A stabilized site is not yet a proven site. The post-stabilization rating is first provisional, and becomes the verified residual risk only when the works have been built as designed, have performed through a triggering event, and are being maintained.
| Condition | Fpost | Rationale |
|---|---|---|
| Works complete and accepted on as-built quality assurance and quality control (Chapter 5.3), not yet tested by a trigger | Fdes + 1 (provisional) | Construction quality and the ground model are not yet proven by performance. |
| Monitoring (survey, instruments, geometry records) shows no movement through at least one triggering season, or one event at or above the site's response level | Fdes (verified) | The works have been tested by the trigger they were built to resist. |
| Drainage-dependent works without a maintenance plan in force | Fdes + 1 (remains provisional) | Unmaintained drainage returns the site to its trigger. |
| Defects or indicators recur after stabilization | Recompute Fc from the new D (Section 3.8.19) | The solution has not removed the cause; the site re-enters the current risk process. |
Spost is the solution severity Ssol (Section 3.8.37.2). The works themselves rarely change it, since severity belongs to the site and its traffic. A reduction credited for detection linked to an operating response, or for a temporary measure, is kept only while that response is in force (Table 3.8-80); when it lapses, Spost returns to the current S.
The implementation stage also closes the loop with the live rating: after stabilization, the site keeps its trigger thresholds, recalibrated to the new works, and each triggering event is recorded so the verified rating rests on performance, not expectation.