3.8.39 Risk Reduction Ratings: Post-Stabilization Construction and Implementation

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.39 Risk Reduction Ratings: Post-Stabilization Construction and Implementation

A stabilized site is not yet a proven site. The post-stabilization rating is first provisional, and becomes the verified residual risk only when the works have been built as designed, have performed through a triggering event, and are being maintained.

Table 3.8-82. Post-stabilization frequency index and rationale
ConditionFpostRationale
Works complete and accepted on as-built quality assurance and quality control (Chapter 5.3), not yet tested by a triggerFdes + 1 (provisional)Construction quality and the ground model are not yet proven by performance.
Monitoring (survey, instruments, geometry records) shows no movement through at least one triggering season, or one event at or above the site's response levelFdes (verified)The works have been tested by the trigger they were built to resist.
Drainage-dependent works without a maintenance plan in forceFdes + 1 (remains provisional)Unmaintained drainage returns the site to its trigger.
Defects or indicators recur after stabilizationRecompute Fc from the new D (Section 3.8.19)The solution has not removed the cause; the site re-enters the current risk process.
Equation 3.8-16. Residual risk and risk reduction
Rres = Fpost × Spost; risk reduction = current rating − residual rating (in levels), and Rc − Rres (in score points)

Spost is the solution severity Ssol (Section 3.8.37.2). The works themselves rarely change it, since severity belongs to the site and its traffic. A reduction credited for detection linked to an operating response, or for a temporary measure, is kept only while that response is in force (Table 3.8-80); when it lapses, Spost returns to the current S.

The implementation stage also closes the loop with the live rating: after stabilization, the site keeps its trigger thresholds, recalibrated to the new works, and each triggering event is recorded so the verified rating rests on performance, not expectation.