Record the mechanism, not just the symptom, in every inspection and report. "Soft track" is a symptom; "progressive
shear failure of wet CL subgrade" is a mechanism.
Look for the preparatory factor that is eroding the margin: a blocked outlet, rising tonnage, toe erosion or a
corroding culvert. It is usually cheaper to stop than the failure it leads to.
Before ditch cleaning or toe excavation at a known slope, have the geotechnical engineer review the work. Maintenance
activity is a recurring trigger.
Pair every rainfall-sensitive site in the inventory with a rain source and response threshold.
After an event, document the trigger magnitude (rain totals, flood stage, earthquake magnitude and distance). This
data calibrates future thresholds.
Use instrumentation to confirm the mechanism before committing capital to a repair. Inclinometers and piezometers
cost little compared with a buttress built for the wrong failure surface.