This chapter sets out the method for rating ground hazard risk on a railroad and applies it to a single site. It starts from the triggering mechanism, which gives every rating its narrative, and determines the current risk from the geospatial risk and the defect rating. It then sets out the 1-to-5 scales, the risk score R = F × S and the risk matrix (Section 3.8.22), and applies them through the situational, instability, static and live ratings and the rated elements behind them. Each proposed solution is rated through three stages (the solution itself, design and construction, and post-stabilization implementation) so that the risk reduction is measured, not assumed. The chapter closes with the Ground Hazard Risk Assessment Report (Section 3.8.42), the worksheet that records the ratings for a site. Primary references: Chapter 1.1 risk framework; Chapter 3.8 failure mechanisms; Chapters 5.3, 7.1 and 7.2 stabilization methods.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Reliability values that relate factor of safety to annual probability of failure. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| COV of factor of safety | Earth structures – Category I | State-of-the-practice design, construction and operation; usually high consequence | 7.2 | % | FGE T31.1, p.476 | |||
| COV of factor of safety | Earth structures – Category II | Standard engineering practice; most ordinary facilities | 10.9 | % | FGE T31.1, p.476 | |||
| COV of factor of safety | Earth structures – Category III | No site-specific design, substandard construction or operation; temporary or low consequence | 17.4 | % | FGE T31.1, p.476 | |||
| COV of factor of safety | Earth structures – Category IV | Little or no engineering | 31.6 | % | FGE T31.1, p.476 | |||
| Average annual failure probability | Homogeneous / composite earth dams – Seepage erosion / piping | Historical rate 2.19×10⁻⁴ | 0.000237 | per year | FGE T6.2, p.108 | |||
| Average annual failure probability | Homogeneous / composite earth dams – Overtopping | Historical rate 4.39×10⁻⁴ | 0.000424 | per year | FGE T6.2, p.108 |
| Estimate | Correlation | Limits / notes | Source |
|---|---|---|---|
| Probability of failure from mean FS and its COV | pf = P(FS < 1) ≈ Φ(−ln μFS / θ) (FS lognormal, θ = COV of FS small) | Reproduces Silva et al. (2008) curves; θ ≈ 0.07–0.32 by structure category | FGE text, p.475 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
Typical Values: Failure Mechanisms and Triggers — from the GHRM Soil & Rock Properties Database
Values behind common track substructure failure mechanisms: fouling, subgrade plastic strain and why failures happen. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Source of ballast fouling (share by weight) | Ballast breakdown | Average of North American sites | 76 | % | SELIG Fig. 8.33, p.8.25 | |||
| Source of ballast fouling (share by weight) | Infiltration from underlying granular layers | Average of North American sites | 13 | % | SELIG Fig. 8.33, p.8.25 | |||
| Source of ballast fouling (share by weight) | Ballast surface (spillage, wind-blown) | Average of North American sites | 7 | % | SELIG Fig. 8.33, p.8.25 | |||
| Source of ballast fouling (share by weight) | Subgrade infiltration | Average of North American sites | 3 | % | SELIG Fig. 8.33, p.8.25 | |||
| Source of ballast fouling (share by weight) | Tie wear | Average of North American sites | 1 | % | SELIG Fig. 8.33, p.8.25 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Cumulative plastic strain coefficient a | Fat clay | CH | Li & Selig (1996) model | 0.82 | 1.2 | 1.5 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain exponent b | Fat clay | CH | Li & Selig (1996) model | 0.12 | 0.18 | 0.27 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain exponent m | Fat clay | CH | Li & Selig (1996) model | 1.3 | 2.4 | 3.9 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain coefficient a | Lean clay | CL | Li & Selig (1996) model | 0.3 | 1.1 | 3.5 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain exponent b | Lean clay | CL | Li & Selig (1996) model | 0.08 | 0.16 | 0.34 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain exponent m | Lean clay | CL | Li & Selig (1996) model | 1 | 2 | 2.6 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain coefficient a | Elastic silt | MH | Li & Selig (1996) model | 0.84 | – | LI16 T4.7, p.174 | ||
| Cumulative plastic strain exponent b | Elastic silt | MH | Li & Selig (1996) model | 0.08 | 0.13 | 0.19 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain exponent m | Elastic silt | MH | Li & Selig (1996) model | 1.3 | 2 | 4.2 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain coefficient a | Silt | ML | Li & Selig (1996) model | 0.64 | – | LI16 T4.7, p.174 | ||
| Cumulative plastic strain exponent b | Silt | ML | Li & Selig (1996) model | 0.06 | 0.1 | 0.17 | – | LI16 T4.7, p.174 |
| Cumulative plastic strain exponent m | Silt | ML | Li & Selig (1996) model | 1.4 | 1.7 | 2 | – | LI16 T4.7, p.174 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Primary cause of geotechnical failure (share of cases) | Shortcomings in design | ISSMGE TC302 Task Force 10, ~100 case histories | 45 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Inadequate site investigation | ISSMGE TC302 Task Force 10, ~100 case histories | 20 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Unforeseen phenomena and occurrences | ISSMGE TC302 Task Force 10, ~100 case histories | 20 | % | FGE text, p.278 | |||
| Primary cause of geotechnical failure (share of cases) | Shortcomings in construction | ISSMGE TC302 Task Force 10, ~100 case histories | 14 | % | FGE text, p.274 |
| Estimate | Correlation | Limits / notes | Source |
|---|---|---|---|
| Fouling index | FI = P4 + P200 (percent passing No. 4 and No. 200 sieves) | Selig & Waters (1994); categories clean < 1 … highly fouled > 40 | LI16 Eq. 3.1, p.84 |
| Cumulative plastic strain of subgrade | εp(%) = a (σd/σs)^m N^b | σd = deviator stress, σs = soil compressive strength, N = load cycles; a, b, m by soil type in the database | LI16 4.7, p.174 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
After a failure: see Forensic Investigation of Ground Failures (Chapter 17) for what to record, how to scope the investigation, back analysis and vibration claims.
A risk rating has to answer four questions in order: what will set this site off, how likely is failure now, how bad would it be, and how much will the proposed fix reduce the risk, and when. This chapter answers them in five steps. Each step uses the same 1-to-5 scales, in which risk increases with the number, and each ends on the same risk matrix (Table 3.8-16), so a rating means the same thing at every step.
Sections 3.8.1 to 3.8.17 describe how track-support and ground-hazard failures develop, the conditions that set them up and the events that set them off (formerly Chapter 2.2, Failure Mechanisms and Triggers). The ratings from Section 3.8.18 on build on them: the trigger narrative names the mechanism, and the defect and instability ratings record its symptoms.
| Step | Question | Ratings produced | Section |
|---|---|---|---|
| 1. Triggering mechanism | What sets the site off, how often, and how close is it now? | Trigger rating T; trigger narrative | 3.8.18 |
| 2. Current risk | How likely is failure now, and how bad would it be? | Geospatial frequency Fg, defect rating D, current frequency Fc, severity S, current risk rating | 3.8.19 to 3.8.21 |
| 3. Solution | How much will the measure reduce the risk if it works as intended? | Solution rating (Fsol, Ssol) | 3.8.37 |
| 4. Design and construct | How much reduction does the design actually earn, and what is the risk while it is built? | Design rating Fdes; construction-stage rating | 3.8.38 |
| 5. Post-stabilization implementation | Has the work performed through a triggering event, and is it maintained? | Provisional and verified residual rating | 3.8.39 |
The same five steps apply at the desk, on the live map and in the field; only the source of each rating changes. Every rating is recorded with a one-line reason for each level chosen (Section 3.8.43), and no rating includes client-confidential data. The elements behind each rating, and what places each one at 1, 2, 3, 4 or 5, are tabulated in Section 3.8.27.
Section 1.1.2 sets out the working equation for ground hazard risk, Risk = Hazard × (Consequence & Vulnerability), and Section 1.1.7 sorts risk scenarios into Unacceptable, Tolerable with Mitigation and Tolerable. Section 1.1.8 explains why a railroad with hundreds or thousands of tracked sites needs standard tools that turn records and field observations into comparable scores. This chapter is that tool for a single embankment, cut or drainage site. Every site is rated on the same scales, so sites can be compared, ranked and funded on a consistent basis.
A site usually enters the program by one of four routes: a recurring track geometry defect (cross level, profile, alignment or warp exceptions reported at the same location), a visible ground hazard (a bulge, tension crack, seepage, erosion, or a blocked or damaged culvert reported by patrol or the public), a slow order placed because the track can no longer be held at normal speed, or network screening, in which the railroad ranks its segments by hazard exposure and studies the highest first. Whatever the route, the railroad needs the same three answers: how serious the site is now, what will fix it, and what the fix will cost.
The chapter answers those questions in six steps. Each step produces a rating, or part of one, on the same five-level scales, and each step hands its result to the next.
The rating is assigned twice for each site. A preliminary rating is made at the desk from the situational and instability attributes before anyone goes on track (Sections 3.8.23 to 3.8.25). The field rating is made by the engineer in charge (EIC) at the site on the Ground Hazard Risk Assessment Report (Section 3.8.42), which carries the preliminary values with it so each one can be confirmed or changed. Between visits, the live rating (Section 3.8.26) watches for the weather and river conditions that change the risk from day to day.
These sections sit in Section 3.0, Risk Management, before investigation planning in Chapter 3.9. Sections 3.8.18 to 3.8.21 and 3.8.37 to 3.8.39 set out the overall rating method (triggering mechanisms as the narrative, current risk as geospatial risk plus defect rating, and risk reduction ratings for each solution through design, construction and post-stabilization implementation); the sections described here apply it at a single site. It draws on the risk framework of Chapter 1.1, the failure mechanisms of Chapter 3.8 and the stabilization methods of Chapters 5.3, 7.1 and 7.2 to reach a recommendation. The reasoning behind every scale, level and rating is collected in Section 3.8.36, so the working sections can stay short. The probability and statistics behind the frequency bands, from return periods and event counts to small data sets and acceptable probability of failure, are grouped in Sections 3.8.30 to 3.8.35. The chapter closes with the field report, the record of the rationale, the limitations and the cross-references (Sections 3.8.42 to 3.8.47).
Chapter 1.1 classifies railway ground hazards by what they are: landslide, hydraulic erosion and subsidence. This chapter explains how they happen. For each family of hazard it describes the physical failure mechanism, the conditions that make a site susceptible, and the triggers that turn susceptibility into an event.
The distinction is practical. Mitigation that addresses only the trigger (for example, a rain-based slow order) manages exposure but leaves the hazard in place. Mitigation that addresses the mechanism (drainage, buttressing, subgrade replacement) reduces the hazard itself. Correctly diagnosing the mechanism is therefore the step that controls whether repair money solves the problem or only treats the symptom. Chapter 1.1 makes this point about "muddy track": identical surface symptoms can come from quite different root causes.
Key outputs: a mechanism–condition–trigger framework (Section 3.8.1); mechanism tables for track substructure, embankments and slopes, hydraulic, subsidence and seismic hazards (Sections 3.8.2–3.8.6); the winter-to-spring frost geohazards of cold regions, with spring break-up hydraulic hazards (Section 3.8.7) and frost heave, thaw weakening and silt liquefaction (Section 3.8.8), contributed by Mario Ruel; a trigger inventory (Section 3.8.11); the use of rainfall thresholds in weather-based operating protocols (Section 3.8.12); a symptom-to-mechanism diagnostic table (Section 3.8.13); and monitoring indicators (Section 3.8.14).
The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.
| ID | Correlation | Gives |
|---|---|---|
| RK-12 | Rockfall Hazard Rating System scoring | RHRS score |
| LS-08 | Rainfall intensity–duration threshold (Caine) | I |
| LS-01 | Reach angle (Fahrböschung) vs. volume — rock avalanches | H/L |
| LS-03 | Debris-flow travel distance | L |
| LS-06 | Debris-flow velocity from superelevation | v |
| LS-09 | Rainfall intensity–duration threshold (global update) | I |
| LS-10 | Newmark sliding displacement (regression) | Dₙ |
| RK-06 | Slope Mass Rating | SMR |
| RK-11 | Rockfall shadow angle | β (shadow) |
Ground failures rarely have a single cause. It is useful to separate three groups of factors:
| Factor | Definition | Railroad Examples | Can the Railroad Change It? |
|---|---|---|---|
| Predisposing conditions | Inherent site characteristics that make failure possible | Soft or sensitive clay, steep slope, fouled ballast over plastic clay, soluble bedrock, loose saturated sand | Only by engineering works (improvement, regrading, replacement) |
| Preparatory (progressive) factors | Processes that reduce the margin of safety over time | Ballast fouling, subgrade softening, toe erosion, weathering, rising tonnage, culvert corrosion, creep | Yes — through maintenance, drainage and inspection |
| Triggers | The event that tips a marginal site into failure | Intense or prolonged rainfall, snowmelt, flood, rapid drawdown, earthquake, toe excavation, blocked culvert | Rarely — but exposure can be managed (slow orders, patrols, warning systems) |
The factor of safety concept from Chapter 1.1 ties these together. Predisposing conditions set the starting factor of safety, preparatory factors erode it, and the trigger is whatever finally pushes it below 1.0. A site with a large margin survives the same storm that fails a marginal site next to it. This is why a risk program targets sites whose margin is being eroded, not just sites that have already failed.
Bissonette separates three things that risk registers often blur. A cause is a fact or existing condition. A risk is an uncertain event that may or may not happen. An effect is the possible impact on one or more project objectives (schedule, cost, scope or quality). To keep them apart he uses a fixed sentence form, or risk metalanguage:
As a result of <CAUSE>, <RISK> may occur, which will lead to <EFFECT>.
The short version for a register title is “<RISK> due to <CAUSE>.” One of his examples reads: “As a result of more than expected test failures, more design/build/test cycles may occur, which will lead to schedule delays and added project costs.” Its register title is “More design/build/test cycles due to more than expected test failures.” Writing every risk this way shows which part can be measured or controlled, whether the cause or the event. It also indicates which objective the impact rating should refer to. The same form keeps a known condition, which is a fact to design for, from being logged as though it were uncertain.
For railroad work: The metalanguage lines up with this chapter’s condition–mechanism–trigger framework. The cause is the condition plus the trigger, the risk is the mechanism being activated, and the effect is the consequence to track or to the project. For example: “As a result of a high-plasticity clay subgrade with a clogged ditch line (condition) and sustained wet-season rainfall (trigger), progressive shear and heave of the subgrade may occur (mechanism), which will lead to repeated surfacing, a slow order and possible mud-pumping derailment risk (effect).” The register title becomes “Subgrade shear failure due to saturated CH subgrade and blocked drainage.” Writing hazard and project risks in this form makes plain which field observation would confirm the cause and which treatment targets the trigger. It also makes the risk register consistent with the diagnostic tables in this chapter.
Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 2.1, “Causes Versus Risks” (unpaginated e-book; PDF pp. 38–40). Summarized and paraphrased. Full reference under Supplemental References.
These mechanisms act within the ballast, subballast and subgrade (Chapter 2.3) and the upper part of the embankment (Chapter 2.1). They account for most of what track patrols encounter day to day: the "subsidence" category of Chapter 1.1.
| Mechanism | What Happens | Susceptible Conditions | Field Indicators | See |
|---|---|---|---|---|
| Ballast degradation and fouling | Particle breakage and abrasion, plus infiltration of fines, fill voids and reduce drainage and strength | Weak or soft aggregate, heavy tonnage, tamping cycles, wind-blown or spilled fines | Fouled shoulders, reduced voids, geometry loss after surfacing | Chapter 2.3, Section 2.3.7 |
| Subgrade attrition and mud pumping | Water plus cyclic loading at the ballast–subgrade contact produces a slurry that is pumped into the ballast | Plastic fine-grained subgrade, no or inadequate subballast, poor drainage | Mud at tie ends and in cribs, "white spots" on shoulders, rapid surface defects | Chapter 2.3, Section 2.3.5 |
| Progressive shear failure | Repeated stress near the subgrade strength remolds the soil and squeezes it laterally beneath the ties | Soft, wet fine-grained subgrade; thin granular layer | Heave of the ballast shoulder or ditch side ("subgrade squeeze"), ties hanging, recurring cross-level defects | Chapter 2.3, Section 2.3.5 |
| Excessive cumulative plastic deformation | Gradual accumulation of permanent strain under millions of load cycles forms ballast pockets and troughs | Fine-grained subgrade with moderate strength; heavy axle loads | Ballast pockets in trench sections; gradual long-wave settlement | Chapter 2.3, Section 2.3.5 |
| Consolidation settlement | Volume decrease of saturated clay and organic soil under sustained load | Soft clay or peat foundations; new fill, raises or a second track | Long-wave settlement, often continuing for years after construction | Chapter 6.2 |
| Frost heave and thaw weakening | Ice lens growth heaves track in winter; excess water on thaw softens the subgrade | Frost-susceptible silts and silty clays, available water, freezing climate | Seasonal differential heave, spring pumping and soft spots | Chapter 2.3, Section 2.3.5; Chapter 7.3 |
| Swell and shrinkage | Moisture change in expansive clay causes volume change | High-plasticity clay, clay shale in cuts, seasonal wetting and drying | Seasonal geometry cycling, shoulder cracking in dry periods | Chapters 2.1, 2.2 |
| Cyclic softening ("subgrade dynamic liquefaction") | Pore pressure buildup under repeated loading in saturated low-plasticity silt causes loss of strength | Saturated silts, poor drainage | Sudden loss of support in wet periods, mud boils | Chapters 1.1, 6.5 |
Profillidis uses a maintenance coefficient k = I / Im, where I is the annual number of maintenance sessions on a section and Im the average for track of the same age, UIC group and axle load. k = 1 is average; k = 0.5 is good; on poor subgrade k can reach 10. Maintenance hours rise steeply with k and with years since renewal (Figure 3.8-1). He uses k to judge whether the track bed is adequately sized:

| k | Assessment |
|---|---|
| k < 1 | Correct dimensioning |
| 1 < k < 2.5 | Track-bed structures slightly under-dimensioned |
| 2.5 < k < 5 | Track-bed structures under-dimensioned; poor functioning of drainage |
| k > 5 | Renewal and strengthening of track-bed structures necessary |
When I passes a threshold, geometry can no longer be held by surfacing alone and the remedy is to reduce k, mainly by thickening the track bed. Applied with Dormon’s rule, subgrade stress also depends on maintenance: traffic between sessions scales with T/k, so tracks with different k values load the subgrade differently. For a ground-hazard program the practical point is that a segment needing repeated spot surfacing (high k) is evidence of a substructure mechanism, and that evidence lives in maintenance records.
After Profillidis (2014), §9.9, Table 9.5, Fig. 9.6. Full reference under Supplemental References.
Short-term versus long-term settlement. On most track, ballast causes most of the settlement between surfacings, both average and differential. This is the short-term component. The subgrade adds a long-term component that builds slowly over decades of traffic. Ballast governs only when three conditions hold:
If any of these is missing, the subgrade dictates the maintenance cycle.
Why track subgrade fails by creep, not by sudden collapse. Train loading on the subgrade does not reverse the direction of shear stress. Under that kind of loading, pore pressure rises to a limit and failure comes as permanent strain accumulating at an increasing rate. Cyclic strain stays small. Two factors make it worse:
After Selig & Waters (1994), chs. 3, 4 and 8. Full reference under Supplemental References.
Classify slope movements by material (rock, debris, earth) and movement type (fall, topple, slide, spread, flow), following Cruden and Varnes (1996) as adopted in Chapter 1.1. The mechanism determines the analysis method (Chapter 6.3) and the likely warning time.
| Mechanism | Typical Railroad Setting | Warning Signs | Warning Time |
|---|---|---|---|
| Rotational slide (slump) | Embankments and cuts in clay; river-bank fills | Crest cracks parallel to track, back-tilted blocks, bulging toe | Days to months; often progressive |
| Translational slide | Fill over sloping bedrock or weak planar layer; colluvium | Tension cracks upslope, displaced ditch, leaning poles | Hours to weeks |
| Earthflow and retrogressive slide | Sensitive and quick clays in river valleys | Often little; small initial slide at the bank | Minutes to hours once started |
| Lateral spread | Sensitive clay or liquefiable layers near free faces | Ground cracking, bulging toward channel | Rapid |
| Debris flow | Steep channels above track; source areas often out of sight | Accumulated debris in upper channel, burn scars, intense rain | Minutes; can reach track 1–2 miles from source (Chapter 1.1) |
| Rockfall and topple | Rock cuts and natural rock faces | Fresh debris in ditch, open joints, freeze-thaw season activity | Seconds |
| Creep | Clay slopes and colluvium | Curved tree trunks, slow drift of track alignment and structures | Years; may accelerate to sliding |
| Shallow sloughing and surface erosion | Steep, unvegetated fill slopes | Rills and gullies, slumped surface layer | Storm-dependent |
| Embankment spreading or foundation squeeze | Embankment on soft foundation | Toe heave, lateral displacement, crest settlement | Weeks to months |

Mass movements are classified by rate against water content, from extremely slow dry creep through earthflows and rotational or translational slides to extremely rapid rockfalls, debris flows and debris avalanches in saturated ground. An earthflow has a characteristic hourglass shape. Creep is spotted by its effects: curved trunks, bent fences and tilted poles.

Embankment collapse by internal erosion (rated Severe) is the hidden mode. Water moves through the fill or overflows through buried rock drains, carrying soil out and leaving voids until the surface collapses. In one case a culvert roof failed about 45 ft inside the fill and produced a sink hole up to 70 ft deep. In another, a 6.5-ft multi-plate culvert with a rusted-out invert let water erode beneath it, causing outlet and toe scour, an over-steepened slope, head-scarp cracks, 14 in. of mainline settlement and 2 in. of lateral deflection.



After Geotechnology for Railroaders Program, Module 5; §05, §09, §14. Full reference under Supplemental References.
Case study: 3.8.45.1 Slope failures whose consequences left the site (Look 2023), in §4.18 Case Studies.
Chapter 1.1 splits hydraulic erosion into surface-flow and seepage mechanisms. They fail differently and call for different controls.





Undersized drainage is a hydraulic mechanism in its own right. Profillidis gives the U.S. Soil Conservation Service method based on Fuller’s formula for the peak flow from a catchment of A mi² for a return period of T years:
His worked values: A = 3.86 mi², T = 10 years gives Q1 ≈ 400 and Qmax ≈ 1,680 ft³/s; A = 5.79 mi², T = 20 years gives ≈ 555 and 2,470 ft³/s. He cautions that such semi-empirical formulas must be checked against measured data. On the TGV Méditerranée, observed extreme runoff was about twice the top of the predicted range ( Chapter 2.1, Section 2.1.5.2 ). He argues that increasing rainfall intensity calls for return periods far longer than the traditional 50–100 years, up to 1,000 years, with the probable maximum flood as the reference event.
After Profillidis (2014), §9.14.2–9.14.3, Eq. 9.11. Full reference under Supplemental References.
Local scour forms horseshoe and wake vortices around piers and abutments; contraction scour deepens the channel through a constricted opening. Both can undermine a foundation well below the water surface. Away from bridges, any bend near the track is scour-critical: the outer radius scours while the inner radius deposits. Banks migrate as the stream undercuts and collapses them. Attack migration before it passes a 2:1 intercept slope with the track, because cost rises steeply with delay, and get engineering help, since riprap alone may not be enough.


Signals stay green when track is undermined by side scour or washed out. Peak flow can arrive after the rain stops, and a long moderate storm can do more damage than a short intense one. Get off the hi-rail and walk the bank at scour-critical locations. AREMA countermeasures (after FHWA) are riprap at piers and abutments, guide banks, spurs and revetments, with riprap always placed from the toe upward.

After Geotechnology for Railroaders Program, Module 6.3; §02–05. Full reference under Supplemental References.
When the water level on one side of an embankment exceeds the other by more than about 6 ft, flow is forced beneath the track. Within days, depending on the fill, wet spots appear at the downhill toe. Dirty or milky seepage and sand fans at the outlet mean soil is being carried out and cavities are forming. In spring, a culvert plugged with ice is the most frequent cause.

Beaver dams in culverts and ditches cause about 80% of beaver trouble but less than 10% of the risk. Dams far uphill, sometimes 100 ft or more above the track and outside railway property, are about 20% of problems but carry the highest risk. The 1992 Nakina derailment, in which two employees were killed, followed a rapid drawdown of a lake after a dam failure and led to the formal Beaver Activity Hazard Assessment (BAHA) program. The program rates watersheds and dams 1–5 and combines them into a global score:


| Watershed | Dam 1 | Dam 2 | Dam 3 | Dam 4 | Dam 5 | +1 severe | +2 severe | +3 severe |
|---|---|---|---|---|---|---|---|---|
| 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | 0 | 0 | 0 | 1 | 2 | 4 | 6 | 8 |
| 3 | 0 | 0 | 2 | 6 | 15 | 30 | 46 | 61 |
| 4 | 0 | 2 | 8 | 26 | 64 | 128 | 192 | 256 |
| 5 | 0 | 5 | 25 | 80 | 195 | 391 | 586 | 781 |
Never use explosives on a beaver dam or culvert plug. In one case a dynamited dam overloaded a 3-ft culvert and more than 300 ft of a 60-ft-high embankment failed, with the water travelling through old permeable fill from a buried timber bridge. After any high water is drawn down, the embankment is least stable for about 12–24 hours, while the confining water is gone but the fill is still saturated and seepage reverses. Beaver ponds are protected fish habitat under the Canadian Fisheries Act; permits are required, and penalties can reach $1,000,000 and imprisonment for individuals.
After Geotechnology for Railroaders Program, Module 6.5, Module 7.1, Module 4; Module 6.5 §02–06; Module 7.1 §04, §06. Full reference under Supplemental References.
Chapter 1.1 separates progressive settlement from sudden collapse. The mechanisms below produce sudden collapse. They are the most dangerous for train operations because warning time is short.
| Mechanism | Process | Where to Expect It |
|---|---|---|
| Karst sinkholes | Soil ravels into solution cavities in limestone, dolomite or gypsum until the overlying arch collapses (cover-collapse) or sags (cover-subsidence) | Karst regions; often triggered by water-table changes or concentrated drainage |
| Mine subsidence | Collapse of underground workings producing troughs (sag) or pits | Abandoned coal and mineral mining districts |
| Hydrocollapse | Low-density, dry soils lose their bonding and compress when first wetted | Loess and some arid-region alluvium; triggered by new drainage or leaks |
| Culvert and pipe failure | Backfill lost through corroded or separated barrels leaves voids that collapse | Aging metal culverts; clay tile and masonry drains |
| Decay of buried timber | Rotting of buried trestles and cribbing leaves voids in the fill | Fills built over or around former timber structures |
| Leaking utilities | Water and sewer leaks wash fines into the pipe or away along the trench | Utility crossings (Chapter 2.1, Section 2.1.9) |
| Burrowing animals | Burrows provide seepage paths and voids in embankments | Embankments near water; flood-control levee analogs |
Earthquakes act as triggers for several of the mechanisms above, and they also introduce mechanisms of their own: liquefaction of loose saturated granular soils, lateral spreading toward free faces, cyclic softening of soft clays, and seismically induced slope failures and rockfall. Evaluate these using Chapter 6.5. After a felt earthquake, the railroad's earthquake notification protocol (Chapter 1.1, Section 1.1.8) sets the inspection radius and speed restrictions.
Profillidis treats earthquakes in two parts: designing structures, track and subgrade for the regional design acceleration (up to about 0.3 g in his text), and protecting trains during an event. For the second, accelerometer sensors in protected housings along the line report to an alarm center:
These values describe one European system and can be compared with client post-earthquake inspection protocols (Chapter 6.5).
After Profillidis (2014), §9.17. Full reference under Supplemental References.
More than 1,500 seismic events are recorded in Canada each year, with a significant one every two to five years. Energy travels farther through dense eastern Precambrian rock. The 1935 Temiskaming M6.2 earthquake caused an embankment failure more than 220 mi from the epicenter. The 1988 Saguenay M5.9 event temporarily liquefied a muskeg zone and triggered nine slope failures; derailments were avoided only because the track was closed. In a 2010 event, straight rail was left kinked into S-curves, buckled at ties and disturbed at culverts, damage not visible from a moving train. Post-event inspection must cover track and roadbed, drainage, culverts, retaining walls, tunnels, overpasses, bridges and approaches, adjacent buildings, fiber and utilities, and signals. Response criteria are in Chapter 6.5.



After Geotechnology for Railroaders Program, Module 7.3; §02, §05–06. Full reference under Supplemental References.
Sections 3.8.7 and 3.8.8 are adapted from Ruel (2026b), Railway Frost Geohazards: Winter to Spring Break-Up, Frost Heave and Soft Subgrade, Chapter 2.8 of the Railway Ground Hazard Research Program (RGHRP) Canadian Railway Geohazard Manual (forthcoming). The figures are from that chapter, with the credits shown on each. Units are given in English, with the original metric values in brackets. All references are listed under References.
In cold regions, the winter-to-spring transition is the most hazardous period of the year for track stability. Seasonal frost hazards fall into the hydraulic and subsidence categories of Chapter 1.1 (Keegan 2007; Keegan n.d.). This section covers the hydraulic group, where meltwater moves around and through the embankment. Section 3.8.8 covers the frost group, where water freezes and thaws inside the track foundation. Both groups have the same root cause, water that cannot drain, and the same first remedy, drainage.
Spring break-up concentrates a large share of the year’s track-bed damage, slope failures and weather-related incidents into a few weeks, because four unfavorable conditions arrive together:
Canadian railways manage this period with a spring readiness (or spring preparedness) plan, traditionally running from about March 1 to May 15 depending on the region (Ruel 2026a). As climate patterns shift, these activities increasingly need to start earlier. The period usually coincides with the spring load-restriction periods that provincial and northern state transportation agencies impose on highways.
The plan follows the same risk-management cycle used for all ground hazards year-round (CSA 1997; CSA 2022; ISO 2018), repeated through the transition season (Figure 3.8.7-1):

Field experience reduces spring threats to ten recurring conditions. Table 3.8.7-1 lists them with what to look for, and the job aid in Figure 3.8.7-2 (Section 3.8.7.8) puts them on one page for crews.

| # | Spring hazard | What to look for |
|---|---|---|
| 1 | Flooding | Rising water level near the right-of-way. |
| 2 | Differential water head | A large difference in water level from one side of the track to the other, for example 3 to 7 ft. Check for seepage near the toe of the downstream slope and water flowing through the fill, which may be causing internal erosion. |
| 3 | Rapid drawdown | An abrupt drop in water level next to the roadbed, which can trigger slope failure. Look for fresh high-water marks. |
| 4 | Ponding from blocked drainage | Flow held back by snow, ice, beaver dams, debris or poor ditches. Check for water entering the fill at the inlet and seeping or flowing out of the fill at the outlet. |
| 5 | Frozen culverts | Ice plugs, especially at outlets. Check in winter and early spring, before snowmelt and heavy rain. |
| 6 | Blocked culverts and ditches on adjacent roads | Blocked drainage on road infrastructure uphill or downstream can cause flooding, washouts and rapid drawdown at the railway embankment. |
| 7 | Water flowing through the ballast | Water over and through the ballast and subgrade can erode and undermine track support. |
| 8 | Hydraulic erosion from watercourses | Erosion along rivers, fast creeks and ditches, and at culvert inlets and outlets. |
| 9 | Ice and debris jams at bridges | Ice and debris piled against piers can push piers and spans and cause flooding upstream. |
| 10 | Signs of slope instability | Tension cracks along the shoulder or slope; small sinkholes below the ties; very soft track and new cross-level defects; a bulging toe; leaning trees; seepage on the lower slope; fans of sand or silt at seepage points. |

Blocked culverts are the root problem. Nearly every spring hydraulic hazard starts with water that cannot drain along, away from or through the embankment. An inlet can look clear while an ice plug has formed at the outlet. During snowmelt and heavy rain, that plug holds back a large volume of water and a rising level on the upstream side. The most valuable preventive action is to inspect and clear the critical culverts before the melt: those with a history of icing or flooding and those on sidehills. Most of this cannot be judged from the track. Get off the hi-rail, walk the shoulder, and look down the bank at the inlet and outlet for blockage, ponding at the inlet, and water seeping through the embankment instead of through the culvert.
Differential water head. With the culvert blocked, water rises on the upstream side while the downstream side stays low. The difference in level is a driving force, not a nuisance: a difference of about 7 ft can be enough to cause instability, and the larger the difference, the greater the pressure pushing water through and under the fill. If the water reaches the crest it overtops the track and can wash it out suddenly (gully erosion), but conditions can be dangerous well before that (Figure 3.8.7-4).

Seepage through the embankment. Under a differential head, water seeps through the fill from the high side to the low side. It raises the pore pressure in the fill and reduces its effective strength. Seepage emerging on the downstream slope or at the toe is a critical warning sign. If the water carries soil particles, internal erosion is under way and voids are forming beneath the roadbed (Figure 3.8.7-5; Section 3.8.4.2).

Field personnel must be able to read the embankment for signs that high water and seepage are undermining it. Many of these signs cannot be seen from a hi-rail vehicle, so walk the ground, carefully, on both sides.
| Stage | Signs | Response |
|---|---|---|
| Early | Small tension cracks along the shoulder or slope crest; small sinkholes in the ballast or shoulder; new seepage zones; new cross-level defects at the track surface. | Report; drain the pond by clearing the culvert, or pump; mark the cracks and start monitoring. |
| Developing | A bulging toe, or cracks anywhere on the slope. | Treat as a slope failure in progress; protect traffic and drain urgently. |
| Imminent failure | Wider and deeper tension cracks; larger sinkholes under the ballast; fans of sand at seepage outlets; a larger toe bulge pushing over and tilting trees. | Stop trains until the site is inspected and made safe. Several signs together mean the fill is approaching failure. |

A high differential head should not be tolerated along the track. Where any sign in Table 3.8.7-2 is present, draining the pond, by clearing the culvert or pumping, is urgent.
Photographs and monitoring. Take photographs wide enough to show the track and the surrounding ground for scale (Figure 3.8.7-7). Judging a crack’s width by eye is not enough and can mislead; measure it from paint marks across the crack or from lines of survey lath, so that acceleration can be seen.

Safety. Inspect the side slopes from a stable location beyond the limits of the unstable zone, walking down near the base of the fill from more stable ground. Never inspect directly on an actively sliding slope or at its toe.
Rapid drawdown (RDD) is one of the least intuitive and most dangerous spring conditions. Once the water is drained, the embankment looks safer. Conditions do improve on the downstream side, but they get much worse on the upstream side.
RDD occurs when an external water body that was buttressing the slope (a flooded ditch, a backed-up culvert or a beaver pond) drains faster than the saturated fill can. The water’s support is removed while high pore pressures stay trapped in the fill. Effective strength drops, seepage forces push the slope downhill, and the factor of safety can fall below 1.0 (Figure 3.8.7-8). The slide can come 24 to 48 hours after the water has visibly receded, with the track still looking undisturbed.

Common triggers are the sudden clearing of an ice plug at a culvert outlet, the breach of a beaver dam at an inlet, and a fast drop in an adjacent creek. Because the slope may show no distress at the moment of peak risk, keep any embankment that was partly or fully submerged under active observation for at least 24 to 48 hours after the water level drops.
Case history: Nakina, Ontario, 1992. A small lake on the downhill side of the track had been there since before the railway was built. During a heavy rainstorm in July 1992, a very old beaver dam that could not be seen from the track ruptured and the lake dropped by more than 7 ft. The embankment failed by rapid drawdown and an approaching train derailed (TSB 1992; Figure 3.8.7-9). It was the first derailment attributed to RDD, and the lessons were shared across railways and transportation agencies to raise awareness of drawdown and of beaver dams along corridors.

A differential head moves fine soil out of the embankment by internal erosion (piping). It is most common along the outside of a blocked, damaged or corroded culvert, through a defect in the fill, or through an old overflowing “blind” stone drain. Over time it hollows out large cavities while the surface looks intact.



| Hazard | Mechanism | Control |
|---|---|---|
| Snow and ice in culverts and ditches (Figures 3.8.7-17 and 3.8.7-13) | Snow and ice reduce drainage capacity during high spring flows. | Clear snow and ice from the most sensitive ditches and culvert openings, starting with locations that have flooded before. Keep a drainage hazard registry so the culverts likely to ice up and the ditches to clear are known in advance. |
| River hydraulic erosion (Figure 3.8.7-18) | Spring brings the highest and fastest flows of the year, especially along meanders. | Walk the bank and beneath bridges; erosion is not visible from the hi-rail. Use helicopter or drone photographs every spring in high-hazard areas. |
| River ice break-up (débâcle; Figures 3.8.7-19 and 3.8.7-14) | Break-up is sudden and short at each reach. Moving ice can lift bridge spans, damage the roadbed, dislodge large riprap and push piers founded on rock; ice has piled up to 33 ft behind piers and displaced piers 3 to 7 ft. | Know when and where break-up will occur, and protect traffic while the ice is running, if necessary by stopping operations until it has passed. |
| Debris against bridges (Figure 3.8.7-20) | Trees and debris, sometimes mixed with ice or released by a beaver dam outburst, jam against piers, restrict flow, and cause upstream flooding, bed scour and bank erosion. | Watch the river when crossing bridges; report obstructions to the bridge engineer at once, as conditions can worsen quickly. |
| Ice fall and rockfall (Figures 3.8.7-21 and 3.8.7-15) | Thick ice walls on high rock cuts can drop large sheets onto the track during the melt. More frequent freeze-thaw cycles increase spring rockfall. | Inspect ice walls for early signs of release; report new rockfall or ice fall (Section 3.8.3). |
| Ice in tunnels (Figures 3.8.7-22 and 3.8.7-16) | Water leaking into tunnels forms crown stalactites that intrude on vertical clearance; ice on the walls that narrows horizontal clearance; and ice that builds up over the rail from side-wall or invert seepage, which can let wheels climb the rail. In spring, with repeated freeze-thaw, ice can cover the rail head in a single day. Falling ice injures workers. | Keep tunnels with icing on the hazard registry with a spring action plan to keep ice off the rail. Remove icicles with mechanical equipment, not hand tools (Bunce, forthcoming). |










Weather monitoring. On warm spring days snow melts quickly, very quickly when rain falls on it, and the frozen ground sends almost all of it to runoff. During the thaw, check forecasts and official advisories every day for flash flood warnings, heavy rain warnings, snowmelt runoff forecasts and combined rain-plus-snowmelt forecasts. In spring, the water expected from snowmelt must be added to the rain forecast; a map that combines the two is the most useful single product for rail operations (Figure 3.8.7-23). This extends the rainfall protocols of Section 3.8.12 to the thaw season.

Table 3.8.7-4 gives a four-level alert system as an example for eastern Canada. Thresholds differ by region and should be set from local experience. Where the combined water exceeds the Red level, consult the weather service provider and a local hydrologist to define how far and how long the operating controls should extend.
| Alert level | Combined snowmelt + rainfall | Required action |
|---|---|---|
| Yellow | 1 to 2 in. | No mandatory action; extra patrols at the track supervisor’s discretion. |
| Orange | 2 to 3 in. | Extra patrols in areas of known concern for flooding, washouts and slope instability. |
| Red | 3 to 4 in. | Mandatory special patrols of all high-hazard locations before train movements; consider slow orders and 24-hour watch. |
| Black | More than 4 in. | Stop trains at high-risk locations until inspected and cleared. |
For a site monitored with the live risk rating of Section 3.8.26.3, add the forecast snowmelt to the 24-hour rainfall during the thaw, and set the thaw indicator of Table 3.8-31 from the alert level: combined water at the Orange level counts as Watch, and at the Red or Black level as Warning. Rain falling on melting snow is Warning at any amount, and so is any thaw at a site that has failed in a thaw before.
Risk-based decisions. When a roadbed hazard is found, field personnel must assess it quickly and decide how to control the risk. Risk is the product of likelihood and consequence: a condition unlikely to fail with minor consequences is low risk, and a condition likely to fail at a vulnerable, high-consequence location is high risk (Figure 3.8.7-24; Chapter 1.1; CSA 2022; Macciotta, forthcoming). A rapid spring assessment considers:

In the terms of this chapter, the field observations are the field indicator elements D5 to D14 (Tables 3.8-46 and 3.8-47), the weather is the live condition of Section 3.8.26, and the consequence is the hazard severity S (Table 3.8-15). Read the rating from the risk matrix (Table 3.8-16) and apply the required response of Table 3.8-17: at High, a slow order or increased inspection; at Severe, on-site protection and operating restrictions before the next train.
Where there is no imminent danger, assess and protect track geometry to standards and add controls as warranted: a watchman, extra patrols or electronic warning devices. Where failure is imminent, or where field personnel are unsure whether a train can pass safely, suspend operations and notify the rail traffic controller and the engineering supervisor immediately. When in doubt about stability, stop the train.
Spring inspection essentials. A focused spring inspection looks specifically for unusually high water near the track, differential head, seepage below the track, signs of slope instability, drawdown potential, and culverts or ditches plugged with snow and ice. Where slope movement is suspected, mark tension cracks with stakes or paint and monitor them for widening. The guiding sequence is see the water, respect the warning signs, and act early: restore drainage before the head builds, and impose a speed restriction before a crack widens. Proactive work is cheaper and safer than responding to a failure. The job aid in Figure 3.8.7-2 supports these inspections.
This section moves from water flowing around and through the embankment to water freezing inside it. Frost hazards belong to the subsidence category of Chapter 1.1 (Keegan 2007). Unlike slope and hydraulic hazards, they start within the soil mass, driven by temperature gradients and the freezing and thawing of pore water. Frost heave and thaw softening from freeze-thaw cycles degrade track geometry, change the vertical force at the wheel-rail interface, and can affect operating safety (Roghani 2021; Roghani, Caldwell et al. 2021; Roghani, Liu and Burgess 2021). In early spring they bring frequent tamping and surfacing and temporary slow orders.
These hazards are deceptive. They develop slowly over weeks, out of sight, and then appear as differential track lift, soft track, cross-level defects or shoulder failures. Because the mechanisms are not intuitive, the warning signs are easy to misread and remedies often treat the symptom rather than the cause. Source material: Ruel (2026b), Part II; see also Selig and Waters (1994), Li et al. (2016) and Ruel (2024).
Differential frost heave is the uneven upward movement of the ground surface caused by ice lenses forming and growing in freezing soil. Water expands about 9% when it freezes; where that expansion is uniform along the track it does little harm. Heave becomes a problem when the ground does not freeze uniformly.
Damaging heave needs three conditions at once (Figure 3.8.8-1):

Remove any one and damaging lenses are unlikely to form. Every remedy in Section 3.8.8.6 works by removing one of the three.
Ice lenses. As the freezing front moves down, freezing creates suction that draws water up from the unfrozen soil and the water table. The water freezes at the front as discrete lenses that grow and push the soil apart, heaving the surface. As the front goes deeper, successive lenses form and the heave accumulates (Figure 3.8.8-2).

Why silt. Frost susceptibility depends on the balance between capillarity and permeability. Silt pores are small enough to produce strong capillary suction yet large enough to move water quickly to the freezing front; water can rise 3 to 7 ft above the water table in silt by capillarity alone. Clean sand has pores too large to sustain much capillary rise. Clay has strong capillarity but is too impermeable to feed lenses fast enough.
Subgrade conditions change quickly along a line, and silt and water are rarely uniform, so heave is not uniform either. Severe heave concentrates in short spots, often only 13 to 33 ft long, where enough silt and water coincide. The track is lifted more in some places than others, producing a rough surface and abrupt changes in elevation at the transitions (Figures 3.8.8-3 and 3.8.8-6).


The thaw is the most dangerous period of the year for track-bed bearing capacity and surface defects (Figure 3.8.8-5):

Highway agencies apply the same principle through spring load-restriction periods. The hazard depends on where the thaw front is relative to the remaining frost, so monitoring both is valuable. The worst heave occurs at maximum frost depth, around the start of surface melt; the worst bearing capacity occurs after moderate thaw, when a soft saturated layer sits on a still-frozen base. Conditions return to normal only when the thaw front reaches the bottom of the frost and the trapped water can drain. Because the loss is predictable and seasonal, it can be managed administratively by reducing axle loads or speeds over vulnerable sections until the subgrade recovers.

Silt liquefaction is the most severe form of the spring loss of bearing capacity. The top of a soft, wet silt layer thaws over hard, still-frozen ground. Heavy, vibrating trains cycle load onto the saturated silt while the frozen base prevents drainage. Pore pressure builds with each load cycle until the silt loses its strength and liquefies. The silt-water mixture is squeezed up and out at the embankment shoulder, leaving voids beneath the track (Figure 3.8.8-7).

Signs.


Silt liquefaction causes differential settlement, a weakened subgrade and shoulder, and hidden voids, and it is a recognized cause of spring derailments. It resolves on its own once the frost is fully out and the trapped water drains, so the danger is confined to the thaw window, but within that window it is acute.
Frost depth controls it. Liquefaction occurs when the thaw front reaches the top of the silt while the silt below is still frozen, which is possible only when frost has penetrated deep into the silt (Figure 3.8.8-10). If the silt did not freeze deeply, it drains and keeps its strength. Evaluate frost depth at locations with a history of silt boils: after a mild winter the risk is low; after a cold winter, inspectors must watch closely for early signs in the spring.


Because frost heave needs silt, water and freezing, every remedy removes one of them. Table 3.8.8-1 lists the measures in broad order of value, starting with drainage.
| Priority | Measure | Condition removed | Key points |
|---|---|---|---|
| 1 | Drainage and subdrainage | Water | The first line of defense and the most cost-effective. Poorly maintained ditches cause roughly three-quarters of frost heave problems, and poor ballast or subballast drainage most of the rest. Clear ditches and daylight the ballast at the shoulder; where water is trapped below the surface, install subdrains (Figure 3.8.8-12). |
| 2 | Marking and salting | Freezing | The most practical treatment for recurring heave spots; reduces differential heave by about 70% for two to three years. |
| 3 | Shimming | None (compensates) | The most common spring response; smooths the surface without disturbing frozen ballast. |
| 4 | Excavate and replace silty soil | Soil | Replace only 50 to 60% of the frost depth, with flat transitions. |
| 5 | Insulation | Freezing | Attenuates heave to match the adjacent track; tapered ends are essential. |
| 6 | Injection or soil treatment | Soil | Cement or chemical mixing, or cement or urethane injection from the surface. |

To stabilize a silt-liquefaction zone, relieve the water pressure at the silt-frost interface while containing the silt. The proven technique is a lateral trench drain that also acts as a reinforcing shear key (Figure 3.8.8-13):


In an emergency, even clean crushed rock without geotextile improves conditions by draining water faster, although silt will slowly migrate into the voids.
Salt lowers the freezing point of the soil moisture, slowing the freezing front and limiting ice lenses (Figure 3.8.8-14).

Shimming compensates for heave rather than curing it. A heave bump produces an abrupt surface change that trains cannot cross safely at normal speed, and severe temporary slow orders, down to 10 mph (16 km/h), may be needed until the surface improves. Tamping is not practical in winter because the ballast is frozen. Shims of different thicknesses placed between rail and tie smooth the transition and gradually raise the track over the heave (Figure 3.8.8-15), following the railway’s track standards. All shims must be removed once the frost bumps go down. Installing them in spring and removing them in summer is slow and labor-intensive, but it remains the most common way of dealing with heave bumps.

Where drainage has been tried and shimming has become too labor-intensive at a chronic location, more disruptive and costly measures may be justified. Replacing the frost-susceptible silt with dry, non-frost-susceptible granular fill fixes the local bump, but the ground on either side keeps heaving slightly, so the repaired zone can become a winter dip that is as hazardous as the bump it replaced. This was common where a culvert was replaced and new granular fill placed over it.

Where the soil or the water cannot be removed, the freezing can be. Rigid extruded polystyrene insulation (Type IV or HI) on a firm granular base beneath the subballast can greatly reduce heave (Figure 3.8.8-17). The aim is to attenuate heave so the insulated zone behaves like the adjacent uninsulated track, not to stop all frost penetration. Tapered transitions at both ends are essential; without them, abrupt differential heave develops exactly where the insulation ends. A designer experienced with thermal insulation should be involved.

Mixing the existing soil with cement or other chemicals, either by excavation and in-place mixing or by injecting cement or urethane through drill holes from the surface, has also been successful (Figure 3.8.8-18; Chapter 7.2).

Repeated axle loads are a trigger in their own right. Each passing axle adds a small permanent strain in the ballast and in any soft fine-grained subgrade, and the sum shows up as loss of track surface and, in the subgrade, as ballast pockets and progressive shear failure. A UK research study of traffic effects on embankments found that the factors that matter most are axle load, the plasticity of the clay fill, and the thickness of ballast and ash cover over it. This section gives the power-law models used to predict the settlement and a diagnostic chart for drainage-related subgrade failure.
Equation 3.8-1. Ballast and subgrade cumulative strain
Subgrade: εp = a(σd/σs)mNb (parameters a, b and m from the soil-type table in Chapter 2.1), N = MGT × 106 × 2,000/(4P); settlement = strain × layer thickness.
Both laws flatten with time. New ballast and newly compacted subgrade settle quickly at first. In an established track the ballast settles after each tamping as it recompacts (only the disturbed upper 6 in. or so), while the subgrade, after many years of traffic, settles at an almost constant small rate. A soft subgrade therefore dominates the settlement of new construction, and the ballast dominates once the line is established.
| High-plasticity clay fill | Vulnerability to traffic loading |
|---|---|
| Less than 10% | Low |
| 10 to 40% | Moderate |
| 40 to 90% | High |
| 90% or more | Very high |
The screen uses fill plasticity only. Axle load, ballast thickness, track geometry, drainage, fill strength and hard spots (culverts, walls) must also be reviewed.
| Failure | Mechanism | Field signs |
|---|---|---|
| Progressive shear failure | Subgrade surface remolded by repeated overstress; soil squeezes outward and upward | Heave at the ballast shoulder, depression under the track, water trapped beneath |
| Excessive plastic deformation | Compaction and shear of a soft layer of substantial depth | Ballast pocket; little shoulder heave |
| Attrition with mud pumping | Ballast grinds the wet subgrade surface into slurry | Wet spots, fines on the ballast surface, rapid loss of geometry |
| Other modes | Liquefaction of saturated silt and fine sand; slope failure; consolidation; frost heave and thaw softening; swell-shrink; slope erosion; collapse on wetting | See Chapters 2.4 to 2.6, 6.2, 6.3 and 6.5 |
The fault chart splits causes into the train loading regime and the environment (rain, flooding, poor or poorly maintained drainage) and links them to subgrade failure, drainage deterioration and embankment or cut slope failure.
| Case | First-year settlement |
|---|---|
| New ballast, 12 in. recompacting | 0.57 in. |
| Established ballast after tamping, 6 in. disturbed | 0.29 in. |
| New subgrade | 0.78 in. |
| Subgrade after 20 years of the same traffic | 0.012 in. |
The ballast and new-subgrade values match the textbook example (0.57, 0.29 and 0.78 in.).
New construction on this soft clay would lose more surface from the subgrade than from the ballast in its first year. Twenty years on, the subgrade contribution is a few hundredths of an inch per year and surfacing cycles are governed by the ballast. If such a site keeps needing surfacing, the cause is more likely the ballast and drainage than continued subgrade consolidation (Chapter 6.4).
Open the traffic settlement calculator →
Ballast and subgrade settlement by year for a given tonnage and wheel load, for new or established track, with the fill-plasticity vulnerability screen.
Paraphrased from these documents in the reference library.
Most railroad embankments and cuts were built long before the slopes were designed. Before the 1930s nearly all fills were end-dumped without systematic compaction, at slopes set by experience, and they settled heavily soon after construction. They now carry heavier and more frequent traffic at lower factors of safety than a new earthwork would be given. UK rail and highway owners, who manage the oldest large earthwork network, group the ways these earthworks fail into the mechanisms in Table 3.8-7. Each has its own trigger and season, so the mechanism decides what to inspect, when, and which analysis applies.
| Mechanism | Typical depth | Trigger and season | What the track inspector sees | Analysis in this manual |
|---|---|---|---|---|
| Shallow translational or circular slip | 3 to 5 ft; survey range 0.7 to 8 ft | Heavy rain after a dry season; drainage that is blocked or absent | Bulging or slumped slope, debris at toe; track usually unaffected | Ch 6.3; Ch 6.4.11 |
| Deep-seated first-time or delayed failure | Deeper than 3 to 7 ft; may pass through the foundation | Slow rise of pore pressure in stiff, high-plasticity clay over years to decades; progressive loss of strength | Crest cracking, track drop and line, toe heave | Ch 6.3.6; Ch 2.5 |
| Slide on an old shear surface | Along the pre-existing surface | Wet season; repairs that left the old surface in place | Recurring movement at a known slip | Ch 6.3.6 (residual strength) |
| Seasonal shrink–swell with ratcheting | Upper 3 to 13 ft of clay fill | Dry summers under high-water-demand trees, then winter wetting; outward movement does not fully recover | Summer settlement and winter heave of track; slow net outward creep | Ch 2.5; Ch 3.8 |
| Shoulder instability | Crest and shoulder | Steep upper slope, train vibration, fine ash or ballast that dries and runs | Narrowing shoulder, ballast loss, tie ends unsupported | Section III (Ch 2.1) |
| Flooding and toe scour | Toe and lower slope | High stream or river levels beside or through the embankment | Toe loss, sudden deep slip after the flood | Ch 2.8; Ch 6.3 |
| Flow failure in cuttings | Shallow, rapid | Short, intense rain on permeable soil with run-off concentrated at the crest | Debris flow onto the track at the toe of a cut | Ch 6.4.11; LS-series equations |
| Frost shattering of rock cuts | Face of the cut | Freeze–thaw in porous or jointed rock (chalk is especially prone) | Debris at the toe; loosened trees falling | Ch 2.7 |
After McGinnity and Saffari (2012), ICE Manual Vol. II, Section 71.2.1, pp. 1069–1073; shallow failure depths from the UK highway survey reported by Nowak (2012), Section 70.1.4, p. 1050. Depths converted from metres.
What the UK network data show. A study of train delays from geotechnical causes on the UK network in 2000–2003 put their cost at about £26 million, concentrated where high-plasticity clays occur. About 80% of the delay time came from about 20% of the incidents. In high-plasticity clay, delays in dry summers were of the same order as those in wet winters. Of 95 ultimate failures recorded later, about half were deep-seated through the crest; the rest were local crest failures, unravelling of oversteepened ash and ballast at the shoulder (mostly in summer), and shallow translational slides. Delayed deep failures were usually on slopes with grass or small shrubs; excessive track movement was usually where large trees grew on the slope (O'Brien, 2013, p. 20).
Progressive failure. In brittle, overconsolidated clay the strength along a developing slip surface drops unevenly from peak toward residual. Skempton's back-analysis of long-term failures in five cuttings in weathered London Clay gave an operating friction angle of about 20° with an average pore pressure ratio ru of 0.25 to 0.35, against laboratory peak values of φ′ = 20°, c′ = 145 psf and residual φ′r = 13°, c′r = 20 psf (McGinnity and Saffari, 2012, p. 1070). The operating strength lies between peak and residual, which is why a peak-strength analysis of an old clay slope overstates its safety.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Most failures are set off by water. Load and human activity come next.

| Trigger | How It Acts | Mechanisms Most Affected |
|---|---|---|
| Intense short-duration rainfall | Surface runoff, erosion, rapid rise of perched water | Debris flow, shallow slides, washout, scour |
| Prolonged rainfall and antecedent moisture | Raises groundwater and pore pressure over days to weeks | Deep-seated slides, subgrade softening, pumping |
| Snowmelt and rain-on-snow | Large water input on saturated or frozen ground | Slides, washouts, thaw weakening |
| Freeze-thaw cycles | Ice wedging in rock; ice lens growth and melt in soil | Rockfall, frost heave, spring pumping |
| Flood and high water | Scour, overtopping, saturation of embankments | Scour, washout, piping |
| Rapid drawdown | Loss of external water support on a saturated slope | Slides of river-bank embankments |
| Blocked drainage | Ponding against embankments; water forced through fill | Piping, slides, subgrade softening |
| Increased load | Heavier axle loads, higher tonnage or speed, new track, stockpiles near crest | Progressive shear, cumulative deformation, slides |
| Construction and maintenance | Toe excavation, ditch cleaning that undercuts slopes, undercutting, vegetation removal, grade raises | Slides, erosion, settlement |
| Earthquake | Cyclic loading and inertial forces | Liquefaction, lateral spread, slides, rockfall |
| Wildfire | Loss of vegetation and water-repellent soils increase runoff for several seasons | Debris flow, erosion |
| Beaver activity | Impounds water against fills; dams fail in storms | Washout, piping |
| Utility leaks and mining | Localized water or loss of support | Sinkholes, collapse, settlement |



Climate trends matter for risk evaluation. Where records show more frequent intense rainfall, return-period assumptions behind existing drainage and past stability evaluations may no longer hold. Note this in the risk evaluation (Chapter 1.1, Section 1.1.7) rather than assuming past performance will continue.
A trigger is an external stimulus that causes a near-immediate landslide or washout by raising stress, reducing strength or removing soil: intense or persistent rain, floods, high stream flow, rapid snowmelt, earthquakes, elevated seepage, water-level change, freeze–thaw and rapid drawdown. Weather is the most common trigger, and antecedent wetness matters as much as the storm. Underlying causes are geological (weak, sensitive, weathered or jointed materials, adverse bedding, permeability contrasts), morphological (toe erosion, piping, crest loading, vegetation loss, thaw) and human (toe excavation, crest loading, reservoir drawdown, deforestation, irrigation, vibration, leaking utilities).
Water weakens slopes in five ways: it adds weight in the voids, is absorbed by clay minerals with loss of strength, dissolves cement between grains, erodes loose material, and becomes trapped under pressure. A failure surface balances driving and resisting mass, and four actions tip it the wrong way: steepening the slope, removing support at the toe, adding mass high on the slope, and allowing bad drainage to continue.
After Geotechnology for Railroaders Program, Module 5, Module 6.4; Module 5 §10, §14; Module 6.4 §07. Full reference under Supplemental References.
Because rainfall is the dominant trigger, many railroads tie patrols, speed restrictions and special inspections to precipitation. FRA 49 CFR 213.239 requires special inspections of track after events such as floods and severe storms that may have damaged track structure. A threshold-based protocol makes that requirement predictable.
Empirical rainfall thresholds relate the average intensity I needed to trigger shallow landslides and debris flows to the storm duration D. The widely cited global lower-bound threshold of Caine (1980) is:

Equation 3.8-18: I = 0.58 × D−0.39
where I = rainfall intensity (in./hr) and D = duration (hr), valid for roughly 10 minutes to 10 days.
A global threshold is only a starting point. Thresholds should be calibrated for each territory from the railroad's own incident history and rain-gauge records. They should also account for antecedent moisture, since the same storm is far more damaging on saturated ground.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
In the course’s Class I practice, the Regional Chief Engineer declares an extreme weather event for a defined subdivision and mile range. The declaration draws on weather-service forecasts and warnings and on reports from train crews and engineering forces, and is passed to Rail Traffic Control, the General Manager and the Regional Senior VP. Restrictions are decided jointly. They weigh the nature of the event, pre-existing ground conditions, topography and incident history, the quality of the weather information, the recency of patrols (a daylight inspection within four hours counts for more than a night inspection twelve hours old), train frequency, and wayside protection such as slide fences and high-water detectors.

The flash-flood trigger used across the Prairies and East is more than 1 in./h totaling over 3 in.; elsewhere, 2 in. in 1 h, 3 in. in 2 h, 4 in. in 4 h or 6 in. in 12 h. A double precipitation index plots short-term intensity against cumulative rainfall to define low-risk, speed-restriction and suspension zones. An antecedent rainfall index plots 2-day against 28-day totals over the history of past landslides at a station. In spring, bearing capacity can drop 30–50%.

After Geotechnology for Railroaders Program, Module 7.2, Module 7.1, Module 4; Module 7.2 §03–06; Module 7.1 §07. Full reference under Supplemental References.
Use this table to move from what the field inspector sees to the most likely mechanisms, and to the investigation that will confirm which one applies.
| Observed Symptom | Likely Mechanisms | Confirming Investigation |
|---|---|---|
| Recurring surface or cross-level defect at one location | Ballast pocket, progressive shear, soft foundation, culvert backfill loss | Trench across track, borings, GPR, geometry-car history |
| Mud at tie ends, fouled shoulders | Mud pumping, ballast fouling | Ballast sampling and fouling index, subgrade plasticity, drainage check |
| Heaved ballast shoulder or ditch side | Progressive shear failure (subgrade squeeze) | Trench, field vane or CPT, moisture content |
| Longitudinal cracks in crest, parallel to track | Rotational or translational slide; embankment spreading | Inclinometers, piezometers, stability analysis |
| Bulging toe, seepage or boils at toe | Slide in progress; internal erosion | Piezometers, seepage mapping, borings at toe |
| Circular depression or hole near track | Sinkhole, pipe or culvert failure, buried timber decay | Probing, geophysics, camera inspection of nearby culverts and utilities |
| Seasonal heave and spring soft spots | Frost heave and thaw weakening | Frost susceptibility testing, groundwater levels |
| Fresh rock in ditch or on track | Rockfall and topple | Rock slope mapping, rockfall hazard rating (Chapter 1.1) |
| Scour hole or exposed footing at bridge | Local or contraction scour | Underwater inspection, scour evaluation per HEC-18 |
The book defines geometry defects against a theoretical track position averaged over a chord: longitudinal defect (surface or profile), transverse defect (cross-level relative to design cant), horizontal defect (alignment), gauge, and twist (deviation of one of four points on two ties from the plane of the other three, i.e. the change in cross-level per unit length).


Geometric parameters degrade about 5–15 times faster than mechanical ones (rail, ties, fastenings). On a typical UIC group 4 line, geometry is restored after about 40–50 million tons, while rail lasts 500–600 million tons.
After Profillidis (2014), §16.2–16.4, Figs. 16.3–16.4. Full reference under Supplemental References.
Mud on the ballast surface can come from three sources, and each needs a different fix:
Before committing to cleaning or renewal, examine the layers down into the subgrade with trenches, pits or trackbed borings (Chapter 3.9).
| Cause | Short-term response | Long-term remedy |
|---|---|---|
| Ballast and tie wear or attrition | Add ballast depth; tamp | Renew with more durable ballast |
| Fouled ballast (breakdown or spillage) | Tamp; this delays cleaning only briefly | Clean by undercutting or shoulder cleaning |
| Subgrade attrition and pumping, no subballast | Clean ballast (temporary) | Clean and place a blanket |
| Subgrade attrition, ballast also worn out | — | Renew the ballast and place a blanket |
| Progressive shear failure | No effective short-term fix | Excavate and rebuild to the required granular depth, and restore drainage |
| Ballast pocket holding water | Drain the pocket where possible | Reshape the subgrade or reconstruct; provide an outlet |
Condensed from the book’s failure-condition and remedy table, which is partly illegible in the source scan. Authors' wording.
Clues in the geometry record.
After Selig & Waters (1994), chs. 14 and 15. Full reference under Supplemental References.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
Monitoring converts an unknown mechanism into a measured one. It also provides warning where mitigation cannot be built right away. Instrument selection, installation and reading frequency are covered in Chapter 5.3.

| Indicator | Instrument or Data Source | Mechanism Monitored |
|---|---|---|
| Subsurface displacement | Inclinometers (ASTM D6230), shape arrays, TDR cable | Slides, creep, spreading |
| Pore pressure | Vibrating-wire piezometers, observation wells | Slides, consolidation, rapid drawdown |
| Settlement | Settlement plates, survey monuments, track geometry-car trends | Consolidation, cumulative deformation, sinkholes |
| Ground surface change | LiDAR change detection, InSAR, UAV photogrammetry | Slides, subsidence, erosion |
| Track bed condition | GPR surveys (Chapter 2.3, Section 2.3.9) | Fouling, ballast pockets, wet subgrade |
| Rockfall and slide detection | Slide fences and detector wires tied to signals | Rockfall, debris flow |
| Rainfall and stream stage | Rain gauges, stream gauges, weather services | All water-triggered mechanisms (Section 3.8.12) |
Recording cars run at fixed intervals: about 3 times a year on main routes, twice a year on intermediate routes and once a year on branch lines. They measure longitudinal, transverse and horizontal defects on a base of about 33 ft and twist on 8–10 ft. At low and medium speeds the absolute (peak and mean) values govern. At higher speeds the standard deviation over 660–980 ft is used as the quality index. Results are ranked by severity and compared with earlier runs and with the limits.

Defects grow quickly until about 2 million tons after maintenance, then slowly and roughly with log T:
Here a1 is the mean settlement at Tr and a0 is the settlement rate per log cycle, 0.079–0.24 in. per decade, depending mainly on subgrade quality (a0/a1 = 0.25–0.70). The standard deviation of longitudinal defects follows the same form with c0 ≈ 0.0039–0.0079 in. per decade. A segment whose fitted a0 or c0 drifts above its neighbors is a candidate for substructure investigation. The sensitive period (about 1–4 months on a UIC group 4 line, 15–40 days on groups 1–3) is when monitoring after a repair matters most.

After Profillidis (2014), §16.5, §16.7, §16.10, Eqs. 16.3–16.5, Figs. 16.5, 16.6, 16.8. Full reference under Supplemental References.

Warning signs appear in a predictable order: unusual high water on one side, seepage at the downhill toe, tension cracks along the shoulder (often hidden in ballast), a bulging toe and a small sand fan, increasingly dirty or milky seepage, trees leaning in different directions, and finally settlement or cross-level change in the track. Test hidden cracks with a lining bar; it meets little resistance over a fissure. Paint reference marks to see whether cracks widen. Walk down to the base of the fill when checking culverts, because much of this cannot be seen from the track. If movement is large and accelerating, take the track out of service and restore drainage urgently.



Moisture clues: groundwater discharge in depressions, wet zones or salt stains in cut ditches, frost boils, ice at culvert sides, moisture-loving plants (cattails, willows), and sudden lush vegetation on a slope. Report every natural-hazard incident, including rock found in a ditch, on the Natural Hazard Incident Report. It records site and weather (at the time and over the prior 24 h), a rockfall section, a mass-movement and washout section, and consequences (damage, delays, slow orders). The data is used to deploy rock gangs and maintenance crews.


After Geotechnology for Railroaders Program, Module 5, Module 7.1, Module 4, Module 6.4; Module 5 §11; Module 7.1 §05; Module 4 §10; Module 6.4 §05. Full reference under Supplemental References.
A responsibility assignment matrix (RAM) makes sure every task has an owner and shows how deeply each person is involved. Tasks are listed as rows and roles as columns. The course uses the RASIC code:

The course example assigns codes for a marketing study (identify market, develop and test the survey, collect and analyze the data, report) across project manager, customer, team members, senior management and support staff.
For railroad work: an early-warning system is only as good as the chain from instrument reading to train movement decision, and that chain crosses organizations. A RASIC matrix agreed before the instruments are installed removes ambiguity at 2 a.m. The illustrative example below must be adapted to each railroad’s own operating rules and authority for slow orders and track removal from service.
Table 4-PM1. Illustrative RASIC matrix for an instrumented slide (adapted from the course method)
| Task | Geotech consultant | Railroad engineering | Track supervisor | Operations / dispatch |
|---|---|---|---|---|
| Set alert and action thresholds | R/S | A | C | I |
| Read and reduce instruments | R/S | I | I | – |
| Threshold exceedance notice | R/S | I | I | I |
| Field inspection of track and slope | S | A | R/S | I |
| Speed restriction or removal from service | C | A | R/S | S |
| Return to normal operation | C | A | R | I |
Keep one Approve per row so that the decision has a single owner. Put named people and phone numbers, with alternates, in the monitoring plan, and review the matrix whenever staff or thresholds change.
Source: Skill Right (2013). Project Management Tools and Techniques: An Introductory Course in Project Management Foundations [training slides sponsored by Texas Instruments, Inc.; minor modifications by N. Santiago, Spring 2013 version], slides 45–47. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
A 2H:1V embankment side slope of silty sand fill carries a main track, and shallow sloughing has been reported after heavy rain. The question is how much of the margin of safety the water takes away. The infinite-slope model (Chapter 6.3) suits this case because the sloughs are shallow and long compared with their depth, and seepage parallel to the slope is the condition that develops in a long wet spell.
| Variable | Value | Description |
|---|---|---|
| β | 26.6° (2H:1V) | Slope angle |
| z | 6 ft | Vertical depth to the slip surface |
| γ | 120 pcf | Total unit weight of the fill |
| γw | 62.4 pcf | Unit weight of water |
| c′ | 50 psf | Effective cohesion |
| φ′ | 32° | Effective friction angle |
| m | 0, 0.5 and 1.0 | Saturated fraction: height of the water table above the slip surface divided by z |
FS = 1.42 dry, 1.10 half saturated and 0.77 fully saturated. The slope is marginal even when dry, below the 1.5 target. A storm that saturates half the slipping depth brings it close to failure, and full saturation fails it.
The example separates the three parts of the story that Section 3.8.1 asks for. The mechanism is shallow translational sliding of the fill. The condition that makes it possible is a steep slope in a weak, permeable fill. The trigger is rainfall infiltration that builds pore pressure. Controls that act on the mechanism are flattening the slope, a drained rock buttress, or surface drainage and vegetation. Until one is built, a rainfall-based patrol (Section 3.8.12) manages the exposure, because it watches the trigger the example shows is decisive.
A rain gauge near a debris-flow channel above the track records a storm. Rainfall thresholds turn a forecast or a gauge reading into a decision, so the check is whether this storm is intense enough, for its length, to be in the range where shallow landslides and debris flows have started worldwide.
| Variable | Value | Description |
|---|---|---|
| P | 2.0 in. | Storm rainfall at the gauge |
| D | 6 hr | Storm duration |
| Threshold | I = 0.58 D−0.39 | Caine (1980) global threshold in in./hr, valid for 10 minutes to 10 days |
Yes. The storm, at 0.333 in./hr over 6 hours, exceeds the Caine threshold of 0.29 in./hr.
Under a protocol calibrated to this threshold, the site would move to its heightened-response level, such as a patrol before the next train or a speed restriction, depending on its risk rating. The global threshold is a lower bound drawn from worldwide data and ignores antecedent moisture, so it is a starting point. Calibrate it against the territory’s own event record before relying on it (Sections 3.8.12 and 3.8.23.7).
Checklist · Part IV · Failure Mechanisms (Triggers)
A ground hazard fails when a triggering event acts on ground that is susceptible to it. The susceptibility is fixed by where the site is and how it was built (soils, geology, slope geometry, water, drainage); the trigger is the event that tips it over: a storm, a flood crest, a thaw, a blocked culvert, an excavation at the toe. Chapter 3.8 describes the mechanisms (Section 3.8.1 distinguishes mechanism, condition and trigger) and the trigger inventory (Section 3.8.11). This chapter puts the trigger at the head of the rating, because it is the thread that ties the rest together: it explains the defects, sets the live thresholds, and is what a solution must remove or resist.
Three things are named for every site:
| Driving mechanism (Section 3.8.23.3) | Typical triggers | How the trigger acts | Data used to rate and monitor it |
|---|---|---|---|
| Slope-driven | Prolonged or intense rainfall; snowmelt; rapid drawdown; toe excavation; added load (new track, fill, stockpiles); earthquake | Raises pore pressure or removes or loads the slope, lowering the factor of safety below 1.0 | Rainfall and antecedent wetness, snowmelt, river stage, construction records, seismic hazard maps |
| Scour-driven | Flood crest; ice jam; debris on a pier or culvert inlet; channel migration | Removes support at the toe, abutment or culvert outlet; oversteepens the bank | River gauges and flood categories, flow percentile, high-water marks, imagery sequence |
| Drainage-driven | Storm exceeding culvert or ditch capacity; blockage by debris, sediment or beavers; frozen culvert | Ponds water against or within the fill; saturates and softens it; causes piping or overtopping | Culvert capacity storm, 24-hour rainfall, beaver activity, inspection records |
| Subgrade-driven | Wet season; spring thaw after deep frost; increased tonnage or axle load | Softens the subgrade; causes pumping, ballast pockets and loss of bearing | Frost depth and thaw, soil moisture, tonnage records, geometry exception frequency |
| Subsidence-driven | Heavy rainfall or a broken pipe in karst; groundwater drawdown; mine void migration; wetting of collapsible soil | Washes soil into voids or collapses a void roof; collapses the soil structure | Karst and mine maps, rainfall, utility records, InSAR where available |
| Rock and debris | Freeze-thaw cycles; intense rainfall; root wedging; wildfire followed by rain; earthquake | Opens joints and loosens blocks; mobilizes debris flows | Freeze-thaw cycle counts, rainfall intensity, burn area maps, rockfall records |
Where two triggers act together, for example a flood that scours the toe followed by drawdown that fails the slope, record both and name the one that starts the sequence as the primary trigger.
The trigger rating scores how often the primary trigger reaches the level that this site has shown, or can be expected, to respond to. The levels use the same annual frequency bands as the frequency index (Table 3.8-14), so a trigger and a failure can be compared directly.
| T | Level | How often the trigger reaches the site's response level | Rationale |
|---|---|---|---|
| 5 | Acting now | The trigger is acting, or reaches the response level one or more times a year (for example, water ponds against the fill in most wet seasons) | A trigger that is present every year leaves no margin: any susceptibility the site has will be tested every year, so failure frequency is limited only by the ground. |
| 4 | Frequent | About 1 in 1 to 1 in 5 years (for example, the paired gauge reaches minor flood stage most years; the culvert overtops in a 2- to 5-year storm) | Events in this band are more likely than not to occur within a five-year maintenance or budget cycle (about 67% at the 1-in-5 edge, Section 3.8.30); the site will meet its trigger before most programs could fix it. |
| 3 | Occasional | About 1 in 5 to 1 in 25 years (for example, a 10-year storm exceeds the culvert capacity) | Likely within the working life of a track structure and of the people managing it; a credible design and planning event. |
| 2 | Rare | About 1 in 25 to 1 in 100 years | Within the range of events that railroad drainage and slopes are commonly designed for; failure from this trigger alone is unusual. |
| 1 | Remote | Less than 1 in 100 years, or no credible trigger for the site's mechanism | Beyond the usual design event; the site needs an extreme or unrecognized event to fail. |
Use the site's own response level (the stage, rainfall or thaw at which it has responded before) where it is known (Section 3.8.23.7). Where it is not known, use the design capacity (culvert capacity storm, flood stage at the toe) and score T no lower than 3 until the record shows otherwise. The trigger elements and their levels are in Section 3.8.27.2.
Every rating begins with a short narrative, written before the numbers, that links the site, the trigger and the evidence. It is the first thing a reviewer reads and the test the numbers must pass: if the narrative and the ratings disagree, one of them is wrong.
The narrative also sets the live rating: the trigger and its response level become the site's thresholds for the live rating of Section 3.8.26.
The current risk combines two independent lines of evidence: the geospatial risk, which says what the location, its conditions and its trigger make likely, and the defect rating, which says what the track and the ground are actually showing. Neither is enough alone. A susceptible site with a frequent trigger can be sound today, and a site that looks benign on every map can be moving. The two are combined into the current frequency index Fc, which with the severity S gives the current risk rating.
The geospatial frequency is assembled at the desk from mapped and recorded data: the situational likelihood attributes L1 to L5 (soils, geology, slope geometry, hydrology, drainage), weighted for the driving mechanism, and the historic instability attribute L6, exactly as in Sections 3.8.23.4 and 3.8.24.3 (element criteria in Sections 3.8.27.3 and 3.8.27.4). It is then bounded by the trigger rating:
Rationale. A site cannot fail more often than the event that triggers it. Bounding L by T keeps a highly susceptible site with no credible trigger from rating as if it failed every year, and it makes the trigger narrative part of the number. Where the trigger is uncertain, T is scored no lower than 3 (Table 3.8-9), so the bound never hides an unrecognized trigger.
The defect rating scores the evidence that the ground is responding: track geometry defects and slow orders at the site, and the instability indicators recorded in the field (Table 3.8-25). Defect frequency is the best single measure of how fast a condition is developing (Section 3.8.24.4).
| D | Level | Defect and indicator evidence | Rationale |
|---|---|---|---|
| 5 | Active | Geometry defects return within weeks of surfacing; standing slow order or track removed from service; active cracking, bulging, settlement or erosion that is visibly progressing | The failure is under way; this is the field evidence that defines an Occurring frequency index (Table 3.8-14). |
| 4 | Recurring | The same defect returns between surfacing cycles (surfaced two or more times in 12 months at the same location), or a slow order in the last 12 months; fresh tension cracks or a growing bulge | Movement is continuing and outpacing maintenance; this is the evidence that defines Emerging. |
| 3 | Present | Defects reported more than once in the record but not returning between cycles, or indicators present (seepage, standing water at the toe, old cracks, a narrow shoulder) without signs of progress | The conditions for failure are showing at the surface, but movement is not demonstrated; consistent with Forming. |
| 2 | Historic | Past failures or repairs at the site, or a single defect in the record, with no current indicators | The site has failed before and may again under a large trigger; consistent with Dormant. |
| 1 | None | No defects in the record and no indicators in the field | No evidence that the ground has responded; frequency can be judged only from the geospatial rating. |
Record each defect with its measurement (in inches) and its frequency, as in Block 2 of the Ground Hazard Risk Assessment Report (Section 3.8.24.4). At the desk, D is scored from the defect and slow order records; in the field it is confirmed or changed from what is seen. The defect elements and their levels are in Section 3.8.27.5.
The rule has three parts, each with a reason:
| Geospatial Fg ↓ / Defect D → | D = 1 None | D = 2 Historic | D = 3 Present | D = 4 Recurring | D = 5 Active |
|---|---|---|---|---|---|
| Fg = 5 | 3 | 3 | 4 | 5 | 5 |
| Fg = 4 | 3 | 3 | 4 | 4 | 5 |
| Fg = 3 | 3 | 3 | 3 | 4 | 5 |
| Fg = 2 | 2 | 2 | 3 | 4 | 5 |
| Fg = 1 | 1 | 2 | 3 | 4 | 5 |
Read the row for Fg and the column for D. Where D is at or above Fg the defects govern; with little or no defect evidence the cap of 3 applies; the cells Fg = 4 or 5 with D = 3, and Fg = 5 with D = 4, carry the one-level amplification.
The current frequency index is the rating under usual conditions. During a weather or river event the live rating of Section 3.8.26 raises it while the trigger's threshold is exceeded, and returns it to Fc when the event has passed and the site has been checked. The trigger named in the narrative is the trigger the live rating watches.
Severity (S) is the consequence if the failure happens, scored 1 to 5 from Table 3.8-15: what the track carries (traffic, speed, passenger and hazardous materials trains), the number of tracks and redundancy of the route, the size of the failure, and what lies below and beside the track. Severity is a property of the site, not of the trigger or the state of the ground; it does not change during a live event. The consequence elements and their levels are in Section 3.8.27.6.
Two rules carry the extra weight on consequence called for in Section 1.1.2: where the consequence and the typical setting point to different levels, the consequence governs; and the engineer may raise the rating one level where the matrix understates the risk (Section 3.8.22.6), but never lower it. Severity changes in a risk reduction only where the solution changes what a failure would reach (Section 3.8.37.3).
Because severity belongs to the site and what it carries, it is rescored when the line changes, not when the ground or the weather does.
A quick check before a severity is recorded: name the train that would meet the failure, what it is carrying and at what speed; say where a derailed train would go (into a creek, onto a road, against a building); and say how long the line would be out and whether traffic can be detoured. If those answers point to different levels, the consequence governs. The same 15-ft slump below the track is Critical or Catastrophic under a main line with hazardous materials traffic over a stream, and Minor under a yard track with a parallel lead.
The current risk rating carries the required response of Table 3.8-17 (Severe: act now; High: act soon; Elevated: plan; Guarded: watch; Low: routine inspection). It is reported with the trigger narrative and with each of its inputs, so a reviewer can see whether the rating is driven by the location (Fg), by the track (D) or by the consequence (S).
| Item | Value | One-line reason |
|---|---|---|
| Primary trigger and T | e.g. culvert overtopping, T = 4 | Ponding against the fill recorded about every 3 years |
| Situational and historic score L | 1–5 | Weighted L1–L6 per Section 3.8.24.3 |
| Geospatial frequency Fg | lesser of L and T | |
| Defect rating D | 1–5 | Defect measurements and frequency; indicators |
| Current frequency Fc | Table 3.8-11 | |
| Severity S | 1–5 | Traffic, setting, what lies below |
| Current risk Rc and rating | Fc × S; Table 3.8-16 |
Every rating in this chapter is built from two questions: how likely is the ground to fail, and how bad would a failure be? The first is answered by the frequency index (F); the second by the hazard severity (S). Each is scored on five levels, and the two are combined into a risk score and a risk rating. The situational, instability, static and live ratings in the sections that follow are not separate systems: they are different ways of arriving at F and S, and they all end on the same matrix. A site rated Elevated at the desk, on a live map or on the field form means the same thing in every case. Figure 3.8-39 shows how the pieces fit together.
Every scale in this chapter runs from 1 to 5, and risk increases with the number. This holds for the situational and instability attributes (L1 to L6 and C1 to C5), the frequency index, the hazard severity, the live frequency index and the risk rating itself. Where the evidence for an attribute is missing, it is scored 3, the middle of the scale, and flagged for the field visit. Table 3.8-13 shows where each scale is used.
| Scale | Symbol | Range | Set from | Section |
|---|---|---|---|---|
| Situational likelihood attributes | L1–L5 | 1–5 each | Location and inherent conditions: soils, geology, slope, hydrology, drainage | 3.8.23 |
| Consequence attributes | C1–C5 | 1–5 each | Track, traffic, train type, what lies below, size of failure, redundancy | 3.8.23 |
| Instability attribute and defect rating | L6, D | 1–5 each | Past failures; geometry defects, slow orders and field indicators (Table 3.8-10) | 3.8.24 |
| Frequency index | F (preliminary Fp) | 1–5 | Geospatial frequency Fg (L1–L6 bounded by trigger rating T) with defect rating D, Table 3.8-11; desk D from records, field D from indicators | 3.8.22.2, 3.8.24, 3.8.25; 3.8.19 |
| Hazard severity | S (preliminary Sp) | 1–5 | Desk: C1–C5. Field: exposure confirmed in Block 1 | 3.8.22.3, 3.8.23 |
| Live frequency index | Flive | 1–5 | F raised by live weather, river and ground data | 3.8.26 |
| Risk score | R = F × S | 1–25 | Product of the two scales; used only to place the site in a rating | 3.8.22.4 |
| Risk rating | — | Low (1) to Severe (5) | Risk matrix, Table 3.8-16 | 3.8.22.4 |
The frequency index describes the state of the hazard, which sets how often a failure can be expected. The worksheet calls this scale the Annual Failure Frequency Index. It is selected from the evidence of instability (Section 3.8.24); the indicative annual frequencies in Table 3.8-14 help when two levels seem to fit.
| Level | F | Field evidence | Indicative annual frequency of failure |
|---|---|---|---|
| Occurring | 5 | Failure under way: movement, settlement or erosion is active and the track is already affected; repeated slow orders or surfacing | 1 or more per year |
| Emerging | 4 | Clear signs developing: fresh tension cracks, a growing bulge, or geometry defects that return between surfacing cycles | About 1 in 1 to 1 in 5 years |
| Forming | 3 | Conditions for failure present (water against the embankment, an over-steepened slope, a blocked culvert), but the ground is not yet moving | About 1 in 5 to 1 in 25 years |
| Dormant | 2 | Evidence of past instability, but no sign that it is active now; a trigger such as extreme rainfall could reactivate it | About 1 in 25 to 1 in 100 years |
| Inactive | 1 | No evidence of instability, or the cause has been removed | Less than 1 in 100 years |
The hazard severity describes the consequence if the failure happens. It is judged from the exposure of the site: traffic, speed, train type, the number of tracks, the population density factor and what lies below and beside the track. At the desk it comes from the consequence attributes of Section 3.8.23; in the field it is confirmed from Block 1 of the report. Where the consequence and the typical setting point to different levels, the consequence governs.
| Level | S | Consequence of failure | Typical setting |
|---|---|---|---|
| Catastrophic | 5 | Derailment or loss of track support likely to cause fatalities, a hazardous materials release or loss of a structure | Main line with passenger or hazardous materials traffic, over water, a road or a populated area; outage longer than a week |
| Critical | 4 | Derailment or main line outage likely; serious injury possible; major property damage | Main line, moderate to heavy traffic; outage of several days |
| Serious | 3 | Track out of service or under a restrictive slow order; damage confined to railroad property | Main line with light traffic, or busy siding; outage of hours to a day |
| Minor | 2 | Geometry defect needing surfacing or a temporary slow order; no derailment expected | Secondary, industry or yard track |
| Low | 1 | Maintenance-level effect only; no effect on train operations | Any track |
Severity is a property of the site and what it carries, not of the weather or the state of the ground. It does not change in a live event (Section 3.8.26) and usually does not change when a site is stabilized; it changes only when the traffic, the track or the exposure changes.
The risk score is the product of the two scales:
R = F × S (1 to 25)
The score has one job: to place the site in one of five risk ratings. Table 3.8-16 gives the rating for every combination of F and S. Because R is a product, neither scale can be ignored: a Catastrophic site stays at Elevated or above until the cause is removed (Inactive), and a site with Low severity never rates above Guarded.
| Frequency index (F) | Hazard severity (S) | ||||
|---|---|---|---|---|---|
| Catastrophic (5) | Critical (4) | Serious (3) | Minor (2) | Low (1) | |
| Occurring (5) | Severe25 | Severe20 | High15 | Elevated10 | Guarded5 |
| Emerging (4) | Severe20 | High16 | High12 | Elevated8 | Guarded4 |
| Forming (3) | High15 | High12 | Elevated9 | Elevated6 | Guarded3 |
| Dormant (2) | Elevated10 | Elevated8 | Elevated6 | Guarded4 | Low2 |
| Inactive (1) | Guarded5 | Guarded4 | Guarded3 | Low2 | Low1 |
The product weights F and S equally. The extra weight on consequence that Section 1.1.2 calls for comes from three rules for selecting S: the consequence floor in the situational rating (Section 3.8.23.6), “the consequence governs” (Table 3.8-15), and the engineer’s one-level adjustment (Section 3.8.22.6).
Each rating carries a required response and a category from the risk resolution matrix of Section 1.1.7, so a site rated in this chapter can be carried directly into a railroad’s corridor-level risk register.
| Level | Rating | Risk score R | Required response | Category (Section 1.1.7) |
|---|---|---|---|---|
| 5 | Severe | 20–25 | Act now: on-site protection and operating restrictions; immediate stabilization | Unacceptable |
| 4 | High | 12–16 | Act soon: slow order or increased inspection; stabilization in the next program | Unacceptable |
| 3 | Elevated | 6–10 | Plan: monitor, design and schedule stabilization | Tolerable with Mitigation |
| 2 | Guarded | 3–5 | Watch: routine inspection with defined trigger levels | Tolerable with Mitigation |
| 1 | Low | 1–2 | No action beyond routine inspection | Tolerable |
The same six steps are used whether the rating is made at the desk, on a live map or in the field. Only the source of F and S changes.
Each stabilization alternative is rated on the same matrix, as the site would be once that alternative is built. Most stabilization work lowers F by removing the cause (a drained embankment moves from Forming to Dormant or Inactive), while S usually stays the same because the track, traffic and setting do not change. An alternative that lowers S, such as track realignment away from the top of the slope, should say why. An alternative that leaves the site at High or above is at best an interim measure and should be labeled as one. Reading the current rating against the alternative ratings and the cost ranges of Section 3.8.42.6 gives the railroad the cost of each step of risk reduction.
Each alternative is rated in the three stages of Sections 3.8.37 to 3.8.39: the solution rating, as the site would be once the alternative works as intended (Section 3.8.37); the design rating earned by the design criteria, with a construction-stage rating for the risk while the work is built (Section 3.8.38); and the post-stabilization rating, provisional until the works have performed through a triggering event and are maintained, then verified (Section 3.8.39). The ratings in Table 3.8-18 are solution ratings; the field report carries them, and the design and post-stabilization ratings are added as each alternative is designed, built and verified.
A single main track runs on the outside of a curve, on a 25-ft fill across a creek floodplain. The site is rated on the report as found, and three stabilization alternatives are rated as the site would be once each works. One site carried through four examples: the field rating and its alternatives here, then the desk ratings that came before the visit in Sections 3.8.23 to 3.8.25.
| Variable | Value | Description |
|---|---|---|
| Site | Single main track on a curve; 25-ft fill across a creek floodplain | Setting |
| Traffic | 28 trains a day including hazardous materials; 50 mph | Exposure for S |
| Drainage | 36-in. culvert half blocked; water about 3 ft higher on the left | Trigger evidence |
| Field indicators | Seepage at mid-slope; fresh tension cracks along the left shoulder | Defect evidence |
| Records | Four cross level exceptions since the last slow order | Defect evidence |
| Fg | 4 | Geospatial frequency from the desk (Section 3.8.24.7) |
| Alternatives | 1: clear culvert and regrade ditches; 2: Alternative 1 plus lateral drains and toe berm; 3: soldier piles and lagging | To be rated |
| Condition | Frequency index | Hazard severity | R | Rating |
|---|---|---|---|---|
| Current condition | Emerging (4) | Critical (4) | 16 | High |
| Alternative 1: clear culvert and regrade ditches (interim) | Emerging (4) | Critical (4) | 16 | High |
| Alternative 2: Alternative 1 plus lateral drains and toe berm | Inactive (1) | Critical (4) | 4 | Guarded |
| Alternative 3: soldier piles and lagging along the shoulder | Inactive (1) | Critical (4) | 4 | Guarded |
The site rates High (Emerging 4 × Critical 4 = 16). Alternative 1 stays High and is an interim measure; Alternatives 2 and 3 both reach Guarded (4).
Alternative 1 is quick and inexpensive and removes the ponding, but the fill is already cracked and the defects are recurring (D = 4). Removing the trigger alone does not earn a lower defect rating, so its solution rating stays High (Section 3.8.37.2). If a wet season then passes with no movement, its post-stabilization rating can fall to Dormant and Elevated (R = 8), the same treatment the clean-culvert alternative receives in Section 3.8.41. Alternative 2 costs less than Alternative 3 and is built in about 3 months, against more than a year (Section 3.8.42.8). The recommendation is Alternative 1 now, followed by Alternative 2.
The same site is followed through the desk in Sections 3.8.23 to 3.8.25, to show how its preliminary rating is assembled before the visit. With the scales defined, the next section turns to the first input: what the site’s location and inherent conditions make possible.
The situational rating describes what the site’s location and inherent physical conditions make possible, before any evidence of movement is considered. Two embankments may both look sound today, yet one is a 30-ft fill of plastic clay with a river against its toe and the other a 6-ft fill of clean gravel on level ground. The situational rating separates them. It answers two of the questions a desktop study must answer: what is the site, and what could fail, and why.
The situational rating has two halves. The situational likelihood (attributes L1 to L5) scores how susceptible the ground is to failure because of its soils, geology, slope geometry, water and drainage. The consequence (attributes C1 to C5) scores what a failure would reach because of the track, the traffic and what lies below and beside it. Both are fixed by where the site is and how it was built; neither depends on whether the ground is moving now. That is the subject of the instability rating in Section 3.8.24.
The situational rating is made at the desk, before anyone goes on track. For a single urgent site it can be done in an afternoon; for a program of dozens of sites it is done for all of them first, so that field time goes where the risk is.
Start with the railroad’s own records; they are the only source of track structure, construction history and drainage inventory. Then build the site picture from public data. The hazard monitoring map assembles most of the public layers in Table 3.8-19 for a site circle and can generate a Site Background Report with a KMZ of the layers used. The railroad’s defect, slow order and repair records, and the event and ground movement layers, are used in the instability rating (Section 3.8.24); they are listed here because they are collected in the same pass.
| Category | Typical sources | What it shows | Feeds |
|---|---|---|---|
| Railroad records | Track charts and valuation maps; track geometry exception reports; slow order history; maintenance, surfacing and ballast records; drainage structure inventory; past reports and photos; inspector and roadmaster notes | Track, curvature, grade, original construction, fill and cut limits, defect frequency, what has been repaired and when | Situational (setting, C1–C5); Instability (L6, defect history) |
| Topography | USGS 3DEP lidar and elevation models; hillshade and slope maps; historic topographic maps | Fill and cut heights, slope angles, scarps, hummocky ground, drainage paths, channel position relative to the toe | Situational (L3); Instability (scarps for L6) |
| Geology and soils | State geologic maps; NRCS soil survey (SSURGO); USGS landslide inventory and susceptibility; karst maps; abandoned mine land and mine map inventories | Soil type and drainage class, shrink-swell, depth to rock, landslide-prone formations, karst, undermining | Situational (L1, L2) |
| Hydrology | FEMA flood maps (NFHL); NHD and StreamStats drainage areas; NOAA Atlas 14 rainfall; dam inventory (NID); river gauges and high-water marks | Floodplain position, contributing drainage area, design rainfall, upstream dams, how high water has actually reached | Situational (L4, H&H thresholds); Live (gauge pairing) |
| Imagery | Historical aerial photographs; Google Earth historical imagery; NAIP; Sanborn maps | Changes in channel, drainage, vegetation, slope face and adjacent land use over time | Situational (L5, setting); Instability (L6) |
| Event history | NOAA Storm Events and local storm reports; NWS damage surveys; FRA accident and incident data; USGS high-water marks; ice jam database; FEMA disaster declarations | Floods, washouts, slides, storms and rail accidents near the site, with dates | Instability (L6); H&H thresholds |
| Current conditions | Soil moisture percentile; antecedent rainfall; frost depth; drought monitor; river stage | Whether the ground is wetter or the river higher than normal now | Live rating; timing of the field visit |
| Ground movement | Satellite radar (InSAR) displacement where available | Measured settlement or creep since 2016 | Instability (L6) |
Most ground hazards on a railroad are the delayed result of how the line was built, so the situational review begins with the setting and its history, oldest first.
The record of what has already gone wrong at the site (past slides, repairs, defects and the events that triggered them) completes the history, but it is evidence of instability rather than situation and is reviewed in Section 3.8.24.
From the setting and the terrain, assign the driving mechanism: the process most likely to cause failure. It decides which situational attribute carries the most weight (Section 3.8.23.4), which H&H thresholds are needed (Section 3.8.23.7), which live indicators apply (Section 3.8.26) and which stabilization items to expect in the field (Section 3.8.42). The mechanisms follow Chapter 3.8:
Where two mechanisms act together (for example, scour that oversteepens the toe and then a slope failure), record both and name the one that starts the sequence as primary. The instability evidence gathered in Section 3.8.24 may confirm or change this choice; the field visit settles it.
The situational likelihood is deterministic: each attribute is scored 1 to 5 against the fixed descriptions in Table 3.8-20, so two engineers working from the same data reach the same score. Score from the evidence in hand; where the data are missing, score 3 and flag the attribute for the field visit. Scores of 2 and 4 fall between the descriptions; written descriptions for them are in Table 3.8-76 (Section 3.8.36.5).
| Attribute | Score 1 | Score 3 | Score 5 | Main sources |
|---|---|---|---|---|
| L1 Surficial soils | Rock, or clean, well-drained sand and gravel | Silty or clayey sand, low-plasticity silt or clay; moderately drained | High-plasticity or organic clay, loess, sensitive or collapsible soil; poorly drained; softens when wet | Soil survey, geologic map, past boring logs |
| L2 Geologic setting | Competent rock at or near the surface | Weathered rock or till at moderate depth | Deep weak overburden, colluvium, mapped landslide-prone formation, karst or undermining | Geologic map, landslide inventory, karst and mine maps |
| L3 Slope geometry | Fill or cut under 10 ft, slopes flatter than 3H:1V | Fill or cut 10 to 30 ft, or slopes about 2H:1V | Fill or cut over 30 ft, slopes steeper than 1.5H:1V, or a sidehill fill | Lidar, track charts |
| L4 Hydrology | No contributing flow; well above any floodplain | Ditch or small-stream flow along the toe; in or near a 500-year floodplain | Stream or river against the toe; in the 100-year floodplain; convergent flow or ponding against the fill | Flood maps, drainage area, imagery, gauges |
| L5 Drainage condition | Ditches and culverts free-draining and adequate | Partly obstructed ditches or an aging culvert; some sediment | Blocked or undersized culvert, no outlet control, record of overtopping, beaver activity | Drainage inventory, imagery sequence, maintenance records |
For L3, score height and steepness separately and use the higher. Each attribute carries a weight of 1, except the attribute that matches the driving mechanism, which carries a weight of 2: L4 for scour-driven, L5 for drainage-driven, L3 for slope-driven, L1 for subgrade-driven, and L2 for subsidence-driven or rock and debris. The situational likelihood is the weighted average:
LS = Σ (wi · Li) / Σ wi, i = 1 to 5
LS is kept to two decimals; it is combined with the instability attribute in Section 3.8.24 before any rounding.
The consequence attributes describe what a failure would do. They are the situational half of the rating that sets hazard severity, and they draw on the exposure that will be confirmed in Block 1 of the report (Section 3.8.42.4).
| Attribute | Score 1 | Score 3 | Score 5 |
|---|---|---|---|
| C1 Track and traffic | Industry, yard or out-of-service track | Main line with light traffic, or a busy siding | Main line with heavy tonnage or high speed; multiple main tracks |
| C2 Train type | No passenger or hazardous materials traffic | Occasional hazardous materials | Passenger trains or a key hazardous materials route |
| C3 Below and beside the track | Open land on railroad property | A road, a small stream or farmland | A river, highway, dwellings, utilities or a water supply |
| C4 Size of failure | Fill under 5 ft; failure would be shallow | Fill 10 to 20 ft | Fill over 30 ft, or a culvert or structure under high fill |
| C5 Redundancy and recovery | Parallel route; repair within a shift | Detour available; repair in days | No detour; difficult access; outage longer than a week |
The consequence value C is the average of C1 to C5, with one floor: a 5 on C2 or C3 sets C at no less than 4, because a failure that can reach passengers, a hazardous materials release or the public governs regardless of the other attributes. Round C half up (2.5 becomes 3) to the nearest whole number to give the preliminary hazard severity Sp on the scale of Table 3.8-15. Sp is the situational rating’s contribution to severity; it is carried unchanged into the static rating (Section 3.8.25) and printed on the report for the EIC to confirm.
For every site whose driving mechanism involves water (scour, drainage, and most slope and subgrade failures), the situational review also sets the site’s water thresholds: the conditions at which this particular embankment, culvert or toe starts to be loaded beyond what it normally carries. They are a property of the location, like the attributes above, and they are what make a live rating possible (Section 3.8.26): live weather and river data mean little until they are compared with what the site can take.
| Threshold | How it is set | Sources |
|---|---|---|
| Paired gauge and toe stage | Choose the nearest gauge on the same stream that responds to the same storms. Relate its stage to the elevation of the embankment toe, the culvert outlet and the lowest point of the subgrade, from lidar and, where available, surveyed high-water marks. Record the gauge stage at which water reaches the toe (toe stage) and the stage at which damage has occurred (damage stage). | NWS and USGS gauges, flood categories, lidar, high-water marks, railroad event records |
| Culvert capacity storm | From the drainage area, time of concentration and the culvert size and condition, estimate the return period the culvert passes without heading up against the fill (culvert hydrology, Section 3.5.10). Convert it to a rainfall depth for the critical duration (typically 1 to 24 hours) with Atlas 14. | StreamStats or lidar drainage area, drainage inventory, NOAA Atlas 14 |
| Site rainfall threshold | The 24-hour rainfall at or above which the site has historically responded (defects, slow orders, slides, overtopping). Where there is no history, start at the 2-year 24-hour Atlas 14 depth, or the culvert capacity storm if that is lower. | Event and defect history matched against rainfall records; Atlas 14 |
| Antecedent wetness | The soil moisture percentile or 30-day rainfall (percent of normal) that preceded past failures. Where there is no history, use the 80th soil moisture percentile. | Soil moisture percentile, antecedent rainfall |
| Freeze-thaw and snowmelt | For northern sites, whether the site has failed during thaw or rain-on-snow, and the frost depth or snowpack that preceded it. | Frost depth, freezing index, snow water equivalent |
The thresholds are first estimates. They are printed on the report so the field visit can check the toe, outlet and culvert elevations, and every later event refines them (Section 3.8.26.6).
The site of Example 3.8-3, scored at the desk before the visit from lidar, the soil survey, an old boring, the floodplain map and imagery.
| Attribute | Score | Weight | Basis |
|---|---|---|---|
| L1 Surficial soils | 4 | 1 | Lean clay that softens when wet |
| L2 Geologic setting | 3 | 1 | Alluvium over weathered shale at moderate depth |
| L3 Slope geometry | 3 | 1 | 25-ft fill, slopes about 2H:1V |
| L4 Hydrology | 5 | 1 | Creek against the toe; 100-year floodplain |
| L5 Drainage condition | 4 | 2 | Culvert half blocked; ponding seen in imagery |
| LS = (4 + 3 + 3 + 5 + 2 × 4) / 6 = 23 / 6 = 3.83 | |||
| C1 Track and traffic | 4 | — | Main line, 28 trains a day |
| C2 Train type | 4 | — | Regular hazardous materials traffic |
| C3 Below and beside | 3 | — | Small stream and farmland |
| C4 Size of failure | 4 | — | Fill 20 to 30 ft |
| C5 Redundancy | 3 | — | Detour available; repair in days |
| C = (4 + 4 + 3 + 4 + 3) / 5 = 3.6; no floor applies (no 5 on C2 or C3); Sp = 4, Critical | |||
Drainage-driven mechanism; LS = 3.83; C = 3.6, giving Sp = 4, Critical. On its situation alone, this is a susceptible site carrying a Critical consequence. What the situation cannot say is whether the ground has started to move. That is the job of the instability rating (Example 3.8-5).
The situational rating says what a site could do. The instability rating says what it has done and is doing: past failures and repairs, track geometry defects that keep coming back, and the cracks, bulges, seeps and voids that the engineer sees on the ground. Past movement is the best single predictor of future movement, and present movement is direct proof that the frequency index is high. The instability rating therefore governs the frequency index: it supplies the defect rating D that, with the geospatial frequency, sets the current frequency index (Table 3.8-11) at the desk and in the field.
The instability rating is assembled in two passes. The desk pass reads the railroad’s records and the public event and movement data (Section 3.8.24.1 to 3.8.24.3). The field pass is made by the EIC on site, in Blocks 2 and 3 of the report (Sections 3.8.24.4 and 3.8.24.5), and turns what is seen into the field frequency index (Section 3.8.24.6).
Continue the site history begun in Section 3.8.23.2, still oldest first, with the record of what has gone wrong:
The instability record is scored on one attribute, L6, using the same 1-to-5 convention as the situational attributes, and the defect history is scored as the defect rating D of Chapter 3.8.
| Item | Score 1 / no change | Score 3 | Score 5 / raise one level | Main sources |
|---|---|---|---|---|
| L6 Historic instability | No evidence of movement | Past repair at the site, or mapped instability nearby | Repeated documented failure, a scarp visible in lidar, or measured movement | Railroad records, lidar, landslide inventory, InSAR |
| Defect rating D | 1: no defects in the record and no indicators | 3: defects reported more than once but not returning between cycles, or indicators without progress | 5: defects returning within weeks of surfacing; standing slow order. 4: the same defect returns between surfacing cycles, or a slow order in the last 12 months (Table 3.8-10) | Track geometry exception reports, slow order history, surfacing records |
This table scores the defect rating at the desk from the records. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.
Scores of 2 and 4 for L6 are described in Table 3.8-76. Defects are scored as a separate rating rather than as an attribute because they are direct evidence that the ground is moving now; they outweigh what the terrain alone suggests, so they act on the frequency index through Table 3.8-11 instead of being diluted in the average.
The preliminary frequency index combines the situational likelihood with the instability attribute. L6 carries a weight of 1 and is added to the weighted situational attributes:
L = [ Σ (wi · Li)i = 1 to 5 + L6 ] / [ Σ wi + 1 ]
Round L half up (2.5 becomes 3) to the nearest whole number, then bound it by the trigger rating to give the geospatial frequency Fg = the lesser of L and T (Equation 3.8-2). The preliminary frequency index Fp is read from Table 3.8-11 using Fg and the defect rating D scored from the railroad's records. The situational and instability contributions (LS, L6, L), T and D are kept separately so they can be seen, and printed, on the report.
On site, the instability rating is completed from what the ground and the track are showing. Block 2 of the report is a checklist of indicators, recorded separately for the left embankment, the track between the rails and the right embankment. The embankment lists are the same on both sides. The between-rails list records the track geometry defects and track structure symptoms that brought the engineer to the site.
| Left and right embankment | Between the rails |
|---|---|
| Upper slope bulge, tension crack or seepage | Reported cross level (measurement and frequency) |
| Mid-slope bulge, tension crack or seepage | Reported profile (measurement and frequency) |
| Lower slope bulge, tension crack or seepage | Reported alignment (measurement and frequency) |
| Standing water in ditch or at toe of slope | Reported warp (measurement and frequency) |
| Obstruction in ditch | Fouled ballast or water between cribs |
| Culvert dry, obstructed or damaged | Tie shift |
| Water level higher than on the opposite side | Voids between cribs |
| Erosion | Shoulder narrower than 12 in. |
Orient and walk the site. Stand on the track centerline facing up station (increasing milepost); the left embankment column is on your left and the right on your right, so “left” and “right” mean the same thing to everyone who reads the form. Walk each embankment from the top of slope to the toe, then check the ditch and toe, each culvert, the water level against the opposite embankment, and erosion. Between the rails, enter each reported defect with its measurement (the defect value, in inches, from the geometry car or track inspector) and its frequency (how often it has been reported or corrected, for example “surfaced 3 times since May”), then mark the track structure symptoms you can see. Photograph every marked indicator with a scale and the milepost in the frame, and write the photo number beside the entry.
Read the pattern, not the item. A single indicator rarely decides the case; the combination does. Typical patterns are:
Defect frequency is the best single field measure of how fast the condition is developing, and it is the main evidence for the field frequency index. Record it exactly as the railroad reports it.
Block 3 records what is failing, what will make it hard to fix, and how it is expected to fail.
| Major element | Construction constraint | Estimated failure type |
|---|---|---|
| Ballast | Access and mobility | Bearing capacity |
| Subgrade | Railroad workload conflict | Slope |
| Foreslope | Property | Settlement |
| Backslope | Material | Washout |
| Bridge abutment | Underground obstructions | Subsidence |
| Culvert | Water source | Surface erosion |
| Ditch | Permit | Stream and wave erosion |
| Adjacent property | Environmental | Underground flow erosion |
Major element is the part of the roadbed or structure whose failure threatens the track. More than one may apply; number them with the governing element as 1.
Estimated failure type is the engineer’s field judgment of the mechanism. Mark one as primary; a second may be marked as contributing. Compare it with the driving mechanism assigned at the desk (printed in the Desktop Study Summary of the report) and note any change. The exploration and analysis scoped in Block 5 confirm or revise it, and it sets which analyses are required (Section 3.8.42.8). Section 3.8.13 shows how to work from the symptom back to the mechanism.
Construction constraints are not part of the rating, but they are recorded here, while the access, the right-of-way and the utilities are in view, because they often decide which alternative is practical. Equipment access, track time (railroad workload conflict, confirmed with the railroad contact), right-of-way and adjacent property, the supply of fill and aggregate, buried utilities, a construction water source, permits and environmental restrictions can each rule out an otherwise sound fix. A toe berm that needs property the railroad does not own, or a sheet pile wall that needs a crane on a single-track main line with no work windows, is not a practical alternative.
In the field the EIC does not recompute L. The EIC confirms the trigger and T, sets the field defect rating D from the instability evidence (Table 3.8-27, which matches Table 3.8-10), and reads the current frequency index Fc from Table 3.8-11 using the geospatial frequency Fg printed on the report. Fc is the field F. The preliminary Fp is printed beside it as a check.
| Instability evidence (Blocks 2 and 3, desk record) | Field defect rating D |
|---|---|
| Active movement, settlement or erosion affecting the track now; repeated slow orders or surfacing; defects recurring faster than surfacing can hold | 5 Active |
| Fresh tension cracks or a growing bulge; geometry defects that return between surfacing cycles; the track still runs at or near normal speed | 4 Recurring |
| No sign of movement, but the conditions for it are present: water ponded against the fill, seepage, a blocked culvert, an over-steepened or eroding slope | 3 Present |
| Old scarps, past repairs or a documented failure (L6 of 3 or more), but no fresh indicators and no recurring defects | 2 Historic |
| No indicators, no instability record, or the cause has been removed | 1 None |
This table sets the defect rating in the field from what is seen. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.
Where the field F differs from Fp by more than one level, write the reason on the report. Those notes are how the desktop attributes and thresholds are calibrated over time.
Continuing Example 3.8-4: the site's record of past movement and its track defects are added to its situation, first at the desk and then on the field visit.
| Variable | Value | Description |
|---|---|---|
| ΣwiLi, Σwi | 23; 6 | From Example 3.8-4 |
| Repair record | Shoulder slump repaired with fill and riprap 12 years ago | Evidence for L6 |
| Geometry record | Four cross level exceptions since the last slow order, returning between surfacing cycles | Desk evidence for D |
| T | 4 | Storm exceeding the half-blocked culvert ponds water in most wet years |
| Field findings | Seepage at mid-slope; water 3 ft higher on the left; culvert half blocked; fresh tension cracks; track at normal speed, no slow order | Field evidence for D |
L6 = 4; L = 3.86 → 4; Fg = 4; D = 4 at the desk and in the field; Fp = Fc = 4, Emerging. The desk rating predicted the field rating: the records already showed the recurring defects that the visit confirmed.
The site now has a situational severity and an instability-based frequency index. Section 3.8.25 combines them into the static rating that ranks the site under usual conditions.
A static hazard rating describes a site or segment under its usual, long-term conditions. It is built from information that changes slowly, if at all: where the line runs, what it is built on, what it carries, and its record of past trouble. Static ratings are used to choose which segments get a desktop study, to rank sites for field assessment, and to set the baseline that the live rating (Section 3.8.26) raises during weather events. They change only when new information arrives: a new data release, a field visit, a repair or a new failure.
Two static ratings are used, at two scales:
The Federal Railroad Administration introduced the Composite Hazard Index (CHI) to short line and regional railroads in an American Short Line and Regional Railroad Association (ASLRRA) webinar, Evaluating Railroad Infrastructure Exposure to Natural Hazards Using FRA’s Composite Hazard Index. The CHI is a screening index: it combines several natural hazard measures into one value for each segment of the rail network, so that segments can be compared and ranked by their exposure.
Underlying data. The federal hazard exposure data released for the rail network show what such an index is built from. The Bureau of Transportation Statistics (BTS) Hazard Exposure: Select North American Rail Network Lines layer (beta, October 2025) attaches hazard values to every main line and operational line segment of the North American Rail Network, across the 50 states and the District of Columbia. For each segment it carries:
The BTS layer reports each hazard separately and does not combine them; the CHI does the combining. At the time of writing, FRA had not published the CHI method (which inputs are used, how each is normalized and how they are weighted) in a form available for review. Before relying on a CHI value, confirm its inputs and weighting against FRA’s documentation.
Related research. A companion approach links recorded events, rather than modeled likelihood, to rail segments. Researchers at Oregon State University, working through the Mineta Transportation Institute, assigned flood, landslide and extreme heat and cold events from 2000 to 2023 to individual segments (flash floods by watershed hydrologic unit, riverine floods by river corridor, heat and cold by NWS forecast zone, landslides by proximity to the track) and checked the result against FRA accident records with weather-related cause codes, such as T002 for washout, rain, slide or flood damage to track. Their dataset is public and gives each segment a count of the events it has actually experienced. Where it is available, that count is the network-scale counterpart of the instability rating.
What the CHI does well. It covers the whole network on one consistent basis, needs no site work, and puts weather, flood, wildfire and ground hazards on the same footing. That makes it well suited to choosing which subdivisions and segments get a desktop study first, and to showing a funding agency that a line is more exposed than most.
What it cannot do. It describes exposure, not condition:
The CHI works from the network down; the situational, instability and live ratings work from the site and its trigger up. They answer different questions and are best used together. Table 3.8-28 compares them.
| Aspect | FRA Composite Hazard Index (network static) | Situational and instability ratings (site static) | River gauge monitoring (live) |
|---|---|---|---|
| Question answered | Which segments of the network are most exposed to natural hazards? | What makes this site susceptible, and what has happened here? | Is a water trigger happening now, or forecast, at this site? |
| Spatial unit | Rail network segment; hazard values mostly from tract, county or regional grids | Site circle or affected limits | Gauge point, applied to the sites paired with it |
| Time basis | Long-term: annualized frequency and modeled likelihood; static between releases | Historical record plus railroad records; static between visits | Real time (typically every 15 minutes to hourly) with NWS forecasts |
| Hazards covered | Weather and climate hazards, riverine and coastal flooding, wildfire, landslide index, sinkholes, storm surge | Geology, soils, slope, landslides, karst, mines, flooding, drainage, storms, frost, ground moisture, accidents | Riverine flooding, scour, backwater; ice jams where reported |
| Railroad condition and defects | Not included | Included, from railroad records (L6 and defect history) | Not included |
| Output | One index value per segment, for ranking | Attribute scores, Fp, Sp and a preliminary rating | Stage and flow against flood categories and percentiles; live rating |
| Effort | Low: look-up | Moderate: analyst time for each site | Low once set up; thresholds need calibrating |
| Main limitation | Exposure, not condition; regional resolution; method to be confirmed | Starts from flagged sites; depends on map scale and record completeness | Point measurement; ungauged drainages; water triggers only |
Using them together.
The preliminary site rating brings the two desk ratings together on the matrix of Table 3.8-16:
Rp = Fp × Sp
where Fp is read from Table 3.8-11 using the geospatial frequency (situational and instability attributes bounded by the trigger rating) and the defect rating from the records (Section 3.8.24.3) and Sp from the consequence attributes (Section 3.8.23.6). The rating is labeled preliminary until the EIC confirms or changes it in the field. Keep the attribute scores, LS, L, T, Fg, D, C and the trigger narrative with the site record: they show the field engineer why the site ranked where it did, and they let a program rank sites that share the same rating, by L × C.
Once a site has been assessed, its field rating replaces the preliminary rating as its static rating. It remains the static rating, and the baseline for the live rating, until the next visit, a repair or a new failure.
The preliminary rating sets how soon the site is visited and how much effort goes into the field assessment. The level of effort rises with the rating, so that borings and instruments go to the sites that need them.
| Preliminary rating | Priority | Field assessment | Level of effort | Monitoring until visited |
|---|---|---|---|---|
| Severe | 1 | Notify the railroad the same day; visit within days | Full assessment; plan exploration and instrumentation from the visit | Inspection after every trigger event; recommend operating restrictions until visited |
| High | 1 | Within two weeks | Full assessment; borings likely | Increased track inspection; gauge or rainfall trigger set |
| Elevated | 2 | Within the program cycle (typically 30 to 90 days) | Full assessment; exploration scoped from the findings | Routine inspection with trigger levels |
| Guarded | 3 | As the program allows; may be confirmed from track video or a hi-rail pass | Walk-through; full assessment if anything is found | Watch list; re-screen after a trigger event |
| Low | – | Not required | Desktop record only | Re-screen with the network screening or after an event |
For a program of many sites, the static rating also starts the sorting that the field assessment finishes. After the visit, sites usually fall into three groups: those ready to move to construction, those that need design, exploration or permits first, and those that can be monitored and deferred. The preliminary rating gives the first cut at that sorting; the field ratings and alternatives (Section 3.8.42) settle it.
The desk ratings of Examples 3.8-Y2 and 3.8-Y3 combine into the preliminary rating that scheduled the visit; the field rating of Example 3.8-3 then confirms or replaces it.
| Variable | Value | Description |
|---|---|---|
| Fp | 4 | Example 3.8-5 |
| Sp | 4 | Example 3.8-4 |
| Fc, S | 4, 4 | Field rating, Example 3.8-3 |
Rp = 16, High (preliminary), confirmed in the field at R = 16, High. From the date of the visit, High is the site’s static rating and the baseline for its live rating (Section 3.8.26).
The static rating describes a site under its usual conditions. Risk at a water-sensitive site is not constant: it rises during a flood, a heavy storm on wet ground or a spring thaw, and falls again when the water drains. The live rating measures that rise. It compares live weather, river and ground data against the site’s own H&H thresholds (Section 3.8.23.7) and raises the frequency index while a threshold is exceeded. Because it uses the same scales and the same matrix as every other rating in this chapter, a jump in the live rating means exactly what the same rating means anywhere else, and it calls for the response in Table 3.8-17.
The live rating needs three things from the earlier sections: a static rating to start from (Section 3.8.25), a driving mechanism that says which water conditions matter (Section 3.8.23.3), and thresholds that say how much water this site can take (Section 3.8.23.7).
The river stage watchlist pairs gauges near the line with their flood categories. NWS gauges in the National Water Prediction Service report observed and forecast stage against four thresholds set for each gauge: action, minor, moderate and major flood stage. USGS gauges add discharge and how the current flow compares with the record for that day of the year (the streamflow percentile). A site whose driving mechanism is scour or drainage is paired with the nearest representative gauge, and its response is tied to the gauge’s thresholds. This applies the rule in Chapter 3.8: pair every water-sensitive site with a trigger source and a response threshold, and record the trigger magnitude after each event so the thresholds can be calibrated.
Gauge monitoring speaks to the conditions that actually fail track, gives real-time and forecast warning of the most common trigger, and lets each event add to the site’s own history. Its limits are that a gauge is a point on a river, that a gauge miles away on the main stem says little about a small tributary culvert, and that many small drainages have no gauge at all. For those sites, rainfall and soil moisture carry the live rating.
| Gauge condition | Default response |
|---|---|
| Below action stage; flow percentile under 90 | Routine inspection |
| Action stage reached or forecast, or flow above the 90th percentile | Alert the roadmaster; check the site at the next opportunity and after the crest |
| Minor flood stage reached or forecast | Inspect the site before and after the crest; watch culvert inlets for debris and backwater |
| Moderate flood stage reached or forecast | Inspect the site at the crest; consider a slow order on Severe and High rated sites |
| Major flood stage, or water against the embankment above any level seen before | Protect the track; operating restrictions until the site is inspected after the water falls |
These are starting values. Set each site’s levels from its own history: the stage at which water first reached the toe, overtopped a culvert or caused a defect. Inspection continues after the crest; many embankments fail on the falling limb, when the water outside drops faster than the water in the fill.
Start from the site’s static rating: the field rating where the site has been assessed, otherwise the preliminary rating. The baseline frequency index is F0 and the severity is S. Severity is not changed by the weather; the consequence of a failure is the same whenever it happens.
Check each indicator that applies to the site’s driving mechanism against the levels in Table 3.8-31. Observed values and forecasts for the next 24 to 48 hours both count; a forecast lets the rating rise before the water arrives. During the thaw, add forecast snowmelt to the rainfall, and use the spring hazards and combined snowmelt-plus-rain alert levels in Section 3.8.7.8 and the frost and thaw mechanisms in Section 3.8.8 to set the thaw indicator.
| Indicator | Applies to | Normal | Watch | Warning |
|---|---|---|---|---|
| River stage at the paired gauge | Scour, drainage, slope at a stream toe | Below action stage and below the toe stage | At or above action stage, or at the toe stage | At or above moderate flood stage, or at the damage stage |
| Rainfall, 24-hour observed plus forecast | All water-driven mechanisms | Below half the site rainfall threshold | Half the site rainfall threshold up to the threshold | At or above the site rainfall threshold or the culvert capacity storm |
| Antecedent wetness | Slope, drainage, subgrade | Below the site’s antecedent threshold | At or above the site’s antecedent threshold (default 80th percentile) | Above the 90th percentile and above the site’s antecedent threshold |
| Thaw and snowmelt | Subgrade, slope, rock (northern sites) | Ground frozen or thawed and drained | Thaw under way after deep frost, or snowmelt with saturated ground | Rain on melting snow, or thaw at a site that has failed in thaw before |
| NWS alerts for the site | All water-driven mechanisms | None | Flood watch, or flood advisory | Flood or flash flood warning |
Raise F0 by the increment in Table 3.8-32, to a maximum of 5. Wet ground and heavy rain together are treated as more than either alone, because most rain-triggered failures need both.
| Live condition | Increment to F |
|---|---|
| All applicable indicators Normal | 0 (live rating = static rating) |
| One indicator at Watch | +1 |
| Two or more indicators at Watch, or any indicator at Warning | +2 |
| Warning on river stage or rainfall at a site whose static frequency index is Emerging (4) or higher | Set F to 5 (Occurring) |
Rlive = Flive × S
The live rating is read from the matrix in Table 3.8-16 and reported beside the static rating as a jump, for example Elevated → High, with the indicators that caused it.
Example. A 25-ft fill over a culvert on a main line with moderate traffic has a static rating of Dormant (F = 2) and Critical (S = 4): R = 8, Elevated. Its desktop study found that the culvert passes about a 10-year storm, 4.3 in. in 24 hours at the site. With soil moisture at the 93rd percentile (Warning) and 2.5 in. of rain forecast (Watch), the increment is +2: Flive = 4, Rlive = 16, High. The roadmaster is alerted and the site is inspected before and after the storm. Had the forecast reached 4.3 in., rainfall would also be at Warning, but because the site’s static frequency index is only Dormant, the increment stays at +2 and the rating stays High. The example site of Sections 3.8.23 to 3.8.25, already Emerging, would go to F = 5 on the same rainfall Warning: Rlive = 5 × 4 = 20, Severe. Figure 3.8-40 traces the first case through the storm.
Holding and dropping. Do not drop the live rating as soon as the rain stops or the river crests. Hold it until the river is back below action stage and at least 48 hours have passed since the crest or the end of heavy rain; embankments often fail on the falling limb, and slopes often fail a day or more after the storm, as the water works into the ground.
Running it. The hazard monitoring map computes the live rating for every monitored site in its Live risk rating panel (desktop and phone). Each site stores its static F and S, its driving mechanism, its paired NWS gauge and its H&H thresholds. Every 15 minutes the hazard monitoring map reads the gauge’s observed stage and 48-hour forecast peak against its action and moderate flood stages and the site’s toe and damage stages; the observed 24-hour rainfall (NWS River Forecast Center analysis) plus the NWS forecast for the next 24 hours; the soil moisture percentile in the top 16 in. (NASA SPoRT); and NWS flood watches, advisories and warnings for the site. Thaw is set on each site by the user, because there is no national live source for it. Sites are drawn on the map in their live rating color, a jumped site is ringed, and the panel lists the sites that have jumped with the indicators that caused it. A service that does not respond is named on the site and left out of that reading rather than read as normal. The live rating is a prompt for inspection and for the railroad’s own operating decisions; it does not replace them.
At the field visit. The live rating at the time of the visit is printed on the report (Section 3.8.42.3), so the EIC knows whether the site is being seen wet or dry, and whether the indicators in front of them reflect a passing event or the site’s usual state.
Log every jump with the indicator values and what was found at the site. The hazard monitoring map writes each jump to its jump log with the readings that caused it; record what was found against each entry. A site that jumps repeatedly with nothing found has thresholds set too low; a site that fails without a jump has thresholds set too high, or a driving mechanism that was misjudged. Adjust the thresholds in Table 3.8-22 accordingly, and review the site’s static frequency index when it keeps responding.
Live risk rating and threshold calibration calculator. The calculator below applies Tables 3.8-31, 3.8-32 and 3.8-16 to one site. Tab 1 gives the live rating from the site’s baseline, thresholds and live values. Tab 2 calibrates the thresholds from the site’s event record (date, stage, 24-hour rain, soil moisture percentile and outcome: none, defect, movement or failure), shows which past events the current thresholds would have caught or missed, and suggests thresholds that catch the most responses with the fewest false alarms (one miss counts as three false alarms). A jump log export can be loaded straight into tab 2. The calculator runs in the page; nothing is sent anywhere.
| Indicator | Value | Level | Why |
|---|
Paste the site’s event record, one event per line: date, stage (ft), rain (in. in 24 h), soil moisture percentile, outcome. Outcome is none (nothing found), defect (geometry defect or slow order), movement (cracks, settlement, scour) or failure. Leave a value blank if it is not known; events with no outcome are left out. A jump log exported from the hazard monitoring map (Live risk rating, Jump log) can be loaded directly. The thresholds and site in tab 1 are used as the starting point.
Hit: the live rating jumped and something was found. Miss: something was found but the rating did not jump (thresholds too high). False alarm: the rating jumped and nothing was found (thresholds too low). Suggested thresholds come from trying each recorded value and keeping the set that misses the fewest responses and then raises the fewest false alarms (one miss counts as three false alarms). Treat them as a starting point for judgement and review them as the record grows.
Static and live ratings together tell the railroad where the risk is and when it rises. Neither replaces the engineer on the ground. The next section is the form the engineer takes there.
Sections 3.8.18 to 3.8.39 define each rating by its levels. This section breaks every rating into the elements that are actually looked at, at the desk or on site, and states for each element what places it at 1, 2, 3, 4 or 5. The tables are the working detail behind Tables 3.8-9, 3.8-10, 3.8-80 to 3.8-82 and Tables 3.8-20, 3.8-21 and 3.8-24; they do not change those tables, the equations or the risk matrix. They make the choice of level repeatable: two engineers looking at the same evidence should land on the same score, and the one-line reason required by Section 3.8.43 can be taken straight from the cell that was matched.
| Rating | Element tables | How the element scores give the rating | Section |
|---|---|---|---|
| Trigger rating T | Tables 3.8-34 to 3.8-38 (T1 to T19) | T is the highest score among the trigger elements that can, on their own, bring the site to its response level. Where two triggers act only in sequence (a flood that scours the toe, then drawdown), score the sequence by the frequency of the event that starts it. Where the response level is unknown, T is not lower than 3. | 3.8.18.3 |
| Situational attributes L1 to L5 | Tables 3.8-39 to 3.8-43 | Each attribute is the highest score among its elements that have data. Elements without data are left blank, not scored. An attribute with no data at all is scored 3 and flagged for the field visit (Section 3.8.22.1). The attributes are then weighted and averaged as before (Section 3.8.23.4). | 3.8.19.1; 3.8.23.4 |
| Historic instability L6 | Table 3.8-44 | The highest score among its elements that have data. | 3.8.24.2 |
| Defect rating D | Tables 3.8-45 to 3.8-47 | The higher of (a) the highest score among the record and measurement elements D1 to D4 and D15, and (b) the highest score shown by two or more of the field indicators D5 to D14. Check the result against the level descriptions of Table 3.8-10. | 3.8.19.2 |
| Consequence attributes C1 to C5, and severity S | Table 3.8-48 | Each attribute is the highest score among its elements. C is the average of C1 to C5, with the floor of Section 3.8.23.6 (a 5 on C2 or C3 sets C at 4 or more), rounded half up to give S. The consequence governs, and the engineer may raise S one level (Section 3.8.20). | 3.8.20; 3.8.23.5 and 3.8.23.6 |
| Solution rating | Table 3.8-49 | The element scores do not average into a rating. Each one sets a limit on, or a condition for, the credit the solution can take, as stated in the last column. | 3.8.37 |
| Design and construction-stage ratings | Tables 3.8-50 and 3.8-51 | Design elements give Fdes through Table 3.8-81; construction-stage elements decide Fcon and any one-level reduction in S for the stage. | 3.8.38 |
| Post-stabilization rating | Table 3.8-52 | The elements decide whether Fpost is provisional (Fdes + 1), verified (Fdes) or reverts to the current-risk process. | 3.8.39 |
Reading the tables. Every table runs from 1 (lowest risk) to 5 (highest), the same direction as every other scale in the manual. For the solution, design and post-stabilization elements, 1 means the stage leaves the least risk. Where the evidence falls between two descriptions, choose the higher until the field visit or the record settles it, and say so in the reason. Numeric thresholds are indicative values from common practice; where a railroad has its own standard for an element (defect limits, culvert design events, monitoring alarm levels), use the railroad standard and record it.
The trigger elements are grouped by the kind of event. Their levels use the five annual frequency bands of Table 3.8-9, so the score of the element is the trigger rating it would give. Score only the elements that can act on the site’s driving mechanism (Table 3.8-8); the rest are left blank.
| ID | Element and what is measured | 1 Remote: less than 1 in 100 years, or none | 2 Rare: 1 in 25 to 1 in 100 years | 3 Occasional: 1 in 5 to 1 in 25 years | 4 Frequent: 1 in 1 to 1 in 5 years | 5 Acting now: once a year or more | Sources |
|---|---|---|---|---|---|---|---|
| T1 | Storm rainfall: return period of the storm at which the site has responded (defects, slow orders, movement, overtopping) | No response to rainfall on record, or responds only to storms rarer than the 100-year event | Responds to 25- to 100-year storms | Responds to 5- to 25-year storms | Responds to 1- to 5-year storms (for example the 2-year, 24-hour depth) | Responds in most wet seasons, to storms smaller than the 1-year event | NOAA Atlas 14; event and defect history; Section 3.8.23.7 |
| T2 | Antecedent wetness: how often soil moisture or 30-day rainfall reaches the level that preceded past failures (default: 80th soil moisture percentile) | No link between wet periods and the site’s response | Only in exceptionally wet years | In wet years, about 1 in 5 to 1 in 25 | In most wet seasons | Every wet season; the site is wet enough to respond for part of every year | Soil moisture percentile; antecedent rainfall; Section 3.8.23.7 |
| T3 | Flood stage at the toe: return period, or gauge stage, at which water reaches the toe (toe stage) | No water body within reach of the toe, or toe stage above the 100-year flood | Water reaches the toe only in 25- to 100-year floods | Water reaches the toe in 5- to 25-year floods | Water reaches the toe in most high-water years (for example at minor flood stage) | Toe in water at normal high water, or every year | NWS and USGS gauges; FEMA flood profiles; lidar; high-water marks |
| T4 | Scour and channel migration: how often flows erode the bank or toe | No channel within reach, or bank in rock | Armored or straight reach; erosion only in floods rarer than 1 in 25 years | Outside of a bend or below a constriction; bank loss in 5- to 25-year floods | Bank retreating toward the toe in most high-water years; undercutting seen | Channel migrating into the fill; toe lost in recent events | Historic aerials; lidar comparison; gauges; field reconnaissance |
| T5 | Rapid drawdown: how often water stands against the slope and falls faster than the fill can drain | No ponded or flood water against the slope | Water against the slope only in rare floods; slow recession | Water against the slope in 5- to 25-year floods; recession over days | Water against the slope most years; recession within a day | Routine drawdown against the slope (reservoir, tide or controlled release) | Gauge hydrographs; dam operator data |
| T6 | Snowmelt and rain-on-snow: how often melt runoff reaches the site at the response level | Negligible snowpack | Snowpack present; rain-on-snow only in rare years | Rain-on-snow or rapid melt about 1 in 5 to 1 in 25 years | Rain-on-snow or rapid melt most years | Melt runoff over frozen ground reaches the site every spring, and the site has failed in the melt season | NOAA snow data; SNOTEL; Section 3.8.7.8 |
| ID | Element and what is measured | 1 Remote: less than 1 in 100 years, or none | 2 Rare: 1 in 25 to 1 in 100 years | 3 Occasional: 1 in 5 to 1 in 25 years | 4 Frequent: 1 in 1 to 1 in 5 years | 5 Acting now: once a year or more | Sources |
|---|---|---|---|---|---|---|---|
| T7 | Culvert capacity exceedance: return period of the storm the culvert passes without heading up against the fill (culvert capacity storm) | No concentrated flow, or the culvert passes the 100-year event | Capacity 25- to 100-year | Capacity 5- to 25-year | Capacity 1- to 5-year | Heads up or overtops every year | StreamStats or lidar drainage area; culvert inventory; Section 3.5.10 |
| T8 | Blockage events: how often debris, sediment, beavers or ice block the inlet, outlet or ditch | No blockage on record; inlet protected; no debris source | Blockage on record only once, long ago | Blocked in some years; debris or sediment source upstream | Blocked most years; beaver activity in the reach | Blocked now, or every year; active beaver dam at the inlet | Maintenance records; imagery sequence; field reconnaissance |
| T9 | Seasonal groundwater rise: how often groundwater reaches the critical zone of the slope or subgrade | Groundwater well below any critical surface in all seasons | Reaches the critical zone only in exceptionally wet years | Approaches the critical zone about 1 in 5 to 1 in 25 years | Within the critical zone in most wet seasons; perched water on low-permeability layers | At or near the surface every year, or artesian or persistent perched water | Piezometers; boring water levels; seepage; Chapter 2.8 |
| ID | Element and what is measured | 1 Remote: less than 1 in 100 years, or none | 2 Rare: 1 in 25 to 1 in 100 years | 3 Occasional: 1 in 5 to 1 in 25 years | 4 Frequent: 1 in 1 to 1 in 5 years | 5 Acting now: once a year or more | Sources |
|---|---|---|---|---|---|---|---|
| T10 | Frost and thaw weakening of the subgrade: how often frost reaches frost-susceptible soil with water available | Frost does not reach frost-susceptible soil, or the subgrade is non-frost-susceptible | Reaches it only in extreme winters | Reaches it in cold winters, about 1 in 5 to 1 in 25 | Reaches it in most winters | Every winter, with heave or thaw softening recorded | Frost depth and freezing index; USACE frost groups (Table 3.8-39); Section 3.8.8 |
| T11 | Freeze-thaw, root wedging and intense rain on rock faces: how often these are followed by falls | No falls on record after these events, or massive rock | Falls only after extreme winters or storms | Falls after some winters or storms | Falls after most winters or storms | Falls every freeze-thaw season or storm season | Rock fall records; freeze-thaw cycle counts; rainfall intensity; Section 3.8.29 |
| T12 | Wet-dry cycles in plastic clay (shrink-swell): how often desiccation cracking and re-wetting soften the slope or shoulder | Non-plastic soils, or no seasonal moisture change in the active zone | Cracking only in severe droughts | Cracking in dry years, about 1 in 5 to 1 in 25 | Cracking in most dry seasons | Deep cracks open every dry season and soften on re-wetting | Plasticity (Table 3.8-39); drought records; Chapter 2.5 |
| ID | Element and what is measured | 1 Remote or none | 2 Rare | 3 Occasional | 4 Frequent or planned | 5 Acting now | Sources |
|---|---|---|---|---|---|---|---|
| T13 | Change in traffic loading: tonnage or axle load increase relative to what the subgrade has carried | No change; traffic within what the subgrade has carried | Increase unlikely within 25 years | Increase possible within 5 to 25 years | Increase planned within 5 years | Increase in the last few years, and the subgrade is responding (pumping, ballast pockets) | Traffic and tonnage records; Chapter 2.3 |
| T14 | Surcharge at the crest: stockpiles, spoil, new fill, added track or structures | None, and none credible | Possible but unlikely; the land use controls it | Occasional temporary stockpiles or spoil within twice the slope height of the crest | A second track, siding or structure planned within 5 years, or recurring stockpiling | Surcharge at the crest now | Field reconnaissance; aerials; railroad plans |
| T15 | Excavation at or below the toe, or other removal of support | None, and none credible | Unlikely; the land below is controlled | Possible; the land below is open to development | Excavation planned or permitted | Excavation under way or recent, with distress | Field reconnaissance; aerials; permits |
| T16 | Upslope development and drainage changes: runoff redirected toward the right-of-way | None | Minor development, no change in drainage | Increased runoff, managed by drainage works | Runoff concentrated toward the right-of-way | Uncontrolled discharge onto the slope or fill now | Aerials; county GIS; field reconnaissance |
| T17 | Vegetation loss and wildfire upslope or on the slope | Dense, healthy cover | Good cover with minor gaps | Sparse cover, or an older burn upslope | Recent clearing or logging | Burned within the last two years with a storm season ahead | Aerials; fire perimeter data; post-fire debris flow hazard maps |
| T18 | Earthquake shaking: return period of the ground motion at which the site fails or liquefies (Chapter 6.5) | More than 100 years (most sites) | 25 to 100 years | 5 to 25 years | 1 to 5 years | Once a year or more (induced seismicity only) | USGS hazard tools; Chapter 6.5 |
Seismic triggers rarely score above 2 on an annual scale. That does not make them unimportant: the screening elements of Table 3.8-38 decide whether the seismic case must be analyzed and designed for, whatever T is.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| T19a | Design ground motion: peak ground acceleration for the 2,475-year return period, site-adjusted | Less than 0.05 g | 0.05 to 0.10 g | 0.10 to 0.20 g | 0.20 to 0.40 g | More than 0.40 g | USGS seismic design maps; Chapter 6.5 |
| T19b | Liquefaction: factor of safety against liquefaction of saturated loose sands and silts (Chapter 6.5) | No liquefiable soil, or above the water table | FS more than 1.3 in all layers | FS 1.1 to 1.3, or isolated thin loose layers | FS 1.0 to 1.1 in a continuous layer, or FS below 1.0 in isolated layers | FS below 1.0 in a continuous layer, with a free face or sloping ground (lateral spread) | Borings and CPT; Chapter 6.5; Chapter 2.4 |
A score of 4 or 5 on either screening element requires the seismic case in the analysis (Chapter 6.5) and in the design factor of safety element DC2 (Table 3.8-50). Record shaking as a secondary trigger in the narrative.
Each table refines one attribute of Table 3.8-20. The 1, 3 and 5 descriptions of Table 3.8-20 and the 2 and 4 descriptions of Table 3.8-76 are carried into the elements of each attribute, so a desk rating made from Table 3.8-20 alone still agrees with these tables. The other elements are used when the data exist.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| L1.1 | Soil type of the fill, the cut face or the foundation (USCS, ASTM D2487) | Rock, or clean, well-drained sand and gravel | Sand and gravel with some fines; well drained | Silty or clayey sand, low-plasticity silt or clay; moderately drained | Lean clay or silt that softens when wet; poorly drained in places | High-plasticity or organic clay, peat, loess, sensitive or collapsible soil; poorly drained | Soil survey; geologic map; boring logs; Chapters 2.2 and 2.4 to 2.7 |
| L1.2 | Consistency of cohesive soil: undrained shear strength su | Very stiff to hard: more than 2,000 psf | Stiff: 1,000 to 2,000 psf | Medium stiff: 500 to 1,000 psf | Soft: 250 to 500 psf | Very soft: less than 250 psf, or sensitive clay | Borings, vane, CPT, lab tests; Appendix D |
| L1.3 | Density of granular soil: SPT N60 | Dense to very dense: more than 30 | Medium dense: 10 to 30 | Loose: 4 to 10 | Very loose: less than 4 | Very loose, saturated fine sand or silt prone to flow | Borings and CPT; Appendix D |
| L1.4 | Fill type and placement | Engineered, compacted granular fill | Older granular fill with a good record | Mixed fill with some fines | Cinders, end-dumped or loose fill | End-dumped fill over soft ground, with debris or organics | Valuation maps; construction records; borings |
| L1.5 | Frost susceptibility of the subgrade (USACE frost group) | Non-frost-susceptible (NFS) | F1 | F2 | F3 | F4 | Gradation and plasticity tests; Chapter 7.3 |
| L1.6 | Plasticity of clay in the active zone: plasticity index PI | Non-plastic, or PI less than 10 | PI 10 to 20 | PI 20 to 35 | PI 35 to 50 | PI more than 50, with seasonal desiccation cracking | Atterberg limits (Chapter 5.2); Chapter 2.5 |
At the desk L1.1 is usually the only element with data. L1.5 applies to subgrade-driven sites and L1.6 to sites in plastic clay; leave them blank elsewhere.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| L2.1 | Overburden over rock: depth and type of the materials below the fill or cut | Competent rock at or near the surface | Weathered rock over competent rock at shallow depth | Weathered rock or till at moderate depth | Thick till, colluvium or weak shale | Deep weak overburden or colluvium, or a mapped landslide-prone formation | Geologic map; boring logs; lidar |
| L2.2 | Landslide susceptibility of the mapped unit | Low or none | Low to moderate | Moderate | High | Very high, or the site sits in a mapped landslide-prone formation with deep colluvium | State and USGS landslide susceptibility maps |
| L2.3 | Karst and undermining | No soluble rock and no mining | Soluble rock at depth, no features within about half a mile | Sinkholes or mine workings mapped within about half a mile | Karst or mine workings mapped nearby but not under the track | Karst features or mine workings under the track | Karst and mine maps; state geological survey; lidar closed depressions |
| L2.4 | Rock mass structure in cuts: discontinuities relative to the face | No rock cut, or massive rock, or joints dipping into the face | Favorable joints; slight weathering | Random or some adverse joints; moderate weathering | Adverse joints daylighting in the face | Daylighting planes or wedges with past failures, toppling, or clay-filled joints | Geologic mapping of the cut; Section 3.8.29 |
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| L3.1 | Height of the fill or cut | Under 10 ft | Height alone does not give 2 | 10 to 30 ft | Height alone does not give 4 | Over 30 ft | Lidar; track charts |
| L3.2 | Steepness of the steepest representative slope | Flatter than 3H:1V | 2.5H:1V to 3H:1V | About 2H:1V (2H:1V to 2.5H:1V) | Steeper than 2H:1V but not steeper than 1.5H:1V | Steeper than 1.5H:1V | Lidar sections; field measurement |
| L3.3 | Distance from the end of the ties to the crest of the slope | More than 10 ft | 6 to 10 ft | 3 to 6 ft | 1 to 3 ft | Less than 1 ft, or the crest is in the ballast shoulder | Lidar; field measurement |
| L3.4 | Setting: what the fill or cut sits on | Fill or cut on level ground | Low sidehill, natural ground flatter than 5H:1V | Sidehill bench on natural ground of 5H:1V to 3H:1V | Cut with natural ground steeper than 3H:1V above it | Sidehill fill on natural ground steeper than 3H:1V, or a fill across a hollow or old channel | Lidar; valuation and historic maps; Section 3.8.23.2 |
Height keeps the three bands of Table 3.8-20, so the intermediate scores 2 and 4 come from steepness, crest distance and setting. Use the highest element, as Section 3.8.23.4 requires for height and steepness.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| L4.1 | Water against or near the toe | No contributing flow; no water body within about 500 ft | Intermittent ditch flow away from the toe, or a water body 200 to 500 ft away | Ditch or small-stream flow along the toe, or a water body 50 to 200 ft away | Stream within about 50 ft of the toe | Stream or river against the toe, or convergent flow or ponding against the fill | Aerials; National Hydrography Dataset; lidar |
| L4.2 | Mapped flood hazard (FEMA zone) | Outside mapped flood hazard areas (Zone X, unshaded), no flow toward the fill | Outside the 500-year floodplain, local ponding possible | In or near the 500-year floodplain (Zone X, shaded) | In the 100-year floodplain (Zone A or AE) without flow against the fill | In the 100-year floodplain with flow against the fill, in a regulatory floodway, or in a coastal high hazard area (Zone VE) | FEMA National Flood Hazard Layer |
| L4.3 | Channel position and flow attack | No channel | Straight reach, flow parallel to an armored or vegetated bank | Flow along the toe in a straight reach | Outside of a bend, or below a constriction or a bridge | Flow impinging directly on the fill | Aerials; lidar; field reconnaissance |
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| L5.1 | Culvert condition and blockage | Clear and sound | Minor debris, sediment or corrosion; full function | Aging; some section loss or partial blockage | About half blocked, damaged, separated joints, or capacity unknown | Mostly blocked, collapsed, or failed and directing water into the fill | Culvert inspections; field reconnaissance |
| L5.2 | Culvert size relative to the design flow | Passes the design flow without heading up against the fill | Adequate, but aging or with little margin | Capacity not known | Undersized for the design flow | Undersized, with a record of overtopping or ponding against the fill | Culvert inventory; StreamStats; Section 3.5.10 (the frequency itself is T7) |
| L5.3 | Ditches and outlets | Free-draining, with outlet control | Minor sediment or vegetation | Partly obstructed; some sediment | Ditch holding water; outlet eroded or undefined | Ditch blocked or missing; water directed onto the slope; no outlet control | Imagery sequence; field reconnaissance; maintenance records |
| L5.4 | Track and subsurface drainage: subdrains, underdrains and drainage of the track section | Section drains freely; subdrains working | Minor fouling; subdrains working | Fouled shoulders or subdrain condition unknown | Water trapped in the section; subdrain outlets buried | Bathtub section or failed subdrains holding water under the track | Field reconnaissance; GPR; Chapter 2.3 |
| L5.5 | Beaver activity and debris sources | None | Old evidence only | Beaver or debris source in the drainage upstream | Active beaver activity in the reach | Active dam at or near the inlet, or debris jam at the structure | Imagery sequence; field reconnaissance; maintenance records |
L5 records the condition of the drainage. How often the drainage is exceeded is the trigger element T7; the two are scored separately, as Section 3.8.37.1 requires when a solution changes both.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| L6.1 | Recorded failures and repairs at the site | None | No record at the site; landslide-prone formation mapped (L2.2 of 4 or more) | A past repair at the site (berm, drains, riprap, wall) | A documented failure at the site within about 20 years | Repeated documented failures, or repairs that have not held | Railroad records; interviews with track forces |
| L6.2 | Geomorphic evidence in lidar and on site | None | Subdued features that may be old movement | Old lobes or hummocky ground near the site | An old scarp visible in lidar at the site | Fresh or repeated scarps at the site | Lidar hillshade and slope maps; field reconnaissance |
| L6.3 | Mapped instability near the site | None within about a mile | Distant mapped slides | Mapped slides within about half a mile, or instability mapped nearby | A mapped slide adjacent to the right-of-way | A mapped active landslide crossing the right-of-way | USGS landslide inventory; state geological survey |
| L6.4 | Slow orders for a geotechnical cause, more than 12 months ago | None | One, more than 10 years ago | One or two in the last 10 years | Three to five in the last 10 years | More than five in the last 10 years | Slow order history |
| L6.5 | Measured past movement | None measured | Movement measured once, since stopped | Intermittent movement after past events | Measured movement in recent years | Continuing measured movement | InSAR; survey; inclinometer records |
Slow orders in the last 12 months and standing slow orders are scored in the defect rating (D3), not here, so the same order is not counted twice.
The defect elements follow the levels of Table 3.8-10: 1 None, 2 Historic, 3 Present, 4 Recurring, 5 Active. The record and measurement elements (D1 to D4 and D15) are direct evidence of what the track and the ground are doing, so any one of them can set D. The field indicators are read as a pattern (Section 3.8.24.4): D is set at the highest level shown by at least two of them. Each defect is entered with its measurement and its frequency.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| D1 | Recurrence of geometry defects at the site (cross level, profile, alignment, warp) | No defects in the record | A single defect in the record, not repeated | Defects reported more than once, but not returning between surfacing cycles | The same defect returns between surfacing cycles (surfaced two or more times in 12 months at the same location) | Defects return within weeks of surfacing | Geometry car and inspection records; surfacing records |
| D2 | Size of the worst defect relative to the limits | None | Within the railroad’s maintenance tolerance | Beyond the maintenance tolerance but within the FRA limit for the track class | Beyond the FRA limit for the track class; remedial action required under 49 CFR Part 213 | Beyond the limits for any class the line can be reduced to; track removed from service | Geometry car data; 49 CFR Part 213 |
| D3 | Slow orders in the last 12 months for a geotechnical cause | None | A slow order more than 12 months ago, lifted after repair, nothing since | Precautionary slow orders during high water or storms, without defects | A slow order for a defect within the last 12 months | Standing slow order, or track removed from service | Slow order history |
| D4 | Trend of defects over successive geometry runs or inspections | No defects | Decreasing | Steady | Increasing | Accelerating, or recurring after each surfacing | Geometry car data |
These elements record the evidence behind the defect rating. The levels themselves, 1 None to 5 Active, are defined once in Table 3.8-10 (Section 3.8.19); where wording here differs, Table 3.8-10 governs.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| D5 | Tension cracks and scarps | None | Old, healed or vegetated cracks or scarps only | Open cracks with weathered edges, no sign of progress | Fresh cracks with clean edges, or a continuous scarp with a small offset | Cracks widening between visits, or cracks through the shoulder or ballast | Field reconnaissance; photographs with scale (Section 3.8.24.4) |
| D6 | Bulges and toe heave | None | Old lobes with no fresh disturbance | Noticeable bulge, no fresh disturbance | Distinct or growing bulge, or fresh toe heave | Active toe heave, a slumped mass, or a bulge advancing | Field reconnaissance |
| D7 | Displaced trees, poles, fences and structures | None | Isolated old tilted trees with recovered growth | Several curved (pistol-butt) trees | Recently tilted poles or fences, cracked headwalls | Structures being displaced now, or broken utilities | Field reconnaissance |
| D8 | Settlement, sags and ballast pockets | None | Minor shoulder irregularity | A low spot that recurs, with no recent change | Repeated surfacing; ballast pockets | Rapid settlement; track hung or voids under the ties | Field reconnaissance; track forces; GPR |
| D9 | Seepage, piping and water at the toe | None | Damp areas only | Seepage or standing water at the toe; clear water | Persistent seepage carrying fines | Active piping, sinkholes or sand boils | Field reconnaissance; seasonal re-inspection |
| D10 | Erosion and undercutting at the face or toe | None | Minor rills | Gullies, or minor undercutting | Significant undercutting; slope oversteepened | Toe lost; erosion reaching the shoulder | Field reconnaissance; aerials |
| D11 | Loss of shoulder or section | Full shoulder | Slightly narrowed shoulder | Narrowed shoulder, stable | Shoulder narrower than 12 in., with recent loss | Tie ends unsupported | Field reconnaissance; Table 3.8-25 |
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| D12 | Fouled ballast, water between the cribs and pumping | None | Isolated | Recurring after storms | Persistent pumping; fouled ballast | Continuous pumping, with geometry defects returning | Field reconnaissance; GPR; Chapter 2.3 |
| D13 | Scour protection (riprap or revetment) condition | Intact, or not needed | Minor displacement | Gaps, or undersized stone | Significant loss of protection | Protection failed, or absent where flow attacks the toe | Field reconnaissance; underwater or low-water inspection |
| D14 | Retaining structures (soldier pile and lagging and other walls) | None needed, or in good condition | Minor deterioration | Moderate deterioration, minor tilt | Lagging loss, significant tilt or bulging | Wall failing or failed | Field reconnaissance; Chapter 7.1 |
| D15 | Monitoring trend: inclinometers, survey, extensometers or InSAR | No movement beyond instrument precision over at least a year of readings | Movement after a past event that has since stopped | Possible slow movement, less than about 0.1 in. per year, not yet confirmed by successive readings | Confirmed steady movement, about 0.1 to 2 in. per year | More than about 2 in. per year, or accelerating | Instrument and survey records; InSAR; Chapter 5.3 |
D15 is a measurement element and can set D on its own. The movement rates are indicative; where the railroad or the design sets alarm levels for the instruments, the alarm levels govern.
The consequence elements refine Tables 3.8-21 and 3.8-76. Each attribute is the highest of its elements; C1 to C5 are averaged with the floor of Section 3.8.23.6, and the result is the hazard severity S of Table 3.8-15. For cuts and natural slopes above the track, C4 is judged from the volume that would reach the track rather than the fill height.
| ID | Element and what is measured | 1 | 2 | 3 | 4 | 5 | Sources |
|---|---|---|---|---|---|---|---|
| C1.1 | Line and track: what the track is used for | Industry, yard or out-of-service track | Lightly used branch line or siding | Main line with light traffic, or a busy siding | Main line with moderate traffic | Main line with heavy tonnage or high speed; multiple main tracks | Railroad network data; timetable |
| C1.2 | Track class: FRA class of the track at the site | Excepted track or Class 1 | Class 2 | Class 3 | Class 4 | Class 5 or higher | Timetable; 49 CFR Part 213 |
| C2.1 | Train type: passenger and hazardous materials traffic | No passenger or hazardous materials traffic | No passenger trains; hazardous materials limited to infrequent cars | Occasional hazardous materials | Regular hazardous materials traffic, or occasional passenger trains | Passenger trains, or a key route for hazardous materials (AAR Circular OT-55) | Railroad traffic data |
| C3.1 | People and property below and beside the track | Open land on railroad property | Railroad or private land with minor drainage | A road or farmland | A local road, or a few dwellings within reach | A highway, dwellings, occupied buildings, utilities or a critical facility | Aerials; county GIS |
| C3.2 | Water and the environment below and beside the track | None | Minor drainage | A small stream or wetland | A stream with fisheries value, or other regulated water | A river, a drinking-water supply or protected habitat | National Wetlands Inventory; state environmental data |
| C4.1 | Size of failure: fill height, or volume reaching the track from above | Fill under 5 ft; a failure would be shallow | Fill 5 to 10 ft | Fill 10 to 20 ft | Fill 20 to 30 ft | Fill over 30 ft, or a culvert or structure under high fill | Lidar; track charts |
| C5.1 | Redundancy: route around the site | A parallel route on the same corridor | A parallel route nearby, with minor delay | A detour is available | Only a long detour | No detour | Railroad network data |
| C5.2 | Recovery: time to restore service, including access | Within a shift | Within a day | Days | About a week | More than a week, or access is difficult | Access study (Chapter 3.6); repair experience |
The floor applies through C2 and C3: a 5 on C2.1, C3.1 or C3.2 sets C at no less than 4, because a failure that can reach passengers, a hazardous materials release or the public governs regardless of the other attributes.
The solution is rated by rescoring T, L1 to L5 and D as the site would be once the solution works (Section 3.8.37.2). The elements below do not change that arithmetic; they decide how much of it can be credited. A score of 1 means the solution leaves the least risk.
| ID | Element | 1 | 2 | 3 | 4 | 5 | Effect on the rating |
|---|---|---|---|---|---|---|---|
| SOL1 | Mechanism match: does the solution act on the primary trigger, or on the susceptibility it exploits? | Acts on the primary and all contributing mechanisms | Acts fully on the primary mechanism | Acts on part of the primary mechanism | Acts on a contributing mechanism only | Does not act on the primary mechanism | 1 or 2: full rescoring. 3: Fsol no more than one level below Fc. 4 or 5: no reduction in F (Fsol = Fc); only S can change, under Table 3.8-80. |
| SOL2 | Way of reducing risk (Table 3.8-79) | Removes the trigger and increases resistance | Removes or controls the trigger | Increases resistance only | Reduces exposure only (detection linked to operating rules) | Monitoring without an operating response | 1 to 3: rescore T and L as the solution changes them. 4: S may drop one level while the response is in force; F unchanged. 5: no credit. |
| SOL3 | Investigation behind the solution | Subsurface investigation, laboratory testing, analysis and instrumentation | Subsurface investigation, laboratory testing and analysis at the design sections | Limited borings, no analysis | Field reconnaissance only | Desk study only | Caps from Table 3.8-80. 1 or 2: full credit. 3 or 4: at most two levels. 5: at most one level. |
| SOL4 | Dependence on maintenance | No maintenance needed to keep working | Routine inspection only | Periodic maintenance (drainage cleaning, vegetation) | Frequent maintenance; works fail if it lapses | Works fail within a season without maintenance | 3 to 5: full credit only with a maintenance plan in force (Table 3.8-80); otherwise the rating stays provisional (Table 3.8-82). |
| SOL5 | Design life against the planning horizon | More than 50 years | 30 to 50 years | 15 to 30 years | 5 to 15 years | Less than 5 years | 4 or 5: record the date the credit expires and re-rate before it; carry the replacement cost into the life-cycle cost (Section 3.8.40). A solution that leaves the site at High or above is interim either way. |
| SOL6 | Constructability and permitting | No permits; easy access; work outside the track | Minor permits; good access | Standard permits; limited access or track time | Major permits; difficult access; long track windows | Permits uncertain; access needs a new road or barge | Not a rating input. 4 or 5: check the construction-stage rating (Table 3.8-51) and the duration before the solution is preferred. |
| ID | Element | 1 | 2 | 3 | 4 | 5 | Effect on the rating |
|---|---|---|---|---|---|---|---|
| DC1 | Investigation adequacy at the design stage | Full investigation with instrumentation | Borings and laboratory tests at the design sections | Limited borings | Desk study and reconnaissance only | No site-specific data | 1 or 2: full design credit. 3: Fdes no lower than 2. 4 or 5: no design credit beyond the caps of Table 3.8-80. |
| DC2 | Slope design factor of safety for the governing condition (Chapter 6.3) | FS of 1.5 or more static, and the required factors of safety met for rapid drawdown and seismic cases where they apply | FS of 1.5 or more static; other cases not applicable or not yet checked | FS 1.3 to under 1.5 | FS 1.1 to under 1.3 | FS under 1.1 | Fdes 1, 1 (2 if a required case is unchecked), 2, 3, no credit (Table 3.8-81). |
| DC3 | Hydraulic design event for culverts, channels and scour countermeasures | 100-year or larger, with scour checked at the 500-year event | 25- to 100-year | 10- to 25-year | 5- to 10-year | Under 5-year | Fdes 1, 2, 3, 3, no credit (Table 3.8-81). |
| DC4 | Subgrade and track section design (Chapter 2.3) | Meets the criteria for the traffic with margin, with drainage | Meets the criteria, but depends on drainage maintenance | Meets bearing criteria; drainage not addressed | Partly meets the criteria | No subgrade design | Fdes 1, 2, then no design credit for 3 to 5. |
| DC5 | Rock and debris, or subsidence, treatment | All mapped blocks stabilized and catchment verified; or track bridged or relocated over the voids | Scaling, bolting or catchment designed for the design block size and energy; or voids treated and verified | Catchment for smaller blocks than the design block; or voids treated but not verified | Scaling only; or partial treatment | None | Fdes 1, 2, 3, then no credit for 4 and 5 (Table 3.8-81). |
| DC6 | Construction quality assurance planned for the works (Chapter 5.3) | Full-time inspection, testing and as-built records | Regular inspection and testing | Periodic inspection | Contractor quality control only | No inspection | 1 or 2: the works can be accepted (Table 3.8-82). 3: acceptable for maintenance-level work only. 4 or 5: works cannot be accepted; Fpost not credited below Fc until inspection or testing confirms them. |
Where several mechanisms apply, Fdes is the highest among them (Section 3.8.38.1).
| ID | Element | 1 | 2 | 3 | 4 | 5 | Effect on the rating |
|---|---|---|---|---|---|---|---|
| CS1 | Temporary loss of resistance or added load during the work | None; the work is away from the slope and the toe | Minor and brief (light equipment, short trenches outside the slope) | Excavation or equipment within the slope or at the toe, stage designed | Trench through the fill or excavation at the toe, stage checked only by judgment | Excavation or loading on a slope already moving | 1 or 2: Fcon = Fc. 3 to 5: Fcon = Fc + 1, to a maximum of 5 (Equation 3.8-15). |
| CS2 | Protection of operations during the stage | Track out of service for the stage | Slow order with monitoring, and temporary support designed for the stage | Slow order only | Inspection only | None | 1 or 2: S may be lowered one level for the stage (Table 3.8-80). 3 to 5: S unchanged. A stage rated Severe requires 1. |
| CS3 | Duration of the work relative to the trigger season | Days, outside the trigger season | Weeks, outside the trigger season | One season | Through a trigger season | More than a year | 4 or 5: the construction-stage rating applies through a triggering season; show it on the schedule and in the rating record. |
| ID | Element | 1 | 2 | 3 | 4 | 5 | Effect on the rating |
|---|---|---|---|---|---|---|---|
| POST1 | Acceptance of the works: as-built quality assurance and quality control (Chapter 5.3) | Accepted on full records and tests | Accepted on regular inspection and testing | Accepted on periodic inspection | Contractor records only | No records | 1 to 3: Fpost = Fdes + 1, provisional. 4 or 5: not accepted; Fpost not credited below Fc. |
| POST2 | Performance monitoring after construction | Automated, alarmed and reviewed | Periodic instrument readings | Periodic survey or engineer’s inspection | Visual by track forces, with geometry records | None | 1 to 4: can verify the rating. 5: the rating stays provisional. |
| POST3 | Testing by a trigger since completion | Two or more triggering seasons, or events at or above the response level, with no movement | One triggering season or event at or above the response level, with no movement | A full season, but the response level was not reached | Less than one season | None | 1 or 2 (with POST2 of 1 to 4): verified, Fpost = Fdes. 3 to 5: provisional, Fdes + 1. |
| POST4 | Maintenance plan for drainage, vegetation and protection | Scheduled and funded, with records | Scheduled | As needed, from inspection | Reactive only | None | Drainage-dependent works need 1 or 2 to be verified; otherwise they stay provisional (Table 3.8-82). |
| POST5 | Defects and indicators after stabilization | None | Rare, maintenance-level | Occasional | Similar to before stabilization | Increasing | 1 or 2: supports verification. 3: hold the rating provisional and find the cause. 4 or 5: recompute Fc from the new D (Section 3.8.19). |
The ratings of the worked example in Section 3.8.41 are rebuilt below from the element tables. The element scores reproduce the attribute scores of Table 3.8-83.
| Rating | Elements scored | Rating given | Reason |
|---|---|---|---|
| T | T7 = 4 (ponding against the fill recorded about every 3 years) | 4 | Primary trigger; no other trigger element scores higher |
| L1 | L1.1 = 4 (lean clay fill that softens when wet); no data for L1.2 to L1.6 | 4 | Highest element with data |
| L2 | L2.1 = 3 (weathered rock or till at moderate depth, assumed) | 3 | |
| L3 | L3.1 = 3 (22-ft fill); L3.2 = 3 (slopes about 2H:1V, assumed) | 3 | |
| L4 | L4.1 = 4 (creek within about 50 ft of the toe); L4.2 = 4 (100-year floodplain, no flow against the fill) | 4 | |
| L5 | L5.1 = 4 (culvert partly blocked); L5.2 = 5 (ponding against the fill on record) | 5 | Weight 2 (drainage-driven) |
| L6 | L6.1 = 3 (berm placed 15 years ago) | 3 | |
| L and Fg | (4 + 3 + 3 + 4 + 2 × 5 + 3) / 7 = 3.86, rounded to 4; lesser of L and T | Fg = 4 | Equation 3.8-2 |
| D | D1 = 4 (surfaced twice in 12 months); D6 = 4 (bulge forming on the downstream slope) | 4 | Record element at 4, confirmed by a field indicator |
| Fc, S and Rc | Fc from Table 3.8-11; S = 4 as in Table 3.8-83 | Fc = 4; Rc = 16, High | Same result as Table 3.8-83 |
Soil consistency and density bands follow the conventional classes used on boring logs (Appendix D). The frost groups are the USACE groups, F4 being the most frost-susceptible. The track class bands are the FRA classes of 49 CFR Part 213. The flood zones are FEMA’s. The trigger bands are the annual frequency bands of Table 3.8-9 and Table 3.8-14, and the design bands are those of Table 3.8-81. The remaining thresholds (distances, crest offsets, movement rates, plasticity bands and design life) are indicative values chosen to separate the five levels; they are starting points to be calibrated, like the H&H thresholds of Section 3.8.23.7, as each site’s record grows.
The elements are evidence for a rating, not a rating in themselves. Where the element scores and the trigger narrative disagree, one of them is wrong (Section 3.8.18.4): resolve it and write down why. A rating may always be raised one level on engineering judgment (Section 3.8.22.6); it is never lowered below what the element tables give without a written reason.
The ratings in Sections 3.8.18 to 3.8.27 are unchanged. The factors below come from UK monitoring of old clay embankments and cut slopes. Record them in the rating justification, and where several point the same way, use the higher end of the existing likelihood band for the element being rated. They apply to clay fills and clay cuts; they do not apply to rock cuts or granular fills.
| Factor | Points to lower likelihood | Points to higher likelihood | Mechanism affected | Source |
|---|---|---|---|---|
| Vegetation on the slope | Grass or small shrubs | Large high-water-demand trees (oak, poplar) | Grass: delayed deep failure in wet winters. Trees: summer track settlement and shoulder loss | O'Brien (2013), pp. 20–22 |
| Recent tree removal on clay fill | None in the last few years | Clearance within the last one to three winters | Wetting-up, swelling and outward movement in the following winter | O'Brien (2013), p. 22 |
| Plasticity of clay fill | PI below about 20 | PI above about 30 (intermediate PI 30–35, high PI 45–50 in the UK studies) | Seasonal shrink–swell and progressive failure | O'Brien (2013), pp. 20, 29 |
| Bulk permeability of clay fill | About 0.0003 ft/day (10−9 m/s) or less | About 0.014 to 0.14 ft/day (5 × 10−8 to 5 × 10−7 m/s) | Winter rain infiltrates fast enough to raise pore pressure | O'Brien (2013), pp. 25, 27 |
| Soft alluvium or topsoil left under the fill | Fill placed on firm ground | Soft or organic layer at the base | Delayed deep failure through the foundation | O'Brien (2013), Table 3 |
| Ash or ballast at the shoulder | Shoulder flatter than about 1.5H:1V, well vegetated | Oversteepened, dry fine ash at the crest | Shoulder unravelling under traffic, mostly in summer | McGinnity and Saffari (2012), p. 1071 |
Permeability converted from m/s to ft/day (1 m/s = 283,000 ft/day). Tree water demand classes follow the UK NHBC (2003) system with oak and poplar placed in a “very high” class, as in the monitoring studies.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Risk ratings (Sections 3.8.18 to 3.8.47) put sites in order so that money goes first where it does the most good. For rock cuts the established system is the Rock Fall Hazard Rating System (RHRS). Pierson and others developed it in 1990 from earlier work by Brawner and Wyllie (1975) and Wyllie (1987), and Wyllie and Mah summarize it in their Chapter 12. Each category is scored 3, 9, 27 or 81 points, and measured categories fall on a continuous scale between those values. The exponential scale makes the worst sites stand out. The highway system has nine categories. For track, two of them (decision sight distance and roadway width) have no equivalent, and average vehicle risk becomes the share of time a train occupies the section.
| Category | 3 points | 9 points | 27 points | 81 points |
|---|---|---|---|---|
| (a) Slope height | 25 ft | 50 ft | 75 ft | 100 ft |
| (b) Ditch effectiveness | Good catchment | Moderate | Limited | No catchment |
| (c) Exposure (% of time occupied) | 25% | 50% | 75% | 100% |
| (f) Geologic character, case 1: structure | Discontinuous joints, favorable | Discontinuous, random | Continuous, adverse | Continuous, adverse, persistent |
| (f) Geologic character, case 1: friction | Rough, irregular | Undulating | Planar | Clay infilling or slickensided |
| (g) Block size | 1 ft | 2 ft | 3 ft | 4 ft |
| (h) Climate and water | Low precipitation, no freezing, dry | Moderate, short freezing or intermittent water | High precipitation or long freezing or continual water | High precipitation and long freezing |
| (i) Rock fall history | Few falls | Occasional | Many | Constant |
Measured categories score 3x; for example 3H/25 for height in feet. Case 2 (differential erosion) replaces the two case 1 entries where erosion controls the falls.
Equation 3.8-5. Train exposure (adapted from average vehicle risk)
The continuous scores agree with Wyllie and Mah's examples. Their highway example, 7,000 vehicles a day over 0.2 km at 90 km/h, gives an average vehicle risk of 65% (64.8% before rounding); the formula scores that 17, against the 18 read from the RHRS chart. Their sight-distance example (52% of the decision distance) gives 3(120 − 52)/20 = 42, the same as published. Each slope also receives an inspection rating (Urgent, Priority, Observe or Okay), and that rating sets the permissible actions in Wyllie and Mah's Table 12.5. An Urgent or Priority slope may never be assigned no action.
A 60 ft cut over 800 ft of single track carries 30 trains a day averaging 7,000 ft at 40 mph. Each train occupies the section for about two minutes, so trains are present 4.6% of time and the exposure score is low. The cut has limited ditch catchment, continuous adverse joints with undulating surfaces, 2 ft blocks, continual seepage and occasional falls, and rates 123. The ditch, the jointing and the water are the largest contributors. Those are what a ditch widening, scaling or drainage project would change. Low train exposure does not make a cut safe: one block on the rail can derail the next train.
Open the rock fall rating calculator →
RHRS-based scoring of a rock cut along track, with continuous scores for height, train exposure and block size, the category breakdown, and the inspection rating with its permissible actions.
Wyllie and Mah set the rating inside a seven-step program for transportation agencies. The program inventories and rates every slope, picks the highest priorities each year, designs and builds the work under a contract flexible enough for conditions found during construction, updates the database with falls and repairs, and re-rates. Because conditions get worse over time and nobody can re-rate hundreds of cuts every year, they add an annual inspection of the higher-priority slopes. Each inspected slope gets an inspection rating, and the rating limits which actions are allowed.
| Inspection rating | Typical condition | Permissible actions |
|---|---|---|
| Urgent | Obvious recent movement or falls; a kinematically feasible block large enough to be a hazard; weather working against stability; failure possible within months | Limit service and work within one month, or follow-up inspection |
| Priority | Likely movement since the last inspection of a block large enough to be a hazard; failure possible within about two years | Work in the current year, follow-up inspection, or work in one to two years |
| Observe | Possible recent movement, no imminent instability | No action; check specific conditions at the next inspection |
| Okay | No evidence of movement | No action |
Urgent and Priority slopes may not be assigned no action.
| Reinforcement | Rock removal | Protection |
|---|---|---|
| Rock bolts and dowels | Resloping | Ditches |
| Tied-back walls | Trimming | Mesh |
| Shotcrete | Scaling | Catch fences |
| Buttresses, including shot-in-place | Warning fences | |
| Drainage | Rock sheds and tunnels |
Where the face is steep and the toe is close to the track, there is no room for a ditch or barrier, so removal, bolting or mesh become the practical choices.
Three cuts on one subdivision were rated with the calculator at the same train traffic. Cut A is the worked example. Cut B is 100 ft high with no catchment, 3 ft blocks and constant falls. Cut C is 35 ft high with a good ditch, random jointing, moderate climate, 1 ft blocks and few falls. The exponential scoring separates them sharply. Cut B scores about eight times Cut C, although none of its categories is more than 27 times Cut C's. That separation is what the system is designed to produce.
| Cut | Score | Rank |
|---|---|---|
| Cut B: 100 ft, no catchment, constant falls | 334 | 1 |
| Cut A (default) | 123 | 2 |
| Cut C: 35 ft, good ditch, few falls | 42 | 3 |
Paraphrased from these documents in the reference library.
Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.
The trigger rating T (Table 3.8-9) and the frequency index F (Table 3.8-14) are both defined by annual frequency: 1 in 5, 1 in 25 and 1 in 100 years mark the band edges. Programming decisions, however, are made over a period: a five-year capital plan, a 50-year service life. The conversion between the two is the probability of at least one event in n independent years. It is the same arithmetic behind the seismic design levels quoted in the library. Duncan, Wright and Brandon tabulate peak rock accelerations for a 10% chance of exceedance in 50 years (the 500-year level) and a 2% chance (the 2,500-year level). The Navy's soil dynamics handbook uses a 10% chance in 100 years (950 years). Hearn's semi-quantitative risk matrix (Section 3.8.34) rates the probability of a landslide over a 20-year road design life, and the GEO factors of safety in Look (Section 3.8.35) are set for a 10-year return period rainfall. Each ties its probability to a stated period or return period, and a rating should do the same.
Equation 3.8-6. Annual probability, exposure and design return period
Tdesign = 1 / [1 − (1 − Ptarget)1/n]; several independent sites or triggers: P = 1 − Π(1 − pi)n
T is the return period (average recurrence interval) and n the exposure period in years. The binomial form treats each year as one independent trial; the Poisson form treats events as random in time. They agree closely once T is more than a few years. The calculator also gives the chance of exactly 0, 1, 2, 3 or 4 events and the band level for the trigger or failure frequency.
| Band edge, T / F levels | In 1 year | In 5 years | In 25 years | In 50 years |
|---|---|---|---|---|
| 5 / 4 (1 per year or more) | 100.0% | 100.0% | 100.0% | 100.0% |
| 4 / 3 (1 in 5) | 20.0% | 67.2% | 99.6% | 100.0% |
| 3 / 2 (1 in 25) | 4.0% | 18.5% | 64.0% | 87.0% |
| 2 / 1 (1 in 100) | 1.0% | 4.9% | 22.2% | 39.5% |
An event at the 1-in-5 edge is about 67% likely within a five-year program; one at the 1-in-100 edge is still about 40% likely within a 50-year life.
| Design level | Return period as quoted | Calculator |
|---|---|---|
| 10% in 50 years (Duncan, Wright and Brandon, Table 10.2) | 500-year | 475 years |
| 2% in 50 years (same table) | 2,500-year | 2,475 years |
| 10% in 100 years (Navy MIL-HDBK-1007/3) | 950-year | 950 years |
The quoted values are the rounded forms of the exact 475, 2,475 and 950 years.
The site of Section 3.8.41 rated its trigger T = 4 because water has ponded against the fill about every 3 years. Alternative A replaces the culvert with one sized for the 100-year event. The question is what those return periods mean over the periods that matter: a five-year program for ranking the site, and a 50-year service life for the new culvert.
| Variable | Value | Description |
|---|---|---|
| Tpond | 3 years | Return period of ponding against the fill (trigger T = 4, Table 3.8-9) |
| n | 5 years | Program cycle used for ranking |
| Tdes, N | 100 years; 50 years | Design event and service life of the new culvert |
| T10 | 10 years | A storm in the level 3 trigger band, still able to reach the site |
The ponding trigger has an 86.8% chance of reaching the site in a five-year program (1.67 events expected); a 100-year culvert still has a 39.5% chance of being exceeded in 50 years; and a 10-year storm has a 41.0% chance in any program.
The first result is what Table 3.8-9 means by a trigger the site will meet before most programs could fix it. The new culvert lowers T to 1 but does not remove the trigger, and storms of the level 3 band still arrive often enough that drainage maintenance remains part of the rating (Section 3.8.39).
Open the trigger probability calculator →
Annual probability, chance of one or more events in an exposure period, the number of events, the return period for a target chance in a design life, and the band level of Tables 3.8-9 and 3.8-14.
A single Forming site (1 in 25 years) has an 18% chance of failing within a five-year program. A subdivision with many such sites is a different matter. If their failures are independent, the chance that at least one of them fails in the program rises quickly with the number of sites. This is why corridor budgets need a reserve for emergency repairs even when every individual site is rated Forming or below. The corridor screening calculator (Section 1.1.15) applies the same rule to a hazard register.
| Sites N | Each 1 in 25 years (F = 3 edge) | Each 1 in 100 years (F = 2 edge) |
|---|---|---|
| 1 | 18.5% | 4.9% |
| 5 | 64.0% | 22.2% |
| 10 | 87.0% | 39.5% |
| 20 | 98.3% | 63.4% |
Sites that share a trigger (one storm over the whole subdivision) are not independent; their failures cluster in the same event, so the chance of several failures together is higher than this table implies.
The figure plots the chance of at least one event against the exposure period for the three band edges. The curves rise steeply over the first few years and then flatten. Most of the benefit of fixing a Frequent or Emerging site is gained by fixing it soon.
Paraphrased from these documents in the reference library.
Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.
Ground hazard ratings combine probabilities all the time: a trigger and a susceptible slope, a failure and a train arriving before it is found, a detector that works or does not. The rules for combining them are few, but applying them in the wrong order gives answers that are off by an order of magnitude. This section sets out the notation and rules used in the manual and shows the one rule most often missed in practice, Bayes’ theorem.
| Symbol | Name | Meaning in this manual |
|---|---|---|
| P(A) | – | Probability of event A, from 0 (impossible) to 1 (certain) |
| Ā | complement | Not A; P(Ā) = 1 − P(A) |
| A ∪ B, A ∩ B | union, intersection | A or B (or both); A and B |
| P(A | B) | conditional probability | Probability of A given that B has happened |
| μ, σ | mu, sigma | Mean and standard deviation of a population or distribution |
| x̄, s | – | Mean and standard deviation of a sample (test results) |
| COV = σ/μ | coefficient of variation | Scatter relative to the mean (Table 3.9-9) |
| λ | lambda | Rate of events per year, or per mile per year |
| T, p = 1/T | – | Return period (years) and annual probability (Section 3.8.30) |
| β | beta | Reliability index: distance from the mean to failure in standard deviations |
| Φ(z) | Phi | Standard normal cumulative probability; Pf = Φ(−β) |
| α | alpha | Significance level (for example 0.05 for 95% confidence); also the Gumbel scale parameter |
| χ² | chi-squared | Goodness-of-fit statistic (Section 3.8.33) |
| tα, n−1 | Student’s t | Multiplier for confidence limits from n tests (Table 3.8-64) |
Equation 3.8-7. Addition, multiplication and total probability
Multiply probabilities only along a chain of events (a trigger, then a failure, then a train on it), and only after making each one conditional on the event before it. Add only for events that cannot happen together, or subtract the overlap. Most errors come from multiplying events that are not independent, such as rainfall and high groundwater at the same site.
Equation 3.8-8. Bayes’ theorem: updating a probability with new evidence
P(Bi) is the prior probability (before the evidence), P(A | Bi) the likelihood of the evidence if Bi is true, and P(Bi | A) the updated (posterior) probability.
Bayes’ theorem is how a rating should change when new evidence arrives. A detector trip, a tension crack found on patrol, an inclinometer reading or a borehole that does not find the karst void are all evidence with known or estimable reliability. The updated probability depends on how common the condition was before the evidence, not only on how good the evidence is: a reliable test for a rare condition still produces mostly false alarms, as Example 3.8-8 shows. Conversely, a clean inspection of a site with a high prior probability of instability lowers that probability less than intuition suggests if the inspection would often miss the early signs.
An event tree follows a hazard from its initiating event to its consequence through a series of branches, each with a conditional probability: for a rock cut, rock reaches the track, the rock is large enough to derail a train, the rock is not detected, and a train arrives before the track is cleared. The annual probability of a derailment is the annual rate of the initiating event times the product of the conditional probabilities along the branch. Because the branches multiply, the weakest assumption controls the answer; show the tree in the report so that the reviewer can see which branch probability carries the result, and test it at half and double its value, as for the life-cycle cost (Section 3.8.40). Fault trees run the other way, from a top event back to the combinations of causes (AND and OR gates) that could produce it, and suit detector, signal and drainage systems with several components.
A Class I railroad located in Oregon protects a 0.4-mi rock cut with a slide detector fence wired to the block signals. A trip drops the signals to stop, and the next train must proceed at restricted speed while the track is inspected. Train crews and dispatchers complain that most trips turn out to be nothing. The rock cut is being rated, and the engineer must say how much protection the fence actually gives, how often a trip is real, and whether reducing false trips is worth paying for.
| Variable | Value | Description |
|---|---|---|
| n | 60 storm days a year | Days with heavy rain, freeze-thaw or high wind, when rockfall and false trips occur |
| P(R) | 0.02 per storm day | Chance that rock reaches the track on a storm day (from the rockfall log) |
| P(T | R) | 0.95 | Chance the fence trips when rock reaches the track (detection rate) |
| P(T | R̄) | 0.05 | Chance of a false trip on a storm day with no rock (trees, snow load, animals, broken wire) |
| P(T | R̄)new | 0.01 | False-trip rate after replacing the wire and clearing the trees |
About 28% of trips are real rockfalls today; cutting false trips to 1% makes about 66% real, without changing how many real rockfalls are caught.
The fence works: it catches about 95% of the rockfalls that reach the track, leaving roughly one undetected rockfall in 17 years, and that residual figure, not the trip count, is what the rating should carry as the likelihood of a train meeting rock. The complaint from the crews is also correct: with rockfall rare and false trips common, most trips are false even though the fence is a good detector. That is Bayes’ theorem at work, and it is the same reason a screening test for a rare condition gives many false positives. The risk is behavioral: when most trips are false, crews start to treat a trip as a nuisance. Every trip must still be handled as real, and the fence should be maintained to keep the false-trip rate low, because trust in the alarm is part of the protection. Cutting the false-trip rate from 5% to 1% roughly doubles the share of trips that are real and saves about 2.4 restricted-speed inspections a year, which can be set against the maintenance cost in the life-cycle comparison (Section 3.8.40). Record the detection rate and the false-trip rate from the signal logs; they are the inputs that make this calculation site-specific.
Open the detector and inspection evidence (Bayes) calculator →
For railroad work: Treat a probability in a rating as a statement about the evidence available when it was made. When an inspection, a monitoring reading or a detector record arrives, update it explicitly (Eq. 3.8-8) and record the prior, the evidence and the result in the rationale (Section 3.8.43). Keep detector logs that separate real trips from false ones; without them the reliability of the protection cannot be stated.
Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 2 (Sections 2.3 and 2.4, statistical independence and conditional probability, including Bayes’ theorem); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (Greek alphabet; probability definitions and theorems).
Most ground hazard data are counts and extremes: rockfalls per mile per year, washouts per decade, the largest daily rainfall or river stage in each year. Each kind of data has a distribution that fits it and a way of turning the record into the annual probabilities used in the ratings. Table 3.8-63 lists the distributions that cover nearly all ground hazard work.
| Distribution | Use in risk assessment | Mean; variance | Notes |
|---|---|---|---|
| Normal (Gaussian) | Sums of many small effects: factor of safety from many parameters; averages of test results | μ; σ² | Can go negative, so a poor model for strengths with high COV |
| Lognormal | Strengths, permeability, settlement; any positive quantity that is a product of factors | exp(λ + ζ²/2); see Eq. 3.9-4 | Used for the lognormal reliability index in Section 3.9.15 |
| Binomial | Number of years with an event in n years; number of sites that fail out of a group | np; np(1 − p) | The 1 − (1 − p)n form of Section 3.8.30 |
| Poisson | Number of events in a time or length: rockfalls, washouts, sinkholes per mile per year | λt; λt | Mean equals variance; check for clustering (variance much larger than the mean) |
| Exponential | Time between Poisson events; time to the next failure | 1/λ; 1/λ² | Memoryless: a long quiet period does not make the next event “due” |
| Gumbel (Extreme Value Type I) | Annual maximum rainfall, flood flow or stage | u + 0.5772/α; 1.645/α² | Basis of the frequency factor in Appendix F; Eq. 3.8-10 |
| Weibull (Extreme Value Type III) | Minimum values and lifetimes: weakest link, time to deterioration of an asset | depends on shape k | Shape k < 1: early failures; k > 1: wear-out |
| Beta | Bounded quantities: a probability or proportion estimated from judgment; PERT cost and duration | depends on two shape parameters | Three-point (low, most likely, high) estimates of cost and duration |
Equation 3.8-9. Poisson distribution of event counts
λ = rate (events per year, or per mile per year with t in mile-years); k = number of events. The same form applies along the track: with λ per mile, t becomes the length of track considered. Events must be independent; storms that cause several rockfalls at once break this assumption, so count storm events rather than individual rocks if they cluster.
A record of N events in t years gives λ ≈ N/t. A short record gives a rough rate: for N = 3 the 90% confidence range on the true rate is about 0.8/t to 7.8/t, so three events in ten years is consistent with anything from one in twelve years to almost one a year. Report the range, not just the point value, and see Section 3.8.33 for the case of no events at all.
Equation 3.8-10. Gumbel (Extreme Value Type I) distribution of annual maxima
x̄ and s are the mean and standard deviation of the annual maxima (method of moments). xT is the value with return period T. The constants 1.2825 = π/√6 and 0.4500 = 0.5772/1.2825 come from the Euler constant 0.5772. For flood flows at a gauge, USGS Bulletin 17C (Log-Pearson Type III) is the standard (Section 3.5.12); Gumbel is a quick check and suits rainfall depths and river stages.
For example, 25 years of annual maximum 24-hour rainfall at a gauge near a cut with mean 3.2 in. and standard deviation 0.9 in. give α = 1.425 in.−1 and u = 2.80 in., so the 25-year value is 2.80 + 3.20/1.425 = 5.0 in. If the cut has responded at 4.5 in. (its response level, Section 3.8.23), that depth has a return period of about 12 years and the trigger rates T = 3 (Table 3.8-9).
A Class I railroad located in Pennsylvania has a 6-mile segment of rock cuts along a river. The maintenance records show 14 rockfalls that reached the track in the last 10 years, 6 of them in mile 3 (Figure 3.8-44). The segment is being rated for a rockfall program. The engineer must turn the counts into annual probabilities, decide whether mile 3 is genuinely worse than the rest or just unlucky, and assign the frequency index F of Table 3.8-14.
| Variable | Value | Description |
|---|---|---|
| N | 14 rockfalls | Rockfalls onto the track in the record |
| t | 10 years | Length of the record |
| L | 6 miles | Segment length |
| N3 | 6 rockfalls | Rockfalls in mile 3 |
| Model | Poisson | Rockfalls independent and random in time and along the segment |
The segment averages 1.4 rockfalls a year (75% chance of at least one in any year). Mile 3 rates F = 4 and the rest F = 3, provided field mapping confirms a physical reason for mile 3.
The counts show a real hazard with a 75% annual chance of rock on the track somewhere in the segment, and about one year in six with three or more. Mile 3 stands out, but six events in one of six miles would happen by chance about one time in five, so the statistics alone cannot justify spending the program on it. The decision should rest on the field evidence: if mile 3 has an adverse joint set, overhangs, a steeper or higher face, or a ditch too narrow to catch what falls (Section 3.8.29), the split rating of F = 4 for mile 3 and F = 3 for the rest is justified and mile 3 goes first. If the cuts look alike, rate the segment uniformly and keep counting; another five years of records will separate a real hot spot from a run of bad luck. Rates per mile also suit the exposure calculations of Section 3.8.30: the Poisson form there (Pn ≈ 1 − e−n/T) is Eq. 3.8-9 with k = 0.
Open the hazard event rate and hot spot (Poisson) calculator →
For railroad work: Keep the incident log by milepost and date, and record each rockfall, washout or sinkhole even when it causes no delay; without that log the frequency index is a guess. Count storm events where events cluster, compare each mile with the segment average before declaring a hot spot, and check the statistics against the field evidence before moving money. Convert rates to the band levels of Tables 3.8-9 and 3.8-14 with the arithmetic of Section 3.8.30.
Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 6 (Poisson distribution, including spatial distributions), Ch. 7 (exponential, lognormal, beta and extreme-value distributions); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (binomial, normal and Poisson distributions).
Risk assessments are built on small data sets: a handful of strength tests, a few years of monitoring, a failure record with few or no failures in it. Small samples give means and rates that are themselves uncertain. This section gives the tools to state that uncertainty, to decide how many more tests are worth doing, to interpret a record with no events, and to check whether an assumed distribution fits the data.
Equation 3.8-11. Confidence limits on a mean from n tests (Student’s t)
x̄, s = sample mean and standard deviation (n − 1 in the denominator of s); t from Table 3.8-64. A one-sided 95% lower limit on the mean is the “cautious estimate of the mean” used in limit state codes for properties that govern over a large volume of ground. For a property that governs locally, use a lower fractile of the individual values instead, such as x̄ − s or x̄ − 1.645 s.
| Degrees of freedom n − 1 | One-sided 90% (t0.10) | One-sided 95% (t0.05), two-sided 90% | Two-sided 95% (t0.025) |
|---|---|---|---|
| 1 | 3.078 | 6.314 | 12.706 |
| 2 | 1.886 | 2.920 | 4.303 |
| 3 | 1.638 | 2.353 | 3.182 |
| 4 | 1.533 | 2.132 | 2.776 |
| 5 | 1.476 | 2.015 | 2.571 |
| 6 | 1.440 | 1.943 | 2.447 |
| 7 | 1.415 | 1.895 | 2.365 |
| 8 | 1.397 | 1.860 | 2.306 |
| 9 | 1.383 | 1.833 | 2.262 |
| 10 | 1.372 | 1.812 | 2.228 |
| 15 | 1.341 | 1.753 | 2.131 |
| 20 | 1.325 | 1.725 | 2.086 |
| 30 | 1.310 | 1.697 | 2.042 |
| ∞ (normal z) | 1.282 | 1.645 | 1.960 |
With two or three tests t is so large that the lower limit is often meaningless, which is the statistical reason for testing each layer that matters at least five or six times (Chapter 5.2).
Equation 3.8-12. Number of tests for a required precision of the mean
E = acceptable half-width of the confidence interval, in the units of the property; s from the tests so far or from a published COV (Table 3.9-9) times the expected mean. Because t depends on n, solve by trial. Halving E multiplies the number of tests by about four.
Equation 3.8-13. Upper confidence bound on an event rate when none has been observed
m = number of independent trials, such as site-years or structure-years of record. The approximation is the “rule of three.” It treats every site-year as alike; a group that mixes high and low hazard sites can hide a few bad sites behind many good ones.
No failures in a record does not mean a probability of zero. A site with 20 years of quiet history can still have a 1 in 7 annual chance of failure at 95% confidence (3/20), which is a frequency index of F = 3 (Table 3.8-14) on the record alone. Field evidence is what moves it lower.
Before rates or extreme values are extrapolated, check that the assumed distribution fits the record. The chi-squared test groups the data into k classes, compares the observed counts Oi with the counts Ei expected from the fitted distribution, and computes χ² = Σ(Oi − Ei)²/Ei. The fit is rejected at significance α if χ² exceeds the tabulated value for k − 1 − r degrees of freedom, where r is the number of parameters estimated from the data; keep Ei at 5 or more by merging classes. The Kolmogorov–Smirnov test compares the cumulative curves directly and works better for the small samples common in geotechnical work. A quick graphical check is to plot the data on probability paper (normal, lognormal or Gumbel): a straight line supports the model, and curvature at the tail warns against extrapolating far beyond the record. For Poisson counts, a variance much larger than the mean (for example, counts by year of 0, 0, 5, 0, 1, 0, 6) indicates clustering by storm, and the count should be by storm event.
Monitoring data in a risk assessment are usually fitted with a straight line: settlement against log time, inclinometer displacement against date, crack width against season. Least squares gives the slope and intercept; the standard error of the slope gives its confidence interval (t with n − 2 degrees of freedom), and a slope whose interval includes zero has not been shown to be a trend. Extrapolating a fitted line to a future date carries a prediction interval that widens with distance from the data, so a forecast of when movement will reach an action level should be stated with its range (Chapter 4.5, the observational method).
A Class I railroad located in Mississippi is rating a 22-ft embankment on a soft clay foundation for a speed increase. Six unconsolidated-undrained (UU) triaxial tests on the foundation clay are available (Figure 3.8-45). The railroad’s records show no failures in 25 years on 48 embankments of similar height on the same formation. The engineer must state the design strength with its uncertainty, decide whether more testing is needed, and say what the clean failure record actually proves.
| Variable | Value | Description |
|---|---|---|
| su | 1,150; 980; 1,320; 870; 1,060; 1,240 psf | UU test results, n = 6 |
| E | ±10% of the mean | Required precision of the mean |
| Confidence | 90% two-sided (precision); 95% one-sided (lower limit) | Confidence levels chosen for the rating |
| m | 48 fills × 25 years = 1,200 fill-years | Exposure in the failure record, with zero failures |
Mean 1,103 psf (COV 15%); use 966 psf as the 95% lower limit on the mean; three more tests would pin the mean within ±10%. The clean record limits the annual failure rate of similar fills to about 1 in 400 or less, at 95% confidence.
Six tests give a mean of 1,103 psf, but with six results the true mean could reasonably be as low as 966 psf, and that is the value to carry into the stability check for the speed increase. It is close to the mean minus one standard deviation (936 psf) recommended by GEC 5 (Section 3.9.15), but the two measure different things: the confidence limit describes uncertainty in the average strength along the failure surface, which governs a large slide, while the mean minus one standard deviation covers the scatter of individual values, which matters for a short, local failure. Three more tests would narrow the uncertainty enough to justify a design strength nearer the mean; at a few hundred dollars a test against a berm or a slower speed, that is usually worth doing.
The clean record is evidence, but weaker evidence than it looks. With 1,200 fill-years and no failures, the true annual failure rate could still be as high as about 1 in 400 at 95% confidence (the “rule of three”), which is frequency index F = 1 (less than 1 in 100 years, Table 3.8-14) for the group. It does not prove that this embankment, under faster and heavier traffic, will behave the same; it shows that similar fills under past loading have rarely failed. Use it as the prior in a Bayesian update (Section 3.8.31) and let the site-specific strength and stability analysis carry the rating.
Open the small data set confidence and number of tests calculator →
For railroad work: State design parameters with their number of tests and confidence limits, not as single values, and report any failure rate with its record length. When a client cites a clean history as the reason not to act, convert it to an upper bound with Eq. 3.8-13; the exposure of the record, not the absence of failures, is what decides how much it proves. Combine these results with the Taylor series probability of failure in Section 3.9.15.
Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 9 (sample statistics, interval estimation and the t-distribution), Ch. 10 (chi-squared and Kolmogorov–Smirnov goodness-of-fit tests), Ch. 11 (linear regression and confidence intervals for regression coefficients); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (tables of the t, χ² and normal distributions).
Sections 3.8.19 to 3.8.21 rank sites by R = F × S. Hearn's Slope Engineering for Mountain Roads sets out two published semi-quantitative systems for road slopes that do the same job and make a useful cross-check. Both follow the definitions of Varnes and of the Australian Geomechanics Society. Risk combines the hazard (its magnitude and probability) with the value of the assets exposed and their vulnerability, the degree of loss if the hazard occurs. The GHRM severity S folds value and vulnerability into one scale. Hearn keeps them separate, so a site where the rankings disagree usually points to a judgment about consequence that deserves a second look. Hearn is explicit that neither system gives absolute risk; they are for recording slopes and putting stabilization work in order.
| Component | 0 | 1 | 2 | 3 |
|---|---|---|---|---|
| Magnitude M | – | Small: shallow, up to about 650 cu yd | Moderate | Large: deep, about 6,500 cu yd or more |
| Probability in a 20-year design life P | Not expected | Possible | Expected | Definite |
| Value of elements at risk Va | – | Slope works and ditch | Slope works, ditch and up to half the formation width | Whole formation and adjacent structures |
| Vulnerability Vu | No effect | Deformation or blockage | Partial loss | Total loss |
Relative risk R = M × P × Va × Vu, 0 to 81. Hearn's road terms (side drain, carriageway) are given here as their track equivalents.
| Asset value class | Vulnerability high | Moderate | Low |
|---|---|---|---|
| 1: heavy traffic, strategic access, buildings in the hazard area, or access lost over 3 days | 5 | 4 | 3 |
| 2: moderate traffic or access, buildings on the margin, access lost 1 to 3 days | 4 | 3 | 2 |
| 3: light traffic, network only, access lost under 1 day | 3 | 2 | 1 |
Entries are the loss value. Risk number = loss value × probability level: 5 high (active indicators, or occurrence at least every 2 years), 3 moderate (landslide morphology or previous movement; periodic, every 2 to 5 years), 1 low (no evidence of movement). Ranks: 20 to 25 Very High, preventative works immediately; 10 to 15 High, preventative works in the following dry season; 5 to 9 Moderate, monitoring; 1 to 4 Low, no action.
Hearn's own illustration of Table A4.1 compares two slides on one road. Put in railroad terms, a small slide below the track is undermining a retaining wall, and a large slide above the track could bury it. The cross-check asks which carries more risk, and whether the answer agrees with the F × S ranking.
| Variable | Value | Description |
|---|---|---|
| M | 1 (slide 1); 3 (slide 2) | Magnitude of the failure |
| P | 2; 1 | Probability of failure |
| Va | 3; 3 | Value of the asset affected |
| Vu | 3; 1 | Vulnerability: 3 where support is removed, 1 where the track is only blocked |
The small slide below the track scores 18 and the large slide above it scores 9: the smaller failure carries twice the risk, because it removes support while the larger one only has to be cleared.
The same reasoning runs through Table 3.8-15, which places loss of track support among the most severe consequences, and through the rule of Section 3.8.20 that the consequence governs. In Hearn's field example, cutting a failed slope back to the dip of the bedding lowered its score from 18 to 12, not lower, because bedding-plane sliding was still possible and tension cracks were still opening.
The three scenarios Hearn uses for Table D1.3 reproduce in the calculator: a moderately likely slide above a busy road scores 15 (High); a wall being undermined by seepage on the only access to a hospital scores 25 (Very High); and a debris flow with buildings in its path but no sign of activity scores 5 (Moderate).
Open the landslide risk score calculator →
Hearn's Table A4.1 relative risk (magnitude, probability, value and vulnerability) and Table D1.3 risk number with its rank and action, for any number of sites, sorted for comparison with the F × S ranking.
| Example | Hearn | Calculator |
|---|---|---|
| Table A4.1: small slide undermining wall foundations | 18 | 18 |
| Table A4.1: large slide blocking the road from above | 9 | 9 |
| Table D1.5 scenario 1: slide above a road carrying over 800 vehicles a day | 15, High | 15, High |
| Table D1.5 scenario 2: retaining wall failure, access to a hospital | 25, Very High | 25, Very High |
| Table D1.5 scenario 3: debris flow, buildings in the hazard area | 5, Low (as printed) | 5, Moderate |
Hearn's Table D1.5 lists scenario 3 as Low, but a risk number of 5 falls in the 5 to 9 Moderate range of Table D1.3; the calculator follows Table D1.3.
| Hearn (Table D1.3) | Description | Closest GHRM level (Table 3.8-14) |
|---|---|---|
| High (5) | Adverse structure, seepage, toe erosion, fresh scarps, bulges or cracks; occurrence at least every 2 years | F = 4 or 5 (Emerging or Occurring) |
| Moderate (3) | Landslide morphology but no visible movement; previous movement; periodic occurrence every 2 to 5 years | F = 2 by evidence (Dormant); F = 4 by frequency |
| Low (1) | No evidence of movement, no sources, stable founding conditions | F = 1 (Inactive) |
Hearn's moderate level mixes evidence of past movement with a frequency of 2 to 5 years, which the GHRM scales keep apart. A site rated by frequency and one rated by morphology can therefore land in the same Hearn level but in different F levels.
Paraphrased from these documents in the reference library.
The frequency index asks how often a site will fail; design asks how often is acceptable. Wyllie and Mah point out that probabilistic design needs accepted ranges of probability of failure, just as deterministic design has accepted factors of safety, and they reproduce Whitman's chart of annual probability of failure against lives lost for a range of engineered works. Look adds that a probability is easier for owners and other disciplines to understand than a factor of safety. He also notes that a higher factor of safety does not by itself mean a lower probability of failure (his example compares 1.3 and 1.4), and that existing and new slopes must be judged by different criteria. Hearn quotes the Norwegian national guidelines, which set a maximum annual probability of failure for each consequence class, and cautions that the approach needs good records of the triggering events. This section brings those benchmarks together and connects them to the factor of safety through the reliability method of Section 3.9.15.
Equation 3.8-14. From factor of safety to annual and lifetime probability
pannual ≈ Pf / Tc; Plife = 1 − (1 − pannual)n
Pf is the probability that F is below 1.0 under the condition analyzed (for example, the 10-year storm water level), with the most likely factor of safety F and its coefficient of variation VF from Section 3.9.15. If failure is credible only when that condition occurs, dividing by its return period Tc gives a first estimate of the annual probability. Conditions more severe than the one analyzed add to it, so the estimate is a lower bound unless they are analyzed too.
| Source | Situation | Probability of failure |
|---|---|---|
| Norwegian guidelines (Nilsen 2000, in Hearn Table C3.5), annual | Consequence class 1 minor / 2 medium / 3 major | 10−2 / 10−3 / less than 10−4 |
| Skipp (1992), in Look Table 10.14, annual, rock slopes | Catastrophic / major / moderate / minor failure | 1 × 10−4 / 5 × 10−4 / 1 × 10−3 / 5 × 10−3 (minor: unmonitored permanent urban slopes with free access) |
| Santamarina and others (1992), in Look Table 10.15 | Existing large highway cut, no potential life loss, minor costs | 1 to 2 × 10−2 (under 10−2 for a new cut) |
| Acceptable in most cases, no potential life loss / acceptable for all slopes, potential life loss / unnecessarily low | 10−3 / 10−4 / under 10−5 | |
| Whitman (1984), in Wyllie and Mah Figure 1.11, annual | Closely managed mine slopes, little risk to life / dams with several hundred lives at risk | 10−1 to 10−2 / 10−4 to 10−5 |
| AGS (2000), in Look Table 10.13, annual risk of loss of life | Existing slope: person most at risk / average / new slope: person most at risk / average | 10−4 / 10−5 / 10−5 / 10−6 |
The AGS values are tolerable risks to an individual's life, not probabilities of slope failure; the individual risk is the failure probability multiplied by the chance that the person is present and is killed.
| Economic risk | Risk to life negligible | Low | High |
|---|---|---|---|
| New slopes: negligible | over 1.1 | 1.2 | 1.4 |
| New slopes: low | 1.2 | 1.3 | 1.5 |
| New slopes: high | 1.4 | 1.5 | 1.6 |
| Existing slopes (any economic risk) | over 1.1 | 1.2 | 1.3 |
A new main-line fill slope is analyzed for the 10-year storm water level and gives a most likely factor of safety of 1.3. The analysis is turned into an annual probability of failure so that it can be compared with consequence-based benchmarks, not only with a target factor of safety.
| Variable | Value | Description |
|---|---|---|
| F | 1.3 | Most likely factor of safety for the 10-year water level |
| VF | 15% | Coefficient of variation of F |
| Tc | 10 years | Return period of the condition analyzed |
| N | 50 years | Service life |
| Limits | 10−3/yr; F = 1.5 | Norwegian medium-consequence limit; GEO factor of safety for high economic, low life risk |
At F = 1.3 and a COV of 15%, the annual probability of failure is about 4.6 × 10−3 (1 in 217 years), or 20.6% over 50 years. That fails the Norwegian medium-consequence limit of 10−3 and the GEO factor of 1.5. Raising F to 1.5 at the same uncertainty gives about 4.1 × 10−4; the 10−3 limit is reached at F of about 1.43, so here the GEO value is the stricter of the two.
Open the acceptable probability of failure calculator →
Annual probability of failure, entered or estimated from a factor of safety, its COV and the return period of the condition analyzed, with the lifetime probability, the F band, the Norwegian and Skipp benchmarks and the GEO factor of safety for the consequence.
The table shows how strongly the annual probability depends on the uncertainty in F as well as on F itself. At a coefficient of variation of 10%, a factor of safety of 1.3 already gives an annual probability below 10−3. At 20%, even a factor of 1.6 gives slightly more than 10−3. The investigation and testing that narrow the uncertainty (Section 3.9.15) are worth as much as a higher factor of safety, and Look's warning about comparing factors of safety alone follows directly.
| F (most likely) | COV of F = 10% | 15% | 20% |
|---|---|---|---|
| 1.3 | 4.9 × 10−4 | 4.6 × 10−3 | 1.1 × 10−2 |
| 1.4 | 4.4 × 10−5 | 1.5 × 10−3 | 5.5 × 10−3 |
| 1.5 | 3.0 × 10−6 | 4.1 × 10−4 | 2.6 × 10−3 |
| 1.6 | 1.6 × 10−7 | 1.0 × 10−4 | 1.1 × 10−3 |
| 1.8 | 2.6 × 10−10 | 5.5 × 10−6 | 2.1 × 10−4 |
| 2.0 | 2.6 × 10−13 | 2.4 × 10−7 | 3.4 × 10−5 |
The figure plots the same results as the logarithm of the annual probability. The dashed black line is the Norwegian limit for a medium consequence (10−3); the dashed grey line is the limit for a major consequence (10−4).
Paraphrased from these documents in the reference library.
This section explains why each level of each scale, and each of the five ratings, sits where it does; checks the logic of the scales and the matrix; and compares the method with published practice. It contains no project or client data. Every example in this chapter is generic.
Five is the number of field conditions an engineer can tell apart consistently from what is seen on the ground: not moving and no cause; moved before; cause present; starting to move; failing. Fewer levels would lump an emerging failure with one under way. More would ask for distinctions that visual evidence cannot support, and two engineers would disagree more often. An odd number also gives a middle level, 3, which is the default where data are missing (Section 3.8.22.1). The risk score R = F × S (1 to 25) is an intermediate number whose only job is to place the site in one of the five ratings (Table 3.8-72).
| Level | Rating | Risk score R | Matrix cells (F × S) | Required response (Table 3.8-17) |
|---|---|---|---|---|
| 5 | Severe | 20–25 | 4×5, 5×4, 5×5 | Act now |
| 4 | High | 12–16 | 3×4, 4×3, 3×5, 5×3, 4×4 | Act soon |
| 3 | Elevated | 6–10 | 2×3, 3×2, 2×4, 4×2, 3×3, 2×5, 5×2 | Plan |
| 2 | Guarded | 3–5 | 1×3, 3×1, 1×4, 4×1, 2×2, 1×5, 5×1 | Watch |
| 1 | Low | 1–2 | 1×1, 1×2, 2×1 | Routine inspection only |
The frequency index describes the state of the hazard, because that is what the engineer can see. The indicative annual frequencies attach a number to each state. The 20-year column turns the annual frequency into the chance of at least one failure over a typical planning horizon, 1 − (1 − p)20; it is the column that explains the response tied to each rating.
| F | Level | What defines it | Indicative annual frequency | Chance of ≥1 failure in 20 years | Why the level is here |
|---|---|---|---|---|---|
| 5 | Occurring | The failure is under way and the track is already affected. | 1 or more per year | Near certain | Nothing has to change for the site to fail again; it is failing now. Repeated slow orders or surfacing at the same spot are the record of it. This is the top of the scale because no further evidence of likelihood is possible. |
| 4 | Emerging | Clear signs of movement developing; defects return between surfacing cycles. | 1 in 1 to 1 in 5 years | About 99% | The ground has started to move but the track still runs. Movement that shows between surfacing cycles normally reaches failure within one or two maintenance or budget cycles, so the level spans 1 to 5 years. |
| 3 | Forming | The conditions for failure are present; the ground is not yet moving. | 1 in 5 to 1 in 25 years | About 56% to 99% | Water against the fill, an over-steepened slope or a blocked culvert means the next large storm can start movement. Storms of a 5- to 25-year return period are common enough that failure is more likely than not within a 20-year planning horizon. |
| 2 | Dormant | Past instability, no sign of present activity. | 1 in 25 to 1 in 100 years | About 18% to 56% | The site has failed before, so it can fail again, but reactivation needs a trigger larger than recent ones. That places it in the range of the storms used to size railroad drainage, about the 25- to 100-year event. |
| 1 | Inactive | No evidence of instability, or the cause has been removed. | Less than 1 in 100 years | Less than about 18% | Only an event beyond normal design conditions would cause failure. The level never reaches zero: drains clog and channels move, so an Inactive site is re-screened after major events. |
Spacing. Each level is roughly 4 to 5 times as frequent as the one below. The spacing follows the stages a failing embankment passes through, not a mathematical series; it is finer than the factor-of-10 steps used in some landslide guidance (Table 3.8-78) because most railroad ground hazards that matter fall between once a year and once a century.
Live increments. The live rating (Section 3.8.26) raises F by 1 for one indicator at Watch and by 2 for two Watch indicators or any Warning. One level is the step from “conditions present” to “signs developing”: a single wet indicator moves a site one stage along. Two levels reflect that most rain-triggered failures need both wet ground and heavy rain. Setting F to 5 for a Warning at a site already Emerging recognizes that a moving fill under flood or storm loading should be treated as failing.
The severity levels mark the points where the consequence of a failure passes from one party to the next: from the maintenance budget, to train operations, to the railroad’s service, to the safety of crews and freight, and finally to the public and the environment. Each boundary is a change in who must respond, not only in cost.
| S | Level | Who bears the consequence | Typical outage | Why the level is here |
|---|---|---|---|---|
| 5 | Catastrophic | The public and the environment | More than a week | A failure that can kill, release hazardous materials, take out a structure or reach a river, road or homes is beyond what the railroad alone can absorb. It is the top level because consequences of this kind are not recoverable by repair. |
| 4 | Critical | Train crews, equipment and freight | Several days | Derailment or loss of the main line is likely and serious injury is possible, but the damage stays mostly within the railroad corridor. The step from 3 is the step from a service problem to a safety problem. |
| 3 | Serious | The railroad’s service and its customers | Hours to a day | The track is out of service or under a restrictive slow order and trains are delayed, but no derailment is expected and damage is confined to railroad property. |
| 2 | Minor | Train operations | None to a few hours | A geometry defect needs surfacing or a temporary slow order. Operations notice it; nothing is damaged beyond the track. |
| 1 | Low | The maintenance budget | None | The effect is handled in routine maintenance and never reaches the train schedule. It is the bottom level because a failure here changes nothing but the work list. |
The band limits are set in the gaps between the possible products. R cannot be 7, 11, 13, 14, 17 to 19, or 21 to 24, so no cell sits on a boundary. Every rating therefore has a plain-language description of the cells it contains, given below, and that description is the reason for its required response.
| Level | Rating | What its cells have in common | Why the response fits |
|---|---|---|---|
| 5 | Severe | One scale is at its top level (Occurring or Catastrophic, 5) and the other at 4 or 5: cells 4×5, 5×4 and 5×5 (R 20–25). | Failure is expected within a few years or is under way, and its consequence is Critical or worse, with at least one of the two at the top of its scale. Emerging and Critical together (4×4 = 16) is High, not Severe. Waiting for the next program accepts a likely failure with injury or public harm, so protection, operating restrictions and immediate stabilization are required. |
| 4 | High | Both scales are at 3 or more and at least one is at 4 or 5, short of Severe: cells 3×4, 4×3, 3×5, 5×3 and 4×4 (R 12–16). Failure is more likely than not within the planning horizon, with at least a Serious consequence. | The site will probably fail before a normal capital cycle comes around. A slow order or increased inspection bridges the gap until stabilization in the next program. |
| 3 | Elevated | One scale is at 2 and the other at 3 to 5, or both are at 3: cells 2×3, 3×2, 2×4, 4×2, 2×5, 5×2 and 3×3 (R 6–10). That is a Dormant site with a consequence beyond maintenance, a forming or active failure with only a Minor consequence, or a Forming site with a Serious one. | There is time to plan, but not to ignore the site. Design and scheduling proceed with monitoring in place. Catastrophic sites that are only Dormant land here, so they are not dropped from the program. |
| 2 | Guarded | One scale is at 1 and the other at 3 to 5, or both are at 2: cells 1×3, 3×1, 1×4, 4×1, 1×5, 5×1 and 2×2 (R 3–5). Either the cause has been removed (F 1) or a failure would not affect trains (S 1), with the other scale at 3 or above, or both scales are at 2. | Nothing needs to be built, but the condition that keeps the rating low (a drain, a culvert, a channel position) can change. Routine inspection with defined triggers catches that change. |
| 1 | Low | One scale is at 1 and the other at 1 or 2: cells 1×1, 1×2 and 2×1 (R 1–2). | No credible failure within the planning horizon would affect operations. Routine inspection is enough. |
Tables 3.8-20, 3.8-21 and 3.8-24 describe scores 1, 3 and 5. Table 3.8-76 gives the reason each attribute is scored and descriptions for scores 2 and 4, so that every score from 1 to 5 has a written basis. Where the evidence fits neither description well, use 3 and flag the attribute for the field visit.
| Attribute | Rating | Why it is scored | Score 2 | Score 4 |
|---|---|---|---|---|
| L1 Surficial soils | Situational | Soil type sets strength loss on wetting, erodibility and how fast water drains out of the fill. | Sand and gravel with some fines; well drained | Lean clay or silt that softens when wet; poorly drained in places |
| L2 Geologic setting | Situational | What lies beneath decides whether failures are shallow or deep and whether the ground can subside. | Weathered rock over competent rock at shallow depth | Thick till, colluvium or weak shale; karst or mine workings mapped nearby but not under the track |
| L3 Slope geometry | Situational | Driving stress grows with height and steepness. Score height and steepness separately and use the higher. | Under 10 ft, slopes 2.5H:1V to 3H:1V | Slopes steeper than 2H:1V but not steeper than 1.5H:1V |
| L4 Hydrology | Situational | Water at the toe is the most common trigger of railroad embankment failure. | Intermittent ditch flow away from the toe; outside the 500-year floodplain | Stream within about 50 ft of the toe, or in the 100-year floodplain without flow against the fill |
| L5 Drainage condition | Situational | Blocked or undersized drainage holds water in and against the fill. | Minor sediment or vegetation in ditches; culverts open | Culvert half blocked, damaged or of unknown capacity; ponding seen in imagery |
| L6 Historic instability | Instability | Past movement is the best single predictor of future movement. | Landslide-prone formation mapped, but no instability recorded at or near the site | Documented failure at the site within about 20 years, or an old scarp visible in lidar |
| C1 Track and traffic | Situational (consequence) | Traffic sets how many trains are exposed and what an outage costs. | Lightly used branch line or siding | Main line with moderate traffic |
| C2 Train type | Situational (consequence) | Passengers and hazardous materials turn a derailment into public harm. | No passenger trains; hazardous materials limited to infrequent cars | Regular hazardous materials traffic, or occasional passenger trains |
| C3 Below and beside the track | Situational (consequence) | What a failure would reach once it leaves railroad property. | Railroad or private land with minor drainage | A local road, a stream with fisheries value, or a few dwellings within reach |
| C4 Size of failure | Situational (consequence) | Volume sets repair time and whether the track is lost entirely. | Fill 5 to 10 ft | Fill 20 to 30 ft |
| C5 Redundancy and recovery | Situational (consequence) | Outage length is what the railroad and its customers actually feel. | Parallel route; repair within a day | Long detour; repair in about a week |
The scales and the matrix were checked against the properties a rating method should have. The results, and the limits of the method, are in Table 3.8-77.
| Check | Result | What to do |
|---|---|---|
| Every scale increases with its number | Yes. All attribute scores, F, S and the five ratings run 1 (lowest risk) to 5 (highest). Tables 3.8-14 and 3.8-15 list the highest level first for reading only. | None. Stated in Section 3.8.22.1. |
| All 25 cells of the matrix carry exactly one rating; the bands do not overlap or leave gaps | Yes. R can only take the values 1, 2, 3, 4, 5, 6, 8, 9, 10, 12, 15, 16, 20 and 25; the band limits fall in the gaps between them. | None. |
| Raising F or S never lowers the rating | Yes, for every cell. | None. |
| A Catastrophic site stays Elevated or above until Inactive; a Low-severity site never exceeds Guarded | Yes. | None. |
| The matrix favors consequence over frequency | No. Because F × S is symmetric, a step in F counts exactly as much as a step in S. The extra weight on consequence comes from three rules: the C floor (a 5 on C2 or C3 sets C at 4 or more), “the consequence governs” in Table 3.8-15, and the engineer’s one-level raise. | Apply those three rules every time (Section 3.8.22.4). |
| R measures risk in proportion | No. F and S are ordered levels, not measured quantities, so R = 10 is not twice the risk of R = 5. F levels are roughly 4 to 5 times apart in frequency; S levels are not quantified. | Use R only to place a site in a rating. Within a rating, rank sites by F, then S, or by L × C for preliminary ratings. |
| Desktop Fp means the same as field F | Close. Both are read from Table 3.8-11 using Fg and a defect rating; the desk D comes from the records and the field D from what is seen. | Without defects Fp is capped at Forming (3), so susceptibility alone cannot rate a site as moving. Where the field D differs from the desk D, record why (Section 3.8.24.6; Section 3.8.24.3). The separate situational and instability scores on the report make this visible. |
| Rounding of L and C is defined | Yes. | Round half up: 2.5 becomes 3. |
| L3 is unambiguous when height and steepness disagree | Yes. | Score height and steepness separately and use the higher. |
| The live rating stays on the same scales | Yes. It raises F only, to a maximum of 5, and reads the same matrix; S never changes with the weather. | None. |
Table 3.8-78 compares the GHRM ratings with six published methods: three that agree with its main features and three that do not.
| Source | Method | Position | Where it agrees with GHRM | Where it differs |
|---|---|---|---|---|
| Australian Geomechanics Society (2007), Practice Note Guidelines for Landslide Risk Management, Appendix C | Likelihood levels with indicative annual probabilities, five consequence levels, and a risk matrix read by lookup | Agrees | Five risk levels (Very Low to Very High), each tied to a defined response; likelihood levels tied to annual frequency; risk skewed toward consequence | Six likelihood levels a factor of 10 apart; consequence numbered 1 = Catastrophic; no multiplication |
| NCHRP Research Report 884 (2018), Guidelines for Managing Geotechnical Risks in Design–Build Projects, Ch. 2.1 | Qualitative geotechnical risk analysis with frequency and impact each rated 1 to 5 | Agrees | 1-to-5 scales increasing with risk; ratings combined to rank risks in a register for mitigation | Written for project delivery risk, not for operating ground hazards |
| FTA (2019), Sample Safety Risk Assessment Matrices for Rail Transit Agencies | Likelihood and severity combined in a matrix; risk levels tied to acceptance and action | Agrees | Rail safety practice of combining likelihood and severity, with the required action set by the rating; likelihood calibrated to frequency | 4 severity by 5 likelihood levels; three risk levels; severity numbered 1 = most severe; lookup, not product |
| Cox (2008), “What’s Wrong with Risk Matrices?” Risk Analysis 28(2) | Mathematical critique of risk matrices | Disagrees | Accepts matrices where the embedded judgments are explained, which this section does | Shows matrices have poor resolution, can rank a smaller risk above a larger one, and depend on arbitrary category boundaries |
| FHWA (2019), Unstable Slope Management Program for Federal Land Management Agencies, FHWA-FLH-19-002 | Exponential category scores of 3, 9, 27 and 81, summed into hazard and risk totals | Disagrees | Scores many terrain, drainage and exposure factors from field and desktop data, as the situational attributes do | No matrix; scores are added, and the exponential points let one severe factor dominate; condition reported as Good, Fair or Poor |
| U.S. Department of Defense (2012), MIL-STD-882E, System Safety | Severity category and probability level combined into a Risk Assessment Code read from a matrix | Disagrees | Risk is a combination of severity and probability, with acceptance authority set by the risk level | Four severity categories against six probability levels; four risk levels (High, Serious, Medium, Low); severity numbered 1 = Catastrophic |
Where GHRM goes further. None of the six sources ties the rating to track geometry defect history, to a desktop study that sets each site’s water thresholds, or to a live rating driven by river, rainfall and soil moisture data. These are additions specific to railroad ground hazards and are not covered by the published methods.
Numbering. Several published methods number severity in the opposite direction (1 = most severe). When translating a GHRM rating into another agency’s matrix, reverse the severity number: GHRM S = 5 corresponds to their category 1.
Every proposed solution is rated for how much it will reduce the risk, in three stages: the solution as conceived (this section), the design and construction that turn it into works (Section 3.8.38), and the post-stabilization implementation that proves it performs (Section 3.8.39). The risk reduction is the difference between the current risk and the rating at each stage. Rating all three keeps a good idea from being credited as if it were already built and proven. Figure 3.8-47 follows the worked example of Section 3.8.41 through the stages.
A solution can reduce risk in only three ways, and the solution rating credits each one through the input it changes:
| Way of reducing risk | Examples | Input changed | Rationale | Typical rescoring (starting values; confirm for the site) |
|---|---|---|---|---|
| Remove or reduce the trigger | Upsize or clean a culvert; divert water; add ditches and subdrains; control beavers; lower groundwater | T, and the hydrology and drainage attributes L4 and L5 | If the trigger reaches the site less often, failure cannot be more frequent than the new trigger rating (Equation 3.8-2). | Culvert sized for the 100-year event: T7 → 1, T8 → 2, L5.1 and L5.2 → 1. Ditches regraded and cleaned: T8 → 2, L5.3 → 1. Horizontal or lateral drains: T9 → 2, L5.4 → 1; because they drain the fill internally they also earn D = 1. |
| Increase resistance | Berms; shear keys; soldier pile walls; ground improvement; riprap and scour countermeasures; rock bolting | The situational attributes (L1–L3) through the design factor of safety (Table 3.8-81) | Raising the margin against failure means a larger trigger is needed, which lowers the frequency of failure. | Riprap or a scour countermeasure for the design flood: T4 → 1, L4.3 → 2. Soldier pile or other retaining wall: L3.2 → 1. Free-draining rock buttress or regrade: L3.2 → 2. Subgrade undercut with a drained granular section: L1.1, L1.4 and L5.4 → 1. Each earns D = 1 (Section 3.8.37.2). |
| Reduce exposure or consequence | Realign the track away from the slope; protective structures; detection linked to operating rules (slide fences, monitoring with alarms and slow orders) | S | The ground may still fail, but a failure reaches less or is caught before a train meets it. | T, L and D unchanged. Detection linked to an operating response: S one level lower while the response is in force (SOL2 = 4). Realignment or a protective structure: S rescored for what a failure would now reach, with the reason written. |
The typical rescoring gives starting values, and it is what the Risk Assessment App suggests when an alternative is selected. Each element takes the lower of its current score and the value shown. Replace the values with the site’s own scores where the design or the conditions differ, rescore only the elements the solution actually changes, and never rescore L6.
For each solution, rate the site as it would be once the solution works as intended. Rescore only the inputs the solution changes (Table 3.8-79); every other input keeps its current value. Work through the steps in order:
| Rule | Rationale |
|---|---|
| Investigation level caps the credit. Desk study only: the solution may lower the rating by at most one level. Field reconnaissance, or limited borings without analysis: by at most two levels. Subsurface investigation and analysis: full credit (SOL3, Table 3.8-49). | Without a confirmed mechanism and ground model, the solution may treat the wrong problem; the cap stops unproven solutions from outranking proven ones. |
| Monitoring and operating rules do not lower F. Detection linked to an operating response (alarms, inspections, slow orders) may lower S by one level, and only while the response is in force. | Monitoring does not change how often the ground fails; it changes whether a train meets the failure. |
| Maintenance-dependent solutions (culverts, ditches, subdrains, beaver control) get full credit only with a maintenance plan (Section 3.8.39). | Drainage that is not maintained silts up and returns the site to its trigger. |
| On a site with recurring or active defects (D = 4 or 5), a solution that removes only the trigger keeps the current D in its solution rating. The credit is earned at the post-stabilization stage once movement has stopped. | Removing the trigger does not restore the strength the fill has already lost. Until the track shows the movement has stopped, the defects are still the best evidence of frequency. |
| A solution that leaves the site at High or above is interim, and is labeled as such. | It manages the risk until a permanent solution is built; it does not resolve it (Section 3.8.22.7). |
| S is lowered only where the solution changes what a failure would reach, with the reason written. | Severity belongs to the site and its traffic; most stabilization works lower F, not S. |
The design and construction stage rates two things: the reduction the design actually earns, and the risk while the work is built.
The design rating replaces the judgment of the solution rating with the design criteria the works meet. The levels follow the indicative annual frequencies of Table 3.8-14, so a design event and a frequency index mean the same thing.
| Mechanism | Design criterion met | Fdes | Rationale |
|---|---|---|---|
| Slope | Long-term static factor of safety ≥ 1.5 under the design groundwater, with the trigger controlled (Section 6.3.5) | 1 | The commonly accepted long-term margin; a much larger event than the design condition is needed to fail the slope. |
| Slope | Factor of safety 1.3 to under 1.5 | 2 | Adequate for many conditions but with less margin for unknowns in strength and groundwater. |
| Slope | Factor of safety 1.1 to under 1.3 | 3 | Marginal; acceptable only as a temporary or short-term condition. |
| Slope | Factor of safety under 1.1 | no credit | Not distinguishable from limiting equilibrium given normal uncertainty. |
| Hydraulic (culvert, channel, scour) | Capacity and countermeasures for the 100-year event or larger, with scour checked at the 500-year event | 1 | Matches the Inactive band (less than 1 in 100 years) and common practice for scour-critical structures. |
| Hydraulic | Design event 25- to 100-year | 2 | Matches the Dormant band. |
| Hydraulic | Design event 5- to 25-year | 3 | Matches the Forming band. |
| Hydraulic | Design event under 5-year | no credit | The trigger will still reach the site within a normal maintenance cycle. |
| Subgrade | Subgrade and track section meet the design criteria of Chapter 2.3 for the traffic, with drainage | 1 to 2 | 1 where drainage and bearing both meet the criteria with margin; 2 where they depend on maintenance. |
| Subsidence | Voids treated and verified, or the track bridged over the zone | 2 (1 if bridged or relocated) | Treatment addresses known voids; new ones can still form nearby. |
| Rock and debris | Scaling, bolting or catchment designed for the design block size and energy | 2 (1 if all mapped blocks are stabilized and the catchment is verified) | Catchment manages, but does not prevent, release. |
Where several mechanisms apply, use the highest Fdes among them. Fdes may not be lower than the solution rating's Fsol unless the design shows why.
Construction can raise the risk before it lowers it: a culvert trench cut through a fill, an excavation at the toe, or heavy equipment on a marginal slope all reduce resistance for a time. The construction-stage rating is the risk during the work:
A stabilized site is not yet a proven site. The post-stabilization rating is first provisional, and becomes the verified residual risk only when the works have been built as designed, have performed through a triggering event, and are being maintained.
| Condition | Fpost | Rationale |
|---|---|---|
| Works complete and accepted on as-built quality assurance and quality control (Chapter 5.3), not yet tested by a trigger | Fdes + 1 (provisional) | Construction quality and the ground model are not yet proven by performance. |
| Monitoring (survey, instruments, geometry records) shows no movement through at least one triggering season, or one event at or above the site's response level | Fdes (verified) | The works have been tested by the trigger they were built to resist. |
| Drainage-dependent works without a maintenance plan in force | Fdes + 1 (remains provisional) | Unmaintained drainage returns the site to its trigger. |
| Defects or indicators recur after stabilization | Recompute Fc from the new D (Section 3.8.19) | The solution has not removed the cause; the site re-enters the current risk process. |
Spost is the solution severity Ssol (Section 3.8.37.2). The works themselves rarely change it, since severity belongs to the site and its traffic. A reduction credited for detection linked to an operating response, or for a temporary measure, is kept only while that response is in force (Table 3.8-80); when it lapses, Spost returns to the current S.
The implementation stage also closes the loop with the live rating: after stabilization, the site keeps its trigger thresholds, recalibrated to the new works, and each triggering event is recorded so the verified rating rests on performance, not expectation.
A risk rating says which sites matter. It does not say whether fixing a site is worth more than living with it. Sullivan, Wicks and Koelling's Engineering Economy supplies the tools: present worth, equivalent uniform annual cost and the benefit-cost ratio, all at the owner's discount rate over a fixed analysis period. For ground hazards the recurring cost has two parts. One is routine maintenance, such as surfacing, ditch cleaning and slow orders. The other is the annual risk cost, the probability of a failure in any year times what one failure costs in repair, outage and exposure. Mitigation buys down the second part. The Construction Materials and Engineering Materials 1 texts are the basis for the service life chosen for each alternative, whether that is corrosion of steel, deterioration of concrete or decay of timber.
Equation 3.8-17. Present worth, annual cost and benefit-cost ratio
PW = K + (M + p·C)×(P/A); EUAC = PW × (A/P)
B/C = [(M + p·C)base − (M + p·C)alt]×(P/A) / (Kalt − Kbase)
A soft-ground embankment is costing $60,000 a year in surfacing and has an estimated 5% annual chance of a $1.5 million failure. Two mitigation alternatives are compared with continuing to maintain it, using the risk cost (probability times consequence) as an annual cost alongside maintenance.
| Variable | Value | Description |
|---|---|---|
| C | $1,500,000 | Cost of a failure (repair, outage and claims) |
| A0 | K = 0; M = $60,000/yr; p = 0.05 | Continue surfacing |
| A1 | K = $450,000; M = $8,000/yr; p = 0.01 | Toe berm |
| A2 | K = $900,000; M = $3,000/yr; p = 0.005 | Sheet pile reinforcement |
| i, N | 7%; 30 years | Discount rate and analysis period |
Continuing to maintain the embankment has a present worth of $1,675,221. The toe berm comes to $735,408 (B/C = 3.09) and sheet pile reinforcement to $1,030,295 (B/C = 1.72). Both pay for themselves, and the berm is the better buy.
The answer turns on the probability and the consequence, which come from the risk assessment, so the calculator is meant to be run across a range of values.
Open the life-cycle cost calculator →
Present worth, equivalent uniform annual cost and benefit-cost ratio of mitigation alternatives, with annual risk cost as probability times consequence, and a cumulative present-worth chart.
Paraphrased from these documents in the reference library.
The present worth factor in Equation 3.8-17 is the sum of a geometric series. An annual cost A paid at the end of each of N years, discounted at rate i, has present worth A[v + v² + … + vN] with v = 1/(1 + i). The finite geometric series a + ar + … + arN−1 sums to a(1 − rN)/(1 − r), which gives (P/A) = [1 − (1 + i)−N]/i, the same as the form in Equation 3.8-17.
For railroad work: Use the growing-cost form when a site is visibly getting worse; a constant annual risk cost understates the case for early repair.
Source: Hirst, K. E. (1995). Numbers, Sequences and Series. Modular Mathematics Series. London: Arnold (Butterworth-Heinemann) Find source ↗ (Ch. on sequences and series: geometric series, convergence, and series expansions).
A hypothetical main line fill, used only to illustrate the method. Alternative A assumes a subsurface investigation and analysis have been completed, so it earns full credit under Table 3.8-80.
At a 22-ft fill of lean clay across a creek, a partly blocked 48-in. culvert makes the fill susceptible to softening and slope movement by a drainage-driven mechanism. The site was buttressed with a berm 15 years ago; today the track has been surfaced twice in 12 months and a bulge is forming downstream. The current risk is rated, and three alternatives are carried through the three risk reduction stages of Sections 3.8.37 to 3.8.39.
| Variable | Value | Description |
|---|---|---|
| L1–L5, weights | 4, 3, 3, 4, 5; L5 weighted 2 | Lean clay fill; creek near the toe; blocked culvert |
| L6 | 3 | Past berm 15 years ago |
| T | 4 | Ponding about every 3 years |
| D | 4 | Same defects return between surfacing cycles; fresh bulge |
| S | 4, Critical | Main line, moderate to heavy freight |
| Alternatives | A: replace culvert (100-yr), toe drain and berm; B: clean culvert only; C: monitoring with slow orders | Investigation complete for A: full credit (Table 3.8-80) |
Table 3.8-83 records the current-risk inputs as they appear on the report.
| Input | Value | Reason |
|---|---|---|
| L1 to L5 (L5 weighted 2), L6 | 4, 3, 3, 4, 5 (×2), 3 | Lean clay fill; creek near the toe; blocked culvert; past berm |
| L | (4 + 3 + 3 + 4 + 10 + 3) / 7 = 3.86 → 4 | Equation 3.8-2 |
| T | 4 | Ponding about every 3 years |
| Fg | lesser of 4 and 4 = 4 | |
| D | 4 | Same defects return between surfacing cycles; fresh bulge |
| Fc | 4 (Table 3.8-11) | Evidence governs; no amplification (Fg is not ≥ D + 1) |
| S | 4 Critical | Main line, moderate to heavy freight traffic |
| Current risk | Rc = 16, High | Act soon: slow order or increased inspection; stabilize in the next program |
| Stage | A. Replace culvert (100-year capacity), toe drain and berm | B. Clean culvert only | C. Monitoring with slow orders |
|---|---|---|---|
| Solution | T 4→1, L5 5→1; D expected 1; Fsol = 1; S = 4; R = 4 Guarded | T 4→3, L5 5→3; L = 3; Fg = 3; D stays 4 until movement stops; Fsol = 4; R = 16 High (interim) | F unchanged 4; S 4→3 while the response is in force; R = 12 High (interim) |
| Design and construct | Culvert for 100-year event; slope FS 1.5 with drained berm: Fdes = 1. Culvert trench through fill: Fcon = 5; with track out of service S = 3; R = 15 High for the work window | No design; maintenance item: Fdes = Fsol | Not applicable |
| Post-stabilization | Provisional Fpost = 2; R = 8 Elevated. After one wet season with no movement and a culvert maintenance plan: Fpost = 1; R = 4 Guarded | R = 16 High until defects stop | R = 12 High while in force |
| Risk reduction | High (16) to Guarded (4): 2 levels, 12 points, once verified | None while defects continue | None in F; one level in S, interim only |
The site is High (16). Alternative A reaches a verified Guarded (4), a reduction of 12 points and two levels; B and C remain High and are interim. A is the only alternative that acts on the trigger and the resistance, and the only one that reaches a verified Guarded rating. B treats part of the trigger but not the movement already under way, so the defects, and the rating, stay. C manages exposure while a permanent fix is designed and is labeled interim.
The Ground Hazard Risk Assessment Report is the form the EIC takes to the site. It records what is found there, frames up to three stabilization alternatives, and rates the site as it stands and after each alternative. It is issued to the railroad the same day as a field copy draft, followed by a formal report within one week.
The previous worksheet was a single page that began with general site information. The desktop study was handed over as a separate package, and the EIC had to carry the preliminary scores, thresholds and questions on other sheets or from memory. The reworked report is three sheets, and the first is new:
The result is that the engineer arrives with the desk’s reasoning in hand, the field evidence is recorded against it item by item, and every difference between desk and field is written down where it can later be used to calibrate the desk scores and thresholds.
Cell shading and text styles show where each entry comes from and when it is made.
Red text marks entries that must be confirmed with the railroad contact before the form is issued (the number of tracks and which is higher, and any railroad workload conflict). Blue italic marks the measurement and frequency of each reported geometry defect. In the checklist blocks, mark (✓ or X) every item that applies and leave the rest blank; a blank means the item was looked for and not found. Write photo numbers, dimensions or a short note beside each marked item.
| Sheet | Block | What is recorded | Question it answers | Section |
|---|---|---|---|---|
| 1 | A. Desktop study summary | Network screening, driving mechanism, situational and instability scores, static rating, H&H thresholds, live rating at visit, questions | What did the desk find, and what does the field need to check? | 3.8.42.3 (from 3.8.23 to 3.8.26) |
| 2 | 1. General site information | Client, contacts, location, track and traffic data, protection, site setting | Where is the site, and what does the railroad have at stake? | 3.8.42.4 |
| 2 | 2. Site conditions | Indicators on the left embankment, between the rails and on the right embankment | What is the ground telling us? | 3.8.24.4 |
| 2 | 3. Site instabilities | Major element affected, construction constraints, estimated failure type | What is failing, and what limits the fix? | 3.8.24.5 |
| 3 | 4. Recommended stabilization items | Engineering, drainage, earthwork and structural measures, by alternative | What would fix it? | 3.8.42.6 |
| 3 | 5. Additional services | Exploration, field testing and engineering by alternative, with low and high cost | What is needed to confirm and design the fix, and what will it cost? | 3.8.42.6 |
| 3 | 6. Risk rating | F, S, R and rating: preliminary, live, current and each alternative | How much risk is there now, and how much does each alternative remove? | 3.8.42.7 |
Workflow.
Download the blank report form (PDF, three sheets) for printing. Each sheet is shown under the description of its blocks below; click a sheet to zoom and pan.
Block A carries the desk’s findings into the field. It is prepared by whoever completed the desktop study and checked by the EIC before mobilizing. The sheet is shown in Figure 3.8-48. Its eight parts follow the order of Sections 3.8.23 to 3.8.26:

Using the field column. Confirm each value with a check, or write the revised value. Revise a desk score only on evidence seen at the site, and note the evidence. The EIC does not recompute LS, L or C in the field: the field rating in Block 6 is set from the field defect rating, the confirmed trigger and the desk Fg (Table 3.8-27 and Table 3.8-11) and from the exposure (Table 3.8-15). The revised attribute scores are returned to the desk after the visit, where they update the site record and calibrate later desk studies. The toe, culvert outlet and culvert elevations checked in A7 are the first refinement of the H&H thresholds.
The desktop package still includes the site map or KMZ, the site history summary and, where prepared, the Site Background Report. Mark which are attached at the foot of Block A.
Block 1 identifies the site and records what the railroad has at risk. Most entries come from the railroad before the visit; the rest are recorded on site. Block 1 is on Sheet 2 with Blocks 2 and 3, shown in Figure 3.8-49.

| Group | Fields |
|---|---|
| Client and contacts | Client; railroad subdivision; project number; railroad contact and phone; EIC and phone |
| Location and protection | Milepost; from MP and to MP; on-site protection type (for example foul time, track and time, or a watchman/lookout); place of safety; date |
| Operations | Operational characteristic (main line, siding, yard or industry; freight, passenger or mixed; hazardous materials); average daily train traffic; number of tracks (and which is higher, or whether they are at the same elevation); normal speed; slow order speed; date of last issue |
| Affected length | Affected track length (ft), measured on site |
| Site setting | Current weather; geologic setting; track cross section (cut or fill); alignment (tangent, inside or outside of curve); track setting (marsh, valley, or slope: top, mid or bottom); population density factor |
Why it matters. Train traffic, normal speed, the number of tracks, train type and the population density factor are the exposure that sets the hazard severity. They were scored at the desk as C1 to C5 (Block A4); Block 1 confirms them on site. If they disagree, mark the check row and revise S in Block 6. An error here changes the rating. The slow order speed and the date of the last issue show how the railroad is already managing the hazard. The affected track length scales every cost in Block 5 and should be stated with each alternative.
Blocks 2 and 3 are the field half of the instability rating. How to orient the form, walk the site, record defects with their measurement and frequency, and read the pattern of indicators is described in Section 3.8.24.4; the major element, construction constraints and failure type in Section 3.8.24.5. Two points apply to the reworked form:
Block 4 lists the measures that could stabilize the site, grouped by discipline. Mark every item that belongs in at least one alternative and write the alternative number(s) beside it; this is what links Block 4 to the three alternative columns of Blocks 5 and 6. Blocks 4 and 5 are on Sheet 3 with Block 6, shown in Figure 3.8-50.

| Engineering studies | Engineering disciplines | Drainage | Earthwork | Structural |
|---|---|---|---|---|
| Site monitoring: track forces | Hydraulics and hydrology (H&H) | Dewater | Grading | Load transfer |
| Site monitoring: instrumentation | Geotechnical | Remove obstruction | Stiffen subgrade | Earth retention |
| H&H study | Structural | Ditching | Remove and replace | Repair |
| Geotechnical exploration | Civil | Erosion control | Counter (toe) berm | Replace |
Order of preference. Follow the risk control hierarchy of Section 1.1.9: remove the cause first (water is the most common one: dewater, remove the obstruction, ditch), then reduce the load or driving force (grading), then add resistance (counter berm, stiffen subgrade, earth retention, load transfer). Use monitoring and operating restrictions to manage the remaining risk while the permanent fix is designed and built. The driving mechanism in Block A2 usually points to the first measure. A useful set of alternatives is often a quick, low-cost measure (Alternative 1), a medium measure (Alternative 2) and the long-term structural answer (Alternative 3). Monitoring and instrumentation are covered in Chapter 5.3, earth retention in Chapter 7.1, and ground improvement in Chapter 7.2 and its technology library (Section 7.2.16).
Ground improvement level. An earlier version of the worksheet carried three levels of ground improvement. They remain a useful shorthand when an alternative depends on ground improvement: low for drainage-led and surface measures; medium for local treatment such as lateral drains, a toe berm or compaction grouting; and robust for structural or deep measures such as soldier piles and lagging, deep mixing or track realignment.
Block 5 turns the recommendation into a scope. For each service, mark (or enter a quantity, such as the number of borings or inclinometers) under each alternative that needs it, and give a low and high estimated cost, so the railroad sees a range rather than a single number that looks more precise than it is.
| Service group | Items | Recorded for each item |
|---|---|---|
| Subsurface exploration | Surveying; soil survey borings; modified SPT soil survey borings; SPT borings | Alternatives 1–3 that need it; estimated cost, low and high |
| Field testing | Dynamic cone penetrometer (DCP); field CBR; inclinometer; piezometer; lateral trench test pit; ground penetrating radar (GPR) | Alternatives 1–3 that need it; estimated cost, low and high |
| Engineering | Laboratory testing; geotechnical analysis; structural analysis; design bid package; construction monitoring | Alternatives 1–3 that need it; estimated cost, low and high |
Each service ties to a chapter of this manual: exploration planning to Chapter 3.9; borings and SPT to Chapter 4.1; DCP, field CBR and GPR to Chapter 5.1; piezometers to Chapter 2.8; inclinometers to Section 5.3.8; laboratory testing to Chapter 5.2; and slope analysis to Chapter 6.3. Field testing on an operating railroad is done in work windows, so note when each test can be done. The level of effort set by the static rating (Table 3.8-29) is a guide to how much exploration to scope.
Alternative notes. On Sheet 3, write a short paragraph for each alternative: what it consists of, the services it needs, how long it will take (Table 3.8-90), and the risk rating expected once it is built. These notes become the alternatives section of the formal report (Chapter 8.4).
Block 6 rates the site using the scales and matrix of Section 3.8.22. It has six columns:
If the live rating at the visit was above the static rating, judge whether the indicators seen are those of the event or of the site’s usual state, and say so in the reason. Record any one-level adjustment (Section 3.8.22.6) and, where the field rating differs from the preliminary rating by more than one level, the reason.
When an alternative includes ground improvement or another stabilization method, the report’s companion sheet sets the analysis it needs, the field and laboratory testing that support the analysis, and the quality control that shows the method worked. The field testing column also records when the test can be done around traffic.
| Method | Analysis required | Field testing | Laboratory testing (standard) | Quality control |
|---|---|---|---|---|
| Preloading and surcharging | Consolidation analysis | SPT during off-peak hours | Triaxial compression (ASTM D4767-11(2020)) | Pore pressure measurement |
| Sand drains | Consolidation analysis | CPT coordinated with rail operations | Unconfined compression (ASTM D2166/D2166M-24) | Settlement monitoring |
| Vibro-compaction | Shear strength analysis | SPT during off-peak hours | Consolidation (ASTM D2435) | Pore pressure measurement |
| Deep mixing | Shear strength analysis | CPT coordinated with rail operations | Triaxial compression (ASTM D4767-11(2020)) | Settlement monitoring |
| Grouting | Liquefaction analysis | SPT or CPT with minimal disturbance | Unconfined compression (ASTM D2166/D2166M-24) | Pore pressure measurement and settlement monitoring |
| Compaction grouting (low-mobility grout to 20 ft below toe of slope) | Ground stabilization analysis | SPT or CPT to verify treatment; GPR | Compressive strength (ASTM C39/C39M-26) | Ground movement monitoring |
| Ballast removal and replacement | Material contamination analysis | SPT or CPT during maintenance windows | Particle size distribution (ASTM D6913; D422 was withdrawn in 2016) | Track settlement monitoring |
| Lateral drains | Seepage analysis | SPT or CPT with piezometer installation; GPR | Permeability (ASTM D5084-24) | Pore pressure and water table monitoring |
| Toe berm | Slope stability analysis | SPT or CPT at the berm location; GPR | Direct shear (ASTM D3080/D3080M-23) | Slope monitoring |
| Embankment widening | Lateral stability analysis | SPT or CPT along the embankment; GPR | Compaction (ASTM D1557) and shear strength | Lateral movement monitoring |
| Soldier piles and lagging | Structural stability analysis | SPT or CPT at pile locations; GPR | Load test (ASTM D1143 axial; ASTM D3966 lateral) | Structural monitoring |
| Track realignment away from top of slope | Track stability analysis | GPR; SPT or CPT during off-peak hours | Compaction (ASTM D698 or D1557) | Track alignment monitoring |
The standards and editions are those listed on the worksheet. Confirm the current edition, and that the standard fits the test intended, when the testing program is written. Method descriptions, design procedures and acceptance criteria are in Chapter 7.2; monitoring methods and trigger levels are in Chapter 5.3.
When alternatives are first framed in the field, before quantities exist, a relative ranking of cost and time is enough to tell a quick, inexpensive fix from a long capital project. Table 3.8-90 lists the methods in the same order as Table 3.8-89. Completion time is scored from 1 to 5; the scores used are 2 (about 1 week), 3 (about 3 months) and 5 (over 1 year).
| Method | Relative cost | Completion time (score) |
|---|---|---|
| Preloading and surcharging | Low | Over 1 year (5) |
| Sand drains | Medium | About 3 months (3) |
| Vibro-compaction | High | About 3 months (3) |
| Deep mixing | High | About 3 months (3) |
| Grouting | High | About 3 months (3) |
| Compaction grouting (low-mobility grout to 20 ft below toe of slope) | High | About 3 months (3) |
| Ballast removal and replacement | Medium | Over 1 year (5) |
| Lateral drains | Medium | About 1 week (2) |
| Toe berm | Medium | About 3 months (3) |
| Embankment widening | Medium | Over 1 year (5) |
| Soldier piles and lagging | High | Over 1 year (5) |
| Track realignment away from top of slope | High | Over 1 year (5) |
Use the ranking with the risk ratings. Lateral drains, a medium-cost method installed in about a week, can move a Forming, Critical site (R = 12, High) to Inactive (R = 4, Guarded). That may be the right first step even where a high-cost structural fix is the long-term answer.
Before the form leaves your hands, check that every block has been completed or marked “N/A”, that each Block A value has been confirmed or revised, that the photo numbers are recorded and that the red-text entries were confirmed with the railroad. Date the form, send it to a senior technical manager for review and issue it to the railroad as the field copy draft, so operating decisions are not held up while the report is written. The statement printed at the foot of Sheet 3 must stay on every copy:
The formal report follows within one week. It carries the three sheets forward with photographs, a site plan, the desk-to-field comparison from Block A, the reasoning behind the failure type, the F and S levels and the rating, and the recommended alternative with its scope, cost range and expected rating. Report format and content are covered in Chapter 8.4.
Every rating is recorded so that a reviewer can follow it without the engineer present, and so that the next assessment of the site starts from the reasons, not just the numbers.
Table 3.8-91 shows a completed record for the culvert fill site carried through Examples 3.8-3 to 3.8-6. Each line gives the level and the evidence behind it, so a reviewer can check the rating, and the next assessment can see which inputs have changed. Write the reason as the evidence, not as a restatement of the level: “four cross level exceptions returning between cycles” can be checked; “defects recurring” cannot.
| Item | Level | Reason and source |
|---|---|---|
| Trigger narrative | — | A half-blocked 36-in. culvert under a 25-ft lean clay fill ponds water against the left slope in most wet years; the fill is cracked and its defects recur. Failure is most likely to be triggered by a storm exceeding the culvert. Current risk High; reducible by restoring drainage and adding resistance. |
| T | 4 | Ponding in most wet years; imagery 2019–2025; water 3 ft higher on the left at the visit (photos 4–7) |
| L1–L5 | 4, 3, 3, 5, 4 (L5 × 2) | Soil survey and old boring (lean clay over alluvium and shale); lidar (25 ft, 2H:1V); floodplain map; culvert half blocked (photo 3) |
| L6 | 4 | Shoulder slump repaired 12 years ago (railroad repair record) |
| D | 4 | Four cross level exceptions since the last slow order, returning between cycles (geometry reports); fresh tension cracks, left shoulder (photos 8–9) |
| Fg, Fc | 4, 4 | L = 27/7 = 3.86 → 4, not capped by T; Table 3.8-11, row 4, column 4 |
| S | 4 | Main line, 28 trains a day with hazardous materials, 50 mph; creek and farmland below; detour available |
| Rc, rating | 16, High | No one-level adjustment: crew escape route available; no shared trigger with nearby sites |
| Alternative 1 | 16, High (interim) | Removes the trigger only; D kept at 4 until a wet season passes with no movement (Section 3.8.37.2) |
| Alternative 2 | 4, Guarded | Drains the fill and adds resistance; D expected 1. Investigation level: field reconnaissance, so a two-level reduction is the most that may be claimed; High to Guarded is two levels and is allowed (Table 3.8-80) |
| Maintenance and monitoring | — | Culvert inspection twice a year and after storms above the site threshold; crack gauges read monthly through the first wet season to verify the post-stabilization rating |
The ratings are a structured way of applying engineering judgment; they do not replace it. The frequency bands are indicative, the trigger record at most sites is short, and the defect record depends on how consistently defects were reported. Ratings should be revisited after every significant triggering event, after stabilization, and whenever the traffic or exposure changes. Where the method and the engineer's judgment disagree, the engineer may raise the rating one level with a written reason (Section 3.8.22.6), and the disagreement should be reported so the method can be improved.
Table 3.8-92 lists the main limitations, what each does to a rating and how to manage it.
| Limitation | Effect on the rating | What to do |
|---|---|---|
| The frequency bands are indicative | F is a level, not a measured probability | Where a number is needed (acceptable risk, life-cycle cost), use the probability methods of Sections 3.8.30 to 3.8.35 and state the exposure period |
| Trigger records at most sites are short | T may be set too high or too low | Use agency frequency analyses for rainfall and flow; log every event and recalibrate the thresholds (Section 3.8.26.6) |
| Defect reporting varies between territories | D is biased low where defects were not recorded | Confirm D in the field; score missing evidence 3 and flag it for the visit (Section 3.8.22.1) |
| F and S are ordered levels and R is their product | R is not proportional to risk; equal scores can hide different sites (Cox 2008) | Use R only to place a site in a rating; rank within a rating by F, then S (Table 3.8-77) |
| Sites are rated one at a time | Sites that share a trigger fail together, so corridor risk is understated | Apply the one-level raise for shared triggers; carry a corridor reserve for emergency repairs (Section 3.8.30) |
| Desk inputs are regional | A preliminary rating can miss a local seep, a buried culvert or old fill | Treat desk ratings as preliminary; the field rating governs (Section 3.8.25) |
| Climate and land use change | Past return periods can understate future triggers | Rate on current gauge and rainfall records, note any trend in the rationale, and revisit thresholds after unusual events |
| Live data feeds can fail | A missing indicator can look like a normal one | A service that does not respond is named on the site and left out, never read as normal; inspect when in doubt (Section 3.8.26.5) |
| A rating is not a stability analysis | It ranks risk but gives no factor of safety or design | Design from investigation and analysis (Chapter 6.3); the investigation level caps solution credit until then (Table 3.8-80) |
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S4 under Supplemental References.
Related section: 3.8.3 Embankment and Slope Failure Mechanisms
Look uses three historical failures to show that a slope’s safety obligations extend beyond the construction boundary:
Most slope instability is smaller and stays on site, costing time and money; but a single 12 in boulder from a cutting can reach a traffic lane or a house 164 ft away.
For railroad work: a track at the toe of mine spoil, a tailings embankment or a steep developed hillside is exposed to a failure that starts on someone else’s property. Section 3.8.3’s flow-slide mechanisms apply, and these sources belong on the hazard inventory even when they are outside the right-of-way.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §3.8, pp. 92. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
A Class I railroad is preparing a hazard register for a line through hilly clay country. Four factors are being entered for one embankment: a sensitive clay deposit, a culvert corroding over 20 years, a 100-year storm, and tonnage on the line doubling over a decade. The engineer must classify each as a predisposing condition, a preparatory factor or a trigger.
Classifying each factor correctly matters because each kind calls for a different response: a predisposing condition is designed around, a preparatory factor is stopped, and a trigger is watched.
| Variable | Value | Description |
|---|---|---|
| (a) | A sensitive clay deposit | Factor to classify |
| (b) | A culvert corroding over 20 years | Factor to classify |
| (c) | A 100-year storm | Factor to classify |
| (d) | Tonnage on the line doubling over a decade | Factor to classify |
| Criteria | Section 3.8.1 | Predisposing: fixed by the site. Preparatory: slowly erodes the margin over time. Trigger: the event that causes failure at a given moment. |
No equation is needed; the answer follows from the criteria listed under Given.
(a) Predisposing condition. (b) Preparatory factor. (c) Trigger. (d) Preparatory factor.
Tonnage is usually preparatory, because it wears the margin down over years. It can also act as a trigger when a single step change, such as heavier cars introduced at once, pushes a marginal subgrade past its limit. The classification therefore depends on how fast the change happens, not only on what it is.
The railroad embankment slope of Example 3.8-1 is to be instrumented with piezometers, and the railroad wants an alarm level. The engineer must find the saturated fraction of the slipping depth at which the slope reaches a factor of safety of 1.0, and the corresponding height of water above the slip surface.
Example 3.8-1 gave the factor of safety for three water levels. This question turns the calculation around and asks how high the water must rise for the slope to fail, which is the number a monitoring program would set its alarm against.
| Variable | Value | Description |
|---|---|---|
| Slope | As Example 3.8-1 | τd = 288 psf; σ = 576 psf; c′ = 50 psf; tanφ′ = 0.625 |
| u | 299.5 m psf | Pore pressure as a function of the saturated fraction m (Example 3.8-1, Step 4) |
| FS | 1.0 | Target condition: limiting equilibrium |
m = 0.65. The slope fails when the water table rises to about two-thirds of the slipping depth, about 3.9 ft above the slip surface.
The answer falls between the half-saturated case (FS = 1.10) and the fully saturated case (FS = 0.77) of Example 3.8-1, as it must. A piezometer at this site would set its warning level well below m = 0.65, for example at m = 0.4 to 0.5, so there is time to act before failure.
A Class I railroad uses a rainfall threshold to decide when to send patrols ahead of trains on a line with a history of debris flows. A storm delivered 3.0 in. of rain over 24 hours. The engineer must compute the average intensity and decide whether the storm exceeded the Caine threshold.
A long storm can deliver more rain than a short one and still fall below the threshold, because the threshold intensity drops as the duration grows. This question checks a 24-hour storm.
| Variable | Value | Description |
|---|---|---|
| P | 3.0 in. | Storm rainfall |
| D | 24 hr | Storm duration |
| Threshold | I = 0.58 D−0.39 | Caine (1980), in./hr |
No. At 0.125 in./hr the storm is below the 24-hour threshold of 0.17 in./hr.
This storm delivers 50% more rain than the one in Example 3.8-2 and still falls below the threshold. The comparison shows why intensity, not total rainfall, governs. It does not close the matter: wet antecedent conditions or a locally calibrated threshold could still call for a response.
A Class I railroad has had a series of slides at one cut and wants to order a repair quickly, before the cause has been studied. The engineer must explain why the failure mechanism, and not only the trigger, should be diagnosed before a repair is selected.
This is a reasoning question. It is answered from the principles of Section 3.8.1 and the control hierarchy of Section 1.1.9.
| Variable | Value | Description |
|---|---|---|
| Principle 1 | Section 3.8.13 | The same symptom can come from different mechanisms. |
| Principle 2 | Section 1.1.9 | Controls that remove or reduce the hazard rank above those that only manage exposure. |
No equation is needed; the answer follows from the criteria listed under Given.
Because the same symptom can come from different mechanisms, and a repair aimed at the wrong one spends money without reducing the hazard.
Managing only the trigger, with patrols or speed restrictions, leaves the hazard in place and commits the railroad to those restrictions indefinitely. Inclinometers and piezometers cost little compared with a buttress built for the wrong failure surface, which is why Section 3.8.16 recommends confirming the mechanism with instruments before committing capital.
A Class I railroad located in Kentucky has a side-hill fill on a main line where the desk study gives a geospatial frequency Fg = 4 and a severity S = 3. The geometry records show defects reported more than once but not returning between surfacing cycles (D = 3). The roadmaster asks what the rating would be if the records had shown no defects at all (D = 1).
The current frequency index is not the higher of Fg and D. Table 3.8-11 caps susceptibility without movement at Forming, and amplifies light defects at a highly susceptible site. This question exercises both rules.
| Variable | Value | Description |
|---|---|---|
| Fg | 4 | Geospatial frequency from the desk study |
| S | 3 | Serious: main line with light traffic |
| D | 3 or 1 | Defect rating, case 1 and case 2 (Table 3.8-10) |
| Rule | Equation 3.8-3 | Fc = the greater of D and the lesser of (Fg, 3), plus 1 where D ≥ 3 and Fg ≥ D + 1 |
With D = 3 the site is Emerging and High (12); with no defects it is Forming and Elevated (9). Without evidence of movement, a susceptible setting can only make a site Forming: Emerging and Occurring require signs at the track (Table 3.8-14). Light defects at a site that susceptible are taken as the start of a response that will be tested again soon, so the rating is raised one level. The desk rating with D = 1 is a reason to visit early, not proof of activity.
A Class I railroad located in Iowa has a fill along a river whose static rating is Forming (F0 = 3) and Critical (S = 4). A spring storm is forecast. The paired gauge is forecast to reach action stage (Watch), and the forecast 24-hour rainfall is 60% of the site threshold (Watch). Soil moisture is normal. The dispatcher asks for the live rating and the response.
The live rating raises F by the increments of Table 3.8-32 while indicators are at Watch or Warning. S does not change with the weather.
| Variable | Value | Description |
|---|---|---|
| F0, S | 3, 4 | Static rating: R = 12, High |
| River | Forecast at action stage | Watch (Table 3.8-31) |
| Rainfall | 60% of the site threshold | Watch: half the threshold up to the threshold |
| Soil moisture | Normal | No increment |
| Rule | Table 3.8-32 | +1 for one Watch; +2 for two or more Watch or any Warning; F = 5 on river or rain Warning where F0 ≥ 4; maximum 5 |
Two Watch indicators raise F from 3 to 5, and the rating jumps from High (12) to Severe (20). The response is to act now: inspect before and after the crest and restrict operations until the site has been checked. The rating is held until the river is back below action stage and at least 48 hours have passed, because many embankments fail as the water falls. Wet ground and heavy rain together are treated as more than either alone, which is why two Watches count as much as one Warning.
A Class I railroad located in Pennsylvania has a fill rated Emerging (F = 4) and Critical (S = 4). The consultant proposes a drained toe berm from a desk study only; no borings have been drilled. Rescored as built, the berm gives Fsol = 1. The program manager wants to enter the solution rating in the capital plan.
Table 3.8-80 caps the risk reduction a solution can claim according to the level of investigation behind it, so that an unproven fix does not outrank a proven one.
| Variable | Value | Description |
|---|---|---|
| F, S | 4, 4 | Current rating: R = 16, High |
| Fsol | 1 | Rescored as the berm would perform once built (Section 3.8.37.2) |
| Investigation | Desk study only | No subsurface investigation or analysis |
| Cap | Table 3.8-80 | Desk study: at most one level; field reconnaissance: two; subsurface investigation and analysis: full credit |
As built the berm would rate Guarded (4), but from a desk study it may claim only one level of reduction, so the solution rating entered in the plan is Elevated (8), marked as capped. Without a confirmed mechanism and ground model, the berm could be treating the wrong problem. A subsurface investigation and stability analysis that confirm the slip surface and the drained strength earn the full credit, and the solution rating then moves to Guarded. The cap is what keeps an unproven idea from outranking a proven design in the capital plan.
A Class I railroad located in Ohio has two sites on the same subdivision, each with a risk score of 12. Site A is Emerging (F = 4) with a Serious consequence (S = 3). Site B is Forming (F = 3) with a Critical consequence (S = 4). There is money to stabilize one site this year, and the manager asks which comes first.
R places a site in a rating; it does not measure risk in proportion. Table 3.8-77 gives the rule for ordering sites within a rating.
| Variable | Value | Description |
|---|---|---|
| Site A | F = 4, S = 3 | Emerging; Serious |
| Site B | F = 3, S = 4 | Forming; Critical |
| Rule | Table 3.8-77 | Use R only to place a site in a rating; within a rating, rank by F, then S |
| Adjustments | Section 3.8.22.4 | C floor, “consequence governs” and the engineer’s one-level raise |
No equation is needed; the answer follows from the rules listed under Given.
Site A ranks first: both are High, and within a rating the site with the higher F comes first. A is failing now, so the benefit of fixing it is gained soonest (Figure 3.8-42 shows how quickly the chance of failure builds with exposure). Site B’s higher consequence is not ignored: it should be monitored and placed first in the next program, and if the hazardous materials traffic, what lies below the fill or a shared trigger justifies the engineer’s one-level raise, B becomes Severe and moves ahead of A. Write the reason for the order in the rationale either way (Section 3.8.43).
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Topic | Refer to |
|---|---|
| Risk equation, risk resolution matrix and risk control hierarchy | Sections 1.1.2, 1.1.7 and 1.1.9 |
| Mechanism, condition and trigger; trigger inventory; rainfall thresholds | Sections 3.8.1, 3.8.11 and 3.8.12 |
| Desktop data sources for the geospatial rating | Chapter 3.2; Section 3.8.23.1 |
| Scales, risk matrix and required responses | Section 3.8.22 |
| Situational and instability attributes; field indicators | Sections 3.8.23 and 3.8.24 |
| Live rating | Section 3.8.26 |
| Cost estimates for alternatives | Chapter 3.7 |
| Slope stability factors of safety | Section 6.3.5 |
| Construction monitoring and quality control | Chapter 5.3 |
| Retaining structures and ground improvement | Chapters 7.1 and 7.2 |
| Rated elements and the criteria for each level of every rating | Section 3.8.27 |
| Track substructure: fouled ballast, pumping, subgrade defects | Chapter 2.3 |
| Hazard monitoring map, river stage watchlist, live risk rating and Site Background Report | Hazard monitoring map |
| Failure mechanisms and triggers; diagnosing the mechanism | Chapter 3.8 |
| Planning the exploration | Chapter 3.9 |
| Borings and sampling | Chapter 4.1 |
| In situ testing: DCP, CPT, GPR | Chapter 5.1 |
| Groundwater, seepage and piezometers | Chapter 2.8 |
| Laboratory testing program | Chapter 5.2 |
| Slope stability analysis | Chapter 6.3 |
| Report preparation | Chapter 8.4 |
| Topic | See Also |
|---|---|
| Hazard classification, risk estimation and control hierarchy | Chapter 1.1 |
| Subgrade failure modes, fouling index, GPR | Chapter 2.3 |
| Foundation elements, culverts, bridge approaches | Chapter 2.1 |
| Frost susceptibility classification of soils | Chapter 2.2, Section 2.2.7 |
| Frost penetration depth and frost design | Chapter 7.3, Section 7.3.5 |
| Live risk rating with thaw and snowmelt indicators | Chapter 3.8, Section 3.8.26.3; Hazard monitoring map |
| Groundwater and seepage | Chapter 2.8 |
| Settlement analysis | Chapter 6.2 |
| Slope stability analysis | Chapter 6.3 |
| Seismic hazard and liquefaction | Chapter 6.5 |
| Instrumentation and monitoring | Chapter 5.3 |
| Stabilization and ground improvement | Chapters 16, 17; Section 7.2.16 |

Sections on this page marked “After Profillidis (2014)” draw on the document below. Text is summarized or paraphrased; tables are transcribed or reproduced with their original source noted; figures and photos are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S3 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S4 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.
Authors: Daniel P. Colwell and Mario Ruel. This part was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management. Sections 3.8.7 and 3.8.8 are adapted from Mario Ruel’s chapter on railway frost geohazards for the Railway Ground Hazard Research Program (Ruel 2026b).
Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.