geotechnical Investigations (January 2001); FHWA NHI-06-019 (superseded by GEC 13 Ground Modification Methods, FHWA-NHI-16-027 (2017)) "Ground Improvement Methods" (2006); Barron (1948); Priebe (1995); AREMA MRE Chapter 1 (Roadway and Ballast); Kirsch & Bell (2012) "Ground Improvement"; ASTM D698 (Standard Proctor); ASTM D1557 (Modified Proctor).

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Compaction and consolidation values for ground improvement design. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Compaction (168 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Maximum dry unit weightGravel–sand, well graded, cleanGWAASHTO T 99127.3132.1136.9pcfCB T3.2, p.80
Optimum moisture contentGravel–sand, well graded, cleanGWAASHTO T 9989.511%CB T3.2, p.80
Maximum dry unit weightGravel–sand, poorly graded, cleanGPAASHTO T 99117.8122.5127.3pcfCB T3.2, p.80
Optimum moisture contentGravel–sand, poorly graded, cleanGPAASHTO T 991112.514%CB T3.2, p.80
Maximum dry unit weightGravel–sand, well graded, small silt contentGMAASHTO T 99121128.9136.9pcfCB T3.2, p.80
Optimum moisture contentGravel–sand, well graded, small silt contentGMAASHTO T 9981012%CB T3.2, p.80
Maximum dry unit weightGravel–sand, well graded, small clay contentGCAASHTO T 99117.8122.5127.3pcfCB T3.2, p.80
Optimum moisture contentGravel–sand, well graded, small clay contentGCAASHTO T 99911.514%CB T3.2, p.80
Maximum dry unit weightSand, well graded, cleanSWAASHTO T 99111.4122.5133.7pcfCB T3.2, p.80
Optimum moisture contentSand, well graded, cleanSWAASHTO T 99912.516%CB T3.2, p.80
Maximum dry unit weightSand, poorly graded, small silt contentSPAASHTO T 99101.9111.5121pcfCB T3.2, p.80
Optimum moisture contentSand, poorly graded, small silt contentSPAASHTO T 991216.521%CB T3.2, p.80
Maximum dry unit weightSand, well graded, small silt contentSMAASHTO T 99111.4119.3127.3pcfCB T3.2, p.80
Optimum moisture contentSand, well graded, small silt contentSMAASHTO T 991113.516%CB T3.2, p.80
Maximum dry unit weightSand, well graded, small clay contentSCAASHTO T 99108.2117.8127.3pcfCB T3.2, p.80
Optimum moisture contentSand, well graded, small clay contentSCAASHTO T 99111519%CB T3.2, p.80
Maximum dry unit weightSilts, low plasticityMLAASHTO T 9995.5108.2121pcfCB T3.2, p.80
Optimum moisture contentSilts, low plasticityMLAASHTO T 99121824%CB T3.2, p.80
Maximum dry unit weightClays, low plasticityCLAASHTO T 9995.5108.2121pcfCB T3.2, p.80
Optimum moisture contentClays, low plasticityCLAASHTO T 99121824%CB T3.2, p.80
Maximum dry unit weightOrganic silts, low plasticityOLAASHTO T 9982.892.3101.9pcfCB T3.2, p.80
Optimum moisture contentOrganic silts, low plasticityOLAASHTO T 992126.532%CB T3.2, p.80
Maximum dry unit weightSilts, high plasticityMHAASHTO T 997082.895.5pcfCB T3.2, p.80
Optimum moisture contentSilts, high plasticityMHAASHTO T 99243240%CB T3.2, p.80
Maximum dry unit weightClays, high plasticityCHAASHTO T 9982.895.5108.2pcfCB T3.2, p.80
Optimum moisture contentClays, high plasticityCHAASHTO T 991927.536%CB T3.2, p.80
Maximum dry unit weightOrganic silts/clays, high plasticityOHAASHTO T 9966.884.3101.9pcfCB T3.2, p.80
Optimum moisture contentOrganic silts/clays, high plasticityOHAASHTO T 99213345%CB T3.2, p.80
Maximum dry unit weightWell-graded gravel–sand mixturesA-1AASHTO T 99117.8127.3136.9pcfCB T3.3, p.81
Optimum moisture contentWell-graded gravel–sand mixturesA-1AASHTO T 9951015%CB T3.3, p.81
Maximum dry unit weightSilty or clayey gravel and sandA-2AASHTO T 99111.4124.2136.9pcfCB T3.3, p.81
Optimum moisture contentSilty or clayey gravel and sandA-2AASHTO T 99913.518%CB T3.3, p.81
Maximum dry unit weightPoorly graded sandsA-3AASHTO T 99101.9111.5121pcfCB T3.3, p.81
Optimum moisture contentPoorly graded sandsA-3AASHTO T 9958.512%CB T3.3, p.81
Maximum dry unit weightSilty sands and gravels of low plasticityA-4AASHTO T 9995.5111.4127.3pcfCB T3.3, p.81
Optimum moisture contentSilty sands and gravels of low plasticityA-4AASHTO T 99101520%CB T3.3, p.81
Maximum dry unit weightElastic silts, diatomaceous or micaceousA-5AASHTO T 9985.993.9101.9pcfCB T3.3, p.81
Optimum moisture contentElastic silts, diatomaceous or micaceousA-5AASHTO T 992027.535%CB T3.3, p.81
Maximum dry unit weightPlastic clay, sandy clayA-6AASHTO T 9995.5108.2121pcfCB T3.3, p.81
Optimum moisture contentPlastic clay, sandy clayA-6AASHTO T 99102030%CB T3.3, p.81
Maximum dry unit weightHighly plastic or elastic clayA-7AASHTO T 9982.8100.3117.8pcfCB T3.3, p.81
Optimum moisture contentHighly plastic or elastic clayA-7AASHTO T 99152535%CB T3.3, p.81
Maximum dry unit weight (ASTM D698)Well graded clean gravelsGWUFC 3-220-20 Table 3-1125130135pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Well graded clean gravelsGWUFC 3-220-20 Table 3-189.511%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilWell graded clean gravelsGWUFC 3-220-20 Table 3-13.0×10⁻⁴3.0×10⁻³3.0×10⁻²cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Poorly graded clean gravelsGPUFC 3-220-20 Table 3-1115120125pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Poorly graded clean gravelsGPUFC 3-220-20 Table 3-11112.514%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilPoorly graded clean gravelsGPUFC 3-220-20 Table 3-13.0×10⁻³3.0×10⁻²3.0×10⁻¹cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Silty gravelsGMUFC 3-220-20 Table 3-1120127.5135pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Silty gravelsGMUFC 3-220-20 Table 3-181012%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilSilty gravelsGMUFC 3-220-20 Table 3-13.0×10⁻⁶3.0×10⁻⁵3.0×10⁻⁴cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Clayey gravelsGCUFC 3-220-20 Table 3-1115122.5130pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Clayey gravelsGCUFC 3-220-20 Table 3-1911.514%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilClayey gravelsGCUFC 3-220-20 Table 3-13.0×10⁻⁷cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Well graded clean sandsSWUFC 3-220-20 Table 3-1110120130pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Well graded clean sandsSWUFC 3-220-20 Table 3-1912.516%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilWell graded clean sandsSWUFC 3-220-20 Table 3-13.0×10⁻⁴3.0×10⁻³3.0×10⁻²cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Poorly graded clean sandsSPUFC 3-220-20 Table 3-1100110120pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Poorly graded clean sandsSPUFC 3-220-20 Table 3-11216.521%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilPoorly graded clean sandsSPUFC 3-220-20 Table 3-13.0×10⁻³3.0×10⁻²3.0×10⁻¹cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Silty sandsSMUFC 3-220-20 Table 3-1110117.5125pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Silty sandsSMUFC 3-220-20 Table 3-11113.516%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilSilty sandsSMUFC 3-220-20 Table 3-13.0×10⁻⁶3.0×10⁻⁵3.0×10⁻⁴cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Sand-silt-clay, slightly plastic finesSM-SCUFC 3-220-20 Table 3-1110120130pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Sand-silt-clay, slightly plastic finesSM-SCUFC 3-220-20 Table 3-1111315%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilSand-silt-clay, slightly plastic finesSM-SCUFC 3-220-20 Table 3-13.0×10⁻⁸3.0×10⁻⁷3.0×10⁻⁶cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Clayey sandsSCUFC 3-220-20 Table 3-1105115125pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Clayey sandsSCUFC 3-220-20 Table 3-1111519%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilClayey sandsSCUFC 3-220-20 Table 3-13.0×10⁻⁷cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Inorganic silts and clayey siltsMLUFC 3-220-20 Table 3-195107.5120pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Inorganic silts and clayey siltsMLUFC 3-220-20 Table 3-1121824%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilInorganic silts and clayey siltsMLUFC 3-220-20 Table 3-13.0×10⁻⁸3.0×10⁻⁷3.0×10⁻⁶cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Silt-clay mixtureCL-MLUFC 3-220-20 Table 3-1100110120pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Silt-clay mixtureCL-MLUFC 3-220-20 Table 3-1121722%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilSilt-clay mixtureCL-MLUFC 3-220-20 Table 3-13.0×10⁻⁸cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Lean clayCLUFC 3-220-20 Table 3-195107.5120pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Lean clayCLUFC 3-220-20 Table 3-1121824%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilLean clayCLUFC 3-220-20 Table 3-13.0×10⁻⁸cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Organic silts, low plasticityOLUFC 3-220-20 Table 3-18090100pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Organic silts, low plasticityOLUFC 3-220-20 Table 3-1212733%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilOrganic silts, low plasticityOLUFC 3-220-20 Table 3-13.0×10⁻⁸cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Elastic siltsMHUFC 3-220-20 Table 3-17082.595pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Elastic siltsMHUFC 3-220-20 Table 3-1243240%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilElastic siltsMHUFC 3-220-20 Table 3-13.0×10⁻⁹cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Fat clayCHUFC 3-220-20 Table 3-17590105pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Fat clayCHUFC 3-220-20 Table 3-11927.536%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilFat clayCHUFC 3-220-20 Table 3-13.0×10⁻⁹cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Organic claysOHUFC 3-220-20 Table 3-16582.5100pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Organic claysOHUFC 3-220-20 Table 3-11228.545%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilOrganic claysOHUFC 3-220-20 Table 3-13.0×10⁻⁹cm/sUFC322020 T3-1, p.120
Maximum compacted layer thickness by roller typeRock fillTowed vibratory 6 t30inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelTowed vibratory 6 t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltTowed vibratory 6 t18inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayTowed vibratory 6 t10inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseTowed vibratory 6 t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseTowed vibratory 6 t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeRock fillTowed vibratory 10 t59inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelTowed vibratory 10 t39inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltTowed vibratory 10 t28inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayTowed vibratory 10 t14inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseTowed vibratory 10 t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseTowed vibratory 10 t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeRock fillTowed vibratory 15 t79inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelTowed vibratory 15 t59inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltTowed vibratory 15 t39inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayTowed vibratory 15 t20inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseTowed vibratory 15 t31inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelTowed padfoot 6 t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltTowed padfoot 6 t18inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayTowed padfoot 6 t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseTowed padfoot 6 t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelTowed padfoot 10 t39inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltTowed padfoot 10 t28inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayTowed padfoot 10 t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseTowed padfoot 10 t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelSelf-propelled vibratory 7 (3) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltSelf-propelled vibratory 7 (3) t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClaySelf-propelled vibratory 7 (3) t6inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseSelf-propelled vibratory 7 (3) t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseSelf-propelled vibratory 7 (3) t10inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeRock fillSelf-propelled vibratory 10 (5) t30inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelSelf-propelled vibratory 10 (5) t20inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltSelf-propelled vibratory 10 (5) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClaySelf-propelled vibratory 10 (5) t8inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseSelf-propelled vibratory 10 (5) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseSelf-propelled vibratory 10 (5) t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeRock fillSelf-propelled vibratory 15 (10) t59inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelSelf-propelled vibratory 15 (10) t39inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltSelf-propelled vibratory 15 (10) t28inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClaySelf-propelled vibratory 15 (10) t14inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseSelf-propelled vibratory 15 (10) t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseSelf-propelled vibratory 15 (10) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelSelf-propelled vibratory 8 (4) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltSelf-propelled vibratory 8 (4) t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClaySelf-propelled vibratory 8 (4) t8inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseSelf-propelled vibratory 8 (4) t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelSelf-propelled padfoot 11 (7) t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltSelf-propelled padfoot 11 (7) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClaySelf-propelled padfoot 11 (7) t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseSelf-propelled padfoot 11 (7) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelSelf-propelled padfoot 15 (10) t39inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltSelf-propelled padfoot 15 (10) t28inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClaySelf-propelled padfoot 15 (10) t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseSelf-propelled padfoot 15 (10) t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelVibratory tandem 2 t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltVibratory tandem 2 t8inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayVibratory tandem 2 t4inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseVibratory tandem 2 t8inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseVibratory tandem 2 t6inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelVibratory tandem 7 t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltVibratory tandem 7 t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayVibratory tandem 7 t6inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseVibratory tandem 7 t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseVibratory tandem 7 t10inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelVibratory tandem 10 t20inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltVibratory tandem 10 t14inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayVibratory tandem 10 t8inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseVibratory tandem 10 t16inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseVibratory tandem 10 t12inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelVibratory tandem 13 t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltVibratory tandem 13 t18inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayVibratory tandem 13 t10inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbaseVibratory tandem 13 t18inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement baseVibratory tandem 13 t14inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSand and gravelPadfoot tandem 18 t35inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeSiltPadfoot tandem 18 t28inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typeClayPadfoot tandem 18 t24inLOOK23 T7.8, p.223
Maximum compacted layer thickness by roller typePavement subbasePadfoot tandem 18 t24inLOOK23 T7.8, p.223
Open this set in the database ↗
Coefficient of consolidation (33 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of consolidationLow plasticity claysCL32.29118.4204.5ft²/yrCB T5.3, p.114
Coefficient of consolidationLow plasticity glacial lake claysCL21.5326.932.29ft²/yrCB T5.3, p.114
Coefficient of consolidationLow plasticity mudCL6.469.712.92ft²/yrCB T5.3, p.114
Coefficient of consolidationMedium plasticity claysCL-CH9.69ft²/yrCB T5.3, p.114
Coefficient of consolidationVolcanic siltMH3.234.3055.38ft²/yrCB T5.3, p.114
Coefficient of consolidationOrganic siltOL6.4619.432.29ft²/yrCB T5.3, p.114
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHUndisturbed – virgin compression1,292ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHUndisturbed – virgin compression538.2ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHUndisturbed – virgin compression215.3ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHUndisturbed – virgin compression107.6ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHUndisturbed – virgin compression53.82ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHUndisturbed – virgin compression32.29ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHUndisturbed – virgin compression16.15ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHUndisturbed – virgin compression10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHUndisturbed – virgin compression9.69ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHUndisturbed – recompression215.3ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHUndisturbed – recompression107.6ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHUndisturbed – recompression53.82ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHUndisturbed – recompression32.29ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHUndisturbed – recompression21.53ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHUndisturbed – recompression10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHUndisturbed – recompression8.61ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHUndisturbed – recompression6.46ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHUndisturbed – recompression5.38ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHRemolded43.06ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHRemolded21.53ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHRemolded16.15ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHRemolded10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHRemolded6.46ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHRemolded4.31ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHRemolded3.77ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHRemolded3.23ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHRemolded2.69ft²/yrLOOK T8.14, p.122
Open this set in the database ↗
Vibration limits near structures (vibro-compaction, dynamic compaction) (50 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Cosmetic damage guide value, peak particle velocityReinforced or framed structures; industrial and heavy commercial4 Hz and above1.97in/sFGE T20.3, p.307
Cosmetic damage guide value, peak particle velocityUnreinforced or light framed; residential and light commercial4 Hz rising to 15 Hz0.590.690.79in/sFGE T20.3, p.307
Cosmetic damage guide value, peak particle velocityUnreinforced or light framed; residential and light commercial15 Hz rising to 40 Hz and above0.791.381.97in/sFGE T20.3, p.307
Maximum zero-to-peak displacement below 4 HzUnreinforced or light framed; residential and light commercialBelow 4 Hz0.024inFGE T20.3, p.307
Human perception threshold, peak particle velocityPeople indoorsBlast or construction vibration0.02in/sFGE text, p.529
Damage potential threshold, peak particle velocity – transient sourcesExtremely fragile historic buildings, ruins, ancient monumentsBlasting, drop balls0.12in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – continuous or frequent sourcesExtremely fragile historic buildings, ruins, ancient monumentsImpact and vibratory pile driving, vibratory compaction0.08in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – transient sourcesFragile buildingsBlasting, drop balls0.2in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – continuous or frequent sourcesFragile buildingsImpact and vibratory pile driving, vibratory compaction0.1in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – transient sourcesHistoric and some old buildingsBlasting, drop balls0.5in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – continuous or frequent sourcesHistoric and some old buildingsImpact and vibratory pile driving, vibratory compaction0.25in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – transient sourcesOlder residential structuresBlasting, drop balls0.5in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – continuous or frequent sourcesOlder residential structuresImpact and vibratory pile driving, vibratory compaction0.3in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – transient sourcesNew residential structuresBlasting, drop balls1in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – continuous or frequent sourcesNew residential structuresImpact and vibratory pile driving, vibratory compaction0.5in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – transient sourcesModern industrial/commercial buildingsBlasting, drop balls2in/sCALTRANS T19, p.27
Damage potential threshold, peak particle velocity – continuous or frequent sourcesModern industrial/commercial buildingsImpact and vibratory pile driving, vibratory compaction0.5in/sCALTRANS T19, p.27
Human annoyance potential, peak particle velocity – transient sourcesBarely perceptible0.04in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – continuous or frequent sourcesBarely perceptible0.01in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – transient sourcesDistinctly perceptible0.25in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – continuous or frequent sourcesDistinctly perceptible0.04in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – transient sourcesStrongly perceptible0.9in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – continuous or frequent sourcesStrongly perceptible0.1in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – transient sourcesSevere2in/sCALTRANS T20, p.27
Human annoyance potential, peak particle velocity – continuous or frequent sourcesSevere0.4in/sCALTRANS T20, p.27
Vibration attenuation exponent nSoil class I – Weak or soft soils (loose, peat, organic, topsoil)Suggested value1.4–CALTRANS T17, p.22
Vibration attenuation exponent nSoil class II – Competent soils (most sands, sandy and silty clays, gravel, weathered rock)Suggested value1.3–CALTRANS T17, p.22
Vibration attenuation exponent nSoil class III – Hard soils (dense compacted sand, glacial till, some rock)Suggested value1.1–CALTRANS T17, p.22
Vibration attenuation exponent nSoil class IV – Hard, competent rockSuggested value1–CALTRANS T17, p.22
Blast vibration PPV threshold effectPerceptible to humansBlasting0.120.160.2in/sWYLLIE T11.6, p.267
Blast vibration PPV threshold effectApproximate limit for poorly constructed and historic buildingsBlasting0.39in/sWYLLIE T11.6, p.267
Blast vibration PPV threshold effectObjectionable to humansBlasting1.31.652in/sWYLLIE T11.6, p.267
Blast vibration PPV threshold effectRisk of structural damage very slight (< 5%)Blasting2in/sWYLLIE T11.6, p.267
Blast vibration PPV threshold effectMinor damage, plaster cracking, serious complaintsBlasting4.9in/sWYLLIE T11.6, p.267
Blast vibration PPV threshold effectCracks in concrete blocksBlasting9.1in/sWYLLIE T11.6, p.267
Allowable PPV in fresh mass concrete vs age (× distance factor)Mass concrete0–4 hours4in/sWYLLIE T11.7, p.268
Allowable PPV in fresh mass concrete vs age (× distance factor)Mass concrete4 hours to 1 day6in/sWYLLIE T11.7, p.268
Allowable PPV in fresh mass concrete vs age (× distance factor)Mass concrete1–3 days9in/sWYLLIE T11.7, p.268
Allowable PPV in fresh mass concrete vs age (× distance factor)Mass concrete3–7 days12in/sWYLLIE T11.7, p.268
Allowable PPV in fresh mass concrete vs age (× distance factor)Mass concrete7–10 days15in/sWYLLIE T11.7, p.268
Allowable PPV in fresh mass concrete vs age (× distance factor)Mass concreteMore than 10 days20in/sWYLLIE T11.7, p.268
Blast attenuation constant k (PPV = k (R/√W)^β)AverageR in ft, W in lb per delay; β ≈ −1.6160in/sWYLLIE Fig. 11.18, p.265
Blast attenuation constant k (PPV = k (R/√W)^β)Typical upper bound (90%)R in ft, W in lb per delay; β ≈ −1.6242in/sWYLLIE Fig. 11.18, p.265
Blast attenuation constant k (PPV = k (R/√W)^β)High confinement, coupling and rock strength (99%)R in ft, W in lb per delay; β ≈ −1.6605in/sWYLLIE Fig. 11.18, p.265
Recommended minimum distance from vibrating roller to nearest buildingRoller class I Small< 1.25 t (maintenance)10 ft; not restricted on roadsftLOOK23 T7.7, p.222
Recommended minimum distance from vibrating roller to nearest buildingRoller class II Light1–2 t16 ft; not restricted on roadsftLOOK23 T7.7, p.222
Recommended minimum distance from vibrating roller to nearest buildingRoller class III Light–medium2–4 t16–33 ftftLOOK23 T7.7, p.222
Recommended minimum distance from vibrating roller to nearest buildingRoller class IV Medium4–6 t33–66 ft; not advised on city and suburban streetsftLOOK23 T7.7, p.222
Recommended minimum distance from vibrating roller to nearest buildingRoller class V Heavy7–11 t66–130 ft; not advised in built-up areasftLOOK23 T7.7, p.222
Recommended minimum distance from vibrating roller to nearest buildingRoller class VI Very heavy> 12 tRural areas away from structures onlyftLOOK23 T7.7, p.222
Open this set in the database ↗
References (7)
  1. CALTRANS – California Department of Transportation (2004). Transportation- and Construction-Induced Vibration Guidance Manual (Jones & Stokes, June 2004).
  2. CB – Carter, M. & Bentley, S.P. (2016). Soil Properties and their Correlations, 2nd ed. Wiley.
  3. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
  4. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.
  5. LOOK23 – Look, B.G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press / Taylor & Francis.
  6. UFC322020 – U.S. Department of Defense (2025). UFC 3-220-20, Foundations and Earth Structures (NAVFAC DM-7.2), 16 January 2025.
  7. WYLLIE – Wyllie, D.C. & Mah, C.W. (2004). Rock Slope Engineering: Civil and Mining, 4th ed. Spon Press.

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
7.2.0 Executive Summary

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or facility loads without unacceptable settlement, slope instability, or bearing capacity failure. Railroad projects present a concentrated set of ground improvement challenges: soft coastal and alluvial clays crossed by Class I railroad mainlines, expansive Prairie clays along Class I railroad corridors, loose liquefiable sands requiring treatment for Class I railroad facilities, and organic deposits that underlie historic rail alignments across multiple clients.

This chapter presents methods for: (1) densification by compaction — mechanical, dynamic, and vibratory; (2) consolidation acceleration using prefabricated vertical drains (PVDs) with staged embankment loading; (3) stone column reinforcement with the Priebe method for composite stiffness; (4) deep soil mixing (DSM) for soft clay improvement and liquefaction mitigation; (5) grouting — permeation, compaction, and jet grouting; (6) lime and cement stabilization; and (7) geosynthetic reinforcement for embankment and subgrade applications. All equations are in English units.

Deep Soil Mixing
Deep Soil Mixing
Engineering Dynamics and Geosynthetics
Engineering Dynamics and Geosynthetics
Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
IS-14Undrained shear strength from CPTSᵤ
IS-17Preconsolidation stress / OCR from CPTσ'ₚ, OCR
IS-20Hydraulic conductivity from CPTk
IS-03Relative density of sand from SPTDᵣ
IS-16Relative density of sand from CPTDᵣ
IS-19Constrained modulus from CPTM
IX-11Hazen hydraulic conductivityk
7.2.1 Background and Railroad Context

Railroad ground improvement projects carry constraints not present in highway or building construction:

  • Active operations: Most ground improvement beneath or adjacent to active track must be designed for minimal vibration transmission to avoid track geometry disturbance. Dynamic compaction and heavy drop weights are generally prohibited within 100 ft of active track without client-approved vibration monitoring protocols.
  • Access limitations: Narrow railroad rights-of-way — often 50–100 ft between fence lines — limit crane swing radii, restricting some methods (stone columns, auger-cast piles) to compact equipment configurations.
  • Track geometry tolerance: Post-improvement differential settlement criteria are driven by FRA track class tolerances (Chapters 6.2 and 3.9), not building codes. Methods must be designed to achieve residual differential settlement within those limits.
  • Rapid execution: Emergency and programmatic track improvement projects often have compressed schedules. Methods selected must be compatible with railroad-standard maintenance windows (e.g., 4-hour possession on mainline, weekend gang windows on secondary).
Ground Improvement Methods
Ground Improvement Methods
Soil Compaction & Ground Improvement Techniques
Soil Compaction & Ground Improvement Techniques
Table 7.2-1: Ground Improvement Method Selection
RailroadPreferred MethodsProhibited/Restricted MethodsGoverning Standard
AREMAAll methods per site conditionsPer owner approvalAREMA MRE Chapter 1

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

Improving the formation layer under an existing track

Many old lines were built without a formation layer. When speed or axle load is raised, the simplest fix is to thicken the track bed during maintenance, but clearance limits or stress targets often rule that out, and the formation layer itself must be improved or installed. The UIC methods compiled by Profillidis differ mainly in possession time, excavation depth and output:

Table 7.2-5. Methods for improving the formation layer under traffic (summary)
MethodExcavation below top of railSpeed on improved track (mph)Track removed?Output (ft/h)
Earthmoving machinery, short sections (< 330 ft)4 ft25–50Yes500
Earthmoving machinery, longer sections (> 330 ft)4 ft43–62Yes500
Track-laying machinery4 ft43–62No (yes with geotextile)66–130
Ballast screening machine33 in.25–37No295
PUSCAL II formation-improvement machine4.6 ft31–50Yes59
PM 200 formation-improvement machine3.6 ft43No115–150
Thermal insulation sheets laid by ballast screener SPX33 in.25No330
Figure 7.2-13. Rolling out geotextile ahead of subgrade rebuilding.
Figure 7.2-13. Rolling out geotextile ahead of subgrade rebuilding.

Excavating deeper than 4 ft makes the stability of the adjacent track critical. Full table, with possession hours and man-hours, in Figure 7.2-11.

Figure 7.2-11. Methods for improving the formation layer, with possession, transport, depth, speed, man-hour and output data. Profillidis Table 9.4.
Figure 7.2-11. Methods for improving the formation layer, with possession, transport, depth, speed, man-hour and output data. Profillidis Table 9.4.

Formation rehabilitation machines insert a new sand–gravel formation layer at the top of the subgrade without removing the track. They are the substructure equivalent of ballast cleaning, for sites where subgrade bearing capacity, not ballast condition, is the problem.

After Profillidis (2014), §9.7.2, §16.8, Table 9.4; after UIC Code 722R. Full reference under Supplemental References.

Subgrade stabilization categories and costs

Subgrade stabilization follows the same logic as slope work. Rehabilitate drainage first, then reinforce the substructure below the ballast and the track structure above it, and improve the ground itself where the problem runs deep.

Table 7.2-6. Remedial categories and indicative costs (course figures, 2016 dollars)
CategoryExamplesIndicative cost (2016 $)
Improve structure above trackEliminate joints, heavier rail, swamp tiesSwamp ties ~$670,000/mile [2012: ~$600,000]
Improve substructure below ballastUndercutting / ballast replacement, geogrid, HMA underlaymentUndercutting ~$280,000/mile [2012: ~$250,000]
Improve subgrade strengthShear key, cross trench, cement or grout injection, remove and replaceSite-specific
UnderpinningMicropiles, screw pilesSite-specific
(Reference) new construction~$6,700,000/mile [2012: ~$6,000,000]

Cost basis: The course figures were in 2012 dollars. They are escalated here to 2016 dollars with the ENR Construction Cost Index (20-city annual average): 10,338 (2016) ÷ 9,308 (2012) = 1.111, an increase of about 11%. Values are rounded; 2012 values are shown in brackets. To move to another year, multiply the 2012 value by CCIyear ÷ 9,308. Railroad work (track time, work trains, flagging, remote access) can vary by far more than the index change, so treat these as order-of-magnitude figures.

After Geotechnology for Railroaders Program, Module 6.2; §01. Full reference under Supplemental References.

Improvement options for existing track

Selig and Waters group the options for existing track into four families:

  • In place: penetration or compaction grouting, lime-slurry injection, electro-osmosis and electrochemical treatment.
  • Reconstruction: compaction, replacement, or admixtures of cement, lime, fly ash or bitumen.
  • Asphalt: full depth or underlayment (Section III, §3.8).
  • Slip stabilization: drainage, retaining structures, slope changes.

Notes on the in-place methods.

  • Electro-osmosis and electrochemical stabilization work from beside the track without interrupting traffic, but they are very expensive.
  • Lime-slurry injection (50–250 psi) follows existing fissures, so placement is poorly controlled. Where K0 < 1 the hydrofractures run vertically, and the slurry can escape into the ballast. Results have been mixed and sometimes adverse, with temporary weakening and lime-fouled ballast. Run a full-scale trial before committing.

After Selig & Waters (1994), ch. 11. Full reference under Supplemental References.

Project management · Sears et al. (2015)

Choosing the Delivery Method and Pricing Basis

Sears et al. separate two decisions that are often blurred together: how the project is delivered and how the contractor is paid.

Delivery methods.

  • Design-bid-construct. The design is finished before bidding. The owner knows the configuration and cost before committing, but the process is the slowest.
  • Fast-tracking (phased construction). Packages are let as each part of the design is completed. This saves time but adds coordination risk.
  • Design-construct. One firm designs and builds, bringing contractor knowledge of methods, cost and time into the design. It is usually negotiated.
  • Construction management. Agency CM advises the owner and builds nothing. CM-at-risk commits to cost and schedule at an early stage of design.
  • Turnkey and build-operate-transfer. These extend the contractor’s responsibility further, into areas such as financing and operation.

Pricing bases.

  • Lump sum. Suitable only when both the nature and the quantity of the work can be fixed before award.
  • Unit price. Suited to work whose nature is well defined but whose quantities cannot be forecast accurately. The contractor is paid measured quantities at bid rates, subject to any clause allowing rates to be renegotiated for large quantity changes.
  • Cost-plus-fee. The fee is a percentage or a fixed sum, often with incentives or a guaranteed maximum.
  • Force account. The owner does the work with its own forces, or the contractor works under owner direction on time and materials for work that cannot be defined or has changed. Public agencies usually limit force account to maintenance, repair and emergencies.

Selection. The authors also describe best-value selection, which scores price together with qualifications, as increasingly accepted.

For railroad work: Ground improvement is where these choices matter most, because the quantity of ground treated is uncertain and the result is a performance outcome rather than a quantity. Practical pairings to consider:

  • Unit-price contracts for undercutting, blanket placement and grouting, where the method is known but depth and take are not.
  • Design-build with a performance specification for proprietary systems such as deep soil mixing, rigid inclusions or compaction grouting, with acceptance tied to verification testing and settlement monitoring.
  • Force account or time-and-materials for slide emergency response, converting to a defined contract once the failure is mapped.

Whatever the method, the GSPs and the geotechnical report should state which party carries quantity risk and which carries performance risk.

Source: Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons, pp. 6–13. Summarized and paraphrased. Full reference under Supplemental References.

7.2.2 Compaction Methods
7.2.2.1 Proctor Compaction Fundamentals

The relationship between dry unit weight and moisture content is defined by the Proctor test. The maximum dry unit weight γ_d,max and optimum moisture content w_opt are the design targets for compaction control (Chapter 5.3).

Understanding Soil Behavior — Compaction
Understanding Soil Behavior — Compaction
Soil Compaction
Soil Compaction
Vibrocompaction process
Vibrocompaction process
Sand compaction pile construction, Hollister CA
Sand compaction pile construction, Hollister CA
Blast densification — casing placement
Blast densification — casing placement

Zero Air Voids (ZAV) line:

γZAV = Gs ⋅ γw1 + w ⋅ Gs    (pcf)

Where G_s = specific gravity (≈ 2.70 for most soils); γ_w = 62.4 pcf; w = water content (decimal).

Relative compaction (RC):

RC = γd,fieldγd,max × 100%

Standard Proctor (ASTM D698): 12,400 ft·lb/ft³ compactive effort; appropriate for light to moderate railroad facility construction. Modified Proctor (ASTM D1557): 56,000 ft·lb/ft³ compactive effort; commonly specified for intermodal yards, bridge approach fills and railroad embankments.

Standard Proctor Test
Standard Proctor Test
Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
Gsspecific gravity (≈ 2.70 for most soils)Lab testSpecific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested.2.64–2.80 mineral; lower if organic · by USCS group
wwater content (decimal).Lab testOven-dry water content of samples (ASTM D2216); field check by microwave (D4643) or nuclear gauge (D6938).gravels/sands 3–25%, clays 15–70% · by USCS group
7.2.2.2 Vibratory Compaction

Vibratory compaction (smooth drum, padfoot) densifies granular fills and coarse-grained subgrades. Compaction effectiveness is described by the influence depth Z_eff:

Withdrawal of vibratory probe
Withdrawal of vibratory probe
Zeff = k √WAf    (ft)

Where W = drum weight (lb); A_f = drum contact area (ft²); k = empirical constant (0.08–0.12 for granular materials).

Lift thickness limits by soil type:

  • Granular (GW, GP, SW): 12–18 in. uncompacted
  • Silty/clayey soils (SM, SC, ML, CL): 8–12 in. uncompacted
  • Heavy clay (CH): 6–8 in. uncompacted (padfoot drum required)
Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
Wdrum weight (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Afdrum contact area (ft²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
kempirical constant (0.08–0.12 for granular materials).Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
7.2.2.3 Dynamic Compaction

Dynamic compaction densifies loose fills and granular soils by repeated high-energy drops of a heavy pounder (10,000–30,000 lb) from heights of 30–90 ft.

Dynamic compaction crater inspection
Dynamic compaction crater inspection
High-energy impact roller
High-energy impact roller
Dynamic Compaction
Dynamic Compaction

Influence depth (Menard & Broise 1975):

D = n √Wh ⋅ H    (m)

Where (metric, as published; multiply D by 3.28 for feet):

  • W_h = weight of pounder (metric tons)
  • H = drop height (m)
  • n = empirical efficiency factor (0.35–0.65; 0.50 typical for saturated granular soil)

Energy per unit area:

E = ndrops ⋅ Wh ⋅ HAgrid    (ton·ft/ft²)

For railroad applications, dynamic compaction is restricted to areas beyond client setback from active track (Table 7.2-1). Vibration monitoring (Chapter 5.3) with a peak particle velocity (PPV) threshold of 0.5 in./s at the nearest track is commonly required.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
Whweight of pounder (tons)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Hdrop height (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
nempirical efficiency factor (0.35–0.65Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Supplemental reference

What densification can realistically achieve

Table 17-S2. Upper-bound test values after deep dynamic compaction (GEC 13, Table 4-2, from FHWA 1986)

Soil typeSPT N (blows/ft)CPT qc (tsf)PMT limit pressure (tsf)
Pervious coarse-grained: sands and gravel30–50200–30020–25
Semipervious: sandy silts25–35135–17714.6–20
Semipervious: silts and clayey silts20–35104–13510.4–14.6
Partially saturated impervious: clay fill, mine spoil20–40*N/A14.6–20
Landfills15–40*N/A5.2–10.4

* Higher values may reflect large particles. These are maxima for estimating what is possible; verify actual improvement by testing while the equipment is still on site, and allow for delayed improvement as pore pressures dissipate.

Rapid impact compaction (RIC) is a smaller-footprint alternative where the setbacks in Table 7.2-1 rule out a crane and pounder. A 5–9 ton weight on an excavator drops about 4 ft onto a 5-ft-diameter tamper at 40–60 blows/min. It densifies granular fills, ash and building waste to about 10–20+ ft and covers about 9,000–30,000 ft2 per shift. Groundwater should be at least 3 ft below the surface. It is not recommended for weak, low-permeability, clayey or high-fines soils. Energy and set per blow are recorded for QC, with SPT or CPT before and after for QA. Recorded peak noise was about 88 dBA. The depth of compaction cannot be controlled precisely.

Dynamic compaction — crane and tamper
Dynamic compaction — crane and tamper
Blast densification — surface expression
Blast densification — surface expression
Rapid Impact Compaction — First Pass
Rapid Impact Compaction — First Pass
Rapid Impact Compaction — Hammer and Anvil Foot
Rapid Impact Compaction — Hammer and Anvil Foot
Rapid Impact Compaction in Progress
Rapid Impact Compaction in Progress

Jet grouting diameters reported by SHRP2 range from about 3 to 15 ft (larger than the 1.5–5 ft in Section 7.2.6.3, which reflects smaller systems). Depths are generally under 100 ft but exceed 160 ft in some cases. Soilcrete strength reflects the soil (higher in sands and gravels). Highly plastic clays and fibrous peat erode poorly and are not recommended. Spoil must be removed continuously, and surface or lateral movement must be watched — an important check beneath or next to track.

Source: Schaefer, V. R. et al. (2017). Ground Modification Methods Reference Manual, Vol. I. Geotechnical Engineering Circular No. 13, FHWA-NHI-16-027 · SHRP2 R02 / GeoTechTools (2012). Rapid Impact Compaction and Jet Grouting fact sheets

Technology sheets for this method · see 7.2.16 Technology Library

Large crane and 14.0 Mg tamper for dynamic compaction
Photo 7.2.2-1. Large crane and 14.0 Mg (30.9 kips) tamper for dynamic compaction. From Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
13.6 Mg tamper and crater formed during dynamic compaction
Photo 7.2.2-2. 13.6 Mg (30.0 kips) tamper and crater formed during dynamic compaction. From Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Hammer and anvil portion of a rapid impact compactor
Photo 7.2.2-3. Hammer and anvil portion of rapid impact compactor. Courtesy of Peter Becker.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rapid impact compactor following the first pass of compaction points, with craters visible in the ground
Photo 7.2.2-4. Rapid impact compactor following first pass of compaction points. Courtesy of Peter Becker.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rapid impact compactor in the process of compaction, tamper foot engaged with the ground
Photo 7.2.2-5. Rapid impact compactor in the process of compaction. Courtesy of Peter Becker.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Case study: 7.2.17.1 Measuring roller force with pile-driving monitors (Look 2023), in §17.17 Case Studies.

CIR deceleration data map during initial IR passes
Photo 7.2.2-6. Initial passes Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
CIR deceleration data map after 40 IR passes
Photo 7.2.2-7. After 40 IR passesSource: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Broons BH-1300 four-sided impact roller towed by a four-wheel drive tractor
Photo 7.2.2-8. Broons (BH-1300) four-sided ("square") impact roller towed using a four-wheel drive heavy tractor. Photograph from http://www.broons.com/impact/Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Impactor 2000 square impact roller in the field
Photo 7.2.2-9. Impactor 2000 "square" impact roller. Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Landpac 25-kJ three-sided impact roller in operation
Photo 7.2.2-10. Landpac 25-kJ three-sided impact roller. Photograph from www.landpac.co.za, courtesy of Land Pac®.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Labeled diagram of vibratory compaction equipment: a crane-mounted mast lowers a vibrator and probe into the ground, connected to a control unit, powerpack, and
Photo 7.2.2-11. Main elements of vibratory compaction equipment. After Massarsch and Fellenius (2005).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Grain size distribution chart with four zones A, B, C, and D bounded by percent passing versus grain size, showing the range of soil gradations suitable for vib
Photo 7.2.2-12. Range of soil types treated by vibrocompaction. Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Three-panel line diagram showing the generic vibrocompaction process: probe penetration, backfill addition, and probe withdrawal with densified soil column
Photo 7.2.2-13. Generic vibrocompaction process. Figure courtesy of FHWA, Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Crane-suspended probe-type vibrator being lowered into the ground at a vibrocompaction site
Photo 7.2.2-14. Probe-type vibrator being lowered into the ground. Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Vibroflotation equipment and crane operating on a large sand island construction site, Palm Island, Dubai
Photo 7.2.2-15. Vibroflotation (vibrocompaction) at Palm Island, Dubai. Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
7.2.2.4 Compaction Control and Lime-Treated Fill: Lessons from UK Practice

Method and end-product specification

UK earthworks specifications control compaction in two ways. A method specification fixes the plant, layer thickness and number of passes for each material class, with daily records of what was done. An end-product specification sets a minimum compacted state that is tested in place; a layer should not be covered until it has been shown to comply (Dumelow, 2012, Section 75.5, pp. 1119–1133). AREMA and most railroad specifications are end-product (percent of maximum dry density at a moisture range), so the testing frequency and the hold on covering a layer are what make them work.

Table 7.2-12. Rapid field acceptability tests for cohesive fill used in UK practice
TestTimeTypical acceptable limitConstraint
Moisture Condition Value (MCV)About 15 min8 to 16Must be correlated with fundamental tests for each material; weak for granular or very silty or sandy soils
Hand shear vaneAbout 1 minOver about 1,460 psf (70 kPa)Not suitable for clay with much sand or gravel

Dumelow (2012), p. 1133. Shear strength converted from kPa.

Lime treatment: the size of the clods matters

Bender-element tests on a clayey soil treated with 3% lime and compacted to a dry density of about 100 pcf (1.60 Mg/m³) found (Tang, Vu and Cui, 2011, pp. 35–44):

  • Lime raised the small-strain stiffness sharply; about 200 hours after treatment the stiffness no longer depended on the moulding water content.
  • The larger the maximum clod size (0.016 to 0.2 in., 0.4 to 5 mm, in the tests), the lower the stiffness. Field clods can be inches across, so laboratory specimens prepared from finely ground soil overstate field stiffness.
  • Wetting–drying cycles cut the stiffness of untreated specimens through microcracking but changed treated specimens little; only drying well below the initial water content cracked the treated soil.

For lime-treated subgrade and fill, specify pulverisation (Section 7.2.7), prepare laboratory mixes at the field clod size, and protect the treated layer from drying out before it is covered.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Dumelow, P. G. (2012). Earthworks material specification, compaction and control. Chapter 75 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1115–1142Find source ↗Library entry
  • Tang, A. M., Vu, M. N. and Cui, Y.-J. (2011). Effects of the maximum soil aggregates size and cyclic wetting–drying on the stiffness of a lime-treated clayey soil. Géotechnique 61(5); reprinted in Partial Saturation in Compacted Soils, pp. 35–44Find source ↗
Supplemental reference · Lu, Filz and Han (2009)

Dynamic Compaction of Dumped Rock-and-Soil Fill

A building pad in mountainous terrain sat on 6.5 to 26 ft of weathered rock and soil that had been end-dumped without compaction two years earlier. Most particles were 0.2 to 8 in., with some over 20 in., and the fill carried only about 1,500 to 2,100 psf. Treatment used two high-energy passes of about 2,200 kip-ft per drop, followed by two lighter ironing passes of about 1,100 and 740 kip-ft.

  • Plate load tests after treatment gave an ultimate bearing pressure above 9,000 psf and a secant modulus of about 5,000 psi.
  • Sand cone tests and ground-penetrating radar both showed improvement to at least 20 ft, with relative compaction above 95%.
  • The strip footings built on the treated fill settled little and stabilized quickly.

For railroad work: Old side-cast and end-dumped fills of rock and soil are common along mountain grades and at abandoned yards. The case shows that coarse, boulder-bearing fill can be brought to a reliable bearing surface by dynamic compaction where vibration limits allow it, and that GPR is a practical way to confirm the depth of improvement. Keep the vibration limits of Section 7.2.2.3 for any work near live track, signals and structures.

Source: Lu, Filz and Han (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Yan, Dong and Chu (2009)

Explosive Replacement of Soft Clay with Crushed Stone

Explosives are best known in ground improvement for densifying loose saturated sand (see the blasting densification sheet in Section 7.2.16). This paper describes a different use: explosive replacement. Crushed stone is stockpiled beside the area to be treated, charges are set in the soft clay in a planned pattern, and the blast opens cavities into which the stockpile slides. Charge weight and spacing were set from blast-cavity equations.

  • On a highway project the stone was densely packed in the top 16 to 20 ft, but in the bottom 10 to 13 ft it was mixed into the clay.
  • Ground-penetrating radar located the dense stone layer reliably.

For railroad work: Explosive replacement is a remote-site option for building a new alignment across a shallow soft clay or organic deposit where excavation and replacement would be slow. It is not suited near operating track or structures. Expect incomplete replacement at the base of the deposit and verify with borings and GPR.

Source: Yan, Dong and Chu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Singh and Hymavathi (n.d.)

Dynamic Replacement and Rotational Dynamic Compaction

Dynamic replacement uses heavy tamping to drive large pillars of imported granular material into soft saturated soil. The craters are filled with stone or sand and pounded again, forming columns that both reinforce the soil and drain it. The soil between the pillars is compressed, and the excess pore pressure this creates takes hours to dissipate, so passes are spaced in time. Rotational dynamic compaction drops a tamper that also rotates as it falls; in comparative trials it penetrated about twice as far as a conventional tamper and gave higher cone resistance, increasing the depth of improvement in granular soils.

For railroad work: Both methods produce strong ground vibration and crater heave, so the setback from active track (Table 7.2-1) and the vibration limits for dynamic compaction in Section 7.2.2 apply. Dynamic replacement suits yard and access road areas on soft ground away from operating track, where its columns also speed consolidation.

Source: Singh and Hymavathi (n.d.). Full reference under Supplemental References.

Supplemental reference · Blasting

Explosive Methods Near Track: Which Limits Apply

Two explosive ground improvement methods appear in this chapter. Blast densification of loose saturated sand is described in the technology sheet in Section 7.2.16. Explosive replacement of soft clay is described in the box above. Both deliberately cause strong vibration and, for blast densification, temporary liquefaction of the treated layer.

For railroad work: Treat either method as blasting, not as ground improvement vibration. The same controls apply as for rock excavation blasting:
(1) the scaled-distance or monitored-PPV limits of Section 5.3.27;
(2) a seismograph at the nearest track, structure and signal equipment;
(3) the 0.5 in./s at-rail threshold in this section.
Liquefaction of the treated layer can spread to untreated loose ground beyond the treatment area, so keep these methods well clear of operating track. Use them for new alignments and yards on greenfield ground, and confirm the result by CPT several weeks after treatment, when strength gain has occurred.

Source: 30 CFR 816.61–816.68. Full reference under S23.

7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading
7.2.3.1 Radial Consolidation Theory (Barron 1948)

PVDs accelerate consolidation by reducing the drainage path from the full layer thickness H_dr (vertical flow) to the horizontal spacing s_r between drains (radial flow). The average degree of consolidation from radial drainage U_r is:

Ur = 1 - exp[-8 Trμ]

Where T_r is the radial time factor:

Tr = ch ⋅ tde2

And:

  • c_h = horizontal coefficient of consolidation (ft²/day); typically 2–5× c_v for laminated clays
  • t = elapsed time (days)
  • d_e = equivalent diameter of influence zone (ft) = 1.13 × s for square grid; 1.05 × s for triangular grid; s = drain spacing (ft)
  • μ = drain spacing/smear/resistance factor:
μ = ln(dedw) - 34 + ds2de2 - ds2(khks - 1)ln(dsdw) + π kh ⋅ z(2L - z)qw

Where:

  • d_w = equivalent drain diameter (ft); standard PVD: d_w = 2(a + b)/π where a = 4 in. (width), b = 0.16 in. (thickness) → 0.22 ft; Rixner et al. (1986) recommend (a + b)/2 ≈ 0.17 ft. This chapter uses d_w ≈ 0.196 ft
  • d_s = smear zone diameter (ft) = 2–3 × d_mandrel (typically 0.5 ft for standard mandrel)
  • k_h/k_s = horizontal to smear zone permeability ratio (typically 3–5)
  • q_w = drain discharge capacity (ft³/day); typically about 10–80 ft³/day (100–800 m³/yr) for standard PVDs
  • L = drain length (ft); z = depth (ft)
Placing the anchor on the drain during PVD installation
Photo 7.2.3-1. Placing the Anchor on the Drain. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Inserting the mandrel into the ground during PVD installation
Photo 7.2.3-2. Inserting the Mandrel into the Ground. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Inserting the drain core within the jacket to maintain continuity
Photo 7.2.3-3. Inserting the Drain Core within the Jacket to Maintain Continuity. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Stapling the drain splice
Photo 7.2.3-4. Stapling the Drain Splice. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Schematic of a generic prefabricated vertical drain installation for a highway embankment
Photo 7.2.3-5. Schematic of a Generic PVD Installation for a Highway Embankment, showing the surcharge, drainage blanket, wick drains, and monitoring instrumentation (deep settlement points, settlement platform, groundwater observation well, inclinometer, and piezometers). (Figure from Elias et al. 2006)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

For preliminary design, the simplified Hansbo (1981) formula is commonly used (omitting well resistance and smear):

μ ≈ ln(dedw) - 0.75
Inputs for the equations in this section (13)
SymbolWhat it isComes fromHow to get itTypical range
Ur1 - exp[ -8 T_r μ ]Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Trintermediate value computed on this pageAnother equationComputed: T_r = c_h ⋅ t d_e^2project-specific
chhorizontal coefficient of consolidation (ft²/day)Lab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
telapsed time (days)TimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
deequivalent diameter of influence zone (ft)Another equationComputed: d_e = 1.13 × s for square grid; 1.05 × s for triangular gridproject-specific
sdrain spacing (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
μdrain spacing/smear/resistance factor:Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
dwequivalent drain diameter (ft)Product dataManufacturer's data sheet for the specified product, confirmed by project QA testing.project-specific
dssmear zone diameter (ft)Another equationComputed: d_s = 2–3 × d_mandrel (typically 0.5 ft for standard mandrel)typically 0.5 ft for standard mandrel
kh/kshorizontal to smear zone permeability ratio (typically 3–5)Field or lab testField: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only.clean sand 1–100, clay < 0.001 ft/day · by USCS group
qwdrain discharge capacity (ft³/day)Product dataManufacturer's data sheet for the specified product, confirmed by project QA testing.typically about 10–80 ft³/day (100–800 m³/yr) for standard PVDs
Ldrain length (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
zdepth (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
7.2.3.2 Combined Radial and Vertical Consolidation

The total degree of consolidation U_total combines radial and vertical drainage:

1 - Utotal = (1 - Ur)(1 - Uv)

Where U_v is from the Terzaghi vertical consolidation equation (Chapter 6.2, Section 6.2.7).

7.2.3.3 Staged Loading for Embankment Construction

Where subgrade shear strength s_u is insufficient for the full embankment load, construction proceeds in stages with PVDs to gain strength before next stage:

Strength gain from consolidation (Ladd 1991 SHANSEP):

su,consolidated = S ⋅ σ'v,consolidated ⋅ OCRm

Where S = 0.22–0.25 (normalized undrained strength ratio for soft clay); m = 0.88 (for CK₀U triaxial compression). For each stage: place fill to height H_i; wait for U_r ≥ 80% before next stage; verify FS_slope ≥ 1.3 (EOC) before next placement.

Table 7.2-2: PVD Design Parameters — Representative Railroad Embankment Cases
ProjectRailroadSoft Layer (ft)c_h (ft²/day)c_v (ft²/day)Drain Spacing (ft)GridTarget UtotalTime to Utarget
Coastal Georgia MainlineClass I350.0120.0065.0Triangle90%120 days
Manitoba Prairie FillClass I280.0180.0094.5Square85%90 days
Louisiana Yard ExpansionClass I420.0150.0085.0Triangle90%150 days
Quebec Mainline Soft ClayClass I500.0100.0054.0Triangle90%180 days
Passenger corridor Embankment WideningPassenger200.0220.0114.0Square95%75 days
Inputs for the equations in this section (5)
SymbolWhat it isComes fromHow to get itTypical range
S0.22–0.25 (normalized undrained strength ratio for soft clay)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
m0.88 (for CK₀U triaxial compression)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
OCRpreconsolidation stress / OCRLab test (or correlation)Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0.OCR 1 (NC) to > 4 (heavily OC) · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific

Wick drains in rail work

Wick drains give trapped pore water a short vertical path out, accelerating consolidation of soft saturated ground that would otherwise take years to drain. Several mandrels can work a large site at once.

After Geotechnology for Railroaders Program, Module 6.2; §02. Full reference under Supplemental References.

Case study: 7.2.17.2 Wick-drain rigs on dredged sand over 104 psf clay: four ways to size the platform (Look 2023), in §17.17 Case Studies.

Figure 7.2-14. Wick-drain installation rigs.
Figure 7.2-14. Wick-drain installation rigs.
7.2.3.4 Prefabricated Vertical Drains Under Embankments and New Track

A new track or siding on soft clay can settle for years. Prefabricated vertical (wick) drains shorten the drainage path from half the clay thickness to half the drain spacing, so most of the primary settlement can be taken out under a preload before the track goes down. Craig's Soil Mechanics and Das's Advanced Soil Mechanics give the theory. Barron's equal-strain solution covers radial flow to the drain. Barron's smear-zone extension (Das Eq. 8.177) accounts for the clay remolded by the mandrel. Carrillo's rule combines radial and vertical drainage. Craig stresses that ch controls the design and matters more than refinements to the theory. Drains do nothing to secondary compression, and they may help little in overconsolidated clay that stays below its preconsolidation pressure.

7.2.3.4.1 Method

Equation 7.2-1. Radial and combined consolidation

dw = 2(a + b)/π;   de = 1.128s (square) or 1.05s (triangular);   n = de/dw

Ur = 1 − exp(−8Tr/F),   Tr = cht/de²
F = n²/(n² − S²) ln(n/S) − 3/4 + S²/(4n²) + (kh/ks)(n² − S²)/n² ln S
U = 1 − (1 − Uv)(1 − Ur)

With no smear (S = 1) F reduces to Barron's F(n) = n²/(n² − 1) ln n − (3n² − 1)/4n². The calculator reproduces Das's Example 8.11: 6 m of clay drained both ways, 0.45 m drains at 3 m effective diameter, and U = 0.871 at one year against the published 0.870 (217.5 mm of the 250 mm). It also reproduces Craig's Example 7.8, where 400 mm sand drains in a square pattern must reach 85% in six months under 10 m of single-drained clay. The calculator's spacing is 10.34 ft (3.15 m), against Craig's 3.2 m read from Barron's chart.

7.2.3.4.2 Worked example

A siding embankment over 30 ft of double-drained soft clay (cv = 0.15, ch = 0.30 ft²/day) will settle 18 in. Without drains only 39.1% of that occurs in six months. Band drains (4 × 0.15 in.) at 5 ft on a triangular grid, with a smear zone twice the drain diameter, reach 99.6% in 180 days and 90% in 72 days. The widest spacing that still reaches 90% in six months is 7.80 ft, which lowers the drain footage.

Get ch from CPTu dissipation tests in the clay itself (Chapter 5.1), not from oedometer cv. Monitor settlement plates and piezometers through the preload, and remove the surcharge on measured settlement, not on the predicted schedule.

Open the wick drain calculator →
Barron equal-strain radial consolidation with a smear zone, combined with vertical drainage, settlement with and without drains, the spacing needed to reach a target degree of consolidation, and the time to reach it.

7.2.3.4.3 Drain types and checks on the theory

Table 7.2-9. Vertical drain types (after Craig, Section 7.11)
TypeTypical sizeNotes
Sand drain (bored or driven, sand backfill)8 to 16 in. diameter, to depths over 100 ftCareful backfilling needed to avoid necking; a large drain can act as a weak pile and carry part of the load
Sandwick (filter sock filled with sand)About 2.5 in. diameterFlexible, so lateral soil movement rarely breaks continuity
Band (wick) drain: plastic core in filter fabricAbout 4 × 0.16 in.Installed with a mandrel and anchor plate; equivalent diameter = perimeter/π; the usual choice today

Smear around the drain can be modeled by a reduced ch or a reduced drain diameter. The calculator instead uses Barron's smear-zone solution as given by Das.

Table 7.2-10. Time factor Tr for radial consolidation, Das Table 8.8 and the calculator's equation
n = de/dwF(n)Tr at Ur = 50%: Das / equationTr at Ur = 80%: Das / equation
50.9360.0811 / 0.08110.1884 / 0.1884
101.5780.1368 / 0.13680.3175 / 0.3175
151.9710.1708 / 0.17080.3966 / 0.3966
202.2540.1953 / 0.19530.4534 / 0.4534
252.4740.2144 / 0.21440.4978 / 0.4978

7.2.3.4.4 Spacing, smear and the settlement curve

The worked example was rerun to show how drain spacing and smear affect the schedule. The time to 90% consolidation rises roughly with the square of the spacing: about 45 days at 4 ft against 285 days at 10 ft. Smear matters less but is not negligible. Going from no smear to a smear zone four times the drain diameter adds about half again to the time. Because the smear zone grows with mandrel size, use the smallest mandrel that can install the drain.

Table 7.2-11. Time to 90% consolidation for the worked example (30 ft clay, ch = 0.30 ft²/day, triangular pattern), from the calculator
Spacing (ft)Days to 90%Smear ratio ds/dw (5 ft spacing, kh/ks = 2)Days to 90%
4451 (no smear)57
572272
6106381
7145486
8189
9236
10285
0100200300051015Time after loading (days)Settlement (in.)Drains at 5 ftDrains at 7 ftDrains at 9 ft
Figure 7.2-25. Settlement against time for the worked example with drains at 5, 7 and 9 ft on a triangular grid (final settlement 18 in.).

7.2.3.4.5 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • R.F. Craig, Craig's Soil Mechanics, 7th edition: vertical drains, design considerations and Example 7.8Find source ↗Library entry
  • B.M. Das, Advanced Soil Mechanics, 4th edition: sand drain theory (free strain, equal strain, smear), Table 8.8 and Example 8.11Find source ↗
  • M. Budhu, Soil Mechanics and Foundations, 3rd edition: one-dimensional consolidation and time rateFind source ↗
  • B.M. Das, Principles of Geotechnical Engineering, 7th edition: precompression and consolidationFind source ↗
Supplemental reference · Yan, Feng and Chu (2009)

Vacuum Preloading: How It Works and What It Achieved

Vacuum preloading lowers the pore water pressure in the soil instead of raising the total stress with fill. The effective stress rises by the same amount in both cases, but under vacuum the soil is pulled inward rather than pushed outward, so there is no risk of a stability failure during loading. Where more load is needed than the vacuum can supply, fill surcharge is added on top of the sealed membrane.

  • Case study: PVDs on a 3.3-ft square grid with 4-in. corrugated collector pipes distributed the vacuum well.
  • Total settlement exceeded 3 ft, field vane strength roughly doubled, and the water content fell substantially.
  • The paper discusses the effective depth of vacuum and how to estimate the degree of consolidation from settlement and pore pressure records.

For railroad work: Vacuum, alone or combined with fill, suits new yard tracks and embankments on very soft clay where the fill needed for an equivalent surcharge would itself be unstable. It removes the staged-loading waiting periods that fill surcharge needs. The vacuum sheet in Section 7.2.16 covers design and specification.

Source: Yan, Feng and Chu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Edil and Berilgen (2009)

Staged Construction of Tall Fills Directly on Soft Ground

Removing thick soft river deposits and replacing them with compacted fill added a third or more to the cost of the earth dams studied. The authors show that 65- to 100-ft-high dams can instead be built directly on fine-grained soft deposits by staged construction, with stage height, rate and waiting time set by undrained strength gain analysis.

  • PVDs shortened the staged program from about 15 years to about 2 years.
  • Cracking was not a problem where the subsurface was laterally uniform; the transition to the abutments needed the most attention.
  • Fine-grained deposits without continuous sand or gravel lenses posed little seepage risk; granular deposits did.

For railroad work: The same principles govern tall railroad embankments and bridge approach fills on soft ground. The transition at an abutment is the counterpart of the dam-to-abutment transition: plan settlement monitoring and stage limits there with the most care (Chapter 6.2, Section 6.2.6).

Source: Edil and Berilgen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

7.2.4 Stone Columns
7.2.4.1 Priebe Method for Composite Modulus

Stone columns (vibro-replacement) improve soft cohesive subgrades by inserting dense granular columns (typically 24–36 in. diameter) on a regular grid. The Priebe (1995) method computes an improvement factor n₀ based on area replacement ratio A_c/A:

Stone column construction with vibro rigs
Stone column construction with vibro rigs
Crane-suspended vibroflot and stone backfill
Crane-suspended vibroflot and stone backfill
Vibro concrete column installation
Vibro concrete column installation

Area replacement ratio:

as = AcA = π Dc2 / 4scol2    (square grid)

Where D_c = column diameter (ft); s_col = column spacing (ft).

Basic improvement factor (Priebe 1995):

n0 = 1 + as [ (1/2 + f) / (Kac ⋅ f) − 1 ],   f = (1 − νs)(1 − as) / (1 − 2νs + as)

For ν_s = 1/3, with column friction angle φ'_col = 40° and K_ac = tan²(45° − 20°) = 0.217, this reduces to:

n0 = 1 + as [ (5 − as) / (4 Kac (1 − as)) − 1 ]

Composite settlement reduction:

SimprovedSuntreated = 1n0

Composite modulus:

Ecomposite = EsoilSimproved/Suntreated = n0 ⋅ Esoil
Inputs for the equations in this section (6)
SymbolWhat it isComes fromHow to get itTypical range
asintermediate value computed on this pageAnother equationComputed: a_s = A_c A = π D_c^2 / 4 s_col^2    (square grid)project-specific
Dccolumn diameter (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
scolcolumn spacing (ft).Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
n0intermediate value computed on this pageAnother equationComputed: n_0 = 1 + a_s [ 1 a_s K_a ⋅ (1 - a_s)(1 - 2ν_s) 1 - ν_s - 1]^-1project-specific
Ecompositesoil elastic modulus = E_soil S_improved/S_untreated = n_0 ⋅ E_soilField test, lab test or correlationPressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc.loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
Geotextile-encased sand column installation
Geotextile-encased sand column installation
7.2.4.2 Load-Carrying Capacity of Stone Column Group

The bearing capacity of the composite improved ground beneath a loaded area is:

Kentledge load test on improved ground
Kentledge load test on improved ground
qult,composite = as ⋅ qult,col + (1 - as) ⋅ qult,soil

Where q_ult,col = bearing capacity of stone column material (typically 8–15 tsf); q_ult,soil = undrained bearing capacity of surrounding clay (N_c × s_u; typically 1–3 tsf).

Table 7.2-3: Stone Column Design Parameters — Railroad Applications
ApplicationD_c (in.)Spacing (ft)a_sn₀ (Priebe)Settlement Reductionφ'_col (°)
Track subgrade support247.50.0571.6–1.844–56%38–42
Intermodal yard (light)308.00.0771.8–2.245–55%40
Bridge abutment366.00.1962.5–3.560–71%40–42
Crane runway (RTG)365.00.2833.0–4.067–75%42
Surcharge preload zone249.00.0401.4–1.638–44%38

Rammed aggregate piers through a slip surface

Stone columns and rammed aggregate piers installed on a triangular grid through a shallow-to-medium failure plane create a composite of native soil and dense columns that carries load and resists shear better than either alone.

Stone column construction by dry bottom feed process
Photo 7.2.4-1. Stone column construction by dry bottom feed process. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Load test on a stone column
Photo 7.2.4-2. Load test on a stone column. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Construction of stone column by wet top feed method
Photo 7.2.4-3. Construction of stone column by wet top feed method. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Stone column construction in soft soil
Photo 7.2.4-4. Stone column construction in soft soil. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rammed aggregate pier construction
Photo 7.2.4-5. Rammed aggregate pier construction. Photograph courtesy of GeoStructures, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rammed aggregate pier tamper
Photo 7.2.4-6. Rammed aggregate pier tamper. Photograph courtesy of GeoStructures, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Pre-drilling of hole for rammed aggregate pier installation
Photo 7.2.4-7. Pre-drilling of hole for rammed aggregate pier installation. Photograph courtesy of GeoStructures, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rammed aggregate pier tamper foot
Rammed aggregate pier tamper foot
Aggregate pier drilling with auger
Aggregate pier drilling with auger
Figure 7.2-15. Slope stabilization with rammed aggregate piers on a triangular grid.
Figure 7.2-15. Slope stabilization with rammed aggregate piers on a triangular grid.

After Geotechnology for Railroaders Program, Module 6.1; §07. Full reference under Supplemental References.

Supplemental reference · Rollins, Quimby, Johnson and Price (2009)

Stone Columns in Silty Sand: Add Wick Drains and Watch the Clay Content

Side-by-side test areas compared vibro stone columns installed with and without prefabricated vertical drains in silty sands and sandy silts.

  • With drains, the average SPT (N1)60 rose about 114% in a zone averaging about 30% fines, but only about 70% where fines averaged 43%.
  • Without drains the improvement was much smaller.
  • Where the soil contained 15% or more clay-size particles, improvement was minimal even with drains.
  • Blow counts continued to rise for some time after treatment where drains were used, but not where they were omitted, so verification testing done too soon understates the result.

For railroad work: For liquefaction mitigation under bridge approaches and embankments in silty ground, specify wick drains between the stone columns, screen each layer for clay-size content before selecting the method, and schedule acceptance SPTs or CPTs a few weeks after installation. Where clay-size content reaches 15%, consider deep soil mixing or a column-supported embankment instead (Chapter 6.5).

Source: Rollins, Quimby, Johnson and Price (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Zhou, Chen and Chen (2009)

Shear Wave Velocity as the Acceptance Target for Liquefaction Treatment

The authors link cyclic resistance to shear wave velocity and shear wave velocity to void ratio for sandy soils. For a given earthquake magnitude, the velocity needed to resist liquefaction sets a target void ratio, which can then be converted into stone column diameter and spacing for square or triangular patterns. On a vibro stone column project, surface-wave (SASW) testing before and after treatment agreed well with SPT-based evaluations.

For railroad work: A velocity target suits long corridor treatments because surface-wave and MASW testing can cover the treated length quickly between borings (Chapter 5.1, Sections 5.1.6 and 5.1.0). Use it alongside SPT or CPT acceptance, not instead of it, and test after any time-dependent strength gain.

Source: Zhou, Chen and Chen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Shao (2009)

Stone Columns for Liquefaction, Soil-Mix Columns for Heavy Loads

A large commercial building site combined two methods: vibro stone columns to densify and drain loose sand layers that would liquefy in the design earthquake, and deep soil mixing columns to carry heavy building column loads past soft clay. CPTs before and after treatment confirmed the liquefaction mitigation. Numerical (FLAC) analysis set the soil-mix column depth, and full-scale load tests on column groups matched the prediction. The facility performed without distress for more than seven years.

For railroad work: Mixed treatments work well where one problem is liquefaction and another is settlement under concentrated loads, such as intermodal crane runways or heavy equipment pads in seismic areas. Size each method for the problem it solves, and prove the column groups with load tests before production.

Source: Shao (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

7.2.5 Deep Soil Mixing (DSM)
7.2.5.1 Method Description

DSM mechanically blends in-situ soil with cementitious binder (Portland cement, lime, or blends) using hollow-stem augers with injection ports. The resulting soil-cement mass (referred to as a "treated mass" or "column") achieves unconfined compressive strengths of 50–300 psi depending on binder content and soil type. DSM is used for:

Cement-soil column auger and cement hopper
Cement-soil column auger and cement hopper
Exposed tops of DSM columns
Exposed tops of DSM columns
Exposed sides of DSM columns
Exposed sides of DSM columns
  • Soft clay improvement beneath railroad embankments (treated mass beneath track)
  • Liquefaction mitigation (Chapter 6.5, Example 6.5-1)
  • Lateral support walls for excavations adjacent to track
  • Embankment toe walls to prevent lateral spreading

Design unconfined compressive strength:

qu,field = flab × qu,lab

Where f_lab = field-to-laboratory strength ratio, commonly 0.2–0.5; use 0.25 for conservative preliminary design. Laboratory mix design targets q_u,lab ≥ 100 psi for soft clay treatment.

Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
quintermediate value computed on this pageAnother equationComputed: q_u = f_lab × q_u,fieldproject-specific
flab0.20–0.33 (field-to-laboratory strength ratioChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
7.2.5.2 Composite Modulus for DSM Treatment

Treated mass elastic modulus:

EDSM = 150 ⋅ qu,field    to    500 ⋅ qu,field    (psi)

For q_u,field = 50–300 psi this gives about 7,500–150,000 psi. For settlement reduction using composite modulus approach:

Ecomposite = aDSM ⋅ EDSM + (1 - aDSM) ⋅ Esoil

Where a_DSM = area replacement ratio of DSM columns within the treated zone (typically 0.15–0.35 for track subgrade improvement).

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
EDSMintermediate value computed on this pageAnother equationComputed: E_DSM = 150 ⋅ q_u,field    to    500 ⋅ q_u,field    (psi)project-specific
Ecompositesoil elastic modulus = a_DSM ⋅ E_DSM + (1 - a_DSM) ⋅ E_soilField test, lab test or correlationPressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc.loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group
aDSMarea replacement ratio of DSM columns within the treated zone (typically 0.15–0.35 for track subgrade improvement).Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.typically 0.15–0.35 for track subgrade improvement
7.2.5.3 Minimum Strength Criteria by Client
Railroadq_u,field minimum (psi)Test MethodCuring Period (days)Notes
Typical50ASTM D216628Common practice; confirm with owner

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

Supplemental reference

Column-supported embankments (CSE) and load transfer platforms

When there is no time to preload, columns of almost any type — aggregate piers, vibro-concrete columns, DSM columns, augered or driven piles — can carry the embankment to a firm layer. SHRP2 R02 notes that the method is most economical for 15–70 ft of soft clay, peat or organic soil, and cites the Rancocas Creek Railroad Bridge approach in New Jersey (Figure 17-S3). Key points of the recommended design procedure (there is no approved FHWA method):

Completed T-Wall column-supported embankment for the Rancocas Creek railroad bridge approach, New Jersey (SHRP2 GeoTechTools).
Supplemental Figure 17-S3. Completed T-Wall column-supported embankment for the Rancocas Creek railroad bridge approach, New Jersey (SHRP2 GeoTechTools). Source: SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographs.
  • Design the columns to carry the entire embankment plus surcharge (commonly 250–300 psf). SHRP2 recommends an allowable post-construction settlement of 3 in.; track tolerances in Chapter 6.2 may govern tighter.
  • The embankment must exceed a critical height (below which differential settlement shows at the surface), and clear span s − a ≤ 10 ft (a = pile-cap width, or 0.886 dcol for round columns).
  • A geosynthetic-reinforced load transfer platform is typical where spacing exceeds about 5 ft. Thickness should be at least 2 ft and at least 0.5(s − a). Use select fill with φ′ ≥ 35°, graded 100% passing 4 in., 15–70% passing No. 4, 10–60% passing No. 40 and 5–15% passing No. 200, with LL < 40 and PI < 20. Place at least two reinforcement layers with 3-ft overlaps.
  • Check global stability (FS ≥ 1.5 recommended with LTPs) and lateral spreading of the reinforcement. Closely spaced aggregate columns often need no LTP.

Table 17-S3. Typical allowable column capacities (SHRP2, adapted from Elias et al., 2006)

Column typeAllowable capacity (kip)Typical length (ft)Diameter/width (in.)
Stone columns20–11010–3518–47
Geotextile-encased columns65–13510–3530–60
Rammed aggregate piers50–15010–3524–36
Augered piles75–25015–8012–24
Vibro-concrete columns100–25010–3518–24
Deep mixing columns90–27030–10024–120
Precast concrete piles90–22530–50up to 24
Steel H / pipe piles90–450 / 180–55015–100 / 30–1306–12 / 8–48
Deep mixing rig on levee, New Orleans
Deep mixing rig on levee, New Orleans
DSM batch plant and mixing rig
DSM batch plant and mixing rig
Close-up of deep soil mixing tool
Close-up of deep soil mixing tool

Source: SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographs

Placement of geosynthetic reinforcement for a load transfer platform over columns (SHRP2 GeoTechTools).
Supplemental Figure 17-S4. Placement of geosynthetic reinforcement for a load transfer platform over columns (SHRP2 GeoTechTools). Source: SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographs.

Technology sheets for this method · see 7.2.16 Technology Library

CSV installation adjacent to a sheet pile wall
Photo 7.2.5-1. CSV installation adjacent to a sheet pile wall. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Top view of the CSV auger and cement hopper
Photo 7.2.5-2. Top view of the CSV auger and cement hopper. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Deep mixing rig on a levee project in New Orleans, LA
Photo 7.2.5-3. Deep mixing rig on levee project in New Orleans, LA. From Trevi Icos Corporation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Batch plant and deep mixing rig
Photo 7.2.5-4. Batch plant and deep mixing rig. From Trevi Icos Corporation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Close-up view of mixing
Photo 7.2.5-5. Close-up view of mixing. From Trevi Icos Corporation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Exposed top of deep mixing columns
Photo 7.2.5-6. Exposed top of deep mixing columns. From Fudo Construction.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Exposed sides of deep mixing columns
Photo 7.2.5-7. Exposed sides of deep mixing columns. From George Filz (2010).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Supplemental reference · Madhyannapu, Puppala, Bhadriraju and Nazarian (2009)

Deep Soil Mixing to Control Swell and Shrinkage of Expansive Clay

Deep soil mixing is usually specified for strength and settlement. This study used it to stop seasonal heave and shrinkage of an expansive clay of moderate depth beneath pavements and earth structures.

  • The laboratory mix design selected a blend of 25% lime and 75% cement by weight, at about 337 lb of binder per cubic yard of soil and a water-to-binder ratio of 1.0.
  • Two instrumented test sections with surcharge fill were monitored for two years against untreated control sections.
  • Both vertical and lateral movements were smaller in the treated sections. The authors give a step-by-step design method.

For railroad work: Expansive clay subgrades cause recurring track surface and cross-level defects in dry and wet seasons (Chapter 2.5). Where the active zone is too deep for lime treatment of the top lifts (Section 7.2.7), soil-mix columns are an option for short critical lengths such as turnouts, crossings and bridge approaches.

Source: Madhyannapu, Puppala, Bhadriraju and Nazarian (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Liu, Zhang and Zhu (2009)

Checking How Well Deep-Mixed Columns Are Mixed

Strength tests alone do not show whether binder is evenly distributed through a column. The authors measured the electrical resistivity of cores, and the parameters derived from it (formation factor, shape factor and anisotropy factor), and found them direct indicators of mixing uniformity. The results agreed with SPTs on the columns and unconfined compression tests on the cores. Double-slurry mixing produced markedly more uniform columns than single-slurry mixing.

For railroad work: Add a uniformity check to deep-mixing QA for railroad work: resistivity of cores, or geophysical testing of whole columns, alongside core recovery and strength. Ask the contractor which mixing process will be used, because the process affects uniformity as much as the binder content does.

Source: Liu, Zhang and Zhu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Zheng, Liu and Chen (2009)

Composite Columns: a Concrete Core Inside a Soil-Cement Column

Column-type elements behave in three ways: granular columns (sand and stone), soil-cement columns (deep-mixed, lime and jet-grouted) and rigid piles (concrete and steel). Composite columns combine them by placing a small-diameter plain concrete, reinforced concrete or steel core in the center of a granular or soil-cement column.

  • The core gives much higher bearing and bending capacity than the soil-cement column alone, and the soil-cement shell provides side resistance.
  • A composite deep-mixed column can carry more than a bored pile of the same outside size and length, at competitive cost.
  • The extra stability allows embankments to be raised faster.

For railroad work: Composite columns fit bridge approach embankments and high fills where ordinary soil-cement columns would be too weak in bending under the side slopes (see Section 7.2.8 on lateral behavior of embankment columns), but a full pile foundation is more than the job needs.

Source: Zheng, Liu and Chen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

7.2.6 Grouting Methods
7.2.6.1 Compaction Grouting

Compaction grouting injects a stiff grout (slump < 2 in.) that does not penetrate soil pores but instead forms a grout bulb, displacing and densifying surrounding soils. Used for:

Bio-mediated soil treatment overview
Bio-mediated soil treatment overview
Jet grouting process
Jet grouting process
Jet Grouting — Multiple Rigs Operating
Jet Grouting — Multiple Rigs Operating
Figure 7.2-17. Compaction grouting and dynamic compaction concept.
Figure 7.2-17. Compaction grouting and dynamic compaction concept.
  • Densification of loose fills beneath existing track (historical mainline settlement)
  • Foundation underpinning adjacent to active track
  • Correction of localized subgrade settlement
Jet grouting process schematic
Photo 7.2.6-1. Jet grouting process schematic. Photograph courtesy of Hayward Baker, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Multiple jet grouting rigs on site
Photo 7.2.6-2. Multiple jet grouting rigs. Photograph courtesy of Soilmec S.p.A. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Grout volume per bulb:

Vgrout = π6 Dbulb3    (ft3)

Where D_bulb = target bulb diameter (ft); typically 1.5–2.5 ft. Injection spacing = 4–8 ft on grid; primary and secondary passes used to achieve uniform densification.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
Dbulbtarget bulb diameter (ft)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.typically 1.5–2.5 ft. Injection spacing = 4–8 ft on grid
7.2.6.2 Permeation Grouting

Low-viscosity grout (sodium silicate, acrylamide, or ultrafine cement) is injected under low pressure to penetrate pore spaces without disturbing soil fabric. Used in granular soils (D₁₅ > 0.025 in.) to reduce permeability or improve strength.

Pressure grouting of fractured rock
Pressure grouting of fractured rock

Groutability ratio (GR):

GR = D15,soilD85,grout ≥ 24    (for successful permeation)

Groutability limits for permeation grouting

  • Cement and clay grouts suit sands and gravels only. They do not suit silts or clays, or soils with more than about 10% fines.
  • Silicate chemical grouts reach coarse silts and medium to fine sands.
  • Check the particle-size ratio: D15(soil) ≥ 25 × D85(grout).

After Selig & Waters (1994), ch. 11. Full reference under Supplemental References.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
GRD_15,soil D_85,grout ≥ 24    (for successful permeation)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
7.2.6.3 Jet Grouting

High-pressure jetting (3,000–7,000 psi) simultaneously erodes and mixes in-situ soil with cement grout, creating cylindrical treated columns. Single-fluid, double-fluid, and triple-fluid systems produce column diameters of 1.5–5.0 ft. Used by a passenger railroad for underpinning passenger corridor structures and by a Class I railroad for liquefaction mitigation under existing embankments.

Column diameter depends on the soil, the jet system and the jetting parameters (pressure, flow, lift and rotation rates), so confirm it with test columns before production.

Supplemental reference

Slurry pressure injection under live track

The grouting methods above are general. The method developed specifically for railroad subgrades is slurry pressure injection from hi-rail equipment, which can clear for trains between injections. Soft fine-grained subgrade and repeated resurfacing drive ballast down into ballast pockets that trap water, cause squeezes and keep the soil weak. Injection works in two ways:

  • Mechanical (void filling): a slurry heavier than water displaces trapped water from the pockets and sets into a ballast–grout block that resists the progressive shear (Figure 17-S1). Railroad cements (about 70–80% finely ground limestone, 20–30% cement clinker) reach up to about 1,000 psi; lime/fly ash up to about 125 psi. Slurry specific gravity should be at least 1.25.
  • Chemical (lime): hydrated or quicklime slurry travels along fissures, slickensides and shear planes and reacts with the clay. Lime slurry does not set on its own. Results may take 6–9 months to appear as lime migrates into the soil. Pengelly reports a CPT-measured average shear strength increase of 308% ten months after lime/fly ash injection.
Subgrade cross-sections before and after slurry injection: ballast pockets forcing lateral shear (top) and the solidified ballast&ndash;slurry block resisting shear (bottom).
Supplemental Figure 17-S1. Subgrade cross-sections before and after slurry injection: ballast pockets forcing lateral shear (top) and the solidified ballast–slurry block resisting shear (bottom). Source: Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR).

Table 17-S1. Typical injection parameters (FRA handbook, 1977, and Pengelly)

ParameterTypical value
RodsThree, 5 ft apart: one on track centerline, one each side (Figure 17-S2)
DepthLime: 10–16 ft historically; most programs ≥ 20 ft; modern units 30–40 ft
Longitudinal spacingAbout 5 ft (every second or third crib; never more than 4 crib spaces); every crib, staged, in severe distress
Stage interval18–24 in., injecting downstage (top down) to refusal or target take
Pump pressure50–250 psi (150 psi common); keep low to maximize take
Lime slurry2.5–3 lb lime per gallon of water (never > 4); SG about 1.15–1.17
Quantity30–50 gal per track ft for a 10–16 ft lime injection (FRA); 200–250 lb dry solids per track ft typical, 150 mild to 1,000 severe (Pengelly)
StagingSecond or third pass 48 hr or more later into skipped cribs, e.g., deep lime pass then shallow void-filling pass
Injection rod spacing across the track (5 ft) and crib staging of initial and secondary injections.
Supplemental Figure 17-S2. Injection rod spacing across the track (5 ft) and crib staging of initial and secondary injections. Source: Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR).

Investigation and testing. The FRA handbook suggests about 2 + L/250 borings for L up to 1,000 ft of problem track, 6 + (L − 1,000)/300 for 1,000–4,000 ft, and 16 + (L − 4,000)/400 for 4,000–10,000 ft, with continuous Shelby tubes for 5 ft just below the ballast and borings at least 5 ft below the deepest planned injection. Lab “lime-inoculated” specimens (1% lime by dry weight, representing 5-ft centers) are compared with untreated controls in swell, consolidation and strength tests. CPT before and after injection locates ballast pockets, sets the target take and verifies improvement. Contractor case histories (a line in Iowa, every other crib, 14–40 ft; a line in Missouri, every crib to 20 ft after CPT found weak soil to 18–20 ft) used this approach. The FRA handbook itself cautions that results cannot yet be predicted reliably from lab tests and recommends a field test section before a program.

Untreated vs bio-cemented sand (microscope)
Untreated vs bio-cemented sand (microscope)

Material caution: Pengelly attributes past poor results partly to substandard fly ash and recommends only ash that reliably sets (Class C in his experience). Test every ash source for compatibility. Note that his description of the coal sources is reversed relative to ASTM C618, where Class F comes from bituminous or anthracite coal and Class C from sub-bituminous or lignite.

How the method developed. Railroads began pumping slurry into subgrades in the 1930s, when maintenance engineers drove pipes into soft roadbed and pumped blends of sand, cement and emulsified asphalt 6 to 12 ft deep to fill ballast pockets. By the 1940s dozens of railroads used the method; one Class I railroad treated more than 1,000 miles of track between 1942 and 1955. Lime slurry, intended to react with the clay rather than fill voids, was first injected under track in 1959. Hi-rail injection units and a federal handbook (Blacklock and Lawson, 1977) made lime injection a routine yearly maintenance contract by the late 1970s. Fly ash was added from about 1978, partly because lime had become expensive and partly because lime and fly ash together set. In the early 1990s finely ground railroad cements took the practice back to void filling. Use declined after railroad consolidation, as the staff who ran injection programs moved on and maintenance budgets turned to other parts of the track. Pengelly attributes much of the doubt about the method to programs that were run without before-and-after test data, and to substandard materials, rather than to the method itself.

Choosing the slurry. Choose the material from the goal of the program.

  • Void filling. Railroad cement can be mixed in batches of about 12,000 gal without a flash set; add a mild retarder if the set comes too soon. Slag cement or masonry cement can be substituted where railroad cement is not available. Much of the past success of lime/fly ash is probably void filling, because its reaction with the soil is weaker than that of lime alone.
  • Chemical treatment of soft clay. Use a quicklime product. Slaking raises the slurry temperature, which speeds the reaction, and gives a finer particle that penetrates the clay better. Mix 2.5 to 3.0 lb of dry solids per gallon (specific gravity about 1.15 to 1.17). In a saturated subgrade, a thicker slurry lets part of the slaking take place in the ground and dries the soil further.
  • Setting the lime dose. Remold subgrade samples to the field density and moisture, treat them with slurry at trial rates, cure them and test their unconfined compressive strength. The dose that gives the needed strength, usually 1 to 2% lime by dry weight of soil and expressed in gallons per cubic foot, becomes the field target.

Under pressure the slurry follows the paths of least resistance: the shear planes, slickensides and disturbed zones of a failing subgrade, which are the zones that most need treatment. Interval timing and staging spread it further.

Injecting downstage. The rods are pushed hydraulically, and slurry is pumped through four 1/4-in. nozzles set 90° apart on the tip at intervals of about 18 in. from the top down. Each interval is pumped to the target take, or for a minimum time, or until slurry refuses through earlier holes or out of the embankment side. If slurry runs up the rod, push the rod deeper to make a seal before pumping. Keep the pressure as low as the ground allows: high pressure brings early refusal and a smaller take. Most soft subgrades accept slurry well below the pump’s upper range, and the pressure is raised only to fracture tight soil. Typical equipment is a hi-rail unit with a mast that reaches 40 ft and three rods 5 ft apart; a piston or progressive-cavity pump of about 90 gal/min at 50 to 200 psi; and an agitated slurry tank of 17,000 to 22,000 gal on a flat car in tow, which can clear for trains between holes. The operator records depth, take and time at every hole. Compare the daily totals with the target, and adjust spacing, staging or depth while the crew is still on site.

Checking the result. Repeat the CPT soundings after treatment. Where railroad cement has filled the pockets the cone may not push through, so use borings to measure moisture content and in-place strength instead. Lime results can take 6 to 9 months to appear, so schedule the after-soundings accordingly.

Table 17-S2. Field test section results after lime/fly ash injection of a clay subgrade (airfield taxiway test area, after Pengelly, Table 1)
AreaDry density (pcf)Percent of ASTM D698 maximumMoisture content (%)Field CBR at 0.1 in. penetrationField CBR at 0.2 in. penetrationLL / PI
Untreated brown and tan clay (4 tests)84.187.634.80.9 to 1.81.2 to 2.371 / 39
Lime/fly ash injected tan and brown clayey silt (3 tests)95.3104.223.424 to 2922 to 3463 / 25

Read Table 17-S2 as an indication of what injection can do to moisture and bearing, not as a design value for track. The test area was an airfield taxiway, and the treated and untreated soils were logged differently, so part of the difference may be the soil itself. The improvement is consistent with the mechanism: hydration of the injected material takes up water, the moisture content drops by about 11 points, and the bearing rises with it.

Running a program. Injection is used in two ways.

  • A single site. This is usually a site where other repairs have failed, and it justifies a full investigation first: a track study of the soils and the cause of failure, lime reactivity tests, and CPT soundings or cross trenches to measure the ballast pockets and set the target take.
  • A system-wide program. Injection is cheapest when many sites are treated under one planned contract. That needs one railroad coordinator who knows every site and orders the work to keep mobilizations down. The plan lists each site by milepost, with its injection depth, nearest siding and order of treatment. The railroad may furnish the material to the sidings, with the contractor unloading and handling it. Price the program as a lump sum for the planned sites, or on time and materials where emergency sites are likely to be added during the contract.

Worked example. Example 7.2-4 in Section 7.2.9 works through the slurry quantity needed to fill the ballast pockets in a section of track, from a CPT sounding.

Source: Blacklock, J. R. and Lawson, C. H. (1977). Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection. FRA/ORD-77/30, Federal Railroad Administration · Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR) · Hayward Baker, Inc. Railroad Subgrade Stabilization (brochure)

Injection and grouting from the track

Cement-slurry injection and compaction grouting pump material into the ground under pressure, densifying loose soil or filling voids without excavating the track. Where poor material is shallow, remove-and-replace with engineered granular fill over a separator geotextile is still the most direct fix. Admixture stabilization, usually with Portland cement, treats soil in place, and is faster and cheaper when the soil responds well.

Drilling to place grout pipes inside a tunnel
Photo 7.2.6-3. Drilling to place grout pipes. Courtesy of Hayward Baker, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cross-section diagram of grout pipes fanning out beneath an existing tunnel to improve soil under the structure
Photo 7.2.6-4. Example of improvement of soil under an existing structure. From Munfakh (1991).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Schematic of chemical grouting equipment injecting grout beneath a structure ahead of planned excavation
Photo 7.2.6-5. Example of chemical grouting underpinning of a structure to allow excavation without settlement of the foundation. Courtesy of Hayward Baker, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Grouting of abandoned mine voids beneath a structure
Grouting of abandoned mine voids beneath a structure
Figure 7.2-16. Rail-mounted cement-slurry injection rig.
Figure 7.2-16. Rail-mounted cement-slurry injection rig.

After Geotechnology for Railroaders Program, Module 6.2; §04–05. Full reference under Supplemental References.

Supplemental reference · Basu, Madhav and Prezzi (2009)

Ground Heave from Inclined Compaction Grouting

To grout beneath an existing foundation, the grout pipe is often inclined from outside the loaded area. The authors estimate the heave at the ground surface above an inclined compaction grout column from elastic theory, with influence factors for the column length, the depth of injection and the inclination.

  • Heave increases with inclination, steeply at first and then more slowly. For deep injection (about 10 column diameters), heave changes little once the inclination exceeds about 70° from vertical.
  • For inclinations of 10° to 30°, injecting deeper than about five grout-column diameters gives little further reduction in the maximum surface heave.
  • Heave can be estimated before work starts from the soil deformation modulus and the planned grouting parameters.

For railroad work: Compaction grouting under track is normally done with inclined holes from the shoulder or between tracks. Estimate the heave beneath the rails before grouting and set track geometry limits and monitoring intervals for the work, so that the track is not lifted out of tolerance (Chapter 5.3).

Source: Basu, Madhav and Prezzi (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Shen, Luo, Xiao and Wang (2009); Wang, Wang and Wang (2009)

Large-Diameter Jet Grouting in Soft Deposits

Double-erosion jet grouting (a rotary-jet variant) cuts the soil twice and forms very large columns. In a deep excavation in a soft coastal deposit, columns reached about 164 ft deep.

  • Column diameters ranged from about 2.6 to 10.8 ft. In soft clay they exceeded 5.9 ft and mixing was uniform.
  • In stiff silty clay the same settings produced columns smaller than 3.3 ft.
  • In sand below the water table the jet cut a wide zone, but cement and soil separated and mixing was poor.
  • 28-day unconfined strength was about 130 to 1,175 psi.
  • A companion review describes jet grouting over the past decade in the same city for foundation support and for horizontal and vertical water cutoffs, with treatment depths increasing from 65–100 ft to about 165 ft.

For railroad work: Column diameter and quality depend heavily on soil type, so specify trial columns in each soil layer and check diameter and uniformity before production. Jet-grouted cutoffs and bottom seals are relevant to deep excavations for underpasses and pump stations beside track.

Source: Shen, Luo, Xiao and Wang (2009); Wang, Wang and Wang (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Singh and Hymavathi (n.d.)

Compensation Grouting

Compensation grouting injects grout under high pressure through sleeve pipes (tubes-à-manchette) to fracture the soil deliberately. The grout fills the fractures, which open in the direction of least principal stress, and the added volume makes up for ground loss. It is used to prevent or reverse settlement of structures above tunnels and excavations, and in repeated passes can lift settled structures in a controlled way.

For railroad work: Compensation grouting can protect track over a tunnel or jacked crossing, or relevel track and structures that have settled. It needs real-time monitoring of the track and the ground during injection, with stop criteria, because grout fractures can heave the track unevenly or reach drains and culverts. Agree the target lift and allowable rates with the railroad before work starts.

Source: Singh and Hymavathi (n.d.). Full reference under Supplemental References.

7.2.7 Lime and Cement Stabilization
7.2.7.1 Lime Stabilization

Hydrated lime (Ca(OH)₂) added to fine-grained soil produces immediate PI reduction through cation exchange and flocculation, and long-term pozzolanic strength gain.

PI reduction rule of thumb:

PIfinal ≈ PIinitial - 5 ⋅ Lp

Where L_p = lime percentage (by dry soil weight, %). Target: PI_final < 12 for use as subgrade; PI_final < 20 for use as embankment fill. Minimum lime content: 3%; maximum practical: 8%.

Strength gain timeline:

Curing Timeq_u (psi) — Typical CL/CH Clayq_u (psi) — ML/MH Silt
1 day15–3010–20
7 days30–8020–50
28 days50–15035–90
1 year100–30070–200

Sulfate precaution: Soluble sulfate above about 3,000 ppm can cause ettringite heave with lime, cement or fly ash alike. Test sulfate (ASTM D4327 or equivalent) and follow the National Lime Association guidance below.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
Lplime percentage (by dry soil weight, %)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.project-specific
7.2.7.2 Cement Stabilization

Portland cement (ASTM C150, Type I/II) or fly ash (ASTM C618, Class C or F) stabilizes both granular and fine-grained soils through cementation. Design target: q_u ≥ 200–300 psi at 7 days (ASTM D1633, withdrawn 2026) for pavement base applications (Chapter 7.3).

Cement Treated Base (CTB)
Cement Treated Base (CTB)

Mix design proportioning:

qu = f[ccement, soil type, wc, tcure]

Determined from laboratory trial mixes at cement contents of 4%, 6%, 8%, 10% by dry weight. Minimum cement content for railroad fill: commonly 4%; confirm with the owner railroad's specification.

Supplemental reference

Sulfate thresholds and construction steps (National Lime Association)

The sulfate problem is not specific to lime. Sulfates react with calcium and clay alumina to form expansive ettringite and thaumasite with any calcium-based additive — lime, portland cement or fly ash. Switching to cement or fly ash therefore does not avoid it. NLA guidance:

Soluble sulfateGuidance
< 3,000 ppm (0.3%)Unlikely to cause problems
3,000–5,000 ppmReadily stabilized with good practice: plenty of water, ample mellowing between mixings
> 5,000 ppmOften two lime applications: first before mixing, second after a multi-day mellowing at about 5% over optimum moisture so that ettringite forms before compaction (research cited suggests a single application at +2% moisture up to 7,000 ppm)

Sulfates occur in isolated seams and pockets (commonly naturally occurring gypsum in the western U.S., or industrial and synthetic-gypsum contamination), so sample more densely than for other index tests. Other NLA criteria: good candidates have at least 25% passing No. 200 and PI > 10; organics > about 1% need extra lime or special procedures; subgrade stabilization typically uses 3–6% lime. Construction sequence: scarify and pulverize, spread lime, preliminary mix and water, mellow 1–7 days, final mix until 100% of non-stone material passes 1 in. and at least 60% passes No. 4, compact, then moist- or membrane-cure. For embankment repairs, treat borrow in a stockpile at 1–3% over optimum so mellowing happens off the critical path.

Source: National Lime Association (2004). Lime-Treated Soil Construction Manual: Lime Stabilization & Lime Modification, Bulletin 326

Stabilized subgrade under track in frost areas

In seasonal-frost areas, use lime or cement stabilized subgrade under track with caution. Use it only after a laboratory program on the treated soil that includes a frost-susceptibility test and a freeze–thaw durability test. UFC 4-860-01FA refers to TM 5-822-14 for the design and construction of soil-stabilized subgrades.

Roller and other heavy equipment compacting a wide field of chemically stabilized soil
Photo 7.2.7-1. Compaction of chemical stabilized soil. Photograph courtesy of Carmeuse Lime & Stone, from carmeusena.com.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Close-up of a mixing rig's blades processing chemically stabilized soil
Photo 7.2.7-2. Mixing of chemical stabilized soil. Photograph courtesy of Carmeuse Lime & Stone, from carmeusena.com. This same photograph is also used as the Fact Sheet document's cover image.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

After UFC 4-860-01FA (2004), ch. 6, §8e. Full reference under Supplemental References.

Choosing cement, lime or bitumen for trackbed soils

Table 17-SW1. Admixture screening criteria
AdmixtureSuitable soilsAvoid / notes
CementBroadly graded sand–gravel; < 35% passing No. 200 and PI < ~30Highly organic, high-salt or high-sulfate soils; coarse gravel (high cement demand); CH clay (hard to mix). Use lime instead where the fines or PI limits are exceeded.
LimeClay fraction (< 2 µm) ≥ 7% and PI > 10; typically 3–7% lime by weightLab reactivity test required. Lowers maximum dry density and raises optimum moisture, which helps wet clay. Strength gains slowly, giving a flexible working time, but it is not for a rapid strength need.
BitumenGW, GP, SW, SP, GM, SMPoor in wet soils. Too much bitumen lowers strength. A sprayed emulsion film works only where the water table will not be trapped beneath it.

Cracking risk. A cement-stabilized layer over softer soil develops tension at its base under each axle. Unlike a granular layer, it cannot build up residual compression, so it may crack and lose its benefit. Lime-treated soil cracks less than soil-cement. Cement also raises wet–dry and freeze–thaw resistance and lowers swell. It reduces permeability in granular soils but can increase it in clay.

After Selig & Waters (1994), ch. 11. Full reference under Supplemental References.

Case study: 7.2.17.3 Lime-treated local soil in a reinforced slope: choosing by total internalised cost (Look 2023), in §17.17 Case Studies.

Project management · Bull (2015)

Life-Cycle Selection Among No Treatment, In-Place Stabilization and Remove-and-Replace

In Bull’s volume, Praticò, Saride and Puppala (Chapter 2.1) build a life-cycle cost model for choosing among three ways of treating a weak subgrade:

Praticò, Saride and Puppala’s life-cycle model linking design alternatives, expected lives, agency, user and externality costs to present values and the “gain” indicators.
Figure 17-PM1. Praticò, Saride and Puppala’s life-cycle model linking design alternatives, expected lives, agency, user and externality costs to present values and the “gain” indicators. Source: Bull (2015), Figure 3.1.
  • NT: leave the soil as it is.
  • S: stabilize it in place.
  • SUB: excavate and replace it.

Each alternative has an expected life that comes from its mechanical properties. Its present value sums three kinds of cost:

  • Agency costs: construction, rehabilitation and maintenance.
  • User costs: work-zone delay and vehicle operating costs.
  • Externality costs: emissions from hauling, quarrying and landfill.

Over an infinite horizon, where the first rehabilitation falls at year E and repeats every O years, the agency present value is:

PV = C + CRE × (1+i)−E / [1 − (1+i)−O]

The “gain” of one alternative over another is simply the difference in their present values.

The authors tested the model on two low-volume roads at a 4% discount rate. In the Italian case, a lime-treated CL subgrade was given a 20-year life against 15 years untreated. Stabilization beat substitution when stabilization was cheap. User costs were only about 1/50 of agency costs at those traffic levels. User gains turned negative once the treated alternative’s work zone lasted about 1.5 times as long as the untreated case. Stabilization paid at higher traffic. At very low traffic, remove-and-replace cost more than doing nothing. In the Texas case, lime–cement treatment turned a CH soil with 6.3% free swell into a non-swelling CL. Its unconfined strength rose from about 13 to 250 psi, and its resilient modulus from about 6 to 35 ksi.

Steps of Soil Lime Treatment
Steps of Soil Lime Treatment

For railroad work: the same three choices come up at most chronic subgrade sites:

  • NT: keep surfacing.
  • S: stabilize in place, by lime or cement treatment or by injection.
  • SUB: undercut and replace with subballast.

The perpetual-cycle factor shows how much each added year of life is worth. At 4%, (1.04)−15/[1 − (1.04)−15] = 1.25, while the same factor at 20 years is 0.84. So a treatment that stretches the maintenance cycle from 15 to 20 years cuts the present value of all future rehabilitation by about a third. Replace the highway user costs with train-delay and slow-order costs. Count the haul trips, quarried aggregate and disposed spoil or fouled ballast as externalities. Then test how the ranking changes with treatment cost and traffic (MGT), as the authors do.

Source: Bull, J. W. (ed.) (2015). Life Cycle Costing for the Analysis, Management and Maintenance of Civil Engineering Infrastructure. Dunbeath, Scotland: Whittles Publishing, pp. 66–77. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

7.2.7.3 Lime Slurry Pressure Injection Planning

Lime slurry pressure injection (LSPI) treats unstable fine-grained roadbed in place without removing the track. A hi-rail injector truck drives hollow rods, normally three (one on the track centerline and one about 5 ft to each side), down through the ballast and pumps a thin slurry of hydrated lime and water into the soil in stages to the full treatment depth. The slurry follows seams and fractures. In heavy clays it forms thin sheets of lime that react with the adjacent soil and act as moisture barriers, so expansive clays are best treated near their driest time of year. In weaker silty and sandy clays it disperses through the soil and gains strength by cation exchange and pozzolanic reaction; very wet soils of this kind may need drainage first. The method is suited to repeated ballast pockets, soft spots and swelling clay under track.

7.2.7.3.1 Injection parameters

Table 7.2-7. Typical LSPI parameters (federal research handbook)
ParameterTypical value
Rod layout3 rods: centerline and about 5 ft each side
Longitudinal spacingEvery second or third tie (about 5 ft gives overlapping seams)
Vertical stage interval18 to 24 in. (12 to 18 in. in early literature)
Treatment depthCommonly 10 to 16 ft below top of tie
Slurry quantity30 to 50 gal per track foot for 10 to 16 ft depth
Lime-water ratioAbout 2 to 3 lb hydrated lime per gallon of water
Pump pressure50 to 250 psi (150 psi common)
Equipment1,500 to 2,000 gal tank; pumping 1,500 to 2,000 gal per hour of track time; 20-ton lime storage

Injection is normally continued at each stage to refusal (slurry running freely at the surface or from earlier holes). Because refusal depends on the operator and on the soil, the handbook recommends that the plan state which layers are to be treated and how much slurry goes into each, that slurry density be checked to within about 10%, and that test sections be used to set spacing and quantities. Where one pass does not place enough lime, staged or double injection (re-injecting between the first holes after about 48 hours) is used.

7.2.7.3.2 Worked example: 1,000 ft of soft clay roadbed

Table 7.2-8. Spacing 3.25 ft, 3 rods, 2 to 12 ft depth at 18 in., 40 gal/ft, 2.5 lb/gal (calculator output)
ResultValue
Injection holes924
Injection stages6,468
Slurry40,000 gal
Hydrated lime44.2 tons
Track time for pumping26.7 hr

Slurry-to-water conversion assumes a lime specific gravity of 2.3; confirm with the supplier.

About 44 tons of lime and roughly 27 hours of pumping means several work windows. Track time, not material, usually controls the cost, which is one reason to target the injection to the problem layers identified in the investigation.

Open the lime injection calculator →
Injection holes and stages, slurry, water and hydrated lime quantities, tank loads and track time for a treated length.

7.2.7.3.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard or published forms.

  • Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection (federal research report), Ground Improvement folder.Find source ↗Library entry
  • Railway Embankment and Ballast Pocket Stabilization in a Soft Soil Environment, Ground Improvement / Subgrade Injection folder.Find source ↗Library entry
  • Railroad Subgrade Injection (paper, scanned), Ground Improvement / Subgrade Injection folder.Find source ↗
Supplemental reference · Yu, Zhang, Lang and Yu (2009)

Lime Sludge from Water Treatment Plants as a Stabilizer

Water treatment plants produce large volumes of lime sludge, which is chemically similar to commercial hydrated lime. Soil treated with it gained stiffness, lost plasticity and was more durable under freeze–thaw cycles.

  • The usual pH-based test for selecting lime content does not work for lime sludge; select the content from unconfined compression tests instead.
  • Wet (slurry) and dry mixing gave similar strength, so the sludge can be used as a slurry without the cost of drying it.

For railroad work: Lime sludge may be a low-cost alternative to hydrated lime for treating embankment fill and subgrade near a water plant. Use a strength-based mix design and check freeze–thaw durability; do not use the pH method in Section 7.2.7.1 for sludge.

Source: Yu, Zhang, Lang and Yu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Daniels and Hourani (2009)

Organosilane Treatment: Making Soil Water-Repellent

Organosilanes bond chemically to silica-based soil particles and leave a near-permanent water-repellent surface, unlike ion-exchange treatments. In laboratory and field tests the treatment changed strength and swell only modestly, but cut infiltration dramatically: the near-saturated hydraulic conductivity fell from about 0.8 ft/day to effectively zero. On a 2H:1V slope, soil loss to erosion fell by a factor of nearly 50.

For railroad work: This is an emerging option for erosion control and for reducing infiltration into cut slopes, shoulders and ditch lines, where surface water drives shallow slides and washouts (Chapter 3.8). Treat it as experimental: specify trial sections and monitor them before wider use.

Source: Daniels and Hourani (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Li, Tian, Zhao and Wang (2009)

Industrial Alkaline Slag as Fill

Residue from an alkali (soda) plant was tested in the laboratory and field as fill. It performed as a usable engineering soil for filling low ground and could be placed like ordinary plain soil, with environmental effects evaluated on specific projects.

For railroad work: Industrial by-products can sometimes serve as fill for yards and access roads, but check leachate chemistry, corrosivity to buried steel and concrete, and any permit conditions before accepting them on railroad property (Chapter 5.4).

Source: Li, Tian, Zhao and Wang (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Singh and Hymavathi (n.d.)

Lime Columns

Lime columns are formed by mixing quicklime into soft clay with a special auger. Quicklime (CaO) takes up water from the surrounding clay and slakes to Ca(OH)2, giving off heat and swelling, which consolidates and dries the soil around the column without added load. Calcium ions then exchange onto the clay particles and pozzolanic reactions develop strength over time, and lime diffuses beyond the column. The short-term gain comes mainly from the dewatering effect. Strength measured on columns in the field was much higher than on laboratory-cured samples, because the field soil is confined by overburden.

For railroad work: Lime columns are an alternative to cement deep mixing for soft clay under embankments and widenings (Section 7.2.5). Quicklime is caustic and reacts with heat on contact with water, so storage, handling and personal protection near the track need planning. The swelling columns push the ground outward, so check movement of the existing embankment and track during installation (Chapter 6.2, Section 6.2.18).

Source: Singh and Hymavathi (n.d.). Full reference under Supplemental References.

7.2.8 Geosynthetic Reinforcement
7.2.8.1 Geotextile Filtration and Separation

Geotextiles placed at subgrade/subballast and subgrade/subbase interfaces prevent fines migration (filtration) and maintain aggregate performance (separation). Key design criteria:

Apparent Opening Size (AOS) criterion:

AOS ≤ D85,soil    (retention criterion)

Permeability criterion:

kgeotextile ≥ ksoil    (permittivity criterion)

AASHTO M 288 sets a minimum permittivity of 0.02 s⁻¹ for separation geotextiles. Check the owner railroad's specification (AREMA MRE Chapter 1) for track applications.

Geotextiles and geomembranes under track: what the field record shows

Use a geotextile for what it can do.

  • It is poor at reinforcement. It needs large stretch to work, creeps, slips against ballast, and its openings enlarge as it stretches. Use geogrid for reinforcement.
  • Its main role is separation, with filtration of seepage and in-plane drainage as secondary roles.
  • It does not shed water from above.

Requirements.

  • Only nonwoven fabrics are acceptable.
  • AOS < D85 of the protected soil. For a gap-graded soil, base this on the fines fraction. For new ballast over an undercut surface, use the gradation of the fouling material and ignore the ballast-size particles.
  • High tensile, puncture, elongation, abrasion, chemical and UV resistance.
  • Proven resistance to clogging, and a thick mat where transmissivity is needed.

Nonwovens fine enough for silt, and especially clay, may not exist.

Placement.

  • At least 12 in. below the tie bottom, out of reach of tamping tines and undercutter chains.
  • On a smooth surface sloped to drain, with no equipment running on the fabric and minimal UV exposure.
  • Never in double layers, which create a slip plane.

Durability record.

  • On a Class I railroad, fabric permeability fell 92% and transmissivity 85% within 15 months. Tensile strength fell 54% within 48 months.
  • At an AAR site near Caldwell, Texas, a clogged low-permittivity fabric trapped water, causing excess pore pressure and subgrade failure. It was believed to be the cause of a derailment.

“Undercut and add fabric” repairs often fail because the mud was not coming from the subgrade, or because the subgrade fines were too fine for the fabric. The book’s process is: diagnose the cause in the field and lab; compare geotextile and non-geotextile options; do an economic analysis; run a field trial; monitor and document. Only a properly graded, durable granular layer gives permanent separation and filtration (Chapter 2.3, §3.5.4).

Geomembranes. Uses:

  • Blocking surface infiltration. Place the membrane between sand layers at least 2–4 in. thick, never against ballast, and drain the water off its top.
  • Keeping expansive soil from drying.
  • Cutting capillary rise in frost-susceptible embankments.
  • Forming a cut-off below the water table in cuts.
Figure 7.2-24. EPS blocks being placed.
Figure 7.2-24. EPS blocks being placed.

Hazards: water trapped beneath the membrane creates a slip surface, and holes or leaky seams concentrate flow and erode soil, which is worse than having no membrane. Most leaks are at seams, so require seam testing. A bitumen emulsion sprayed into a sand or subballast layer, which can be done behind an undercutter, is a cheaper alternative with the same trapped-water risk.

After Selig & Waters (1994), ch. 12. Full reference under Supplemental References.

7.2.8.2 Geogrid Reinforcement

Biaxial geogrids (ASTM D6637) placed at subgrade/subbase interface improve load distribution and reduce differential settlement. The Giroud-Han (2004) method for granular layer thickness over weak subgrade:

Geogrid placement on subgrade
Geogrid placement on subgrade

The method gives the required base thickness h from the wheel load P, the tire contact radius r, the subgrade CBR, the number of axle passes N, the allowable rut depth, the base-to-subgrade modulus ratio and, for geogrids, the aperture stability modulus J. Its bearing capacity factor N_c is 3.14 without reinforcement, 5.14 with a geotextile and 5.71 with a geogrid, so the reinforcement benefit is largest on weak subgrade. Use the published equation or a calculator that implements it; for an intermodal reach stacker take the actual tire load and contact area.

For preliminary design, the simplified California chart method (USACE TM 5-818-8) is also acceptable when subgrade CBR and geogrid type are known.

Inputs for the equations in this section (7)
SymbolWhat it isComes fromHow to get itTypical range
hintermediate value computed on this pageAnother equationComputed: h = P / (A_p ⋅ p_s) - 1 K_R ⋅ (1 + ε ⋅ h/√ A_p )    (iterative; ft)project-specific
Pwheel load per wheel (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Apcontact area per wheel (in.²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.≈ 100 in.²
psallowable subgrade stress = 3.2 × s_u for non-reinforcedDesign criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.project-specific
TBRtraffic benefit ratio (1.5–3.0 for biaxial geogrid)Product dataManufacturer's data sheet for the specified product, confirmed by project QA testing.project-specific
KRload distribution factor (depends on h, A_p, and layer modular ratio)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
7.2.8.3 Geosynthetic-Reinforced Load Transfer Platform (GRLT)

Over piled foundations or column-supported embankments (stone columns, rigid inclusions), a Geosynthetic-Reinforced Load Transfer Platform (GRLT) distributes track loads to column heads. GRLT design follows BS 8006:2010 or FHWA-HRT-17-097 (Giroud-Han approach):

Geosynthetic-reinforced haul road
Geosynthetic-reinforced haul road

Membrane tension in geosynthetic over column caps:

Fill placement tensioning geosynthetic
Fill placement tensioning geosynthetic
Tgeosynthetic = WT ⋅ s28 ⋅ δallow    (lb/ft)    (catenary approximation)

Where W_T = net soil weight transferred to geosynthetic (psf); s = clear span between column caps (ft); δ_allow = allowable sag (ft); typically δ ≤ s/30 for railroad applications.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
WTnet soil weight transferred to geosynthetic (psf)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
sclear span between column caps (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
δallowallowable deflection (in.)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.typically δ ≤ s/30 for railroad applications
Base geosynthetic layer over columns
Base geosynthetic layer over columns

Geotextiles in railway subgrades

  • Types: woven (two perpendicular fiber sets, strongly anisotropic) and non-woven (random fibers, isotropic); polypropylene or polyester; 0.016–0.12 in. thick; 2.1–10 oz/yd².
  • Functions: separation of granular layers, reinforcement of weak soil, filtration and drainage, and some frost protection. Most railway installations are simply separators between subballast and subgrade.
  • Placement: under the subballast, never directly under ballast. A geotextile does not spread load, so it must not be used as a reason to reduce ballast or subballast thickness. Railways that did so saw puncture of the fabric and loss of the crossfall.
  • Benefit: a finite-element study found about a 10% reduction in stress at the top of subgrade (Figure 7.2-12). Maintenance savings were reported to repay the geotextile cost quickly.
  • Acceptance: verify tensile strength, elongation at failure, puncture and compressive strength, permeability and filtration against the soil before use. Filter criteria are in Chapter 2.3, §2.3.8.
Geotextile placement, Kansas DOT
Geotextile placement, Kansas DOT
Geotextile Design for Coastal Protection
Geotextile Design for Coastal Protection
Geotextile Filter Design
Geotextile Filter Design
Geosynthetic placement
Geosynthetic placement
Select fill placement over geosynthetic
Select fill placement over geosynthetic
Figure 7.2-12. Finite-element mesh for assessing the reinforcing effect of a geotextile in a railway subgrade. Profillidis Fig. 9.20.
Figure 7.2-12. Finite-element mesh for assessing the reinforcing effect of a geotextile in a railway subgrade. Profillidis Fig. 9.20.

After Profillidis (2014), §9.15, Fig. 9.20. Full reference under Supplemental References.

Geosynthetics, HMA underlayment and EPS: case histories

Geogrid can be placed before laying track or during out-of-face work with an undercutting chain. A hot-mix asphalt layer between 12 in. of ballast and 6 in. of compacted sub ballast spreads load and sheds water to the sides.

Figure 7.2-18. Geogrid reinforcement under the ties or by undercutting chain.
Figure 7.2-18. Geogrid reinforcement under the ties or by undercutting chain.
Figure 7.2-19. HMA underlayment between ballast and sub ballast, shedding water to the sides.
Figure 7.2-19. HMA underlayment between ballast and sub ballast, shedding water to the sides.
  • Prairie main line: subgrade fines contaminated the ballast. Finger tests confirmed plastic fines, and bearing calculations sized the fix: excavate, place full-width woven geotextile, and backfill with clean granular fill.
  • Quebec swamp crossing: decomposed corduroy and organic soil pumped mud. The fix was a shear-key trench along the shoulder backfilled with clean ballast (ideally with nonwoven geotextile), shoulders regraded to drain, and the trench left to drain ballast pockets toward the clay below.
  • Ontario main line: woven geotextile placed beneath a lifted track panel at night within a possession window.
  • EPS lightweight fill (about $670/m³, or about $19/ft³, in 2016 dollars; about $600/m³ in 2012) reduces load on soft ground, but it can float in a flood unless ballasted and drained.
Geotextile Selection — Woven vs Nonwoven
Geotextile Selection — Woven vs Nonwoven
Figure 7.2-20. Full-width woven geotextile on a prairie main line.
Figure 7.2-20. Full-width woven geotextile on a prairie main line.
Figure 7.2-21. Organic mud pumping through ballast at a Quebec swamp crossing.
Figure 7.2-21. Organic mud pumping through ballast at a Quebec swamp crossing.
Figure 7.2-22. Track panel lifted for geotextile placement on an Ontario main line.
Figure 7.2-22. Track panel lifted for geotextile placement on an Ontario main line.
Figure 7.2-23. EPS block fill mass over soft foundation soil.
Figure 7.2-23. EPS block fill mass over soft foundation soil.

After Geotechnology for Railroaders Program, Module 6.2; §03–05. Full reference under Supplemental References.

Geotextile handling under track

  • Limit sunlight exposure to 7 days from removal of the shipping cover to final placement.
  • Keep equipment off geotextile until it has at least 6 in. of sub-ballast or ballast cover.
  • Overlap at least 3 ft in both the longitudinal and transverse directions.
  • Direct surface drainage away from placed fabric to prevent contamination.

Inspection checks are in Chapter 5.3, Table 15-S1.

After UFC 4-860-01FA (2004), ch. 9, §4b. Full reference under Supplemental References.

Case study: 7.2.17.4 Working platform at the edge of a creek, designed for slope stability (Look 2023), in §17.17 Case Studies.

Supplemental reference · Chen, Chen, Wang and Xu (2009)

Column-Supported Embankments: Arching Height and Which Design Method to Trust

Field measurements on an instrumented column-supported embankment confirmed soil arching in the fill and allowed four design approaches to be compared.

  • Arching developed fully once the fill height was at least 1.1 to 1.5 times the clear spacing between column caps.
  • Where the columns floated in the soft layer, the soil below the column tips contributed 50% to 60% of the total settlement.
  • BS 8006 predicted the share of load carried by the columns poorly, and the German EBGEO method predicted much higher values than were measured. The Nordic guideline and the authors’ closed-form method, which includes negative skin friction on the columns, agreed with the measurements.

For railroad work: Keep the embankment above the full-arching height everywhere, including at the low ends of bridge approaches. If the columns do not reach a firm layer, compute the settlement of the soil beneath the column tips explicitly. Check the load share with more than one method; the design procedure in the column-supported embankment sheet (Section 7.2.16) is the starting point.

Source: Chen, Chen, Wang and Xu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Filz and Plaut (2009)

Geosynthetic over Column Caps: Where It Strains Most

Three kinds of numerical analysis of the geosynthetic layer over column caps all showed that strain peaks at the corners of square caps and at the edges of round caps.

  • Peak strain is smaller with round caps than with square caps at the same area replacement ratio.
  • With square caps, strain is smaller when the strands run parallel to the diagonals of the column layout than when they run parallel to the rows.
  • Deflection and strain increase as the vertical load on the geosynthetic increases, and as the area replacement ratio, the stiffness of the soil between columns and the geosynthetic stiffness decrease.

For railroad work: Where a load transfer platform (Section 7.2.8.3) carries track, specify round caps where practical, or orient biaxial reinforcement diagonally to square caps, to reduce peak strain and long-term creep of the reinforcement.

Source: Filz and Plaut (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Han and Bhandari (2009)

Column-Supported Embankments Under Repeated Loading

Most studies of geosynthetic-reinforced, column-supported embankments use static loads, but railroad embankments carry repeated loads. A discrete element model of the fill over pile caps was loaded cyclically.

  • Permanent strain accumulated in the fill with each cycle. The geogrid-reinforced embankment deformed about 25% less than the unreinforced one.
  • Reinforcement increased the share of load carried by the piles, and that share stayed nearly constant through the cycles.
  • Tension in the geogrid kept increasing as it deformed with each cycle, and its distribution between caps depended on the geogrid’s bending stiffness as well as the fill and foundation properties.

For railroad work: Static design methods do not capture the growth of reinforcement tension and fill deformation under train loading. For column-supported track, keep the load transfer platform well above the full-arching height, allow for reinforcement tension growth with load cycles, and monitor track settlement through the first months of traffic (Chapter 3.8, Section 3.8.9).

Source: Han and Bhandari (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Zheng and Liu (2009)

Lateral Behavior of Embankment Columns: Where They Break

Three-dimensional analyses of piled embankments loaded to failure divided the ground under and beside the embankment into three zones:

  • An extension-bending zone under the crest, where columns are pulled and bent.
  • A shear zone under the side slope, where deflections and bending moments are largest and unreinforced columns are most likely to break in bending.
  • A compression-bending zone beyond the toe, where columns are least affected.

For columns without steel reinforcement, bending failure is more critical than shear failure. Stability analyses that credit the full shear strength of every column therefore overstate the factor of safety.

For railroad work: For embankment widenings and approach fills on columns, check the columns under the side slope for bending, consider reinforced or composite columns in the outer rows, and do not credit unreinforced column shear strength in the slope stability analysis without checking bending (Chapter 6.3).

Source: Zheng and Liu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Liu, Chen and Liu (2009); Miao, Wang, Zhang and Zhang (2009)

Large-Diameter Concrete Pipe Piles and Controlled Modulus Columns

Cast-in-place concrete pipe piles. A thin-walled concrete pipe about 3.3 ft in outside diameter with a 4-in. wall is cast in place between vibro-driven casings. Field trials for a highway embankment found:

  • Concrete slump should be 2.4 to 3.5 in.
  • Install piles from the center of the area outward.
  • Short controlled pauses while casting prevent gaps in the wall, but pauses longer than about 20 seconds sharply increase concrete use.
  • Integrity and load testing methods used for drilled shafts apply.

Controlled modulus columns. Model tests showed that the share of load carried by the columns is sensitive to the stiffness of the load plate above them, so the stiffness of the cushion or load transfer layer can be used to control total and differential settlement.

For railroad work: Both are alternatives to driven piles for bridge approach embankments. Whatever the column type, the stiffness of the cushion or load transfer platform is a design variable, not just a working surface.

Source: Liu, Chen and Liu (2009); Miao, Wang, Zhang and Zhang (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Huang and Li (2009); Liu, Xie, Shi and Zhu (2009)

Mixed Long and Short, Rigid and Flexible Columns

  • Long, relatively rigid piles control total and differential settlement; short piles mainly raise bearing capacity of the upper soft soil. For the same maximum settlement, a mixed long-and-short layout needs less total pile length than uniform piles.
  • Pile caps raise the share of load carried by the piles. There is an optimum cap coverage that minimizes total and differential settlement.
  • With rigid and flexible piles together, lengthening the rigid piles reduces settlement more effectively than stiffening the flexible ones.
  • The stiffness of the cushion over the piles controls how load is shared among rigid piles, flexible piles and soil.

For railroad work: For long approach embankments, a layout that varies column length with fill height and with depth to firm soil can save cost over a uniform grid. Check differential settlement where the layout changes (Chapter 6.2).

Source: Huang and Li (2009); Liu, Xie, Shi and Zhu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Liao, Ye and Xu (2009)

Geogrid Pullout: Bearing on the Cross Ribs Does Most of the Work

Pullout tests on biaxial geogrid in sand separated the two parts of pullout resistance: friction along the longitudinal ribs and passive (bearing) resistance against the transverse ribs.

  • Both grow with pullout displacement and soften after their peaks.
  • Passive resistance on the transverse ribs was the main contributor, but its share decreased as the normal stress increased.

For railroad work: Pullout capacity of geogrid in reinforced platforms and walls depends on intact transverse ribs and good fill around them. Use the manufacturer’s tested interaction coefficients for the actual fill (Chapter 7.1), and protect the grid from installation damage that would cut the cross ribs.

Source: Liao, Ye and Xu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

7.2.9 Worked Examples
The four examples size the most common ground improvement methods under railroad fills, yards and track: wick drains, stone columns, lime treatment and slurry injection of ballast pockets. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 7.2-1: Wick Drain Spacing for a Staged Embankment

A main line embankment widening on a Class I railroad located in coastal Georgia sits on 30 ft of soft fat clay. The next fill stage can go on only after 90% consolidation, and the schedule allows 120 days. Vertical drainage alone is hopeless at this thickness, so the question is how close the wick drains must be.

Plan: triangular patterns = ?de = ?Soft CH, 30 fttwo-way, Hdr = 15 ftUv, Ur at 120 d = ?Staged fillGivenH = 30 ft, two-way; Hdr = 15 ftcv = 0.006; ch = 0.012 ft²/daydw = 0.196 ftTarget U ≥ 90% in 120 daysRequiredUv at 120 daysUr neededDrain spacingBlack = given; red = required
Given and required for Example 7.2-1.

Given

VariableValueDescription
H30 ft, two-way; Hdr = 15 ftSoft CH
cv, ch0.006 and 0.012 ft²/day
dw0.196 ftEquivalent drain diameter
TargetU ≥ 90% in 120 days

Required

  • Vertical degree of consolidation in 120 days
  • Radial degree needed
  • Drain spacing that achieves it

Equations

  1. Eq. 4: Tv = cvt/Hdr²; Uv ≈ √(4Tv/π) — vertical
  2. Eq. 5: 1 − U = (1 − Uv)(1 − Ur) — Carrillo
  3. Eq. 1: μ = ln(de/dw) − 0.75 — drain geometry term, no smear or well resistance; de = 1.05s (triangular)
  4. Eq. 2: Ur = 1 − exp(−8Tr/μ); Tr = cht/de² — Barron and Hansbo radial consolidation

Steps

Step 1 · Vertical (Eq. 4)
0.006 × 120 / 225 = 0.0032
Uv ≈ 6.4%
↓
Step 2 · Radial needed (Eq. 5)
0.10 = (1 − Ur)(0.936)
Ur = 0.893; Tr = 2.235μ/8
↓
Step 3 · s = 5.0 ft
de = 5.25; μ = ln 26.8 − 0.75 = 2.538; Tr = 0.709; t = 0.709 × 27.6 / 0.012
1,628 days: far too long
↓
Step 4 · s = 2.0 ft
de = 2.10; μ = 1.621; Tr = 0.453; t = 0.453 × 4.41 / 0.012
166 days: still too long
↓
Step 5 · s = 1.5 ft
de = 1.575; μ = 1.334; Tr = 0.373; t = 0.373 × 2.48 / 0.012
77 days < 120 days
Spot check: Time scales with de²: halving the spacing cuts the time by about four.
↓
Solution
1.5-ft triangular spacing: about 77 days.

Solution

Wick drains at 1.5-ft triangular spacing reach 90% in about 77 days, inside the 120-day window.

The margin covers part of the effect of smear and well resistance, which are ignored here; check the spacing with the full μ before final design. Install with a static-push mandrel to limit disturbance, and place piezometers at three depths: the next stage goes on when they show 90%, not when the calendar does.

Example 7.2-2: Stone Columns Under a Container Stack

A container laydown area on a Class I railroad located in Port Arthur, Texas, sits on 18 ft of soft fat clay. Four-high stacks would settle about 18 in. Stone columns stiffen the ground; Priebe’s improvement factor says how much, and the column size and spacing are adjusted until the settlement meets the 6-in. target.

Container stack, Δσ = 1,800 psfClay 18 ft, su = 450 psfs = ?S untreated = ? Diameter, spacing for 6 in.?GivenClay 18 ft; Cc 0.45; e0 1.20σ′0 = 1,100 psf; su = 450 psfΔσ = 1,800 psfφ′c = 40° (Kac = 0.217)Target S ≤ 6 in.RequiredUntreated settlementColumn diameter and spacingBlack = given; red = required
Given and required for Example 7.2-2.

Given

VariableValueDescription
ClayH = 18 ft; Cc = 0.45; e0 = 1.20; σ′0 = 1,100 psf; su = 450 psf
Δσ1,800 psfFour-high container stack
φ′c40° (Kac = 0.217)Column stone
TargetS ≤ 6 in.

Required

  • Untreated settlement
  • Column diameter and spacing that meet the target

Equations

  1. Eq. 1: Sc = [CcH/(1 + e0)] log[(σ′0 + Δσ)/σ′0]
  2. Eq. 3: n0 = 1 + as[(5 − as)/(4Kac(1 − as)) − 1]; as = Ac/A; Kac = tan²(45° − φ′c/2) — Priebe (1995), ν = 1/3
  3. Eq. 4: Simproved = Sc/n0

Steps

Step 1 · Untreated (Eq. 1)
(0.45 × 18/2.20) log 2.636 = 3.68 × 0.421
1.55 ft = 18.6 in.; need n0 ≥ 3.1
↓
Step 2 · 30 in. at 5.0 ft square
as = 4.909/25 = 0.196
n0 = 2.15; S = 8.7 in.: no
↓
Step 3 · 36 in. at 5.0 ft
as = 7.069/25 = 0.283
n0 = 2.86; S = 6.5 in.: no
↓
Step 4 · 36 in. at 4.5 ft
as = 7.069/20.25 = 0.349; 1 + 0.349[4.651/(4 × 0.217 × 0.651) − 1]
n0 = 3.52; S = 5.3 in.: yes
↓
Solution
36-in. columns at 4.5-ft square spacing: 5.3 in.

Solution

Untreated settlement is about 18.6 in. Stone columns 36 in. in diameter at 4.5-ft square spacing (n0 = 3.52) bring it to about 5.3 in.

Carry the columns through the full 18 ft of clay, with angular 3/4- to 3-in. stone (φ′ ≥ 40°). Load test production columns (ASTM D1143) at about one per 100, minimum five, and place settlement plates in each quadrant of the stacking area to confirm the performance.

Example 7.2-3: Lime Treatment of a High-Plasticity Clay Subgrade

An access road subgrade on a Class I railroad located near Moose Jaw, Saskatchewan, is fat clay with a PI of 46. Lime lowers the plasticity and builds strength. The first estimate of the lime content uses the PI reduction rule; the design content is then confirmed in the laboratory.

Track subgradeLime-treated layerFat clay (CH) subgradeLime content = ? Field spec = ?GivenCH: LL 66, PL 20, PI 46Sulfate 850 ppm (< ~3,000 review)γd,max = 93 pcf; wopt = 22%Target PI < 12; qu,28 ≥ 50 psiRequiredLime contentField specificationBlack = given; red = required
Given and required for Example 7.2-3.

Given

VariableValueDescription
SoilCH; LL 66, PL 20, PI 46
Sulfate850 ppmBelow the NLA review level of about 3,000 ppm
Proctorγd,max = 93 pcf; wopt = 22%Untreated
TargetPI < 12; qu,28 ≥ 50 psi (assumed)

Required

  • Lime content
  • Field specification

Equations

  1. Eq. 1: PIf ≈ PIi − 5Lp — screening rule, Lp in percent

Steps

Step 1 · Lime content (Eq. 1)
Lp = (46 − 12)/5
6.8%: use 7%
↓
Step 2 · Laboratory check
Treated Proctor about 88 pcf at 24%; qu,28 of 90 to 130 psi in trial mixes; lime demand by the Eades-Grim test (ASTM D6276, pH ≥ 12.4)
↓
Step 3 · Specification
7% hydrated lime, 12 in. deep; mellow 24 to 48 hours; 98% Modified Proctor at −2 to +1% of optimum; protect from freezing 3 days
↓
Solution
7% hydrated lime, 12 in. deep.

Solution

Use 7% hydrated lime (ASTM C977) mixed 12 in. deep, mellowed 24 to 48 hours and compacted to 98% of the treated Proctor.

Test the sulfate content of every borrow lot of about 500 yd³. If any lot exceeds about 3,000 ppm, stop and review the treatment under the NLA guidance (Section 7.2.7.1); switching to cement does not avoid sulfate heave. QC: phenolphthalein checks of distribution, PI at 1 and 7 days, and qu at 7 and 28 days (ASTM D2166).

Example 7.2-4: Slurry Quantity to Fill Ballast Pockets

A main line on a Class I railroad located in central Kansas has been surfaced again and again over a soft clay cut. A CPT sounding at the worst low spot shows ballast from about 2 ft to 6 ft below the top of tie. The roadmaster plans railroad-cement injection over 600 ft of track and asks how much slurry and how much dry cement to order, and how many tank loads that is.

top of tieballast pocketsn = 20% void space3 rods, 5 ft apartw = 8 ftt = 4 ft2 ftSoft clay subgrade (CPT: ballast to 6 ft)V = ? gal/track ft; W = ? lb/track ft; totals for 600 ft = ?GivenPocket zone w × t = 8 ft × 4 ftVoid (replacement) ratio n = 20%7.48 gal per cubic footSlurry: 5 lb dry solids per gallonLength L = 600 ftTank 20,000 galRequiredSlurry per track ft, VDry solids per track ft, WTotals and tank loadsBlack = given; red = required
Given and required for Example 7.2-4.

Given

VariableValueDescription
w, t8 ft, 4 ftWidth and thickness of the ballast pocket zone from the CPT sounding (2 to 6 ft below top of tie)
n20%Void space in the pocket zone that slurry replaces (water and voids)
—7.48 gal/ft³Unit conversion
c5 lb/galDry solids per gallon of railroad-cement slurry (specific gravity about 1.4, above the 1.25 minimum)
L600 ftLength of track to treat
—20,000 galSlurry tank on the flat car

Required

  • Slurry per track foot, V
  • Dry solids per track foot, W, compared with the usual range
  • Total slurry, total dry solids and tank loads for 600 ft

Equations

  1. Eq. 1: A = w × t — area of the pocket zone, ft² (ft³ per track ft)
  2. Eq. 2: V = n × A × 7.48 — slurry, gal per track ft
  3. Eq. 3: W = V × c — dry solids, lb per track ft
  4. Eq. 4: Totals = V × L and W × L

Steps

Step 1 · Pocket zone (Eq. 1)
A = 8 × 4
32 ft² = 32 ft³ per track ft
↓
Step 2 · Slurry (Eq. 2)
0.20 × 32 = 6.4 ft³; 6.4 × 7.48
V ≈ 48 gal per track ft
↓
Step 3 · Dry solids (Eq. 3)
48 × 5
W = 240 lb per track ft
Spot check: Within the usual 200 to 250 lb per track ft; mild sites take about 150 and severe sites up to 1,000.
↓
Step 4 · Totals (Eq. 4)
48 × 600 = 28,800 gal; 240 × 600 = 144,000 lb
28,800 gal; 72 tons; 28,800 / 20,000 = 1.44, so 2 tank loads
↓
Solution
48 gal and 240 lb per track ft; about 72 tons of dry cement in 2 tank loads.

Solution

Plan on about 48 gal of slurry and 240 lb of dry cement per track foot: 28,800 gal and 72 tons for the 600 ft, mixed in two tank loads.

The 20% void ratio is the weakest number in the calculation. It is assumed from the track geometry and maintenance history, not measured, so order some margin and use 48 gal per track ft as the target in the operator’s daily log. If the takes run well short, tighten the crib spacing or add a staged second pass into the skipped cribs. If they run well over, the pockets are larger than the sounding suggested. Because the cone will not push through set cement, check the result with borings for moisture and strength rather than a repeat CPT.

7.2.10 Representative Data Table
Table 7.2-4: Ground Improvement Performance Summary — Multi-Client Railroad Projects
ProjectRailroadSoft SoilMethodSpacing/GridImprovement FactorPre-Treat S_c (in.)Post-Treat S_c (in.)Performance Met?
Coastal GA EmbankmentClass ICH clay, 35 ftPVDs @ 1.5-ft tri1.5 ftU_total = 90%N/A (time)120 daysYes
Port Arthur YardClass ICH clay, 18 ftStone col., 36 in.@5 ftSquare 5 ftn₀ = 3.218.65.8Yes
Moose Jaw RoadClass ICH clay, PI=467% lime, 12-in. depthN/API: 46→11N/API=11Yes
Winnipeg TerminalClass IVarved clay, 25 ftDSM col., 24-in.@5 ftHex 5 ftn₀ = 2.814.25.1Yes
Willamette BridgeClass ILoose sand, liq.DSM panels + cols3 ft gridFS_L: 0.67→1.35——Yes
Passenger corridor EmbankmentPassengerSoft clay, 20 ftPVDs @ 1.25-ft tri1.25 ftU_total = 95%—75 daysYes
Atlanta Yard CLClass ICL clay, PI=225% lime, 12-in. depthN/API: 22→10N/API=10Yes
7.2.11 Reference Photographs
Ground Improvement Methods
Ground Improvement Methods
Stone column construction with vibro rigs
Stone column construction with vibro rigs
Cement-soil column auger and cement hopper
Cement-soil column auger and cement hopper
Proctor Compaction Test
Proctor Compaction Test
Column Load Distribution
Column Load Distribution
7.2.12 Practical Recommendations
  1. Select the improvement method based on the governing constraint, not generic practice. For railroad applications, the governing constraint is almost always time (construction schedule), not cost. PVDs with surcharge are cost-effective but slow; DSM and stone columns are faster but more expensive. Always map the client's construction schedule against the consolidation time required for each method before recommending.
  2. Conduct a pre-improvement investigation parallel to improvement design. Ground improvement design requires additional data beyond standard investigation: c_h (from horizontal permeability tests or piezocone dissipation testing), sensitivity (from VST — Chapter 5.1), OCR profile (from consolidation test or CPTu — Chapters 5.1, 2.2, 6.2). Schedule these tests during the same mobilization as standard borings to avoid a second mobilization.
  3. Verify smear zone impact on PVD performance before finalizing spacing. In sensitive and structured clays (for example, Champlain Sea clays in Quebec), mandrel installation smears the horizontal permeability zone by a factor k_h/k_s of 3–8. Uncorrected Hansbo-Barron analysis that ignores smear can substantially overestimate the consolidation rate, leading to inadequate wait periods. Use the full μ formulation or correct from piezocone dissipation results.
  4. Install pre-construction and post-improvement plate bearing tests for stone column and DSM projects. Improvement factor n₀ is a design estimate. Owner railroads may require at least one post-treatment plate bearing or pressuremeter test per 5,000 ft² of treated area to verify that the design improvement factor has been achieved in the field. Document pre-improvement and post-improvement data in the same GDR section for direct comparison.
  5. Do not specify lime treatment without sulfate testing. Ettringite swell from high-sulfate clays has caused heave failures under pavements and track. The roughly $28–55 cost (2016 dollars) of an ASTM D4327 sulfate test is trivial compared to remediation of failed lime stabilization. Test every distinct soil horizon and every new borrow area before specifying lime.
  6. Coordinate vibration exclusion zones with railroad operations before mobilization. Dynamic compaction and vibratory pile driving within 150–200 ft of active track require written authorization from the client's chief engineer, a pre-activity vibration baseline, continuous PPV monitoring during work, and a defined shutdown threshold (typically 0.5 in./s at rail). Failure to coordinate this before mobilization results in work stoppages and day-rate equipment charges. Obtain written approval from the owner railroad's engineering department well before the activity (often 30 days).
  7. Provide a performance monitoring plan as a deliverable — not an afterthought. Ground improvement performance is verified by instrumentation: settlement plates, piezometers, inclinometers, and periodic plate bearing or vane shear tests. The monitoring plan, trigger levels, and reporting frequency should be finalized during design and included in the GDR. Owner railroads may expect electronic data transmittal to their infrastructure management systems weekly during active consolidation monitoring.
Project management · Miller (2009)

Precedence Logic, Lags and Effective-Workday Durations for Ground Improvement Sequencing

Miller describes the precedence diagramming method (PDM), in which boxes are activities and arrows are relationships. PDM allows four link types: finish-to-start (F-S), start-to-start (S-S), finish-to-finish (F-F) and start-to-finish (S-F). He considers F-S sufficient for almost every real situation and warns that the other three are seldom needed. A lag is a delay placed on a link. It is appropriate only for a true waiting period that uses no resources and is outside the manager’s control, such as shipping time. It should not be used to hide work, and because most software does not draw lags on the network, they show up only in the dates.

Two further points apply to duration estimates. First, the most common network flaw is building logic around limited resources; logic should assume unlimited resources, with resource conflicts resolved later during scheduling. Second, subject-matter experts usually estimate workload (hours of effort for an average performer), not duration. Duration is workload divided by the effective workday, the hours per day actually available to the activity: 48 hours ÷ 6 hours per day = 8 days. Where an estimate is uncertain, Miller uses a PERT weighted average, (optimistic + 4 × most likely + pessimistic) ÷ 6; with 6, 10 and 20 days the result is about 11 days.

For railroad work:

  • Do not model a surcharge or PVD consolidation hold as a lag. It is a geotechnical hold point with an exit criterion (settlement rate or excess pore pressure from the monitoring program), so show it as a visible activity whose duration is the design estimate, with a separate “geotechnical release” milestone.
  • Lags suit genuine passive waiting periods, such as cure time before coring cement-treated or deep-mixed soil, or delivery of geosynthetics and drain material after approval of submittals.
  • S-S links with a lag describe production that follows behind other production: test-column verification or QC coring can start a set number of days after stone column or DSM installation starts, without waiting for it to finish.
  • For work under track protection, the effective workday is the authorized window minus time to set up protection, travel, and clear the track. Estimate rig or crew workload in hours and divide by that effective figure, not by the nominal shift length.

Source: Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group), pp. 72–75, 105–109. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Kelly et al. (2004)

Paired Comparison and Weighted Scoring for Option Selection

Kelly, Male and Graham recommend weighting and scoring when several technically feasible options compete and none is clearly best. The first step is to agree on the criteria. Correlated criteria should be avoided because they count the same attribute twice; their example is that ease of cleaning and cost of cleaning should not both be used. Weights then come from a paired comparison. Each criterion is compared with every other, the more important of each pair is recorded, and each criterion’s number of “wins” becomes its weight. Each option is scored 1–5 against each criterion. Score is multiplied by weight and the products are summed. Sensitivity checks, made by changing a few weights and scores, show whether the ranking is robust.

Paired-comparison grid in which each criterion is compared with every other, and the count of wins becomes the criterion weight.
Figure 17-PM2. Paired-comparison grid in which each criterion is compared with every other, and the count of wins becomes the criterion weight. Source: Kelly et al. (2004), Fig. A1.15.

Their worked example compares internal partitions for a building that is reorganized every two to six years. Eight criteria (demountability, noise attenuation, finish, support of fittings, concealing services, capital cost, maintenance cost and reliability of supply) received weights of 4, 6, 3, 0, 5, 3, 4 and 3. Stud-and-board partitions totaled 109 and plastered blockwork 104, while the proprietary systems scored 76–91, mainly because noise attenuation carried the highest weight. The authors say the result should prompt a second look rather than be accepted mechanically. Any preferred option must still be technically feasible, economically viable, functionally suitable and acceptable to the client.

For railroad work: The method suits ground improvement and subgrade remediation choices, such as undercut-and-replace versus geogrid-reinforced subballast versus lime or cement stabilization versus deep soil mixing. Typical criteria are track outage required, ability to work from the track or the right-of-way, settlement performance under the design traffic in MGT, construction risk in the expected soils, capital cost, maintenance demand and supply-chain or contractor availability. Derive the weights with the railroad’s engineering and operations staff in the room, because operations typically values outage time very differently from engineering. Keep capital cost as one weighted criterion, or compare it separately on a whole-life basis, and show the sensitivity run in the report so the choice can be audited.

Source: Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science, pp. 75–77, 308–310. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · ASCE (2013)

Prescriptive versus Performance Specifications for Ground Improvement

The ASCE Committee on Specifications defines two basic types of specification.

  • A prescriptive specification is a recipe. It names the materials, procedures and workmanship. If the contractor follows the recipe and the result falls short, the engineer is responsible.
  • A performance specification describes the end result and leaves products, equipment and techniques to the contractor.

A performance specification has three requirements:

  1. the end result must be described completely;
  2. it must be verifiable by straightforward testing or inspection with detailed acceptance criteria;
  3. the bidding period may need to be longer, because bidders may have to do development work before pricing.

The guide compares the two types as follows:

  • Bidding: easier under prescriptive specifications.
  • Innovation: favors performance specifications.
  • Design control: stays with the engineer under prescriptive specifications.
  • Cost: performance specifications usually cost less on complex work and make little difference on simple work.
  • Testing: prescriptive work needs more testing as it is placed, while performance work needs more testing of the finished product.

Prescriptive specifications fit where the end result cannot be fully defined or where loss of design control is unacceptable. Performance specifications fit where end-result specification is normal practice, or where the contractor’s ingenuity is wanted. The two can be combined, as with concrete specified by both strength and mix limits, but they must not conflict on the same product or activity.

For “or equal” clauses, list the salient characteristics that will be used to judge equality. Read every reference standard before citing it, because standards contain options and may conflict with one another. Do not over-specify. Each tighter quality level or tolerance adds cost.

For railroad work: Ground improvement suits a performance or hybrid approach, because specialty contractors own the equipment and know-how. A deep soil mixing or grouting GSP for an embankment or subgrade might specify:

  • minimum unconfined strength and coefficient-of-variation targets, from wet-grab or core testing at stated frequencies;
  • column geometry and overlap;
  • allowable heave or ground and track movement, monitored against track-geometry limits;
  • the mix design, test columns and QC records as contractor submittals.

Avoid also fixing the binder dosage and mixing energy unless the railroad accepts responsibility for the result. Stone columns and PVDs are often specified prescriptively (spacing, length, material). In that case acceptance should be based on installation records, and settlement performance should not be made a separate contractual guarantee unless the design responsibility is transferred clearly.

Source: ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers, pp. 14–22. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Sullivan et al. (2015)

Breakeven Analysis: How Often Must a Problem Recur Before Improvement Pays?

Sullivan et al. use breakeven analysis when the choice between two alternatives turns mainly on one uncertain factor. Write the equivalent worth (PW or annual worth) of each alternative as a function of that factor, set the two expressions equal, and solve for the factor. If the best estimate of the factor lies above the breakeven value, one alternative wins; if below, the other does. The method works the same way for a single project: set its equivalent worth to zero and solve for the factor.

Factors commonly tested this way are annual expenses, interest rate, service life, and hours of use. In their examples, a hybrid car beats a conventional car only above a fuel price of $3.64/gal. Three motors trade places at 1,694 and 4,389 operating hours per year. In each case the analysis gives the decision-maker one number to argue about instead of a whole cash-flow table.

For railroad work: the classic case is ground improvement or undercutting compared with continued spot maintenance at a chronic soft subgrade or mud spot. The uncertain factor is how many maintenance interventions a year the location really needs. Each intervention includes surfacing, ballast, flagging, and the train-delay cost of the slow order that follows. As an illustration only, with inputs chosen for the example:

  • Permanent fix: $600,000 first cost, 25-year life, 7% discount rate. Its equivalent annual cost is $600,000 × (A/P, 7%, 25) = $600,000 × 0.0858 = $51,500/yr.
  • Each maintenance intervention: $12,000 all-in.
  • Breakeven: $51,500 / $12,000 = about 4.3 interventions per year, ignoring the small residual maintenance after the fix.

If track inspection records show the spot being surfaced six times a year, the fix is justified. If it is surfaced twice a year, it is not, unless safety risk or capacity value changes the picture. Two other breakeven tests are useful: the service life the improvement must achieve, and the first cost at which it stops paying. Present these breakeven values to the client rather than a single net present worth, because they show plainly which input the decision depends on. They also show which records to check, such as maintenance-of-way work orders and slow-order logs.

Source: Sullivan, W. G., Wicks, E. M. and Koelling, C. P. (2015). Engineering Economy, 16th ed. Upper Saddle River, NJ: Pearson, pp. 476–482. Summarized and paraphrased. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-17 Preconsolidation stress / OCR from CPT σ'ₚ, OCRUse: Intact, inorganic clays. Limits: k is higher in aged/heavily OC clays and lower in fissured clays; calibrate with oedometer tests.
  • IS-20 Hydraulic conductivity from CPT kUse: Naturally deposited soils; first-order profiling of k with depth. Limits: Order-of-magnitude only (±1 log cycle). Not for man-made fills; prefer CPTu dissipation t50 or field pumping tests for design.
7.2.13 Ground Improvement Checklist

Checklist · Part VII · Stabilization Methods

Ground Improvement Checklist

Investigation Phase (Pre-Design)0 of 6
Design Phase0 of 8
Construction Phase0 of 6
Deliverable Phase0 of 5

Levy (2007) describes how a contractor builds a formal Construction Quality Control Plan (CQCP). A qualified CQCP manager owns the plan in the same way a safety director owns the safety program. The plan should include, at a minimum, an organization chart locating the CQCP manager, proposed personnel, designated authorities and their duties, operating procedures for inspections, tests and documentation, a subcontractor and vendor rating system, help in selecting quality-oriented subcontractors, training for field staff, and field inspection report forms.

The core tool is the inspection checklist: a short, numbered list of the quality points for one work type, signed and dated by the inspector. Levy’s concrete placement checklist, for example, runs from approved shop drawings on site and the correct strength ordered, through form and rebar approval, testing requirements (slump, number of cylinders, temperature), vibration, curing, and hot- or cold-weather protection. Similar lists can be prepared for every trade with help from an engineer or a qualified subcontractor. Checklists serve as a guide for less experienced supervisors and also signal that quality matters; copies can be given to the subcontractor to document compliance or deficiencies.

His inspection tips: check quality on every walkthrough and at least weekly; notify the subcontractor promptly of unacceptable work and set a date for correction, then verify it; if poor work continues, bring the subcontractor’s owner or the manufacturer’s representative to the site and confirm the meeting in writing; and walk the work for a punch list before a subcontractor demobilizes.

For railroad work: Ground improvement under or beside track lends itself to this method because acceptance depends on records produced as the work is done. A checklist for each technique (stone columns, jet grouting, compaction grouting, deep soil mixing, PVDs, geosynthetic placement) might cover approved submittal and mix design on site, layout against track stationing and clearance envelopes, installation parameters logged per element (depth, pressure, volume, time), spoil and heave observations, track surface monitoring during work near live track, sampling and testing frequency, and nonconformance actions. Signed checklists, combined with the element logs, give the railroad a defensible basis for accepting work that cannot be seen once it is installed.

Source: Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill, pp. 220–227. Summarized and paraphrased. Full reference under Supplemental References.

Ticks are saved in this browser.
Plain text version

Investigation Phase (Pre-Design)

  • [ ] Confirm soft layer depth, thickness, and lateral extent from boring/CPTu data
  • [ ] Obtain c_v and c_h from consolidation tests and/or piezocone dissipation tests
  • [ ] Measure s_u profile (VST or CPTu N_kt method) to determine staged loading feasibility
  • [ ] Test sulfate content (ASTM D4327) at all sites where lime or cement stabilization is planned
  • [ ] Evaluate sensitivity (S_t = s_u / s_u,remolded) to assess disturbance risk from installation
  • [ ] Confirm access constraints (setback from track, overhead clearance, crane swing radius)

Design Phase

  • [ ] Select improvement method by owner railroad requirements and schedule constraint
  • [ ] For PVDs: compute d_e, μ (full formulation), T_r required; verify drain discharge capacity q_w
  • [ ] For stone columns: compute a_s, n₀ (Priebe); verify composite bearing capacity
  • [ ] For DSM: select binder type; set the laboratory q_u target ≥ 4× the field design q_u (f_lab = 0.25)
  • [ ] For lime/cement: run laboratory trial mixes at 4%, 6%, 8% binder; confirm target PI or q_u
  • [ ] For geosynthetics: verify AOS criterion for filtration; specify permittivity per AASHTO M 288 and the owner's specification
  • [ ] Prepare staged loading schedule with FS_slope ≥ 1.3 at each stage (see Chapter 6.3)
  • [ ] Define performance monitoring instrumentation plan (type, location, frequency, trigger levels)

Construction Phase

  • [ ] Verify mandrel type and size (PVD); document mandrel dimensions for smear zone estimate
  • [ ] Confirm as-installed drain/column locations vs. design grid; document deviations > 6 in.
  • [ ] Monitor piezometer responses and compare to predicted dissipation curves during wait period
  • [ ] Perform QC strength/bearing tests (Table 7.2-3 criteria) after improvement and before loading
  • [ ] Document any anomalous grout takes (grouting), column refusals (stone columns), or auger torque spikes (DSM)
  • [ ] Maintain vibration monitoring log for all activities within client exclusion zone

Deliverable Phase

  • [ ] Include improvement design calculation in GDR appendix (PVD spacing, stone column a_s/n₀, etc.)
  • [ ] Provide as-built drain/column layout plan
  • [ ] Provide performance monitoring data summary (piezometer, settlement plate, strength tests)
  • [ ] Compare post-improvement performance to design targets; note any deficiencies
  • [ ] Transmit monitoring data to client's infrastructure management system in required format
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-14 Undrained shear strength from CPT SᵤUse: Fine-grained soils penetrated undrained (Ic > ~2.6). Limits: Nkt depends on reference test (vane, CIUC, DSS) and plasticity; calibrate locally. Use Nkt toward upper end for conservative Su.
  • IS-20 Hydraulic conductivity from CPT kUse: Naturally deposited soils; first-order profiling of k with depth. Limits: Order-of-magnitude only (±1 log cycle). Not for man-made fills; prefer CPTu dissipation t50 or field pumping tests for design.
7.2.14 Practice Questions
Each question is worked in the same five parts as the examples.
Question 7.2-1: Radial Consolidation at 90 Days

Problem Statement

A railroad bridge approach embankment is to be built over 40 ft of soft clay, and wick drains are planned at the spacing shown to speed consolidation. The railroad wants to lay track 90 days after the fill is placed. The engineer must compute the degree of radial consolidation at 90 days and comment on the drain spacing.

Plan: triangular patterns = 1.5 ftde = 1.575 ftUr at 90 days = ?40 ft soft clay, bridge approachGivench = 0.015 ft²/days = 1.5 ft triangular; de = 1.575 ftdw = 0.196 ftt = 90 daysRequiredUr after 90 daysComment on spacingBlack = given; red = required
Given and required for Question 7.2-1.

Given

VariableValueDescription
ch0.015 ft²/day
s1.5 ft triangular; de = 1.575 ft
dw0.196 ft
t90 days

Required

  • Ur after 90 days

Equations

  1. Eq. 1: μ = ln(de/dw) − 0.75 — drain geometry term, no smear or well resistance; de = 1.05s (triangular)
  2. Eq. 2: Ur = 1 − exp(−8Tr/μ); Tr = cht/de² — Barron and Hansbo radial consolidation

Steps

Step 1 · μ (Eq. 1)
ln 8.035 − 0.75
1.334
↓
Step 2 · Tr
0.015 × 90 / 2.481
0.544
↓
Step 3 · Ur (Eq. 2)
1 − exp(−8 × 0.544/1.334) = 1 − e−3.26
96%
↓
Step 4 · Can the spacing open up?
s = 1.7 ft: de = 1.785, μ = 1.459, Tr = 0.424
About 90%, with 22% fewer drains
↓
Solution
Ur = 96%; 1.7-ft spacing would still reach 90%.

Solution

Ur ≈ 96% at 90 days.

The 1.5-ft spacing is more than needed: 1.7 ft gives about 90% with 22% fewer drains (1.75 ft gives only 88%). Check with smear before opening the spacing.

Question 7.2-2: Stone Column Spacing for a 6-in. Target

Problem Statement

A new railroad yard embankment is predicted to settle 15 in. on untreated soft ground, but the railroad wants no more than 6 in. Stone columns of the diameter and friction angle shown are proposed at a trial square spacing of 6.0 ft. The engineer must find the improvement factor and settlement and adjust the spacing to meet the target.

The method of Example 7.2-2.

Yard embankment, untreated S = 15 in.30-in. columns, 6.0 ft square trials = ?as, n0, improved S = ?Given30-in. columns (Ac = 4.909 ft²)Trial 6.0 ft squareφ′c = 40°Sc untreated = 15 in.Target 6 in.Requiredas and n0 Improved settlementSpacing for the targetBlack = given; red = required
Given and required for Question 7.2-2.

Given

VariableValueDescription
Columns30 in. diameter (Ac = 4.909 ft²)
Trial spacing6.0 ft square
φ′c40°
Sc15 in.Untreated
Target6 in.

Required

  • as, n0 and improved settlement

Equations

  1. Eq. 3: n0 = 1 + as[(5 − as)/(4Kac(1 − as)) − 1]; as = Ac/A; Kac = tan²(45° − φ′c/2) — Priebe (1995), ν = 1/3
  2. Eq. 4: S = Sc/n0

Steps

Step 1 · 6.0 ft
as = 4.909/36 = 0.136
n0 = 1.75; S = 8.6 in.
↓
Step 2 · 5.0 ft
as = 0.196
n0 = 2.15; S = 7.0 in.
↓
Step 3 · 4.5 ft
as = 0.242
n0 = 2.51; S = 6.0 in.
↓
Solution
30-in. columns at 4.5-ft square spacing.

Solution

At 6.0 ft the settlement is about 8.6 in.; 30-in. columns at 4.5-ft square spacing bring it to 6.0 in.

The improvement factor depends almost entirely on the area ratio, so spacing is the main design lever; larger columns at the same spacing do the same job.

Question 7.2-3: Lime Content and Sulfate Screening

Problem Statement

A railroad yard lead is to be built on a fat clay subgrade with the plasticity index shown, and lime treatment is proposed to bring the PI down to 12. A soil test found 1,200 ppm sulfate. The engineer must estimate the lime content and decide whether the sulfate level is a concern for heave.

The method of Example 7.2-3.

Yard leadLime-treated layerFat clay (CH) subgradeLime content = ? Sulfate a concern?GivenPI = 52 (CH)Target PI = 12Sulfate 1,200 ppmRequiredLime contentIs sulfate a heave concern?Black = given; red = required
Given and required for Question 7.2-3.

Given

VariableValueDescription
PI52CH clay
Target PI12
Sulfate1,200 ppm

Required

  • Lime content
  • Whether sulfate is a concern

Equations

  1. Eq. 1: Lp = (PIi − PIf)/5

Steps

Step 1 · Lime
(52 − 12)/5
8.0%
↓
Step 2 · Sulfate
1,200 < about 3,000 ppm (NLA)
Acceptable, with lot testing
↓
Solution
8% lime; sulfate acceptable but test each lot.

Solution

About 8.0% hydrated lime (ASTM C977). Sulfate at 1,200 ppm is acceptable.

Retest each lot of about 500 yd³ during construction; sulfate varies within a deposit. If any sample exceeds about 3,000 ppm, review the treatment; cement is subject to sulfate heave too.

Question 7.2-4: Compaction Acceptance of CL Fill

Problem Statement

A lean clay fill is being placed for a new railroad embankment. A field density test on the latest lift gave the density and moisture shown, and the railroad’s specification requires 95% of Modified Proctor within 2% of optimum moisture. The inspector must decide whether the lift is accepted.

1216202495100105Water content w (%)γd (pcf)105 pcf at 16%field 99.5 at 18%Accept the lift?Givenγd,max = 105 pcf; wopt = 16%γd,field = 99.5 pcf; w = 18%Spec: 95%; w ±2%RequiredAcceptance (density and moisture)Black = given; red = required
Given and required for Question 7.2-4.

Given

VariableValueDescription
γd,max, wopt105 pcf; 16%
γd,field, w99.5 pcf; 18%
Spec95% Modified Proctor; w within ±2% of optimum

Required

  • Acceptance

Equations

  1. Eq. 1: RC = γd/γd,max

Steps

Step 1 · RC
99.5/105
94.8% < 95%: fails
↓
Step 2 · Moisture
18% = wopt + 2%
At the wet limit
↓
Solution
Not acceptable: RC 94.8%, at the wet limit.

Solution

Not acceptable: RC = 94.8%, below 95%, and the moisture is at the wet limit.

Scarify, dry back toward optimum, recompact and retest. Wet-side CL loses strength and settles more, so dry-back is usually more effective than extra passes.

Question 7.2-5: Laboratory Target and Composite Modulus for DSM

Problem Statement

Deep soil mixing is proposed under a new high-speed passenger track built over soft clay, with the field strength, area replacement ratio and moduli shown. The engineer must set the laboratory strength the mix design must reach and estimate the composite modulus and the reduction in track settlement.

High-speed passenger trackSoft clay, Esoil = 500 psiDSM columns, aDSM = 0.25, qu,field = 75 psiflab target = ? Ecomp = ? Settlement reduction?Givenqu,field = 75 psiflab = 0.25 (field/lab)aDSM = 0.25Esoil = 500 psiEDSM = 300 qu,field RequiredLaboratory design strengthComposite modulusSettlement reductionBlack = given; red = required
Given and required for Question 7.2-5.

Given

VariableValueDescription
qu,field75 psiTarget
flab0.25Field-to-laboratory strength ratio
aDSM0.25Area replacement ratio
Esoil500 psiSoft clay
EDSM300 qu,fieldMidpoint of 150 to 500

Required

  • Laboratory design strength
  • Composite modulus and settlement reduction

Equations

  1. Eq. 1: qu,lab = qu,field/flab
  2. Eq. 2: Ecomp = a EDSM + (1 − a)Esoil

Steps

Step 1 · qu,lab
75/0.25
300 psi
↓
Step 2 · EDSM
300 × 75
22,500 psi
↓
Step 3 · Ecomp
0.25 × 22,500 + 0.75 × 500 = 5,625 + 375
6,000 psi: 12 times the soil
↓
Solution
Lab target 300 psi; composite modulus 6,000 psi (12×).

Solution

Specify 300 psi in the laboratory; the composite modulus is about 6,000 psi, twelve times the untreated clay.

A 3-in. untreated settlement would fall to about 0.25 in., within the 0.375-in. Class 7 limit (Table 6.2-1). Verify the field-to-laboratory ratio with wet-grab or core samples early in production; it is the least certain number here.

Question 7.2-6: Freezing for a Jacked Culvert Under Two Tracks

Problem Statement

A Class I railroad located in Ohio needs a box culvert jacked under two main tracks through saturated silty sand below the water table. Dewatering is ruled out because it would settle the track, so the contractor proposes freezing a block of ground around the culvert path with liquid nitrogen for a six-week drive. The railroad’s engineer must estimate the frozen volume, the heat to be removed, the nitrogen needed, and the possible heave of the track (Section 7.2.19).

Two main tracks Saturated silty sand below the water table; γd = 105 pcf, w = 0.20 Water table Frozen block Culvert 20 ft 14 ft Length 60 ft(into page) Required: heave potential GivenLN2: 1,350 lb/yd³initial; same againper 2–3 weeksDrive: 6 weeks RequiredVolume, latentheat, LN2, heave
Figure 7.2-26. Question 7.2-6: frozen block under two tracks.

Given

VariableValueDescription
Frozen block20 ft wide × 14 ft high × 60 ft longAround the culvert path, below both tracks
γd, w105 pcf and 0.20Saturated silty sand
LN2 use1,350 lb/yd³ initial; the same quantity again every 2 to 3 weeksPreliminary values (Table 7.2-20)
Duration6 weeksJacking period after initial freeze
Expansion9%Water to ice by volume

Required

  • (a) Frozen volume
  • (b) Latent heat to remove
  • (c) Liquid nitrogen for the initial freeze and the six-week drive
  • (d) Upper-bound heave if the pore water expansion all went upward

Equations

  1. Eq. 7.2-1: L = 144 γd w Btu/ft³
  2. Eq. 1: Vw/V = γd w / 62.4 — pore water per unit volume
  3. Eq. 2: Δh = 0.09 (Vw/V) × thickness

Steps

Step 1 · (a) Volume
20 × 14 × 60 = 16,800 ft³; / 27
V = 16,800 ft³ = 622 yd³
↓
Step 2 · (b) Latent heat
144 × 105 × 0.20 = 3,024 Btu/ft³; × 16,800
About 51 million Btu
Spot check: Sensible heat to cool the soil well below 32°F comes on top of this.
↓
Step 3 · (c) Nitrogen
Initial 622 × 1,350 = 840,000 lb; six weeks needs 2 to 3 more quantities: 1.68 to 2.52 million lb
Total about 2.5 to 3.4 million lb (1,260 to 1,680 tons)
↓
Step 4 · (d) Heave
Vw/V = 105 × 0.20/62.4 = 0.337; 0.09 × 0.337 = 0.030; × 14 ft
Up to about 0.42 ft (5 in.)
Spot check: Water migrating to ice lenses can add more in silty soil; confinement and lateral expansion can reduce it. Five inches is a first estimate, not a bound.
↓
Solution
622 yd³; about 51 million Btu; 2.5 to 3.4 million lb of nitrogen; up to about 5 in. of heave.

Solution

(a) About 622 yd³. (b) About 51 million Btu of latent heat. (c) About 840,000 lb initially and 2.5 to 3.4 million lb in total. (d) Up to about 5 in. of heave, possibly more in silt.

Several inches of heave under two main tracks is not acceptable without control. Ask the contractor to keep the frozen zone below the track structure, freeze in stages, monitor track geometry continuously with action levels and slow orders, and plan for thaw settlement afterward. The nitrogen quantity, roughly 60 to 80 tanker loads, shows why brine freezing is usually cheaper for jobs lasting several weeks, with nitrogen kept for fast freezing or emergencies. These quantities are preliminary; the freezing contractor designs the system.

7.2.15 Cross-References
TopicRefer To
Laboratory consolidation parameters (c_v, C_c, e₀)Chapter 5.2, Sections 5.2.8–5.2.9
Settlement analysis — untreated and surchargeChapter 6.2, Sections 6.2.4–6.2.8
Slope stability — staged embankment loadingChapter 6.3, Section 6.3.6
Seismic liquefaction — DSM and stone column mitigationChapter 6.5, Section 6.5.7
Bearing capacity of improved groundChapter 6.1, Sections 6.1.3–6.1.4
Subgrade improvement for pavementChapter 7.3, Sections 7.3.6–7.3.7
Compaction testing — nuclear gauge, sand coneChapter 5.3, Sections 5.3.1–5.3.2
Geotechnical Special Provisions — ground improvementAppendix C
Monitoring instrumentation — settlement plates, piezometersChapter 5.3, Section 5.3.5
Rockfall Mitigation and Slope Stabilization
Rockfall Mitigation and Slope Stabilization

End of Chapter 7.2 — Ground Improvement Methods

7.2.16 Ground Improvement Technology Library

Sections 7.2.2 through 7.2.8 describe how each family of ground improvement works and how it is designed for railway loading. This library carries the supporting technology sheets: 45 techniques, numbered 7.2.16.1–7.2.16.45 in alphabetical order and grouped below by category. Each sheet opens with a how-it-works schematic and key figures, followed by its fact sheet, design guidance, QC/QA, specifications, cost information and case histories. Use the Previous / Next buttons at the bottom of each sheet to step through the library in order.

Diagram of the bio-treatment process, linking biogeochemistry, soil habitat, mechanical properties, and field application
Photo 7.2.16-1. Overview of bio-treatment soil improvement systems, showing how biogeochemistry (the chemical reaction network and biological system) and soil habitat interact to alter mechanical properties, with process monitoring guiding up-scaling toward field application. (Adapted from DeJong et al. 2011.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cross-section of a levee illustrating possible bio-treatment applications, including bio-reinforcement of erosion, bio-mineralization of slopes and carbon, bio-
Photo 7.2.16-2. Overview of possible bio-treatment soil improvement systems applied to a levee cross-section — including bio-reinforcement to prevent erosion, bio-mineralization to stabilize slopes and immobilize carbon, bio-film to prevent groundwater seepage, and bio-dechlorination of contaminants. (Jason DeJong, personal communication, 2012.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Light microscope comparison of untreated sand grains and sand grains treated with iron-based biocement
Photo 7.2.16-3. Light microscope photos of (a) untreated sand and (b) sand treated with an iron-based biocement. (Chu et al. 2011; with permission from ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Ground Improvement Techniques
Ground Improvement Techniques

The sheets most relevant to each method are also linked at the end of Sections 7.2.2–7.2.8. Soil nailing, MSE walls and deep foundation sheets support Chapter 7.1 — Retaining Structures and Chapter 6.1 — Bearing Capacity.

Section 7.2.16 · Selection guide

Choosing a technology for a railway problem

Find the problem on the cross-section, read the section that explains the method, then open the technology sheets to compare options.

8Railway problems
35Technology sheets
Railway cross-section showing where each of the eight ground problems occurs Soft clayLoose sandBedrock Cut slopeStockpileEmbankment fill 1234 5678
1Locate the problem on the section
2Read the method in the chapter
3Compare the technology sheets
1
Soft clay under embankment

Soft, compressible clay under new or widened embankment

Drain, preload or support on columns

Click a number on the cross-section to jump to its card. Some technologies, such as aggregate columns, jet grouting, and excavation and replacement, serve more than one problem. Technology sheets open on dirtbert.com.

Open the selection guide on its own page (for printing) →

Full table: choosing a technology for a railway problem

Railway problemWhere the method is discussedTechnology sheets
Soft, compressible clay under new or widened embankment17.3 PVDs / preloading; 17.4–17.5 columns7.2.16.36 Prefabricated Vertical Drains and Fill Preloading
7.2.16.43 Vacuum Preloading with and without Prefabricated Vertical Drains
7.2.16.8 Column-Supported Embankments
7.2.16.9 Combined Soil Stabilization with Vertical Columns
7.2.16.13 Deep Mixing Methods
7.2.16.26 Geotextile Encased Columns
Loose sand or silty sand — settlement or liquefaction17.2 densification; 17.4 stone columns7.2.16.45 Vibrocompaction
7.2.16.12 Deep Dynamic Compaction
7.2.16.37 Rapid Impact Compaction
7.2.16.4 Blasting Densification
7.2.16.1 Aggregate Columns
7.2.16.38 Sand Compaction Piles
Weak or pumping subgrade under track, yard or access road17.7 stabilization; 17.8 geosynthetics7.2.16.7 Chemical Stabilization of Subgrades and Bases
7.2.16.31 Mechanical Stabilization of Subgrades and Bases
7.2.16.2 Bio-Treatment for Subgrade Stabilization
7.2.16.16 Excavation and Replacement
7.2.16.21 Geosynthetic Reinforced Embankments
7.2.16.23 Geosynthetic Separation in Pavement Systems
Voids, sinkholes, abandoned mines or culvert backfill loss17.6 grouting7.2.16.10 Compaction Grouting
7.2.16.5 Bulk-Infill Grouting
7.2.16.6 Chemical Grouting & Injection Systems
7.2.16.30 Jet Grouting
Cut slope or embankment slope instabilityCh 6.3 slope stability; Ch 7.1 retaining structures7.2.16.14 Drilled-Grouted and Hollow Bar Soil Nailing
7.2.16.39 Screw-in Soil Nailing
7.2.16.40 Shoot-in Soil Nailing
7.2.16.32 Mechanically Stabilized Earth Wall System
7.2.16.41 Shored Mechanically Stabilized Earth Wall System
7.2.16.1 Aggregate Columns
Foundations near live track / limited headroomCh 6.1 bearing capacity7.2.16.33 Micropiles
7.2.16.27 Helical Pile
7.2.16.11 Continuous Flight Auger Piles
7.2.16.30 Jet Grouting
Compaction QA and fill acceptance17.2 compaction; Ch 5.3 monitoring7.2.16.29 Intelligent Compaction
7.2.16.42 Traditional Compaction
7.2.16.28 High-Energy Impact Rollers
Reuse of on-site or recycled materials17.7 stabilization7.2.16.3 Beneficial Reuse of Waste Materials
7.2.16.34 Onsite Use of Recycled Pavement Materials
7.2.16.16 Excavation and Replacement
Geosynthetic grids for foundation reinforcement and slope stabilization
Geosynthetic grids for foundation reinforcement and slope stabilization

Vertical Columns & Deep Mixing (7)

Subgrade & Base Stabilization (3)

Materials Reuse & Recycling (3)

Densification & Compaction (7)

Grouting & Injection (4)

Piles & Deep Foundations (3)

Soil Nailing & Retaining Structures (5)

Preloading, Drainage & Dewatering (3)

Geosynthetics & Pavement Systems (10)

Technology sheets compiled from FHWA, SHRP2 GeoTechTools and manufacturer literature; each sheet lists its own sources.

7.2.17 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental References.

Case Study 17.17.1 — Measuring roller force with pile-driving monitors
Case study · Look (2023) §7.10

Related section: 7.2.2 Compaction Methods

Three trial embankments were built from extremely to slightly weathered rock taken from site cuttings: sandstone, basalt, and interbedded siltstone/sandstone. All of it broke down to meet “soil” specifications during placement and rolling (Look and Lacey, 2017). A 20.6-ton vibrating padfoot and a 19-ton smooth drum roller compacted each fill at field and targeted moisture.

Pile-driving monitors (PDM), which normally record set and energy for each hammer blow, tracked reflectors on the rollers. They measured each pass’s set, vibration frequency, amplitude, peak velocity and acceleration, and so the peak compaction force, which is not the same as static weight. Findings:

  • Dynamic force was well above static weight and changed with material and with each pass as the ground stiffened: about 26–40 tons equivalent for the padfoot and up to 76 tons for the smooth drum on the interbedded fill.
  • Maximum force and best material performance came after five to six passes; beyond that the values cycled and some rebound occurred.
  • Over-compaction broke the material down, which showed both in the force record and later in borehole shear test strengths.

Table 17-LK1. Padfoot roller, manufacturer’s values against PDM measurements (after Look 2023, Table 7.13)

ParameterManufacturerMeasured with PDM, three fills
Vibration frequency29 Hz high amp., 31 Hz low27.2–30.9 Hz (range)
Roller speed0–7 mphmedian 2.8 mph
Amplitude0.071 in. high, 0.047 in. lowmedians 0.055–0.087 in.
Force71 kips high amp., 52 kips lowmedians 53–83 kips

For railroad work: a pass-count specification without a check of the roller’s actual output can over-work weathered-rock fill. A trial embankment with measured rebound is a sound way to set the pass count for a large rail embankment.

Measured dynamic force of a 20.6-ton padfoot and a 19-ton smooth drum roller on three trial embankments.
Figure 17-LK1. Measured dynamic force of a 20.6-ton padfoot and a 19-ton smooth drum roller on three trial embankments. Source: Look (2023), Figure 7.10-3, p. 235.
Induced compaction (mm in the original figure; 25.4 mm = 1 in.) with each pass on the interbedded trial; rebound appears at about 5–6 passes.
Figure 17-LK2. Induced compaction (mm in the original figure; 25.4 mm = 1 in.) with each pass on the interbedded trial; rebound appears at about 5–6 passes. Source: Look (2023), Figure 7.10-5, p. 237.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §7.10, pp. 232–236. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 17.17.2 — Wick-drain rigs on dredged sand over 104 psf clay: four ways to size the platform
Case study · Look (2023) §12.7

Related section: 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading

At the Port of Brisbane reclamation, wick-drain rigs had to work for nine months on 31 acres of dredged sand, about 8.2 ft thick, over Holocene clay with a design undrained strength of 104 psf in the top 20 ft (Look and Honeyfield, 2016). Mud waves during filling left the sand thickness uncertain. BR470 is outside its range here, both for clay under 420 psf and for platform thickness to load width (D/W) above 1.5; it was used for the preliminary design for want of anything better.

Loads. The heaviest rig did not exert the highest pressure: the 50-ton CAT on narrower tracks produced 3,500 psf against 2,030 psf for the 89-ton machine. Check every rig.

Parameters. 27 LFWD tests, 8 DCPs and 4 borehole shear tests gave the sand properties. Two proof-roll passes raised the LFWD modulus by about 20% and reduced its scatter (10th percentile 4,400 psi rolled against 3,260 psi unrolled). Groundwater was found at 6.2–10 ft, not the 20 in. assumed. Clay directly under the sand measured 42–380 psf.

Four answers.

  • BR470 deterministic: 7.5 ft required.
  • BR470 with a PERT distribution and Latin Hypercube simulation: baseline 7 ft; 7.5 ft has under 5% probability of being exceeded. Subgrade strength dominates the tornado chart.
  • Finite element displacement, calibrated to proof-roll ruts, with a 3 in limit: 6.9 ft.
  • Finite element stress at the sand/clay interface against a lower-bound bearing factor Nc = 3.14 for combined shear, as mud waves imply: 7 ft.

Proof rolling as the check. A loaded proof truck will bog rather than topple, while an eccentrically loaded rig can topple, so the truck is the safer test. Proof rolling only means something with a defined vehicle and an acceptance deflection. A rock-filled truck loaded more evenly than a water truck (whose load sloshes) and was preferred. Mean ruts were 3.7 in. after one pass and 5.2 in. after two, and 4.7 in was adopted as the acceptance criterion.

Table 17-LK2. Wick-drain rigs and track pressures (after Look 2023, Table 12.20)

RigWeight (tons)Track width (ft)Critical track pressure
Komatsu excavator6532,700 psf
CAT excavator5033,500 psf
Komatsu excavator894.32,030 psf

For railroad work: ground improvement under new embankments on soft soil, such as wick drains for a yard expansion or a new grade across a marsh, puts the rigs on exactly this kind of platform. Size it by more than one method and calibrate the proof roll before the rigs move on.

Issues considered for the platform: load, rig type, parameters, thickness, groundwater and methodology (Look and Honeyfield 2016).
Figure 17-LK3. Issues considered for the platform: load, rig type, parameters, thickness, groundwater and methodology (Look and Honeyfield 2016). Source: Look (2023), Figure 12.7-1, p. 437.
Measuring proof-roll rut depth; LFWD tests were run in and away from the wheel path (Look and Honeyfield 2016).
Figure 17-LK4. Measuring proof-roll rut depth; LFWD tests were run in and away from the wheel path (Look and Honeyfield 2016). Source: Look (2023), Figure 12.7-8, p. 445.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.7, pp. 432–446. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 17.17.3 — Lime-treated local soil in a reinforced slope: choosing by total internalised cost
Case study · Look (2023) §12.8

Related section: 7.2.7 Lime and Cement Stabilization

Prolonged rain in 2010/11 triggered a 656 ft landslide under a Sunshine Coast hinterland road, in colluvium up to 20 ft thick below a steep escarpment (Look 2012; Chew et al. 2012; Boyer et al. 2013). Five remediation options were compared on total internalised cost: construction cost plus embodied energy, greenhouse-gas emissions from fuel, transport and materials, and the cost of damage to local roads from heavy trucks hauling material. Environmental costs ranged from 2% to 23% of construction cost.

Options 3 and 4 had the lowest totals. Option 3 was chosen because the road authority wanted the fewest heavy trucks on local roads, and lime treatment let the high-plasticity “unsuitable” colluvium be screened of boulders and reused. With 4% hydrated lime cured seven days, shear box cohesion rose from about 420 psf to 1,250–2,200 psf at a similar friction angle; the design still used a softened cohesion of 104 psf.

The work was done in five stages with soil-nailed temporary slopes, drainage slots and regular inclinometer and survey monitoring. When inclinometer 2 showed excessive movement, inspection found a tree at the crown destabilized by the excavation. Once it was felled, the movement stopped.

Table 17-LK3. Remediation options, 2011 AU$ (after Look 2023, Table 12.23, from Chew et al. 2012)

OptionConstructionEnvironmentalTotal internalised
1. Cast-in-place pile wall with ground anchors*3,300,00067,0003,367,000
2. Rockfill buttress3,800,000628,0004,428,000
3. Reinforced fill slope, lime-treated local soil2,400,000278,0002,678,000
4. Reinforced fill slope, imported granular fill2,000,000452,0002,452,000
5. Earth fill embankment with rock toe3,200,000444,0003,644,000
* Greatest technical uncertainty.

For railroad work: slide repairs on remote lines face the same haul-cost and community questions. Reusing treated local soil cuts truck traffic on rural roads, and staged excavation with inclinometers is the standard of care on an active slide.

Cross section through the 660 ft landslide in up to 20 ft of colluvium (Chew et al. 2012).
Figure 17-LK5. Cross section through the 660 ft landslide in up to 20 ft of colluvium (Chew et al. 2012). Source: Look (2023), Figure 12.8-1, p. 447.
Inclinometer 2 showed excessive movement, traced to a crown tree destabilized by the excavation.
Figure 17-LK6. Inclinometer 2 showed excessive movement, traced to a crown tree destabilized by the excavation. Source: Look (2023), Figure 12.9-3, p. 449.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.8, pp. 446–448. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 17.17.4 — Working platform at the edge of a creek, designed for slope stability
Case study · Look (2023) §12.6

Related section: 7.2.8 Geosynthetic Reinforcement

A bridge pier at the edge of a creek, with the next pier 8 ft into it, needed a platform for a BG28 piling rig for a day and an outrigger crane for beam lifting. The temporary-works designer rightly declined to design it with the standard method, since slope stability over soft clay governed. Sheet piling would have cost almost five times the roughly AU$100,000 (2015) platform. Moving the pier about 10 ft would have removed the problem, which shows why constructability belongs in design.

A deep rock-fill replacement moved the critical slip surface deeper, with high-strength geogrids within the rock fill. Stability was checked separately for standing (uniform 3,800 psf, FS 1.5, above the 1.3 usually accepted for temporary works), penetrating (uniform and trapezoidal, FS 1.3) and extracting. The extracting case was the most critical (FS 1.2) even though its 5,500 psf design pressure is lower than penetration’s 6,400 psf, because of where the load sits. Large plate load tests were run but cannot test a deep slip surface, so an excavator was walked along the edge first. The work went without incident, though rig depressions had to be repaired before the outrigger came on.

Table 17-LK4. Design pressures for the BG28 piling rig (after Look 2023, Table 12.19)

OperationDesign pressureFactor of safety adopted
Handling / transporting / standing3,780 psf1.5
Penetration6,390 psf1.3
Extracting5,470 psf1.2 (critical, trapezoidal)

For railroad work: bridge replacement platforms beside streams and next to embankment slopes need a global stability check for each rig operation, not only a bearing check. The extract phase and the outrigger reactions are often the governing cases.

Platform beside the creek, edge checked with an excavator before the piling rig moved on; design section with multiple high-strength geogrids.
Figure 17-LK7. Platform beside the creek, edge checked with an excavator before the piling rig moved on; design section with multiple high-strength geogrids. Source: Look (2023), Figure 12.6-2, p. 433.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.6, pp. 430–432. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

7.2.18 Research to Practice: Findings for Railroad Ground Improvement

This section collects findings from the proceedings of a United States–China workshop on ground improvement technologies (ASCE Geotechnical Special Publication 188, 2009) that add to the methods in this chapter. Thirty-three papers cover column-supported embankments, column technologies, deep mixing, jet grouting, accelerated consolidation and new materials. The findings that change how a method is designed, specified or checked are placed in orange supplemental boxes in the sections they apply to; this section summarizes them, adds the remaining items, and lists every paper used.

Most of the field cases are highway, building and dam projects. They transfer to railroad work with one important difference: track loading is repeated, and track tolerates much less differential movement than a pavement does. Treat the findings on repeated loading, differential settlement and transitions as the most important for railroad use.

7.2.18.1 Summary of findings and where they apply

Table 7.2-18. Workshop findings for railroad ground improvement (English units)
TopicFindingRailroad useSection
Column-supported embankmentsArching is complete when fill height is at least 1.1–1.5 × clear cap spacing; Nordic guideline best matched field data; floating columns leave 50–60% of settlement below the tipsApproach fills, new track on soft ground7.2.8
Column-supported embankments under repeated loadGeogrid cut permanent deformation about 25%; geogrid tension keeps growing with cyclesAny column-supported track7.2.8
Columns under side slopesUnreinforced columns in the shear zone fail in bending; full shear credit overstates stabilityWidenings, approach fills7.2.8, Ch. 6.3
Geosynthetic over capsRound caps and diagonal strand orientation lower peak strainLoad transfer platforms7.2.8.3
Stone columns in silty sandAdd wick drains; gains fall from ~114% to ~70% as fines rise 30% to 43%; little effect at ≥15% clay-sizeLiquefaction under approaches7.2.4, Ch. 6.5
Acceptance by shear wave velocityVelocity target from earthquake magnitude, converted to void ratio and column spacingCorridor-length liquefaction treatment7.2.4, Ch. 5.1
Deep soil mixing in expansive clay25:75 lime:cement, about 337 lb/yd³, water-to-binder 1.0; reduced swell and shrink over two yearsTurnouts, crossings, approaches on expansive clay7.2.5
Deep-mixing uniformityCore resistivity measures mixing; double-slurry mixing more uniformDeep-mixing QA7.2.5
Composite columnsConcrete or steel core in a soil-cement column; capacity can exceed a bored pile of the same sizeHigh fills, approach embankments7.2.5
Inclined compaction groutingHeave grows with inclination; little change beyond ~70°; depth beyond ~5 diameters adds little at 10–30°Grouting under track from the shoulder7.2.6
Large-diameter jet groutingColumns 2.6–10.8 ft; poor mixing in sand below water; small columns in stiff clayExcavation support and cutoffs beside track7.2.6
Vacuum preloadingNo stability risk during loading; settlement >3 ft and vane strength doubled in case studyYards and embankments on very soft clay7.2.3
Staged construction of tall fillsPVDs cut stage time from ~15 to ~2 years; transitions to abutments need most careTall fills, bridge approaches7.2.3, Ch. 6.2
Dynamic compaction of dumped fillImproved rock-and-soil fill to ≥20 ft; bearing above 9,000 psf; depth confirmed by GPROld end-dumped fills on mountain grades7.2.2
Explosive replacementBlast-driven replacement of soft clay with stone; dense in top 16–20 ftRemote new alignments only7.2.2
Lime sludge; organosilane; alkaline slagSludge acts like lime (use strength, not pH, to set content); organosilane cut erosion ~50×; slag usable as fillFill treatment, slope erosion control, yard fill7.2.7
Geogrid pulloutBearing on transverse ribs is the main resistancePlatforms and walls7.2.8, Ch. 7.1

7.2.18.2 Other findings

  • Reliability-based column coverage. Zheng, Liu and Xu (2009) set the area replacement ratio of multi-column treatments from the spatial variability of the soil, using a target reliability index of 3.0. This is a way to choose column spacing where the soil is variable along an alignment.
  • Simplifying 3D models. Huang and Han (2009) compared ways of converting a three-dimensional column-supported embankment into a plane-strain model. Converting the geometry represented a field-instrumented bridge approach on deep-mixed columns better than converting the material properties.
  • Composite ground in earthquakes. Song and Wu (2009) found that the cushion between rigid piles and the foundation lowers pile forces in earthquakes compared with a conventional pile foundation; the risk of pile damage is at interfaces between soil layers of very different stiffness.
  • Composite ground under flexible loads. Yu, Gong, Liu, Lv and Jing (2009) give closed-form settlement and pile-to-soil stress ratio for a flexible load (such as an embankment) over a cushion and composite ground, considering interaction among all four components.
  • Trench remixing deep (TRD) walls. Evans and Garbin (2009) describe in-place soil mixing of a continuous wall with a slag–cement slurry, used in the United States for cutoff walls including a large lake levee. Cores and borehole camera records showed a more uniform, continuous wall than other methods. Relevant where a railroad embankment also serves as a levee or must cut off seepage.
  • Bio-cementation (MICP). Martinez and DeJong (2009) found that microbially induced calcite forms mainly at grain contacts and reduced footing settlement up to five-fold in model tests, but the cemented sand was brittle and uniform treatment at field scale was unresolved. See the bio-treatment sheet in Section 7.2.16.
  • Post-grouting of bored piles. Xiao, Wu and Wu (2009) report base and side post-grouting of more than 18,000 slurry-drilled piles at one airport terminal, with 72 static load tests showing large gains in capacity and settlement performance, especially in sand. This belongs with deep foundation design; see Chapter 6.1, Section 6.1.5.
  • SHRP2 R02 technology catalog. Schaefer, Filz and Vanzler (2009) report the first phase of the SHRP2 R02 project, which identified 47 ground improvement technologies and the technical and non-technical obstacles to their use. The technology sheets in Section 7.2.16 are built from that program’s products.

7.2.18.3 How to use these findings

  • Design. For column-supported track, check arching height, column bending under side slopes and reinforcement tension growth under repeated load, in addition to the static design procedure in the Section 7.2.16 sheet.
  • Specification. Require trial columns or test sections in each soil type for jet grouting, deep mixing and stone columns, because diameter, uniformity and improvement vary strongly with soil.
  • Acceptance. Add a uniformity check for deep mixing, consider shear wave velocity targets for liquefaction treatment, and allow time for strength gain before acceptance testing.
  • Track protection. Estimate heave before grouting under track and settlement before preloading beside it, and set geometry limits and monitoring frequency for the work (Chapter 5.3).
  • Risk rating. Record which of these measures are part of the design and construction when assigning the risk reduction ratings in Chapter 3.8.

7.2.18.4 Sources

Papers in Han, J., Zheng, G., Schaefer, V. R. and Huang, M. (eds.) (2009), Advances in Ground Improvement: Research to Practice in the United States and China, ASCE Geotechnical Special Publication 188, Reston, VA. Summaries are paraphrased and values converted to English units.

  1. Schaefer, V. R., Filz, G. M. and Vanzler, L. S. (2009). “SHRP2 R02 Phase 1 — Geotechnical Solutions for Soil Improvement, Rapid Embankment Construction, and Stabilization of the Pavement Working Platform.” GSP 188, 1–11.Find source ↗
  2. Zheng, G., Liu, S. and Chen, R. (2009). “State of Advancement of Column-Type Reinforcement Element and Its Application in China.” GSP 188, 12–25.Find source ↗
  3. Chen, R. P., Chen, Y. M., Wang, S. H. and Xu, Z. Z. (2009). “Theoretical Study and Field Tests on Pile-Supported Embankments over Soft Ground.” GSP 188, 26–35.Find source ↗
  4. Huang, J. and Han, J. (2009). “Approaches for 2D Coupled Modeling of Column-Supported Embankments.” GSP 188, 36–45.Find source ↗
  5. Huang, M. and Li, B. (2009). “Numerical Analysis of Pile-Supported Earth Platforms with Non-Uniform Piles.” GSP 188, 46–54.Find source ↗
  6. Filz, G. M. and Plaut, R. H. (2009). “Practical Implications of Numerical Analyses of Geosynthetic Reinforcement in Column-Supported Embankments.” GSP 188, 55–62.Find source ↗
  7. Zheng, G. and Liu, L. (2009). “Numerical Analysis of the Pile Lateral Behavior and Anti-Slip Mechanism of Rigid Pile Supported Embankments.” GSP 188, 63–72.Find source ↗
  8. Han, J. and Bhandari, A. (2009). “Evaluation of Geogrid-Reinforced Pile-Supported Embankments under Cyclic Loading Using Discrete Element Method.” GSP 188, 73–82.Find source ↗
  9. Zheng, J. J., Liu, Y. and Xu, Z. J. (2009). “Reliability-Based Design Applied to Multi-Column Composite Foundations.” GSP 188, 83–91.Find source ↗
  10. Yu, J. L., Gong, X. N., Liu, C., Lv, W. Z. and Jing, Z. J. (2009). “Working Behavior of Composite Ground under Flexible Foundations Based on Super-Substructure Interaction.” GSP 188, 92–101.Find source ↗
  11. Liu, K., Xie, X., Shi, S. and Zhu, X. (2009). “Numerical Analysis on the Performance of a Cushioned Foundation with a Mixture of Both Rigid and Flexible Piles.” GSP 188, 102–111.Find source ↗
  12. Miao, L., Wang, F., Zhang, Y. and Zhang, C. (2009). “Experimental Study on Controlled Modulus Column Methods.” GSP 188, 112–119.Find source ↗
  13. Liu, H., Chen, Y. and Liu, J. (2009). “Construction of a Large Diameter Cast-in-Situ Concrete Pipe Pile for Ground Improvement.” GSP 188, 120–129.Find source ↗
  14. Madhyannapu, R. S., Puppala, A. J., Bhadriraju, V. and Nazarian, S. (2009). “Deep Soil Mixing (DSM) Treatment of Expansive Soils.” GSP 188, 130–139.Find source ↗
  15. Liu, S., Zhang, D. and Zhu, Z. (2009). “On the Uniformity of Deep Mixed Soil-Cement Columns with Electrical Resistivity Method.” GSP 188, 140–149.Find source ↗
  16. Zhou, Y. G., Chen, Y. M. and Chen, R. P. (2009). “Evaluation of Ground Improvement for Liquefiable Deposits Using Shear Wave Velocity.” GSP 188, 150–159.Find source ↗
  17. Rollins, K. M., Quimby, M., Johnson, S. R. and Price, B. (2009). “Effectiveness of Stone Columns for Liquefaction Mitigation of Silty Sands with and without Wick Drains.” GSP 188, 160–169.Find source ↗
  18. Shen, S. L., Luo, C. Y., Xiao, X. C. and Wang, J. L. (2009). “Improvement Efficacy of RJP Method in Shanghai Soft Deposit.” GSP 188, 170–178.Find source ↗
  19. Wang, J. L., Wang, D. F. and Wang, J. W. (2009). “State of Jet Grouting in Shanghai.” GSP 188, 179–188.Find source ↗
  20. Song, E. and Wu, S. (2009). “Seismic Analysis of Rigid Pile Composite Ground.” GSP 188, 189–197.Find source ↗
  21. Xiao, D., Wu, C. and Wu, C. (2009). “Bored Pile Post-Grouting Technology and Its Engineering Application.” GSP 188, 198–206.Find source ↗
  22. Shao, L. (2009). “Soil Improvement to Support a Warehouse Building over Difficult Soils.” GSP 188, 207–216.Find source ↗
  23. Daniels, J. L. and Hourani, M. S. (2009). “Soil Improvement with Organo-Silane.” GSP 188, 217–224.Find source ↗
  24. Li, X., Tian, X., Zhao, Z. and Wang, X. (2009). “Study for Engineering Utilization of Slag Soil in Tianjin Alkaline Factory.” GSP 188, 225–233.Find source ↗
  25. Basu, P., Madhav, M. R. and Prezzi, M. (2009). “Estimation of Heave Due to Inclined Compaction Grouting.” GSP 188, 234–241.Find source ↗
  26. Martinez, B. C. and DeJong, J. T. (2009). “Bio-Mediated Soil Improvement: Load Transfer Mechanisms at the Micro- and Macro-Scales.” GSP 188, 242–251.Find source ↗
  27. Liao, X., Ye, G. and Xu, C. (2009). “Friction and Passive Resistance of Geogrid in Pullout Tests.” GSP 188, 252–259.Find source ↗
  28. Yu, X., Zhang, B., Lang, J. and Yu, X. (2009). “Sustainability through Beneficial Use of Lime Sludge for Construction.” GSP 188, 260–270.Find source ↗
  29. Evans, J. C. and Garbin, E. J. (2009). “The TRD Method for In Situ Mixed Vertical Barriers.” GSP 188, 271–280.Find source ↗
  30. Lu, X., Filz, G. and Han, J. (2009). “Dynamic Compaction of Fill in a Mountainous Area.” GSP 188, 281–289.Find source ↗
  31. Yan, S., Dong, W. and Chu, J. (2009). “Use of Explosion in Improving Highway Foundation.” GSP 188, 290–297.Find source ↗
  32. Edil, T. B. and Berilgen, M. M. (2009). “Construction of Earth Dams on Soft Ground: Principles and Examples.” GSP 188, 298–307.Find source ↗
  33. Yan, S., Feng, X. and Chu, J. (2009). “Mechanism of Using Vacuum Preloading Method in Improving Soft Clay Layers.” GSP 188, 308–318.Find source ↗
7.2.19 Thermal Methods: Ground Freezing and Heat Treatment

Thermal methods change the ground by removing or adding heat. Artificial ground freezing turns pore water into ice, giving the soil very high temporary strength and making it nearly watertight within hours to weeks. Heat treatment bakes clay at several hundred degrees and changes it permanently. Freezing is a specialist but established method; heat treatment is mostly of historical interest because of its fuel use (Hausmann 1990).

7.2.19.1 Where freezing is used

  • Temporary earth retention and groundwater cutoff for excavations and shafts in water-bearing sand, silt and weak rock.
  • Ground support and seepage control ahead of tunnels and jacked or bored crossings.
  • Sealing leaks in buried pipes, temporary stabilization of landslides, and undisturbed sampling of clean sand.

Freezing works in almost any soil or rock with enough pore water, which sets it apart from grouting. It fails where groundwater flows fast enough to carry heat in faster than the pipes remove it, so seepage velocity must be checked (pumping tests, Chapter 2.8) before freezing is chosen.

7.2.19.2 Properties of frozen ground

Frozen soil is a four-phase material: solids, ice, unfrozen water and air. Some water stays unfrozen well below 32°F, especially in clay and in salty pore water, and this unfrozen water explains why frozen-soil strength and stiffness depend so strongly on temperature. Artificial freezing runs much colder (−4°F to −256°F) than natural frost, and the ice lenses form parallel to the freeze pipes rather than to the ground surface.

Table 7.2-19. Rough short-term unconfined compressive strength of frozen ground at 14°F (−10°C) (after Hausmann 1990)
Materialqu (psi)qu (tsf)
Pure ice22016
Frozen sand1,450104
Frozen silt58042
Frozen clay29021
  • These values are a rough, conservative guide only. For comparison, a soft to medium clay has qu of about 7 psi (0.5 tsf).
  • Strength rises roughly with the logarithm of the temperature below freezing; at −40°F it may be about three times the value at 14°F.
  • The modulus of frozen soil is 10 to 100 times the unfrozen value. Tensile strength is one-half to one-sixth of compressive strength. A frozen granular soil has a friction angle of about two-thirds of its unfrozen value.
  • Frozen soil creeps. Design on the long-term strength (the lowest stress that leads to tertiary creep) or on an allowable strain over the time the wall must stand, not on short-term test strength.

7.2.19.3 Heave and thaw settlement

Water expands about 9% when it freezes. Saturated fine-grained soils under low confining stress can heave much more than that, because water migrates to the freezing front and builds ice lenses. When the ground thaws, the ice lenses melt and the soil consolidates, so settlement can follow. Thaw also returns the soil to, or below, its original strength: freezing is a temporary support, not a permanent improvement.

7.2.19.4 Freezing methods

Table 7.2-20. Brine and liquid nitrogen freezing compared (after Hausmann 1990)
Circulating brineLiquid nitrogen (LN2)
CoolantCalcium chloride brine in a closed loop; lowest theoretical temperature −67°FLiquid nitrogen vented to the air after passing through the pipes, or injected into porous soil; −321°F
Time to freezeDays to weeks, depending on soil, water content, brine temperature and pipe spacing (typically about 2 to 4.5 ft)Hours; suited to emergencies and active seepage
QuantityRefrigeration plant runs continuouslyAbout 1,000 to 3,200 lb of LN2 per yd³ of soil for initial freezing (about 1,350 lb/yd³ for preliminary estimates); the same quantity again maintains the frozen state for about 2 to 3 weeks
OtherLower cost for long jobs. A pipe leak releases brine that can thaw the frozen zone and contaminate groundwaterHigher frozen strength allows thinner walls and less ice-lens heave; requires closer control and monitoring; the gas is not toxic but displaces oxygen in confined spaces

Heat to remove. The latent heat of the pore water dominates: L = 144 γd w Btu/ft³ (Eq. 7.2-1), where γd is the dry unit weight (pcf), w the water content (decimal) and 144 Btu/lb the heat of fusion of water. A soil with γd = 100 pcf and w = 0.25 needs about 3,600 Btu/ft³ of latent heat alone, plus the sensible heat to cool it.

Freeze wall for a circular shaft. The simplest (elastic, Lamé) estimate of the thickness of a frozen ring around an opening of radius a under lateral earth and water pressure p0 is d = a [ (qu / (qu − 2 p0))0.5 − 1 ] (Eq. 7.2-2), with qu chosen for the design temperature, strain and duration. More advanced elastic-plastic and creep formulas exist; a specialty contractor normally designs the freeze.

Monitoring. Thermocouples or temperature probes in the frozen zone and on the coolant lines; survey and inclinometers for heave and creep movement. Ultrasonic measurements can sometimes confirm frozen thickness.

7.2.19.5 Heat treatment

Heating clay above about 750°F (400°C) causes permanent mineral changes: the clay loses lattice water, plasticity drops and strength and durability rise. Past methods used moving surface furnaces for roads and burners in boreholes to stabilize embankments and waste deposits; each borehole treated a zone about 3 ft in radius. Fuel use is high, about 10 to 20 gallons of fuel oil per cubic yard of soil, so the method is rarely economical today except where the ground already contains fuel or waste.

For railroad work: Freezing is most likely on a railroad project as support for a jacked, bored or mined crossing under the track through running sand or silt below the water table, or to cut off seepage in a deep excavation beside the track where dewatering would cause settlement (Section 7.1.17). The frozen zone heaves as it forms and settles as it thaws, and both move the track: keep the frozen zone below the track structure where possible, set track geometry and settlement monitoring with action levels and slow orders for both the freezing and the thaw periods, and plan for thaw consolidation after the crossing is complete. Brine leaks under the track can thaw the wall locally, so ask how leaks are detected and isolated. Confirm the groundwater velocity before relying on freezing, and coordinate with utilities in the right-of-way, which can be damaged by frost heave or act as heat sources.

Source: Hausmann (1990), Chapter 15. Full reference under Supplemental References.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

Supplemental references

  • Blacklock, J. R. and Lawson, C. H. (1977). Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection. FRA/ORD-77/30, Federal Railroad AdministrationFind source ↗Library entry
  • Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR)Find source ↗
  • Hayward Baker, Inc. Railroad Subgrade Stabilization (brochure)Find source ↗
  • National Lime Association (2004). Lime-Treated Soil Construction Manual: Lime Stabilization & Lime Modification, Bulletin 326Find source ↗
  • SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographsFind source ↗
  • SHRP2 R02 / GeoTechTools (2012). Rapid Impact Compaction and Jet Grouting fact sheetsFind source ↗
  • Schaefer, V. R. et al. (2017). Ground Modification Methods Reference Manual, Vol. I. Geotechnical Engineering Circular No. 13, FHWA-NHI-16-027Find source ↗
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §7.10, §12.6, §12.7, §12.8Find source ↗Library entry
  • Han, J., Zheng, G., Schaefer, V. R. and Huang, M. (eds.) (2009). Advances in Ground Improvement: Research to Practice in the United States and China. ASCE Geotechnical Special Publication 188Find source ↗

File locations for these documents are listed under Supplemental References.

Project management sources

  • Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & SonsFind source ↗
  • Bull, J. W. (ed.) (2015). Life Cycle Costing for the Analysis, Management and Maintenance of Civil Engineering Infrastructure. Dunbeath, Scotland: Whittles PublishingFind source ↗
  • Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group)Find source ↗
  • Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell ScienceFind source ↗
  • ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil EngineersFind source ↗
  • Sullivan, W. G., Wicks, E. M. and Koelling, C. P. (2015). Engineering Economy, 16th ed. Upper Saddle River, NJ: PearsonFind source ↗
  • Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-HillFind source ↗
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After UFC 4-860-01FA (2004)” draw on item S10 and are rewritten for railroad clients. Blocks marked “After Selig & Waters (1994)” summarize item S11 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S12 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Blacklock, J. R. and Lawson, C. H. (1977). Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection. FRA/ORD-77/30, Federal Railroad AdministrationFind source ↗Library entry
  2. Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR)Find source ↗
  3. Hayward Baker, Inc. Railroad Subgrade Stabilization (brochure)Find source ↗
  4. National Lime Association (2004). Lime-Treated Soil Construction Manual: Lime Stabilization & Lime Modification, Bulletin 326Find source ↗
  5. SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographsFind source ↗
  6. SHRP2 R02 / GeoTechTools (2012). Rapid Impact Compaction and Jet Grouting fact sheetsFind source ↗
  7. Schaefer, V. R. et al. (2017). Ground Modification Methods Reference Manual, Vol. I. Geotechnical Engineering Circular No. 13, FHWA-NHI-16-027Find source ↗
  8. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  9. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  10. U.S. Army Corps of Engineers, Naval Facilities Engineering Command and Air Force Civil Engineer Support Agency (2004). UFC 4-860-01FA, Railroad Design and Rehabilitation. Unified Facilities Criteria, 16 January 2004 (supersedes TI 850-02, 1 March 2000); approved for public release, distribution unlimited. Used on this page: ch. 6 (§8) and ch. 9 (§4)Find source ↗Library entry
  11. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 11 and 12Find source ↗Library entry
  12. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §7.10, §12.6, §12.7, §12.8Find source ↗Library entry
  13. Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons. Used on this page for project-management materialFind source ↗
  14. Bull, J. W. (ed.) (2015). Life Cycle Costing for the Analysis, Management and Maintenance of Civil Engineering Infrastructure. Dunbeath, Scotland: Whittles Publishing. Used on this page for project-management materialFind source ↗
  15. Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group). Used on this page for project-management materialFind source ↗
  16. Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science. Used on this page for project-management materialFind source ↗
  17. ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers. Used on this page for project-management materialFind source ↗
  18. Sullivan, W. G., Wicks, E. M. and Koelling, C. P. (2015). Engineering Economy, 16th ed. Upper Saddle River, NJ: Pearson. Used on this page for project-management materialFind source ↗
  19. Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill. Used on this page for project-management materialFind source ↗
  20. Han, J., Zheng, G., Schaefer, V. R. and Huang, M. (eds.) (2009). Advances in Ground Improvement: Research to Practice in the United States and China. Proceedings of the US–China Workshop on Ground Improvement Technologies, Orlando, Florida. ASCE Geotechnical Special Publication 188. Reston, VA: ASCE. Used on this page: Sections 7.2.2 to 7.2.8 and 7.2.18Find source ↗
  21. Hausmann, M. R. (1990). Engineering Principles of Ground Modification. New York: McGraw-Hill. Used on this page: Section 7.2.19Find source ↗
  22. Singh, K. and Hymavathi, J. (n.d.). Lecture Notes on Ground Improvement Techniques (A60127). Hyderabad: Institute of Aeronautical Engineering, Department of Civil Engineering. Used on this page: Sections 7.2.2, 7.2.6 and 7.2.7 (dynamic replacement, compensation grouting, lime columns)Find source ↗
  23. U.S. Office of Surface Mining Reclamation and Enforcement. 30 CFR 816.61–816.68, Use of Explosives (airblast limits 816.67(b); ground vibration limits, scaled distance and blasting-level chart 816.67(d)). Used on this page: Section 7.2.2Open source ↗

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 7.2.2-1 — Large crane and 14.0 Mg (30.9 kips) tamper for dynamic compaction. From Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  2. Photo 7.2.2-2 — 13.6 Mg (30.0 kips) tamper and crater formed during dynamic compaction. From Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  3. Photo 7.2.2-3 — Hammer and anvil portion of rapid impact compactor. Courtesy of Peter Becker. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  4. Photo 7.2.2-4 — Rapid impact compactor following first pass of compaction points. Courtesy of Peter Becker. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  5. Photo 7.2.2-5 — Rapid impact compactor in the process of compaction. Courtesy of Peter Becker. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  6. Photo 7.2.2-6 — Initial passes Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  7. Photo 7.2.2-7 — After 40 IR passes Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  8. Photo 7.2.2-8 — Broons (BH-1300) four-sided ("square") impact roller towed using a four-wheel drive heavy tractor. Photograph from http://www.broons.com/impact/ Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  9. Photo 7.2.2-9 — Impactor 2000 "square" impact roller. Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  10. Photo 7.2.2-10 — Landpac 25-kJ three-sided impact roller. Photograph from www.landpac.co.za, courtesy of Land Pac®. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  11. Photo 7.2.2-11 — Main elements of vibratory compaction equipment. After Massarsch and Fellenius (2005). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  12. Photo 7.2.2-12 — Range of soil types treated by vibrocompaction. Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  13. Photo 7.2.2-13 — Generic vibrocompaction process. Figure courtesy of FHWA, Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  14. Photo 7.2.2-14 — Probe-type vibrator being lowered into the ground. Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  15. Photo 7.2.2-15 — Vibroflotation (vibrocompaction) at Palm Island, Dubai. Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  16. Photo 7.2.3-1 — Placing the Anchor on the Drain. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  17. Photo 7.2.3-2 — Inserting the Mandrel into the Ground. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  18. Photo 7.2.3-3 — Inserting the Drain Core within the Jacket to Maintain Continuity. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  19. Photo 7.2.3-4 — Stapling the Drain Splice. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  20. Photo 7.2.3-5 — Schematic of a Generic PVD Installation for a Highway Embankment, showing the surcharge, drainage blanket, wick drains, and monitoring instrumentation (deep settlement points, settlement platform, groundwater observation well, inclinometer, and piezometers). (Figure from Elias et al. 2006) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  21. Photo 7.2.4-1 — Stone column construction by dry bottom feed process. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  22. Photo 7.2.4-2 — Load test on a stone column. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  23. Photo 7.2.4-3 — Construction of stone column by wet top feed method. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  24. Photo 7.2.4-4 — Stone column construction in soft soil. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  25. Photo 7.2.4-5 — Rammed aggregate pier construction. Photograph courtesy of GeoStructures, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  26. Photo 7.2.4-6 — Rammed aggregate pier tamper. Photograph courtesy of GeoStructures, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  27. Photo 7.2.4-7 — Pre-drilling of hole for rammed aggregate pier installation. Photograph courtesy of GeoStructures, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  28. Photo 7.2.5-1 — CSV installation adjacent to a sheet pile wall. From the files of Jim Collin. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  29. Photo 7.2.5-2 — Top view of the CSV auger and cement hopper. From the files of Jim Collin. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  30. Photo 7.2.5-3 — Deep mixing rig on levee project in New Orleans, LA. From Trevi Icos Corporation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  31. Photo 7.2.5-4 — Batch plant and deep mixing rig. From Trevi Icos Corporation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  32. Photo 7.2.5-5 — Close-up view of mixing. From Trevi Icos Corporation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  33. Photo 7.2.5-6 — Exposed top of deep mixing columns. From Fudo Construction. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  34. Photo 7.2.5-7 — Exposed sides of deep mixing columns. From George Filz (2010). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  35. Photo 7.2.6-1 — Jet grouting process schematic. Photograph courtesy of Hayward Baker, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  36. Photo 7.2.6-2 — Multiple jet grouting rigs. Photograph courtesy of Soilmec S.p.A. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  37. Photo 7.2.6-3 — Drilling to place grout pipes. Courtesy of Hayward Baker, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  38. Photo 7.2.6-4 — Example of improvement of soil under an existing structure. From Munfakh (1991). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  39. Photo 7.2.6-5 — Example of chemical grouting underpinning of a structure to allow excavation without settlement of the foundation. Courtesy of Hayward Baker, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  40. Photo 7.2.7-1 — Compaction of chemical stabilized soil. Photograph courtesy of Carmeuse Lime & Stone, from carmeusena.com. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  41. Photo 7.2.7-2 — Mixing of chemical stabilized soil. Photograph courtesy of Carmeuse Lime & Stone, from carmeusena.com. This same photograph is also used as the Fact Sheet document's cover image. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  42. Photo 7.2.16-1 — Overview of bio-treatment soil improvement systems, showing how biogeochemistry (the chemical reaction network and biological system) and soil habitat interact to alter mechanical properties, with process monitoring guiding up-scaling toward field application. (Adapted from DeJong et al. 2011.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  43. Photo 7.2.16-2 — Overview of possible bio-treatment soil improvement systems applied to a levee cross-section — including bio-reinforcement to prevent erosion, bio-mineralization to stabilize slopes and immobilize carbon, bio-film to prevent groundwater seepage, and bio-dechlorination of contaminants. (Jason DeJong, personal communication, 2012.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  44. Photo 7.2.16-3 — Light microscope photos of (a) untreated sand and (b) sand treated with an iron-based biocement. (Chu et al. 2011; with permission from ASCE.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗