3.8.44 Limitations

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.44 Limitations

The ratings are a structured way of applying engineering judgment; they do not replace it. The frequency bands are indicative, the trigger record at most sites is short, and the defect record depends on how consistently defects were reported. Ratings should be revisited after every significant triggering event, after stabilization, and whenever the traffic or exposure changes. Where the method and the engineer's judgment disagree, the engineer may raise the rating one level with a written reason (Section 3.8.22.6), and the disagreement should be reported so the method can be improved.

Table 3.8-92 lists the main limitations, what each does to a rating and how to manage it.

Table 3.8-92. Limitations of the rating method and how to manage them
LimitationEffect on the ratingWhat to do
The frequency bands are indicativeF is a level, not a measured probabilityWhere a number is needed (acceptable risk, life-cycle cost), use the probability methods of Sections 3.8.30 to 3.8.35 and state the exposure period
Trigger records at most sites are shortT may be set too high or too lowUse agency frequency analyses for rainfall and flow; log every event and recalibrate the thresholds (Section 3.8.26.6)
Defect reporting varies between territoriesD is biased low where defects were not recordedConfirm D in the field; score missing evidence 3 and flag it for the visit (Section 3.8.22.1)
F and S are ordered levels and R is their productR is not proportional to risk; equal scores can hide different sites (Cox 2008)Use R only to place a site in a rating; rank within a rating by F, then S (Table 3.8-77)
Sites are rated one at a timeSites that share a trigger fail together, so corridor risk is understatedApply the one-level raise for shared triggers; carry a corridor reserve for emergency repairs (Section 3.8.30)
Desk inputs are regionalA preliminary rating can miss a local seep, a buried culvert or old fillTreat desk ratings as preliminary; the field rating governs (Section 3.8.25)
Climate and land use changePast return periods can understate future triggersRate on current gauge and rainfall records, note any trend in the rationale, and revisit thresholds after unusual events
Live data feeds can failA missing indicator can look like a normal oneA service that does not respond is named on the site and left out, never read as normal; inspect when in doubt (Section 3.8.26.5)
A rating is not a stability analysisIt ranks risk but gives no factor of safety or designDesign from investigation and analysis (Chapter 6.3); the investigation level caps solution credit until then (Table 3.8-80)