3.8.4 Hydraulic Failure Mechanisms

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.4 Hydraulic Failure Mechanisms

Chapter 1.1 splits hydraulic erosion into surface-flow and seepage mechanisms. They fail differently and call for different controls.

3.8.4.1 Surface-Flow Mechanisms
  • Scour at bridge piers and abutments: local scour around obstructions, contraction scour where the channel is narrowed, and long-term degradation of the bed. Evaluate per FHWA HEC-18 (Chapter 2.8, Section 2.8.5.4).
  • Bank and toe erosion where the alignment parallels a river, lake or coast. This removes toe support and leads to slope failure (Section 3.8.3).
  • Overtopping and washout when a culvert or bridge opening is exceeded or blocked. Water flowing over the embankment erodes the downstream face and can remove the fill entirely.
  • Beaver dam failure releasing stored water as a surge, a recognized washout cause in wooded territory (Chapter 1.1).
Figure 3.8-7. Bank erosion, scour, debris jam, degradation and avulsion at a single crossing (BGC).
Figure 3.8-7. Bank erosion, scour, debris jam, degradation and avulsion at a single crossing (BGC).
Figure 3.8-8. Partial culvert obstruction by beaver debris.
Figure 3.8-8. Partial culvert obstruction by beaver debris.
Figure 3.8-9. After the dynamited-dam failure: more than 300 ft of bank removed.
Figure 3.8-9. After the dynamited-dam failure: more than 300 ft of bank removed.
3.8.4.2 Seepage (Internal) Mechanisms
  • Piping and internal erosion where water flows through or beneath an embankment with enough gradient to move particles. This is especially common along the outside of culvert barrels and through fills ponded on one side.
  • Seepage forces and uplift reducing effective stress in slopes and at the toe.
  • Rapid drawdown when flood water recedes faster than pore pressure in the embankment can dissipate, leaving the saturated slope without the stabilizing water load on its face.
Figure 3.8-10. A trestle span that did not survive the flood.
Figure 3.8-10. A trestle span that did not survive the flood.
Figure 3.8-11. Seepage under the track creating internal voids.
Figure 3.8-11. Seepage under the track creating internal voids.

Underestimated peak flows

Undersized drainage is a hydraulic mechanism in its own right. Profillidis gives the U.S. Soil Conservation Service method based on Fuller’s formula for the peak flow from a catchment of A mi² for a return period of T years:

Qmax = Q1 · (1 + 0.8 log T) · (1 + 2.00 / A0.3),   with Q1 = 136 · A0.8 (ft³/s)

His worked values: A = 3.86 mi², T = 10 years gives Q1 ≈ 400 and Qmax ≈ 1,680 ft³/s; A = 5.79 mi², T = 20 years gives ≈ 555 and 2,470 ft³/s. He cautions that such semi-empirical formulas must be checked against measured data. On the TGV Méditerranée, observed extreme runoff was about twice the top of the predicted range ( Chapter 2.1, Section 2.1.5.2 ). He argues that increasing rainfall intensity calls for return periods far longer than the traditional 50–100 years, up to 1,000 years, with the probable maximum flood as the reference event.

After Profillidis (2014), §9.14.2–9.14.3, Eq. 9.11. Full reference under Supplemental References.

Scour: why it is invisible from the hi-rail

Local scour forms horseshoe and wake vortices around piers and abutments; contraction scour deepens the channel through a constricted opening. Both can undermine a foundation well below the water surface. Away from bridges, any bend near the track is scour-critical: the outer radius scours while the inner radius deposits. Banks migrate as the stream undercuts and collapses them. Attack migration before it passes a 2:1 intercept slope with the track, because cost rises steeply with delay, and get engineering help, since riprap alone may not be enough.

Figure 3.8-12. Horseshoe and wake vortices carving a scour hole around a pier.
Figure 3.8-12. Horseshoe and wake vortices carving a scour hole around a pier.
Figure 3.8-13. Bank migration toward the railroad.
Figure 3.8-13. Bank migration toward the railroad.

Signals stay green when track is undermined by side scour or washed out. Peak flow can arrive after the rain stops, and a long moderate storm can do more damage than a short intense one. Get off the hi-rail and walk the bank at scour-critical locations. AREMA countermeasures (after FHWA) are riprap at piers and abutments, guide banks, spurs and revetments, with riprap always placed from the toe upward.

Figure 3.8-14. A trestle left hanging after the approach embankment washed out.
Figure 3.8-14. A trestle left hanging after the approach embankment washed out.

After Geotechnology for Railroaders Program, Module 6.3; §02–05. Full reference under Supplemental References.

Differential head, beaver dams and rapid drawdown

When the water level on one side of an embankment exceeds the other by more than about 6 ft, flow is forced beneath the track. Within days, depending on the fill, wet spots appear at the downhill toe. Dirty or milky seepage and sand fans at the outlet mean soil is being carried out and cavities are forming. In spring, a culvert plugged with ice is the most frequent cause.

Figure 3.8-15. High differential water level driving seepage beneath the track.
Figure 3.8-15. High differential water level driving seepage beneath the track.

Beaver dams in culverts and ditches cause about 80% of beaver trouble but less than 10% of the risk. Dams far uphill, sometimes 100 ft or more above the track and outside railway property, are about 20% of problems but carry the highest risk. The 1992 Nakina derailment, in which two employees were killed, followed a rapid drawdown of a lake after a dam failure and led to the formal Beaver Activity Hazard Assessment (BAHA) program. The program rates watersheds and dams 1–5 and combines them into a global score:

Figure 3.8-16. An uphill dam about 100 ft above the track: the highest-risk configuration.
Figure 3.8-16. An uphill dam about 100 ft above the track: the highest-risk configuration.
Figure 3.8-17. Nakina, 1992: the sudden drop in lake level undermining the embankment under the train.
Figure 3.8-17. Nakina, 1992: the sudden drop in lake level undermining the embankment under the train.
Table 3.8-3. BAHA global risk matrix (watershed rating × worst dam rating, with additional severe dams)
WatershedDam 1Dam 2Dam 3Dam 4Dam 5+1 severe+2 severe+3 severe
100000000
200012468
3002615304661
40282664128192256
5052580195391586781

Never use explosives on a beaver dam or culvert plug. In one case a dynamited dam overloaded a 3-ft culvert and more than 300 ft of a 60-ft-high embankment failed, with the water travelling through old permeable fill from a buried timber bridge. After any high water is drawn down, the embankment is least stable for about 12–24 hours, while the confining water is gone but the fill is still saturated and seepage reverses. Beaver ponds are protected fish habitat under the Canadian Fisheries Act; permits are required, and penalties can reach $1,000,000 and imprisonment for individuals.

After Geotechnology for Railroaders Program, Module 6.5, Module 7.1, Module 4; Module 6.5 §02–06; Module 7.1 §04, §06. Full reference under Supplemental References.