A ground hazard fails when a triggering event acts on ground that is susceptible to it. The susceptibility is fixed by where the site is and how it was built (soils, geology, slope geometry, water, drainage); the trigger is the event that tips it over: a storm, a flood crest, a thaw, a blocked culvert, an excavation at the toe. Chapter 3.8 describes the mechanisms (Section 3.8.1 distinguishes mechanism, condition and trigger) and the trigger inventory (Section 3.8.11). This chapter puts the trigger at the head of the rating, because it is the thread that ties the rest together: it explains the defects, sets the live thresholds, and is what a solution must remove or resist.
Three things are named for every site:
| Driving mechanism (Section 3.8.23.3) | Typical triggers | How the trigger acts | Data used to rate and monitor it |
|---|---|---|---|
| Slope-driven | Prolonged or intense rainfall; snowmelt; rapid drawdown; toe excavation; added load (new track, fill, stockpiles); earthquake | Raises pore pressure or removes or loads the slope, lowering the factor of safety below 1.0 | Rainfall and antecedent wetness, snowmelt, river stage, construction records, seismic hazard maps |
| Scour-driven | Flood crest; ice jam; debris on a pier or culvert inlet; channel migration | Removes support at the toe, abutment or culvert outlet; oversteepens the bank | River gauges and flood categories, flow percentile, high-water marks, imagery sequence |
| Drainage-driven | Storm exceeding culvert or ditch capacity; blockage by debris, sediment or beavers; frozen culvert | Ponds water against or within the fill; saturates and softens it; causes piping or overtopping | Culvert capacity storm, 24-hour rainfall, beaver activity, inspection records |
| Subgrade-driven | Wet season; spring thaw after deep frost; increased tonnage or axle load | Softens the subgrade; causes pumping, ballast pockets and loss of bearing | Frost depth and thaw, soil moisture, tonnage records, geometry exception frequency |
| Subsidence-driven | Heavy rainfall or a broken pipe in karst; groundwater drawdown; mine void migration; wetting of collapsible soil | Washes soil into voids or collapses a void roof; collapses the soil structure | Karst and mine maps, rainfall, utility records, InSAR where available |
| Rock and debris | Freeze-thaw cycles; intense rainfall; root wedging; wildfire followed by rain; earthquake | Opens joints and loosens blocks; mobilizes debris flows | Freeze-thaw cycle counts, rainfall intensity, burn area maps, rockfall records |
Where two triggers act together, for example a flood that scours the toe followed by drawdown that fails the slope, record both and name the one that starts the sequence as the primary trigger.
The trigger rating scores how often the primary trigger reaches the level that this site has shown, or can be expected, to respond to. The levels use the same annual frequency bands as the frequency index (Table 3.8-14), so a trigger and a failure can be compared directly.
| T | Level | How often the trigger reaches the site's response level | Rationale |
|---|---|---|---|
| 5 | Acting now | The trigger is acting, or reaches the response level one or more times a year (for example, water ponds against the fill in most wet seasons) | A trigger that is present every year leaves no margin: any susceptibility the site has will be tested every year, so failure frequency is limited only by the ground. |
| 4 | Frequent | About 1 in 1 to 1 in 5 years (for example, the paired gauge reaches minor flood stage most years; the culvert overtops in a 2- to 5-year storm) | Events in this band are more likely than not to occur within a five-year maintenance or budget cycle (about 67% at the 1-in-5 edge, Section 3.8.30); the site will meet its trigger before most programs could fix it. |
| 3 | Occasional | About 1 in 5 to 1 in 25 years (for example, a 10-year storm exceeds the culvert capacity) | Likely within the working life of a track structure and of the people managing it; a credible design and planning event. |
| 2 | Rare | About 1 in 25 to 1 in 100 years | Within the range of events that railroad drainage and slopes are commonly designed for; failure from this trigger alone is unusual. |
| 1 | Remote | Less than 1 in 100 years, or no credible trigger for the site's mechanism | Beyond the usual design event; the site needs an extreme or unrecognized event to fail. |
Use the site's own response level (the stage, rainfall or thaw at which it has responded before) where it is known (Section 3.8.23.7). Where it is not known, use the design capacity (culvert capacity storm, flood stage at the toe) and score T no lower than 3 until the record shows otherwise. The trigger elements and their levels are in Section 3.8.27.2.
Every rating begins with a short narrative, written before the numbers, that links the site, the trigger and the evidence. It is the first thing a reviewer reads and the test the numbers must pass: if the narrative and the ratings disagree, one of them is wrong.
The narrative also sets the live rating: the trigger and its response level become the site's thresholds for the live rating of Section 3.8.26.