Chapter 3.8 — Risk Ratings and Ground Hazard Risk Assessment

How ground hazard failures develop and what sets them off, then how to rate the risk now and how much each solution will reduce it: failure mechanisms and triggers, current risk, and risk reduction ratings.
Author: Daniel P. Colwell

This chapter sets out the method for rating ground hazard risk on a railroad and applies it to a single site. It starts from the triggering mechanism, which gives every rating its narrative, and determines the current risk from the geospatial risk and the defect rating. It then sets out the 1-to-5 scales, the risk score R = F × S and the risk matrix (Section 3.8.22), and applies them through the situational, instability, static and live ratings and the rated elements behind them. Each proposed solution is rated through three stages (the solution itself, design and construction, and post-stabilization implementation) so that the risk reduction is measured, not assumed. The chapter closes with the Ground Hazard Risk Assessment Report (Section 3.8.42), the worksheet that records the ratings for a site. Primary references: Chapter 1.1 risk framework; Chapter 3.8 failure mechanisms; Chapters 5.3, 7.1 and 7.2 stabilization methods.

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Reliability values that relate factor of safety to annual probability of failure. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

COV of factor of safety and annual failure probability (6 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
COV of factor of safetyEarth structures – Category IState-of-the-practice design, construction and operation; usually high consequence7.2%FGE T31.1, p.476
COV of factor of safetyEarth structures – Category IIStandard engineering practice; most ordinary facilities10.9%FGE T31.1, p.476
COV of factor of safetyEarth structures – Category IIINo site-specific design, substandard construction or operation; temporary or low consequence17.4%FGE T31.1, p.476
COV of factor of safetyEarth structures – Category IVLittle or no engineering31.6%FGE T31.1, p.476
Average annual failure probabilityHomogeneous / composite earth dams – Seepage erosion / pipingHistorical rate 2.19×10⁻⁴0.000237per yearFGE T6.2, p.108
Average annual failure probabilityHomogeneous / composite earth dams – OvertoppingHistorical rate 4.39×10⁻⁴0.000424per yearFGE T6.2, p.108
Open this set in the database ↗
References (1)
  1. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
Correlations (1)
EstimateCorrelationLimits / notesSource
Probability of failure from mean FS and its COVpf = P(FS < 1) ≈ Φ(−ln μFS / θ) (FS lognormal, θ = COV of FS small)Reproduces Silva et al. (2008) curves; θ ≈ 0.07–0.32 by structure categoryFGE text, p.475
All correlations ↗

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Typical Values: Failure Mechanisms and Triggers — from the GHRM Soil & Rock Properties Database

Values behind common track substructure failure mechanisms: fouling, subgrade plastic strain and why failures happen. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Where ballast fouling comes from (5 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Source of ballast fouling (share by weight)Ballast breakdownAverage of North American sites76%SELIG Fig. 8.33, p.8.25
Source of ballast fouling (share by weight)Infiltration from underlying granular layersAverage of North American sites13%SELIG Fig. 8.33, p.8.25
Source of ballast fouling (share by weight)Ballast surface (spillage, wind-blown)Average of North American sites7%SELIG Fig. 8.33, p.8.25
Source of ballast fouling (share by weight)Subgrade infiltrationAverage of North American sites3%SELIG Fig. 8.33, p.8.25
Source of ballast fouling (share by weight)Tie wearAverage of North American sites1%SELIG Fig. 8.33, p.8.25
Open this set in the database ↗
Subgrade cumulative plastic strain parameters (progressive shear and settlement) (12 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Cumulative plastic strain coefficient aFat clayCHLi & Selig (1996) model0.821.21.5–LI16 T4.7, p.174
Cumulative plastic strain exponent bFat clayCHLi & Selig (1996) model0.120.180.27–LI16 T4.7, p.174
Cumulative plastic strain exponent mFat clayCHLi & Selig (1996) model1.32.43.9–LI16 T4.7, p.174
Cumulative plastic strain coefficient aLean clayCLLi & Selig (1996) model0.31.13.5–LI16 T4.7, p.174
Cumulative plastic strain exponent bLean clayCLLi & Selig (1996) model0.080.160.34–LI16 T4.7, p.174
Cumulative plastic strain exponent mLean clayCLLi & Selig (1996) model122.6–LI16 T4.7, p.174
Cumulative plastic strain coefficient aElastic siltMHLi & Selig (1996) model0.84–LI16 T4.7, p.174
Cumulative plastic strain exponent bElastic siltMHLi & Selig (1996) model0.080.130.19–LI16 T4.7, p.174
Cumulative plastic strain exponent mElastic siltMHLi & Selig (1996) model1.324.2–LI16 T4.7, p.174
Cumulative plastic strain coefficient aSiltMLLi & Selig (1996) model0.64–LI16 T4.7, p.174
Cumulative plastic strain exponent bSiltMLLi & Selig (1996) model0.060.10.17–LI16 T4.7, p.174
Cumulative plastic strain exponent mSiltMLLi & Selig (1996) model1.41.72–LI16 T4.7, p.174
Open this set in the database ↗
Why geotechnical failures happen (4 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Primary cause of geotechnical failure (share of cases)Shortcomings in designISSMGE TC302 Task Force 10, ~100 case histories45%FGE text, p.278
Primary cause of geotechnical failure (share of cases)Inadequate site investigationISSMGE TC302 Task Force 10, ~100 case histories20%FGE text, p.278
Primary cause of geotechnical failure (share of cases)Unforeseen phenomena and occurrencesISSMGE TC302 Task Force 10, ~100 case histories20%FGE text, p.278
Primary cause of geotechnical failure (share of cases)Shortcomings in constructionISSMGE TC302 Task Force 10, ~100 case histories14%FGE text, p.274
Open this set in the database ↗
References (3)
  1. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
  2. LI16 – Li, D., Hyslip, J., Sussmann, T. & Chrismer, S. (2016). Railway Geotechnics. CRC Press / Taylor & Francis.
  3. SELIG – Selig, E.T. & Waters, J.M. (1994). Track Geotechnology and Substructure Management. Thomas Telford.
Correlations (2)
EstimateCorrelationLimits / notesSource
Fouling indexFI = P4 + P200 (percent passing No. 4 and No. 200 sieves)Selig & Waters (1994); categories clean < 1 … highly fouled > 40LI16 Eq. 3.1, p.84
Cumulative plastic strain of subgradeεp(%) = a (σd/σs)^m N^bσd = deviator stress, σs = soil compressive strength, N = load cycles; a, b, m by soil type in the databaseLI16 4.7, p.174
All correlations ↗

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

After a failure: see Forensic Investigation of Ground Failures (Chapter 17) for what to record, how to scope the investigation, back analysis and vibration claims.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
3.8.0 Purpose and Overview

A risk rating has to answer four questions in order: what will set this site off, how likely is failure now, how bad would it be, and how much will the proposed fix reduce the risk, and when. This chapter answers them in five steps. Each step uses the same 1-to-5 scales, in which risk increases with the number, and each ends on the same risk matrix (Table 3.8-16), so a rating means the same thing at every step.

Sections 3.8.1 to 3.8.17 describe how track-support and ground-hazard failures develop, the conditions that set them up and the events that set them off (formerly Chapter 2.2, Failure Mechanisms and Triggers). The ratings from Section 3.8.18 on build on them: the trigger narrative names the mechanism, and the defect and instability ratings record its symptoms.

1. Triggering mechanism
Narrative: what sets the site off, how often, and how close it is now
→
2. Current risk
Geospatial risk + defect rating → Fc; with S → current rating
→
3. Solution
Projected risk once the risk reduction measure works as intended
→
4. Design and construct
Credit the design earns; risk while it is built
→
5. Post-stabilization
Provisional, then verified residual risk
Table 3.8-1. The five steps of a ground hazard risk rating
StepQuestionRatings producedSection
1. Triggering mechanismWhat sets the site off, how often, and how close is it now?Trigger rating T; trigger narrative3.8.18
2. Current riskHow likely is failure now, and how bad would it be?Geospatial frequency Fg, defect rating D, current frequency Fc, severity S, current risk rating3.8.19 to 3.8.21
3. SolutionHow much will the measure reduce the risk if it works as intended?Solution rating (Fsol, Ssol)3.8.37
4. Design and constructHow much reduction does the design actually earn, and what is the risk while it is built?Design rating Fdes; construction-stage rating3.8.38
5. Post-stabilization implementationHas the work performed through a triggering event, and is it maintained?Provisional and verified residual rating3.8.39
Why the order matters. The trigger comes first because it decides which data matter, which defects are meaningful and which solutions can work. A solution that does not act on the trigger or on the susceptibility it exploits does not reduce the frequency of failure, whatever it costs.

The same five steps apply at the desk, on the live map and in the field; only the source of each rating changes. Every rating is recorded with a one-line reason for each level chosen (Section 3.8.43), and no rating includes client-confidential data. The elements behind each rating, and what places each one at 1, 2, 3, 4 or 5, are tabulated in Section 3.8.27.

3.8.0.1 How the Risk Assessment Sections Are Organized

Section 1.1.2 sets out the working equation for ground hazard risk, Risk = Hazard × (Consequence & Vulnerability), and Section 1.1.7 sorts risk scenarios into Unacceptable, Tolerable with Mitigation and Tolerable. Section 1.1.8 explains why a railroad with hundreds or thousands of tracked sites needs standard tools that turn records and field observations into comparable scores. This chapter is that tool for a single embankment, cut or drainage site. Every site is rated on the same scales, so sites can be compared, ranked and funded on a consistent basis.

A site usually enters the program by one of four routes: a recurring track geometry defect (cross level, profile, alignment or warp exceptions reported at the same location), a visible ground hazard (a bulge, tension crack, seepage, erosion, or a blocked or damaged culvert reported by patrol or the public), a slow order placed because the track can no longer be held at normal speed, or network screening, in which the railroad ranks its segments by hazard exposure and studies the highest first. Whatever the route, the railroad needs the same three answers: how serious the site is now, what will fix it, and what the fix will cost.

The chapter answers those questions in six steps. Each step produces a rating, or part of one, on the same five-level scales, and each step hands its result to the next.

3.8.22 RatingsThe scales: frequency index F, hazard severity S, risk score R = F × S and the five risk ratings.
3.8.23 SituationalWhat the location and its inherent conditions make possible: soils, geology, slope, water, drainage, and what is exposed.
3.8.24 InstabilityWhat the site has already shown: past failures, recurring defects, and the indicators seen in the field.
3.8.25 StaticThe rating under usual conditions: network exposure (FRA CHI) and the preliminary site rating.
3.8.26 LiveThe rating during a weather or river event, raised while live data exceed the site’s thresholds.
3.8.42 ReportThe field form, pre-filled with the desktop metrics and completed by the engineer on site.

The rating is assigned twice for each site. A preliminary rating is made at the desk from the situational and instability attributes before anyone goes on track (Sections 3.8.23 to 3.8.25). The field rating is made by the engineer in charge (EIC) at the site on the Ground Hazard Risk Assessment Report (Section 3.8.42), which carries the preliminary values with it so each one can be confirmed or changed. Between visits, the live rating (Section 3.8.26) watches for the weather and river conditions that change the risk from day to day.

These sections sit in Section 3.0, Risk Management, before investigation planning in Chapter 3.9. Sections 3.8.18 to 3.8.21 and 3.8.37 to 3.8.39 set out the overall rating method (triggering mechanisms as the narrative, current risk as geospatial risk plus defect rating, and risk reduction ratings for each solution through design, construction and post-stabilization implementation); the sections described here apply it at a single site. It draws on the risk framework of Chapter 1.1, the failure mechanisms of Chapter 3.8 and the stabilization methods of Chapters 5.3, 7.1 and 7.2 to reach a recommendation. The reasoning behind every scale, level and rating is collected in Section 3.8.36, so the working sections can stay short. The probability and statistics behind the frequency bands, from return periods and event counts to small data sets and acceptable probability of failure, are grouped in Sections 3.8.30 to 3.8.35. The chapter closes with the field report, the record of the rationale, the limitations and the cross-references (Sections 3.8.42 to 3.8.47).

3.8.0.2 Failure Mechanisms and Triggers: Summary

Chapter 1.1 classifies railway ground hazards by what they are: landslide, hydraulic erosion and subsidence. This chapter explains how they happen. For each family of hazard it describes the physical failure mechanism, the conditions that make a site susceptible, and the triggers that turn susceptibility into an event.

The distinction is practical. Mitigation that addresses only the trigger (for example, a rain-based slow order) manages exposure but leaves the hazard in place. Mitigation that addresses the mechanism (drainage, buttressing, subgrade replacement) reduces the hazard itself. Correctly diagnosing the mechanism is therefore the step that controls whether repair money solves the problem or only treats the symptom. Chapter 1.1 makes this point about "muddy track": identical surface symptoms can come from quite different root causes.

Key outputs: a mechanism–condition–trigger framework (Section 3.8.1); mechanism tables for track substructure, embankments and slopes, hydraulic, subsidence and seismic hazards (Sections 3.8.2–3.8.6); the winter-to-spring frost geohazards of cold regions, with spring break-up hydraulic hazards (Section 3.8.7) and frost heave, thaw weakening and silt liquefaction (Section 3.8.8), contributed by Mario Ruel; a trigger inventory (Section 3.8.11); the use of rainfall thresholds in weather-based operating protocols (Section 3.8.12); a symptom-to-mechanism diagnostic table (Section 3.8.13); and monitoring indicators (Section 3.8.14).

Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
RK-12Rockfall Hazard Rating System scoringRHRS score
LS-08Rainfall intensity–duration threshold (Caine)I
LS-01Reach angle (Fahrböschung) vs. volume — rock avalanchesH/L
LS-03Debris-flow travel distanceL
LS-06Debris-flow velocity from superelevationv
LS-09Rainfall intensity–duration threshold (global update)I
LS-10Newmark sliding displacement (regression)Dₙ
RK-06Slope Mass RatingSMR
RK-11Rockfall shadow angleβ (shadow)
3.8.1 Mechanism, Condition and Trigger

Ground failures rarely have a single cause. It is useful to separate three groups of factors:

FactorDefinitionRailroad ExamplesCan the Railroad Change It?
Predisposing conditionsInherent site characteristics that make failure possibleSoft or sensitive clay, steep slope, fouled ballast over plastic clay, soluble bedrock, loose saturated sandOnly by engineering works (improvement, regrading, replacement)
Preparatory (progressive) factorsProcesses that reduce the margin of safety over timeBallast fouling, subgrade softening, toe erosion, weathering, rising tonnage, culvert corrosion, creepYes — through maintenance, drainage and inspection
TriggersThe event that tips a marginal site into failureIntense or prolonged rainfall, snowmelt, flood, rapid drawdown, earthquake, toe excavation, blocked culvertRarely — but exposure can be managed (slow orders, patrols, warning systems)
Factor of Safety vs. Probability of Failure
Factor of Safety vs. Probability of Failure

The factor of safety concept from Chapter 1.1 ties these together. Predisposing conditions set the starting factor of safety, preparatory factors erode it, and the trigger is whatever finally pushes it below 1.0. A site with a large margin survives the same storm that fails a marginal site next to it. This is why a risk program targets sites whose margin is being eroded, not just sites that have already failed.

Project management · Bissonette (2016)

Cause–Risk–Effect Statements (Risk Metalanguage)

Bissonette separates three things that risk registers often blur. A cause is a fact or existing condition. A risk is an uncertain event that may or may not happen. An effect is the possible impact on one or more project objectives (schedule, cost, scope or quality). To keep them apart he uses a fixed sentence form, or risk metalanguage:

As a result of <CAUSE>, <RISK> may occur, which will lead to <EFFECT>.

The short version for a register title is “<RISK> due to <CAUSE>.” One of his examples reads: “As a result of more than expected test failures, more design/build/test cycles may occur, which will lead to schedule delays and added project costs.” Its register title is “More design/build/test cycles due to more than expected test failures.” Writing every risk this way shows which part can be measured or controlled, whether the cause or the event. It also indicates which objective the impact rating should refer to. The same form keeps a known condition, which is a fact to design for, from being logged as though it were uncertain.

For railroad work: The metalanguage lines up with this chapter’s condition–mechanism–trigger framework. The cause is the condition plus the trigger, the risk is the mechanism being activated, and the effect is the consequence to track or to the project. For example: “As a result of a high-plasticity clay subgrade with a clogged ditch line (condition) and sustained wet-season rainfall (trigger), progressive shear and heave of the subgrade may occur (mechanism), which will lead to repeated surfacing, a slow order and possible mud-pumping derailment risk (effect).” The register title becomes “Subgrade shear failure due to saturated CH subgrade and blocked drainage.” Writing hazard and project risks in this form makes plain which field observation would confirm the cause and which treatment targets the trigger. It also makes the risk register consistent with the diagnostic tables in this chapter.

How Rainfall Becomes Floods
How Rainfall Becomes Floods

Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 2.1, “Causes Versus Risks” (unpaginated e-book; PDF pp. 38–40). Summarized and paraphrased. Full reference under Supplemental References.

3.8.2 Track Substructure Failure Mechanisms

These mechanisms act within the ballast, subballast and subgrade (Chapter 2.3) and the upper part of the embankment (Chapter 2.1). They account for most of what track patrols encounter day to day: the "subsidence" category of Chapter 1.1.

MechanismWhat HappensSusceptible ConditionsField IndicatorsSee
Ballast degradation and foulingParticle breakage and abrasion, plus infiltration of fines, fill voids and reduce drainage and strengthWeak or soft aggregate, heavy tonnage, tamping cycles, wind-blown or spilled finesFouled shoulders, reduced voids, geometry loss after surfacingChapter 2.3, Section 2.3.7
Subgrade attrition and mud pumpingWater plus cyclic loading at the ballast–subgrade contact produces a slurry that is pumped into the ballastPlastic fine-grained subgrade, no or inadequate subballast, poor drainageMud at tie ends and in cribs, "white spots" on shoulders, rapid surface defectsChapter 2.3, Section 2.3.5
Progressive shear failureRepeated stress near the subgrade strength remolds the soil and squeezes it laterally beneath the tiesSoft, wet fine-grained subgrade; thin granular layerHeave of the ballast shoulder or ditch side ("subgrade squeeze"), ties hanging, recurring cross-level defectsChapter 2.3, Section 2.3.5
Excessive cumulative plastic deformationGradual accumulation of permanent strain under millions of load cycles forms ballast pockets and troughsFine-grained subgrade with moderate strength; heavy axle loadsBallast pockets in trench sections; gradual long-wave settlementChapter 2.3, Section 2.3.5
Consolidation settlementVolume decrease of saturated clay and organic soil under sustained loadSoft clay or peat foundations; new fill, raises or a second trackLong-wave settlement, often continuing for years after constructionChapter 6.2
Frost heave and thaw weakeningIce lens growth heaves track in winter; excess water on thaw softens the subgradeFrost-susceptible silts and silty clays, available water, freezing climateSeasonal differential heave, spring pumping and soft spotsChapter 2.3, Section 2.3.5; Chapter 7.3
Swell and shrinkageMoisture change in expansive clay causes volume changeHigh-plasticity clay, clay shale in cuts, seasonal wetting and dryingSeasonal geometry cycling, shoulder cracking in dry periodsChapters 2.1, 2.2
Cyclic softening ("subgrade dynamic liquefaction")Pore pressure buildup under repeated loading in saturated low-plasticity silt causes loss of strengthSaturated silts, poor drainageSudden loss of support in wet periods, mud boilsChapters 1.1, 6.5
Foundation Failure
Foundation Failure
Foundation Failure — Excessive Settlement
Foundation Failure — Excessive Settlement
Dynamic Soil and Liquefaction
Dynamic Soil and Liquefaction

Reading the substructure through maintenance demand

Profillidis uses a maintenance coefficient k = I / Im, where I is the annual number of maintenance sessions on a section and Im the average for track of the same age, UIC group and axle load. k = 1 is average; k = 0.5 is good; on poor subgrade k can reach 10. Maintenance hours rise steeply with k and with years since renewal (Figure 3.8-1). He uses k to judge whether the track bed is adequately sized:

Figure 3.8-1. Manual maintenance hours H per km and annual number of maintenance sessions I vs. years since renewal, for maintenance coefficients k = 0.3 to 10 (UIC groups 1–3). Profillidis Fig. 9.6.
Figure 3.8-1. Manual maintenance hours H per km and annual number of maintenance sessions I vs. years since renewal, for maintenance coefficients k = 0.3 to 10 (UIC groups 1–3). Profillidis Fig. 9.6.
Table 3.8-2. Assessment of track-bed sizing from the maintenance coefficient k
kAssessment
k < 1Correct dimensioning
1 < k < 2.5Track-bed structures slightly under-dimensioned
2.5 < k < 5Track-bed structures under-dimensioned; poor functioning of drainage
k > 5Renewal and strengthening of track-bed structures necessary

When I passes a threshold, geometry can no longer be held by surfacing alone and the remedy is to reduce k, mainly by thickening the track bed. Applied with Dormon’s rule, subgrade stress also depends on maintenance: traffic between sessions scales with T/k, so tracks with different k values load the subgrade differently. For a ground-hazard program the practical point is that a segment needing repeated spot surfacing (high k) is evidence of a substructure mechanism, and that evidence lives in maintenance records.

After Profillidis (2014), §9.9, Table 9.5, Fig. 9.6. Full reference under Supplemental References.

Ballast or subgrade: which one sets the maintenance cycle?

Short-term versus long-term settlement. On most track, ballast causes most of the settlement between surfacings, both average and differential. This is the short-term component. The subgrade adds a long-term component that builds slowly over decades of traffic. Ballast governs only when three conditions hold:

  • A filter or separation layer is present.
  • The subgrade is strong enough.
  • Surface drainage is good.

If any of these is missing, the subgrade dictates the maintenance cycle.

Why track subgrade fails by creep, not by sudden collapse. Train loading on the subgrade does not reverse the direction of shear stress. Under that kind of loading, pore pressure rises to a limit and failure comes as permanent strain accumulating at an increasing rate. Cyclic strain stays small. Two factors make it worse:

  • Static shear stress, such as beneath an embankment shoulder or slope, magnifies the plastic strain caused by traffic.
  • Subgrade saturation changes with the seasons, so the same section can perform differently in spring and in autumn.

After Selig & Waters (1994), chs. 3, 4 and 8. Full reference under Supplemental References.

3.8.3 Embankment and Slope Failure Mechanisms

Classify slope movements by material (rock, debris, earth) and movement type (fall, topple, slide, spread, flow), following Cruden and Varnes (1996) as adopted in Chapter 1.1. The mechanism determines the analysis method (Chapter 6.3) and the likely warning time.

MechanismTypical Railroad SettingWarning SignsWarning Time
Rotational slide (slump)Embankments and cuts in clay; river-bank fillsCrest cracks parallel to track, back-tilted blocks, bulging toeDays to months; often progressive
Translational slideFill over sloping bedrock or weak planar layer; colluviumTension cracks upslope, displaced ditch, leaning polesHours to weeks
Earthflow and retrogressive slideSensitive and quick clays in river valleysOften little; small initial slide at the bankMinutes to hours once started
Lateral spreadSensitive clay or liquefiable layers near free facesGround cracking, bulging toward channelRapid
Debris flowSteep channels above track; source areas often out of sightAccumulated debris in upper channel, burn scars, intense rainMinutes; can reach track 1–2 miles from source (Chapter 1.1)
Rockfall and toppleRock cuts and natural rock facesFresh debris in ditch, open joints, freeze-thaw season activitySeconds
CreepClay slopes and colluviumCurved tree trunks, slow drift of track alignment and structuresYears; may accelerate to sliding
Shallow sloughing and surface erosionSteep, unvegetated fill slopesRills and gullies, slumped surface layerStorm-dependent
Embankment spreading or foundation squeezeEmbankment on soft foundationToe heave, lateral displacement, crest settlementWeeks to months
Figure 3.8-2. Rotational and translational slides, block slide, rockfall, topple, debris flow, debris avalanche, earthflow, creep and lateral spread.
Figure 3.8-2. Rotational and translational slides, block slide, rockfall, topple, debris flow, debris avalanche, earthflow, creep and lateral spread.

Mass-movement types and internal-erosion collapse

Mass movements are classified by rate against water content, from extremely slow dry creep through earthflows and rotational or translational slides to extremely rapid rockfalls, debris flows and debris avalanches in saturated ground. An earthflow has a characteristic hourglass shape. Creep is spotted by its effects: curved trunks, bent fences and tilted poles.

Figure 3.8-3. Mass-movement classification: rate of movement vs. water content.
Figure 3.8-3. Mass-movement classification: rate of movement vs. water content.

Embankment collapse by internal erosion (rated Severe) is the hidden mode. Water moves through the fill or overflows through buried rock drains, carrying soil out and leaving voids until the surface collapses. In one case a culvert roof failed about 45 ft inside the fill and produced a sink hole up to 70 ft deep. In another, a 6.5-ft multi-plate culvert with a rusted-out invert let water erode beneath it, causing outlet and toe scour, an over-steepened slope, head-scarp cracks, 14 in. of mainline settlement and 2 in. of lateral deflection.

Figure 3.8-4. Montmagny, mile 115.53: settlement from a culvert collapse.
Figure 3.8-4. Montmagny, mile 115.53: settlement from a culvert collapse.
Figure 3.8-5. Sink hole over a failed culvert (illustrative risk rating: Severe).
Figure 3.8-5. Sink hole over a failed culvert (illustrative risk rating: Severe).
Figure 3.8-6. A sink hole forming under the track from internal erosion.
Figure 3.8-6. A sink hole forming under the track from internal erosion.

After Geotechnology for Railroaders Program, Module 5; §05, §09, §14. Full reference under Supplemental References.

Case study: 3.8.45.1 Slope failures whose consequences left the site (Look 2023), in §4.18 Case Studies.

3.8.4 Hydraulic Failure Mechanisms

Chapter 1.1 splits hydraulic erosion into surface-flow and seepage mechanisms. They fail differently and call for different controls.

3.8.4.1 Surface-Flow Mechanisms
  • Scour at bridge piers and abutments: local scour around obstructions, contraction scour where the channel is narrowed, and long-term degradation of the bed. Evaluate per FHWA HEC-18 (Chapter 2.8, Section 2.8.5.4).
  • Bank and toe erosion where the alignment parallels a river, lake or coast. This removes toe support and leads to slope failure (Section 3.8.3).
  • Overtopping and washout when a culvert or bridge opening is exceeded or blocked. Water flowing over the embankment erodes the downstream face and can remove the fill entirely.
  • Beaver dam failure releasing stored water as a surge, a recognized washout cause in wooded territory (Chapter 1.1).
Figure 3.8-7. Bank erosion, scour, debris jam, degradation and avulsion at a single crossing (BGC).
Figure 3.8-7. Bank erosion, scour, debris jam, degradation and avulsion at a single crossing (BGC).
Figure 3.8-8. Partial culvert obstruction by beaver debris.
Figure 3.8-8. Partial culvert obstruction by beaver debris.
Figure 3.8-9. After the dynamited-dam failure: more than 300 ft of bank removed.
Figure 3.8-9. After the dynamited-dam failure: more than 300 ft of bank removed.
3.8.4.2 Seepage (Internal) Mechanisms
  • Piping and internal erosion where water flows through or beneath an embankment with enough gradient to move particles. This is especially common along the outside of culvert barrels and through fills ponded on one side.
  • Seepage forces and uplift reducing effective stress in slopes and at the toe.
  • Rapid drawdown when flood water recedes faster than pore pressure in the embankment can dissipate, leaving the saturated slope without the stabilizing water load on its face.
Figure 3.8-10. A trestle span that did not survive the flood.
Figure 3.8-10. A trestle span that did not survive the flood.
Figure 3.8-11. Seepage under the track creating internal voids.
Figure 3.8-11. Seepage under the track creating internal voids.

Underestimated peak flows

Undersized drainage is a hydraulic mechanism in its own right. Profillidis gives the U.S. Soil Conservation Service method based on Fuller’s formula for the peak flow from a catchment of A mi² for a return period of T years:

Qmax = Q1 · (1 + 0.8 log T) · (1 + 2.00 / A0.3),   with Q1 = 136 · A0.8 (ft³/s)

His worked values: A = 3.86 mi², T = 10 years gives Q1 ≈ 400 and Qmax ≈ 1,680 ft³/s; A = 5.79 mi², T = 20 years gives ≈ 555 and 2,470 ft³/s. He cautions that such semi-empirical formulas must be checked against measured data. On the TGV Méditerranée, observed extreme runoff was about twice the top of the predicted range ( Chapter 2.1, Section 2.1.5.2 ). He argues that increasing rainfall intensity calls for return periods far longer than the traditional 50–100 years, up to 1,000 years, with the probable maximum flood as the reference event.

After Profillidis (2014), §9.14.2–9.14.3, Eq. 9.11. Full reference under Supplemental References.

Scour: why it is invisible from the hi-rail

Local scour forms horseshoe and wake vortices around piers and abutments; contraction scour deepens the channel through a constricted opening. Both can undermine a foundation well below the water surface. Away from bridges, any bend near the track is scour-critical: the outer radius scours while the inner radius deposits. Banks migrate as the stream undercuts and collapses them. Attack migration before it passes a 2:1 intercept slope with the track, because cost rises steeply with delay, and get engineering help, since riprap alone may not be enough.

Figure 3.8-12. Horseshoe and wake vortices carving a scour hole around a pier.
Figure 3.8-12. Horseshoe and wake vortices carving a scour hole around a pier.
Figure 3.8-13. Bank migration toward the railroad.
Figure 3.8-13. Bank migration toward the railroad.

Signals stay green when track is undermined by side scour or washed out. Peak flow can arrive after the rain stops, and a long moderate storm can do more damage than a short intense one. Get off the hi-rail and walk the bank at scour-critical locations. AREMA countermeasures (after FHWA) are riprap at piers and abutments, guide banks, spurs and revetments, with riprap always placed from the toe upward.

Figure 3.8-14. A trestle left hanging after the approach embankment washed out.
Figure 3.8-14. A trestle left hanging after the approach embankment washed out.

After Geotechnology for Railroaders Program, Module 6.3; §02–05. Full reference under Supplemental References.

Differential head, beaver dams and rapid drawdown

When the water level on one side of an embankment exceeds the other by more than about 6 ft, flow is forced beneath the track. Within days, depending on the fill, wet spots appear at the downhill toe. Dirty or milky seepage and sand fans at the outlet mean soil is being carried out and cavities are forming. In spring, a culvert plugged with ice is the most frequent cause.

Figure 3.8-15. High differential water level driving seepage beneath the track.
Figure 3.8-15. High differential water level driving seepage beneath the track.

Beaver dams in culverts and ditches cause about 80% of beaver trouble but less than 10% of the risk. Dams far uphill, sometimes 100 ft or more above the track and outside railway property, are about 20% of problems but carry the highest risk. The 1992 Nakina derailment, in which two employees were killed, followed a rapid drawdown of a lake after a dam failure and led to the formal Beaver Activity Hazard Assessment (BAHA) program. The program rates watersheds and dams 1–5 and combines them into a global score:

Figure 3.8-16. An uphill dam about 100 ft above the track: the highest-risk configuration.
Figure 3.8-16. An uphill dam about 100 ft above the track: the highest-risk configuration.
Figure 3.8-17. Nakina, 1992: the sudden drop in lake level undermining the embankment under the train.
Figure 3.8-17. Nakina, 1992: the sudden drop in lake level undermining the embankment under the train.
Table 3.8-3. BAHA global risk matrix (watershed rating × worst dam rating, with additional severe dams)
WatershedDam 1Dam 2Dam 3Dam 4Dam 5+1 severe+2 severe+3 severe
100000000
200012468
3002615304661
40282664128192256
5052580195391586781

Never use explosives on a beaver dam or culvert plug. In one case a dynamited dam overloaded a 3-ft culvert and more than 300 ft of a 60-ft-high embankment failed, with the water travelling through old permeable fill from a buried timber bridge. After any high water is drawn down, the embankment is least stable for about 12–24 hours, while the confining water is gone but the fill is still saturated and seepage reverses. Beaver ponds are protected fish habitat under the Canadian Fisheries Act; permits are required, and penalties can reach $1,000,000 and imprisonment for individuals.

After Geotechnology for Railroaders Program, Module 6.5, Module 7.1, Module 4; Module 6.5 §02–06; Module 7.1 §04, §06. Full reference under Supplemental References.

3.8.5 Subsidence and Collapse Mechanisms

Chapter 1.1 separates progressive settlement from sudden collapse. The mechanisms below produce sudden collapse. They are the most dangerous for train operations because warning time is short.

MechanismProcessWhere to Expect It
Karst sinkholesSoil ravels into solution cavities in limestone, dolomite or gypsum until the overlying arch collapses (cover-collapse) or sags (cover-subsidence)Karst regions; often triggered by water-table changes or concentrated drainage
Mine subsidenceCollapse of underground workings producing troughs (sag) or pitsAbandoned coal and mineral mining districts
HydrocollapseLow-density, dry soils lose their bonding and compress when first wettedLoess and some arid-region alluvium; triggered by new drainage or leaks
Culvert and pipe failureBackfill lost through corroded or separated barrels leaves voids that collapseAging metal culverts; clay tile and masonry drains
Decay of buried timberRotting of buried trestles and cribbing leaves voids in the fillFills built over or around former timber structures
Leaking utilitiesWater and sewer leaks wash fines into the pipe or away along the trenchUtility crossings (Chapter 2.1, Section 2.1.9)
Burrowing animalsBurrows provide seepage paths and voids in embankmentsEmbankments near water; flood-control levee analogs
3.8.6 Seismic Mechanisms

Earthquakes act as triggers for several of the mechanisms above, and they also introduce mechanisms of their own: liquefaction of loose saturated granular soils, lateral spreading toward free faces, cyclic softening of soft clays, and seismically induced slope failures and rockfall. Evaluate these using Chapter 6.5. After a felt earthquake, the railroad's earthquake notification protocol (Chapter 1.1, Section 1.1.8) sets the inspection radius and speed restrictions.

Seismic train-protection thresholds

Profillidis treats earthquakes in two parts: designing structures, track and subgrade for the regional design acceleration (up to about 0.3 g in his text), and protecting trains during an event. For the second, accelerometer sensors in protected housings along the line report to an alarm center:

  • measured acceleration above 0.066 g (2.1 ft/s²): stop traffic immediately;
  • between 1.3 and 2.1 ft/s² (≈ 0.04–0.066 g): reduce permitted speeds;
  • an alarm is issued when three consecutive sensors report within 5 seconds;
  • reliability target: no more than one false alarm in 30 years.

These values describe one European system and can be compared with client post-earthquake inspection protocols (Chapter 6.5).

After Profillidis (2014), §9.17. Full reference under Supplemental References.

What earthquakes have done to track

More than 1,500 seismic events are recorded in Canada each year, with a significant one every two to five years. Energy travels farther through dense eastern Precambrian rock. The 1935 Temiskaming M6.2 earthquake caused an embankment failure more than 220 mi from the epicenter. The 1988 Saguenay M5.9 event temporarily liquefied a muskeg zone and triggered nine slope failures; derailments were avoided only because the track was closed. In a 2010 event, straight rail was left kinked into S-curves, buckled at ties and disturbed at culverts, damage not visible from a moving train. Post-event inspection must cover track and roadbed, drainage, culverts, retaining walls, tunnels, overpasses, bridges and approaches, adjacent buildings, fiber and utilities, and signals. Response criteria are in Chapter 6.5.

Figure 3.8-18. Track buckled into an S-curve by a 2010 earthquake.
Figure 3.8-18. Track buckled into an S-curve by a 2010 earthquake.
Figure 3.8-19. A kink in the rail at a culvert crossing.
Figure 3.8-19. A kink in the rail at a culvert crossing.
Figure 3.8-20. A slope failure in a muskeg zone, of the type triggered at Saguenay in 1988.
Figure 3.8-20. A slope failure in a muskeg zone, of the type triggered at Saguenay in 1988.

After Geotechnology for Railroaders Program, Module 7.3; §02, §05–06. Full reference under Supplemental References.

3.8.7 Spring Break-Up: Hydraulic Geohazards

Sections 3.8.7 and 3.8.8 are adapted from Ruel (2026b), Railway Frost Geohazards: Winter to Spring Break-Up, Frost Heave and Soft Subgrade, Chapter 2.8 of the Railway Ground Hazard Research Program (RGHRP) Canadian Railway Geohazard Manual (forthcoming). The figures are from that chapter, with the credits shown on each. Units are given in English, with the original metric values in brackets. All references are listed under References.

In cold regions, the winter-to-spring transition is the most hazardous period of the year for track stability. Seasonal frost hazards fall into the hydraulic and subsidence categories of Chapter 1.1 (Keegan 2007; Keegan n.d.). This section covers the hydraulic group, where meltwater moves around and through the embankment. Section 3.8.8 covers the frost group, where water freezes and thaws inside the track foundation. Both groups have the same root cause, water that cannot drain, and the same first remedy, drainage.

3.8.7.1 Why Spring Is the High-Risk Season

Spring break-up concentrates a large share of the year’s track-bed damage, slope failures and weather-related incidents into a few weeks, because four unfavorable conditions arrive together:

  1. Abundant water. Melting snow releases large volumes of water toward and away from the track. The threat is highest when a sudden warm spell coincides with heavy late-winter rain.
  2. Blocked drainage. Culverts and ditches are often still plugged with ice, snow and the previous fall’s debris, so water cannot pass under or along the track as designed.
  3. Weakest subgrade. The thawing subgrade is at its lowest strength of the year (Section 3.8.8.3).
  4. Fast runoff over frozen ground. Frozen soil is far less permeable than thawed soil, so meltwater and rain run off instead of soaking in, overwhelm surface drainage, and collect in the thawed upper layer above the frozen base, saturating and weakening the track foundation.

Canadian railways manage this period with a spring readiness (or spring preparedness) plan, traditionally running from about March 1 to May 15 depending on the region (Ruel 2026a). As climate patterns shift, these activities increasingly need to start earlier. The period usually coincides with the spring load-restriction periods that provincial and northern state transportation agencies impose on highways.

The plan follows the same risk-management cycle used for all ground hazards year-round (CSA 1997; CSA 2022; ISO 2018), repeated through the transition season (Figure 3.8.7-1):

Figure 3.8.7-1. The spring hazard risk-management cycle.
Figure 3.8.7-1. The spring hazard risk-management cycle: list the hazards, assess the risk, control it, then act, document and prepare for the next inspection. Source: Ruel (2026b), Figure 1.9-1.
  1. List the hazards. Start from known problem locations, look for new ones, and judge how likely each is. This builds a hazard registry that grows every year.
  2. Assess. Combine the likelihood of each hazard with its consequences, considering how vulnerable the track and its traffic are to repeated seasonal water and frost.
  3. Control. Put proactive mitigation on high-risk zones, with action and contingency plans for the most vulnerable locations.
  4. Act and document. Clear blocked drainage, run special patrols or protect traffic during combined rain and snowmelt events, reinforce embankments that show distress, record what was done, and update the registry for the next inspection round.
3.8.7.2 The Top Ten Spring Hazards

Field experience reduces spring threats to ten recurring conditions. Table 3.8.7-1 lists them with what to look for, and the job aid in Figure 3.8.7-2 (Section 3.8.7.8) puts them on one page for crews.

Figure 3.8.7-2. Spring inspection job aid.
Figure 3.8.7-2. Proposed job aid showing the most common spring hazards to check and the warning signs of bank instability. Source: Ruel (2026b), Figure 1.9-24.
Table 3.8.7-1. The top ten spring hazards to watch for along the track (after Ruel 2026b, Table 1.9-1)
#Spring hazardWhat to look for
1FloodingRising water level near the right-of-way.
2Differential water headA large difference in water level from one side of the track to the other, for example 3 to 7 ft. Check for seepage near the toe of the downstream slope and water flowing through the fill, which may be causing internal erosion.
3Rapid drawdownAn abrupt drop in water level next to the roadbed, which can trigger slope failure. Look for fresh high-water marks.
4Ponding from blocked drainageFlow held back by snow, ice, beaver dams, debris or poor ditches. Check for water entering the fill at the inlet and seeping or flowing out of the fill at the outlet.
5Frozen culvertsIce plugs, especially at outlets. Check in winter and early spring, before snowmelt and heavy rain.
6Blocked culverts and ditches on adjacent roadsBlocked drainage on road infrastructure uphill or downstream can cause flooding, washouts and rapid drawdown at the railway embankment.
7Water flowing through the ballastWater over and through the ballast and subgrade can erode and undermine track support.
8Hydraulic erosion from watercoursesErosion along rivers, fast creeks and ditches, and at culvert inlets and outlets.
9Ice and debris jams at bridgesIce and debris piled against piers can push piers and spans and cause flooding upstream.
10Signs of slope instabilityTension cracks along the shoulder or slope; small sinkholes below the ties; very soft track and new cross-level defects; a bulging toe; leaning trees; seepage on the lower slope; fans of sand or silt at seepage points.
Figure 3.8.7-3. Early signs of instability caused by a high differential water level.
Figure 3.8.7-3. Early signs of instability caused by a high differential water level: tension cracks along the shoulder, new seepage zones and sinkholes. Source: Ruel (2026b), Figure 1.9-4.
3.8.7.3 Blocked Culverts, Differential Head and Seepage

Blocked culverts are the root problem. Nearly every spring hydraulic hazard starts with water that cannot drain along, away from or through the embankment. An inlet can look clear while an ice plug has formed at the outlet. During snowmelt and heavy rain, that plug holds back a large volume of water and a rising level on the upstream side. The most valuable preventive action is to inspect and clear the critical culverts before the melt: those with a history of icing or flooding and those on sidehills. Most of this cannot be judged from the track. Get off the hi-rail, walk the shoulder, and look down the bank at the inlet and outlet for blockage, ponding at the inlet, and water seeping through the embankment instead of through the culvert.

Differential water head. With the culvert blocked, water rises on the upstream side while the downstream side stays low. The difference in level is a driving force, not a nuisance: a difference of about 7 ft can be enough to cause instability, and the larger the difference, the greater the pressure pushing water through and under the fill. If the water reaches the crest it overtops the track and can wash it out suddenly (gully erosion), but conditions can be dangerous well before that (Figure 3.8.7-4).

Figure 3.8.7-4. Normal dry embankment and the hazardous condition created by a plugged culvert.
Figure 3.8.7-4. (A) Normal dry embankment. (B) Hazardous condition created by a plugged culvert: a high differential water level drives seepage through the fill, causing internal erosion and possibly a landslide or washout. Source: Ruel (2026b), Figure 1.9-2.

Seepage through the embankment. Under a differential head, water seeps through the fill from the high side to the low side. It raises the pore pressure in the fill and reduces its effective strength. Seepage emerging on the downstream slope or at the toe is a critical warning sign. If the water carries soil particles, internal erosion is under way and voids are forming beneath the roadbed (Figure 3.8.7-5; Section 3.8.4.2).

Figure 3.8.7-5. Dangerous seepage through an embankment driven by a high differential head, with an ice-plugged culvert outlet.
Figure 3.8.7-5. Dangerous seepage through a railway embankment driven by a high differential water head, with an ice-plugged culvert outlet (inset). Source: Ruel (2026b), Figure 1.9-3.
3.8.7.4 Reading the Embankment: Signs of Instability

Field personnel must be able to read the embankment for signs that high water and seepage are undermining it. Many of these signs cannot be seen from a hi-rail vehicle, so walk the ground, carefully, on both sides.

Table 3.8.7-2. Warning signs of embankment instability from differential water (after Ruel 2026b, Figures 1.9-4 and 1.9-5)
StageSignsResponse
EarlySmall tension cracks along the shoulder or slope crest; small sinkholes in the ballast or shoulder; new seepage zones; new cross-level defects at the track surface.Report; drain the pond by clearing the culvert, or pump; mark the cracks and start monitoring.
DevelopingA bulging toe, or cracks anywhere on the slope.Treat as a slope failure in progress; protect traffic and drain urgently.
Imminent failureWider and deeper tension cracks; larger sinkholes under the ballast; fans of sand at seepage outlets; a larger toe bulge pushing over and tilting trees.Stop trains until the site is inspected and made safe. Several signs together mean the fill is approaching failure.
Figure 3.8.7-6. Advanced signs of imminent embankment failure.
Figure 3.8.7-6. Advanced signs of imminent embankment failure. Source: Ruel (2026b), Figure 1.9-5.

A high differential head should not be tolerated along the track. Where any sign in Table 3.8.7-2 is present, draining the pond, by clearing the culvert or pumping, is urgent.

Photographs and monitoring. Take photographs wide enough to show the track and the surrounding ground for scale (Figure 3.8.7-7). Judging a crack’s width by eye is not enough and can mislead; measure it from paint marks across the crack or from lines of survey lath, so that acceleration can be seen.

Figure 3.8.7-7. A proper field photograph of an unstable slope, with paint marks and stakes for monitoring.
Figure 3.8.7-7. A proper field photograph of an unstable slope: tension cracks shown against the track, the adjacent river and the topography. Paint marks and stakes are simple ways to track the slide. Source: Ruel (2026b), Figure 1.9-6.

Safety. Inspect the side slopes from a stable location beyond the limits of the unstable zone, walking down near the base of the fill from more stable ground. Never inspect directly on an actively sliding slope or at its toe.

3.8.7.5 Rapid Drawdown

Rapid drawdown (RDD) is one of the least intuitive and most dangerous spring conditions. Once the water is drained, the embankment looks safer. Conditions do improve on the downstream side, but they get much worse on the upstream side.

RDD occurs when an external water body that was buttressing the slope (a flooded ditch, a backed-up culvert or a beaver pond) drains faster than the saturated fill can. The water’s support is removed while high pore pressures stay trapped in the fill. Effective strength drops, seepage forces push the slope downhill, and the factor of safety can fall below 1.0 (Figure 3.8.7-8). The slide can come 24 to 48 hours after the water has visibly receded, with the track still looking undisturbed.

Figure 3.8.7-8. Sequence of rapid-drawdown conditions.
Figure 3.8.7-8. Rapid drawdown, from the initial differential water level, through peak risk once the pond is drained, to the bank back in its normal drained condition. Source: Ruel (2026b), Figure 1.9-7.

Common triggers are the sudden clearing of an ice plug at a culvert outlet, the breach of a beaver dam at an inlet, and a fast drop in an adjacent creek. Because the slope may show no distress at the moment of peak risk, keep any embankment that was partly or fully submerged under active observation for at least 24 to 48 hours after the water level drops.

Case history: Nakina, Ontario, 1992. A small lake on the downhill side of the track had been there since before the railway was built. During a heavy rainstorm in July 1992, a very old beaver dam that could not be seen from the track ruptured and the lake dropped by more than 7 ft. The embankment failed by rapid drawdown and an approaching train derailed (TSB 1992; Figure 3.8.7-9). It was the first derailment attributed to RDD, and the lessons were shared across railways and transportation agencies to raise awareness of drawdown and of beaver dams along corridors.

Figure 3.8.7-9. The Nakina rapid-drawdown derailment.
Figure 3.8.7-9. Rapid-drawdown failure at Nakina, Ontario: the sudden draining of a beaver-dammed lake removed the supporting water pressure and triggered a catastrophic embankment failure (TSB 1992). Source: Ruel (2026b), Figure 1.9-8.
3.8.7.6 Internal Erosion at Culverts

A differential head moves fine soil out of the embankment by internal erosion (piping). It is most common along the outside of a blocked, damaged or corroded culvert, through a defect in the fill, or through an old overflowing “blind” stone drain. Over time it hollows out large cavities while the surface looks intact.

Figure 3.8.7-10. Erosion and undermining around a stone box culvert after a flood.
Figure 3.8.7-10. Erosion and undermining around a stone box culvert after a flood about 7 ft above the top of the culvert. Source: Ruel (2026b), Figure 1.9-11.
  • First signs. Small surface holes (“turtle holes”) above vertical chimneys that migrate upward from a deeper cavity, and deposits of silt nearby. Treat a hole about 12 in. across beside the track as a possible sign of a much larger cavity, especially if a new track surface defect has also appeared.
  • Over culverts. Inspect the barrel for open joints or holes at the crown or near the invert. Dry sand can run into a crown opening and be carried away by the flow (Figure 3.8.7-12), or water can start to flow outside the barrel and accelerate the erosion. A fan of sand or debris at the outlet is a clue.
  • Sudden collapse. A cavity above a culvert is held up temporarily by arching and apparent cohesion. If it collapses, the embankment can fail suddenly. While the track is frozen it can bridge over voids; when the frost comes out, it may drop.
  • Response. Find the source of the erosion. Backfill a surface hole by pushing granular material down with a lining bar, using geosynthetics if available. Repair the culvert, fill the cavity from its base, and inject from the surface where needed (Figure 3.8.7-11).
Figure 3.8.7-11. Development of an internal cavity from sand eroding into a culvert hole.
Figure 3.8.7-11. Embankment section showing a dangerous internal cavity formed by sand eroding into a hole in a culvert. Source: Ruel (2026b), Figure 1.9-9.
Figure 3.8.7-12. Open joints in a culvert causing internal erosion and sinkholes.
Figure 3.8.7-12. Open joints in a culvert (top) causing internal erosion of the bank and sinkholes on the embankment and beneath the track (bottom right). Source: Ruel (2026b), Figure 1.9-10.
3.8.7.7 Other Spring Hazards
Table 3.8.7-3. Other spring hazards and controls (after Ruel 2026b, Section 1.9.5)
HazardMechanismControl
Snow and ice in culverts and ditches (Figures 3.8.7-17 and 3.8.7-13)Snow and ice reduce drainage capacity during high spring flows.Clear snow and ice from the most sensitive ditches and culvert openings, starting with locations that have flooded before. Keep a drainage hazard registry so the culverts likely to ice up and the ditches to clear are known in advance.
River hydraulic erosion (Figure 3.8.7-18)Spring brings the highest and fastest flows of the year, especially along meanders.Walk the bank and beneath bridges; erosion is not visible from the hi-rail. Use helicopter or drone photographs every spring in high-hazard areas.
River ice break-up (débâcle; Figures 3.8.7-19 and 3.8.7-14)Break-up is sudden and short at each reach. Moving ice can lift bridge spans, damage the roadbed, dislodge large riprap and push piers founded on rock; ice has piled up to 33 ft behind piers and displaced piers 3 to 7 ft.Know when and where break-up will occur, and protect traffic while the ice is running, if necessary by stopping operations until it has passed.
Debris against bridges (Figure 3.8.7-20)Trees and debris, sometimes mixed with ice or released by a beaver dam outburst, jam against piers, restrict flow, and cause upstream flooding, bed scour and bank erosion.Watch the river when crossing bridges; report obstructions to the bridge engineer at once, as conditions can worsen quickly.
Ice fall and rockfall (Figures 3.8.7-21 and 3.8.7-15)Thick ice walls on high rock cuts can drop large sheets onto the track during the melt. More frequent freeze-thaw cycles increase spring rockfall.Inspect ice walls for early signs of release; report new rockfall or ice fall (Section 3.8.3).
Ice in tunnels (Figures 3.8.7-22 and 3.8.7-16)Water leaking into tunnels forms crown stalactites that intrude on vertical clearance; ice on the walls that narrows horizontal clearance; and ice that builds up over the rail from side-wall or invert seepage, which can let wheels climb the rail. In spring, with repeated freeze-thaw, ice can cover the rail head in a single day. Falling ice injures workers.Keep tunnels with icing on the hazard registry with a spring action plan to keep ice off the rail. Remove icicles with mechanical equipment, not hand tools (Bunce, forthcoming).
Figure 3.8.7-13. Clearing snow and ice at a culvert inlet.
Figure 3.8.7-13. Clearing snow and ice at a problem culvert inlet to restore capacity for the spring peak and allow the inlet to be inspected. Source: Ruel (2026b), Figure 1.9-13.
Figure 3.8.7-14. Ice piled behind bridge piers.
Figure 3.8.7-14. Ice break-up piled up to 33 ft high behind several piers; two piers were displaced 3 to 7 ft laterally. Source: Ruel (2026b), Figure 1.9-16.
Figure 3.8.7-15. Track damage from an ice wall collapse.
Figure 3.8.7-15. Damage along the track from an ice wall collapse. Source: Ruel (2026b), Figure 1.9-19.
Figure 3.8.7-16. Sources of ice build-up over the rail in tunnels.
Figure 3.8.7-16. Ice in tunnels: (A) ice building up below a stalactite; (B) ice over the track from side-wall icing and seepage; (C) ice over the rail from upward seepage freezing at the invert. Source: Ruel (2026b), Figure 1.9-21.
Figure 3.8.7-17. Small culverts plugged by ice and ditches full of snow and ice.
Figure 3.8.7-17. Small culverts plugged by ice, and sensitive ditches full of snow and ice. Source: Ruel (2026b), Figure 1.9-12.
Figure 3.8.7-18. River erosion during spring along the Matapédia River.
Figure 3.8.7-18. Spring river erosion along the Matapédia River, photographed from the shoreline. Source: Ruel (2026b), Figure 1.9-14.
Figure 3.8.7-19. Ice break-up displacing steel bridges and damaging the roadbed.
Figure 3.8.7-19. Ice break-up that displaced steel bridges and damaged the roadbed and track embankments. Source: Ruel (2026b), Figure 1.9-15.
Figure 3.8.7-20. Trees and debris jammed against bridge piles.
Figure 3.8.7-20. Trees and debris jammed against bridge piles. Obstructions from trees, ice and beaver dam outbursts must be reported to the bridge engineer. Source: Ruel (2026b), Figure 1.9-17.
Figure 3.8.7-21. Thick ice wall on a steep rock cut.
Figure 3.8.7-21. A thick ice wall on a steep rock cut, which can fall onto the track during the thaw. Source: Ruel (2026b), Figure 1.9-18.
Figure 3.8.7-22. Ice stalactites in an unlined rock tunnel.
Figure 3.8.7-22. Typical ice stalactites in an unlined rock tunnel. Source: Ruel (2026b), Figure 1.9-20.
3.8.7.8 Spring Weather Monitoring, Decisions and Inspection

Weather monitoring. On warm spring days snow melts quickly, very quickly when rain falls on it, and the frozen ground sends almost all of it to runoff. During the thaw, check forecasts and official advisories every day for flash flood warnings, heavy rain warnings, snowmelt runoff forecasts and combined rain-plus-snowmelt forecasts. In spring, the water expected from snowmelt must be added to the rain forecast; a map that combines the two is the most useful single product for rail operations (Figure 3.8.7-23). This extends the rainfall protocols of Section 3.8.12 to the thaw season.

Figure 3.8.7-23. Idealized spring weather warning map of snowmelt plus rain.
Figure 3.8.7-23. Idealized spring weather warning report on a railway map: forecast snowmelt water, expected rainfall, and their sum, the most critical information for rail operations. Source: Ruel (2026b), Figure 1.9-22.

Table 3.8.7-4 gives a four-level alert system as an example for eastern Canada. Thresholds differ by region and should be set from local experience. Where the combined water exceeds the Red level, consult the weather service provider and a local hydrologist to define how far and how long the operating controls should extend.

Table 3.8.7-4. Suggested combined snowmelt-plus-rainfall alert thresholds and actions, eastern Canada example (after Ruel 2026b, Table 1.9-2)
Alert levelCombined snowmelt + rainfallRequired action
Yellow1 to 2 in.No mandatory action; extra patrols at the track supervisor’s discretion.
Orange2 to 3 in.Extra patrols in areas of known concern for flooding, washouts and slope instability.
Red3 to 4 in.Mandatory special patrols of all high-hazard locations before train movements; consider slow orders and 24-hour watch.
BlackMore than 4 in.Stop trains at high-risk locations until inspected and cleared.

For a site monitored with the live risk rating of Section 3.8.26.3, add the forecast snowmelt to the 24-hour rainfall during the thaw, and set the thaw indicator of Table 3.8-31 from the alert level: combined water at the Orange level counts as Watch, and at the Red or Black level as Warning. Rain falling on melting snow is Warning at any amount, and so is any thaw at a site that has failed in a thaw before.

Risk-based decisions. When a roadbed hazard is found, field personnel must assess it quickly and decide how to control the risk. Risk is the product of likelihood and consequence: a condition unlikely to fail with minor consequences is low risk, and a condition likely to fail at a vulnerable, high-consequence location is high risk (Figure 3.8.7-24; Chapter 1.1; CSA 2022; Macciotta, forthcoming). A rapid spring assessment considers:

Figure 3.8.7-24. Typical risk assessment chart.
Figure 3.8.7-24. Typical risk assessment chart, consistent with CSA Q850, CMREA (CSA R114) and ISO 31000. Source: Ruel (2026b), Figure 1.9-23.
  • Site history: whether the hazard has occurred here before, how fast conditions are worsening, and whether anything has changed since the last inspection.
  • Weather: current and forecast rain and snowmelt.
  • Field observations: blocked drainage, differential water level, seepage through the embankment, tension cracks and bulges.

In the terms of this chapter, the field observations are the field indicator elements D5 to D14 (Tables 3.8-46 and 3.8-47), the weather is the live condition of Section 3.8.26, and the consequence is the hazard severity S (Table 3.8-15). Read the rating from the risk matrix (Table 3.8-16) and apply the required response of Table 3.8-17: at High, a slow order or increased inspection; at Severe, on-site protection and operating restrictions before the next train.

Where there is no imminent danger, assess and protect track geometry to standards and add controls as warranted: a watchman, extra patrols or electronic warning devices. Where failure is imminent, or where field personnel are unsure whether a train can pass safely, suspend operations and notify the rail traffic controller and the engineering supervisor immediately. When in doubt about stability, stop the train.

Spring inspection essentials. A focused spring inspection looks specifically for unusually high water near the track, differential head, seepage below the track, signs of slope instability, drawdown potential, and culverts or ditches plugged with snow and ice. Where slope movement is suspected, mark tension cracks with stakes or paint and monitor them for widening. The guiding sequence is see the water, respect the warning signs, and act early: restore drainage before the head builds, and impose a speed restriction before a crack widens. Proactive work is cheaper and safer than responding to a failure. The job aid in Figure 3.8.7-2 supports these inspections.

3.8.8 Frost Heave, Thaw Weakening and Silt Liquefaction

This section moves from water flowing around and through the embankment to water freezing inside it. Frost hazards belong to the subsidence category of Chapter 1.1 (Keegan 2007). Unlike slope and hydraulic hazards, they start within the soil mass, driven by temperature gradients and the freezing and thawing of pore water. Frost heave and thaw softening from freeze-thaw cycles degrade track geometry, change the vertical force at the wheel-rail interface, and can affect operating safety (Roghani 2021; Roghani, Caldwell et al. 2021; Roghani, Liu and Burgess 2021). In early spring they bring frequent tamping and surfacing and temporary slow orders.

These hazards are deceptive. They develop slowly over weeks, out of sight, and then appear as differential track lift, soft track, cross-level defects or shoulder failures. Because the mechanisms are not intuitive, the warning signs are easy to misread and remedies often treat the symptom rather than the cause. Source material: Ruel (2026b), Part II; see also Selig and Waters (1994), Li et al. (2016) and Ruel (2024).

3.8.8.1 The Three Conditions for Frost Heave

Differential frost heave is the uneven upward movement of the ground surface caused by ice lenses forming and growing in freezing soil. Water expands about 9% when it freezes; where that expansion is uniform along the track it does little harm. Heave becomes a problem when the ground does not freeze uniformly.

Damaging heave needs three conditions at once (Figure 3.8.8-1):

Figure 3.8.8-1. The three conditions required for damaging frost heave.
Figure 3.8.8-1. The three conditions required for damaging frost heave below the track. Removing any one prevents ice lenses from forming. Source: Ruel (2026b), Figure 1.9-25.
  1. Frost-susceptible soil, typically silt (Chapter 2.2, Section 2.2.7);
  2. A supply of water; and
  3. Freezing temperatures with a slowly advancing freezing front.

Remove any one and damaging lenses are unlikely to form. Every remedy in Section 3.8.8.6 works by removing one of the three.

Ice lenses. As the freezing front moves down, freezing creates suction that draws water up from the unfrozen soil and the water table. The water freezes at the front as discrete lenses that grow and push the soil apart, heaving the surface. As the front goes deeper, successive lenses form and the heave accumulates (Figure 3.8.8-2).

Figure 3.8.8-2. Ice-lens formation in silt.
Figure 3.8.8-2. Ice-lens formation: suction at the advancing freezing front draws water up through silt to feed growing lenses, heaving the surface. Source: Ruel (2026b), Figure 1.9-26.

Why silt. Frost susceptibility depends on the balance between capillarity and permeability. Silt pores are small enough to produce strong capillary suction yet large enough to move water quickly to the freezing front; water can rise 3 to 7 ft above the water table in silt by capillarity alone. Clean sand has pores too large to sustain much capillary rise. Clay has strong capillarity but is too impermeable to feed lenses fast enough.

3.8.8.2 Differential Heave in the Field

Subgrade conditions change quickly along a line, and silt and water are rarely uniform, so heave is not uniform either. Severe heave concentrates in short spots, often only 13 to 33 ft long, where enough silt and water coincide. The track is lifted more in some places than others, producing a rough surface and abrupt changes in elevation at the transitions (Figures 3.8.8-3 and 3.8.8-6).

Figure 3.8.8-3. Frost heave bumps on wood and concrete ties.
Figure 3.8.8-3. Typical frost heave bumps on wood-tie and concrete-tie track. Source: Ruel (2026b), Figure 1.9-27.
  • Culverts. Cold air moving through the barrel drives frost deeper around the structure, and the surrounding backfill is often disturbed, fine-grained and poorly drained. Severe heave spots above culverts usually affect both rails, and although lenses grow over weeks, a heave can surge within a few days in late winter once a threshold is reached (Figure 3.8.8-4).
  • Fouled ballast. A heave spot on a high, free-draining sandy embankment far above the water table usually points to old, fouled ballast. Over decades, ballast breaks down to silt-size particles, and a buried pocket of fouled ballast behaves like frost-susceptible silt (Section 3.8.2; Ruel 2024). Heave can also come from a silty subballast or from water trapped in the upper embankment.
  • Climate trend. Warmer, drier winters with more frequent freeze-thaw cycles are becoming normal in seasonally frozen regions. Shorter freezing periods may limit frost depth, but more frequent intermittent cycles are expected to increase track roughness from repeated differential heave and softening (Roghani 2021). Owners who do not plan for this shift face higher maintenance costs and possible exceedance of track geometry limits.
Figure 3.8.8-4. Frost heave over a culvert.
Figure 3.8.8-4. Frost heave over a culvert: deeper and faster frost penetration around the culvert produces more swelling and a greater chance of ice lenses in wet, silty ground. Source: Ruel (2026b), Figure 1.9-29.
3.8.8.3 Spring Thaw and Bearing Capacity

The thaw is the most dangerous period of the year for track-bed bearing capacity and surface defects (Figure 3.8.8-5):

Figure 3.8.8-5. Variation of track-bed bearing capacity through the year.
Figure 3.8.8-5. Variation of track-bed bearing capacity through the year: (a) winter peak in frozen ground; (b) spring-thaw drop below the required level; (c) summer recovery when well drained. Source: Ruel (2026b), Figure 1.9-30.
  • Winter. Frozen ground is very strong; capacity peaks well above what train loads require.
  • Spring thaw. The ground thaws from the top down while the base stays frozen and impermeable. Meltwater cannot drain through the frozen base, so the thawed layer saturates and softens. Roadbed bearing capacity can be 50 to 75% lower than in summer, often below what passing trains require, and most permanent track-bed deformation happens in this short window. Its timing varies with latitude and from year to year with the freezing index and frost depth.
  • Late spring and summer. When the frost leaves the ground, drainage returns and capacity recovers. A well-drained foundation then carries traffic with routine maintenance.

Highway agencies apply the same principle through spring load-restriction periods. The hazard depends on where the thaw front is relative to the remaining frost, so monitoring both is valuable. The worst heave occurs at maximum frost depth, around the start of surface melt; the worst bearing capacity occurs after moderate thaw, when a soft saturated layer sits on a still-frozen base. Conditions return to normal only when the thaw front reaches the bottom of the frost and the trapped water can drain. Because the loss is predictable and seasonal, it can be managed administratively by reducing axle loads or speeds over vulnerable sections until the subgrade recovers.

Figure 3.8.8-6. Seasonal progression of frost heave.
Figure 3.8.8-6. Seasonal progression of frost heave: (a) mid-winter; (b) end of winter, at the deepest frost; (c) early spring, a shallow thaw producing differential heave. Source: Ruel (2026b), Figure 1.9-28.
3.8.8.4 Silt Liquefaction over Frozen Ground

Silt liquefaction is the most severe form of the spring loss of bearing capacity. The top of a soft, wet silt layer thaws over hard, still-frozen ground. Heavy, vibrating trains cycle load onto the saturated silt while the frozen base prevents drainage. Pore pressure builds with each load cycle until the silt loses its strength and liquefies. The silt-water mixture is squeezed up and out at the embankment shoulder, leaving voids beneath the track (Figure 3.8.8-7).

Figure 3.8.8-7A. Section through a spring bearing-capacity failure by silt liquefaction.
Figure 3.8.8-7A. Spring bearing-capacity failure by silt liquefaction: soft thawed silt over the frozen base liquefies under dynamic train loading and is pushed up, leaving voids under the track and a silt boil on the shoulder (inset). Source: Ruel (2026b), Figure 1.9-31A.

Signs.

  • A cross-level defect that appears under a passing train; in one case history, about 3 in. (Figure 3.8.8-8).
  • A bulging shoulder, with liquefied silt emerging from it.
  • Silt boils: fans of pale, saturated silt flowed up to the surface, at the shoulder several feet from the track or between the ties (Figures 3.8.8-8 and 3.8.8-9).
  • A lining bar pushed into ballast that looks sound meets almost no resistance.
Figure 3.8.8-8. A silt boil at the shoulder during spring thaw.
Figure 3.8.8-8. A silt boil at the shoulder during spring thaw; the liquefied silt caused a 3 in. cross-level defect. Source: Ruel (2026b), Figure 1.9-32.
Figure 3.8.8-9. More silt boils below the track and shoulders.
Figure 3.8.8-9. More examples of silt boils below the track and at the shoulders. Source: Ruel (2026b), Figure 1.9-33.

Silt liquefaction causes differential settlement, a weakened subgrade and shoulder, and hidden voids, and it is a recognized cause of spring derailments. It resolves on its own once the frost is fully out and the trapped water drains, so the danger is confined to the thaw window, but within that window it is acute.

Frost depth controls it. Liquefaction occurs when the thaw front reaches the top of the silt while the silt below is still frozen, which is possible only when frost has penetrated deep into the silt (Figure 3.8.8-10). If the silt did not freeze deeply, it drains and keeps its strength. Evaluate frost depth at locations with a history of silt boils: after a mild winter the risk is low; after a cold winter, inspectors must watch closely for early signs in the spring.

Figure 3.8.8-10. Time sequence of frost bump and silt boil formation.
Figure 3.8.8-10. Time sequence through winter and spring: frost bump formation, then possible silt boils when frost is deep in soft silty soil. Source: Ruel (2026b), Figure 1.9-34.
3.8.8.5 Other Frost Heave Problems
  • Grade crossings, where drainage is often poor and frost can go deeper.
  • Frost jacking of piles. Deep frost can grow ice lenses along some piles but not others, pushing them up and lifting the structure (Figure 3.8.8-11). This has happened with wood piles and steel H-piles. After the thaw the piles settle back but usually remain higher than before. Insulation on the ground around the piles reduces frost penetration; for end-bearing or high-capacity friction piles, a shallow excavation around the pile backfilled with a low-friction material can also work.
Figure 3.8.8-11. Frost jacking of a wood bridge in northern Quebec.
Figure 3.8.8-11. Frost jacking of a wood bridge in northern Quebec. Source: Ruel (2026b), Figure 1.9-35.
3.8.8.6 Remedial Measures: Order of Priority

Because frost heave needs silt, water and freezing, every remedy removes one of them. Table 3.8.8-1 lists the measures in broad order of value, starting with drainage.

Table 3.8.8-1. Frost heave and thaw-weakening remedies in order of priority (after Ruel 2026b, Section 1.9.14)
PriorityMeasureCondition removedKey points
1Drainage and subdrainageWaterThe first line of defense and the most cost-effective. Poorly maintained ditches cause roughly three-quarters of frost heave problems, and poor ballast or subballast drainage most of the rest. Clear ditches and daylight the ballast at the shoulder; where water is trapped below the surface, install subdrains (Figure 3.8.8-12).
2Marking and saltingFreezingThe most practical treatment for recurring heave spots; reduces differential heave by about 70% for two to three years.
3ShimmingNone (compensates)The most common spring response; smooths the surface without disturbing frozen ballast.
4Excavate and replace silty soilSoilReplace only 50 to 60% of the frost depth, with flat transitions.
5InsulationFreezingAttenuates heave to match the adjacent track; tapered ends are essential.
6Injection or soil treatmentSoilCement or chemical mixing, or cement or urethane injection from the surface.
Figure 3.8.8-12. Subdrainage techniques along the track.
Figure 3.8.8-12. Subdrainage to lower the groundwater table: lateral subdrains along the track, or cross-drain trenches perpendicular to it. Source: Ruel (2026b), Figure 1.9-36.

Drainage, subdrainage and cross-drains for silt liquefaction

To stabilize a silt-liquefaction zone, relieve the water pressure at the silt-frost interface while containing the silt. The proven technique is a lateral trench drain that also acts as a reinforcing shear key (Figure 3.8.8-13):

Figure 3.8.8-13. Stabilizing a silt-liquefaction zone with a lateral trench drain.
Figure 3.8.8-13. Stabilizing a silt-liquefaction zone with a lateral trench drain and geotextile, which relieves pore pressure at the frost interface and reinforces the track as a shear key. Source: Ruel (2026b), Figure 1.9-37.
  1. Excavate the trench at the point of bulging silt, down to the soft layer at the frost front, to drain the water pocket.
  2. Place a non-woven geotextile against the silt to pass water and retain the silt.
  3. Backfill with free-draining stone compacted in lifts of about 1 ft.
  4. Wrap the geotextile over the trench about 2 ft below the base of rail, and top off with ballast.
  5. Space trenches across the weak zone every 15 to 20 ft along the affected length, working from the track center or the tie ends as the site allows. Use a vacuum truck where buried cables are present.
Figure 3.8.8-7B. Trench below the track shoulder showing the silt layer.
Figure 3.8.8-7B. Trench below the track shoulder showing the silt layer. Source: Ruel (2026b), Figure 1.9-31B.

In an emergency, even clean crushed rock without geotextile improves conditions by draining water faster, although silt will slowly migrate into the voids.

Marking and salting

Salt lowers the freezing point of the soil moisture, slowing the freezing front and limiting ice lenses (Figure 3.8.8-14).

Figure 3.8.8-14. Sequence of salt treatment for a frost heave bump.
Figure 3.8.8-14. Sequence of salt treatment to control a frost heave bump. Source: Ruel (2026b), Figure 1.9-38.
  • Mark in spring. Mark active heave spots directly on the ties while they are obvious, and record them in the ground hazard registry. Standard handheld GPS is not accurate enough to relocate them.
  • Treat in mid-fall. Apply salt or an equivalent brine several weeks before freezing begins. About 3 to 4 in. of rain is needed afterward to carry it through the ballast into the subgrade. Applied too early, it washes out before freezing; too late, it does not penetrate and is lost in the spring runoff.
  • Benefit. One correctly timed treatment commonly cuts differential heave by about 70% for two to three years, at a fraction of the cost of raising and releveling the track.
  • Cautions. Misapplication can make heave worse. Keep salt off the rail; it corrodes rail, fasteners and joint bars. Do not use it in concrete-tie territory, where it attacks tie hardware. In signaled territory it lowers ballast resistance and can interfere with track circuits, and grade crossing predictors are especially sensitive. The technique was widely used by Canadian railways, mostly in non-signaled territory, but few practitioners today have enough experience to apply it confidently, and environmental approval is now required.

Shimming

Shimming compensates for heave rather than curing it. A heave bump produces an abrupt surface change that trains cannot cross safely at normal speed, and severe temporary slow orders, down to 10 mph (16 km/h), may be needed until the surface improves. Tamping is not practical in winter because the ballast is frozen. Shims of different thicknesses placed between rail and tie smooth the transition and gradually raise the track over the heave (Figure 3.8.8-15), following the railway’s track standards. All shims must be removed once the frost bumps go down. Installing them in spring and removing them in summer is slow and labor-intensive, but it remains the most common way of dealing with heave bumps.

Figure 3.8.8-15. Track shimming over a frost heave spot.
Figure 3.8.8-15. Track shimming over a frost heave spot, per typical track standards. Source: Ruel (2026b), Figure 1.9-39.

Excavation and replacement of silty soil

Where drainage has been tried and shimming has become too labor-intensive at a chronic location, more disruptive and costly measures may be justified. Replacing the frost-susceptible silt with dry, non-frost-susceptible granular fill fixes the local bump, but the ground on either side keeps heaving slightly, so the repaired zone can become a winter dip that is as hazardous as the bump it replaced. This was common where a culvert was replaced and new granular fill placed over it.

  • Replace frost-susceptible soil to only 50 to 60% of the frost penetration depth, leaving a small residual heave that matches the approaching track. This is counter-intuitive: deeper is not better.
  • Use flat transition slopes into and out of the excavation (Figure 3.8.8-16).
  • A woven geosynthetic with wicking properties at the base of the excavation helps control local moisture and heave.
  • When replacing culverts, reuse as much of the excavated material as possible over the new culvert so the section behaves uniformly in winter.
  • Involve a transportation geotechnical engineer experienced with frost heave in the design.
Figure 3.8.8-16. Gradual partial excavation and replacement of silty soil.
Figure 3.8.8-16. Gradual partial excavation of silty soil and replacement with non-frost-susceptible soil. Source: Ruel (2026b), Figure 1.9-40.

Insulation

Where the soil or the water cannot be removed, the freezing can be. Rigid extruded polystyrene insulation (Type IV or HI) on a firm granular base beneath the subballast can greatly reduce heave (Figure 3.8.8-17). The aim is to attenuate heave so the insulated zone behaves like the adjacent uninsulated track, not to stop all frost penetration. Tapered transitions at both ends are essential; without them, abrupt differential heave develops exactly where the insulation ends. A designer experienced with thermal insulation should be involved.

Figure 3.8.8-17. Insulation below the track to control frost heave.
Figure 3.8.8-17. Insulation below the track to control frost heave. Source: Ruel (2026b), Figure 1.9-41.

Injection and soil treatment

Mixing the existing soil with cement or other chemicals, either by excavation and in-place mixing or by injecting cement or urethane through drill holes from the surface, has also been successful (Figure 3.8.8-18; Chapter 7.2).

Figure 3.8.8-18. Injection through the track to control frost heave and stabilize soft spots.
Figure 3.8.8-18. Injection through the track to control frost heave and stabilize soft spots. Source: Ruel (2026b), Figure 1.9-42.
3.8.8.7 Key Points for Winter and Spring
  • Spring is the highest-risk season because its hazards compound: abundant water, blocked drainage and a weakened subgrade arrive together.
  • Recognition is everything. High differential water, seepage, tension cracks, leaning trees, toe bulging, silt boils and fresh cross-level defects must be recognized and acted on. Crews must get off the hi-rail to see most of them, especially culvert conditions.
  • Decisions are risk-based and biased toward caution: when in doubt, stop the train.
  • Water dominates both families of hazard. Poor drainage underlies roughly three-quarters of frost heave problems directly, and differential head, seepage, drawdown, bearing-capacity loss and silt liquefaction are all the story of meltwater that cannot drain. Drainage, surface and subsurface, is both the first line of defense and the most cost-effective remedy.
  • See the water, respect the warning signs, and act early.
3.8.9 Traffic-Induced Settlement of Ballast and Subgrade

Repeated axle loads are a trigger in their own right. Each passing axle adds a small permanent strain in the ballast and in any soft fine-grained subgrade, and the sum shows up as loss of track surface and, in the subgrade, as ballast pockets and progressive shear failure. A UK research study of traffic effects on embankments found that the factors that matter most are axle load, the plasticity of the clay fill, and the thickness of ballast and ash cover over it. This section gives the power-law models used to predict the settlement and a diagnostic chart for drainage-related subgrade failure.

3.8.9.1 Settlement models and failure diagnosis

Equation 3.8-1. Ballast and subgrade cumulative strain

Ballast: εp = ε1 Nb, with ε1 ≈ 0.22% and b ≈ 0.21; N = MGT × 106 × 2,000/(2P)

Subgrade: εp = a(σd/σs)mNb (parameters a, b and m from the soil-type table in Chapter 2.1), N = MGT × 106 × 2,000/(4P); settlement = strain × layer thickness.

Both laws flatten with time. New ballast and newly compacted subgrade settle quickly at first. In an established track the ballast settles after each tamping as it recompacts (only the disturbed upper 6 in. or so), while the subgrade, after many years of traffic, settles at an almost constant small rate. A soft subgrade therefore dominates the settlement of new construction, and the ballast dominates once the line is established.

Table 3.8-4. Embankment vulnerability screen by share of high-plasticity clay fill (UK study)
High-plasticity clay fillVulnerability to traffic loading
Less than 10%Low
10 to 40%Moderate
40 to 90%High
90% or moreVery high

The screen uses fill plasticity only. Axle load, ballast thickness, track geometry, drainage, fill strength and hard spots (culverts, walls) must also be reviewed.

Table 3.8-5. Drainage-related subgrade failure: causes and signs (after a published fault-chart study)
FailureMechanismField signs
Progressive shear failureSubgrade surface remolded by repeated overstress; soil squeezes outward and upwardHeave at the ballast shoulder, depression under the track, water trapped beneath
Excessive plastic deformationCompaction and shear of a soft layer of substantial depthBallast pocket; little shoulder heave
Attrition with mud pumpingBallast grinds the wet subgrade surface into slurryWet spots, fines on the ballast surface, rapid loss of geometry
Other modesLiquefaction of saturated silt and fine sand; slope failure; consolidation; frost heave and thaw softening; swell-shrink; slope erosion; collapse on wettingSee Chapters 2.4 to 2.6, 6.2, 6.3 and 6.5

The fault chart splits causes into the train loading regime and the environment (rain, flooding, poor or poorly maintained drainage) and links them to subgrade failure, drainage deterioration and embankment or cut slope failure.

3.8.9.2 Worked example: soft CH subgrade under 75 MGT per year

Table 3.8-6. 33-kip wheels, 75 MGT/yr, 18 in. of soft CH at σd/σs = 0.6 (calculator output)
CaseFirst-year settlement
New ballast, 12 in. recompacting0.57 in.
Established ballast after tamping, 6 in. disturbed0.29 in.
New subgrade0.78 in.
Subgrade after 20 years of the same traffic0.012 in.

The ballast and new-subgrade values match the textbook example (0.57, 0.29 and 0.78 in.).

New construction on this soft clay would lose more surface from the subgrade than from the ballast in its first year. Twenty years on, the subgrade contribution is a few hundredths of an inch per year and surfacing cycles are governed by the ballast. If such a site keeps needing surfacing, the cause is more likely the ballast and drainage than continued subgrade consolidation (Chapter 6.4).

Open the traffic settlement calculator →
Ballast and subgrade settlement by year for a given tonnage and wheel load, for new or established track, with the fill-plasticity vulnerability screen.

3.8.9.3 Sources in the library

Paraphrased from these documents in the reference library.

  • Railway Geotechnics (Li, Hyslip, Sussmann and Chrismer, 2016), Chapter 4: ballast and subgrade deformation models and the track settlement example.Find source ↗
  • The Effects of Railway Traffic on Embankment Stability (UK rail safety research report, 2011): failure modes, axle load and fill plasticity, vulnerability classes.Find source ↗
  • Railway Track Subgrade Failure Mechanisms Using a Fault Chart Approach (Procedia Engineering, 2015).Find source ↗Library entry
  • An Empirical Rail Track Degradation Model (thesis), Ballast folder.Find source ↗
3.8.10 Failure Mechanisms of Old Railroad Earthworks

Most railroad embankments and cuts were built long before the slopes were designed. Before the 1930s nearly all fills were end-dumped without systematic compaction, at slopes set by experience, and they settled heavily soon after construction. They now carry heavier and more frequent traffic at lower factors of safety than a new earthwork would be given. UK rail and highway owners, who manage the oldest large earthwork network, group the ways these earthworks fail into the mechanisms in Table 3.8-7. Each has its own trigger and season, so the mechanism decides what to inspect, when, and which analysis applies.

Table 3.8-7. Failure mechanisms of existing earthworks and their triggers
MechanismTypical depthTrigger and seasonWhat the track inspector seesAnalysis in this manual
Shallow translational or circular slip3 to 5 ft; survey range 0.7 to 8 ftHeavy rain after a dry season; drainage that is blocked or absentBulging or slumped slope, debris at toe; track usually unaffectedCh 6.3; Ch 6.4.11
Deep-seated first-time or delayed failureDeeper than 3 to 7 ft; may pass through the foundationSlow rise of pore pressure in stiff, high-plasticity clay over years to decades; progressive loss of strengthCrest cracking, track drop and line, toe heaveCh 6.3.6; Ch 2.5
Slide on an old shear surfaceAlong the pre-existing surfaceWet season; repairs that left the old surface in placeRecurring movement at a known slipCh 6.3.6 (residual strength)
Seasonal shrink–swell with ratchetingUpper 3 to 13 ft of clay fillDry summers under high-water-demand trees, then winter wetting; outward movement does not fully recoverSummer settlement and winter heave of track; slow net outward creepCh 2.5; Ch 3.8
Shoulder instabilityCrest and shoulderSteep upper slope, train vibration, fine ash or ballast that dries and runsNarrowing shoulder, ballast loss, tie ends unsupportedSection III (Ch 2.1)
Flooding and toe scourToe and lower slopeHigh stream or river levels beside or through the embankmentToe loss, sudden deep slip after the floodCh 2.8; Ch 6.3
Flow failure in cuttingsShallow, rapidShort, intense rain on permeable soil with run-off concentrated at the crestDebris flow onto the track at the toe of a cutCh 6.4.11; LS-series equations
Frost shattering of rock cutsFace of the cutFreeze–thaw in porous or jointed rock (chalk is especially prone)Debris at the toe; loosened trees fallingCh 2.7

After McGinnity and Saffari (2012), ICE Manual Vol. II, Section 71.2.1, pp. 1069–1073; shallow failure depths from the UK highway survey reported by Nowak (2012), Section 70.1.4, p. 1050. Depths converted from metres.

What the UK network data show. A study of train delays from geotechnical causes on the UK network in 2000–2003 put their cost at about £26 million, concentrated where high-plasticity clays occur. About 80% of the delay time came from about 20% of the incidents. In high-plasticity clay, delays in dry summers were of the same order as those in wet winters. Of 95 ultimate failures recorded later, about half were deep-seated through the crest; the rest were local crest failures, unravelling of oversteepened ash and ballast at the shoulder (mostly in summer), and shallow translational slides. Delayed deep failures were usually on slopes with grass or small shrubs; excessive track movement was usually where large trees grew on the slope (O'Brien, 2013, p. 20).

Progressive failure. In brittle, overconsolidated clay the strength along a developing slip surface drops unevenly from peak toward residual. Skempton's back-analysis of long-term failures in five cuttings in weathered London Clay gave an operating friction angle of about 20° with an average pore pressure ratio ru of 0.25 to 0.35, against laboratory peak values of φ′ = 20°, c′ = 145 psf and residual φ′r = 13°, c′r = 20 psf (McGinnity and Saffari, 2012, p. 1070). The operating strength lies between peak and residual, which is why a peak-strength analysis of an old clay slope overstates its safety.

Name the mechanism before choosing the analysis. A limit-equilibrium factor of safety with a hydrostatic water table answers the deep-seated question only; it says nothing about seasonal track movement, shoulder loss or flow failure, which are the more frequent causes of slow orders on old earthworks.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • McGinnity, B. T. and Saffari, N. (2012). Earthworks asset management and remedial design. Chapter 71 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1067–1086Find source ↗Library entry
  • Nowak, P. A. (2012). Design of new earthworks. Chapter 70 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1047–1066Find source ↗Library entry
  • O'Brien, A. S. (2013). The assessment of old railway embankments – time for a change? In Gallipoli (ed.), Partial Saturation in Compacted Soils, pp. 19–32. ICE PublishingFind source ↗
3.8.11 Trigger Inventory

Most failures are set off by water. Load and human activity come next.

Figure 3.8-21. North Vancouver public-education diagram showing nearly every warning sign and cause.
Figure 3.8-21. North Vancouver public-education diagram showing nearly every warning sign and cause.
TriggerHow It ActsMechanisms Most Affected
Intense short-duration rainfallSurface runoff, erosion, rapid rise of perched waterDebris flow, shallow slides, washout, scour
Prolonged rainfall and antecedent moistureRaises groundwater and pore pressure over days to weeksDeep-seated slides, subgrade softening, pumping
Snowmelt and rain-on-snowLarge water input on saturated or frozen groundSlides, washouts, thaw weakening
Freeze-thaw cyclesIce wedging in rock; ice lens growth and melt in soilRockfall, frost heave, spring pumping
Flood and high waterScour, overtopping, saturation of embankmentsScour, washout, piping
Rapid drawdownLoss of external water support on a saturated slopeSlides of river-bank embankments
Blocked drainagePonding against embankments; water forced through fillPiping, slides, subgrade softening
Increased loadHeavier axle loads, higher tonnage or speed, new track, stockpiles near crestProgressive shear, cumulative deformation, slides
Construction and maintenanceToe excavation, ditch cleaning that undercuts slopes, undercutting, vegetation removal, grade raisesSlides, erosion, settlement
EarthquakeCyclic loading and inertial forcesLiquefaction, lateral spread, slides, rockfall
WildfireLoss of vegetation and water-repellent soils increase runoff for several seasonsDebris flow, erosion
Beaver activityImpounds water against fills; dams fail in stormsWashout, piping
Utility leaks and miningLocalized water or loss of supportSinkholes, collapse, settlement
Figure 3.8-22. Removal of the toe: an access-road cut undercutting the fill.
Figure 3.8-22. Removal of the toe: an access-road cut undercutting the fill.
Figure 3.8-23. Oversteepening and overloading with fill placed on the shoulder.
Figure 3.8-23. Oversteepening and overloading with fill placed on the shoulder.
Figure 3.8-24. Improved slope geometry correcting the same problem.
Figure 3.8-24. Improved slope geometry correcting the same problem.

Climate trends matter for risk evaluation. Where records show more frequent intense rainfall, return-period assumptions behind existing drainage and past stability evaluations may no longer hold. Note this in the risk evaluation (Chapter 1.1, Section 1.1.7) rather than assuming past performance will continue.

Triggers and the four don’ts

A trigger is an external stimulus that causes a near-immediate landslide or washout by raising stress, reducing strength or removing soil: intense or persistent rain, floods, high stream flow, rapid snowmelt, earthquakes, elevated seepage, water-level change, freeze–thaw and rapid drawdown. Weather is the most common trigger, and antecedent wetness matters as much as the storm. Underlying causes are geological (weak, sensitive, weathered or jointed materials, adverse bedding, permeability contrasts), morphological (toe erosion, piping, crest loading, vegetation loss, thaw) and human (toe excavation, crest loading, reservoir drawdown, deforestation, irrigation, vibration, leaking utilities).

Water weakens slopes in five ways: it adds weight in the voids, is absorbed by clay minerals with loss of strength, dissolves cement between grains, erodes loose material, and becomes trapped under pressure. A failure surface balances driving and resisting mass, and four actions tip it the wrong way: steepening the slope, removing support at the toe, adding mass high on the slope, and allowing bad drainage to continue.

After Geotechnology for Railroaders Program, Module 5, Module 6.4; Module 5 §10, §14; Module 6.4 §07. Full reference under Supplemental References.

3.8.12 Rainfall Thresholds and Weather-Based Operating Protocols

Because rainfall is the dominant trigger, many railroads tie patrols, speed restrictions and special inspections to precipitation. FRA 49 CFR 213.239 requires special inspections of track after events such as floods and severe storms that may have damaged track structure. A threshold-based protocol makes that requirement predictable.

3.8.12.1 Intensity–Duration Thresholds

Empirical rainfall thresholds relate the average intensity I needed to trigger shallow landslides and debris flows to the storm duration D. The widely cited global lower-bound threshold of Caine (1980) is:

Figure 3.8-25. Slopes remain stable until rainfall intensity and duration pass a threshold.
Figure 3.8-25. Slopes remain stable until rainfall intensity and duration pass a threshold.

Equation 3.8-18: I = 0.58 × D−0.39

where I = rainfall intensity (in./hr) and D = duration (hr), valid for roughly 10 minutes to 10 days.

A global threshold is only a starting point. Thresholds should be calibrated for each territory from the railroad's own incident history and rain-gauge records. They should also account for antecedent moisture, since the same storm is far more damaging on saturated ground.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

3.8.12.2 Building a Protocol
  • Identify sites in the ground hazard inventory whose mechanism is rainfall-sensitive (Section 3.8.11).
  • Assign each a rain gauge or gridded precipitation source and a threshold (intensity, 24-hour and multi-day totals).
  • Define the response for each threshold level: heightened patrol, speed restriction, or hold trains until inspected.
  • Review each season's triggered responses and incidents, and adjust thresholds and site lists.

Declaring an extreme weather event and scaling the response

In the course’s Class I practice, the Regional Chief Engineer declares an extreme weather event for a defined subdivision and mile range. The declaration draws on weather-service forecasts and warnings and on reports from train crews and engineering forces, and is passed to Rail Traffic Control, the General Manager and the Regional Senior VP. Restrictions are decided jointly. They weigh the nature of the event, pre-existing ground conditions, topography and incident history, the quality of the weather information, the recency of patrols (a daylight inspection within four hours counts for more than a night inspection twelve hours old), train frequency, and wayside protection such as slide fences and high-water detectors.

Figure 3.8-26. Dry conditions vs. storm conditions with ponding at a blocked culvert.
Figure 3.8-26. Dry conditions vs. storm conditions with ponding at a blocked culvert.
  • Increased patrol frequency.
  • Patrols immediately ahead of each train.
  • Trains on lookout, prepared to stop within one-half the range of vision.
  • Daylight operations only.
  • No new trains into the territory; clear trains to safety.
  • Cessation of operations; move crews to safety.

The flash-flood trigger used across the Prairies and East is more than 1 in./h totaling over 3 in.; elsewhere, 2 in. in 1 h, 3 in. in 2 h, 4 in. in 4 h or 6 in. in 12 h. A double precipitation index plots short-term intensity against cumulative rainfall to define low-risk, speed-restriction and suspension zones. An antecedent rainfall index plots 2-day against 28-day totals over the history of past landslides at a station. In spring, bearing capacity can drop 30–50%.

Figure 3.8-27. Double precipitation index: hourly vs. continuous rainfall with low-risk, speed-restriction and suspension zones.
Figure 3.8-27. Double precipitation index: hourly vs. continuous rainfall with low-risk, speed-restriction and suspension zones.

After Geotechnology for Railroaders Program, Module 7.2, Module 7.1, Module 4; Module 7.2 §03–06; Module 7.1 §07. Full reference under Supplemental References.

3.8.13 Diagnosing the Mechanism from the Symptom

Use this table to move from what the field inspector sees to the most likely mechanisms, and to the investigation that will confirm which one applies.

Observed SymptomLikely MechanismsConfirming Investigation
Recurring surface or cross-level defect at one locationBallast pocket, progressive shear, soft foundation, culvert backfill lossTrench across track, borings, GPR, geometry-car history
Mud at tie ends, fouled shouldersMud pumping, ballast foulingBallast sampling and fouling index, subgrade plasticity, drainage check
Heaved ballast shoulder or ditch sideProgressive shear failure (subgrade squeeze)Trench, field vane or CPT, moisture content
Longitudinal cracks in crest, parallel to trackRotational or translational slide; embankment spreadingInclinometers, piezometers, stability analysis
Bulging toe, seepage or boils at toeSlide in progress; internal erosionPiezometers, seepage mapping, borings at toe
Circular depression or hole near trackSinkhole, pipe or culvert failure, buried timber decayProbing, geophysics, camera inspection of nearby culverts and utilities
Seasonal heave and spring soft spotsFrost heave and thaw weakeningFrost susceptibility testing, groundwater levels
Fresh rock in ditch or on trackRockfall and toppleRock slope mapping, rockfall hazard rating (Chapter 1.1)
Scour hole or exposed footing at bridgeLocal or contraction scourUnderwater inspection, scour evaluation per HEC-18
Impact of Excavation on the Hydrogeologic Regime and Slope Stability
Impact of Excavation on the Hydrogeologic Regime and Slope Stability

Geometry defect types and what drives them

The book defines geometry defects against a theoretical track position averaged over a chord: longitudinal defect (surface or profile), transverse defect (cross-level relative to design cant), horizontal defect (alignment), gauge, and twist (deviation of one of four points on two ties from the plane of the other three, i.e. the change in cross-level per unit length).

Figure 3.8-28. Longitudinal (a), transverse (b) and horizontal (c) track defects. Profillidis Fig. 16.3.
Figure 3.8-28. Longitudinal (a), transverse (b) and horizontal (c) track defects. Profillidis Fig. 16.3.
Figure 3.8-29. Track twist: deviation of one point from the plane defined by the other three on successive ties i and i+1. Profillidis Fig. 16.4.
Figure 3.8-29. Track twist: deviation of one point from the plane defined by the other three on successive ties i and i+1. Profillidis Fig. 16.4.
  • Longitudinal defect is the most reliable indicator of vertical loading on the track and, with transverse defect, the main driver of maintenance cost. This is where subgrade settlement and pumping appear first.
  • Horizontal defect depends mostly on lateral track effects and rolling-stock behavior, which points toward ballast-section and lateral-resistance issues (Chapter 2.3, §2.3.3).
  • Gauge deviations depend mainly on the subgrade and the type of rolling stock.
  • Twist is one of the most frequent causes of derailment, and at speeds below 87 mph it is the main critical safety parameter. Localized differential settlement under one rail, for example at a culvert, a soft spot or a shoulder failure, shows up as twist.

Geometric parameters degrade about 5–15 times faster than mechanical ones (rail, ties, fastenings). On a typical UIC group 4 line, geometry is restored after about 40–50 million tons, while rail lasts 500–600 million tons.

After Profillidis (2014), §16.2–16.4, Figs. 16.3–16.4. Full reference under Supplemental References.

Match the remedy to the cause

Mud on the ballast surface can come from three sources, and each needs a different fix:

  • Subgrade pumping: renew the ballast and add a blanket.
  • Worn ballast: renew the ballast.
  • Spillage from cars: clean the ballast.

Before committing to cleaning or renewal, examine the layers down into the subgrade with trenches, pits or trackbed borings (Chapter 3.9).

Table 4-SW1. Short-term and long-term remedies by cause (condensed)
CauseShort-term responseLong-term remedy
Ballast and tie wear or attritionAdd ballast depth; tampRenew with more durable ballast
Fouled ballast (breakdown or spillage)Tamp; this delays cleaning only brieflyClean by undercutting or shoulder cleaning
Subgrade attrition and pumping, no subballastClean ballast (temporary)Clean and place a blanket
Subgrade attrition, ballast also worn out—Renew the ballast and place a blanket
Progressive shear failureNo effective short-term fixExcavate and rebuild to the required granular depth, and restore drainage
Ballast pocket holding waterDrain the pocket where possibleReshape the subgrade or reconstruct; provide an outlet

Condensed from the book’s failure-condition and remedy table, which is partly illegible in the source scan. Authors' wording.

Clues in the geometry record.

  • A sharp rise in the deterioration rate from one cycle to the next flags fouling.
  • Track that settles back to the same profile after each tamp is showing its inherent shape (Chapter 5.3). Low-lift tamping will not change that shape.

After Selig & Waters (1994), chs. 14 and 15. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • RK-12 Rockfall Hazard Rating System scoring RHRS scoreUse: Prioritizing highway (and adapted rail) rock slopes for remediation. Limits: Relative ranking, not a probability of failure. Rail adaptations (e.g., corridor-specific USMP / RHRS variants) modify categories.
3.8.14 Monitoring and Early-Warning Indicators

Monitoring converts an unknown mechanism into a measured one. It also provides warning where mitigation cannot be built right away. Instrument selection, installation and reading frequency are covered in Chapter 5.3.

Figure 3.8-30. Signs-of-instability job aid.
Figure 3.8-30. Signs-of-instability job aid.
IndicatorInstrument or Data SourceMechanism Monitored
Subsurface displacementInclinometers (ASTM D6230), shape arrays, TDR cableSlides, creep, spreading
Pore pressureVibrating-wire piezometers, observation wellsSlides, consolidation, rapid drawdown
SettlementSettlement plates, survey monuments, track geometry-car trendsConsolidation, cumulative deformation, sinkholes
Ground surface changeLiDAR change detection, InSAR, UAV photogrammetrySlides, subsidence, erosion
Track bed conditionGPR surveys (Chapter 2.3, Section 2.3.9)Fouling, ballast pockets, wet subgrade
Rockfall and slide detectionSlide fences and detector wires tied to signalsRockfall, debris flow
Rainfall and stream stageRain gauges, stream gauges, weather servicesAll water-triggered mechanisms (Section 3.8.12)

Track-recording data as an early-warning stream

Recording cars run at fixed intervals: about 3 times a year on main routes, twice a year on intermediate routes and once a year on branch lines. They measure longitudinal, transverse and horizontal defects on a base of about 33 ft and twist on 8–10 ft. At low and medium speeds the absolute (peak and mean) values govern. At higher speeds the standard deviation over 660–980 ft is used as the quality index. Results are ranked by severity and compared with earlier runs and with the limits.

Figure 3.8-31. Longitudinal defects as recorded. Profillidis Fig. 16.6.
Figure 3.8-31. Longitudinal defects as recorded. Profillidis Fig. 16.6.

Defects grow quickly until about 2 million tons after maintenance, then slowly and roughly with log T:

me(T) = a1 + a0 · log(T / Tr),    Tr = 2.2×106 tons

Here a1 is the mean settlement at Tr and a0 is the settlement rate per log cycle, 0.079–0.24 in. per decade, depending mainly on subgrade quality (a0/a1 = 0.25–0.70). The standard deviation of longitudinal defects follows the same form with c0 ≈ 0.0039–0.0079 in. per decade. A segment whose fitted a0 or c0 drifts above its neighbors is a candidate for substructure investigation. The sensitive period (about 1–4 months on a UIC group 4 line, 15–40 days on groups 1–3) is when monitoring after a repair matters most.

Figure 3.8-32. Mean track settlement me(T) vs. log of traffic since maintenance. Profillidis Fig. 16.8.
Figure 3.8-32. Mean track settlement me(T) vs. log of traffic since maintenance. Profillidis Fig. 16.8.

After Profillidis (2014), §16.5, §16.7, §16.10, Eqs. 16.3–16.5, Figs. 16.5, 16.6, 16.8. Full reference under Supplemental References.

Figure 3.8-33. Chord-type track recording car (French railways) and its measurement bases. Profillidis Fig. 16.5.
Figure 3.8-33. Chord-type track recording car (French railways) and its measurement bases. Profillidis Fig. 16.5.

Signs of instability job aid and field reporting

Warning signs appear in a predictable order: unusual high water on one side, seepage at the downhill toe, tension cracks along the shoulder (often hidden in ballast), a bulging toe and a small sand fan, increasingly dirty or milky seepage, trees leaning in different directions, and finally settlement or cross-level change in the track. Test hidden cracks with a lining bar; it meets little resistance over a fissure. Paint reference marks to see whether cracks widen. Walk down to the base of the fill when checking culverts, because much of this cannot be seen from the track. If movement is large and accelerating, take the track out of service and restore drainage urgently.

Figure 3.8-34. Testing a suspected tension crack in the field.
Figure 3.8-34. Testing a suspected tension crack in the field.
Figure 3.8-35. Paint marks used to monitor crack widening.
Figure 3.8-35. Paint marks used to monitor crack widening.
Figure 3.8-36. Leaning trees: a subtle sign of slope movement.
Figure 3.8-36. Leaning trees: a subtle sign of slope movement.

Moisture clues: groundwater discharge in depressions, wet zones or salt stains in cut ditches, frost boils, ice at culvert sides, moisture-loving plants (cattails, willows), and sudden lush vegetation on a slope. Report every natural-hazard incident, including rock found in a ditch, on the Natural Hazard Incident Report. It records site and weather (at the time and over the prior 24 h), a rockfall section, a mass-movement and washout section, and consequences (damage, delays, slow orders). The data is used to deploy rock gangs and maintenance crews.

Figure 3.8-37. Natural Hazard Incident Report, rockfall section.
Figure 3.8-37. Natural Hazard Incident Report, rockfall section.
Figure 3.8-38. Natural Hazard Incident Report, mass movement, washout and consequence sections.
Figure 3.8-38. Natural Hazard Incident Report, mass movement, washout and consequence sections.

After Geotechnology for Railroaders Program, Module 5, Module 7.1, Module 4, Module 6.4; Module 5 §11; Module 7.1 §05; Module 4 §10; Module 6.4 §05. Full reference under Supplemental References.

Project management · Skill Right (2013)

RASIC Responsibility Matrix for Monitoring and Alarm Response

A responsibility assignment matrix (RAM) makes sure every task has an owner and shows how deeply each person is involved. Tasks are listed as rows and roles as columns. The course uses the RASIC code:

Example responsibility assignment matrix that assigns R, A, S, I and C codes to each task and each project role.
Figure 4-PM1. Example responsibility assignment matrix that assigns R, A, S, I and C codes to each task and each project role. Source: Skill Right (2013), Slide: Responsibility Assignment Matrix (RASIC Method).
  • R – Responsible: makes sure the work is completed and delivered.
  • A – Approve: confirms the work meets the requirements.
  • S – Support: does the work and is committed to completing it.
  • I – Inform: kept up to date on status; makes no decisions.
  • C – Consult: gives input before the work is done.

The course example assigns codes for a marketing study (identify market, develop and test the survey, collect and analyze the data, report) across project manager, customer, team members, senior management and support staff.

For railroad work: an early-warning system is only as good as the chain from instrument reading to train movement decision, and that chain crosses organizations. A RASIC matrix agreed before the instruments are installed removes ambiguity at 2 a.m. The illustrative example below must be adapted to each railroad’s own operating rules and authority for slow orders and track removal from service.

Table 4-PM1. Illustrative RASIC matrix for an instrumented slide (adapted from the course method)

TaskGeotech consultantRailroad engineeringTrack supervisorOperations / dispatch
Set alert and action thresholdsR/SACI
Read and reduce instrumentsR/SII–
Threshold exceedance noticeR/SIII
Field inspection of track and slopeSAR/SI
Speed restriction or removal from serviceCAR/SS
Return to normal operationCARI

Keep one Approve per row so that the decision has a single owner. Put named people and phone numbers, with alternates, in the monitoring plan, and review the matrix whenever staff or thresholds change.

Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 45–47. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

3.8.15 Worked Calculation Examples
The two examples show how a trigger changes the margin of safety at a site. Each is laid out in five parts: what is known (Given), what is wanted (Required), the equations, a flow chart of the steps in the order they are solved with a spot check at each step, and the solution with what it means for the track.
Example 3.8-1: Effect of a Rising Water Table on an Embankment Side Slope

A 2H:1V embankment side slope of silty sand fill carries a main track, and shallow sloughing has been reported after heavy rain. The question is how much of the margin of safety the water takes away. The infinite-slope model (Chapter 6.3) suits this case because the sloughs are shallow and long compared with their depth, and seepage parallel to the slope is the condition that develops in a long wet spell.

slip surfacez = 6 ft (vertical, arrow)β = 26.6° (2H:1V)water table at height m·z above slip, m = 0, 0.5, 1.0FS (dry, half, full) = ?Givenβ = 26.6°; z = 6 ftγ = 120 pcf; γw = 62.4 pcfc′ = 50 psf; φ′ = 32°m = 0, 0.5, 1.0RequiredFS for dry, half and full saturationMeets 1.5 target? Meaning for the triggerBlack = given; red = required
Given and required for Example 3.8-1.

Given

VariableValueDescription
β26.6° (2H:1V)Slope angle
z6 ftVertical depth to the slip surface
γ120 pcfTotal unit weight of the fill
γw62.4 pcfUnit weight of water
c′50 psfEffective cohesion
φ′32°Effective friction angle
m0, 0.5 and 1.0Saturated fraction: height of the water table above the slip surface divided by z

Required

  • Factor of safety FS for dry, half-saturated and fully saturated conditions
  • Whether the slope meets the 1.5 target, and what the result means for the trigger

Equations

  1. Eq. 1: τd = γ z sinβ cosβ — driving shear stress on the slip plane
  2. Eq. 2: σ = γ z cos²β — total normal stress on the slip plane
  3. Eq. 3: u = m γw z cos²β — pore pressure for seepage parallel to the slope
  4. Eq. 4 (Equation 3.8-19): FS = [c′ + (σ − u) tanφ′] / τd — infinite-slope factor of safety

Steps

Step 1 · Trigonometric terms
cos²β and sinβ cosβ for β = 26.6°
cosβ = 0.894, sinβ = 0.447
cos²β = 0.800; sinβ cosβ = 0.400; tanφ′ = tan 32° = 0.625
Spot check: For a 2H:1V slope tanβ = 0.5, so cos²β = 1/(1 + 0.25) = 0.800 exactly.
↓
Step 2 · Driving stress τd (Eq. 1)
Uses: γ, z, sinβ cosβ
τd = 120 × 6 × 0.400
τd = 288 psf
Spot check: 120 × 6 = 720; 720 × 0.4 = 288.
↓
Step 3 · Normal stress σ (Eq. 2)
Uses: γ, z, cos²β
σ = 120 × 6 × 0.800
σ = 576 psf
Spot check: σ is exactly twice τd, because cos²β / (sinβ cosβ) = 1/tanβ = 2.
↓
Step 4 · Pore pressure u for each condition (Eq. 3)
Uses: m, γw, z, cos²β
u = m × 62.4 × 6 × 0.800 = 299.5 m
u = 0, 150 and 300 psf for m = 0, 0.5 and 1.0
Spot check: At m = 1.0, u / σ = 299.5 / 576 = 0.52, close to γw/γ = 0.52, as it must be.
↓
Step 5 · Factor of safety for each condition (Eq. 4)
Uses: c′, σ, u, tanφ′, τd
Dry: [50 + 576 × 0.625] / 288 = 410 / 288
Half: [50 + 426 × 0.625] / 288 = 316 / 288
Full: [50 + 276 × 0.625] / 288 = 223 / 288
FS = 1.42 (dry), 1.10 (half saturated), 0.77 (fully saturated)
Spot check: Each step of 0.5 in m removes 150 × 0.625 = 94 psf of resistance, or 0.33 in FS; 1.42 − 0.33 = 1.09 and 1.09 − 0.33 = 0.76, matching within rounding.
↓
Solution
FS falls from 1.42 (dry) to 1.10 (half saturated) to 0.77 (saturated).

Solution

FS = 1.42 dry, 1.10 half saturated and 0.77 fully saturated. The slope is marginal even when dry, below the 1.5 target. A storm that saturates half the slipping depth brings it close to failure, and full saturation fails it.

The example separates the three parts of the story that Section 3.8.1 asks for. The mechanism is shallow translational sliding of the fill. The condition that makes it possible is a steep slope in a weak, permeable fill. The trigger is rainfall infiltration that builds pore pressure. Controls that act on the mechanism are flattening the slope, a drained rock buttress, or surface drainage and vegetation. Until one is built, a rainfall-based patrol (Section 3.8.12) manages the exposure, because it watches the trigger the example shows is decisive.

Example 3.8-2: Checking a Storm Against the Caine Threshold

A rain gauge near a debris-flow channel above the track records a storm. Rainfall thresholds turn a forecast or a gauge reading into a decision, so the check is whether this storm is intense enough, for its length, to be in the range where shallow landslides and debris flows have started worldwide.

0.1110100Duration D (hr, log)Intensity I (in./hr, log)0.010.1110Caine (1980): I = 0.58 D−0.39D = 6 hr: I = ? Exceeds?GivenP = 2.0 in.D = 6 hrI = 0.58 D−0.39 (in./hr)RequiredAverage storm intensity IThreshold at 6 hr; exceeded?Black = given; red = required
Given and required for Example 3.8-2.

Given

VariableValueDescription
P2.0 in.Storm rainfall at the gauge
D6 hrStorm duration
ThresholdI = 0.58 D−0.39Caine (1980) global threshold in in./hr, valid for 10 minutes to 10 days

Required

  • Average storm intensity I
  • Threshold intensity for a 6-hour storm, and whether the storm exceeds it

Equations

  1. Eq. 1: I = P / D — average intensity
  2. Eq. 2 (Equation 3.8-18): It = 0.58 D−0.39 — threshold intensity (in./hr, D in hours)

Steps

Step 1 · Storm intensity I (Eq. 1)
Uses: P, D
I = 2.0 / 6
I = 0.333 in./hr
Spot check: One-third of an inch an hour: 6 × 0.333 = 2.0 in.
↓
Step 2 · Threshold intensity It (Eq. 2)
Uses: D
60.39 = 2.01; It = 0.58 / 2.01
It = 0.29 in./hr
Spot check: ln 6 = 1.79; 0.39 × 1.79 = 0.70; e0.70 = 2.01.
↓
Step 3 · Compare
Uses: I, It
0.333 in./hr against 0.29 in./hr
I > It: the storm exceeds the global threshold
Spot check: The ratio is 0.333 / 0.29 = 1.15, a 15% exceedance.
↓
Solution
The storm exceeds the threshold (0.333 > 0.29 in./hr).

Solution

Yes. The storm, at 0.333 in./hr over 6 hours, exceeds the Caine threshold of 0.29 in./hr.

Under a protocol calibrated to this threshold, the site would move to its heightened-response level, such as a patrol before the next train or a speed restriction, depending on its risk rating. The global threshold is a lower bound drawn from worldwide data and ignores antecedent moisture, so it is a starting point. Calibrate it against the territory’s own event record before relying on it (Sections 3.8.12 and 3.8.23.7).

3.8.16 Practical Recommendations
  • Record the mechanism, not just the symptom, in every inspection and report. "Soft track" is a symptom; "progressive shear failure of wet CL subgrade" is a mechanism.
  • Look for the preparatory factor that is eroding the margin: a blocked outlet, rising tonnage, toe erosion or a corroding culvert. It is usually cheaper to stop than the failure it leads to.
  • Before ditch cleaning or toe excavation at a known slope, have the geotechnical engineer review the work. Maintenance activity is a recurring trigger.
  • Pair every rainfall-sensitive site in the inventory with a rain source and response threshold.
  • After an event, document the trigger magnitude (rain totals, flood stage, earthquake magnitude and distance). This data calibrates future thresholds.
  • Use instrumentation to confirm the mechanism before committing capital to a repair. Inclinometers and piezometers cost little compared with a buttress built for the wrong failure surface.
3.8.17 Failure Mechanism Assessment Checklist

Checklist · Part IV · Failure Mechanisms (Triggers)

Failure Mechanism Assessment Checklist

Failure Mechanism Assessment Checklist0 of 12
Ticks are saved in this browser.
Plain text version
  • [ ] Hazard category assigned (landslide, hydraulic, subsidence) per Chapter 1.1
  • [ ] Mechanism identified and supported by field evidence (Section 3.8.13)
  • [ ] Predisposing conditions documented (soil, geometry, groundwater)
  • [ ] Preparatory factors identified and, where possible, stopped
  • [ ] Relevant triggers listed with site-specific thresholds where applicable
  • [ ] Factor of safety estimated for current and triggered conditions
  • [ ] Monitoring installed where the mechanism is uncertain or mitigation is deferred
  • [ ] Operating protocol (patrol, slow order, warning system) defined for residual risk
  • [ ] Mitigation selected to address the mechanism, not only the trigger (Chapter 1.1, Section 1.1.9)
  • [ ] Spring readiness: critical culverts inspected and cleared of ice before the melt; differential water levels and seepage checked from the ground, not the hi-rail (Section 3.8.7)
  • [ ] Embankments that were submerged kept under observation for 24 to 48 hours after any rapid drop in water level (Section 3.8.7.5)
  • [ ] Frost heave and silt-boil locations marked on the ties and logged in the registry; remedy chosen to remove water, silt or freezing (Section 3.8.8)
3.8.18 Triggering Mechanisms

A ground hazard fails when a triggering event acts on ground that is susceptible to it. The susceptibility is fixed by where the site is and how it was built (soils, geology, slope geometry, water, drainage); the trigger is the event that tips it over: a storm, a flood crest, a thaw, a blocked culvert, an excavation at the toe. Chapter 3.8 describes the mechanisms (Section 3.8.1 distinguishes mechanism, condition and trigger) and the trigger inventory (Section 3.8.11). This chapter puts the trigger at the head of the rating, because it is the thread that ties the rest together: it explains the defects, sets the live thresholds, and is what a solution must remove or resist.

3.8.18.1 Preparatory Conditions, Triggers and Failure Modes

Three things are named for every site:

  • Preparatory conditions: the slowly changing conditions that bring the ground closer to failure (weathering, softening of a clay fill, a culvert silting up, a channel migrating toward the toe, loss of vegetation). They are scored in the geospatial rating (Section 3.8.19).
  • Triggering mechanism: the event that causes failure at a given time. It is scored by the trigger rating T (Section 3.8.18.3).
  • Failure mode: what the failure does to the track (loss of support, washout, settlement, slide, rockfall). It sets the severity S together with what the track carries.

3.8.18.2 Triggering Mechanisms by Driving Mechanism

Table 3.8-8. Common triggering mechanisms on railroad ground hazard sites
Driving mechanism (Section 3.8.23.3)Typical triggersHow the trigger actsData used to rate and monitor it
Slope-drivenProlonged or intense rainfall; snowmelt; rapid drawdown; toe excavation; added load (new track, fill, stockpiles); earthquakeRaises pore pressure or removes or loads the slope, lowering the factor of safety below 1.0Rainfall and antecedent wetness, snowmelt, river stage, construction records, seismic hazard maps
Scour-drivenFlood crest; ice jam; debris on a pier or culvert inlet; channel migrationRemoves support at the toe, abutment or culvert outlet; oversteepens the bankRiver gauges and flood categories, flow percentile, high-water marks, imagery sequence
Drainage-drivenStorm exceeding culvert or ditch capacity; blockage by debris, sediment or beavers; frozen culvertPonds water against or within the fill; saturates and softens it; causes piping or overtoppingCulvert capacity storm, 24-hour rainfall, beaver activity, inspection records
Subgrade-drivenWet season; spring thaw after deep frost; increased tonnage or axle loadSoftens the subgrade; causes pumping, ballast pockets and loss of bearingFrost depth and thaw, soil moisture, tonnage records, geometry exception frequency
Subsidence-drivenHeavy rainfall or a broken pipe in karst; groundwater drawdown; mine void migration; wetting of collapsible soilWashes soil into voids or collapses a void roof; collapses the soil structureKarst and mine maps, rainfall, utility records, InSAR where available
Rock and debrisFreeze-thaw cycles; intense rainfall; root wedging; wildfire followed by rain; earthquakeOpens joints and loosens blocks; mobilizes debris flowsFreeze-thaw cycle counts, rainfall intensity, burn area maps, rockfall records

Where two triggers act together, for example a flood that scours the toe followed by drawdown that fails the slope, record both and name the one that starts the sequence as the primary trigger.

3.8.18.3 Trigger Rating (T)

The trigger rating scores how often the primary trigger reaches the level that this site has shown, or can be expected, to respond to. The levels use the same annual frequency bands as the frequency index (Table 3.8-14), so a trigger and a failure can be compared directly.

Table 3.8-9. Trigger rating levels and rationale
TLevelHow often the trigger reaches the site's response levelRationale
5Acting nowThe trigger is acting, or reaches the response level one or more times a year (for example, water ponds against the fill in most wet seasons)A trigger that is present every year leaves no margin: any susceptibility the site has will be tested every year, so failure frequency is limited only by the ground.
4FrequentAbout 1 in 1 to 1 in 5 years (for example, the paired gauge reaches minor flood stage most years; the culvert overtops in a 2- to 5-year storm)Events in this band are more likely than not to occur within a five-year maintenance or budget cycle (about 67% at the 1-in-5 edge, Section 3.8.30); the site will meet its trigger before most programs could fix it.
3OccasionalAbout 1 in 5 to 1 in 25 years (for example, a 10-year storm exceeds the culvert capacity)Likely within the working life of a track structure and of the people managing it; a credible design and planning event.
2RareAbout 1 in 25 to 1 in 100 yearsWithin the range of events that railroad drainage and slopes are commonly designed for; failure from this trigger alone is unusual.
1RemoteLess than 1 in 100 years, or no credible trigger for the site's mechanismBeyond the usual design event; the site needs an extreme or unrecognized event to fail.

Use the site's own response level (the stage, rainfall or thaw at which it has responded before) where it is known (Section 3.8.23.7). Where it is not known, use the design capacity (culvert capacity storm, flood stage at the toe) and score T no lower than 3 until the record shows otherwise. The trigger elements and their levels are in Section 3.8.27.2.

3.8.18.4 The Trigger Narrative

Every rating begins with a short narrative, written before the numbers, that links the site, the trigger and the evidence. It is the first thing a reviewer reads and the test the numbers must pass: if the narrative and the ratings disagree, one of them is wrong.

Trigger narrative template. At [site], [preparatory conditions] make the [fill, cut or slope] susceptible to [failure mode] by a [driving mechanism] mechanism. Failure is most likely to be triggered by [primary trigger] when [response level or threshold], which occurs about [frequency] (T = [1–5]). The site has responded to this trigger [history of defects and failures]. Today, [current conditions and defects]; the current risk is therefore [rating]. The risk can be reduced by [removing the trigger, increasing resistance, or reducing exposure].

The narrative also sets the live rating: the trigger and its response level become the site's thresholds for the live rating of Section 3.8.26.

3.8.19 Determination of Current Risk: Geospatial Risk Plus Defect Rating

The current risk combines two independent lines of evidence: the geospatial risk, which says what the location, its conditions and its trigger make likely, and the defect rating, which says what the track and the ground are actually showing. Neither is enough alone. A susceptible site with a frequent trigger can be sound today, and a site that looks benign on every map can be moving. The two are combined into the current frequency index Fc, which with the severity S gives the current risk rating.

3.8.19.1 Geospatial Frequency (Fg)

The geospatial frequency is assembled at the desk from mapped and recorded data: the situational likelihood attributes L1 to L5 (soils, geology, slope geometry, hydrology, drainage), weighted for the driving mechanism, and the historic instability attribute L6, exactly as in Sections 3.8.23.4 and 3.8.24.3 (element criteria in Sections 3.8.27.3 and 3.8.27.4). It is then bounded by the trigger rating:

Equation 3.8-2. Geospatial frequency
L = [ Σ (wi · Li)i = 1 to 5 + L6 ] / [ Σ wi + 1 ], rounded half up (Section 3.8.24.3)
Fg = the lesser of L and T

Rationale. A site cannot fail more often than the event that triggers it. Bounding L by T keeps a highly susceptible site with no credible trigger from rating as if it failed every year, and it makes the trigger narrative part of the number. Where the trigger is uncertain, T is scored no lower than 3 (Table 3.8-9), so the bound never hides an unrecognized trigger.

3.8.19.2 Defect Rating (D)

The defect rating scores the evidence that the ground is responding: track geometry defects and slow orders at the site, and the instability indicators recorded in the field (Table 3.8-25). Defect frequency is the best single measure of how fast a condition is developing (Section 3.8.24.4).

Table 3.8-10. Defect rating levels and rationale
DLevelDefect and indicator evidenceRationale
5ActiveGeometry defects return within weeks of surfacing; standing slow order or track removed from service; active cracking, bulging, settlement or erosion that is visibly progressingThe failure is under way; this is the field evidence that defines an Occurring frequency index (Table 3.8-14).
4RecurringThe same defect returns between surfacing cycles (surfaced two or more times in 12 months at the same location), or a slow order in the last 12 months; fresh tension cracks or a growing bulgeMovement is continuing and outpacing maintenance; this is the evidence that defines Emerging.
3PresentDefects reported more than once in the record but not returning between cycles, or indicators present (seepage, standing water at the toe, old cracks, a narrow shoulder) without signs of progressThe conditions for failure are showing at the surface, but movement is not demonstrated; consistent with Forming.
2HistoricPast failures or repairs at the site, or a single defect in the record, with no current indicatorsThe site has failed before and may again under a large trigger; consistent with Dormant.
1NoneNo defects in the record and no indicators in the fieldNo evidence that the ground has responded; frequency can be judged only from the geospatial rating.

Record each defect with its measurement (in inches) and its frequency, as in Block 2 of the Ground Hazard Risk Assessment Report (Section 3.8.24.4). At the desk, D is scored from the defect and slow order records; in the field it is confirmed or changed from what is seen. The defect elements and their levels are in Section 3.8.27.5.

3.8.19.3 Combining Them: Current Frequency (Fc)

Equation 3.8-3. Current frequency index
Fc = the greater of D and the lesser of (Fg, 3)
then add 1 (to a maximum of 5) where D ≥ 3 and Fg ≥ D + 1

The rule has three parts, each with a reason:

  • Evidence governs. Where the defect rating is at or above the geospatial frequency, Fc = D. What the track is showing outweighs what the maps suggest.
  • Susceptibility without movement is capped at Forming. Without defects or indicators, the geospatial frequency can raise Fc only to 3. By definition (Table 3.8-14), Emerging and Occurring require signs of movement; a desk rating of 4 or 5 with D = 1 or 2 is a reason to visit early, not proof of activity (Section 3.8.24.3).
  • A susceptible setting with a frequent trigger amplifies defects. Where defects are present (D ≥ 3) and the geospatial frequency is higher still, the site is responding and will be tested again soon, so Fc is raised one level.
Table 3.8-11. Current frequency index Fc for each combination of geospatial frequency and defect rating
Geospatial Fg ↓ / Defect D →D = 1 NoneD = 2 HistoricD = 3 PresentD = 4 RecurringD = 5 Active
Fg = 533455
Fg = 433445
Fg = 333345
Fg = 222345
Fg = 112345

Read the row for Fg and the column for D. Where D is at or above Fg the defects govern; with little or no defect evidence the cap of 3 applies; the cells Fg = 4 or 5 with D = 3, and Fg = 5 with D = 4, carry the one-level amplification.

3.8.19.4 Live Adjustment

The current frequency index is the rating under usual conditions. During a weather or river event the live rating of Section 3.8.26 raises it while the trigger's threshold is exceeded, and returns it to Fc when the event has passed and the site has been checked. The trigger named in the narrative is the trigger the live rating watches.

3.8.20 Severity

Severity (S) is the consequence if the failure happens, scored 1 to 5 from Table 3.8-15: what the track carries (traffic, speed, passenger and hazardous materials trains), the number of tracks and redundancy of the route, the size of the failure, and what lies below and beside the track. Severity is a property of the site, not of the trigger or the state of the ground; it does not change during a live event. The consequence elements and their levels are in Section 3.8.27.6.

Two rules carry the extra weight on consequence called for in Section 1.1.2: where the consequence and the typical setting point to different levels, the consequence governs; and the engineer may raise the rating one level where the matrix understates the risk (Section 3.8.22.6), but never lower it. Severity changes in a risk reduction only where the solution changes what a failure would reach (Section 3.8.37.3).

When severity changes, and when it does not

Because severity belongs to the site and what it carries, it is rescored when the line changes, not when the ground or the weather does.

  • S rises when passenger service or hazardous materials routing is added, when traffic or speed increases materially, when development appears below or beside the fill (a road, homes, a water intake), or when a detour is lost.
  • S falls when the line is downgraded or taken out of main-line service, when the track is realigned away from the slope, when a protective structure is built between the hazard and the track, or when a detour becomes available.
  • S does not change during a storm or a flood (the live rating raises F only), when a stabilization lowers the chance of failure, or when monitoring is installed. The one exception is detection tied to an operating response, which may lower S by one level, and only while the response is in force (Table 3.8-80).

A quick check before a severity is recorded: name the train that would meet the failure, what it is carrying and at what speed; say where a derailed train would go (into a creek, onto a road, against a building); and say how long the line would be out and whether traffic can be detoured. If those answers point to different levels, the consequence governs. The same 15-ft slump below the track is Critical or Catastrophic under a main line with hazardous materials traffic over a stream, and Minor under a yard track with a parallel lead.

3.8.21 Current Risk Rating
Equation 3.8-4. Current risk
Rc = Fc × S (1 to 25); the current risk rating is read from the risk matrix, Table 3.8-16

The current risk rating carries the required response of Table 3.8-17 (Severe: act now; High: act soon; Elevated: plan; Guarded: watch; Low: routine inspection). It is reported with the trigger narrative and with each of its inputs, so a reviewer can see whether the rating is driven by the location (Fg), by the track (D) or by the consequence (S).

Table 3.8-12. Record of the current risk
ItemValueOne-line reason
Primary trigger and Te.g. culvert overtopping, T = 4Ponding against the fill recorded about every 3 years
Situational and historic score L1–5Weighted L1–L6 per Section 3.8.24.3
Geospatial frequency Fglesser of L and T
Defect rating D1–5Defect measurements and frequency; indicators
Current frequency FcTable 3.8-11
Severity S1–5Traffic, setting, what lies below
Current risk Rc and ratingFc × S; Table 3.8-16
Check the narrative against the numbers. A High rating driven by D = 4 should read as a site that is moving; one driven by Fg with D = 1 cannot be above Forming and should read as a susceptible site awaiting its trigger.
3.8.22 Ratings: Scales and How They Are Applied

Every rating in this chapter is built from two questions: how likely is the ground to fail, and how bad would a failure be? The first is answered by the frequency index (F); the second by the hazard severity (S). Each is scored on five levels, and the two are combined into a risk score and a risk rating. The situational, instability, static and live ratings in the sections that follow are not separate systems: they are different ways of arriving at F and S, and they all end on the same matrix. A site rated Elevated at the desk, on a live map or on the field form means the same thing in every case. Figure 3.8-39 shows how the pieces fit together.

InputsTrigger Twhat sets it off (3.8.18)Situational L1–L5soils, geology, slope, waterInstability L6past movement (3.8.24)Defect rating Dtrack and field (3.8.19)Consequence C1–C5track, traffic, settingGeospatial F​gL1–L6, no higherthan T (Eq. 3.8-2)Current F​cF​g with D(Eq. 3.8-3, Table 3.8-11)Severity S(3.8.20)R = F × Srisk score 1–25(3.8.22.4)RatingTable 3.8-16and responseTable 3.8-17The same F, S and matrix are used again forLive ratingF​live = F​0 + increment from gauges,rain, soil moisture, thaw (3.8.26)Risk reductionF​sol → F​des, F​con → F​postsolution, design, verified (3.8.37–3.8.39)Desk: from records(preliminary F​p, S​p)Field: confirmedon the report (3.8.42)
Figure 3.8-39. How the ratings fit together. Every rating in the chapter is a route to the same frequency index F and severity S, combined on one matrix. The live rating and the risk-reduction ratings reuse F, S and the matrix.

3.8.22.1 The 1-to-5 Convention

Every scale in this chapter runs from 1 to 5, and risk increases with the number. This holds for the situational and instability attributes (L1 to L6 and C1 to C5), the frequency index, the hazard severity, the live frequency index and the risk rating itself. Where the evidence for an attribute is missing, it is scored 3, the middle of the scale, and flagged for the field visit. Table 3.8-13 shows where each scale is used.

Table 3.8-13. The rating scales and where each is used
ScaleSymbolRangeSet fromSection
Situational likelihood attributesL1–L51–5 eachLocation and inherent conditions: soils, geology, slope, hydrology, drainage3.8.23
Consequence attributesC1–C51–5 eachTrack, traffic, train type, what lies below, size of failure, redundancy3.8.23
Instability attribute and defect ratingL6, D1–5 eachPast failures; geometry defects, slow orders and field indicators (Table 3.8-10)3.8.24
Frequency indexF (preliminary Fp)1–5Geospatial frequency Fg (L1–L6 bounded by trigger rating T) with defect rating D, Table 3.8-11; desk D from records, field D from indicators3.8.22.2, 3.8.24, 3.8.25; 3.8.19
Hazard severityS (preliminary Sp)1–5Desk: C1–C5. Field: exposure confirmed in Block 13.8.22.3, 3.8.23
Live frequency indexFlive1–5F raised by live weather, river and ground data3.8.26
Risk scoreR = F × S1–25Product of the two scales; used only to place the site in a rating3.8.22.4
Risk rating—Low (1) to Severe (5)Risk matrix, Table 3.8-163.8.22.4

3.8.22.2 Frequency Index (F)

The frequency index describes the state of the hazard, which sets how often a failure can be expected. The worksheet calls this scale the Annual Failure Frequency Index. It is selected from the evidence of instability (Section 3.8.24); the indicative annual frequencies in Table 3.8-14 help when two levels seem to fit.

Table 3.8-14. Frequency index levels
LevelFField evidenceIndicative annual frequency of failure
Occurring5Failure under way: movement, settlement or erosion is active and the track is already affected; repeated slow orders or surfacing1 or more per year
Emerging4Clear signs developing: fresh tension cracks, a growing bulge, or geometry defects that return between surfacing cyclesAbout 1 in 1 to 1 in 5 years
Forming3Conditions for failure present (water against the embankment, an over-steepened slope, a blocked culvert), but the ground is not yet movingAbout 1 in 5 to 1 in 25 years
Dormant2Evidence of past instability, but no sign that it is active now; a trigger such as extreme rainfall could reactivate itAbout 1 in 25 to 1 in 100 years
Inactive1No evidence of instability, or the cause has been removedLess than 1 in 100 years

3.8.22.3 Hazard Severity (S)

The hazard severity describes the consequence if the failure happens. It is judged from the exposure of the site: traffic, speed, train type, the number of tracks, the population density factor and what lies below and beside the track. At the desk it comes from the consequence attributes of Section 3.8.23; in the field it is confirmed from Block 1 of the report. Where the consequence and the typical setting point to different levels, the consequence governs.

Table 3.8-15. Hazard severity levels
LevelSConsequence of failureTypical setting
Catastrophic5Derailment or loss of track support likely to cause fatalities, a hazardous materials release or loss of a structureMain line with passenger or hazardous materials traffic, over water, a road or a populated area; outage longer than a week
Critical4Derailment or main line outage likely; serious injury possible; major property damageMain line, moderate to heavy traffic; outage of several days
Serious3Track out of service or under a restrictive slow order; damage confined to railroad propertyMain line with light traffic, or busy siding; outage of hours to a day
Minor2Geometry defect needing surfacing or a temporary slow order; no derailment expectedSecondary, industry or yard track
Low1Maintenance-level effect only; no effect on train operationsAny track

Severity is a property of the site and what it carries, not of the weather or the state of the ground. It does not change in a live event (Section 3.8.26) and usually does not change when a site is stabilized; it changes only when the traffic, the track or the exposure changes.

3.8.22.4 Risk Score and Risk Matrix

The risk score is the product of the two scales:

R = F × S (1 to 25)

The score has one job: to place the site in one of five risk ratings. Table 3.8-16 gives the rating for every combination of F and S. Because R is a product, neither scale can be ignored: a Catastrophic site stays at Elevated or above until the cause is removed (Inactive), and a site with Low severity never rates above Guarded.

Table 3.8-16. Risk matrix: risk rating and risk score R = F × S
Frequency index (F)Hazard severity (S)
Catastrophic (5)Critical (4)Serious (3)Minor (2)Low (1)
Occurring (5)Severe25Severe20High15Elevated10Guarded5
Emerging (4)Severe20High16High12Elevated8Guarded4
Forming (3)High15High12Elevated9Elevated6Guarded3
Dormant (2)Elevated10Elevated8Elevated6Guarded4Low2
Inactive (1)Guarded5Guarded4Guarded3Low2Low1

The product weights F and S equally. The extra weight on consequence that Section 1.1.2 calls for comes from three rules for selecting S: the consequence floor in the situational rating (Section 3.8.23.6), “the consequence governs” (Table 3.8-15), and the engineer’s one-level adjustment (Section 3.8.22.6).

3.8.22.5 Risk Ratings and Required Response

Each rating carries a required response and a category from the risk resolution matrix of Section 1.1.7, so a site rated in this chapter can be carried directly into a railroad’s corridor-level risk register.

Table 3.8-17. Risk ratings, required response and Chapter 1.1 category
LevelRatingRisk score RRequired responseCategory (Section 1.1.7)
5Severe20–25Act now: on-site protection and operating restrictions; immediate stabilizationUnacceptable
4High12–16Act soon: slow order or increased inspection; stabilization in the next programUnacceptable
3Elevated6–10Plan: monitor, design and schedule stabilizationTolerable with Mitigation
2Guarded3–5Watch: routine inspection with defined trigger levelsTolerable with Mitigation
1Low1–2No action beyond routine inspectionTolerable

3.8.22.6 Applying the Rating

The same six steps are used whether the rating is made at the desk, on a live map or in the field. Only the source of F and S changes.

  1. Name the trigger. Write the trigger narrative and score the trigger rating T (Section 3.8.18).
  2. Select F as the current frequency Fc: the greater of the defect rating D and the geospatial frequency Fg capped at 3, raised one level where D ≥ 3 and Fg ≥ D + 1 (Table 3.8-11). At the desk this is the preliminary Fp of Section 3.8.24.3, using the defect rating from the records; in the field it is set from the field defect rating (Section 3.8.24.6); during an event it is the live Flive of Section 3.8.26, raised from Fc.
  3. Select S from the exposure (Table 3.8-15). At the desk this is Sp from the consequence attributes; in the field it is confirmed from Block 1 of the report.
  4. Compute R = F × S and read the rating from Table 3.8-16.
  5. Record F, S, R and the rating with a one-line reason for each level, so a reviewer can follow the rating.
  6. Adjust if warranted. The EIC may raise the rating by one level where the matrix understates the risk, for example where the field crew has no safe escape route, or where several nearby sites share the same trigger (the corridor effect of Section 1.1.7). Write the reason on the form. The rating is never set below the matrix value.

3.8.22.7 Rating the Alternatives

Each stabilization alternative is rated on the same matrix, as the site would be once that alternative is built. Most stabilization work lowers F by removing the cause (a drained embankment moves from Forming to Dormant or Inactive), while S usually stays the same because the track, traffic and setting do not change. An alternative that lowers S, such as track realignment away from the top of the slope, should say why. An alternative that leaves the site at High or above is at best an interim measure and should be labeled as one. Reading the current rating against the alternative ratings and the cost ranges of Section 3.8.42.6 gives the railroad the cost of each step of risk reduction.

Each alternative is rated in the three stages of Sections 3.8.37 to 3.8.39: the solution rating, as the site would be once the alternative works as intended (Section 3.8.37); the design rating earned by the design criteria, with a construction-stage rating for the risk while the work is built (Section 3.8.38); and the post-stabilization rating, provisional until the works have performed through a triggering event and are maintained, then verified (Section 3.8.39). The ratings in Table 3.8-18 are solution ratings; the field report carries them, and the design and post-stabilization ratings are added as each alternative is designed, built and verified.

Example 3.8-3: Culvert Fill Site, Part 1: Field Rating and Alternatives

A single main track runs on the outside of a curve, on a 25-ft fill across a creek floodplain. The site is rated on the report as found, and three stabilization alternatives are rated as the site would be once each works. One site carried through four examples: the field rating and its alternatives here, then the desk ratings that came before the visit in Sections 3.8.23 to 3.8.25.

Main track36-in. culvert, half blockedponded water (left)seepagetension cracks25 ftGiven25-ft fill, 2H:1V; 28 trains/day with hazmatCulvert half blocked; water 3 ft higher on leftSeepage mid-slope; fresh shoulder cracks4 cross level exceptions since last slow orderF​g = 4 (Section 3.8.24.7)RequiredTrigger T, defect rating D, F​c and SR and rating for the site as foundSolution ratings of three alternativesRecommendationBlack = given; red = required
Given and required for Example 3.8-3.

Given

VariableValueDescription
SiteSingle main track on a curve; 25-ft fill across a creek floodplainSetting
Traffic28 trains a day including hazardous materials; 50 mphExposure for S
Drainage36-in. culvert half blocked; water about 3 ft higher on the leftTrigger evidence
Field indicatorsSeepage at mid-slope; fresh tension cracks along the left shoulderDefect evidence
RecordsFour cross level exceptions since the last slow orderDefect evidence
Fg4Geospatial frequency from the desk (Section 3.8.24.7)
Alternatives1: clear culvert and regrade ditches; 2: Alternative 1 plus lateral drains and toe berm; 3: soldier piles and laggingTo be rated

Required

  • Trigger rating T, defect rating D, current frequency index Fc and severity S
  • Risk score R and rating as found
  • Solution rating of each alternative
  • The recommendation

Equations

  1. Eq. 1: Fc from Fg and D — Table 3.8-11 (Equation 3.8-3)
  2. Eq. 2: R = F × S — risk score
  3. Eq. 3: Rating = matrix(F, S) — Table 3.8-16

Steps

Step 1 · Trigger
Uses: Drainage evidence
A storm exceeding the half-blocked culvert ponds water against the left embankment in most wet years
T = 4
Spot check: Ponding in most wet years is a return period of a few years, inside the level 4 band of Table 3.8-9.
↓
Step 2 · Defect rating and current frequency (Table 3.8-11)
Uses: Field indicators, records, Fg
Fresh cracks and defects returning between surfacing cycles: D = 4 (Recurring); row Fg = 4, column D = 4
Fc = 4, Emerging
Spot check: D equals Fg, so the defects govern and no amplification applies (Fg is not ≥ D + 1).
↓
Step 3 · Severity (Table 3.8-15)
Uses: Traffic, setting
Main line outage with derailment possible, moderate traffic, not over a populated area
S = 4, Critical
Spot check: Hazardous materials traffic alone does not make it Catastrophic; the setting below the fill is a creek and farmland.
↓
Step 4 · Risk score and rating (Table 3.8-16)
Uses: Fc, S
R = 4 × 4
R = 16, High
Spot check: 16 lies in 12–16; 4×4 is High, not Severe (Table 3.8-75).
↓
Step 5 · Solution ratings (Section 3.8.37.2)
Uses: Alternatives
Alt. 1 removes the trigger only; D stays 4 → F = 4, R = 16. Alt. 2 drains the fill and adds resistance; D expected 1, Fg = 1 → F = 1, R = 4. Alt. 3 adds resistance: F = 1, R = 4
16 High (interim); 4 Guarded; 4 Guarded
Spot check: Every alternative keeps S = 4: none changes what a failure would reach.
↓
Solution
As found: 16 High. Alt. 1: 16 High (interim). Alts. 2 and 3: 4 Guarded.

Solution

Table 3.8-18. Worked example: ratings as recorded on the report
ConditionFrequency indexHazard severityRRating
Current conditionEmerging (4)Critical (4)16High
Alternative 1: clear culvert and regrade ditches (interim)Emerging (4)Critical (4)16High
Alternative 2: Alternative 1 plus lateral drains and toe bermInactive (1)Critical (4)4Guarded
Alternative 3: soldier piles and lagging along the shoulderInactive (1)Critical (4)4Guarded

The site rates High (Emerging 4 × Critical 4 = 16). Alternative 1 stays High and is an interim measure; Alternatives 2 and 3 both reach Guarded (4).

Alternative 1 is quick and inexpensive and removes the ponding, but the fill is already cracked and the defects are recurring (D = 4). Removing the trigger alone does not earn a lower defect rating, so its solution rating stays High (Section 3.8.37.2). If a wet season then passes with no movement, its post-stabilization rating can fall to Dormant and Elevated (R = 8), the same treatment the clean-culvert alternative receives in Section 3.8.41. Alternative 2 costs less than Alternative 3 and is built in about 3 months, against more than a year (Section 3.8.42.8). The recommendation is Alternative 1 now, followed by Alternative 2.

The same site is followed through the desk in Sections 3.8.23 to 3.8.25, to show how its preliminary rating is assembled before the visit. With the scales defined, the next section turns to the first input: what the site’s location and inherent conditions make possible.

3.8.23 Situational Ratings: Location and Inherent Site Conditions

The situational rating describes what the site’s location and inherent physical conditions make possible, before any evidence of movement is considered. Two embankments may both look sound today, yet one is a 30-ft fill of plastic clay with a river against its toe and the other a 6-ft fill of clean gravel on level ground. The situational rating separates them. It answers two of the questions a desktop study must answer: what is the site, and what could fail, and why.

The situational rating has two halves. The situational likelihood (attributes L1 to L5) scores how susceptible the ground is to failure because of its soils, geology, slope geometry, water and drainage. The consequence (attributes C1 to C5) scores what a failure would reach because of the track, the traffic and what lies below and beside it. Both are fixed by where the site is and how it was built; neither depends on whether the ground is moving now. That is the subject of the instability rating in Section 3.8.24.

The situational rating is made at the desk, before anyone goes on track. For a single urgent site it can be done in an afternoon; for a program of dozens of sites it is done for all of them first, so that field time goes where the risk is.

3.8.23.1 Data Sources

Start with the railroad’s own records; they are the only source of track structure, construction history and drainage inventory. Then build the site picture from public data. The hazard monitoring map assembles most of the public layers in Table 3.8-19 for a site circle and can generate a Site Background Report with a KMZ of the layers used. The railroad’s defect, slow order and repair records, and the event and ground movement layers, are used in the instability rating (Section 3.8.24); they are listed here because they are collected in the same pass.

Table 3.8-19. Desktop data sources and the rating each one feeds
CategoryTypical sourcesWhat it showsFeeds
Railroad recordsTrack charts and valuation maps; track geometry exception reports; slow order history; maintenance, surfacing and ballast records; drainage structure inventory; past reports and photos; inspector and roadmaster notesTrack, curvature, grade, original construction, fill and cut limits, defect frequency, what has been repaired and whenSituational (setting, C1–C5); Instability (L6, defect history)
TopographyUSGS 3DEP lidar and elevation models; hillshade and slope maps; historic topographic mapsFill and cut heights, slope angles, scarps, hummocky ground, drainage paths, channel position relative to the toeSituational (L3); Instability (scarps for L6)
Geology and soilsState geologic maps; NRCS soil survey (SSURGO); USGS landslide inventory and susceptibility; karst maps; abandoned mine land and mine map inventoriesSoil type and drainage class, shrink-swell, depth to rock, landslide-prone formations, karst, underminingSituational (L1, L2)
HydrologyFEMA flood maps (NFHL); NHD and StreamStats drainage areas; NOAA Atlas 14 rainfall; dam inventory (NID); river gauges and high-water marksFloodplain position, contributing drainage area, design rainfall, upstream dams, how high water has actually reachedSituational (L4, H&H thresholds); Live (gauge pairing)
ImageryHistorical aerial photographs; Google Earth historical imagery; NAIP; Sanborn mapsChanges in channel, drainage, vegetation, slope face and adjacent land use over timeSituational (L5, setting); Instability (L6)
Event historyNOAA Storm Events and local storm reports; NWS damage surveys; FRA accident and incident data; USGS high-water marks; ice jam database; FEMA disaster declarationsFloods, washouts, slides, storms and rail accidents near the site, with datesInstability (L6); H&H thresholds
Current conditionsSoil moisture percentile; antecedent rainfall; frost depth; drought monitor; river stageWhether the ground is wetter or the river higher than normal nowLive rating; timing of the field visit
Ground movementSatellite radar (InSAR) displacement where availableMeasured settlement or creep since 2016Instability (L6)

3.8.23.2 Site Setting and Construction History

Most ground hazards on a railroad are the delayed result of how the line was built, so the situational review begins with the setting and its history, oldest first.

  1. Original construction. From the valuation maps and historic topographic maps, establish whether the track is on fill, in cut or on a sidehill bench, what the ground was before the railroad, and where the original drainage crossed. Fills placed across hollows and over old channels are the usual seat of later trouble.
  2. Changes since. Line changes, added tracks, widened shoulders, replaced or extended culverts, and new development uphill or upstream. Compare successive aerial photographs for channel migration toward the toe, new impervious area, ponding and beaver dams.
  3. Track setting. Record the track cross section (cut or fill), the alignment (tangent, inside or outside of a curve) and the setting (marsh, valley, or slope: top, mid or bottom). These point toward the likely mechanism: a fill on the outside of a curve on a mid-slope bench fails differently from a cut on a valley floor (Section 3.8.3).

The record of what has already gone wrong at the site (past slides, repairs, defects and the events that triggered them) completes the history, but it is evidence of instability rather than situation and is reviewed in Section 3.8.24.

3.8.23.3 Driving Mechanism

From the setting and the terrain, assign the driving mechanism: the process most likely to cause failure. It decides which situational attribute carries the most weight (Section 3.8.23.4), which H&H thresholds are needed (Section 3.8.23.7), which live indicators apply (Section 3.8.26) and which stabilization items to expect in the field (Section 3.8.42). The mechanisms follow Chapter 3.8:

  • Slope-driven: rotational or translational sliding of the embankment, cut or natural slope.
  • Scour-driven: stream or river flow removing support at the toe or around a structure.
  • Drainage-driven: water held against or within the fill by blocked, undersized or failed drainage; piping and softening.
  • Subgrade-driven: settlement, pumping or loss of bearing in the track foundation.
  • Subsidence-driven: karst, mining or collapsible soils.
  • Rock and debris: rockfall, debris flow or slides from above the track.

Where two mechanisms act together (for example, scour that oversteepens the toe and then a slope failure), record both and name the one that starts the sequence as primary. The instability evidence gathered in Section 3.8.24 may confirm or change this choice; the field visit settles it.

3.8.23.4 Situational Likelihood (L1 to L5)

The situational likelihood is deterministic: each attribute is scored 1 to 5 against the fixed descriptions in Table 3.8-20, so two engineers working from the same data reach the same score. Score from the evidence in hand; where the data are missing, score 3 and flag the attribute for the field visit. Scores of 2 and 4 fall between the descriptions; written descriptions for them are in Table 3.8-76 (Section 3.8.36.5).

Table 3.8-20. Situational likelihood attributes and scoring
AttributeScore 1Score 3Score 5Main sources
L1 Surficial soilsRock, or clean, well-drained sand and gravelSilty or clayey sand, low-plasticity silt or clay; moderately drainedHigh-plasticity or organic clay, loess, sensitive or collapsible soil; poorly drained; softens when wetSoil survey, geologic map, past boring logs
L2 Geologic settingCompetent rock at or near the surfaceWeathered rock or till at moderate depthDeep weak overburden, colluvium, mapped landslide-prone formation, karst or underminingGeologic map, landslide inventory, karst and mine maps
L3 Slope geometryFill or cut under 10 ft, slopes flatter than 3H:1VFill or cut 10 to 30 ft, or slopes about 2H:1VFill or cut over 30 ft, slopes steeper than 1.5H:1V, or a sidehill fillLidar, track charts
L4 HydrologyNo contributing flow; well above any floodplainDitch or small-stream flow along the toe; in or near a 500-year floodplainStream or river against the toe; in the 100-year floodplain; convergent flow or ponding against the fillFlood maps, drainage area, imagery, gauges
L5 Drainage conditionDitches and culverts free-draining and adequatePartly obstructed ditches or an aging culvert; some sedimentBlocked or undersized culvert, no outlet control, record of overtopping, beaver activityDrainage inventory, imagery sequence, maintenance records

For L3, score height and steepness separately and use the higher. Each attribute carries a weight of 1, except the attribute that matches the driving mechanism, which carries a weight of 2: L4 for scour-driven, L5 for drainage-driven, L3 for slope-driven, L1 for subgrade-driven, and L2 for subsidence-driven or rock and debris. The situational likelihood is the weighted average:

LS = Σ (wi · Li) / Σ wi, i = 1 to 5

LS is kept to two decimals; it is combined with the instability attribute in Section 3.8.24 before any rounding.

3.8.23.5 Consequence (C1 to C5)

The consequence attributes describe what a failure would do. They are the situational half of the rating that sets hazard severity, and they draw on the exposure that will be confirmed in Block 1 of the report (Section 3.8.42.4).

Table 3.8-21. Consequence attributes and scoring
AttributeScore 1Score 3Score 5
C1 Track and trafficIndustry, yard or out-of-service trackMain line with light traffic, or a busy sidingMain line with heavy tonnage or high speed; multiple main tracks
C2 Train typeNo passenger or hazardous materials trafficOccasional hazardous materialsPassenger trains or a key hazardous materials route
C3 Below and beside the trackOpen land on railroad propertyA road, a small stream or farmlandA river, highway, dwellings, utilities or a water supply
C4 Size of failureFill under 5 ft; failure would be shallowFill 10 to 20 ftFill over 30 ft, or a culvert or structure under high fill
C5 Redundancy and recoveryParallel route; repair within a shiftDetour available; repair in daysNo detour; difficult access; outage longer than a week

3.8.23.6 Preliminary Hazard Severity (Sp)

The consequence value C is the average of C1 to C5, with one floor: a 5 on C2 or C3 sets C at no less than 4, because a failure that can reach passengers, a hazardous materials release or the public governs regardless of the other attributes. Round C half up (2.5 becomes 3) to the nearest whole number to give the preliminary hazard severity Sp on the scale of Table 3.8-15. Sp is the situational rating’s contribution to severity; it is carried unchanged into the static rating (Section 3.8.25) and printed on the report for the EIC to confirm.

3.8.23.7 Hydrology and Hydraulics Thresholds

For every site whose driving mechanism involves water (scour, drainage, and most slope and subgrade failures), the situational review also sets the site’s water thresholds: the conditions at which this particular embankment, culvert or toe starts to be loaded beyond what it normally carries. They are a property of the location, like the attributes above, and they are what make a live rating possible (Section 3.8.26): live weather and river data mean little until they are compared with what the site can take.

Table 3.8-22. Hydrology and hydraulics thresholds set in the desktop study
ThresholdHow it is setSources
Paired gauge and toe stageChoose the nearest gauge on the same stream that responds to the same storms. Relate its stage to the elevation of the embankment toe, the culvert outlet and the lowest point of the subgrade, from lidar and, where available, surveyed high-water marks. Record the gauge stage at which water reaches the toe (toe stage) and the stage at which damage has occurred (damage stage).NWS and USGS gauges, flood categories, lidar, high-water marks, railroad event records
Culvert capacity stormFrom the drainage area, time of concentration and the culvert size and condition, estimate the return period the culvert passes without heading up against the fill (culvert hydrology, Section 3.5.10). Convert it to a rainfall depth for the critical duration (typically 1 to 24 hours) with Atlas 14.StreamStats or lidar drainage area, drainage inventory, NOAA Atlas 14
Site rainfall thresholdThe 24-hour rainfall at or above which the site has historically responded (defects, slow orders, slides, overtopping). Where there is no history, start at the 2-year 24-hour Atlas 14 depth, or the culvert capacity storm if that is lower.Event and defect history matched against rainfall records; Atlas 14
Antecedent wetnessThe soil moisture percentile or 30-day rainfall (percent of normal) that preceded past failures. Where there is no history, use the 80th soil moisture percentile.Soil moisture percentile, antecedent rainfall
Freeze-thaw and snowmeltFor northern sites, whether the site has failed during thaw or rain-on-snow, and the frost depth or snowpack that preceded it.Frost depth, freezing index, snow water equivalent

The thresholds are first estimates. They are printed on the report so the field visit can check the toe, outlet and culvert elevations, and every later event refines them (Section 3.8.26.6).

3.8.23.8 Example: Situational Rating

Example 3.8-4: Culvert Fill Site, Part 2: Situational Rating at the Desk

The site of Example 3.8-3, scored at the desk before the visit from lidar, the soil survey, an old boring, the floodplain map and imagery.

Main track36-in. culvert, half blockedponded water (left)seepagetension cracks25 ftGivenLidar: 25-ft fill, about 2H:1VSoil survey and old boring: lean clay overalluvium and weathered shaleCreek against the left toe; 100-yr floodplainImagery: ponding upstream of the culvertRequiredDriving mechanism and L5 weightSituational likelihood L​SConsequence C and preliminary S​pBlack = given; red = required
Given and required for Example 3.8-4.

Given

Table 3.8-23. Example situational scores
AttributeScoreWeightBasis
L1 Surficial soils41Lean clay that softens when wet
L2 Geologic setting31Alluvium over weathered shale at moderate depth
L3 Slope geometry3125-ft fill, slopes about 2H:1V
L4 Hydrology51Creek against the toe; 100-year floodplain
L5 Drainage condition42Culvert half blocked; ponding seen in imagery
LS = (4 + 3 + 3 + 5 + 2 × 4) / 6 = 23 / 6 = 3.83
C1 Track and traffic4—Main line, 28 trains a day
C2 Train type4—Regular hazardous materials traffic
C3 Below and beside3—Small stream and farmland
C4 Size of failure4—Fill 20 to 30 ft
C5 Redundancy3—Detour available; repair in days
C = (4 + 4 + 3 + 4 + 3) / 5 = 3.6; no floor applies (no 5 on C2 or C3); Sp = 4, Critical

Required

  • The driving mechanism and the weight on L5
  • The weighted situational likelihood LS
  • The consequence C and the preliminary severity Sp

Equations

  1. Eq. 1: LS = Σ(wi Li) / Σwi — weighted situational likelihood
  2. Eq. 2: C = (C1 + C2 + C3 + C4 + C5) / 5 — consequence, before the floor rule
  3. Eq. 3: Sp = round(C), with the C floor — preliminary severity (Section 3.8.23)

Steps

Step 1 · Driving mechanism
Uses: Imagery, hydrology
Water held against the fill is the likely cause
Drainage-driven; L5 weighted 2
Spot check: The weight goes to the attribute that names the mechanism (Section 3.8.23).
↓
Step 2 · Situational likelihood (Eq. 1)
Uses: L1–L5 from the table
LS = (4 + 3 + 3 + 5 + 2 × 4) / 6 = 23 / 6
LS = 3.83
Spot check: Divide by the sum of the weights, 6, not by the 5 attributes.
↓
Step 3 · Consequence (Eq. 2)
Uses: C1–C5 from the table
C = (4 + 4 + 3 + 4 + 3) / 5 = 18 / 5
C = 3.6
Spot check: No 5 on C2 or C3, so the C floor of Section 3.8.23 does not apply.
↓
Step 4 · Preliminary severity
Uses: C
3.6 rounds to 4
Sp = 4, Critical
Spot check: Matches the field severity of Example 3.8-3, S = 4.
↓
Solution
LS = 3.83; Sp = 4 (Critical).

Solution

Drainage-driven mechanism; LS = 3.83; C = 3.6, giving Sp = 4, Critical. On its situation alone, this is a susceptible site carrying a Critical consequence. What the situation cannot say is whether the ground has started to move. That is the job of the instability rating (Example 3.8-5).

3.8.24 Instability Ratings: Evidence That the Ground Is Moving

The situational rating says what a site could do. The instability rating says what it has done and is doing: past failures and repairs, track geometry defects that keep coming back, and the cracks, bulges, seeps and voids that the engineer sees on the ground. Past movement is the best single predictor of future movement, and present movement is direct proof that the frequency index is high. The instability rating therefore governs the frequency index: it supplies the defect rating D that, with the geospatial frequency, sets the current frequency index (Table 3.8-11) at the desk and in the field.

The instability rating is assembled in two passes. The desk pass reads the railroad’s records and the public event and movement data (Section 3.8.24.1 to 3.8.24.3). The field pass is made by the EIC on site, in Blocks 2 and 3 of the report (Sections 3.8.24.4 and 3.8.24.5), and turns what is seen into the field frequency index (Section 3.8.24.6).

3.8.24.1 Instability Record

Continue the site history begun in Section 3.8.23.2, still oldest first, with the record of what has gone wrong:

  1. Instability record. Past slides, washouts, repairs, berms, riprap, drains and slow orders. Lidar hillshade often shows old scarps and lobes that never made it into the records, and InSAR, where available, shows whether the ground has moved since 2016.
  2. Defect record. Geometry exceptions (cross level, profile, alignment, warp) at the site, their frequency, and whether they return between surfacing cycles.
  3. Triggering events. Match the dates of failures and defects against rainfall, flood stage, snowmelt and freeze-thaw. A site that fails after every high-water event has a different driving mechanism, and a different fix, from one that fails after long wet spells. These matches also calibrate the H&H thresholds of Section 3.8.23.7.

3.8.24.2 Historic Instability (L6) and Defect History

The instability record is scored on one attribute, L6, using the same 1-to-5 convention as the situational attributes, and the defect history is scored as the defect rating D of Chapter 3.8.

Table 3.8-24. Instability attribute and defect rating
ItemScore 1 / no changeScore 3Score 5 / raise one levelMain sources
L6 Historic instabilityNo evidence of movementPast repair at the site, or mapped instability nearbyRepeated documented failure, a scarp visible in lidar, or measured movementRailroad records, lidar, landslide inventory, InSAR
Defect rating D1: no defects in the record and no indicators3: defects reported more than once but not returning between cycles, or indicators without progress5: defects returning within weeks of surfacing; standing slow order. 4: the same defect returns between surfacing cycles, or a slow order in the last 12 months (Table 3.8-10)Track geometry exception reports, slow order history, surfacing records

This table scores the defect rating at the desk from the records. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.

Scores of 2 and 4 for L6 are described in Table 3.8-76. Defects are scored as a separate rating rather than as an attribute because they are direct evidence that the ground is moving now; they outweigh what the terrain alone suggests, so they act on the frequency index through Table 3.8-11 instead of being diluted in the average.

3.8.24.3 Preliminary Frequency Index (Fp)

The preliminary frequency index combines the situational likelihood with the instability attribute. L6 carries a weight of 1 and is added to the weighted situational attributes:

L = [ Σ (wi · Li)i = 1 to 5 + L6 ] / [ Σ wi + 1 ]

Round L half up (2.5 becomes 3) to the nearest whole number, then bound it by the trigger rating to give the geospatial frequency Fg = the lesser of L and T (Equation 3.8-2). The preliminary frequency index Fp is read from Table 3.8-11 using Fg and the defect rating D scored from the railroad's records. The situational and instability contributions (LS, L6, L), T and D are kept separately so they can be seen, and printed, on the report.

Susceptibility is not activity. Fg comes mostly from susceptibility, while D describes activity. Without defects or indicators (D of 1 or 2), Fp cannot exceed Forming (3), however susceptible the site; a high Fg with no defects is a reason to visit early, not evidence that the ground is moving.

3.8.24.4 Field Indicators of Instability (Report Block 2)

On site, the instability rating is completed from what the ground and the track are showing. Block 2 of the report is a checklist of indicators, recorded separately for the left embankment, the track between the rails and the right embankment. The embankment lists are the same on both sides. The between-rails list records the track geometry defects and track structure symptoms that brought the engineer to the site.

Table 3.8-25. Field indicators of instability
Left and right embankmentBetween the rails
Upper slope bulge, tension crack or seepageReported cross level (measurement and frequency)
Mid-slope bulge, tension crack or seepageReported profile (measurement and frequency)
Lower slope bulge, tension crack or seepageReported alignment (measurement and frequency)
Standing water in ditch or at toe of slopeReported warp (measurement and frequency)
Obstruction in ditchFouled ballast or water between cribs
Culvert dry, obstructed or damagedTie shift
Water level higher than on the opposite sideVoids between cribs
ErosionShoulder narrower than 12 in.

Orient and walk the site. Stand on the track centerline facing up station (increasing milepost); the left embankment column is on your left and the right on your right, so “left” and “right” mean the same thing to everyone who reads the form. Walk each embankment from the top of slope to the toe, then check the ditch and toe, each culvert, the water level against the opposite embankment, and erosion. Between the rails, enter each reported defect with its measurement (the defect value, in inches, from the geometry car or track inspector) and its frequency (how often it has been reported or corrected, for example “surfaced 3 times since May”), then mark the track structure symptoms you can see. Photograph every marked indicator with a scale and the milepost in the frame, and write the photo number beside the entry.

Read the pattern, not the item. A single indicator rarely decides the case; the combination does. Typical patterns are:

  • Upper slope tension cracks with a mid- or lower slope bulge on one side, and recurring cross level and alignment defects: rotational or translational slope movement through the embankment or its foundation (Section 6.3.2).
  • Seepage on the slope, standing water at the toe and a higher water level on one side: a drainage or seepage problem, often a blocked or undersized culvert ponding water against the embankment (Chapter 2.8; Section 3.8.4).
  • Fouled ballast, water between the cribs, voids and profile defects with no slope indicators: a track substructure problem such as subgrade pumping, ballast pockets or poor drainage within the section (Chapter 2.3).
  • A shoulder narrower than 12 in., erosion and tie shift: loss of lateral support at the edge of the section.

Defect frequency is the best single field measure of how fast the condition is developing, and it is the main evidence for the field frequency index. Record it exactly as the railroad reports it.

3.8.24.5 Site Instabilities (Report Block 3)

Block 3 records what is failing, what will make it hard to fix, and how it is expected to fail.

Table 3.8-26. Site instabilities
Major elementConstruction constraintEstimated failure type
BallastAccess and mobilityBearing capacity
SubgradeRailroad workload conflictSlope
ForeslopePropertySettlement
BackslopeMaterialWashout
Bridge abutmentUnderground obstructionsSubsidence
CulvertWater sourceSurface erosion
DitchPermitStream and wave erosion
Adjacent propertyEnvironmentalUnderground flow erosion

Major element is the part of the roadbed or structure whose failure threatens the track. More than one may apply; number them with the governing element as 1.

Estimated failure type is the engineer’s field judgment of the mechanism. Mark one as primary; a second may be marked as contributing. Compare it with the driving mechanism assigned at the desk (printed in the Desktop Study Summary of the report) and note any change. The exploration and analysis scoped in Block 5 confirm or revise it, and it sets which analyses are required (Section 3.8.42.8). Section 3.8.13 shows how to work from the symptom back to the mechanism.

Construction constraints are not part of the rating, but they are recorded here, while the access, the right-of-way and the utilities are in view, because they often decide which alternative is practical. Equipment access, track time (railroad workload conflict, confirmed with the railroad contact), right-of-way and adjacent property, the supply of fill and aggregate, buried utilities, a construction water source, permits and environmental restrictions can each rule out an otherwise sound fix. A toe berm that needs property the railroad does not own, or a sheet pile wall that needs a crane on a single-track main line with no work windows, is not a practical alternative.

3.8.24.6 Setting the Field Frequency Index

In the field the EIC does not recompute L. The EIC confirms the trigger and T, sets the field defect rating D from the instability evidence (Table 3.8-27, which matches Table 3.8-10), and reads the current frequency index Fc from Table 3.8-11 using the geospatial frequency Fg printed on the report. Fc is the field F. The preliminary Fp is printed beside it as a check.

Table 3.8-27. Instability evidence and the field defect rating
Instability evidence (Blocks 2 and 3, desk record)Field defect rating D
Active movement, settlement or erosion affecting the track now; repeated slow orders or surfacing; defects recurring faster than surfacing can hold5 Active
Fresh tension cracks or a growing bulge; geometry defects that return between surfacing cycles; the track still runs at or near normal speed4 Recurring
No sign of movement, but the conditions for it are present: water ponded against the fill, seepage, a blocked culvert, an over-steepened or eroding slope3 Present
Old scarps, past repairs or a documented failure (L6 of 3 or more), but no fresh indicators and no recurring defects2 Historic
No indicators, no instability record, or the cause has been removed1 None

This table sets the defect rating in the field from what is seen. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.

Where the field F differs from Fp by more than one level, write the reason on the report. Those notes are how the desktop attributes and thresholds are calibrated over time.

3.8.24.7 Example: Instability Rating

Example 3.8-5: Culvert Fill Site, Part 3: Instability Rating

Continuing Example 3.8-4: the site's record of past movement and its track defects are added to its situation, first at the desk and then on the field visit.

Main track36-in. culvert, half blockedponded water (left)seepagetension cracks25 ftGivenWeighted sum of L1–L5 = 23 (weights 6)Shoulder slump repaired 12 yr ago4 cross level exceptions, returning between cyclesTrigger T = 4Field: seepage, cracks, track at normal speedRequiredL6 and overall LF​g, desk D and F​pField D and F​cBlack = given; red = required
Given and required for Example 3.8-5.

Given

VariableValueDescription
ΣwiLi, Σwi23; 6From Example 3.8-4
Repair recordShoulder slump repaired with fill and riprap 12 years agoEvidence for L6
Geometry recordFour cross level exceptions since the last slow order, returning between surfacing cyclesDesk evidence for D
T4Storm exceeding the half-blocked culvert ponds water in most wet years
Field findingsSeepage at mid-slope; water 3 ft higher on the left; culvert half blocked; fresh tension cracks; track at normal speed, no slow orderField evidence for D

Required

  • The instability attribute L6 and the overall likelihood L
  • The geospatial frequency Fg, the desk defect rating and the preliminary Fp
  • The field defect rating and Fc

Equations

  1. Eq. 1: L = (ΣwiLi + L6) / (Σwi + 1) — overall likelihood (Equation 3.8-2)
  2. Eq. 2: Fg = lesser of (L, T) — geospatial frequency bounded by the trigger
  3. Eq. 3: Fc from Fg and D — Table 3.8-11 (Equation 3.8-3)

Steps

Step 1 · Historic instability
Uses: Repair record
A documented failure within about 20 years
L6 = 4
Spot check: A single repaired slump is 4, not 5; 5 needs repeated failure or measured movement (Table 3.8-24).
↓
Step 2 · Overall likelihood (Eq. 1)
Uses: ΣwiLi, L6
L = (23 + 4) / (6 + 1) = 27 / 7
L = 3.86 → 4
Spot check: Adding a 4 to an average of 3.83 can only move it toward 4.
↓
Step 3 · Geospatial frequency (Eq. 2)
Uses: L, T
Fg = lesser of (4, 4)
Fg = 4
Spot check: The trigger does not cap it here, because T = L.
↓
Step 4 · Desk defect rating and Fp (Eq. 3)
Uses: Geometry record
Recurring defects in the records: D = 4; Table 3.8-11, row 4, column 4
Fp = 4
Spot check: D = Fg, so the defects govern without amplification.
↓
Step 5 · Field defect rating and Fc (Eq. 3)
Uses: Field findings
Fresh cracks and recurring defects confirm D = 4; no slow order yet, so not 5
Fc = 4, Emerging, the same as Fp
Spot check: D = 5 needs a standing slow order or defects returning within weeks (Table 3.8-10).
↓
Solution
Fp = Fc = 4 (Emerging).

Solution

L6 = 4; L = 3.86 → 4; Fg = 4; D = 4 at the desk and in the field; Fp = Fc = 4, Emerging. The desk rating predicted the field rating: the records already showed the recurring defects that the visit confirmed.

The site now has a situational severity and an instability-based frequency index. Section 3.8.25 combines them into the static rating that ranks the site under usual conditions.

3.8.25 Static Hazard Ratings: Network Exposure and the Preliminary Rating

A static hazard rating describes a site or segment under its usual, long-term conditions. It is built from information that changes slowly, if at all: where the line runs, what it is built on, what it carries, and its record of past trouble. Static ratings are used to choose which segments get a desktop study, to rank sites for field assessment, and to set the baseline that the live rating (Section 3.8.26) raises during weather events. They change only when new information arrives: a new data release, a field visit, a repair or a new failure.

Two static ratings are used, at two scales:

  • Network exposure: an index such as the FRA Composite Hazard Index that scores every segment of a rail network for its exposure to natural hazards. It ranks segments, not sites, and comes before the desktop study.
  • The preliminary site rating: the product of the situational and instability ratings of Sections 3.8.23 and 3.8.24, read from the risk matrix. It ranks individual sites and sets the timing and effort of the field assessment.

3.8.25.1 Network Exposure: FRA Composite Hazard Index (CHI)

The Federal Railroad Administration introduced the Composite Hazard Index (CHI) to short line and regional railroads in an American Short Line and Regional Railroad Association (ASLRRA) webinar, Evaluating Railroad Infrastructure Exposure to Natural Hazards Using FRA’s Composite Hazard Index. The CHI is a screening index: it combines several natural hazard measures into one value for each segment of the rail network, so that segments can be compared and ranked by their exposure.

Underlying data. The federal hazard exposure data released for the rail network show what such an index is built from. The Bureau of Transportation Statistics (BTS) Hazard Exposure: Select North American Rail Network Lines layer (beta, October 2025) attaches hazard values to every main line and operational line segment of the North American Rail Network, across the 50 states and the District of Columbia. For each segment it carries:

  • Weather and climate hazards: the annualized frequency of coastal flooding, riverine flooding, cold wave, drought, hail, hurricane, heat wave, ice storm, lightning, strong wind, tornado and winter weather, from the FEMA National Risk Index.
  • Ground hazards: a USGS landslide index (maximum and median along the segment) and a USGS sinkhole susceptibility index.
  • Wildfire: USDA Forest Service burn probability (maximum, mean and minimum).
  • Storm surge: whether the segment is inundated by a Category 1 to 5 hurricane in NOAA’s SLOSH model.
  • Floodplain: presence in the FEMA flood hazard layer.

The BTS layer reports each hazard separately and does not combine them; the CHI does the combining. At the time of writing, FRA had not published the CHI method (which inputs are used, how each is normalized and how they are weighted) in a form available for review. Before relying on a CHI value, confirm its inputs and weighting against FRA’s documentation.

Related research. A companion approach links recorded events, rather than modeled likelihood, to rail segments. Researchers at Oregon State University, working through the Mineta Transportation Institute, assigned flood, landslide and extreme heat and cold events from 2000 to 2023 to individual segments (flash floods by watershed hydrologic unit, riverine floods by river corridor, heat and cold by NWS forecast zone, landslides by proximity to the track) and checked the result against FRA accident records with weather-related cause codes, such as T002 for washout, rain, slide or flood damage to track. Their dataset is public and gives each segment a count of the events it has actually experienced. Where it is available, that count is the network-scale counterpart of the instability rating.

What the CHI does well. It covers the whole network on one consistent basis, needs no site work, and puts weather, flood, wildfire and ground hazards on the same footing. That makes it well suited to choosing which subdivisions and segments get a desktop study first, and to showing a funding agency that a line is more exposed than most.

What it cannot do. It describes exposure, not condition:

  • It knows nothing of the track structure: fill height, slope angle, culvert size and condition, or ballast and subgrade condition (the situational attributes of Section 3.8.23).
  • It knows nothing of defect history, slow orders or past repairs, which are the strongest evidence of where the ground is moving (the instability rating of Section 3.8.24).
  • Most of its inputs are regional. The National Risk Index frequencies are computed for census tracts and counties, so a short segment inherits the value of the area around it. A 40-ft fill over an undersized culvert and a stretch of level track in the same tract score alike.
  • Several hazards that dominate railroad ground failures are missing or only implied: scour at bridges and culverts, drainage failure, frost and freeze-thaw, rockfall and seismic shaking.
  • It is static. It does not say whether the river is high or the ground saturated today; that is the job of the live rating (Section 3.8.26).

3.8.25.2 Network Exposure Compared with Site Ratings

The CHI works from the network down; the situational, instability and live ratings work from the site and its trigger up. They answer different questions and are best used together. Table 3.8-28 compares them.

Table 3.8-28. FRA Composite Hazard Index compared with site-based ratings
AspectFRA Composite Hazard Index (network static)Situational and instability ratings (site static)River gauge monitoring (live)
Question answeredWhich segments of the network are most exposed to natural hazards?What makes this site susceptible, and what has happened here?Is a water trigger happening now, or forecast, at this site?
Spatial unitRail network segment; hazard values mostly from tract, county or regional gridsSite circle or affected limitsGauge point, applied to the sites paired with it
Time basisLong-term: annualized frequency and modeled likelihood; static between releasesHistorical record plus railroad records; static between visitsReal time (typically every 15 minutes to hourly) with NWS forecasts
Hazards coveredWeather and climate hazards, riverine and coastal flooding, wildfire, landslide index, sinkholes, storm surgeGeology, soils, slope, landslides, karst, mines, flooding, drainage, storms, frost, ground moisture, accidentsRiverine flooding, scour, backwater; ice jams where reported
Railroad condition and defectsNot includedIncluded, from railroad records (L6 and defect history)Not included
OutputOne index value per segment, for rankingAttribute scores, Fp, Sp and a preliminary ratingStage and flow against flood categories and percentiles; live rating
EffortLow: look-upModerate: analyst time for each siteLow once set up; thresholds need calibrating
Main limitationExposure, not condition; regional resolution; method to be confirmedStarts from flagged sites; depends on map scale and record completenessPoint measurement; ungauged drainages; water triggers only

Using them together.

  1. Screen the network. Use the CHI, or the BTS hazard exposure values and the segment event counts where the CHI is not available, to rank segments. Add the railroad’s own lists: recurring geometry defects, slow orders and patrol reports. A segment high on either list goes forward.
  2. Rate each site at the desk. Score the situational and instability attributes for each site on the forwarded segments (Sections 3.8.23 and 3.8.24) and give it a preliminary rating (Section 3.8.25.3).
  3. Pair with a trigger. Pair each water-sensitive site with a gauge, a rain gauge or a rainfall product, and load its static rating and thresholds into the live rating (Section 3.8.26).
  4. Assess in the field. Visit and rate the site on the Ground Hazard Risk Assessment Report (Section 3.8.42).
  5. Feed back. After each event, record the gauge reading or rainfall and what happened at the site. A site that responds below its threshold has its threshold lowered and its frequency index reviewed; a segment that keeps producing events moves up the screening list regardless of its index.

3.8.25.3 The Preliminary Site Rating

The preliminary site rating brings the two desk ratings together on the matrix of Table 3.8-16:

Rp = Fp × Sp

where Fp is read from Table 3.8-11 using the geospatial frequency (situational and instability attributes bounded by the trigger rating) and the defect rating from the records (Section 3.8.24.3) and Sp from the consequence attributes (Section 3.8.23.6). The rating is labeled preliminary until the EIC confirms or changes it in the field. Keep the attribute scores, LS, L, T, Fg, D, C and the trigger narrative with the site record: they show the field engineer why the site ranked where it did, and they let a program rank sites that share the same rating, by L × C.

Once a site has been assessed, its field rating replaces the preliminary rating as its static rating. It remains the static rating, and the baseline for the live rating, until the next visit, a repair or a new failure.

3.8.25.4 Priority and Level of Effort

The preliminary rating sets how soon the site is visited and how much effort goes into the field assessment. The level of effort rises with the rating, so that borings and instruments go to the sites that need them.

Table 3.8-29. Static rating, field timing and level of effort
Preliminary ratingPriorityField assessmentLevel of effortMonitoring until visited
Severe1Notify the railroad the same day; visit within daysFull assessment; plan exploration and instrumentation from the visitInspection after every trigger event; recommend operating restrictions until visited
High1Within two weeksFull assessment; borings likelyIncreased track inspection; gauge or rainfall trigger set
Elevated2Within the program cycle (typically 30 to 90 days)Full assessment; exploration scoped from the findingsRoutine inspection with trigger levels
Guarded3As the program allows; may be confirmed from track video or a hi-rail passWalk-through; full assessment if anything is foundWatch list; re-screen after a trigger event
Low–Not requiredDesktop record onlyRe-screen with the network screening or after an event

For a program of many sites, the static rating also starts the sorting that the field assessment finishes. After the visit, sites usually fall into three groups: those ready to move to construction, those that need design, exploration or permits first, and those that can be monitored and deferred. The preliminary rating gives the first cut at that sorting; the field ratings and alternatives (Section 3.8.42) settle it.

3.8.25.5 Limits of Static Ratings

  • Public soils and geologic maps are drawn at a scale far coarser than a single embankment. Use them to set expectations, not to set design parameters.
  • Lidar shows the ground surface at the date it was flown. Recent movement, new erosion and recent repairs will not appear.
  • Flood maps show regulatory floodplains; they do not show culvert capacity, backwater from a blocked structure or a channel that has moved.
  • Event databases record what someone reported. The absence of a record is not evidence that nothing happened.
  • A desk study cannot see a fresh tension crack, a seep at the toe or a culvert that silted in last month. The preliminary rating ranks sites for field attention; it is not a basis for operating decisions or for design.
  • A static rating describes usual conditions. During a flood, a heavy storm on wet ground or a thaw, the risk can be one or two levels higher; Section 3.8.26 measures that rise.

3.8.25.6 Example: Static Rating

Example 3.8-6: Culvert Fill Site, Part 4: Static Rating

The desk ratings of Examples 3.8-Y2 and 3.8-Y3 combine into the preliminary rating that scheduled the visit; the field rating of Example 3.8-3 then confirms or replaces it.

Main track36-in. culvert, half blockedponded water (left)seepagetension cracks25 ftGivenF​p = 4 (Example 3.8-5)S​p = 4 (Example 3.8-4)Field: F​c = 4, S = 4 (Example 3.8-3)RequiredPreliminary R​p and ratingField rating and whether it confirmsStatic rating and live baselineBlack = given; red = required
Given and required for Example 3.8-6.

Given

VariableValueDescription
Fp4Example 3.8-5
Sp4Example 3.8-4
Fc, S4, 4Field rating, Example 3.8-3

Required

  • The preliminary risk score and rating
  • Whether the field rating confirms it
  • The static rating and live baseline

Equations

  1. Eq. 1: R = F × S — risk score
  2. Eq. 2: Rating = matrix(F, S) — Table 3.8-16

Steps

Step 1 · Preliminary rating (Eq. 1, 2)
Uses: Fp, Sp
Rp = 4 × 4
Rp = 16, High (preliminary)
Spot check: Under Table 3.8-29 a High preliminary rating schedules the visit early.
↓
Step 2 · Field rating (Eq. 1, 2)
Uses: Fc, S
R = 4 × 4
R = 16, High
Spot check: Same F and S, so the same cell of Table 3.8-16.
↓
Solution
16 High, preliminary and confirmed.

Solution

Rp = 16, High (preliminary), confirmed in the field at R = 16, High. From the date of the visit, High is the site’s static rating and the baseline for its live rating (Section 3.8.26).

3.8.26 Live Ratings: Weather and River Events

The static rating describes a site under its usual conditions. Risk at a water-sensitive site is not constant: it rises during a flood, a heavy storm on wet ground or a spring thaw, and falls again when the water drains. The live rating measures that rise. It compares live weather, river and ground data against the site’s own H&H thresholds (Section 3.8.23.7) and raises the frequency index while a threshold is exceeded. Because it uses the same scales and the same matrix as every other rating in this chapter, a jump in the live rating means exactly what the same rating means anywhere else, and it calls for the response in Table 3.8-17.

The live rating needs three things from the earlier sections: a static rating to start from (Section 3.8.25), a driving mechanism that says which water conditions matter (Section 3.8.23.3), and thresholds that say how much water this site can take (Section 3.8.23.7).

3.8.26.1 River Gauge Monitoring

The river stage watchlist pairs gauges near the line with their flood categories. NWS gauges in the National Water Prediction Service report observed and forecast stage against four thresholds set for each gauge: action, minor, moderate and major flood stage. USGS gauges add discharge and how the current flow compares with the record for that day of the year (the streamflow percentile). A site whose driving mechanism is scour or drainage is paired with the nearest representative gauge, and its response is tied to the gauge’s thresholds. This applies the rule in Chapter 3.8: pair every water-sensitive site with a trigger source and a response threshold, and record the trigger magnitude after each event so the thresholds can be calibrated.

Gauge monitoring speaks to the conditions that actually fail track, gives real-time and forecast warning of the most common trigger, and lets each event add to the site’s own history. Its limits are that a gauge is a point on a river, that a gauge miles away on the main stem says little about a small tributary culvert, and that many small drainages have no gauge at all. For those sites, rainfall and soil moisture carry the live rating.

Table 3.8-30. Default gauge trigger levels for water-sensitive sites
Gauge conditionDefault response
Below action stage; flow percentile under 90Routine inspection
Action stage reached or forecast, or flow above the 90th percentileAlert the roadmaster; check the site at the next opportunity and after the crest
Minor flood stage reached or forecastInspect the site before and after the crest; watch culvert inlets for debris and backwater
Moderate flood stage reached or forecastInspect the site at the crest; consider a slow order on Severe and High rated sites
Major flood stage, or water against the embankment above any level seen beforeProtect the track; operating restrictions until the site is inspected after the water falls

These are starting values. Set each site’s levels from its own history: the stage at which water first reached the toe, overtopped a culvert or caused a defect. Inspection continues after the crest; many embankments fail on the falling limb, when the water outside drops faster than the water in the fill.

3.8.26.2 Baseline

Start from the site’s static rating: the field rating where the site has been assessed, otherwise the preliminary rating. The baseline frequency index is F0 and the severity is S. Severity is not changed by the weather; the consequence of a failure is the same whenever it happens.

3.8.26.3 Live Condition Indicators

Check each indicator that applies to the site’s driving mechanism against the levels in Table 3.8-31. Observed values and forecasts for the next 24 to 48 hours both count; a forecast lets the rating rise before the water arrives. During the thaw, add forecast snowmelt to the rainfall, and use the spring hazards and combined snowmelt-plus-rain alert levels in Section 3.8.7.8 and the frost and thaw mechanisms in Section 3.8.8 to set the thaw indicator.

Table 3.8-31. Live condition indicators and levels
IndicatorApplies toNormalWatchWarning
River stage at the paired gaugeScour, drainage, slope at a stream toeBelow action stage and below the toe stageAt or above action stage, or at the toe stageAt or above moderate flood stage, or at the damage stage
Rainfall, 24-hour observed plus forecastAll water-driven mechanismsBelow half the site rainfall thresholdHalf the site rainfall threshold up to the thresholdAt or above the site rainfall threshold or the culvert capacity storm
Antecedent wetnessSlope, drainage, subgradeBelow the site’s antecedent thresholdAt or above the site’s antecedent threshold (default 80th percentile)Above the 90th percentile and above the site’s antecedent threshold
Thaw and snowmeltSubgrade, slope, rock (northern sites)Ground frozen or thawed and drainedThaw under way after deep frost, or snowmelt with saturated groundRain on melting snow, or thaw at a site that has failed in thaw before
NWS alerts for the siteAll water-driven mechanismsNoneFlood watch, or flood advisoryFlood or flash flood warning

3.8.26.4 Live Frequency Index and Live Rating

Raise F0 by the increment in Table 3.8-32, to a maximum of 5. Wet ground and heavy rain together are treated as more than either alone, because most rain-triggered failures need both.

Table 3.8-32. Live frequency increment
Live conditionIncrement to F
All applicable indicators Normal0 (live rating = static rating)
One indicator at Watch+1
Two or more indicators at Watch, or any indicator at Warning+2
Warning on river stage or rainfall at a site whose static frequency index is Emerging (4) or higherSet F to 5 (Occurring)

Rlive = Flive × S

The live rating is read from the matrix in Table 3.8-16 and reported beside the static rating as a jump, for example Elevated → High, with the indicators that caused it.

Example. A 25-ft fill over a culvert on a main line with moderate traffic has a static rating of Dormant (F = 2) and Critical (S = 4): R = 8, Elevated. Its desktop study found that the culvert passes about a 10-year storm, 4.3 in. in 24 hours at the site. With soil moisture at the 93rd percentile (Warning) and 2.5 in. of rain forecast (Watch), the increment is +2: Flive = 4, Rlive = 16, High. The roadmaster is alerted and the site is inspected before and after the storm. Had the forecast reached 4.3 in., rainfall would also be at Warning, but because the site’s static frequency index is only Dormant, the increment stays at +2 and the rating stays High. The example site of Sections 3.8.23 to 3.8.25, already Emerging, would go to F = 5 on the same rainfall Warning: Rlive = 5 × 4 = 20, Severe. Figure 3.8-40 traces the first case through the storm.

01224364860728496108120Hours from the forecastSoilmoistureRainfall24 h + fcstNormalWarningNormalNormalWatchNormalLive Fand ratingF = 2F = 4, HighF = 2, Elevatedstatic+2 (soil moisture at Warning): R = 4 × 4 = 16; held after the indicators clear at 60 hback to static: R = 8Storm forecast:alert, inspect beforeRain ends:inspect after; keep therating (falling-limb risk)48 h after the rain andbelow action stage: backto the static ratingStatic rating: Dormant (F​0 = 2) × Critical (S = 4) = 8, Elevated. S does not change with the weather.
Figure 3.8-40. The live rating through a storm at the example culvert site: Watch and Warning indicators raise F by the increments of Table 3.8-32, the rating jumps from Elevated to High, and it is held until 48 hours after the rain before returning to the static rating. Timing is schematic.

3.8.26.5 Holding, Dropping and Running the Live Rating

Holding and dropping. Do not drop the live rating as soon as the rain stops or the river crests. Hold it until the river is back below action stage and at least 48 hours have passed since the crest or the end of heavy rain; embankments often fail on the falling limb, and slopes often fail a day or more after the storm, as the water works into the ground.

Running it. The hazard monitoring map computes the live rating for every monitored site in its Live risk rating panel (desktop and phone). Each site stores its static F and S, its driving mechanism, its paired NWS gauge and its H&H thresholds. Every 15 minutes the hazard monitoring map reads the gauge’s observed stage and 48-hour forecast peak against its action and moderate flood stages and the site’s toe and damage stages; the observed 24-hour rainfall (NWS River Forecast Center analysis) plus the NWS forecast for the next 24 hours; the soil moisture percentile in the top 16 in. (NASA SPoRT); and NWS flood watches, advisories and warnings for the site. Thaw is set on each site by the user, because there is no national live source for it. Sites are drawn on the map in their live rating color, a jumped site is ringed, and the panel lists the sites that have jumped with the indicators that caused it. A service that does not respond is named on the site and left out of that reading rather than read as normal. The live rating is a prompt for inspection and for the railroad’s own operating decisions; it does not replace them.

At the field visit. The live rating at the time of the visit is printed on the report (Section 3.8.42.3), so the EIC knows whether the site is being seen wet or dry, and whether the indicators in front of them reflect a passing event or the site’s usual state.

3.8.26.6 Calibrating the Thresholds

Log every jump with the indicator values and what was found at the site. The hazard monitoring map writes each jump to its jump log with the readings that caused it; record what was found against each entry. A site that jumps repeatedly with nothing found has thresholds set too low; a site that fails without a jump has thresholds set too high, or a driving mechanism that was misjudged. Adjust the thresholds in Table 3.8-22 accordingly, and review the site’s static frequency index when it keeps responding.

Live risk rating and threshold calibration calculator. The calculator below applies Tables 3.8-31, 3.8-32 and 3.8-16 to one site. Tab 1 gives the live rating from the site’s baseline, thresholds and live values. Tab 2 calibrates the thresholds from the site’s event record (date, stage, 24-hour rain, soil moisture percentile and outcome: none, defect, movement or failure), shows which past events the current thresholds would have caught or missed, and suggests thresholds that catch the most responses with the fewest false alarms (one miss counts as three false alarms). A jump log export can be loaded straight into tab 2. The calculator runs in the page; nothing is sent anywhere.

ToolsLive Risk Rating and Threshold Calibration CalculatorRuns in this page; nothing is sent anywhere. Uses Tables 3.8-31, 3.8-32 and 3.8-16.
Site
H&H thresholds (Table 3.8-22)
Live conditions (observed now or forecast in the next 24 to 48 hours)
IndicatorValueLevelWhy

Static and live ratings together tell the railroad where the risk is and when it rises. Neither replaces the engineer on the ground. The next section is the form the engineer takes there.

3.8.27 Rated Elements and Rating Criteria

Sections 3.8.18 to 3.8.39 define each rating by its levels. This section breaks every rating into the elements that are actually looked at, at the desk or on site, and states for each element what places it at 1, 2, 3, 4 or 5. The tables are the working detail behind Tables 3.8-9, 3.8-10, 3.8-80 to 3.8-82 and Tables 3.8-20, 3.8-21 and 3.8-24; they do not change those tables, the equations or the risk matrix. They make the choice of level repeatable: two engineers looking at the same evidence should land on the same score, and the one-line reason required by Section 3.8.43 can be taken straight from the cell that was matched.

This section is the working detail behind the ratings, so its element tables are folded. Open the group you need; each lists what places an element at 1 to 5.
  • 3.8.27.2 Trigger Rating Elements (T) (Tables 3.8-34 to 3.8-38)
  • 3.8.27.3 Situational Attribute Elements (L1 to L5) (Tables 3.8-39 to 3.8-43)
  • 3.8.27.4 Historic Instability Elements (L6) (Table 3.8-44)
  • 3.8.27.5 Defect Rating Elements (D) (Tables 3.8-45 to 3.8-47)
  • 3.8.27.6 Consequence Elements (C1 to C5) and Severity (S) (Table 3.8-48)
  • 3.8.27.7 Solution Elements (Table 3.8-49)
  • 3.8.27.8 Design and Construction Elements (Tables 3.8-50 to 3.8-51)
  • 3.8.27.9 Post-Stabilization Elements (Table 3.8-52)
  • 3.8.27.10 Example: Element Scores Behind the Worked Example (Table 3.8-53)
  • 3.8.27.11 Basis and Limits of the Element Criteria

3.8.27.1 How the Element Tables Work

Table 3.8-33. Ratings, the elements that feed them and how the elements combine
RatingElement tablesHow the element scores give the ratingSection
Trigger rating TTables 3.8-34 to 3.8-38 (T1 to T19)T is the highest score among the trigger elements that can, on their own, bring the site to its response level. Where two triggers act only in sequence (a flood that scours the toe, then drawdown), score the sequence by the frequency of the event that starts it. Where the response level is unknown, T is not lower than 3.3.8.18.3
Situational attributes L1 to L5Tables 3.8-39 to 3.8-43Each attribute is the highest score among its elements that have data. Elements without data are left blank, not scored. An attribute with no data at all is scored 3 and flagged for the field visit (Section 3.8.22.1). The attributes are then weighted and averaged as before (Section 3.8.23.4).3.8.19.1; 3.8.23.4
Historic instability L6Table 3.8-44The highest score among its elements that have data.3.8.24.2
Defect rating DTables 3.8-45 to 3.8-47The higher of (a) the highest score among the record and measurement elements D1 to D4 and D15, and (b) the highest score shown by two or more of the field indicators D5 to D14. Check the result against the level descriptions of Table 3.8-10.3.8.19.2
Consequence attributes C1 to C5, and severity STable 3.8-48Each attribute is the highest score among its elements. C is the average of C1 to C5, with the floor of Section 3.8.23.6 (a 5 on C2 or C3 sets C at 4 or more), rounded half up to give S. The consequence governs, and the engineer may raise S one level (Section 3.8.20).3.8.20; 3.8.23.5 and 3.8.23.6
Solution ratingTable 3.8-49The element scores do not average into a rating. Each one sets a limit on, or a condition for, the credit the solution can take, as stated in the last column.3.8.37
Design and construction-stage ratingsTables 3.8-50 and 3.8-51Design elements give Fdes through Table 3.8-81; construction-stage elements decide Fcon and any one-level reduction in S for the stage.3.8.38
Post-stabilization ratingTable 3.8-52The elements decide whether Fpost is provisional (Fdes + 1), verified (Fdes) or reverts to the current-risk process.3.8.39
Why the highest element governs. A slope fails through its weakest layer, a culvert overtops at its smallest capacity, and a fill moves where its toe is wettest. Averaging the elements of one attribute would let good conditions in one place hide the condition that controls. The same rule is already used for slope geometry (score height and steepness separately and use the higher, Section 3.8.23.4). The weighting and averaging that follow, across attributes, are unchanged.

Reading the tables. Every table runs from 1 (lowest risk) to 5 (highest), the same direction as every other scale in the manual. For the solution, design and post-stabilization elements, 1 means the stage leaves the least risk. Where the evidence falls between two descriptions, choose the higher until the field visit or the record settles it, and say so in the reason. Numeric thresholds are indicative values from common practice; where a railroad has its own standard for an element (defect limits, culvert design events, monitoring alarm levels), use the railroad standard and record it.

3.8.27.2 Trigger Rating Elements (T)

The trigger elements are grouped by the kind of event. Their levels use the five annual frequency bands of Table 3.8-9, so the score of the element is the trigger rating it would give. Score only the elements that can act on the site’s driving mechanism (Table 3.8-8); the rest are left blank.

Table 3.8-34. Hydrologic and hydraulic trigger elements
IDElement and what is measured1 Remote: less than 1 in 100 years, or none2 Rare: 1 in 25 to 1 in 100 years3 Occasional: 1 in 5 to 1 in 25 years4 Frequent: 1 in 1 to 1 in 5 years5 Acting now: once a year or moreSources
T1Storm rainfall: return period of the storm at which the site has responded (defects, slow orders, movement, overtopping)No response to rainfall on record, or responds only to storms rarer than the 100-year eventResponds to 25- to 100-year stormsResponds to 5- to 25-year stormsResponds to 1- to 5-year storms (for example the 2-year, 24-hour depth)Responds in most wet seasons, to storms smaller than the 1-year eventNOAA Atlas 14; event and defect history; Section 3.8.23.7
T2Antecedent wetness: how often soil moisture or 30-day rainfall reaches the level that preceded past failures (default: 80th soil moisture percentile)No link between wet periods and the site’s responseOnly in exceptionally wet yearsIn wet years, about 1 in 5 to 1 in 25In most wet seasonsEvery wet season; the site is wet enough to respond for part of every yearSoil moisture percentile; antecedent rainfall; Section 3.8.23.7
T3Flood stage at the toe: return period, or gauge stage, at which water reaches the toe (toe stage)No water body within reach of the toe, or toe stage above the 100-year floodWater reaches the toe only in 25- to 100-year floodsWater reaches the toe in 5- to 25-year floodsWater reaches the toe in most high-water years (for example at minor flood stage)Toe in water at normal high water, or every yearNWS and USGS gauges; FEMA flood profiles; lidar; high-water marks
T4Scour and channel migration: how often flows erode the bank or toeNo channel within reach, or bank in rockArmored or straight reach; erosion only in floods rarer than 1 in 25 yearsOutside of a bend or below a constriction; bank loss in 5- to 25-year floodsBank retreating toward the toe in most high-water years; undercutting seenChannel migrating into the fill; toe lost in recent eventsHistoric aerials; lidar comparison; gauges; field reconnaissance
T5Rapid drawdown: how often water stands against the slope and falls faster than the fill can drainNo ponded or flood water against the slopeWater against the slope only in rare floods; slow recessionWater against the slope in 5- to 25-year floods; recession over daysWater against the slope most years; recession within a dayRoutine drawdown against the slope (reservoir, tide or controlled release)Gauge hydrographs; dam operator data
T6Snowmelt and rain-on-snow: how often melt runoff reaches the site at the response levelNegligible snowpackSnowpack present; rain-on-snow only in rare yearsRain-on-snow or rapid melt about 1 in 5 to 1 in 25 yearsRain-on-snow or rapid melt most yearsMelt runoff over frozen ground reaches the site every spring, and the site has failed in the melt seasonNOAA snow data; SNOTEL; Section 3.8.7.8
Table 3.8-35. Drainage and groundwater trigger elements
IDElement and what is measured1 Remote: less than 1 in 100 years, or none2 Rare: 1 in 25 to 1 in 100 years3 Occasional: 1 in 5 to 1 in 25 years4 Frequent: 1 in 1 to 1 in 5 years5 Acting now: once a year or moreSources
T7Culvert capacity exceedance: return period of the storm the culvert passes without heading up against the fill (culvert capacity storm)No concentrated flow, or the culvert passes the 100-year eventCapacity 25- to 100-yearCapacity 5- to 25-yearCapacity 1- to 5-yearHeads up or overtops every yearStreamStats or lidar drainage area; culvert inventory; Section 3.5.10
T8Blockage events: how often debris, sediment, beavers or ice block the inlet, outlet or ditchNo blockage on record; inlet protected; no debris sourceBlockage on record only once, long agoBlocked in some years; debris or sediment source upstreamBlocked most years; beaver activity in the reachBlocked now, or every year; active beaver dam at the inletMaintenance records; imagery sequence; field reconnaissance
T9Seasonal groundwater rise: how often groundwater reaches the critical zone of the slope or subgradeGroundwater well below any critical surface in all seasonsReaches the critical zone only in exceptionally wet yearsApproaches the critical zone about 1 in 5 to 1 in 25 yearsWithin the critical zone in most wet seasons; perched water on low-permeability layersAt or near the surface every year, or artesian or persistent perched waterPiezometers; boring water levels; seepage; Chapter 2.8
Table 3.8-36. Climatic and cyclic trigger elements
IDElement and what is measured1 Remote: less than 1 in 100 years, or none2 Rare: 1 in 25 to 1 in 100 years3 Occasional: 1 in 5 to 1 in 25 years4 Frequent: 1 in 1 to 1 in 5 years5 Acting now: once a year or moreSources
T10Frost and thaw weakening of the subgrade: how often frost reaches frost-susceptible soil with water availableFrost does not reach frost-susceptible soil, or the subgrade is non-frost-susceptibleReaches it only in extreme wintersReaches it in cold winters, about 1 in 5 to 1 in 25Reaches it in most wintersEvery winter, with heave or thaw softening recordedFrost depth and freezing index; USACE frost groups (Table 3.8-39); Section 3.8.8
T11Freeze-thaw, root wedging and intense rain on rock faces: how often these are followed by fallsNo falls on record after these events, or massive rockFalls only after extreme winters or stormsFalls after some winters or stormsFalls after most winters or stormsFalls every freeze-thaw season or storm seasonRock fall records; freeze-thaw cycle counts; rainfall intensity; Section 3.8.29
T12Wet-dry cycles in plastic clay (shrink-swell): how often desiccation cracking and re-wetting soften the slope or shoulderNon-plastic soils, or no seasonal moisture change in the active zoneCracking only in severe droughtsCracking in dry years, about 1 in 5 to 1 in 25Cracking in most dry seasonsDeep cracks open every dry season and soften on re-wettingPlasticity (Table 3.8-39); drought records; Chapter 2.5
Table 3.8-37. Loading, land-use and seismic trigger elements
IDElement and what is measured1 Remote or none2 Rare3 Occasional4 Frequent or planned5 Acting nowSources
T13Change in traffic loading: tonnage or axle load increase relative to what the subgrade has carriedNo change; traffic within what the subgrade has carriedIncrease unlikely within 25 yearsIncrease possible within 5 to 25 yearsIncrease planned within 5 yearsIncrease in the last few years, and the subgrade is responding (pumping, ballast pockets)Traffic and tonnage records; Chapter 2.3
T14Surcharge at the crest: stockpiles, spoil, new fill, added track or structuresNone, and none crediblePossible but unlikely; the land use controls itOccasional temporary stockpiles or spoil within twice the slope height of the crestA second track, siding or structure planned within 5 years, or recurring stockpilingSurcharge at the crest nowField reconnaissance; aerials; railroad plans
T15Excavation at or below the toe, or other removal of supportNone, and none credibleUnlikely; the land below is controlledPossible; the land below is open to developmentExcavation planned or permittedExcavation under way or recent, with distressField reconnaissance; aerials; permits
T16Upslope development and drainage changes: runoff redirected toward the right-of-wayNoneMinor development, no change in drainageIncreased runoff, managed by drainage worksRunoff concentrated toward the right-of-wayUncontrolled discharge onto the slope or fill nowAerials; county GIS; field reconnaissance
T17Vegetation loss and wildfire upslope or on the slopeDense, healthy coverGood cover with minor gapsSparse cover, or an older burn upslopeRecent clearing or loggingBurned within the last two years with a storm season aheadAerials; fire perimeter data; post-fire debris flow hazard maps
T18Earthquake shaking: return period of the ground motion at which the site fails or liquefies (Chapter 6.5)More than 100 years (most sites)25 to 100 years5 to 25 years1 to 5 yearsOnce a year or more (induced seismicity only)USGS hazard tools; Chapter 6.5

Seismic triggers rarely score above 2 on an annual scale. That does not make them unimportant: the screening elements of Table 3.8-38 decide whether the seismic case must be analyzed and designed for, whatever T is.

Table 3.8-38. Seismic screening elements
IDElement and what is measured12345Sources
T19aDesign ground motion: peak ground acceleration for the 2,475-year return period, site-adjustedLess than 0.05 g0.05 to 0.10 g0.10 to 0.20 g0.20 to 0.40 gMore than 0.40 gUSGS seismic design maps; Chapter 6.5
T19bLiquefaction: factor of safety against liquefaction of saturated loose sands and silts (Chapter 6.5)No liquefiable soil, or above the water tableFS more than 1.3 in all layersFS 1.1 to 1.3, or isolated thin loose layersFS 1.0 to 1.1 in a continuous layer, or FS below 1.0 in isolated layersFS below 1.0 in a continuous layer, with a free face or sloping ground (lateral spread)Borings and CPT; Chapter 6.5; Chapter 2.4

A score of 4 or 5 on either screening element requires the seismic case in the analysis (Chapter 6.5) and in the design factor of safety element DC2 (Table 3.8-50). Record shaking as a secondary trigger in the narrative.

3.8.27.3 Situational Attribute Elements (L1 to L5)

Each table refines one attribute of Table 3.8-20. The 1, 3 and 5 descriptions of Table 3.8-20 and the 2 and 4 descriptions of Table 3.8-76 are carried into the elements of each attribute, so a desk rating made from Table 3.8-20 alone still agrees with these tables. The other elements are used when the data exist.

Table 3.8-39. L1 Surficial soils: elements
IDElement and what is measured12345Sources
L1.1Soil type of the fill, the cut face or the foundation (USCS, ASTM D2487)Rock, or clean, well-drained sand and gravelSand and gravel with some fines; well drainedSilty or clayey sand, low-plasticity silt or clay; moderately drainedLean clay or silt that softens when wet; poorly drained in placesHigh-plasticity or organic clay, peat, loess, sensitive or collapsible soil; poorly drainedSoil survey; geologic map; boring logs; Chapters 2.2 and 2.4 to 2.7
L1.2Consistency of cohesive soil: undrained shear strength suVery stiff to hard: more than 2,000 psfStiff: 1,000 to 2,000 psfMedium stiff: 500 to 1,000 psfSoft: 250 to 500 psfVery soft: less than 250 psf, or sensitive clayBorings, vane, CPT, lab tests; Appendix D
L1.3Density of granular soil: SPT N60Dense to very dense: more than 30Medium dense: 10 to 30Loose: 4 to 10Very loose: less than 4Very loose, saturated fine sand or silt prone to flowBorings and CPT; Appendix D
L1.4Fill type and placementEngineered, compacted granular fillOlder granular fill with a good recordMixed fill with some finesCinders, end-dumped or loose fillEnd-dumped fill over soft ground, with debris or organicsValuation maps; construction records; borings
L1.5Frost susceptibility of the subgrade (USACE frost group)Non-frost-susceptible (NFS)F1F2F3F4Gradation and plasticity tests; Chapter 7.3
L1.6Plasticity of clay in the active zone: plasticity index PINon-plastic, or PI less than 10PI 10 to 20PI 20 to 35PI 35 to 50PI more than 50, with seasonal desiccation crackingAtterberg limits (Chapter 5.2); Chapter 2.5

At the desk L1.1 is usually the only element with data. L1.5 applies to subgrade-driven sites and L1.6 to sites in plastic clay; leave them blank elsewhere.

Table 3.8-40. L2 Geologic setting: elements
IDElement and what is measured12345Sources
L2.1Overburden over rock: depth and type of the materials below the fill or cutCompetent rock at or near the surfaceWeathered rock over competent rock at shallow depthWeathered rock or till at moderate depthThick till, colluvium or weak shaleDeep weak overburden or colluvium, or a mapped landslide-prone formationGeologic map; boring logs; lidar
L2.2Landslide susceptibility of the mapped unitLow or noneLow to moderateModerateHighVery high, or the site sits in a mapped landslide-prone formation with deep colluviumState and USGS landslide susceptibility maps
L2.3Karst and underminingNo soluble rock and no miningSoluble rock at depth, no features within about half a mileSinkholes or mine workings mapped within about half a mileKarst or mine workings mapped nearby but not under the trackKarst features or mine workings under the trackKarst and mine maps; state geological survey; lidar closed depressions
L2.4Rock mass structure in cuts: discontinuities relative to the faceNo rock cut, or massive rock, or joints dipping into the faceFavorable joints; slight weatheringRandom or some adverse joints; moderate weatheringAdverse joints daylighting in the faceDaylighting planes or wedges with past failures, toppling, or clay-filled jointsGeologic mapping of the cut; Section 3.8.29
Table 3.8-41. L3 Slope geometry: elements
IDElement and what is measured12345Sources
L3.1Height of the fill or cutUnder 10 ftHeight alone does not give 210 to 30 ftHeight alone does not give 4Over 30 ftLidar; track charts
L3.2Steepness of the steepest representative slopeFlatter than 3H:1V2.5H:1V to 3H:1VAbout 2H:1V (2H:1V to 2.5H:1V)Steeper than 2H:1V but not steeper than 1.5H:1VSteeper than 1.5H:1VLidar sections; field measurement
L3.3Distance from the end of the ties to the crest of the slopeMore than 10 ft6 to 10 ft3 to 6 ft1 to 3 ftLess than 1 ft, or the crest is in the ballast shoulderLidar; field measurement
L3.4Setting: what the fill or cut sits onFill or cut on level groundLow sidehill, natural ground flatter than 5H:1VSidehill bench on natural ground of 5H:1V to 3H:1VCut with natural ground steeper than 3H:1V above itSidehill fill on natural ground steeper than 3H:1V, or a fill across a hollow or old channelLidar; valuation and historic maps; Section 3.8.23.2

Height keeps the three bands of Table 3.8-20, so the intermediate scores 2 and 4 come from steepness, crest distance and setting. Use the highest element, as Section 3.8.23.4 requires for height and steepness.

Table 3.8-42. L4 Hydrology: elements
IDElement and what is measured12345Sources
L4.1Water against or near the toeNo contributing flow; no water body within about 500 ftIntermittent ditch flow away from the toe, or a water body 200 to 500 ft awayDitch or small-stream flow along the toe, or a water body 50 to 200 ft awayStream within about 50 ft of the toeStream or river against the toe, or convergent flow or ponding against the fillAerials; National Hydrography Dataset; lidar
L4.2Mapped flood hazard (FEMA zone)Outside mapped flood hazard areas (Zone X, unshaded), no flow toward the fillOutside the 500-year floodplain, local ponding possibleIn or near the 500-year floodplain (Zone X, shaded)In the 100-year floodplain (Zone A or AE) without flow against the fillIn the 100-year floodplain with flow against the fill, in a regulatory floodway, or in a coastal high hazard area (Zone VE)FEMA National Flood Hazard Layer
L4.3Channel position and flow attackNo channelStraight reach, flow parallel to an armored or vegetated bankFlow along the toe in a straight reachOutside of a bend, or below a constriction or a bridgeFlow impinging directly on the fillAerials; lidar; field reconnaissance
Table 3.8-43. L5 Drainage condition: elements
IDElement and what is measured12345Sources
L5.1Culvert condition and blockageClear and soundMinor debris, sediment or corrosion; full functionAging; some section loss or partial blockageAbout half blocked, damaged, separated joints, or capacity unknownMostly blocked, collapsed, or failed and directing water into the fillCulvert inspections; field reconnaissance
L5.2Culvert size relative to the design flowPasses the design flow without heading up against the fillAdequate, but aging or with little marginCapacity not knownUndersized for the design flowUndersized, with a record of overtopping or ponding against the fillCulvert inventory; StreamStats; Section 3.5.10 (the frequency itself is T7)
L5.3Ditches and outletsFree-draining, with outlet controlMinor sediment or vegetationPartly obstructed; some sedimentDitch holding water; outlet eroded or undefinedDitch blocked or missing; water directed onto the slope; no outlet controlImagery sequence; field reconnaissance; maintenance records
L5.4Track and subsurface drainage: subdrains, underdrains and drainage of the track sectionSection drains freely; subdrains workingMinor fouling; subdrains workingFouled shoulders or subdrain condition unknownWater trapped in the section; subdrain outlets buriedBathtub section or failed subdrains holding water under the trackField reconnaissance; GPR; Chapter 2.3
L5.5Beaver activity and debris sourcesNoneOld evidence onlyBeaver or debris source in the drainage upstreamActive beaver activity in the reachActive dam at or near the inlet, or debris jam at the structureImagery sequence; field reconnaissance; maintenance records

L5 records the condition of the drainage. How often the drainage is exceeded is the trigger element T7; the two are scored separately, as Section 3.8.37.1 requires when a solution changes both.

3.8.27.4 Historic Instability Elements (L6)
Table 3.8-44. L6 Historic instability: elements
IDElement and what is measured12345Sources
L6.1Recorded failures and repairs at the siteNoneNo record at the site; landslide-prone formation mapped (L2.2 of 4 or more)A past repair at the site (berm, drains, riprap, wall)A documented failure at the site within about 20 yearsRepeated documented failures, or repairs that have not heldRailroad records; interviews with track forces
L6.2Geomorphic evidence in lidar and on siteNoneSubdued features that may be old movementOld lobes or hummocky ground near the siteAn old scarp visible in lidar at the siteFresh or repeated scarps at the siteLidar hillshade and slope maps; field reconnaissance
L6.3Mapped instability near the siteNone within about a mileDistant mapped slidesMapped slides within about half a mile, or instability mapped nearbyA mapped slide adjacent to the right-of-wayA mapped active landslide crossing the right-of-wayUSGS landslide inventory; state geological survey
L6.4Slow orders for a geotechnical cause, more than 12 months agoNoneOne, more than 10 years agoOne or two in the last 10 yearsThree to five in the last 10 yearsMore than five in the last 10 yearsSlow order history
L6.5Measured past movementNone measuredMovement measured once, since stoppedIntermittent movement after past eventsMeasured movement in recent yearsContinuing measured movementInSAR; survey; inclinometer records

Slow orders in the last 12 months and standing slow orders are scored in the defect rating (D3), not here, so the same order is not counted twice.

3.8.27.5 Defect Rating Elements (D)

The defect elements follow the levels of Table 3.8-10: 1 None, 2 Historic, 3 Present, 4 Recurring, 5 Active. The record and measurement elements (D1 to D4 and D15) are direct evidence of what the track and the ground are doing, so any one of them can set D. The field indicators are read as a pattern (Section 3.8.24.4): D is set at the highest level shown by at least two of them. Each defect is entered with its measurement and its frequency.

Table 3.8-45. Track defect and slow order elements
IDElement and what is measured12345Sources
D1Recurrence of geometry defects at the site (cross level, profile, alignment, warp)No defects in the recordA single defect in the record, not repeatedDefects reported more than once, but not returning between surfacing cyclesThe same defect returns between surfacing cycles (surfaced two or more times in 12 months at the same location)Defects return within weeks of surfacingGeometry car and inspection records; surfacing records
D2Size of the worst defect relative to the limitsNoneWithin the railroad’s maintenance toleranceBeyond the maintenance tolerance but within the FRA limit for the track classBeyond the FRA limit for the track class; remedial action required under 49 CFR Part 213Beyond the limits for any class the line can be reduced to; track removed from serviceGeometry car data; 49 CFR Part 213
D3Slow orders in the last 12 months for a geotechnical causeNoneA slow order more than 12 months ago, lifted after repair, nothing sincePrecautionary slow orders during high water or storms, without defectsA slow order for a defect within the last 12 monthsStanding slow order, or track removed from serviceSlow order history
D4Trend of defects over successive geometry runs or inspectionsNo defectsDecreasingSteadyIncreasingAccelerating, or recurring after each surfacingGeometry car data

These elements record the evidence behind the defect rating. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.

Table 3.8-46. Field indicator elements: slope and ground
IDElement and what is measured12345Sources
D5Tension cracks and scarpsNoneOld, healed or vegetated cracks or scarps onlyOpen cracks with weathered edges, no sign of progressFresh cracks with clean edges, or a continuous scarp with a small offsetCracks widening between visits, or cracks through the shoulder or ballastField reconnaissance; photographs with scale (Section 3.8.24.4)
D6Bulges and toe heaveNoneOld lobes with no fresh disturbanceNoticeable bulge, no fresh disturbanceDistinct or growing bulge, or fresh toe heaveActive toe heave, a slumped mass, or a bulge advancingField reconnaissance
D7Displaced trees, poles, fences and structuresNoneIsolated old tilted trees with recovered growthSeveral curved (pistol-butt) treesRecently tilted poles or fences, cracked headwallsStructures being displaced now, or broken utilitiesField reconnaissance
D8Settlement, sags and ballast pocketsNoneMinor shoulder irregularityA low spot that recurs, with no recent changeRepeated surfacing; ballast pocketsRapid settlement; track hung or voids under the tiesField reconnaissance; track forces; GPR
D9Seepage, piping and water at the toeNoneDamp areas onlySeepage or standing water at the toe; clear waterPersistent seepage carrying finesActive piping, sinkholes or sand boilsField reconnaissance; seasonal re-inspection
D10Erosion and undercutting at the face or toeNoneMinor rillsGullies, or minor undercuttingSignificant undercutting; slope oversteepenedToe lost; erosion reaching the shoulderField reconnaissance; aerials
D11Loss of shoulder or sectionFull shoulderSlightly narrowed shoulderNarrowed shoulder, stableShoulder narrower than 12 in., with recent lossTie ends unsupportedField reconnaissance; Table 3.8-25
Table 3.8-47. Field indicator elements: track section, protection and structures, and monitoring
IDElement and what is measured12345Sources
D12Fouled ballast, water between the cribs and pumpingNoneIsolatedRecurring after stormsPersistent pumping; fouled ballastContinuous pumping, with geometry defects returningField reconnaissance; GPR; Chapter 2.3
D13Scour protection (riprap or revetment) conditionIntact, or not neededMinor displacementGaps, or undersized stoneSignificant loss of protectionProtection failed, or absent where flow attacks the toeField reconnaissance; underwater or low-water inspection
D14Retaining structures (soldier pile and lagging and other walls)None needed, or in good conditionMinor deteriorationModerate deterioration, minor tiltLagging loss, significant tilt or bulgingWall failing or failedField reconnaissance; Chapter 7.1
D15Monitoring trend: inclinometers, survey, extensometers or InSARNo movement beyond instrument precision over at least a year of readingsMovement after a past event that has since stoppedPossible slow movement, less than about 0.1 in. per year, not yet confirmed by successive readingsConfirmed steady movement, about 0.1 to 2 in. per yearMore than about 2 in. per year, or acceleratingInstrument and survey records; InSAR; Chapter 5.3

D15 is a measurement element and can set D on its own. The movement rates are indicative; where the railroad or the design sets alarm levels for the instruments, the alarm levels govern.

3.8.27.6 Consequence Elements (C1 to C5) and Severity (S)

The consequence elements refine Tables 3.8-21 and 3.8-76. Each attribute is the highest of its elements; C1 to C5 are averaged with the floor of Section 3.8.23.6, and the result is the hazard severity S of Table 3.8-15. For cuts and natural slopes above the track, C4 is judged from the volume that would reach the track rather than the fill height.

Table 3.8-48. Consequence attribute elements
IDElement and what is measured12345Sources
C1.1Line and track: what the track is used forIndustry, yard or out-of-service trackLightly used branch line or sidingMain line with light traffic, or a busy sidingMain line with moderate trafficMain line with heavy tonnage or high speed; multiple main tracksRailroad network data; timetable
C1.2Track class: FRA class of the track at the siteExcepted track or Class 1Class 2Class 3Class 4Class 5 or higherTimetable; 49 CFR Part 213
C2.1Train type: passenger and hazardous materials trafficNo passenger or hazardous materials trafficNo passenger trains; hazardous materials limited to infrequent carsOccasional hazardous materialsRegular hazardous materials traffic, or occasional passenger trainsPassenger trains, or a key route for hazardous materials (AAR Circular OT-55)Railroad traffic data
C3.1People and property below and beside the trackOpen land on railroad propertyRailroad or private land with minor drainageA road or farmlandA local road, or a few dwellings within reachA highway, dwellings, occupied buildings, utilities or a critical facilityAerials; county GIS
C3.2Water and the environment below and beside the trackNoneMinor drainageA small stream or wetlandA stream with fisheries value, or other regulated waterA river, a drinking-water supply or protected habitatNational Wetlands Inventory; state environmental data
C4.1Size of failure: fill height, or volume reaching the track from aboveFill under 5 ft; a failure would be shallowFill 5 to 10 ftFill 10 to 20 ftFill 20 to 30 ftFill over 30 ft, or a culvert or structure under high fillLidar; track charts
C5.1Redundancy: route around the siteA parallel route on the same corridorA parallel route nearby, with minor delayA detour is availableOnly a long detourNo detourRailroad network data
C5.2Recovery: time to restore service, including accessWithin a shiftWithin a dayDaysAbout a weekMore than a week, or access is difficultAccess study (Chapter 3.6); repair experience

The floor applies through C2 and C3: a 5 on C2.1, C3.1 or C3.2 sets C at no less than 4, because a failure that can reach passengers, a hazardous materials release or the public governs regardless of the other attributes.

3.8.27.7 Solution Elements

The solution is rated by rescoring T, L1 to L5 and D as the site would be once the solution works (Section 3.8.37.2). The elements below do not change that arithmetic; they decide how much of it can be credited. A score of 1 means the solution leaves the least risk.

Table 3.8-49. Solution elements and their effect on the solution rating
IDElement12345Effect on the rating
SOL1Mechanism match: does the solution act on the primary trigger, or on the susceptibility it exploits?Acts on the primary and all contributing mechanismsActs fully on the primary mechanismActs on part of the primary mechanismActs on a contributing mechanism onlyDoes not act on the primary mechanism1 or 2: full rescoring. 3: Fsol no more than one level below Fc. 4 or 5: no reduction in F (Fsol = Fc); only S can change, under Table 3.8-80.
SOL2Way of reducing risk (Table 3.8-79)Removes the trigger and increases resistanceRemoves or controls the triggerIncreases resistance onlyReduces exposure only (detection linked to operating rules)Monitoring without an operating response1 to 3: rescore T and L as the solution changes them. 4: S may drop one level while the response is in force; F unchanged. 5: no credit.
SOL3Investigation behind the solutionSubsurface investigation, laboratory testing, analysis and instrumentationSubsurface investigation, laboratory testing and analysis at the design sectionsLimited borings, no analysisField reconnaissance onlyDesk study onlyCaps from Table 3.8-80. 1 or 2: full credit. 3 or 4: at most two levels. 5: at most one level.
SOL4Dependence on maintenanceNo maintenance needed to keep workingRoutine inspection onlyPeriodic maintenance (drainage cleaning, vegetation)Frequent maintenance; works fail if it lapsesWorks fail within a season without maintenance3 to 5: full credit only with a maintenance plan in force (Table 3.8-80); otherwise the rating stays provisional (Table 3.8-82).
SOL5Design life against the planning horizonMore than 50 years30 to 50 years15 to 30 years5 to 15 yearsLess than 5 years4 or 5: record the date the credit expires and re-rate before it; carry the replacement cost into the life-cycle cost (Section 3.8.40). A solution that leaves the site at High or above is interim either way.
SOL6Constructability and permittingNo permits; easy access; work outside the trackMinor permits; good accessStandard permits; limited access or track timeMajor permits; difficult access; long track windowsPermits uncertain; access needs a new road or bargeNot a rating input. 4 or 5: check the construction-stage rating (Table 3.8-51) and the duration before the solution is preferred.
3.8.27.8 Design and Construction Elements
Table 3.8-50. Design elements and the design frequency index Fdes
IDElement12345Effect on the rating
DC1Investigation adequacy at the design stageFull investigation with instrumentationBorings and laboratory tests at the design sectionsLimited boringsDesk study and reconnaissance onlyNo site-specific data1 or 2: full design credit. 3: Fdes no lower than 2. 4 or 5: no design credit beyond the caps of Table 3.8-80.
DC2Slope design factor of safety for the governing condition (Chapter 6.3)FS of 1.5 or more static, and the required factors of safety met for rapid drawdown and seismic cases where they applyFS of 1.5 or more static; other cases not applicable or not yet checkedFS 1.3 to under 1.5FS 1.1 to under 1.3FS under 1.1Fdes 1, 1 (2 if a required case is unchecked), 2, 3, no credit (Table 3.8-81).
DC3Hydraulic design event for culverts, channels and scour countermeasures100-year or larger, with scour checked at the 500-year event25- to 100-year10- to 25-year5- to 10-yearUnder 5-yearFdes 1, 2, 3, 3, no credit (Table 3.8-81).
DC4Subgrade and track section design (Chapter 2.3)Meets the criteria for the traffic with margin, with drainageMeets the criteria, but depends on drainage maintenanceMeets bearing criteria; drainage not addressedPartly meets the criteriaNo subgrade designFdes 1, 2, then no design credit for 3 to 5.
DC5Rock and debris, or subsidence, treatmentAll mapped blocks stabilized and catchment verified; or track bridged or relocated over the voidsScaling, bolting or catchment designed for the design block size and energy; or voids treated and verifiedCatchment for smaller blocks than the design block; or voids treated but not verifiedScaling only; or partial treatmentNoneFdes 1, 2, 3, then no credit for 4 and 5 (Table 3.8-81).
DC6Construction quality assurance planned for the works (Chapter 5.3)Full-time inspection, testing and as-built recordsRegular inspection and testingPeriodic inspectionContractor quality control onlyNo inspection1 or 2: the works can be accepted (Table 3.8-82). 3: acceptable for maintenance-level work only. 4 or 5: works cannot be accepted; Fpost not credited below Fc until inspection or testing confirms them.

Where several mechanisms apply, Fdes is the highest among them (Section 3.8.38.1).

Table 3.8-51. Construction-stage elements
IDElement12345Effect on the rating
CS1Temporary loss of resistance or added load during the workNone; the work is away from the slope and the toeMinor and brief (light equipment, short trenches outside the slope)Excavation or equipment within the slope or at the toe, stage designedTrench through the fill or excavation at the toe, stage checked only by judgmentExcavation or loading on a slope already moving1 or 2: Fcon = Fc. 3 to 5: Fcon = Fc + 1, to a maximum of 5 (Equation 3.8-15).
CS2Protection of operations during the stageTrack out of service for the stageSlow order with monitoring, and temporary support designed for the stageSlow order onlyInspection onlyNone1 or 2: S may be lowered one level for the stage (Table 3.8-80). 3 to 5: S unchanged. A stage rated Severe requires 1.
CS3Duration of the work relative to the trigger seasonDays, outside the trigger seasonWeeks, outside the trigger seasonOne seasonThrough a trigger seasonMore than a year4 or 5: the construction-stage rating applies through a triggering season; show it on the schedule and in the rating record.
3.8.27.9 Post-Stabilization Elements
Table 3.8-52. Post-stabilization elements and the post-stabilization frequency index Fpost
IDElement12345Effect on the rating
POST1Acceptance of the works: as-built quality assurance and quality control (Chapter 5.3)Accepted on full records and testsAccepted on regular inspection and testingAccepted on periodic inspectionContractor records onlyNo records1 to 3: Fpost = Fdes + 1, provisional. 4 or 5: not accepted; Fpost not credited below Fc.
POST2Performance monitoring after constructionAutomated, alarmed and reviewedPeriodic instrument readingsPeriodic survey or engineer’s inspectionVisual by track forces, with geometry recordsNone1 to 4: can verify the rating. 5: the rating stays provisional.
POST3Testing by a trigger since completionTwo or more triggering seasons, or events at or above the response level, with no movementOne triggering season or event at or above the response level, with no movementA full season, but the response level was not reachedLess than one seasonNone1 or 2 (with POST2 of 1 to 4): verified, Fpost = Fdes. 3 to 5: provisional, Fdes + 1.
POST4Maintenance plan for drainage, vegetation and protectionScheduled and funded, with recordsScheduledAs needed, from inspectionReactive onlyNoneDrainage-dependent works need 1 or 2 to be verified; otherwise they stay provisional (Table 3.8-82).
POST5Defects and indicators after stabilizationNoneRare, maintenance-levelOccasionalSimilar to before stabilizationIncreasing1 or 2: supports verification. 3: hold the rating provisional and find the cause. 4 or 5: recompute Fc from the new D (Section 3.8.19).
3.8.27.10 Example: Element Scores Behind the Worked Example

The ratings of the worked example in Section 3.8.41 are rebuilt below from the element tables. The element scores reproduce the attribute scores of Table 3.8-83.

Table 3.8-53. Worked example: element scores and the ratings they give
RatingElements scoredRating givenReason
TT7 = 4 (ponding against the fill recorded about every 3 years)4Primary trigger; no other trigger element scores higher
L1L1.1 = 4 (lean clay fill that softens when wet); no data for L1.2 to L1.64Highest element with data
L2L2.1 = 3 (weathered rock or till at moderate depth, assumed)3
L3L3.1 = 3 (22-ft fill); L3.2 = 3 (slopes about 2H:1V, assumed)3
L4L4.1 = 4 (creek within about 50 ft of the toe); L4.2 = 4 (100-year floodplain, no flow against the fill)4
L5L5.1 = 4 (culvert partly blocked); L5.2 = 5 (ponding against the fill on record)5Weight 2 (drainage-driven)
L6L6.1 = 3 (berm placed 15 years ago)3
L and Fg(4 + 3 + 3 + 4 + 2 × 5 + 3) / 7 = 3.86, rounded to 4; lesser of L and TFg = 4Equation 3.8-2
DD1 = 4 (surfaced twice in 12 months); D6 = 4 (bulge forming on the downstream slope)4Record element at 4, confirmed by a field indicator
Fc, S and RcFc from Table 3.8-11; S = 4 as in Table 3.8-83Fc = 4; Rc = 16, HighSame result as Table 3.8-83
3.8.27.11 Basis and Limits of the Element Criteria

Soil consistency and density bands follow the conventional classes used on boring logs (Appendix D). The frost groups are the USACE groups, F4 being the most frost-susceptible. The track class bands are the FRA classes of 49 CFR Part 213. The flood zones are FEMA’s. The trigger bands are the annual frequency bands of Table 3.8-9 and Table 3.8-14, and the design bands are those of Table 3.8-81. The remaining thresholds (distances, crest offsets, movement rates, plasticity bands and design life) are indicative values chosen to separate the five levels; they are starting points to be calibrated, like the H&H thresholds of Section 3.8.23.7, as each site’s record grows.

The elements are evidence for a rating, not a rating in themselves. Where the element scores and the trigger narrative disagree, one of them is wrong (Section 3.8.18.4): resolve it and write down why. A rating may always be raised one level on engineering judgment (Section 3.8.22.6); it is never lowered below what the element tables give without a written reason.

3.8.28 Vegetation, Fill Plasticity and Permeability as Likelihood Modifiers

The ratings in Sections 3.8.18 to 3.8.27 are unchanged. The factors below come from UK monitoring of old clay embankments and cut slopes. Record them in the rating justification, and where several point the same way, use the higher end of the existing likelihood band for the element being rated. They apply to clay fills and clay cuts; they do not apply to rock cuts or granular fills.

Table 3.8-54. Site factors that raise or lower the likelihood of earthwork failure (guidance; ratings unchanged)
FactorPoints to lower likelihoodPoints to higher likelihoodMechanism affectedSource
Vegetation on the slopeGrass or small shrubsLarge high-water-demand trees (oak, poplar)Grass: delayed deep failure in wet winters. Trees: summer track settlement and shoulder lossO'Brien (2013), pp. 20–22
Recent tree removal on clay fillNone in the last few yearsClearance within the last one to three wintersWetting-up, swelling and outward movement in the following winterO'Brien (2013), p. 22
Plasticity of clay fillPI below about 20PI above about 30 (intermediate PI 30–35, high PI 45–50 in the UK studies)Seasonal shrink–swell and progressive failureO'Brien (2013), pp. 20, 29
Bulk permeability of clay fillAbout 0.0003 ft/day (10−9 m/s) or lessAbout 0.014 to 0.14 ft/day (5 × 10−8 to 5 × 10−7 m/s)Winter rain infiltrates fast enough to raise pore pressureO'Brien (2013), pp. 25, 27
Soft alluvium or topsoil left under the fillFill placed on firm groundSoft or organic layer at the baseDelayed deep failure through the foundationO'Brien (2013), Table 3
Ash or ballast at the shoulderShoulder flatter than about 1.5H:1V, well vegetatedOversteepened, dry fine ash at the crestShoulder unravelling under traffic, mostly in summerMcGinnity and Saffari (2012), p. 1071

Permeability converted from m/s to ft/day (1 m/s = 283,000 ft/day). Tree water demand classes follow the UK NHBC (2003) system with oak and poplar placed in a “very high” class, as in the monitoring studies.

Vegetation cuts both ways. Trees that cause summer track movement may also be what keeps a clay embankment from a winter failure, so a rating that improves the serviceability score by clearing trees should be re-checked for the deep-seated case (Chapter 2.5, Section 2.5.18).

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • O'Brien, A. S. (2013). The assessment of old railway embankments – time for a change? In Gallipoli (ed.), Partial Saturation in Compacted Soils, pp. 19–32. ICE PublishingFind source ↗
  • McGinnity, B. T. and Saffari, N. (2012). Earthworks asset management and remedial design. Chapter 71 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1067–1086Find source ↗Library entry
3.8.29 Rock Fall Hazard Rating for Cuts Along Track

Risk ratings (Sections 3.8.18 to 3.8.47) put sites in order so that money goes first where it does the most good. For rock cuts the established system is the Rock Fall Hazard Rating System (RHRS). Pierson and others developed it in 1990 from earlier work by Brawner and Wyllie (1975) and Wyllie (1987), and Wyllie and Mah summarize it in their Chapter 12. Each category is scored 3, 9, 27 or 81 points, and measured categories fall on a continuous scale between those values. The exponential scale makes the worst sites stand out. The highway system has nine categories. For track, two of them (decision sight distance and roadway width) have no equivalent, and average vehicle risk becomes the share of time a train occupies the section.

3.8.29.1 Categories and scoring

Table 3.8-55. Rating categories (after Wyllie and Mah, Table 12.3)
Category3 points9 points27 points81 points
(a) Slope height25 ft50 ft75 ft100 ft
(b) Ditch effectivenessGood catchmentModerateLimitedNo catchment
(c) Exposure (% of time occupied)25%50%75%100%
(f) Geologic character, case 1: structureDiscontinuous joints, favorableDiscontinuous, randomContinuous, adverseContinuous, adverse, persistent
(f) Geologic character, case 1: frictionRough, irregularUndulatingPlanarClay infilling or slickensided
(g) Block size1 ft2 ft3 ft4 ft
(h) Climate and waterLow precipitation, no freezing, dryModerate, short freezing or intermittent waterHigh precipitation or long freezing or continual waterHigh precipitation and long freezing
(i) Rock fall historyFew fallsOccasionalManyConstant

Measured categories score 3x; for example 3H/25 for height in feet. Case 2 (differential erosion) replaces the two case 1 entries where erosion controls the falls.

Equation 3.8-5. Train exposure (adapted from average vehicle risk)

Exposure (%) = Ntrains/day × (Lsection + Ltrain) / speed ÷ 86,400 s × 100;   score = 3exposure/25

The continuous scores agree with Wyllie and Mah's examples. Their highway example, 7,000 vehicles a day over 0.2 km at 90 km/h, gives an average vehicle risk of 65% (64.8% before rounding); the formula scores that 17, against the 18 read from the RHRS chart. Their sight-distance example (52% of the decision distance) gives 3(120 − 52)/20 = 42, the same as published. Each slope also receives an inspection rating (Urgent, Priority, Observe or Okay), and that rating sets the permissible actions in Wyllie and Mah's Table 12.5. An Urgent or Priority slope may never be assigned no action.

3.8.29.2 Worked example

A 60 ft cut over 800 ft of single track carries 30 trains a day averaging 7,000 ft at 40 mph. Each train occupies the section for about two minutes, so trains are present 4.6% of time and the exposure score is low. The cut has limited ditch catchment, continuous adverse joints with undulating surfaces, 2 ft blocks, continual seepage and occasional falls, and rates 123. The ditch, the jointing and the water are the largest contributors. Those are what a ditch widening, scaling or drainage project would change. Low train exposure does not make a cut safe: one block on the rail can derail the next train.

Use the score to rank cuts against each other, not as an absolute measure. Rate every cut on a subdivision with the same inspector or team, record falls in a database so the history category is based on data, and re-rate after any stabilization work.

Open the rock fall rating calculator →
RHRS-based scoring of a rock cut along track, with continuous scores for height, train exposure and block size, the category breakdown, and the inspection rating with its permissible actions.

3.8.29.3 Running a rock slope program

Wyllie and Mah set the rating inside a seven-step program for transportation agencies. The program inventories and rates every slope, picks the highest priorities each year, designs and builds the work under a contract flexible enough for conditions found during construction, updates the database with falls and repairs, and re-rates. Because conditions get worse over time and nobody can re-rate hundreds of cuts every year, they add an annual inspection of the higher-priority slopes. Each inspected slope gets an inspection rating, and the rating limits which actions are allowed.

Table 3.8-56. Inspection ratings and permissible actions (after Wyllie and Mah, Table 12.5)
Inspection ratingTypical conditionPermissible actions
UrgentObvious recent movement or falls; a kinematically feasible block large enough to be a hazard; weather working against stability; failure possible within monthsLimit service and work within one month, or follow-up inspection
PriorityLikely movement since the last inspection of a block large enough to be a hazard; failure possible within about two yearsWork in the current year, follow-up inspection, or work in one to two years
ObservePossible recent movement, no imminent instabilityNo action; check specific conditions at the next inspection
OkayNo evidence of movementNo action

Urgent and Priority slopes may not be assigned no action.

Table 3.8-57. Stabilization measures by category (after Wyllie and Mah, Figure 12.3)
ReinforcementRock removalProtection
Rock bolts and dowelsReslopingDitches
Tied-back wallsTrimmingMesh
ShotcreteScalingCatch fences
Buttresses, including shot-in-placeWarning fences
DrainageRock sheds and tunnels

Where the face is steep and the toe is close to the track, there is no room for a ditch or barrier, so removal, bolting or mesh become the practical choices.

3.8.29.4 Ranking example

Three cuts on one subdivision were rated with the calculator at the same train traffic. Cut A is the worked example. Cut B is 100 ft high with no catchment, 3 ft blocks and constant falls. Cut C is 35 ft high with a good ditch, random jointing, moderate climate, 1 ft blocks and few falls. The exponential scoring separates them sharply. Cut B scores about eight times Cut C, although none of its categories is more than 27 times Cut C's. That separation is what the system is designed to produce.

Table 3.8-58. Ranking of three cuts, from the calculator
CutScoreRank
Cut B: 100 ft, no catchment, constant falls3341
Cut A (default)1232
Cut C: 35 ft, good ditch, few falls423
0.5011.522.533.50100200300Cut A, Cut B, Cut CHazard scoreHazard score
Figure 3.8-41. Hazard scores of the three example cuts.

3.8.29.5 Sources in the library

Paraphrased from these documents in the reference library.

Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.

3.8.30 Return Period, Exposure and the Trigger and Frequency Bands

The trigger rating T (Table 3.8-9) and the frequency index F (Table 3.8-14) are both defined by annual frequency: 1 in 5, 1 in 25 and 1 in 100 years mark the band edges. Programming decisions, however, are made over a period: a five-year capital plan, a 50-year service life. The conversion between the two is the probability of at least one event in n independent years. It is the same arithmetic behind the seismic design levels quoted in the library. Duncan, Wright and Brandon tabulate peak rock accelerations for a 10% chance of exceedance in 50 years (the 500-year level) and a 2% chance (the 2,500-year level). The Navy's soil dynamics handbook uses a 10% chance in 100 years (950 years). Hearn's semi-quantitative risk matrix (Section 3.8.34) rates the probability of a landslide over a 20-year road design life, and the GEO factors of safety in Look (Section 3.8.35) are set for a 10-year return period rainfall. Each ties its probability to a stated period or return period, and a rating should do the same.

3.8.30.1 Method

Equation 3.8-6. Annual probability, exposure and design return period

p = 1/T;   Pn = 1 − (1 − p)n ≈ 1 − e−n/T;   expected number of events = n/T

Tdesign = 1 / [1 − (1 − Ptarget)1/n];   several independent sites or triggers: P = 1 − Π(1 − pi)n

T is the return period (average recurrence interval) and n the exposure period in years. The binomial form treats each year as one independent trial; the Poisson form treats events as random in time. They agree closely once T is more than a few years. The calculator also gives the chance of exactly 0, 1, 2, 3 or 4 events and the band level for the trigger or failure frequency.

Table 3.8-59. Chance of at least one event at the band edges of Tables 3.8-9 and 3.8-14, from the calculator
Band edge, T / F levelsIn 1 yearIn 5 yearsIn 25 yearsIn 50 years
5 / 4 (1 per year or more)100.0%100.0%100.0%100.0%
4 / 3 (1 in 5)20.0%67.2%99.6%100.0%
3 / 2 (1 in 25)4.0%18.5%64.0%87.0%
2 / 1 (1 in 100)1.0%4.9%22.2%39.5%

An event at the 1-in-5 edge is about 67% likely within a five-year program; one at the 1-in-100 edge is still about 40% likely within a 50-year life.

Table 3.8-60. Check against design levels quoted in the library
Design levelReturn period as quotedCalculator
10% in 50 years (Duncan, Wright and Brandon, Table 10.2)500-year475 years
2% in 50 years (same table)2,500-year2,475 years
10% in 100 years (Navy MIL-HDBK-1007/3)950-year950 years

The quoted values are the rounded forms of the exact 475, 2,475 and 950 years.

3.8.30.2 Worked example

Example 3.8-7: What the Trigger Rating Means over a Program and a Service Life

The site of Section 3.8.41 rated its trigger T = 4 because water has ponded against the fill about every 3 years. Alternative A replaces the culvert with one sized for the 100-year event. The question is what those return periods mean over the periods that matter: a five-year program for ranking the site, and a 50-year service life for the new culvert.

ponding about every 3 years5-yr program50-yr service life of new culvertP = ?GivenPonding return period T = 3 yr (trigger T = 4)Program n = 5 yr; service life N = 50 yrNew culvert sized for the 100-yr eventResidual storm checked: 10-yr eventRequiredP(ponding) in 5 yr; expected numberP(new culvert exceeded) in 50 yrP(10-yr storm) in 5 yr; meaning for TBlack = given; red = required
Given and required for Example 3.8-7.

Given

VariableValueDescription
Tpond3 yearsReturn period of ponding against the fill (trigger T = 4, Table 3.8-9)
n5 yearsProgram cycle used for ranking
Tdes, N100 years; 50 yearsDesign event and service life of the new culvert
T1010 yearsA storm in the level 3 trigger band, still able to reach the site

Required

  • Chance of at least one ponding event in the program, and the expected number
  • Chance that the new culvert's capacity is exceeded in its service life
  • Chance of a 10-year storm in a program, and what the three results mean for T

Equations

  1. Eq. 1: p = 1/T — annual probability
  2. Eq. 2: Pn = 1 − (1 − p)n — chance of at least one event in n years (Equation 3.8-6)
  3. Eq. 3: E = n/T — expected number of events in n years

Steps

Step 1 · Ponding in the program (Eq. 1, 2, 3)
Uses: Tpond, n
p = 1/3 = 0.3333; P5 = 1 − 0.66675 = 1 − 0.1317; E = 5/3
P5 = 86.8%; E = 1.67 events
Spot check: 0.6667² = 0.444, &sup4; = 0.198, × 0.6667 = 0.132.
↓
Step 2 · New culvert over its life (Eq. 1, 2)
Uses: Tdes, N
p = 0.01; P50 = 1 − 0.9950 = 1 − 0.605
P50 = 39.5%
Spot check: e−50/100 = 0.607 gives 39.3%, within the approximation error of Section 3.8.40.
↓
Step 3 · 10-year storm in a program (Eq. 1, 2)
Uses: T10, n
p = 0.1; P5 = 1 − 0.95 = 1 − 0.590
P5 = 41.0%
Spot check: 0.9² = 0.81, 0.81² = 0.656, × 0.9 = 0.590.
↓
Solution
86.8% now; 39.5% over the new culvert's life; 41.0% for a 10-year storm in any program.

Solution

The ponding trigger has an 86.8% chance of reaching the site in a five-year program (1.67 events expected); a 100-year culvert still has a 39.5% chance of being exceeded in 50 years; and a 10-year storm has a 41.0% chance in any program.

The first result is what Table 3.8-9 means by a trigger the site will meet before most programs could fix it. The new culvert lowers T to 1 but does not remove the trigger, and storms of the level 3 band still arrive often enough that drainage maintenance remains part of the rating (Section 3.8.39).

A T-year event is not one that happens once every T years. Over an exposure equal to T its chance is about 63%. State the exposure period with every probability in a rating: the program cycle when ranking sites, the service life when sizing works. Return periods of rare events estimated from short gauge or defect records are uncertain; use agency frequency analyses where they exist.

Open the trigger probability calculator →
Annual probability, chance of one or more events in an exposure period, the number of events, the return period for a target chance in a design life, and the band level of Tables 3.8-9 and 3.8-14.

3.8.30.3 Many sites, one program

A single Forming site (1 in 25 years) has an 18% chance of failing within a five-year program. A subdivision with many such sites is a different matter. If their failures are independent, the chance that at least one of them fails in the program rises quickly with the number of sites. This is why corridor budgets need a reserve for emergency repairs even when every individual site is rated Forming or below. The corridor screening calculator (Section 1.1.15) applies the same rule to a hazard register.

Table 3.8-61. Chance that at least one of N independent sites fails in a five-year program
Sites NEach 1 in 25 years (F = 3 edge)Each 1 in 100 years (F = 2 edge)
118.5%4.9%
564.0%22.2%
1087.0%39.5%
2098.3%63.4%

Sites that share a trigger (one storm over the whole subdivision) are not independent; their failures cluster in the same event, so the chance of several failures together is higher than this table implies.

3.8.30.4 How the chance grows with exposure

The figure plots the chance of at least one event against the exposure period for the three band edges. The curves rise steeply over the first few years and then flatten. Most of the benefit of fixing a Frequent or Emerging site is gained by fixing it soon.

020406080100020406080100Exposure period (years)Chance of at least one event (%)5-year event25-year event100-year event
Figure 3.8-42. Chance of at least one event against exposure period for 5-, 25- and 100-year events, the edges of the trigger and frequency bands.

3.8.30.5 Sources in the library

Paraphrased from these documents in the reference library.

  • J.M. Duncan, S.G. Wright and T.L. Brandon, Soil Strength and Slope Stability, 2nd edition: Table 10.2, peak rock accelerations for 10% and 2% probability of exceedance in 50 yearsFind source ↗
  • U.S. Navy, Soil Dynamics and Special Design Aspects, MIL-HDBK-1007/3: response spectrum for 10% exceedance in 100 years (950-year average return period) (Cancelled in 2006; current Department of Defense criteria are in UFC 3-220-01, Geotechnical Engineering, 2012 with Change 3, 2025. The 950-year return period quoted here is a historical example.)Find source ↗
  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section A4, probability of a landslide during a 20-year design lifeFind source ↗Library entry
  • B.G. Look, Handbook of Geotechnical Investigation and Design Tables (2007): Tables 14.5 and 14.6, factors of safety for a 10-year return period rainfall (Current edition: 2nd edition, CRC Press, 2014; this section cites the edition held in the library.)Find source ↗

Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.

3.8.31 Combining Probabilities: Conditional Probability, Bayes’ Theorem and Event Trees

Ground hazard ratings combine probabilities all the time: a trigger and a susceptible slope, a failure and a train arriving before it is found, a detector that works or does not. The rules for combining them are few, but applying them in the wrong order gives answers that are off by an order of magnitude. This section sets out the notation and rules used in the manual and shows the one rule most often missed in practice, Bayes’ theorem.

Table 3.8-62. Symbols used in the probability and statistics of risk assessments (Greek letters after the CRC handbook appendix)
SymbolNameMeaning in this manual
P(A)–Probability of event A, from 0 (impossible) to 1 (certain)
ĀcomplementNot A; P(Ā) = 1 − P(A)
A ∪ B, A ∩ Bunion, intersectionA or B (or both); A and B
P(A | B)conditional probabilityProbability of A given that B has happened
μ, σmu, sigmaMean and standard deviation of a population or distribution
x̄, s–Mean and standard deviation of a sample (test results)
COV = σ/μcoefficient of variationScatter relative to the mean (Table 3.9-9)
λlambdaRate of events per year, or per mile per year
T, p = 1/T–Return period (years) and annual probability (Section 3.8.30)
βbetaReliability index: distance from the mean to failure in standard deviations
Φ(z)PhiStandard normal cumulative probability; Pf = Φ(−β)
αalphaSignificance level (for example 0.05 for 95% confidence); also the Gumbel scale parameter
χ²chi-squaredGoodness-of-fit statistic (Section 3.8.33)
tα, n−1Student’s tMultiplier for confidence limits from n tests (Table 3.8-64)

3.8.31.1 Rules for combining probabilities

Equation 3.8-7. Addition, multiplication and total probability

P(A ∪ B) = P(A) + P(B) − P(A ∩ B);   P(A ∩ B) = P(A | B) P(B)
independent events: P(A ∩ B) = P(A) P(B);   at least one of n: P = 1 − Π(1 − pi)
total probability: P(A) = Σ P(A | Bi) P(Bi) over mutually exclusive Bi

Multiply probabilities only along a chain of events (a trigger, then a failure, then a train on it), and only after making each one conditional on the event before it. Add only for events that cannot happen together, or subtract the overlap. Most errors come from multiplying events that are not independent, such as rainfall and high groundwater at the same site.

Equation 3.8-8. Bayes’ theorem: updating a probability with new evidence

P(Bi | A) = P(A | Bi) P(Bi) / Σj P(A | Bj) P(Bj)

P(Bi) is the prior probability (before the evidence), P(A | Bi) the likelihood of the evidence if Bi is true, and P(Bi | A) the updated (posterior) probability.

Bayes’ theorem is how a rating should change when new evidence arrives. A detector trip, a tension crack found on patrol, an inclinometer reading or a borehole that does not find the karst void are all evidence with known or estimable reliability. The updated probability depends on how common the condition was before the evidence, not only on how good the evidence is: a reliable test for a rare condition still produces mostly false alarms, as Example 3.8-8 shows. Conversely, a clean inspection of a site with a high prior probability of instability lowers that probability less than intuition suggests if the inspection would often miss the early signs.

3.8.31.2 Event trees

An event tree follows a hazard from its initiating event to its consequence through a series of branches, each with a conditional probability: for a rock cut, rock reaches the track, the rock is large enough to derail a train, the rock is not detected, and a train arrives before the track is cleared. The annual probability of a derailment is the annual rate of the initiating event times the product of the conditional probabilities along the branch. Because the branches multiply, the weakest assumption controls the answer; show the tree in the report so that the reviewer can see which branch probability carries the result, and test it at half and double its value, as for the life-cycle cost (Section 3.8.40). Fault trees run the other way, from a top event back to the combinations of causes (AND and OR gates) that could produce it, and suit detector, signal and drainage systems with several components.

3.8.31.3 Worked example

Example 3.8-8: Slide Detector Fence: How Often Is a Trip a Real Rockfall?

Problem Statement

A Class I railroad located in Oregon protects a 0.4-mi rock cut with a slide detector fence wired to the block signals. A trip drops the signals to stop, and the next train must proceed at restricted speed while the track is inspected. Train crews and dispatchers complain that most trips turn out to be nothing. The rock cut is being rated, and the engineer must say how much protection the fence actually gives, how often a trip is real, and whether reducing false trips is worth paying for.

1,000storm daysP(R) = 0.020.98Rock: 20No rock: 9800.950.050.050.95Trip: 19No trip: 1Trip: 49No trip: 931Trips = 19 + 49 = 68; real = 19 of 68 = ?Given60 storm days a yearP(rock on track) = 0.02 per storm dayDetection P(T|R) = 0.95False trip P(T|R̄) = 0.05Improved fence: 0.01Required(a) P(trip) per storm day(b) P(rock | trip)(c) P(rock | no trip)(d) Effect of fewer false trips
Figure 3.8-43. Example 3.8-8: probability tree for a rock cut protected by a slide detector fence, shown as counts in 1,000 storm days.

Given

VariableValueDescription
n60 storm days a yearDays with heavy rain, freeze-thaw or high wind, when rockfall and false trips occur
P(R)0.02 per storm dayChance that rock reaches the track on a storm day (from the rockfall log)
P(T | R)0.95Chance the fence trips when rock reaches the track (detection rate)
P(T | R̄)0.05Chance of a false trip on a storm day with no rock (trees, snow load, animals, broken wire)
P(T | R̄)new0.01False-trip rate after replacing the wire and clearing the trees

Required

  • (a) Probability of a trip on a storm day, and trips per year
  • (b) Probability that rock is on the track, given a trip
  • (c) Probability that rock is on the track with no trip, and missed rockfalls per year
  • (d) The answer to (b) with the false-trip rate cut to 0.01

Equations

  1. Eq. 3.8-7 (total probability): P(T) = P(T|R)P(R) + P(T|R̄)P(R̄)
  2. Eq. 3.8-8 (Bayes’ theorem): P(R|T) = P(T|R)P(R) / P(T)
  3. P(R|T̄) = [1 − P(T|R)]P(R) / [1 − P(T)]

Steps

Step 1 · (a) Chance of a trip (Eq. 3.8-7)
0.95 × 0.02 + 0.05 × 0.98 = 0.019 + 0.049
P(T) = 0.068 per storm day; 60 × 0.068 = 4.1 trips a year
Spot check: the tree in Figure 3.8-43 gives 68 trips in 1,000 storm days ✓.
↓
Step 2 · (b) Rock given a trip (Eq. 3.8-8)
0.019 / 0.068
P(R|T) = 0.28: about 1 trip in 3.6 is real
Spot check: 19 real trips out of 68 in the tree ✓.
↓
Step 3 · (c) Rock with no trip
0.05 × 0.02 / (1 − 0.068) = 0.001 / 0.932
P(R|T̄) = 0.0011 per storm day; 60 × 0.02 × 0.05 = 0.06 missed rockfalls a year (about 1 in 17 years)
↓
Step 4 · (d) Fewer false trips
P(T) = 0.019 + 0.01 × 0.98 = 0.0288; P(R|T) = 0.019 / 0.0288
P(R|T) = 0.66; trips fall to 1.7 a year
Spot check: the real trips (1.14 a year) are unchanged; only the false ones (2.9 a year to 0.6 a year) drop.
↓
Solution
About 28% of trips are real rockfalls today; cutting false trips to 1% makes about 66% real, without changing how many real rockfalls are caught.

Solution

About 28% of trips are real rockfalls today; cutting false trips to 1% makes about 66% real, without changing how many real rockfalls are caught.

The fence works: it catches about 95% of the rockfalls that reach the track, leaving roughly one undetected rockfall in 17 years, and that residual figure, not the trip count, is what the rating should carry as the likelihood of a train meeting rock. The complaint from the crews is also correct: with rockfall rare and false trips common, most trips are false even though the fence is a good detector. That is Bayes’ theorem at work, and it is the same reason a screening test for a rare condition gives many false positives. The risk is behavioral: when most trips are false, crews start to treat a trip as a nuisance. Every trip must still be handled as real, and the fence should be maintained to keep the false-trip rate low, because trust in the alarm is part of the protection. Cutting the false-trip rate from 5% to 1% roughly doubles the share of trips that are real and saves about 2.4 restricted-speed inspections a year, which can be set against the maintenance cost in the life-cycle comparison (Section 3.8.40). Record the detection rate and the false-trip rate from the signal logs; they are the inputs that make this calculation site-specific.

Open the detector and inspection evidence (Bayes) calculator →

For railroad work: Treat a probability in a rating as a statement about the evidence available when it was made. When an inspection, a monitoring reading or a detector record arrives, update it explicitly (Eq. 3.8-8) and record the prior, the evidence and the result in the rationale (Section 3.8.43). Keep detector logs that separate real trips from false ones; without them the reliability of the protection cannot be stated.

Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 2 (Sections 2.3 and 2.4, statistical independence and conditional probability, including Bayes’ theorem); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (Greek alphabet; probability definitions and theorems).

3.8.32 Counting Hazard Events: Poisson, Exponential and Extreme-Value Distributions

Most ground hazard data are counts and extremes: rockfalls per mile per year, washouts per decade, the largest daily rainfall or river stage in each year. Each kind of data has a distribution that fits it and a way of turning the record into the annual probabilities used in the ratings. Table 3.8-63 lists the distributions that cover nearly all ground hazard work.

Table 3.8-63. Probability distributions for ground hazard data (after Soong 2004, Ch. 6 and 7)
DistributionUse in risk assessmentMean; varianceNotes
Normal (Gaussian)Sums of many small effects: factor of safety from many parameters; averages of test resultsμ; σ²Can go negative, so a poor model for strengths with high COV
LognormalStrengths, permeability, settlement; any positive quantity that is a product of factorsexp(λ + ζ²/2); see Eq. 3.9-4Used for the lognormal reliability index in Section 3.9.15
BinomialNumber of years with an event in n years; number of sites that fail out of a groupnp; np(1 − p)The 1 − (1 − p)n form of Section 3.8.30
PoissonNumber of events in a time or length: rockfalls, washouts, sinkholes per mile per yearλt; λtMean equals variance; check for clustering (variance much larger than the mean)
ExponentialTime between Poisson events; time to the next failure1/λ; 1/λ²Memoryless: a long quiet period does not make the next event “due”
Gumbel (Extreme Value Type I)Annual maximum rainfall, flood flow or stageu + 0.5772/α; 1.645/α²Basis of the frequency factor in Appendix F; Eq. 3.8-10
Weibull (Extreme Value Type III)Minimum values and lifetimes: weakest link, time to deterioration of an assetdepends on shape kShape k < 1: early failures; k > 1: wear-out
BetaBounded quantities: a probability or proportion estimated from judgment; PERT cost and durationdepends on two shape parametersThree-point (low, most likely, high) estimates of cost and duration

3.8.32.1 Events in time and along the track

Equation 3.8-9. Poisson distribution of event counts

P(X = k) = (λt)k e−λt / k!;   P(X ≥ 1) = 1 − e−λt;   time between events: P(T > t) = e−λt

λ = rate (events per year, or per mile per year with t in mile-years); k = number of events. The same form applies along the track: with λ per mile, t becomes the length of track considered. Events must be independent; storms that cause several rockfalls at once break this assumption, so count storm events rather than individual rocks if they cluster.

A record of N events in t years gives λ ≈ N/t. A short record gives a rough rate: for N = 3 the 90% confidence range on the true rate is about 0.8/t to 7.8/t, so three events in ten years is consistent with anything from one in twelve years to almost one a year. Report the range, not just the point value, and see Section 3.8.33 for the case of no events at all.

3.8.32.2 Annual maxima: rainfall, floods and river stage

Equation 3.8-10. Gumbel (Extreme Value Type I) distribution of annual maxima

F(x) = exp{−exp[−α(x − u)]};   α = 1.2825/s,  u = x̄ − 0.4500 s
xT = u − (1/α) ln[−ln(1 − 1/T)]

x̄ and s are the mean and standard deviation of the annual maxima (method of moments). xT is the value with return period T. The constants 1.2825 = π/√6 and 0.4500 = 0.5772/1.2825 come from the Euler constant 0.5772. For flood flows at a gauge, USGS Bulletin 17C (Log-Pearson Type III) is the standard (Section 3.5.12); Gumbel is a quick check and suits rainfall depths and river stages.

For example, 25 years of annual maximum 24-hour rainfall at a gauge near a cut with mean 3.2 in. and standard deviation 0.9 in. give α = 1.425 in.−1 and u = 2.80 in., so the 25-year value is 2.80 + 3.20/1.425 = 5.0 in. If the cut has responded at 4.5 in. (its response level, Section 3.8.23), that depth has a return period of about 12 years and the trigger rates T = 3 (Table 3.8-9).

3.8.32.3 Worked example

Example 3.8-9: Rockfall Counts Along a Cut Segment: Rate, Hot Spot and Frequency Index

Problem Statement

A Class I railroad located in Pennsylvania has a 6-mile segment of rock cuts along a river. The maintenance records show 14 rockfalls that reached the track in the last 10 years, 6 of them in mile 3 (Figure 3.8-44). The segment is being rated for a rockfall program. The engineer must turn the counts into annual probabilities, decide whether mile 3 is genuinely worse than the rest or just unlucky, and assign the frequency index F of Table 3.8-14.

0246112263241526mean 2.33 per mileMile of segmentRockfalls in 10 yearsIs mile 3 really worse, or chance?Given14 rockfalls onto the track in 10 years, 6 milesMile 3: 6 of the 14Events random in time (Poisson)Required(a) λ and P(≥ 1) per year(b) P(≥ 3) in a year(c) Is mile 3 unusual?(d) Frequency index F, mile 3 and the rest
Figure 3.8-44. Example 3.8-9: rockfalls onto the track by mile over 10 years.

Given

VariableValueDescription
N14 rockfallsRockfalls onto the track in the record
t10 yearsLength of the record
L6 milesSegment length
N36 rockfallsRockfalls in mile 3
ModelPoissonRockfalls independent and random in time and along the segment

Required

  • (a) Annual rate for the segment and the chance of at least one rockfall in a year
  • (b) Chance of 3 or more rockfalls in one year
  • (c) Whether 6 rockfalls in one mile is unusual if the segment were uniform
  • (d) Frequency index F for mile 3 and for the other 5 miles

Equations

  1. Eq. 3.8-9 (Poisson): P(X = k) = (λt)k e−λt / k!; P(X ≥ 1) = 1 − e−λt
  2. λ = N / t (events per year), or N / (t L) per mile per year

Steps

Step 1 · (a) Segment rate
λ = 14 / 10; P(≥ 1) = 1 − e−1.4
λ = 1.4 a year; P(≥ 1 in a year) = 0.75
Spot check: mean time between rockfalls 1/1.4 = 0.71 year, consistent with 14 in 10 years ✓.
↓
Step 2 · (b) Three or more in a year
1 − e−1.4(1 + 1.4 + 1.4²/2) = 1 − 0.2466 × 3.38
P(≥ 3) = 0.17, about 1 year in 6
↓
Step 3 · (c) Mile 3 against a uniform segment
Expected per mile in 10 years: 14/6 = 2.33. P(X ≥ 6 | 2.33) = 1 − Σk=0..5 P(k)
P = 0.032 for a mile chosen in advance; but the chance that some one of 6 miles reaches 6 is 1 − (1 − 0.032)6 = 0.18
Spot check: picking the worst mile after the fact makes a 3% coincidence an 18% one, so the count alone is suggestive, not proof.
↓
Step 4 · (d) Frequency index
Mile 3: 6/10 = 0.6 a year (1 in 1.7 years). Other miles: 8/(10 × 5) = 0.16 a mile a year (1 in 6.3 years)
Mile 3: F = 4 (1 in 1 to 1 in 5 years); other miles: F = 3 (1 in 5 to 1 in 25 years), if the field evidence supports the split
↓
Solution
The segment averages 1.4 rockfalls a year (75% chance of at least one in any year). Mile 3 rates F = 4 and the rest F = 3, provided field mapping confirms a physical reason for mile 3.

Solution

The segment averages 1.4 rockfalls a year (75% chance of at least one in any year). Mile 3 rates F = 4 and the rest F = 3, provided field mapping confirms a physical reason for mile 3.

The counts show a real hazard with a 75% annual chance of rock on the track somewhere in the segment, and about one year in six with three or more. Mile 3 stands out, but six events in one of six miles would happen by chance about one time in five, so the statistics alone cannot justify spending the program on it. The decision should rest on the field evidence: if mile 3 has an adverse joint set, overhangs, a steeper or higher face, or a ditch too narrow to catch what falls (Section 3.8.29), the split rating of F = 4 for mile 3 and F = 3 for the rest is justified and mile 3 goes first. If the cuts look alike, rate the segment uniformly and keep counting; another five years of records will separate a real hot spot from a run of bad luck. Rates per mile also suit the exposure calculations of Section 3.8.30: the Poisson form there (Pn ≈ 1 − e−n/T) is Eq. 3.8-9 with k = 0.

Open the hazard event rate and hot spot (Poisson) calculator →

For railroad work: Keep the incident log by milepost and date, and record each rockfall, washout or sinkhole even when it causes no delay; without that log the frequency index is a guess. Count storm events where events cluster, compare each mile with the segment average before declaring a hot spot, and check the statistics against the field evidence before moving money. Convert rates to the band levels of Tables 3.8-9 and 3.8-14 with the arithmetic of Section 3.8.30.

Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 6 (Poisson distribution, including spatial distributions), Ch. 7 (exponential, lognormal, beta and extreme-value distributions); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (binomial, normal and Poisson distributions).

3.8.33 Small Data Sets: Confidence Limits, Sample Size and Goodness of Fit

Risk assessments are built on small data sets: a handful of strength tests, a few years of monitoring, a failure record with few or no failures in it. Small samples give means and rates that are themselves uncertain. This section gives the tools to state that uncertainty, to decide how many more tests are worth doing, to interpret a record with no events, and to check whether an assumed distribution fits the data.

3.8.33.1 Confidence limits on a mean

Equation 3.8-11. Confidence limits on a mean from n tests (Student’s t)

two-sided: x̄ ± tα/2, n−1 s/√n;   one-sided lower limit: x̄ − tα, n−1 s/√n

x̄, s = sample mean and standard deviation (n − 1 in the denominator of s); t from Table 3.8-64. A one-sided 95% lower limit on the mean is the “cautious estimate of the mean” used in limit state codes for properties that govern over a large volume of ground. For a property that governs locally, use a lower fractile of the individual values instead, such as x̄ − s or x̄ − 1.645 s.

Table 3.8-64. Student’s t multipliers
Degrees of freedom n − 1One-sided 90% (t0.10)One-sided 95% (t0.05), two-sided 90%Two-sided 95% (t0.025)
13.0786.31412.706
21.8862.9204.303
31.6382.3533.182
41.5332.1322.776
51.4762.0152.571
61.4401.9432.447
71.4151.8952.365
81.3971.8602.306
91.3831.8332.262
101.3721.8122.228
151.3411.7532.131
201.3251.7252.086
301.3101.6972.042
∞ (normal z)1.2821.6451.960

With two or three tests t is so large that the lower limit is often meaningless, which is the statistical reason for testing each layer that matters at least five or six times (Chapter 5.2).

3.8.33.2 How many tests

Equation 3.8-12. Number of tests for a required precision of the mean

n ≥ (tα/2, n−1 s / E)²   (first estimate with z: n ≈ (1.645 s/E)² for 90%)

E = acceptable half-width of the confidence interval, in the units of the property; s from the tests so far or from a published COV (Table 3.9-9) times the expected mean. Because t depends on n, solve by trial. Halving E multiplies the number of tests by about four.

3.8.33.3 A record with no failures

Equation 3.8-13. Upper confidence bound on an event rate when none has been observed

pU = 1 − α1/m ≈ −ln(α)/m;   95%: pU ≈ 3/m;   90%: pU ≈ 2.3/m

m = number of independent trials, such as site-years or structure-years of record. The approximation is the “rule of three.” It treats every site-year as alike; a group that mixes high and low hazard sites can hide a few bad sites behind many good ones.

No failures in a record does not mean a probability of zero. A site with 20 years of quiet history can still have a 1 in 7 annual chance of failure at 95% confidence (3/20), which is a frequency index of F = 3 (Table 3.8-14) on the record alone. Field evidence is what moves it lower.

3.8.33.4 Checking the distribution: goodness of fit

Before rates or extreme values are extrapolated, check that the assumed distribution fits the record. The chi-squared test groups the data into k classes, compares the observed counts Oi with the counts Ei expected from the fitted distribution, and computes χ² = Σ(Oi − Ei)²/Ei. The fit is rejected at significance α if χ² exceeds the tabulated value for k − 1 − r degrees of freedom, where r is the number of parameters estimated from the data; keep Ei at 5 or more by merging classes. The Kolmogorov–Smirnov test compares the cumulative curves directly and works better for the small samples common in geotechnical work. A quick graphical check is to plot the data on probability paper (normal, lognormal or Gumbel): a straight line supports the model, and curvature at the tail warns against extrapolating far beyond the record. For Poisson counts, a variance much larger than the mean (for example, counts by year of 0, 0, 5, 0, 1, 0, 6) indicates clustering by storm, and the count should be by storm event.

3.8.33.5 Trends and regression

Monitoring data in a risk assessment are usually fitted with a straight line: settlement against log time, inclinometer displacement against date, crack width against season. Least squares gives the slope and intercept; the standard error of the slope gives its confidence interval (t with n − 2 degrees of freedom), and a slope whose interval includes zero has not been shown to be a trend. Extrapolating a fitted line to a future date carries a prediction interval that widens with distance from the data, so a forecast of when movement will reach an action level should be stated with its range (Chapter 4.5, the observational method).

3.8.33.6 Worked example

Example 3.8-10: Six Strength Tests and No Recorded Failures: How Much Do They Tell Us?

Problem Statement

A Class I railroad located in Mississippi is rating a 22-ft embankment on a soft clay foundation for a speed increase. Six unconsolidated-undrained (UU) triaxial tests on the foundation clay are available (Figure 3.8-45). The railroad’s records show no failures in 25 years on 48 embankments of similar height on the same formation. The engineer must state the design strength with its uncertainty, decide whether more testing is needed, and say what the clean failure record actually proves.

8009001,0001,1001,2001,300mean 1,10395% lower limit = ?mean − s = ?Undrained shear strength su (psf)Records: 48 similar fills, 25 years, no failuresGiven6 UU tests, s​u (psf):1,150; 980; 1,320;870; 1,060; 1,240Target: mean within ±10% at 90% confidence48 fills × 25 yr, 0 failuresRequired(a) x̄, s, COV(b) 95% lower limit on mean(c) Tests for ±10%(d) Upper bound on the annual failure rate
Figure 3.8-45. Example 3.8-10: six undrained strength results for an embankment foundation clay, and the failure record for similar fills.

Given

VariableValueDescription
su1,150; 980; 1,320; 870; 1,060; 1,240 psfUU test results, n = 6
E±10% of the meanRequired precision of the mean
Confidence90% two-sided (precision); 95% one-sided (lower limit)Confidence levels chosen for the rating
m48 fills × 25 years = 1,200 fill-yearsExposure in the failure record, with zero failures

Required

  • (a) Sample mean, standard deviation and COV, compared with published values
  • (b) One-sided 95% lower confidence limit on the mean, and the mean minus one standard deviation
  • (c) Number of tests needed to know the mean within ±10% at 90% confidence
  • (d) The 95% upper bound on the annual failure rate from the clean record

Equations

  1. x̄ = Σx/n; s = √[Σ(x − x̄)²/(n − 1)]; COV = s/x̄
  2. Eq. 3.8-11: x̄ − tα, n−1 s/√n (one-sided lower limit)
  3. Eq. 3.8-12: n ≥ (tα/2, n−1 s / E)² (solve by trial)
  4. Eq. 3.8-13: pU = 1 − α1/m ≈ 3/m for α = 0.05

Steps

Step 1 · (a) Sample statistics
Σx = 6,620; x̄ = 6,620/6; Σ(x − x̄)² = 139,333; s = √(139,333/5)
x̄ = 1,103 psf; s = 167 psf; COV = 15%
Spot check: 15% lies within the 13 to 40% range for undrained strength in Table 3.9-9 ✓.
↓
Step 2 · (b) Lower limit on the mean (Eq. 3.8-11)
t0.05, 5 = 2.015 (Table 3.8-64); 1,103 − 2.015 × 167/√6 = 1,103 − 137
95% lower limit = 966 psf; x̄ − s = 936 psf
↓
Step 3 · (c) Tests for ±10% (Eq. 3.8-12)
E = 110 psf. n = 8: t = 1.895, (1.895 × 167/110)² = 8.2 > 8, no. n = 9: t = 1.860, (1.860 × 1.513)² = 7.9 ≤ 9, yes
n = 9: three more tests
Spot check: with n = 9, half-width = 1.860 × 167/3 = 104 psf ≤ 110 psf ✓.
↓
Step 4 · (d) Zero-failure bound (Eq. 3.8-13)
m = 1,200 fill-years; 1 − 0.051/1,200
pU = 0.0025 a year, about 1 in 400; 3/1,200 gives the same
↓
Solution
Mean 1,103 psf (COV 15%); use 966 psf as the 95% lower limit on the mean; three more tests would pin the mean within ±10%. The clean record limits the annual failure rate of similar fills to about 1 in 400 or less, at 95% confidence.

Solution

Mean 1,103 psf (COV 15%); use 966 psf as the 95% lower limit on the mean; three more tests would pin the mean within ±10%. The clean record limits the annual failure rate of similar fills to about 1 in 400 or less, at 95% confidence.

Six tests give a mean of 1,103 psf, but with six results the true mean could reasonably be as low as 966 psf, and that is the value to carry into the stability check for the speed increase. It is close to the mean minus one standard deviation (936 psf) recommended by GEC 5 (Section 3.9.15), but the two measure different things: the confidence limit describes uncertainty in the average strength along the failure surface, which governs a large slide, while the mean minus one standard deviation covers the scatter of individual values, which matters for a short, local failure. Three more tests would narrow the uncertainty enough to justify a design strength nearer the mean; at a few hundred dollars a test against a berm or a slower speed, that is usually worth doing.

The clean record is evidence, but weaker evidence than it looks. With 1,200 fill-years and no failures, the true annual failure rate could still be as high as about 1 in 400 at 95% confidence (the “rule of three”), which is frequency index F = 1 (less than 1 in 100 years, Table 3.8-14) for the group. It does not prove that this embankment, under faster and heavier traffic, will behave the same; it shows that similar fills under past loading have rarely failed. Use it as the prior in a Bayesian update (Section 3.8.31) and let the site-specific strength and stability analysis carry the rating.

Open the small data set confidence and number of tests calculator →

For railroad work: State design parameters with their number of tests and confidence limits, not as single values, and report any failure rate with its record length. When a client cites a clean history as the reason not to act, convert it to an upper bound with Eq. 3.8-13; the exposure of the record, not the absence of failures, is what decides how much it proves. Combine these results with the Taylor series probability of failure in Section 3.9.15.

Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 9 (sample statistics, interval estimation and the t-distribution), Ch. 10 (chi-squared and Kolmogorov–Smirnov goodness-of-fit tests), Ch. 11 (linear regression and confidence intervals for regression coefficients); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (tables of the t, χ² and normal distributions).

3.8.34 Semi-Quantitative Landslide Risk Scores as a Cross-Check

Sections 3.8.19 to 3.8.21 rank sites by R = F × S. Hearn's Slope Engineering for Mountain Roads sets out two published semi-quantitative systems for road slopes that do the same job and make a useful cross-check. Both follow the definitions of Varnes and of the Australian Geomechanics Society. Risk combines the hazard (its magnitude and probability) with the value of the assets exposed and their vulnerability, the degree of loss if the hazard occurs. The GHRM severity S folds value and vulnerability into one scale. Hearn keeps them separate, so a site where the rankings disagree usually points to a judgment about consequence that deserves a second look. Hearn is explicit that neither system gives absolute risk; they are for recording slopes and putting stabilization work in order.

3.8.34.1 Method

Table 3.8-65. Table A4.1 relative risk (after Hearn, developed for mountain roads in Laos)
Component0123
Magnitude M–Small: shallow, up to about 650 cu ydModerateLarge: deep, about 6,500 cu yd or more
Probability in a 20-year design life PNot expectedPossibleExpectedDefinite
Value of elements at risk Va–Slope works and ditchSlope works, ditch and up to half the formation widthWhole formation and adjacent structures
Vulnerability VuNo effectDeformation or blockagePartial lossTotal loss

Relative risk R = M × P × Va × Vu, 0 to 81. Hearn's road terms (side drain, carriageway) are given here as their track equivalents.

Table 3.8-66. Table D1.3 prioritization (after Hearn and Hunt)
Asset value classVulnerability highModerateLow
1: heavy traffic, strategic access, buildings in the hazard area, or access lost over 3 days543
2: moderate traffic or access, buildings on the margin, access lost 1 to 3 days432
3: light traffic, network only, access lost under 1 day321

Entries are the loss value. Risk number = loss value × probability level: 5 high (active indicators, or occurrence at least every 2 years), 3 moderate (landslide morphology or previous movement; periodic, every 2 to 5 years), 1 low (no evidence of movement). Ranks: 20 to 25 Very High, preventative works immediately; 10 to 15 High, preventative works in the following dry season; 5 to 9 Moderate, monitoring; 1 to 4 Low, no action.

3.8.34.2 Worked example

Example 3.8-11: Two Slides Ranked with Hearn's Relative Risk Score

Hearn's own illustration of Table A4.1 compares two slides on one road. Put in railroad terms, a small slide below the track is undermining a retaining wall, and a large slide above the track could bury it. The cross-check asks which carries more risk, and whether the answer agrees with the F × S ranking.

TrackSlide 1: small, below the track,undermining a wall: M1 P2 Va3 Vu3Slide 2: large, above the track:M3 P1 Va3 Vu1R = ?GivenSlide 1: M = 1, P = 2, Va = 3, Vu = 3Slide 2: M = 3, P = 1, Va = 3, Vu = 1Scores from Hearn Table A4.1RequiredRelative risk of each slideWhich ranks higher, and whyAgreement with F × S rankingBlack = given; red = required
Given and required for Example 3.8-11.

Given

VariableValueDescription
M1 (slide 1); 3 (slide 2)Magnitude of the failure
P2; 1Probability of failure
Va3; 3Value of the asset affected
Vu3; 1Vulnerability: 3 where support is removed, 1 where the track is only blocked

Required

  • Relative risk score of each slide
  • Which ranks higher and why
  • Whether the order agrees with the GHRM severity rules

Equations

  1. Eq. 1: RH = M × P × Va × Vu — Hearn's relative risk, Table A4.1

Steps

Step 1 · Slide 1, below the track (Eq. 1)
Uses: M, P, Va, Vu
RH = 1 × 2 × 3 × 3
RH = 18
Spot check: Matches Hearn's published 18 (Table 3.8-67).
↓
Step 2 · Slide 2, above the track (Eq. 1)
Uses: M, P, Va, Vu
RH = 3 × 1 × 3 × 1
RH = 9
Spot check: Matches Hearn's published 9.
↓
Step 3 · Compare
Uses: Steps 1 and 2
18 / 9
Slide 1 carries twice the relative risk
Spot check: Vulnerability alone accounts for the ratio: 3/1 = 3, offset in part by magnitude 1/3 and probability 2/1.
↓
Solution
Slide 1 (18) outranks slide 2 (9).

Solution

The small slide below the track scores 18 and the large slide above it scores 9: the smaller failure carries twice the risk, because it removes support while the larger one only has to be cleared.

The same reasoning runs through Table 3.8-15, which places loss of track support among the most severe consequences, and through the rule of Section 3.8.20 that the consequence governs. In Hearn's field example, cutting a failed slope back to the dip of the bedding lowered its score from 18 to 12, not lower, because bedding-plane sliding was still possible and tension cracks were still opening.

The three scenarios Hearn uses for Table D1.3 reproduce in the calculator: a moderately likely slide above a busy road scores 15 (High); a wall being undermined by seepage on the only access to a hospital scores 25 (Very High); and a debris flow with buildings in its path but no sign of activity scores 5 (Moderate).

Run both systems on the same sites when a program is being set. Where Hearn's order and the F × S order disagree, find out why before accepting either: the usual cause is a consequence judgment, such as a failure below the track rated as a minor blockage, or a probability scored on morphology alone. Record the reason in the rationale (Section 3.8.43).

Open the landslide risk score calculator →
Hearn's Table A4.1 relative risk (magnitude, probability, value and vulnerability) and Table D1.3 risk number with its rank and action, for any number of sites, sorted for comparison with the F × S ranking.

3.8.34.3 Verification against the published examples

Table 3.8-67. Published and calculated scores
ExampleHearnCalculator
Table A4.1: small slide undermining wall foundations1818
Table A4.1: large slide blocking the road from above99
Table D1.5 scenario 1: slide above a road carrying over 800 vehicles a day15, High15, High
Table D1.5 scenario 2: retaining wall failure, access to a hospital25, Very High25, Very High
Table D1.5 scenario 3: debris flow, buildings in the hazard area5, Low (as printed)5, Moderate

Hearn's Table D1.5 lists scenario 3 as Low, but a risk number of 5 falls in the 5 to 9 Moderate range of Table D1.3; the calculator follows Table D1.3.

3.8.34.4 How the scales compare

Table 3.8-68. Hearn's probability levels beside the GHRM frequency index
Hearn (Table D1.3)DescriptionClosest GHRM level (Table 3.8-14)
High (5)Adverse structure, seepage, toe erosion, fresh scarps, bulges or cracks; occurrence at least every 2 yearsF = 4 or 5 (Emerging or Occurring)
Moderate (3)Landslide morphology but no visible movement; previous movement; periodic occurrence every 2 to 5 yearsF = 2 by evidence (Dormant); F = 4 by frequency
Low (1)No evidence of movement, no sources, stable founding conditionsF = 1 (Inactive)

Hearn's moderate level mixes evidence of past movement with a frequency of 2 to 5 years, which the GHRM scales keep apart. A site rated by frequency and one rated by morphology can therefore land in the same Hearn level but in different F levels.

3.8.34.5 Sources in the library

Paraphrased from these documents in the reference library.

  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section A4 (G.J. Hearn), landslide susceptibility, hazard and risk, Table A4.1 and Figure A4.1Find source ↗Library entry
  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section D1 (G.J. Hearn and T. Hunt), slope management, Tables D1.3 to D1.5Find source ↗Library entry
3.8.35 Acceptable Probability of Failure by Consequence

The frequency index asks how often a site will fail; design asks how often is acceptable. Wyllie and Mah point out that probabilistic design needs accepted ranges of probability of failure, just as deterministic design has accepted factors of safety, and they reproduce Whitman's chart of annual probability of failure against lives lost for a range of engineered works. Look adds that a probability is easier for owners and other disciplines to understand than a factor of safety. He also notes that a higher factor of safety does not by itself mean a lower probability of failure (his example compares 1.3 and 1.4), and that existing and new slopes must be judged by different criteria. Hearn quotes the Norwegian national guidelines, which set a maximum annual probability of failure for each consequence class, and cautions that the approach needs good records of the triggering events. This section brings those benchmarks together and connects them to the factor of safety through the reliability method of Section 3.9.15.

3.8.35.1 Method

Equation 3.8-14. From factor of safety to annual and lifetime probability

βLN = ln[F/√(1 + VF²)] / √ln(1 + VF²);   Pf = Φ(−βLN)

pannual ≈ Pf / Tc;   Plife = 1 − (1 − pannual)n

Pf is the probability that F is below 1.0 under the condition analyzed (for example, the 10-year storm water level), with the most likely factor of safety F and its coefficient of variation VF from Section 3.9.15. If failure is credible only when that condition occurs, dividing by its return period Tc gives a first estimate of the annual probability. Conditions more severe than the one analyzed add to it, so the estimate is a lower bound unless they are analyzed too.

Table 3.8-69. Published benchmarks for probability of failure
SourceSituationProbability of failure
Norwegian guidelines (Nilsen 2000, in Hearn Table C3.5), annualConsequence class 1 minor / 2 medium / 3 major10−2 / 10−3 / less than 10−4
Skipp (1992), in Look Table 10.14, annual, rock slopesCatastrophic / major / moderate / minor failure1 × 10−4 / 5 × 10−4 / 1 × 10−3 / 5 × 10−3 (minor: unmonitored permanent urban slopes with free access)
Santamarina and others (1992), in Look Table 10.15Existing large highway cut, no potential life loss, minor costs1 to 2 × 10−2 (under 10−2 for a new cut)
Acceptable in most cases, no potential life loss / acceptable for all slopes, potential life loss / unnecessarily low10−3 / 10−4 / under 10−5
Whitman (1984), in Wyllie and Mah Figure 1.11, annualClosely managed mine slopes, little risk to life / dams with several hundred lives at risk10−1 to 10−2 / 10−4 to 10−5
AGS (2000), in Look Table 10.13, annual risk of loss of lifeExisting slope: person most at risk / average / new slope: person most at risk / average10−4 / 10−5 / 10−5 / 10−6

The AGS values are tolerable risks to an individual's life, not probabilities of slope failure; the individual risk is the failure probability multiplied by the chance that the person is present and is killed.

Table 3.8-70. GEO (1984) factors of safety for a 10-year return period rainfall (in Look Tables 14.5 and 14.6)
Economic riskRisk to life negligibleLowHigh
New slopes: negligibleover 1.11.21.4
New slopes: low1.21.31.5
New slopes: high1.41.51.6
Existing slopes (any economic risk)over 1.11.21.3

3.8.35.2 Worked example

Example 3.8-12: Annual Probability of Failure of a New Fill Slope

A new main-line fill slope is analyzed for the 10-year storm water level and gives a most likely factor of safety of 1.3. The analysis is turned into an annual probability of failure so that it can be compared with consequence-based benchmarks, not only with a target factor of safety.

10-yr storm water levelMain lineF = 1.0F = 1.3, COV 15%P(F < 1) = ?GivenMost likely F = 1.3 at the 10-yr water levelCOV of F = 15%Service life 50 yr; medium consequenceLimits: Norway 10⁻³ (medium); GEO F = 1.5RequiredP(F < 1), annual and 50-yr probabilityWhether the slope meets either benchmarkF needed for 10⁻³; result at F = 1.5Black = given; red = required
Given and required for Example 3.8-12.

Given

VariableValueDescription
F1.3Most likely factor of safety for the 10-year water level
VF15%Coefficient of variation of F
Tc10 yearsReturn period of the condition analyzed
N50 yearsService life
Limits10−3/yr; F = 1.5Norwegian medium-consequence limit; GEO factor of safety for high economic, low life risk

Required

  • Probability that F is below 1.0 in the condition, the annual probability and the 50-year probability
  • Whether the slope meets the Norwegian limit and the GEO factor
  • The factor of safety that just meets 10−3, and the result at F = 1.5

Equations

  1. Eq. 1: β = ln[F/√(1 + VF²)] / √ln(1 + VF²) — lognormal reliability index (Equation 3.8-14)
  2. Eq. 2: Pf = Φ(−β) — probability that F < 1 in the condition
  3. Eq. 3: pa = Pf / Tc — annual probability
  4. Eq. 4: PN = 1 − (1 − pa)N — lifetime probability

Steps

Step 1 · Reliability index (Eq. 1)
Uses: F, VF
√ln(1.0225) = 0.1492; ln(1.3/1.0112) = 0.2512
β = 0.2512 / 0.1492 = 1.684
Spot check: For small V, β ≈ ln F / V = 0.262 / 0.15 = 1.75, slightly higher, as expected.
↓
Step 2 · Probability in the condition (Eq. 2)
Uses: β
Pf = Φ(−1.684)
Pf = 4.61%
Spot check: Φ(−1.645) = 5%, so a slightly larger β gives slightly less than 5%.
↓
Step 3 · Annual and lifetime probability (Eq. 3, 4)
Uses: Pf, Tc, N
pa = 0.0461/10; P50 = 1 − (1 − 0.00461)50
pa = 4.6 × 10−3 (1 in 217 years); P50 = 20.6%
Spot check: 50 × 0.00461 = 0.23; the exact value is lower because events cannot overlap.
↓
Step 4 · Compare and redesign (Eq. 1–3)
Uses: Limits
At F = 1.5: β = 2.643, Pf = 0.41%; for pa = 10−3: Pf = 1%, β = 2.326, F = 1.43
Fails both now; F = 1.5 gives 4.1 × 10−4; 10−3 is met at F ≈ 1.43
Spot check: Table 3.8-71 gives 4.1 × 10−4 at F = 1.5 and 15%, the same value.
↓
Solution
4.6 × 10−3 a year at F = 1.3; F = 1.5 meets both benchmarks.

Solution

At F = 1.3 and a COV of 15%, the annual probability of failure is about 4.6 × 10−3 (1 in 217 years), or 20.6% over 50 years. That fails the Norwegian medium-consequence limit of 10−3 and the GEO factor of 1.5. Raising F to 1.5 at the same uncertainty gives about 4.1 × 10−4; the 10−3 limit is reached at F of about 1.43, so here the GEO value is the stricter of the two.

Choose the benchmark by consequence. Where the severity is 4 or 5 (Table 3.8-15), a derailment with possible injury, fatality or a hazardous materials release, the benchmarks for potential loss of life apply, not those for nuisance failures. Report the annual probability, its return period and the lifetime probability together, and state the condition it was computed for.

Open the acceptable probability of failure calculator →
Annual probability of failure, entered or estimated from a factor of safety, its COV and the return period of the condition analyzed, with the lifetime probability, the F band, the Norwegian and Skipp benchmarks and the GEO factor of safety for the consequence.

3.8.35.3 Factor of safety, uncertainty and annual probability

The table shows how strongly the annual probability depends on the uncertainty in F as well as on F itself. At a coefficient of variation of 10%, a factor of safety of 1.3 already gives an annual probability below 10−3. At 20%, even a factor of 1.6 gives slightly more than 10−3. The investigation and testing that narrow the uncertainty (Section 3.9.15) are worth as much as a higher factor of safety, and Look's warning about comparing factors of safety alone follows directly.

Table 3.8-71. Annual probability of failure for a 10-year design condition, from the calculator
F (most likely)COV of F = 10%15%20%
1.34.9 × 10−44.6 × 10−31.1 × 10−2
1.44.4 × 10−51.5 × 10−35.5 × 10−3
1.53.0 × 10−64.1 × 10−42.6 × 10−3
1.61.6 × 10−71.0 × 10−41.1 × 10−3
1.82.6 × 10−105.5 × 10−62.1 × 10−4
2.02.6 × 10−132.4 × 10−73.4 × 10−5

3.8.35.4 Annual probability against factor of safety

The figure plots the same results as the logarithm of the annual probability. The dashed black line is the Norwegian limit for a medium consequence (10−3); the dashed grey line is the limit for a major consequence (10−4).

1.21.41.61.82-8-6-4-20Most likely factor of safety F (10-year design condition)log10 of annual probability of failureCOV of F = 10%COV of F = 15%COV of F = 20%
Figure 3.8-46. Annual probability of failure against the most likely factor of safety for three coefficients of variation, with the Norwegian limits for medium and major consequences.

3.8.35.5 Sources in the library

Paraphrased from these documents in the reference library.

  • D.C. Wyllie and C.W. Mah, Rock Slope Engineering: Civil and Mining, 4th edition: Section 2.3.4, probabilistic design methods, and Figure 1.11 (Whitman 1984) (Current edition: D.C. Wyllie, Rock Slope Engineering: Civil Applications, 5th edition, CRC Press, 2017; this section cites the edition held in the library.)Find source ↗
  • B.G. Look, Handbook of Geotechnical Investigation and Design Tables (2007): Tables 10.13 to 10.16, tolerable risk and probability of failure; Tables 14.5 and 14.6, GEO factors of safety (Current edition: 2nd edition, CRC Press, 2014; this section cites the edition held in the library.)Find source ↗
  • Slope Engineering for Mountain Roads (Geological Society of London, Engineering Geology Special Publication): Section C3.2, Table C3.5, acceptable annual probability of failure in NorwayFind source ↗Library entry
  • J.M. Duncan, S.G. Wright and T.L. Brandon, Soil Strength and Slope Stability, 2nd edition: Chapter 13, reliability and probability of failure (lognormal method)Find source ↗
3.8.36 Basis and Rationale of the Risk Ratings

This section explains why each level of each scale, and each of the five ratings, sits where it does; checks the logic of the scales and the matrix; and compares the method with published practice. It contains no project or client data. Every example in this chapter is generic.

3.8.36.1 Why Five Levels

Five is the number of field conditions an engineer can tell apart consistently from what is seen on the ground: not moving and no cause; moved before; cause present; starting to move; failing. Fewer levels would lump an emerging failure with one under way. More would ask for distinctions that visual evidence cannot support, and two engineers would disagree more often. An odd number also gives a middle level, 3, which is the default where data are missing (Section 3.8.22.1). The risk score R = F × S (1 to 25) is an intermediate number whose only job is to place the site in one of the five ratings (Table 3.8-72).

Table 3.8-72. Risk rating levels
LevelRatingRisk score RMatrix cells (F × S)Required response (Table 3.8-17)
5Severe20–254×5, 5×4, 5×5Act now
4High12–163×4, 4×3, 3×5, 5×3, 4×4Act soon
3Elevated6–102×3, 3×2, 2×4, 4×2, 3×3, 2×5, 5×2Plan
2Guarded3–51×3, 3×1, 1×4, 4×1, 2×2, 1×5, 5×1Watch
1Low1–21×1, 1×2, 2×1Routine inspection only

3.8.36.2 Frequency Index Levels

The frequency index describes the state of the hazard, because that is what the engineer can see. The indicative annual frequencies attach a number to each state. The 20-year column turns the annual frequency into the chance of at least one failure over a typical planning horizon, 1 − (1 − p)20; it is the column that explains the response tied to each rating.

Table 3.8-73. Frequency index: rationale for each level
FLevelWhat defines itIndicative annual frequencyChance of ≥1 failure in 20 yearsWhy the level is here
5OccurringThe failure is under way and the track is already affected.1 or more per yearNear certainNothing has to change for the site to fail again; it is failing now. Repeated slow orders or surfacing at the same spot are the record of it. This is the top of the scale because no further evidence of likelihood is possible.
4EmergingClear signs of movement developing; defects return between surfacing cycles.1 in 1 to 1 in 5 yearsAbout 99%The ground has started to move but the track still runs. Movement that shows between surfacing cycles normally reaches failure within one or two maintenance or budget cycles, so the level spans 1 to 5 years.
3FormingThe conditions for failure are present; the ground is not yet moving.1 in 5 to 1 in 25 yearsAbout 56% to 99%Water against the fill, an over-steepened slope or a blocked culvert means the next large storm can start movement. Storms of a 5- to 25-year return period are common enough that failure is more likely than not within a 20-year planning horizon.
2DormantPast instability, no sign of present activity.1 in 25 to 1 in 100 yearsAbout 18% to 56%The site has failed before, so it can fail again, but reactivation needs a trigger larger than recent ones. That places it in the range of the storms used to size railroad drainage, about the 25- to 100-year event.
1InactiveNo evidence of instability, or the cause has been removed.Less than 1 in 100 yearsLess than about 18%Only an event beyond normal design conditions would cause failure. The level never reaches zero: drains clog and channels move, so an Inactive site is re-screened after major events.

Spacing. Each level is roughly 4 to 5 times as frequent as the one below. The spacing follows the stages a failing embankment passes through, not a mathematical series; it is finer than the factor-of-10 steps used in some landslide guidance (Table 3.8-78) because most railroad ground hazards that matter fall between once a year and once a century.

Live increments. The live rating (Section 3.8.26) raises F by 1 for one indicator at Watch and by 2 for two Watch indicators or any Warning. One level is the step from “conditions present” to “signs developing”: a single wet indicator moves a site one stage along. Two levels reflect that most rain-triggered failures need both wet ground and heavy rain. Setting F to 5 for a Warning at a site already Emerging recognizes that a moving fill under flood or storm loading should be treated as failing.

3.8.36.3 Hazard Severity Levels

The severity levels mark the points where the consequence of a failure passes from one party to the next: from the maintenance budget, to train operations, to the railroad’s service, to the safety of crews and freight, and finally to the public and the environment. Each boundary is a change in who must respond, not only in cost.

Table 3.8-74. Hazard severity: rationale for each level
SLevelWho bears the consequenceTypical outageWhy the level is here
5CatastrophicThe public and the environmentMore than a weekA failure that can kill, release hazardous materials, take out a structure or reach a river, road or homes is beyond what the railroad alone can absorb. It is the top level because consequences of this kind are not recoverable by repair.
4CriticalTrain crews, equipment and freightSeveral daysDerailment or loss of the main line is likely and serious injury is possible, but the damage stays mostly within the railroad corridor. The step from 3 is the step from a service problem to a safety problem.
3SeriousThe railroad’s service and its customersHours to a dayThe track is out of service or under a restrictive slow order and trains are delayed, but no derailment is expected and damage is confined to railroad property.
2MinorTrain operationsNone to a few hoursA geometry defect needs surfacing or a temporary slow order. Operations notice it; nothing is damaged beyond the track.
1LowThe maintenance budgetNoneThe effect is handled in routine maintenance and never reaches the train schedule. It is the bottom level because a failure here changes nothing but the work list.

3.8.36.4 The Five Risk Ratings

The band limits are set in the gaps between the possible products. R cannot be 7, 11, 13, 14, 17 to 19, or 21 to 24, so no cell sits on a boundary. Every rating therefore has a plain-language description of the cells it contains, given below, and that description is the reason for its required response.

Table 3.8-75. Risk ratings: rationale for each rating
LevelRatingWhat its cells have in commonWhy the response fits
5SevereOne scale is at its top level (Occurring or Catastrophic, 5) and the other at 4 or 5: cells 4×5, 5×4 and 5×5 (R 20–25).Failure is expected within a few years or is under way, and its consequence is Critical or worse, with at least one of the two at the top of its scale. Emerging and Critical together (4×4 = 16) is High, not Severe. Waiting for the next program accepts a likely failure with injury or public harm, so protection, operating restrictions and immediate stabilization are required.
4HighBoth scales are at 3 or more and at least one is at 4 or 5, short of Severe: cells 3×4, 4×3, 3×5, 5×3 and 4×4 (R 12–16). Failure is more likely than not within the planning horizon, with at least a Serious consequence.The site will probably fail before a normal capital cycle comes around. A slow order or increased inspection bridges the gap until stabilization in the next program.
3ElevatedOne scale is at 2 and the other at 3 to 5, or both are at 3: cells 2×3, 3×2, 2×4, 4×2, 2×5, 5×2 and 3×3 (R 6–10). That is a Dormant site with a consequence beyond maintenance, a forming or active failure with only a Minor consequence, or a Forming site with a Serious one.There is time to plan, but not to ignore the site. Design and scheduling proceed with monitoring in place. Catastrophic sites that are only Dormant land here, so they are not dropped from the program.
2GuardedOne scale is at 1 and the other at 3 to 5, or both are at 2: cells 1×3, 3×1, 1×4, 4×1, 1×5, 5×1 and 2×2 (R 3–5). Either the cause has been removed (F 1) or a failure would not affect trains (S 1), with the other scale at 3 or above, or both scales are at 2.Nothing needs to be built, but the condition that keeps the rating low (a drain, a culvert, a channel position) can change. Routine inspection with defined triggers catches that change.
1LowOne scale is at 1 and the other at 1 or 2: cells 1×1, 1×2 and 2×1 (R 1–2).No credible failure within the planning horizon would affect operations. Routine inspection is enough.

3.8.36.5 Situational, Instability and Consequence Attribute Scores

Tables 3.8-20, 3.8-21 and 3.8-24 describe scores 1, 3 and 5. Table 3.8-76 gives the reason each attribute is scored and descriptions for scores 2 and 4, so that every score from 1 to 5 has a written basis. Where the evidence fits neither description well, use 3 and flag the attribute for the field visit.

Table 3.8-76. Attributes: rationale and intermediate scores 2 and 4
AttributeRatingWhy it is scoredScore 2Score 4
L1 Surficial soilsSituationalSoil type sets strength loss on wetting, erodibility and how fast water drains out of the fill.Sand and gravel with some fines; well drainedLean clay or silt that softens when wet; poorly drained in places
L2 Geologic settingSituationalWhat lies beneath decides whether failures are shallow or deep and whether the ground can subside.Weathered rock over competent rock at shallow depthThick till, colluvium or weak shale; karst or mine workings mapped nearby but not under the track
L3 Slope geometrySituationalDriving stress grows with height and steepness. Score height and steepness separately and use the higher.Under 10 ft, slopes 2.5H:1V to 3H:1VSlopes steeper than 2H:1V but not steeper than 1.5H:1V
L4 HydrologySituationalWater at the toe is the most common trigger of railroad embankment failure.Intermittent ditch flow away from the toe; outside the 500-year floodplainStream within about 50 ft of the toe, or in the 100-year floodplain without flow against the fill
L5 Drainage conditionSituationalBlocked or undersized drainage holds water in and against the fill.Minor sediment or vegetation in ditches; culverts openCulvert half blocked, damaged or of unknown capacity; ponding seen in imagery
L6 Historic instabilityInstabilityPast movement is the best single predictor of future movement.Landslide-prone formation mapped, but no instability recorded at or near the siteDocumented failure at the site within about 20 years, or an old scarp visible in lidar
C1 Track and trafficSituational (consequence)Traffic sets how many trains are exposed and what an outage costs.Lightly used branch line or sidingMain line with moderate traffic
C2 Train typeSituational (consequence)Passengers and hazardous materials turn a derailment into public harm.No passenger trains; hazardous materials limited to infrequent carsRegular hazardous materials traffic, or occasional passenger trains
C3 Below and beside the trackSituational (consequence)What a failure would reach once it leaves railroad property.Railroad or private land with minor drainageA local road, a stream with fisheries value, or a few dwellings within reach
C4 Size of failureSituational (consequence)Volume sets repair time and whether the track is lost entirely.Fill 5 to 10 ftFill 20 to 30 ft
C5 Redundancy and recoverySituational (consequence)Outage length is what the railroad and its customers actually feel.Parallel route; repair within a dayLong detour; repair in about a week

3.8.36.6 Logic Check

The scales and the matrix were checked against the properties a rating method should have. The results, and the limits of the method, are in Table 3.8-77.

Table 3.8-77. Logic check of the rating method
CheckResultWhat to do
Every scale increases with its numberYes. All attribute scores, F, S and the five ratings run 1 (lowest risk) to 5 (highest). Tables 3.8-14 and 3.8-15 list the highest level first for reading only.None. Stated in Section 3.8.22.1.
All 25 cells of the matrix carry exactly one rating; the bands do not overlap or leave gapsYes. R can only take the values 1, 2, 3, 4, 5, 6, 8, 9, 10, 12, 15, 16, 20 and 25; the band limits fall in the gaps between them.None.
Raising F or S never lowers the ratingYes, for every cell.None.
A Catastrophic site stays Elevated or above until Inactive; a Low-severity site never exceeds GuardedYes.None.
The matrix favors consequence over frequencyNo. Because F × S is symmetric, a step in F counts exactly as much as a step in S. The extra weight on consequence comes from three rules: the C floor (a 5 on C2 or C3 sets C at 4 or more), “the consequence governs” in Table 3.8-15, and the engineer’s one-level raise.Apply those three rules every time (Section 3.8.22.4).
R measures risk in proportionNo. F and S are ordered levels, not measured quantities, so R = 10 is not twice the risk of R = 5. F levels are roughly 4 to 5 times apart in frequency; S levels are not quantified.Use R only to place a site in a rating. Within a rating, rank sites by F, then S, or by L × C for preliminary ratings.
Desktop Fp means the same as field FClose. Both are read from Table 3.8-11 using Fg and a defect rating; the desk D comes from the records and the field D from what is seen.Without defects Fp is capped at Forming (3), so susceptibility alone cannot rate a site as moving. Where the field D differs from the desk D, record why (Section 3.8.24.6; Section 3.8.24.3). The separate situational and instability scores on the report make this visible.
Rounding of L and C is definedYes.Round half up: 2.5 becomes 3.
L3 is unambiguous when height and steepness disagreeYes.Score height and steepness separately and use the higher.
The live rating stays on the same scalesYes. It raises F only, to a maximum of 5, and reads the same matrix; S never changes with the weather.None.

3.8.36.7 Comparison with Published Practice

Table 3.8-78 compares the GHRM ratings with six published methods: three that agree with its main features and three that do not.

Table 3.8-78. The GHRM risk ratings compared with published practice
SourceMethodPositionWhere it agrees with GHRMWhere it differs
Australian Geomechanics Society (2007), Practice Note Guidelines for Landslide Risk Management, Appendix CLikelihood levels with indicative annual probabilities, five consequence levels, and a risk matrix read by lookupAgreesFive risk levels (Very Low to Very High), each tied to a defined response; likelihood levels tied to annual frequency; risk skewed toward consequenceSix likelihood levels a factor of 10 apart; consequence numbered 1 = Catastrophic; no multiplication
NCHRP Research Report 884 (2018), Guidelines for Managing Geotechnical Risks in Design–Build Projects, Ch. 2.1Qualitative geotechnical risk analysis with frequency and impact each rated 1 to 5Agrees1-to-5 scales increasing with risk; ratings combined to rank risks in a register for mitigationWritten for project delivery risk, not for operating ground hazards
FTA (2019), Sample Safety Risk Assessment Matrices for Rail Transit AgenciesLikelihood and severity combined in a matrix; risk levels tied to acceptance and actionAgreesRail safety practice of combining likelihood and severity, with the required action set by the rating; likelihood calibrated to frequency4 severity by 5 likelihood levels; three risk levels; severity numbered 1 = most severe; lookup, not product
Cox (2008), “What’s Wrong with Risk Matrices?” Risk Analysis 28(2)Mathematical critique of risk matricesDisagreesAccepts matrices where the embedded judgments are explained, which this section doesShows matrices have poor resolution, can rank a smaller risk above a larger one, and depend on arbitrary category boundaries
FHWA (2019), Unstable Slope Management Program for Federal Land Management Agencies, FHWA-FLH-19-002Exponential category scores of 3, 9, 27 and 81, summed into hazard and risk totalsDisagreesScores many terrain, drainage and exposure factors from field and desktop data, as the situational attributes doNo matrix; scores are added, and the exponential points let one severe factor dominate; condition reported as Good, Fair or Poor
U.S. Department of Defense (2012), MIL-STD-882E, System SafetySeverity category and probability level combined into a Risk Assessment Code read from a matrixDisagreesRisk is a combination of severity and probability, with acceptance authority set by the risk levelFour severity categories against six probability levels; four risk levels (High, Serious, Medium, Low); severity numbered 1 = Catastrophic

Where GHRM goes further. None of the six sources ties the rating to track geometry defect history, to a desktop study that sets each site’s water thresholds, or to a live rating driven by river, rainfall and soil moisture data. These are additions specific to railroad ground hazards and are not covered by the published methods.

Numbering. Several published methods number severity in the opposite direction (1 = most severe). When translating a GHRM rating into another agency’s matrix, reverse the severity number: GHRM S = 5 corresponds to their category 1.

3.8.37 Risk Reduction Ratings: The Solution

Every proposed solution is rated for how much it will reduce the risk, in three stages: the solution as conceived (this section), the design and construction that turn it into works (Section 3.8.38), and the post-stabilization implementation that proves it performs (Section 3.8.39). The risk reduction is the difference between the current risk and the rating at each stage. Rating all three keeps a good idea from being credited as if it were already built and proven. Figure 3.8-47 follows the worked example of Section 3.8.41 through the stages.

LowGuardedElevatedHighSevere0510152025Risk score R = F × SCurrentSolutionConstruction(work window)Post-stabilization(provisional)Verified(after a wet season)1641584B. Clean culvert only: 16 High until defects stopA. Replace culvert, toe drain, bermtrench through fill:F​con = 5 × S = 3
Figure 3.8-47. Risk at each stage of risk reduction for the worked example of Section 3.8.41 (Table 3.8-84). Alternative A is credited in full only after it has performed through a wet season; its construction window is rated separately. Alternative B, which removes the trigger only, earns no reduction while the defects continue.

3.8.37.1 How a Solution Reduces Risk

A solution can reduce risk in only three ways, and the solution rating credits each one through the input it changes:

Table 3.8-79. Ways a solution reduces risk, the rating input each one changes and typical rescoring
Way of reducing riskExamplesInput changedRationaleTypical rescoring (starting values; confirm for the site)
Remove or reduce the triggerUpsize or clean a culvert; divert water; add ditches and subdrains; control beavers; lower groundwaterT, and the hydrology and drainage attributes L4 and L5If the trigger reaches the site less often, failure cannot be more frequent than the new trigger rating (Equation 3.8-2).Culvert sized for the 100-year event: T7 → 1, T8 → 2, L5.1 and L5.2 → 1. Ditches regraded and cleaned: T8 → 2, L5.3 → 1. Horizontal or lateral drains: T9 → 2, L5.4 → 1; because they drain the fill internally they also earn D = 1.
Increase resistanceBerms; shear keys; soldier pile walls; ground improvement; riprap and scour countermeasures; rock boltingThe situational attributes (L1–L3) through the design factor of safety (Table 3.8-81)Raising the margin against failure means a larger trigger is needed, which lowers the frequency of failure.Riprap or a scour countermeasure for the design flood: T4 → 1, L4.3 → 2. Soldier pile or other retaining wall: L3.2 → 1. Free-draining rock buttress or regrade: L3.2 → 2. Subgrade undercut with a drained granular section: L1.1, L1.4 and L5.4 → 1. Each earns D = 1 (Section 3.8.37.2).
Reduce exposure or consequenceRealign the track away from the slope; protective structures; detection linked to operating rules (slide fences, monitoring with alarms and slow orders)SThe ground may still fail, but a failure reaches less or is caught before a train meets it.T, L and D unchanged. Detection linked to an operating response: S one level lower while the response is in force (SOL2 = 4). Realignment or a protective structure: S rescored for what a failure would now reach, with the reason written.

The typical rescoring gives starting values, and it is what the Risk Assessment App suggests when an alternative is selected. Each element takes the lower of its current score and the value shown. Replace the values with the site’s own scores where the design or the conditions differ, rescore only the elements the solution actually changes, and never rescore L6.

3.8.37.2 Solution Rating (Fsol, Ssol)

For each solution, rate the site as it would be once the solution works as intended. Rescore only the inputs the solution changes (Table 3.8-79); every other input keeps its current value. Work through the steps in order:

  1. Trigger and setting. Rescore T and L1 to L5 for the changes the solution makes, and recompute Fg (Equation 3.8-2). Leave L6 unchanged: the site's history does not change. Where the solution increases resistance (a berm, shear key, wall or ground improvement), rescore L1 to L3 for the factor of safety the solution is intended to reach, using the margins of Table 3.8-81. The design rating (Section 3.8.38.1) confirms or corrects that credit once a design exists.
  2. Expected defect rating. Take D as 1 where the solution removes the cause of the defects, and keep the current D where it does not (for example, resurfacing alone). On a site with recurring or active defects (D = 4 or 5), a solution that removes only the trigger (cleaning a culvert, regrading ditches) also keeps the current D: a fill that has cracked and started to move can keep moving on its reduced strength without the trigger (Table 3.8-80). That reduction is credited at the post-stabilization stage, when a wet season passes with no movement (Section 3.8.39). A solution that also restores resistance or drains the fill internally (a berm, lateral drains, a wall) earns D = 1 here.
  3. Solution frequency, Fsol. Combine the new Fg and D with Equation 3.8-3 and Table 3.8-11, exactly as for the current rating.
  4. Solution severity, Ssol. Keep the current S unless the solution changes what a failure would reach: a realignment, a protective structure, or detection linked to an operating response (Table 3.8-79). Lower S only under the rules of Table 3.8-80, and write the reason.
  5. Solution rating. Compute Rsol = Fsol × Ssol and read its level from the risk matrix (Table 3.8-16).
  6. Limits on credit. Score the solution elements of Table 3.8-49 (Section 3.8.27.7) and check the result against Table 3.8-80 (Section 3.8.37.3). The elements do not average into the rating; each one sets a limit or a condition. A solution that acts on only part of the primary mechanism (SOL1 = 3) may lower F by at most one level, and one that does not act on it (SOL1 = 4 or 5) may not lower F at all. The investigation behind the solution (SOL3) caps how many levels the rating may fall. A maintenance-dependent solution (SOL4 of 3 or more) earns full credit only with a maintenance plan in force. A short design life (SOL5 of 4 or 5) sets a date when the credit expires. A solution that leaves the site at High or above is labeled interim.

3.8.37.3 Limits on Credit

Table 3.8-80. Limits on risk reduction credit and rationale
RuleRationale
Investigation level caps the credit. Desk study only: the solution may lower the rating by at most one level. Field reconnaissance, or limited borings without analysis: by at most two levels. Subsurface investigation and analysis: full credit (SOL3, Table 3.8-49).Without a confirmed mechanism and ground model, the solution may treat the wrong problem; the cap stops unproven solutions from outranking proven ones.
Monitoring and operating rules do not lower F. Detection linked to an operating response (alarms, inspections, slow orders) may lower S by one level, and only while the response is in force.Monitoring does not change how often the ground fails; it changes whether a train meets the failure.
Maintenance-dependent solutions (culverts, ditches, subdrains, beaver control) get full credit only with a maintenance plan (Section 3.8.39).Drainage that is not maintained silts up and returns the site to its trigger.
On a site with recurring or active defects (D = 4 or 5), a solution that removes only the trigger keeps the current D in its solution rating. The credit is earned at the post-stabilization stage once movement has stopped.Removing the trigger does not restore the strength the fill has already lost. Until the track shows the movement has stopped, the defects are still the best evidence of frequency.
A solution that leaves the site at High or above is interim, and is labeled as such.It manages the risk until a permanent solution is built; it does not resolve it (Section 3.8.22.7).
S is lowered only where the solution changes what a failure would reach, with the reason written.Severity belongs to the site and its traffic; most stabilization works lower F, not S.
3.8.38 Risk Reduction Ratings: Design and Construct

The design and construction stage rates two things: the reduction the design actually earns, and the risk while the work is built.

3.8.38.1 Design Rating (Fdes)

The design rating replaces the judgment of the solution rating with the design criteria the works meet. The levels follow the indicative annual frequencies of Table 3.8-14, so a design event and a frequency index mean the same thing.

Table 3.8-81. Frequency index credited by the design and rationale
MechanismDesign criterion metFdesRationale
SlopeLong-term static factor of safety ≥ 1.5 under the design groundwater, with the trigger controlled (Section 6.3.5)1The commonly accepted long-term margin; a much larger event than the design condition is needed to fail the slope.
SlopeFactor of safety 1.3 to under 1.52Adequate for many conditions but with less margin for unknowns in strength and groundwater.
SlopeFactor of safety 1.1 to under 1.33Marginal; acceptable only as a temporary or short-term condition.
SlopeFactor of safety under 1.1no creditNot distinguishable from limiting equilibrium given normal uncertainty.
Hydraulic (culvert, channel, scour)Capacity and countermeasures for the 100-year event or larger, with scour checked at the 500-year event1Matches the Inactive band (less than 1 in 100 years) and common practice for scour-critical structures.
HydraulicDesign event 25- to 100-year2Matches the Dormant band.
HydraulicDesign event 5- to 25-year3Matches the Forming band.
HydraulicDesign event under 5-yearno creditThe trigger will still reach the site within a normal maintenance cycle.
SubgradeSubgrade and track section meet the design criteria of Chapter 2.3 for the traffic, with drainage1 to 21 where drainage and bearing both meet the criteria with margin; 2 where they depend on maintenance.
SubsidenceVoids treated and verified, or the track bridged over the zone2 (1 if bridged or relocated)Treatment addresses known voids; new ones can still form nearby.
Rock and debrisScaling, bolting or catchment designed for the design block size and energy2 (1 if all mapped blocks are stabilized and the catchment is verified)Catchment manages, but does not prevent, release.

Where several mechanisms apply, use the highest Fdes among them. Fdes may not be lower than the solution rating's Fsol unless the design shows why.

3.8.38.2 Construction-Stage Rating

Construction can raise the risk before it lowers it: a culvert trench cut through a fill, an excavation at the toe, or heavy equipment on a marginal slope all reduce resistance for a time. The construction-stage rating is the risk during the work:

Equation 3.8-15. Construction-stage frequency
Fcon = Fc + 1 (maximum 5) where the work temporarily reduces resistance or adds load; otherwise Fcon = Fc
  • Temporary measures that change what a failure would reach (track out of service, slow orders with monitoring, temporary shoring designed for the stage) may lower S for the construction stage by one level, as in Table 3.8-80.
  • A construction stage rated Severe requires the track to be protected or out of service for that stage.
  • Record the expected duration of construction; the current risk continues until the works are complete.
3.8.39 Risk Reduction Ratings: Post-Stabilization Construction and Implementation

A stabilized site is not yet a proven site. The post-stabilization rating is first provisional, and becomes the verified residual risk only when the works have been built as designed, have performed through a triggering event, and are being maintained.

Table 3.8-82. Post-stabilization frequency index and rationale
ConditionFpostRationale
Works complete and accepted on as-built quality assurance and quality control (Chapter 5.3), not yet tested by a triggerFdes + 1 (provisional)Construction quality and the ground model are not yet proven by performance.
Monitoring (survey, instruments, geometry records) shows no movement through at least one triggering season, or one event at or above the site's response levelFdes (verified)The works have been tested by the trigger they were built to resist.
Drainage-dependent works without a maintenance plan in forceFdes + 1 (remains provisional)Unmaintained drainage returns the site to its trigger.
Defects or indicators recur after stabilizationRecompute Fc from the new D (Section 3.8.19)The solution has not removed the cause; the site re-enters the current risk process.
Equation 3.8-16. Residual risk and risk reduction
Rres = Fpost × Spost; risk reduction = current rating − residual rating (in levels), and Rc − Rres (in score points)

Spost is the solution severity Ssol (Section 3.8.37.2). The works themselves rarely change it, since severity belongs to the site and its traffic. A reduction credited for detection linked to an operating response, or for a temporary measure, is kept only while that response is in force (Table 3.8-80); when it lapses, Spost returns to the current S.

The implementation stage also closes the loop with the live rating: after stabilization, the site keeps its trigger thresholds, recalibrated to the new works, and each triggering event is recorded so the verified rating rests on performance, not expectation.

3.8.40 Life-Cycle Cost of Ground Hazard Mitigation

A risk rating says which sites matter. It does not say whether fixing a site is worth more than living with it. Sullivan, Wicks and Koelling's Engineering Economy supplies the tools: present worth, equivalent uniform annual cost and the benefit-cost ratio, all at the owner's discount rate over a fixed analysis period. For ground hazards the recurring cost has two parts. One is routine maintenance, such as surfacing, ditch cleaning and slow orders. The other is the annual risk cost, the probability of a failure in any year times what one failure costs in repair, outage and exposure. Mitigation buys down the second part. The Construction Materials and Engineering Materials 1 texts are the basis for the service life chosen for each alternative, whether that is corrosion of steel, deterioration of concrete or decay of timber.

3.8.40.1 Method

Equation 3.8-17. Present worth, annual cost and benefit-cost ratio

(P/A, i, N) = [(1 + i)N − 1] / [i(1 + i)N]

PW = K + (M + p·C)×(P/A);   EUAC = PW × (A/P)
B/C = [(M + p·C)base − (M + p·C)alt]×(P/A) / (Kalt − Kbase)

3.8.40.2 Worked example

Example 3.8-13: Life-Cycle Cost of Two Mitigation Alternatives

A soft-ground embankment is costing $60,000 a year in surfacing and has an estimated 5% annual chance of a $1.5 million failure. Two mitigation alternatives are compared with continuing to maintain it, using the risk cost (probability times consequence) as an annual cost alongside maintenance.

Year 0Year 30A0 Continue surfacingA1 Toe berm $450,000A2 Sheet pile $900,000PW, B/C = ?GivenFailure cost C = $1.5 millionA0: M = $60,000/yr, p = 5%A1: K = $450,000, M = $8,000, p = 1%A2: K = $900,000, M = $3,000, p = 0.5%i = 7%, N = 30 yrRequiredPresent worth of each alternativeBenefit-cost ratio of A1 and A2Best buy, and how robust it isBlack = given; red = required
Given and required for Example 3.8-13.

Given

VariableValueDescription
C$1,500,000Cost of a failure (repair, outage and claims)
A0K = 0; M = $60,000/yr; p = 0.05Continue surfacing
A1K = $450,000; M = $8,000/yr; p = 0.01Toe berm
A2K = $900,000; M = $3,000/yr; p = 0.005Sheet pile reinforcement
i, N7%; 30 yearsDiscount rate and analysis period

Required

  • Present worth of each alternative
  • Benefit-cost ratio of A1 and A2 against A0
  • The better buy, and whether the choice holds when p is halved or doubled

Equations

  1. Eq. 1: (P/A) = [(1 + i)N − 1] / [i(1 + i)N] — present worth factor (Equation 3.8-17)
  2. Eq. 2: PW = K + (M + p·C)(P/A) — present worth with annual risk cost
  3. Eq. 3: B/C = [(M + pC)A0 − (M + pC)alt](P/A) / Kalt — benefit-cost ratio

Steps

Step 1 · Present worth factor (Eq. 1)
Uses: i, N
1.0730 = 7.612; (7.612 − 1) / (0.07 × 7.612)
(P/A) = 12.409
Spot check: The perpetual factor is 1/0.07 = 14.3, and 30 years should be somewhat less.
↓
Step 2 · Annual costs
Uses: M, p, C
A0: 60,000 + 75,000; A1: 8,000 + 15,000; A2: 3,000 + 7,500
$135,000; $23,000; $10,500 a year
Spot check: Risk cost is 56% of A0's annual cost; for A1 it is 65%.
↓
Step 3 · Present worth (Eq. 2)
Uses: Steps 1–2, K
A0: 135,000 × 12.409; A1: 450,000 + 23,000 × 12.409; A2: 900,000 + 10,500 × 12.409
PW = $1,675,221; $735,408; $1,030,295
Spot check: A1 adds 285,408 to its capital and A2 only 130,295, but A2 starts $450,000 higher.
↓
Step 4 · Benefit-cost ratio (Eq. 3)
Uses: Steps 1–3
A1: (135,000 − 23,000) × 12.409 / 450,000; A2: (135,000 − 10,500) × 12.409 / 900,000
B/C = 3.09 (A1); 1.72 (A2)
Spot check: Both B/C > 1 is consistent with both PW below A0's $1.68 million.
↓
Solution
Toe berm: PW $735,408, B/C 3.09; sheet pile: PW $1,030,295, B/C 1.72.

Solution

Continuing to maintain the embankment has a present worth of $1,675,221. The toe berm comes to $735,408 (B/C = 3.09) and sheet pile reinforcement to $1,030,295 (B/C = 1.72). Both pay for themselves, and the berm is the better buy.

The answer turns on the probability and the consequence, which come from the risk assessment, so the calculator is meant to be run across a range of values.

Present the result as a range, not a single number: run the probability at half and double the estimate. If the preferred alternative holds across that range, the recommendation is robust; if it flips, the decision rests on the risk estimate and more investigation may be the best investment.

Open the life-cycle cost calculator →
Present worth, equivalent uniform annual cost and benefit-cost ratio of mitigation alternatives, with annual risk cost as probability times consequence, and a cumulative present-worth chart.

3.8.40.3 Sources in the library

Paraphrased from these documents in the reference library.

Supplemental reference · Hirst (1995)

Where the Present Worth Factor Comes From: Geometric Series

The present worth factor in Equation 3.8-17 is the sum of a geometric series. An annual cost A paid at the end of each of N years, discounted at rate i, has present worth A[v + v² + … + vN] with v = 1/(1 + i). The finite geometric series a + ar + … + arN−1 sums to a(1 − rN)/(1 − r), which gives (P/A) = [1 − (1 + i)−N]/i, the same as the form in Equation 3.8-17.

  • Perpetual cost. Because v < 1, the series converges as N grows: (P/A) → 1/i. At 7%, an annual risk cost carried forever is worth 1/0.07 = 14.3 years of that cost; over 30 years it is already 12.4 years. A cost avoided permanently is therefore worth only about 15% more than one avoided for 30 years, which is why the analysis period matters less than the probability and consequence.
  • Growing cost. If the annual cost grows at rate g (deteriorating slope, rising traffic), the ratio becomes (1 + g)/(1 + i), and the series still converges if g < i: (P/A) = [1 − ((1 + g)/(1 + i))N]/(i − g). With g ≥ i the sum grows without limit, a warning that deferring work on a site that worsens faster than the discount rate is never the cheaper choice.
  • Series approximations. The exposure formula of Section 3.8.30 uses (1 − p)n ≈ e−np, from the series ln(1 − p) = −p − p²/2 − …. The relative error in the exponent is about p/2, so the approximation is within 1% for annual probabilities below about 0.02 (return periods longer than 50 years) and about 12% at p = 0.2 (a 5-year return period).

For railroad work: Use the growing-cost form when a site is visibly getting worse; a constant annual risk cost understates the case for early repair.

Source: Hirst, K. E. (1995). Numbers, Sequences and Series. Modular Mathematics Series. London: Arnold (Butterworth-Heinemann) Find source ↗ (Ch. on sequences and series: geometric series, convergence, and series expansions).

3.8.41 Worked Example

A hypothetical main line fill, used only to illustrate the method. Alternative A assumes a subsurface investigation and analysis have been completed, so it earns full credit under Table 3.8-80.

Example 3.8-14: Current Risk and Risk Reduction for Three Alternatives

At a 22-ft fill of lean clay across a creek, a partly blocked 48-in. culvert makes the fill susceptible to softening and slope movement by a drainage-driven mechanism. The site was buttressed with a berm 15 years ago; today the track has been surfaced twice in 12 months and a bulge is forming downstream. The current risk is rated, and three alternatives are carried through the three risk reduction stages of Sections 3.8.37 to 3.8.39.

Main track48-in. culvert, partly blockedponded water (left)22 ftold berm, bulgeGivenLean clay fill; creek; blocked culvert; old bermL1–L5 = 4, 3, 3, 4, 5 (L5 × 2); L6 = 3Ponding about every 3 yr: T = 4Surfaced twice in 12 months; fresh bulgeMain line, moderate to heavy freight: S = 4RequiredCurrent risk R​cSolution, design/construct and post-stabilization ratings for A, B and CRisk reduction of eachBlack = given; red = required
Given and required for Example 3.8-14.

Given

VariableValueDescription
L1–L5, weights4, 3, 3, 4, 5; L5 weighted 2Lean clay fill; creek near the toe; blocked culvert
L63Past berm 15 years ago
T4Ponding about every 3 years
D4Same defects return between surfacing cycles; fresh bulge
S4, CriticalMain line, moderate to heavy freight
AlternativesA: replace culvert (100-yr), toe drain and berm; B: clean culvert only; C: monitoring with slow ordersInvestigation complete for A: full credit (Table 3.8-80)

Required

  • The current risk Rc
  • The solution, design and construct, and post-stabilization ratings of A, B and C
  • The risk reduction each one earns

Equations

  1. Eq. 1: L = (ΣwiLi + L6) / (Σwi + 1) — Equation 3.8-2
  2. Eq. 2: Fg = lesser of (L, T) — geospatial frequency
  3. Eq. 3: Fc from Fg and D — Table 3.8-11
  4. Eq. 4: R = F × S — risk score and rating, Table 3.8-16
  5. Eq. 5: ΔR = Rc − Rstage — risk reduction at each stage

Steps

Step 1 · Overall likelihood (Eq. 1)
Uses: L1–L6
L = (4 + 3 + 3 + 4 + 2 × 5 + 3) / 7 = 27 / 7
L = 3.86 → 4
Spot check: Weights sum to 7: five attributes, L5 counted twice, plus L6.
↓
Step 2 · Geospatial and current frequency (Eq. 2, 3)
Uses: L, T, D
Fg = lesser of (4, 4) = 4; Table 3.8-11, row 4, column 4
Fc = 4
Spot check: Fg is not ≥ D + 1, so no amplification.
↓
Step 3 · Current risk (Eq. 4)
Uses: Fc, S
Rc = 4 × 4
Rc = 16, High: act soon
Spot check: Table 3.8-17: slow order or increased inspection; stabilize in the next program.
↓
Step 4 · Solution ratings (Eq. 2–4)
Uses: Alternatives
A: T 4→1, L5 5→1, D expected 1 → F = 1. B: T 4→3, L5 5→3, Fg = 3, D stays 4 → F = 4. C: F stays 4, S 4→3 while in force
A: 4 Guarded; B: 16 High (interim); C: 12 High (interim)
Spot check: B: Table 3.8-11, row 3, column 4 gives 4, so the defects still govern.
↓
Step 5 · Design, construction and post-stabilization
Uses: Design criteria, work window
A: Fdes = 1; trench through fill Fcon = 5 with track out of service S = 3; provisional Fpost = 2, then 1 after a wet season with no movement and a maintenance plan
A: 15 High for the work window; 8 Elevated provisional; 4 Guarded verified
Spot check: 5 × 3 = 15 is High, which is why the work window is planned with the railroad.
↓
Step 6 · Risk reduction (Eq. 5)
Uses: Rc, verified ratings
A: 16 − 4; B: 16 − 16; C: no change in F
A: 12 points, two levels, once verified; B: none while defects continue; C: one level in S, interim
Spot check: Only A changes the rating band permanently.
↓
Solution
Rc = 16 High; A verified 4 Guarded; B 16 and C 12, both interim.

Table 3.8-83 records the current-risk inputs as they appear on the report.

Table 3.8-83. Worked example: current risk
InputValueReason
L1 to L5 (L5 weighted 2), L64, 3, 3, 4, 5 (×2), 3Lean clay fill; creek near the toe; blocked culvert; past berm
L(4 + 3 + 3 + 4 + 10 + 3) / 7 = 3.86 → 4Equation 3.8-2
T4Ponding about every 3 years
Fglesser of 4 and 4 = 4
D4Same defects return between surfacing cycles; fresh bulge
Fc4 (Table 3.8-11)Evidence governs; no amplification (Fg is not ≥ D + 1)
S4 CriticalMain line, moderate to heavy freight traffic
Current riskRc = 16, HighAct soon: slow order or increased inspection; stabilize in the next program

Solution

Table 3.8-84. Worked example: risk reduction ratings for three alternatives
StageA. Replace culvert (100-year capacity), toe drain and bermB. Clean culvert onlyC. Monitoring with slow orders
SolutionT 4→1, L5 5→1; D expected 1; Fsol = 1; S = 4; R = 4 GuardedT 4→3, L5 5→3; L = 3; Fg = 3; D stays 4 until movement stops; Fsol = 4; R = 16 High (interim)F unchanged 4; S 4→3 while the response is in force; R = 12 High (interim)
Design and constructCulvert for 100-year event; slope FS 1.5 with drained berm: Fdes = 1. Culvert trench through fill: Fcon = 5; with track out of service S = 3; R = 15 High for the work windowNo design; maintenance item: Fdes = FsolNot applicable
Post-stabilizationProvisional Fpost = 2; R = 8 Elevated. After one wet season with no movement and a culvert maintenance plan: Fpost = 1; R = 4 GuardedR = 16 High until defects stopR = 12 High while in force
Risk reductionHigh (16) to Guarded (4): 2 levels, 12 points, once verifiedNone while defects continueNone in F; one level in S, interim only

The site is High (16). Alternative A reaches a verified Guarded (4), a reduction of 12 points and two levels; B and C remain High and are interim. A is the only alternative that acts on the trigger and the resistance, and the only one that reaches a verified Guarded rating. B treats part of the trigger but not the movement already under way, so the defects, and the rating, stay. C manages exposure while a permanent fix is designed and is labeled interim.

3.8.42 The Ground Hazard Risk Assessment Report

The Ground Hazard Risk Assessment Report is the form the EIC takes to the site. It records what is found there, frames up to three stabilization alternatives, and rates the site as it stands and after each alternative. It is issued to the railroad the same day as a field copy draft, followed by a formal report within one week.

3.8.42.1 What Has Changed in the Form

The previous worksheet was a single page that began with general site information. The desktop study was handed over as a separate package, and the EIC had to carry the preliminary scores, thresholds and questions on other sheets or from memory. The reworked report is three sheets, and the first is new:

  • Sheet 1, Block A — Desktop Study Summary. Every metric determined before the visit is printed on the form: the network screening value and entry route, the driving mechanism, the situational likelihood (L1 to L5) and consequence (C1 to C5) scores, the trigger and trigger rating T, the instability attribute (L6), the geospatial frequency Fg and defect rating D, the preliminary Fp, Sp and static rating, the H&H thresholds, the live rating on the day of the visit, and the questions for the field. Each value has a field column beside it, so the EIC confirms it with a check or writes the revised value.
  • Sheet 2, Blocks 1 to 3 keep the content of the previous worksheet, with two check rows added: whether the exposure seen on site agrees with the consequence scores, and whether the failure type agrees with the desk driving mechanism.
  • Sheet 3, Blocks 4 to 6 keep the stabilization items, services and costs, and the risk rating. Block 6 now places the preliminary and live ratings beside the field and alternative ratings, and asks for the reason whenever the field rating differs from the preliminary rating by more than one level.

The result is that the engineer arrives with the desk’s reasoning in hand, the field evidence is recorded against it item by item, and every difference between desk and field is written down where it can later be used to calibrate the desk scores and thresholds.

3.8.42.2 Reading the Form and Workflow

Cell shading and text styles show where each entry comes from and when it is made.

Blue: desktop study values, printed before mobilizing (Block A; preliminary and live columns of Block 6).
Yellow: from the railroad’s request and track data, before the visit (Block 1).
White: recorded on site.
Gray: rating outputs and totals.
Green: block titles and headings; do not write in them.

Red text marks entries that must be confirmed with the railroad contact before the form is issued (the number of tracks and which is higher, and any railroad workload conflict). Blue italic marks the measurement and frequency of each reported geometry defect. In the checklist blocks, mark (✓ or X) every item that applies and leave the rest blank; a blank means the item was looked for and not found. Write photo numbers, dimensions or a short note beside each marked item.

Table 3.8-85. Blocks of the Ground Hazard Risk Assessment Report
SheetBlockWhat is recordedQuestion it answersSection
1A. Desktop study summaryNetwork screening, driving mechanism, situational and instability scores, static rating, H&H thresholds, live rating at visit, questionsWhat did the desk find, and what does the field need to check?3.8.42.3 (from 3.8.23 to 3.8.26)
21. General site informationClient, contacts, location, track and traffic data, protection, site settingWhere is the site, and what does the railroad have at stake?3.8.42.4
22. Site conditionsIndicators on the left embankment, between the rails and on the right embankmentWhat is the ground telling us?3.8.24.4
23. Site instabilitiesMajor element affected, construction constraints, estimated failure typeWhat is failing, and what limits the fix?3.8.24.5
34. Recommended stabilization itemsEngineering, drainage, earthwork and structural measures, by alternativeWhat would fix it?3.8.42.6
35. Additional servicesExploration, field testing and engineering by alternative, with low and high costWhat is needed to confirm and design the fix, and what will it cost?3.8.42.6
36. Risk ratingF, S, R and rating: preliminary, live, current and each alternativeHow much risk is there now, and how much does each alternative remove?3.8.42.7

Workflow.

  1. Before the visit. Print Sheet 1 with Block A filled from the desktop study, and fill the yellow cells of Block 1 from the railroad’s request and track data. On the day of the visit, print or write the live readings in A7. Arrange on-site protection and identify the place of safety.
  2. On site. Hold the job briefing, then walk the site before writing. Complete the white cells of Block 1, then Block 2 looking up station, then Block 3. Work through the field column of Block A and the questions in A8 as you go. Photograph each marked indicator.
  3. Before leaving. Check Block 4 and frame up to three alternatives. Assign the current rating in Block 6 while the evidence is in front of you. If the site is Severe or High, tell the railroad contact before leaving.
  4. After the visit. Complete the Block 5 costs and the ratings for each alternative, write the alternative notes and issue the field copy draft. The formal report follows within one week.

Download the blank report form (PDF, three sheets) for printing. Each sheet is shown under the description of its blocks below; click a sheet to zoom and pan.

3.8.42.3 Block A — Desktop Study Summary

Block A carries the desk’s findings into the field. It is prepared by whoever completed the desktop study and checked by the EIC before mobilizing. The sheet is shown in Figure 3.8-48. Its eight parts follow the order of Sections 3.8.23 to 3.8.26:

  • A1 Static network screening: the segment ID, its CHI value or network rank, the segment event count where available, and the route by which the site entered the program (Section 3.8.25.1).
  • A2 Driving mechanism and trigger: primary and contributing mechanism, with the weighted attribute; the primary trigger, its response level, the trigger rating T and the trigger narrative (Section 3.8.18; Section 3.8.23.3).
  • A3 Situational likelihood: L1 to L5 with weights, basis and LS (Section 3.8.23.4).
  • A4 Consequence: C1 to C5, C with the floor rule, and Sp (Sections 3.8.23.5 and 3.8.23.6).
  • A5 Instability rating: L6, the reported defects and whether they recur, the last slow order, L, Fg, the desk defect rating D and Fp (Section 3.8.24), with cells for the field D from Table 3.8-27 and the field Fc from Table 3.8-11.
  • A6 Static (preliminary) rating: Fp, Sp, Rp, the rating, priority and level of effort (Section 3.8.25).
  • A7 H&H thresholds and live rating: the paired gauge and its action and moderate stages, the toe and damage stages, the site rainfall, culvert capacity and antecedent thresholds, thaw history, and the live readings and live rating on the day of the visit (Sections 3.8.23.7 and 3.8.26).
  • A8 Questions for the field: every attribute scored 3 for lack of data, every feature seen in lidar or imagery that needs checking, and the culverts and outlets to find and measure, with space for the answer and photo number.
Ground Hazard Risk Assessment Report, Sheet 1: Block A Desktop Study Summary (blank)
Figure 3.8-48. Report Sheet 1, Block A — Desktop Study Summary. New in this edition. Every metric from Sections 3.8.23 to 3.8.26 is printed here before mobilizing, with a field column beside it so the EIC can confirm or revise each value on site. Blocks A5 and A6 follow the method of Sections 3.8.18 to 3.8.21: trigger rating, geospatial frequency, defect rating and preliminary current risk.

Using the field column. Confirm each value with a check, or write the revised value. Revise a desk score only on evidence seen at the site, and note the evidence. The EIC does not recompute LS, L or C in the field: the field rating in Block 6 is set from the field defect rating, the confirmed trigger and the desk Fg (Table 3.8-27 and Table 3.8-11) and from the exposure (Table 3.8-15). The revised attribute scores are returned to the desk after the visit, where they update the site record and calibrate later desk studies. The toe, culvert outlet and culvert elevations checked in A7 are the first refinement of the H&H thresholds.

The desktop package still includes the site map or KMZ, the site history summary and, where prepared, the Site Background Report. Mark which are attached at the foot of Block A.

3.8.42.4 Block 1 — General Site Information

Block 1 identifies the site and records what the railroad has at risk. Most entries come from the railroad before the visit; the rest are recorded on site. Block 1 is on Sheet 2 with Blocks 2 and 3, shown in Figure 3.8-49.

Ground Hazard Risk Assessment Report, Sheet 2: Blocks 1 to 3 (blank)
Figure 3.8-49. Report Sheet 2: Block 1 General Site Information, Block 2 Site Conditions and Block 3 Site Instabilities. Blocks 2 and 3 record the field instability evidence of Section 3.8.24; new check rows tie Block 1 and Block 3 back to the desktop values on Sheet 1.
Table 3.8-86. General site information
GroupFields
Client and contactsClient; railroad subdivision; project number; railroad contact and phone; EIC and phone
Location and protectionMilepost; from MP and to MP; on-site protection type (for example foul time, track and time, or a watchman/lookout); place of safety; date
OperationsOperational characteristic (main line, siding, yard or industry; freight, passenger or mixed; hazardous materials); average daily train traffic; number of tracks (and which is higher, or whether they are at the same elevation); normal speed; slow order speed; date of last issue
Affected lengthAffected track length (ft), measured on site
Site settingCurrent weather; geologic setting; track cross section (cut or fill); alignment (tangent, inside or outside of curve); track setting (marsh, valley, or slope: top, mid or bottom); population density factor

Why it matters. Train traffic, normal speed, the number of tracks, train type and the population density factor are the exposure that sets the hazard severity. They were scored at the desk as C1 to C5 (Block A4); Block 1 confirms them on site. If they disagree, mark the check row and revise S in Block 6. An error here changes the rating. The slow order speed and the date of the last issue show how the railroad is already managing the hazard. The affected track length scales every cost in Block 5 and should be stated with each alternative.

3.8.42.5 Blocks 2 and 3 — Site Conditions and Site Instabilities

Blocks 2 and 3 are the field half of the instability rating. How to orient the form, walk the site, record defects with their measurement and frequency, and read the pattern of indicators is described in Section 3.8.24.4; the major element, construction constraints and failure type in Section 3.8.24.5. Two points apply to the reworked form:

  • Compare the indicators with the desk L6 and defect history in Block A5, and record the field defect rating D from Table 3.8-27 and the field Fc from Table 3.8-11 in A5. Fc goes to the current column of Block 6.
  • Compare the estimated failure type in Block 3 with the desk driving mechanism in A2, and complete the check row at the foot of Block 3. A changed mechanism changes the weighted attribute, the H&H thresholds that matter and the live indicators that apply; return it to the desk.

3.8.42.6 Blocks 4 and 5 — Stabilization Items, Services and Cost

Block 4 lists the measures that could stabilize the site, grouped by discipline. Mark every item that belongs in at least one alternative and write the alternative number(s) beside it; this is what links Block 4 to the three alternative columns of Blocks 5 and 6. Blocks 4 and 5 are on Sheet 3 with Block 6, shown in Figure 3.8-50.

Ground Hazard Risk Assessment Report, Sheet 3: Blocks 4 to 6 (blank)
Figure 3.8-50. Report Sheet 3: Block 4 Recommended Stabilization Items, Block 5 Additional Services by alternative with cost range, and Block 6 Risk Rating. Block 6 places the preliminary and live ratings beside the field rating and each alternative’s risk reduction ratings (solution, design, construction stage and post-stabilization), so the change from desk to field to residual risk is visible on one sheet.
Table 3.8-87. Recommended stabilization items
Engineering studiesEngineering disciplinesDrainageEarthworkStructural
Site monitoring: track forcesHydraulics and hydrology (H&H)DewaterGradingLoad transfer
Site monitoring: instrumentationGeotechnicalRemove obstructionStiffen subgradeEarth retention
H&H studyStructuralDitchingRemove and replaceRepair
Geotechnical explorationCivilErosion controlCounter (toe) bermReplace

Order of preference. Follow the risk control hierarchy of Section 1.1.9: remove the cause first (water is the most common one: dewater, remove the obstruction, ditch), then reduce the load or driving force (grading), then add resistance (counter berm, stiffen subgrade, earth retention, load transfer). Use monitoring and operating restrictions to manage the remaining risk while the permanent fix is designed and built. The driving mechanism in Block A2 usually points to the first measure. A useful set of alternatives is often a quick, low-cost measure (Alternative 1), a medium measure (Alternative 2) and the long-term structural answer (Alternative 3). Monitoring and instrumentation are covered in Chapter 5.3, earth retention in Chapter 7.1, and ground improvement in Chapter 7.2 and its technology library (Section 7.2.16).

Ground improvement level. An earlier version of the worksheet carried three levels of ground improvement. They remain a useful shorthand when an alternative depends on ground improvement: low for drainage-led and surface measures; medium for local treatment such as lateral drains, a toe berm or compaction grouting; and robust for structural or deep measures such as soldier piles and lagging, deep mixing or track realignment.

Block 5 turns the recommendation into a scope. For each service, mark (or enter a quantity, such as the number of borings or inclinometers) under each alternative that needs it, and give a low and high estimated cost, so the railroad sees a range rather than a single number that looks more precise than it is.

Table 3.8-88. Additional services recommended, by alternative
Service groupItemsRecorded for each item
Subsurface explorationSurveying; soil survey borings; modified SPT soil survey borings; SPT boringsAlternatives 1–3 that need it; estimated cost, low and high
Field testingDynamic cone penetrometer (DCP); field CBR; inclinometer; piezometer; lateral trench test pit; ground penetrating radar (GPR)Alternatives 1–3 that need it; estimated cost, low and high
EngineeringLaboratory testing; geotechnical analysis; structural analysis; design bid package; construction monitoringAlternatives 1–3 that need it; estimated cost, low and high

Each service ties to a chapter of this manual: exploration planning to Chapter 3.9; borings and SPT to Chapter 4.1; DCP, field CBR and GPR to Chapter 5.1; piezometers to Chapter 2.8; inclinometers to Section 5.3.8; laboratory testing to Chapter 5.2; and slope analysis to Chapter 6.3. Field testing on an operating railroad is done in work windows, so note when each test can be done. The level of effort set by the static rating (Table 3.8-29) is a guide to how much exploration to scope.

Alternative notes. On Sheet 3, write a short paragraph for each alternative: what it consists of, the services it needs, how long it will take (Table 3.8-90), and the risk rating expected once it is built. These notes become the alternatives section of the formal report (Chapter 8.4).

3.8.42.7 Block 6 — Ground Hazard Risk Rating

Block 6 rates the site using the scales and matrix of Section 3.8.22. It has six columns:

  • Preliminary and Live at visit (blue): copied from Blocks A6 and A7 before the visit. They are the desk’s expectation and the conditions the site was seen in.
  • Current (field): the trigger narrative and T, Fg, the field D and Fc (Table 3.8-27 and Table 3.8-11), and S from the exposure confirmed in Block 1. Compute R = F × S, read the rating from Table 3.8-16 and circle it. Write a one-line reason for each level.
  • Alternatives 1 to 3: the solution rating for each alternative (Section 3.8.22.7), with its design, construction-stage and post-stabilization ratings added as the alternative is designed, built and verified (Sections 3.8.37 to 3.8.39).

If the live rating at the visit was above the static rating, judge whether the indicators seen are those of the event or of the site’s usual state, and say so in the reason. Record any one-level adjustment (Section 3.8.22.6) and, where the field rating differs from the preliminary rating by more than one level, the reason.

Severe or High now? A Severe rating calls for on-site protection, operating restrictions and immediate stabilization; tell the railroad contact before leaving the site rather than waiting for the field copy, and record who was told and when.

3.8.42.8 Stabilization Methods: Analysis, Testing, Quality Control, Cost and Time

When an alternative includes ground improvement or another stabilization method, the report’s companion sheet sets the analysis it needs, the field and laboratory testing that support the analysis, and the quality control that shows the method worked. The field testing column also records when the test can be done around traffic.

Table 3.8-89. Stabilization methods: analysis, testing and quality control
MethodAnalysis requiredField testingLaboratory testing (standard)Quality control
Preloading and surchargingConsolidation analysisSPT during off-peak hoursTriaxial compression (ASTM D4767-11(2020))Pore pressure measurement
Sand drainsConsolidation analysisCPT coordinated with rail operationsUnconfined compression (ASTM D2166/D2166M-24)Settlement monitoring
Vibro-compactionShear strength analysisSPT during off-peak hoursConsolidation (ASTM D2435)Pore pressure measurement
Deep mixingShear strength analysisCPT coordinated with rail operationsTriaxial compression (ASTM D4767-11(2020))Settlement monitoring
GroutingLiquefaction analysisSPT or CPT with minimal disturbanceUnconfined compression (ASTM D2166/D2166M-24)Pore pressure measurement and settlement monitoring
Compaction grouting (low-mobility grout to 20 ft below toe of slope)Ground stabilization analysisSPT or CPT to verify treatment; GPRCompressive strength (ASTM C39/C39M-26)Ground movement monitoring
Ballast removal and replacementMaterial contamination analysisSPT or CPT during maintenance windowsParticle size distribution (ASTM D6913; D422 was withdrawn in 2016)Track settlement monitoring
Lateral drainsSeepage analysisSPT or CPT with piezometer installation; GPRPermeability (ASTM D5084-24)Pore pressure and water table monitoring
Toe bermSlope stability analysisSPT or CPT at the berm location; GPRDirect shear (ASTM D3080/D3080M-23)Slope monitoring
Embankment wideningLateral stability analysisSPT or CPT along the embankment; GPRCompaction (ASTM D1557) and shear strengthLateral movement monitoring
Soldier piles and laggingStructural stability analysisSPT or CPT at pile locations; GPRLoad test (ASTM D1143 axial; ASTM D3966 lateral)Structural monitoring
Track realignment away from top of slopeTrack stability analysisGPR; SPT or CPT during off-peak hoursCompaction (ASTM D698 or D1557)Track alignment monitoring

The standards and editions are those listed on the worksheet. Confirm the current edition, and that the standard fits the test intended, when the testing program is written. Method descriptions, design procedures and acceptance criteria are in Chapter 7.2; monitoring methods and trigger levels are in Chapter 5.3.

When alternatives are first framed in the field, before quantities exist, a relative ranking of cost and time is enough to tell a quick, inexpensive fix from a long capital project. Table 3.8-90 lists the methods in the same order as Table 3.8-89. Completion time is scored from 1 to 5; the scores used are 2 (about 1 week), 3 (about 3 months) and 5 (over 1 year).

Table 3.8-90. Relative cost and completion time of stabilization methods
MethodRelative costCompletion time (score)
Preloading and surchargingLowOver 1 year (5)
Sand drainsMediumAbout 3 months (3)
Vibro-compactionHighAbout 3 months (3)
Deep mixingHighAbout 3 months (3)
GroutingHighAbout 3 months (3)
Compaction grouting (low-mobility grout to 20 ft below toe of slope)HighAbout 3 months (3)
Ballast removal and replacementMediumOver 1 year (5)
Lateral drainsMediumAbout 1 week (2)
Toe bermMediumAbout 3 months (3)
Embankment wideningMediumOver 1 year (5)
Soldier piles and laggingHighOver 1 year (5)
Track realignment away from top of slopeHighOver 1 year (5)

Use the ranking with the risk ratings. Lateral drains, a medium-cost method installed in about a week, can move a Forming, Critical site (R = 12, High) to Inactive (R = 4, Guarded). That may be the right first step even where a high-cost structural fix is the long-term answer.

3.8.42.9 Field Copy Draft and Formal Report

Before the form leaves your hands, check that every block has been completed or marked “N/A”, that each Block A value has been confirmed or revised, that the photo numbers are recorded and that the red-text entries were confirmed with the railroad. Date the form, send it to a senior technical manager for review and issue it to the railroad as the field copy draft, so operating decisions are not held up while the report is written. The statement printed at the foot of Sheet 3 must stay on every copy:

FIELD COPY DRAFT – THIS DOCUMENT IS TO BE CONSIDERED A DRAFT. IT HAS ALSO BEEN SUBMITTED TO A SENIOR TECHNICAL MANAGER FOR REVIEW. THIS DOCUMENT IS SUBJECT TO EDITS, REMOVALS AND ADDITIONS. THE FORMAL REPORT WILL BE SUBMITTED WITHIN 1 WEEK OF THIS DRAFT SUBMITTAL.

The formal report follows within one week. It carries the three sheets forward with photographs, a site plan, the desk-to-field comparison from Block A, the reasoning behind the failure type, the F and S levels and the rating, and the recommended alternative with its scope, cost range and expected rating. Report format and content are covered in Chapter 8.4.

3.8.42.10 Ground Hazard Risk Assessment Checklist

  • Network screening value and entry route recorded (Section 3.8.25.1)
  • Situational rating complete: data sources, setting and construction history, driving mechanism, L1 to L5, C1 to C5, Sp (Section 3.8.23)
  • H&H thresholds set: paired gauge, toe and damage stage, culvert capacity storm, rainfall and antecedent thresholds (Section 3.8.23.7)
  • Trigger and instability rating complete: trigger narrative and T, instability record, L6, defect rating D, Fg and Fp (Section 3.8.24)
  • Static (preliminary) rating, priority and level of effort assigned (Section 3.8.25)
  • Water-sensitive sites paired with a gauge or rainfall trigger; static F and S and thresholds loaded for the live rating (Section 3.8.26)
  • Block A printed; questions for the field written; site map or KMZ in hand; live readings for the day of the visit entered (Section 3.8.42.3)
  • Railroad contact, protection type and place of safety confirmed before going on track
  • Milepost limits, affected track length, and track and traffic data recorded; exposure checked against C1 to C5 (Section 3.8.42.4)
  • Site walked; conditions recorded looking up station: left embankment, between the rails, right embankment (Section 3.8.24.4)
  • Each checked indicator photographed with scale and milepost; photo numbers noted
  • Reported geometry defects recorded with measurement and frequency
  • Major element, construction constraints and estimated failure type selected; failure type compared with the desk mechanism (Section 3.8.24.5)
  • Each Block A value confirmed or revised; questions answered
  • Stabilization items checked and assembled into up to three alternatives (Section 3.8.42.6)
  • Exploration, field testing and engineering services marked by alternative, with low and high cost
  • F, S, R and rating recorded, with reasons, for the current condition and each alternative; any one-level adjustment explained; differences of more than one level from the preliminary rating explained (Section 3.8.42.7)
  • Railroad told before leaving if the site is Severe or High
  • Alternative notes written; field copy draft issued and sent for senior review (Section 3.8.42.9)
  • Formal report scheduled within one week; revised attribute scores and thresholds returned to the desk
3.8.43 Documenting the Rationale

Every rating is recorded so that a reviewer can follow it without the engineer present, and so that the next assessment of the site starts from the reasons, not just the numbers.

  • The trigger narrative (Section 3.8.18.4), written first.
  • For T, each of L1 to L6, D and S: the level chosen and a one-line reason, with the source (record, map, photo number, measurement).
  • Fg, Fc, Rc and the current rating, with any one-level adjustment and its reason.
  • For each alternative: the solution, design, construction-stage, provisional and verified ratings, the input each changes and why, and any cap from Table 3.8-80.
  • The maintenance plan and the monitoring that will verify the residual rating.
  • No client-confidential data: use generic site descriptions in any rating that leaves the client's records.

Table 3.8-91 shows a completed record for the culvert fill site carried through Examples 3.8-3 to 3.8-6. Each line gives the level and the evidence behind it, so a reviewer can check the rating, and the next assessment can see which inputs have changed. Write the reason as the evidence, not as a restatement of the level: “four cross level exceptions returning between cycles” can be checked; “defects recurring” cannot.

Table 3.8-91. Example rationale record for the culvert fill site of Examples 3.8-3 to 3.8-6
ItemLevelReason and source
Trigger narrative—A half-blocked 36-in. culvert under a 25-ft lean clay fill ponds water against the left slope in most wet years; the fill is cracked and its defects recur. Failure is most likely to be triggered by a storm exceeding the culvert. Current risk High; reducible by restoring drainage and adding resistance.
T4Ponding in most wet years; imagery 2019–2025; water 3 ft higher on the left at the visit (photos 4–7)
L1–L54, 3, 3, 5, 4 (L5 × 2)Soil survey and old boring (lean clay over alluvium and shale); lidar (25 ft, 2H:1V); floodplain map; culvert half blocked (photo 3)
L64Shoulder slump repaired 12 years ago (railroad repair record)
D4Four cross level exceptions since the last slow order, returning between cycles (geometry reports); fresh tension cracks, left shoulder (photos 8–9)
Fg, Fc4, 4L = 27/7 = 3.86 → 4, not capped by T; Table 3.8-11, row 4, column 4
S4Main line, 28 trains a day with hazardous materials, 50 mph; creek and farmland below; detour available
Rc, rating16, HighNo one-level adjustment: crew escape route available; no shared trigger with nearby sites
Alternative 116, High (interim)Removes the trigger only; D kept at 4 until a wet season passes with no movement (Section 3.8.37.2)
Alternative 24, GuardedDrains the fill and adds resistance; D expected 1. Investigation level: field reconnaissance, so a two-level reduction is the most that may be claimed; High to Guarded is two levels and is allowed (Table 3.8-80)
Maintenance and monitoring—Culvert inspection twice a year and after storms above the site threshold; crack gauges read monthly through the first wet season to verify the post-stabilization rating
Record the investigation level with every solution rating. It decides how much credit the solution may claim (Table 3.8-80), and it is the first thing a reviewer will ask about a large reduction.
3.8.44 Limitations

The ratings are a structured way of applying engineering judgment; they do not replace it. The frequency bands are indicative, the trigger record at most sites is short, and the defect record depends on how consistently defects were reported. Ratings should be revisited after every significant triggering event, after stabilization, and whenever the traffic or exposure changes. Where the method and the engineer's judgment disagree, the engineer may raise the rating one level with a written reason (Section 3.8.22.6), and the disagreement should be reported so the method can be improved.

Table 3.8-92 lists the main limitations, what each does to a rating and how to manage it.

Table 3.8-92. Limitations of the rating method and how to manage them
LimitationEffect on the ratingWhat to do
The frequency bands are indicativeF is a level, not a measured probabilityWhere a number is needed (acceptable risk, life-cycle cost), use the probability methods of Sections 3.8.30 to 3.8.35 and state the exposure period
Trigger records at most sites are shortT may be set too high or too lowUse agency frequency analyses for rainfall and flow; log every event and recalibrate the thresholds (Section 3.8.26.6)
Defect reporting varies between territoriesD is biased low where defects were not recordedConfirm D in the field; score missing evidence 3 and flag it for the visit (Section 3.8.22.1)
F and S are ordered levels and R is their productR is not proportional to risk; equal scores can hide different sites (Cox 2008)Use R only to place a site in a rating; rank within a rating by F, then S (Table 3.8-77)
Sites are rated one at a timeSites that share a trigger fail together, so corridor risk is understatedApply the one-level raise for shared triggers; carry a corridor reserve for emergency repairs (Section 3.8.30)
Desk inputs are regionalA preliminary rating can miss a local seep, a buried culvert or old fillTreat desk ratings as preliminary; the field rating governs (Section 3.8.25)
Climate and land use changePast return periods can understate future triggersRate on current gauge and rainfall records, note any trend in the rationale, and revisit thresholds after unusual events
Live data feeds can failA missing indicator can look like a normal oneA service that does not respond is named on the site and left out, never read as normal; inspect when in doubt (Section 3.8.26.5)
A rating is not a stability analysisIt ranks risk but gives no factor of safety or designDesign from investigation and analysis (Chapter 6.3); the investigation level caps solution credit until then (Table 3.8-80)
3.8.45 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S4 under Supplemental References.

Case Study 4.18.1 — Slope failures whose consequences left the site
Case study · Look (2023) §3.8

Related section: 3.8.3 Embankment and Slope Failure Mechanisms

Look uses three historical failures to show that a slope’s safety obligations extend beyond the construction boundary:

  • Aberfan, South Wales (1966). Colliery spoil tips had been built over highly porous sandstone containing numerous springs. After heavy rain, water built up in the tip and it failed as a slurry flow that travelled about 1,430 ft downhill, killing 144 people, 116 of them schoolchildren.
  • Samarco tailings dam, Brazil (2015). The collapse flooded downstream villages, killed 19 people and carried pollutants more than a hundred miles down watercourses. Look notes an upward trend in deaths from tailings-dam failures.
  • Po Shan Road, Hong Kong (1972). After about 27.6 in of rain in three days, a landslip on a developed hillside with cuttings killed 67 people. It led to the formation of the Geotechnical Control Office in 1977 (now the Geotechnical Engineering Office).

Most slope instability is smaller and stays on site, costing time and money; but a single 12 in boulder from a cutting can reach a traffic lane or a house 164 ft away.

For railroad work: a track at the toe of mine spoil, a tailings embankment or a steep developed hillside is exposed to a failure that starts on someone else’s property. Section 3.8.3’s flow-slide mechanisms apply, and these sources belong on the hazard inventory even when they are outside the right-of-way.

Aberfan, 1966: flow of uncontrolled colliery spoil over porous sandstone with springs (after Bromhead 1992).
Figure 4-LK1. Aberfan, 1966: flow of uncontrolled colliery spoil over porous sandstone with springs (after Bromhead 1992). Source: Look (2023), Figure 3.8-42, p. 91.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §3.8, pp. 92. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

3.8.46 Practice Questions
Each question is worked in the same five parts as the examples. Try the question from the Given and Required before opening the steps. Questions 3.8-1 to 3.8-4 cover the failure mechanisms and 3.8-5 to 3.8-8 the risk ratings. Questions 3.8-1, 3.8-4 and 3.8-8 are reasoning questions; their steps are the chain of reasoning rather than a chain of equations.
Question 3.8-1: Predisposing Condition, Preparatory Factor or Trigger

Problem Statement

A Class I railroad is preparing a hazard register for a line through hilly clay country. Four factors are being entered for one embankment: a sensitive clay deposit, a culvert corroding over 20 years, a 100-year storm, and tonnage on the line doubling over a decade. The engineer must classify each as a predisposing condition, a preparatory factor or a trigger.

Classifying each factor correctly matters because each kind calls for a different response: a predisposing condition is designed around, a preparatory factor is stopped, and a trigger is watched.

(a) Sensitive clay depositclass = ?(b) Culvert corroding 20 yrclass = ?(c) 100-year stormclass = ?(d) Tonnage doubling, 10 yrclass = ?Predisposing: fixed by the sitePreparatory: slowly erodes the marginTrigger: causes failure at a given momentClassify (a) to (d)GivenFour factors at one embankmentCriteria: Section 3.8.1RequiredClass of each factor (a) to (d)Black = given; red = required
Given and required for Question 3.8-1.

Given

VariableValueDescription
(a)A sensitive clay depositFactor to classify
(b)A culvert corroding over 20 yearsFactor to classify
(c)A 100-year stormFactor to classify
(d)Tonnage on the line doubling over a decadeFactor to classify
CriteriaSection 3.8.1Predisposing: fixed by the site. Preparatory: slowly erodes the margin over time. Trigger: the event that causes failure at a given moment.

Required

  • The class of each factor (a) to (d)

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Does the factor change with time?
(a) No: predisposing. (b), (c), (d) change: go on.
Spot check: Sensitive clay is a property of the deposit; nothing the railroad does changes it.
↓
Step 2 · Does it act slowly or at one moment?
(b) and (d) act slowly: preparatory. (c) acts at one moment: trigger.
Spot check: A corroding culvert and rising tonnage reduce the margin a little each year; a storm is a single event.
↓
Solution
(a) predisposing; (b) preparatory; (c) trigger; (d) preparatory.

Solution

(a) Predisposing condition. (b) Preparatory factor. (c) Trigger. (d) Preparatory factor.

Tonnage is usually preparatory, because it wears the margin down over years. It can also act as a trigger when a single step change, such as heavier cars introduced at once, pushes a marginal subgrade past its limit. The classification therefore depends on how fast the change happens, not only on what it is.

Question 3.8-2: Saturated Fraction That Brings the Slope to Failure

Problem Statement

The railroad embankment slope of Example 3.8-1 is to be instrumented with piezometers, and the railroad wants an alarm level. The engineer must find the saturated fraction of the slipping depth at which the slope reaches a factor of safety of 1.0, and the corresponding height of water above the slip surface.

Example 3.8-1 gave the factor of safety for three water levels. This question turns the calculation around and asks how high the water must rise for the slope to fail, which is the number a monitoring program would set its alarm against.

slip surfacez = 6 ft (vertical, arrow)β = 26.6° (2H:1V)water height m·z = ? (red)m at FS = 1.0 = ?Givenτd = 288 psf; σ = 576 psfc′ = 50 psf; tanφ′ = 0.625u = 299.5 m psfTarget FS = 1.0RequiredSaturated fraction m at FS = 1.0Water height m × z (alarm level)Black = given; red = required
Given and required for Question 3.8-2.

Given

VariableValueDescription
SlopeAs Example 3.8-1τd = 288 psf; σ = 576 psf; c′ = 50 psf; tanφ′ = 0.625
u299.5 m psfPore pressure as a function of the saturated fraction m (Example 3.8-1, Step 4)
FS1.0Target condition: limiting equilibrium

Required

  • The saturated fraction m at which FS = 1.0
  • The height of water above the slip surface, m × z

Equations

  1. Eq. 1: FS = [c′ + (σ − u) tanφ′] / τd — infinite-slope factor of safety
  2. Eq. 2: u = 299.5 m — pore pressure for this slope

Steps

Step 1 · Set FS = 1.0 and substitute Eq. 2 into Eq. 1
50 + (576 − 299.5 m) × 0.625 = 288
410 − 187.2 m = 288
↓
Step 2 · Solve for m
m = (410 − 288) / 187.2 = 122 / 187.2
m = 0.65
Spot check: Back-substitute: u = 299.5 × 0.65 = 195 psf; [50 + (576 − 195) × 0.625] / 288 = 288 / 288 = 1.00.
↓
Step 3 · Height of water above the slip surface
Uses: m, z = 6 ft
0.65 × 6
About 3.9 ft above the slip surface
↓
Solution
m = 0.65: failure when water rises to about two-thirds of the slip depth.

Solution

m = 0.65. The slope fails when the water table rises to about two-thirds of the slipping depth, about 3.9 ft above the slip surface.

The answer falls between the half-saturated case (FS = 1.10) and the fully saturated case (FS = 0.77) of Example 3.8-1, as it must. A piezometer at this site would set its warning level well below m = 0.65, for example at m = 0.4 to 0.5, so there is time to act before failure.

Question 3.8-3: A Long, Moderate Storm Against the Caine Threshold

Problem Statement

A Class I railroad uses a rainfall threshold to decide when to send patrols ahead of trains on a line with a history of debris flows. A storm delivered 3.0 in. of rain over 24 hours. The engineer must compute the average intensity and decide whether the storm exceeded the Caine threshold.

A long storm can deliver more rain than a short one and still fall below the threshold, because the threshold intensity drops as the duration grows. This question checks a 24-hour storm.

0.1110100Duration D (hr, log)Intensity I (in./hr, log)0.010.1110Caine (1980): I = 0.58 D−0.39D = 24 hr: I = ? Exceeds?GivenP = 3.0 in.D = 24 hrI = 0.58 D−0.39 (in./hr)RequiredAverage intensity and threshold at 24 hrIs the threshold exceeded?Black = given; red = required
Given and required for Question 3.8-3.

Given

VariableValueDescription
P3.0 in.Storm rainfall
D24 hrStorm duration
ThresholdI = 0.58 D−0.39Caine (1980), in./hr

Required

  • Average intensity and the threshold at 24 hours
  • Whether the storm exceeds the threshold

Equations

  1. Eq. 1: I = P / D — average intensity
  2. Eq. 2: It = 0.58 D−0.39 — threshold intensity

Steps

Step 1 · Storm intensity I (Eq. 1)
I = 3.0 / 24
I = 0.125 in./hr
Spot check: 0.125 × 24 = 3.0 in.
↓
Step 2 · Threshold intensity It (Eq. 2)
240.39 = 3.45; It = 0.58 / 3.45
It = 0.17 in./hr
Spot check: ln 24 = 3.18; 0.39 × 3.18 = 1.24; e1.24 = 3.45.
↓
Step 3 · Compare
0.125 in./hr against 0.17 in./hr
I < It: the storm does not exceed the threshold
Spot check: Ratio 0.125 / 0.17 = 0.74.
↓
Solution
The storm does not exceed the threshold (0.125 < 0.17 in./hr).

Solution

No. At 0.125 in./hr the storm is below the 24-hour threshold of 0.17 in./hr.

This storm delivers 50% more rain than the one in Example 3.8-2 and still falls below the threshold. The comparison shows why intensity, not total rainfall, governs. It does not close the matter: wet antecedent conditions or a locally calibrated threshold could still call for a response.

Question 3.8-4: Why Diagnose the Mechanism Before the Repair

Problem Statement

A Class I railroad has had a series of slides at one cut and wants to order a repair quickly, before the cause has been studied. The engineer must explain why the failure mechanism, and not only the trigger, should be diagnosed before a repair is selected.

This is a reasoning question. It is answered from the principles of Section 3.8.1 and the control hierarchy of Section 1.1.9.

Same symptomtrack dip / slideMechanism Ae.g. seepageMechanism Be.g. weak layerMechanism Ce.g. erosionRepair A?Repair B?Repair C?Why diagnose the mechanism first?GivenRepeated slides at one cutPrinciple 1: one symptom, many mechanismsPrinciple 2: remove the hazard ranks above managing exposureRequiredWhy the mechanism, not just the trigger, must be diagnosed firstBlack = given; red = required
Given and required for Question 3.8-4.

Given

VariableValueDescription
Principle 1Section 3.8.13The same symptom can come from different mechanisms.
Principle 2Section 1.1.9Controls that remove or reduce the hazard rank above those that only manage exposure.

Required

  • Why the mechanism, and not just the trigger, must be diagnosed before a repair is selected

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · What does a repair act on?
A repair works only if it acts on the mechanism that is failing the ground.
↓
Step 2 · What happens if the mechanism is wrong?
Money is spent and the hazard stays. Example: undercutting ballast where the cause is a deep-seated slide.
↓
Step 3 · What happens if only the trigger is managed?
The hazard stays in place, and the railroad relies on patrols and slow orders indefinitely.
↓
Solution
Diagnose the mechanism, or the repair may treat the wrong problem.

Solution

Because the same symptom can come from different mechanisms, and a repair aimed at the wrong one spends money without reducing the hazard.

Managing only the trigger, with patrols or speed restrictions, leaves the hazard in place and commits the railroad to those restrictions indefinitely. Inclinometers and piezometers cost little compared with a buttress built for the wrong failure surface, which is why Section 3.8.16 recommends confirming the mechanism with instruments before committing capital.

Question 3.8-5: Current Frequency When the Defects Are Light

Problem Statement

A Class I railroad located in Kentucky has a side-hill fill on a main line where the desk study gives a geospatial frequency Fg = 4 and a severity S = 3. The geometry records show defects reported more than once but not returning between surfacing cycles (D = 3). The roadmaster asks what the rating would be if the records had shown no defects at all (D = 1).

The current frequency index is not the higher of Fg and D. Table 3.8-11 caps susceptibility without movement at Forming, and amplifies light defects at a highly susceptible site. This question exercises both rules.

51015202548121620369121524681012345D = 3D = 1Severity S →Frequency F →GivenF​g = 4 (desk)S = 3, SeriousCase 1: D = 3 (Present)Case 2: D = 1 (None)RequiredF​c for each case (Table 3.8-11)R and rating for each caseWhy the two differBlack = given; red = required
Given and required for Question 3.8-5.

Given

VariableValueDescription
Fg4Geospatial frequency from the desk study
S3Serious: main line with light traffic
D3 or 1Defect rating, case 1 and case 2 (Table 3.8-10)
RuleEquation 3.8-3Fc = the greater of D and the lesser of (Fg, 3), plus 1 where D ≥ 3 and Fg ≥ D + 1

Required

  • Fc, R and the rating for D = 3 and for D = 1
  • The reason for the difference

Equations

  1. Eq. 1: Fc = max[D, min(Fg, 3)] (+1 if D ≥ 3 and Fg ≥ D + 1) — Equation 3.8-3, Table 3.8-11
  2. Eq. 2: R = Fc × S — risk score, Table 3.8-16

Steps

Step 1 · Case 1, D = 3 (Eq. 1)
Uses: Fg, D
max[3, min(4, 3)] = 3; D ≥ 3 and Fg = 4 ≥ D + 1 = 4, so add 1
Fc = 4, Emerging
Spot check: Table 3.8-11, row Fg = 4, column D = 3 reads 4.
↓
Step 2 · Case 1 rating (Eq. 2)
Uses: Fc, S
R = 4 × 3
R = 12, High
Spot check: 12 is the lower edge of High.
↓
Step 3 · Case 2, D = 1 (Eq. 1)
Uses: Fg, D
max[1, min(4, 3)] = 3; D < 3, no amplification
Fc = 3, Forming
Spot check: Table 3.8-11, row 4, column 1 reads 3: the cap.
↓
Step 4 · Case 2 rating (Eq. 2)
Uses: Fc, S
R = 3 × 3
R = 9, Elevated
Spot check: One level lower than case 1 from a single step in F.
↓
Solution
D = 3: Fc = 4, R = 12 High. D = 1: Fc = 3, R = 9 Elevated.

Solution

With D = 3 the site is Emerging and High (12); with no defects it is Forming and Elevated (9). Without evidence of movement, a susceptible setting can only make a site Forming: Emerging and Occurring require signs at the track (Table 3.8-14). Light defects at a site that susceptible are taken as the start of a response that will be tested again soon, so the rating is raised one level. The desk rating with D = 1 is a reason to visit early, not proof of activity.

Question 3.8-6: Live Rating During a River Rise

Problem Statement

A Class I railroad located in Iowa has a fill along a river whose static rating is Forming (F0 = 3) and Critical (S = 4). A spring storm is forecast. The paired gauge is forecast to reach action stage (Watch), and the forecast 24-hour rainfall is 60% of the site threshold (Watch). Soil moisture is normal. The dispatcher asks for the live rating and the response.

The live rating raises F by the increments of Table 3.8-32 while indicators are at Watch or Warning. S does not change with the weather.

51015202548121620369121524681012345staticliveSeverity S →Frequency F →GivenStatic: F​0 = 3, S = 4 (R = 12, High)River forecast at action stage: WatchRainfall at 60% of threshold: WatchSoil moisture: NormalRequiredIncrement and F​liveR​live and ratingResponse and when to drop itBlack = given; red = required
Given and required for Question 3.8-6.

Given

VariableValueDescription
F0, S3, 4Static rating: R = 12, High
RiverForecast at action stageWatch (Table 3.8-31)
Rainfall60% of the site thresholdWatch: half the threshold up to the threshold
Soil moistureNormalNo increment
RuleTable 3.8-32+1 for one Watch; +2 for two or more Watch or any Warning; F = 5 on river or rain Warning where F0 ≥ 4; maximum 5

Required

  • The increment, Flive, Rlive and the rating
  • The response, and when the live rating may be dropped

Equations

  1. Eq. 1: Flive = min(5, F0 + increment) — Table 3.8-32
  2. Eq. 2: Rlive = Flive × S — read from Table 3.8-16

Steps

Step 1 · Count the indicators
Uses: River, rainfall, soil moisture
Two indicators at Watch; none at Warning
Increment = +2
Spot check: The “set F to 5” rule does not apply: no Warning, and F0 = 3 is below 4.
↓
Step 2 · Live frequency (Eq. 1)
Uses: F0, increment
min(5, 3 + 2)
Flive = 5
Spot check: The maximum is not exceeded, so no truncation.
↓
Step 3 · Live rating (Eq. 2)
Uses: Flive, S
Rlive = 5 × 4
Rlive = 20, Severe
Spot check: Reported as a jump: High → Severe (Section 3.8.26.4).
↓
Step 4 · Response and hold
Uses: Table 3.8-17; Section 3.8.26.5
Act now: protect the track and restrict operations until inspected
Hold until the river is below action stage and 48 h after the crest or end of rain
Spot check: Fills along rivers often fail on the falling limb, so the rating is not dropped at the crest.
↓
Solution
Flive = 5; Rlive = 20, Severe (jump from High).

Solution

Two Watch indicators raise F from 3 to 5, and the rating jumps from High (12) to Severe (20). The response is to act now: inspect before and after the crest and restrict operations until the site has been checked. The rating is held until the river is back below action stage and at least 48 hours have passed, because many embankments fail as the water falls. Wet ground and heavy rain together are treated as more than either alone, which is why two Watches count as much as one Warning.

Question 3.8-7: Credit for a Solution Proposed from the Desk

Problem Statement

A Class I railroad located in Pennsylvania has a fill rated Emerging (F = 4) and Critical (S = 4). The consultant proposes a drained toe berm from a desk study only; no borings have been drilled. Rescored as built, the berm gives Fsol = 1. The program manager wants to enter the solution rating in the capital plan.

Table 3.8-80 caps the risk reduction a solution can claim according to the level of investigation behind it, so that an unproven fix does not outrank a proven one.

51015202548121620369121524681012345currentuncappedcappedSeverity S →Frequency F →GivenCurrent: F = 4, S = 4 (R = 16, High)Berm as built: F​sol = 1, S = 4Investigation level: desk study onlyCap: desk study, at most one levelRequiredUncapped solution ratingCapped solution rating to reportWhat earns full creditBlack = given; red = required
Given and required for Question 3.8-7.

Given

VariableValueDescription
F, S4, 4Current rating: R = 16, High
Fsol1Rescored as the berm would perform once built (Section 3.8.37.2)
InvestigationDesk study onlyNo subsurface investigation or analysis
CapTable 3.8-80Desk study: at most one level; field reconnaissance: two; subsurface investigation and analysis: full credit

Required

  • The uncapped solution rating
  • The capped solution rating to report
  • What would earn full credit

Equations

  1. Eq. 1: R = F × S — risk score and rating, Table 3.8-16

Steps

Step 1 · Uncapped rating (Eq. 1)
Uses: Fsol, S
R = 1 × 4
R = 4, Guarded
Spot check: High to Guarded is a drop of two levels (High, Elevated, Guarded).
↓
Step 2 · Apply the cap
Uses: Table 3.8-80
Desk study allows one level: High → Elevated at best
Capped rating: Elevated
Spot check: Two levels claimed, one allowed.
↓
Step 3 · Report it
Uses: Section 3.8.43
Enter the lowest F that gives Elevated with S = 4: F = 2, R = 8, with the reason
R = 8, Elevated (capped: desk study)
Spot check: 2 × 4 = 8 is Elevated; 1 × 4 = 4 would not be allowed.
↓
Solution
Report Elevated (R = 8), capped from Guarded (4) until borings and analysis confirm the mechanism.

Solution

As built the berm would rate Guarded (4), but from a desk study it may claim only one level of reduction, so the solution rating entered in the plan is Elevated (8), marked as capped. Without a confirmed mechanism and ground model, the berm could be treating the wrong problem. A subsurface investigation and stability analysis that confirm the slip surface and the drained strength earn the full credit, and the solution rating then moves to Guarded. The cap is what keeps an unproven idea from outranking a proven design in the capital plan.

Question 3.8-8: Ranking Two Sites with the Same Score

Problem Statement

A Class I railroad located in Ohio has two sites on the same subdivision, each with a risk score of 12. Site A is Emerging (F = 4) with a Serious consequence (S = 3). Site B is Forming (F = 3) with a Critical consequence (S = 4). There is money to stabilize one site this year, and the manager asks which comes first.

R places a site in a rating; it does not measure risk in proportion. Table 3.8-77 gives the rule for ordering sites within a rating.

51015202548121620369121524681012345ABSeverity S →Frequency F →GivenSite A: F = 4, S = 3, R = 12Site B: F = 3, S = 4, R = 12Both HighRule: within a rating, rank by F, then SRequiredWhich site ranks firstWhen the order would changeBlack = given; red = required
Given and required for Question 3.8-8.

Given

VariableValueDescription
Site AF = 4, S = 3Emerging; Serious
Site BF = 3, S = 4Forming; Critical
RuleTable 3.8-77Use R only to place a site in a rating; within a rating, rank by F, then S
AdjustmentsSection 3.8.22.4C floor, “consequence governs” and the engineer’s one-level raise

Required

  • Which site ranks first and why
  • What would change the order

Equations

No equation is needed; the answer follows from the rules listed under Given.

Steps

Step 1 · Place both in a rating
Uses: R
Both R = 12
Both High
Spot check: 3×4 and 4×3 are both in the High list of Table 3.8-72.
↓
Step 2 · Rank within the rating
Uses: Table 3.8-77
Compare F first: A = 4, B = 3
Site A ranks first
Spot check: A is already moving (Emerging); B has the conditions for failure but no movement yet.
↓
Step 3 · Check the adjustments
Uses: Section 3.8.22.4
Does B carry a 5 on C2 or C3, or a reason for the one-level raise (no safe escape, shared trigger)?
If so, B rises to Severe and ranks first
Spot check: A one-level raise on B gives Severe, which outranks any High.
↓
Solution
Site A first, unless an adjustment raises Site B to Severe.

Solution

Site A ranks first: both are High, and within a rating the site with the higher F comes first. A is failing now, so the benefit of fixing it is gained soonest (Figure 3.8-42 shows how quickly the chance of failure builds with exposure). Site B’s higher consequence is not ignored: it should be monitored and placed first in the next program, and if the hazardous materials traffic, what lies below the fill or a shared trigger justifies the engineer’s one-level raise, B becomes Severe and moves ahead of A. Write the reason for the order in the rationale either way (Section 3.8.43).

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

3.8.47 Cross-References
Table 3.8-93. Related chapters and sections
TopicRefer to
Risk equation, risk resolution matrix and risk control hierarchySections 1.1.2, 1.1.7 and 1.1.9
Mechanism, condition and trigger; trigger inventory; rainfall thresholdsSections 3.8.1, 3.8.11 and 3.8.12
Desktop data sources for the geospatial ratingChapter 3.2; Section 3.8.23.1
Scales, risk matrix and required responsesSection 3.8.22
Situational and instability attributes; field indicatorsSections 3.8.23 and 3.8.24
Live ratingSection 3.8.26
Cost estimates for alternativesChapter 3.7
Slope stability factors of safetySection 6.3.5
Construction monitoring and quality controlChapter 5.3
Retaining structures and ground improvementChapters 7.1 and 7.2
Rated elements and the criteria for each level of every ratingSection 3.8.27
Track substructure: fouled ballast, pumping, subgrade defectsChapter 2.3
Hazard monitoring map, river stage watchlist, live risk rating and Site Background ReportHazard monitoring map
Failure mechanisms and triggers; diagnosing the mechanismChapter 3.8
Planning the explorationChapter 3.9
Borings and samplingChapter 4.1
In situ testing: DCP, CPT, GPRChapter 5.1
Groundwater, seepage and piezometersChapter 2.8
Laboratory testing programChapter 5.2
Slope stability analysisChapter 6.3
Report preparationChapter 8.4

Failure mechanisms and triggers

TopicSee Also
Hazard classification, risk estimation and control hierarchyChapter 1.1
Subgrade failure modes, fouling index, GPRChapter 2.3
Foundation elements, culverts, bridge approachesChapter 2.1
Frost susceptibility classification of soilsChapter 2.2, Section 2.2.7
Frost penetration depth and frost designChapter 7.3, Section 7.3.5
Live risk rating with thaw and snowmelt indicatorsChapter 3.8, Section 3.8.26.3; Hazard monitoring map
Groundwater and seepageChapter 2.8
Settlement analysisChapter 6.2
Slope stability analysisChapter 6.3
Seismic hazard and liquefactionChapter 6.5
Instrumentation and monitoringChapter 5.3
Stabilization and ground improvementChapters 16, 17; Section 7.2.16
Groundwater Monitoring for Slope Stability
Groundwater Monitoring for Slope Stability
Rockfall Mitigation and Slope Stabilization
Rockfall Mitigation and Slope Stabilization
References
  • Caine, N. (1980). The rainfall intensity–duration control of shallow landslides and debris flows. Geografiska Annaler, Series A, 62(1–2), 23–27.Find source ↗
  • Cruden, D.M. and Varnes, D.J. (1996). Landslide types and processes. In Landslides: Investigation and Mitigation, TRB Special Report 247.Find source ↗
  • Hungr, O., Leroueil, S. and Picarelli, L. (2014). The Varnes classification of landslide types, an update. Landslides, 11, 167–194.Find source ↗
  • Selig, E.T. and Waters, J.M. (1994). Track Geotechnology and Substructure Management. Thomas Telford.Find source ↗
  • Li, D., Hyslip, J., Sussmann, T. and Chrismer, S. (2016). Railway Geotechnics. CRC Press, Boca Raton, Florida. Cited as 2015 in Ruel (2026b).Find source ↗
  • Federal Railroad Administration, Track Safety Standards, 49 CFR Part 213 (incl. §213.239 Special inspections).eCFR Part 213 ↗
  • FHWA, HEC-18, Evaluating Scour at Bridges, 5th edition, FHWA-HIF-12-003 (2012), the current edition.Find source ↗
  • ASTM D6230, Standard Test Method for Monitoring Ground Movement Using Probe-Type Inclinometers.Official page ↗
  • Bunce, C. (forthcoming). Chapter 11, Railway tunnel hazards. In Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada.Find source ↗
  • CSA (Canadian Standards Association) (1997). Risk Management: Guideline for Decision-Makers. CAN/CSA-Q850-97. Canadian Standards Association, Mississauga, Ontario.Find source ↗
  • CSA (Canadian Standards Association) (2022). CSA R114: Canadian Methodology for Risk Evaluation and Assessment for Railways (CMREA). CSA Group, Toronto, Ontario.Find source ↗
  • ISO (International Organization for Standardization) (2018). ISO 31000:2018, Risk Management — Guidelines. ISO, Geneva.Find source ↗
  • Keegan, T.R. (2007). Methodology for Risk Management of Railway Ground Hazards. Ph.D. thesis, Department of Civil and Environmental Engineering, University of Alberta, Edmonton, Alberta.Find source ↗
  • Keegan, T.R. (n.d.). A Railway Ground Hazard Risk Analysis Methodology Overview. Klohn Crippen Berger Ltd., Vancouver, British Columbia.Find source ↗
  • Macciotta, R. (forthcoming). Chapter 2, Risk assessment methodologies. In Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada.Find source ↗
  • RGHRP (Railway Ground Hazard Research Program) (forthcoming). Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada.Find source ↗
  • Roghani, A. (2021). Quantifying the effect of freeze–thaw cycles on track surface deformation and degradation of railway track geometry; case study. Transportation Geotechnics, 30, 100601.Find source ↗
  • Roghani, A., Caldwell, R., Hiedra-Cobo, J. and Charbachi, P. (2021). Lessons learned from a long-term frost heave monitoring under a railway embankment. Proceedings of the 1st Canadian and Cold Regions Rail Research Conference (CCRC 2021), National Research Council Canada.Find source ↗
  • Roghani, A., Liu, Y. and Burgess, P. (2021). Investigating the impact of frost heave and thaw softening on changing the vertical force at wheel/rail interface. Proceedings of the 1st Canadian and Cold Regions Rail Research Conference (CCRC 2021), National Research Council Canada.Find source ↗
  • Ruel, M. (2024). Railway ballast, Chapter 12. In Canadian Railway Geohazard Manual (forthcoming). Proceedings of the 77th Canadian Geotechnical Conference (GeoMontréal 2024), Montréal, Québec, September 15–18, 2024.Find source ↗
  • Ruel, M. (2026a). Recommended Method 1606: Spring Preparedness. A Canadian passenger railroad, Montréal, Québec.Find source ↗
  • Ruel, M. (2026b). Railway frost geohazards: winter to spring break-up, frost heave and soft subgrade. Chapter 9 (final draft, September 3, 2026), Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada. Source of Sections 3.8.7 and 3.8.8 and Figures 3.8.7-1 to 3.8.8-18.Find source ↗
  • TSB (Transportation Safety Board of Canada) (1992). Derailment, Class I railroad Company, Train No. 303-18, Mile 133.5, Caramat subdivision, Nakina, Ontario, 19 July 1992. Railway Investigation Report R92T0183. TSB, Gatineau, Québec.Find source ↗
Supplemental References

Sections on this page marked “After Profillidis (2014)” draw on the document below. Text is summarized or paraphrased; tables are transcribed or reproduced with their original source noted; figures and photos are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S3 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S4 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  2. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  3. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 3, 4, 8, 14 and 15Find source ↗Library entry
  4. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §3.8Find source ↗Library entry
  5. Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute. Used on this page for project-management materialFind source ↗
  6. Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]. Used on this page for project-management materialFind source ↗
Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This part was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management. Sections 3.8.7 and 3.8.8 are adapted from Mario Ruel’s chapter on railway frost geohazards for the Railway Ground Hazard Research Program (Ruel 2026b).

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

References

  • Caine, N. (1980). The rainfall intensity–duration control of shallow landslides and debris flows. Geografiska Annaler, Series A, 62(1–2), 23–27.Find source ↗
  • Cruden, D.M. and Varnes, D.J. (1996). Landslide types and processes. In Landslides: Investigation and Mitigation, TRB Special Report 247.Find source ↗
  • Hungr, O., Leroueil, S. and Picarelli, L. (2014). The Varnes classification of landslide types, an update. Landslides, 11, 167–194.Find source ↗
  • Selig, E.T. and Waters, J.M. (1994). Track Geotechnology and Substructure Management. Thomas Telford.Find source ↗
  • Li, D., Hyslip, J., Sussmann, T. and Chrismer, S. (2016). Railway Geotechnics. CRC Press, Boca Raton, Florida. Cited as 2015 in Ruel (2026b).Find source ↗
  • Federal Railroad Administration, Track Safety Standards, 49 CFR Part 213 (incl. §213.239 Special inspections).eCFR Part 213 ↗
  • FHWA, HEC-18, Evaluating Scour at Bridges, 5th edition, FHWA-HIF-12-003 (2012), the current edition.Find source ↗
  • ASTM D6230, Standard Test Method for Monitoring Ground Movement Using Probe-Type Inclinometers.Official page ↗
  • Bunce, C. (forthcoming). Chapter 11, Railway tunnel hazards. In Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada.Find source ↗
  • CSA (Canadian Standards Association) (1997). Risk Management: Guideline for Decision-Makers. CAN/CSA-Q850-97. Canadian Standards Association, Mississauga, Ontario.Find source ↗
  • CSA (Canadian Standards Association) (2022). CSA R114: Canadian Methodology for Risk Evaluation and Assessment for Railways (CMREA). CSA Group, Toronto, Ontario.Find source ↗
  • ISO (International Organization for Standardization) (2018). ISO 31000:2018, Risk Management — Guidelines. ISO, Geneva.Find source ↗
  • Keegan, T.R. (2007). Methodology for Risk Management of Railway Ground Hazards. Ph.D. thesis, Department of Civil and Environmental Engineering, University of Alberta, Edmonton, Alberta.Find source ↗
  • Keegan, T.R. (n.d.). A Railway Ground Hazard Risk Analysis Methodology Overview. Klohn Crippen Berger Ltd., Vancouver, British Columbia.Find source ↗
  • Macciotta, R. (forthcoming). Chapter 2, Risk assessment methodologies. In Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada.Find source ↗
  • RGHRP (Railway Ground Hazard Research Program) (forthcoming). Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada.Find source ↗
  • Roghani, A. (2021). Quantifying the effect of freeze–thaw cycles on track surface deformation and degradation of railway track geometry; case study. Transportation Geotechnics, 30, 100601.Find source ↗
  • Roghani, A., Caldwell, R., Hiedra-Cobo, J. and Charbachi, P. (2021). Lessons learned from a long-term frost heave monitoring under a railway embankment. Proceedings of the 1st Canadian and Cold Regions Rail Research Conference (CCRC 2021), National Research Council Canada.Find source ↗
  • Roghani, A., Liu, Y. and Burgess, P. (2021). Investigating the impact of frost heave and thaw softening on changing the vertical force at wheel/rail interface. Proceedings of the 1st Canadian and Cold Regions Rail Research Conference (CCRC 2021), National Research Council Canada.Find source ↗
  • Ruel, M. (2024). Railway ballast, Chapter 12. In Canadian Railway Geohazard Manual (forthcoming). Proceedings of the 77th Canadian Geotechnical Conference (GeoMontréal 2024), Montréal, Québec, September 15–18, 2024.Find source ↗
  • Ruel, M. (2026a). Recommended Method 1606: Spring Preparedness. A Canadian passenger railroad, Montréal, Québec.Find source ↗
  • Ruel, M. (2026b). Railway frost geohazards: winter to spring break-up, frost heave and soft subgrade. Chapter 9 (final draft, September 3, 2026), Canadian Railway Geohazard Manual. Railway Ground Hazard Research Program, Canada. Source of Sections 3.8.7 and 3.8.8 and Figures 3.8.7-1 to 3.8.8-18.Find source ↗
  • TSB (Transportation Safety Board of Canada) (1992). Derailment, Class I railroad Company, Train No. 303-18, Mile 133.5, Caramat subdivision, Nakina, Ontario, 19 July 1992. Railway Investigation Report R92T0183. TSB, Gatineau, Québec.Find source ↗

Case studies

  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §3.8Find source ↗Library entry

Project management sources

  • Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management InstituteFind source ↗
  • Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version]Find source ↗