3.8.12 Rainfall Thresholds and Weather-Based Operating Protocols

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.12 Rainfall Thresholds and Weather-Based Operating Protocols

Because rainfall is the dominant trigger, many railroads tie patrols, speed restrictions and special inspections to precipitation. FRA 49 CFR 213.239 requires special inspections of track after events such as floods and severe storms that may have damaged track structure. A threshold-based protocol makes that requirement predictable.

3.8.12.1 Intensity–Duration Thresholds

Empirical rainfall thresholds relate the average intensity I needed to trigger shallow landslides and debris flows to the storm duration D. The widely cited global lower-bound threshold of Caine (1980) is:

Figure 3.8-25. Slopes remain stable until rainfall intensity and duration pass a threshold.
Figure 3.8-25. Slopes remain stable until rainfall intensity and duration pass a threshold.

Equation 3.8-18: I = 0.58 × D−0.39

where I = rainfall intensity (in./hr) and D = duration (hr), valid for roughly 10 minutes to 10 days.

A global threshold is only a starting point. Thresholds should be calibrated for each territory from the railroad's own incident history and rain-gauge records. They should also account for antecedent moisture, since the same storm is far more damaging on saturated ground.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

3.8.12.2 Building a Protocol
  • Identify sites in the ground hazard inventory whose mechanism is rainfall-sensitive (Section 3.8.11).
  • Assign each a rain gauge or gridded precipitation source and a threshold (intensity, 24-hour and multi-day totals).
  • Define the response for each threshold level: heightened patrol, speed restriction, or hold trains until inspected.
  • Review each season's triggered responses and incidents, and adjust thresholds and site lists.

Declaring an extreme weather event and scaling the response

In the course’s Class I practice, the Regional Chief Engineer declares an extreme weather event for a defined subdivision and mile range. The declaration draws on weather-service forecasts and warnings and on reports from train crews and engineering forces, and is passed to Rail Traffic Control, the General Manager and the Regional Senior VP. Restrictions are decided jointly. They weigh the nature of the event, pre-existing ground conditions, topography and incident history, the quality of the weather information, the recency of patrols (a daylight inspection within four hours counts for more than a night inspection twelve hours old), train frequency, and wayside protection such as slide fences and high-water detectors.

Figure 3.8-26. Dry conditions vs. storm conditions with ponding at a blocked culvert.
Figure 3.8-26. Dry conditions vs. storm conditions with ponding at a blocked culvert.
  • Increased patrol frequency.
  • Patrols immediately ahead of each train.
  • Trains on lookout, prepared to stop within one-half the range of vision.
  • Daylight operations only.
  • No new trains into the territory; clear trains to safety.
  • Cessation of operations; move crews to safety.

The flash-flood trigger used across the Prairies and East is more than 1 in./h totaling over 3 in.; elsewhere, 2 in. in 1 h, 3 in. in 2 h, 4 in. in 4 h or 6 in. in 12 h. A double precipitation index plots short-term intensity against cumulative rainfall to define low-risk, speed-restriction and suspension zones. An antecedent rainfall index plots 2-day against 28-day totals over the history of past landslides at a station. In spring, bearing capacity can drop 30–50%.

Figure 3.8-27. Double precipitation index: hourly vs. continuous rainfall with low-risk, speed-restriction and suspension zones.
Figure 3.8-27. Double precipitation index: hourly vs. continuous rainfall with low-risk, speed-restriction and suspension zones.

After Geotechnology for Railroaders Program, Module 7.2, Module 7.1, Module 4; Module 7.2 §03–06; Module 7.1 §07. Full reference under Supplemental References.