3.8.18 Triggering Mechanisms

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.18 Triggering Mechanisms

A ground hazard fails when a triggering event acts on ground that is susceptible to it. The susceptibility is fixed by where the site is and how it was built (soils, geology, slope geometry, water, drainage); the trigger is the event that tips it over: a storm, a flood crest, a thaw, a blocked culvert, an excavation at the toe. Chapter 3.8 describes the mechanisms (Section 3.8.1 distinguishes mechanism, condition and trigger) and the trigger inventory (Section 3.8.11). This chapter puts the trigger at the head of the rating, because it is the thread that ties the rest together: it explains the defects, sets the live thresholds, and is what a solution must remove or resist.

3.8.18.1 Preparatory Conditions, Triggers and Failure Modes

Three things are named for every site:

  • Preparatory conditions: the slowly changing conditions that bring the ground closer to failure (weathering, softening of a clay fill, a culvert silting up, a channel migrating toward the toe, loss of vegetation). They are scored in the geospatial rating (Section 3.8.19).
  • Triggering mechanism: the event that causes failure at a given time. It is scored by the trigger rating T (Section 3.8.18.3).
  • Failure mode: what the failure does to the track (loss of support, washout, settlement, slide, rockfall). It sets the severity S together with what the track carries.

3.8.18.2 Triggering Mechanisms by Driving Mechanism

Table 3.8-8. Common triggering mechanisms on railroad ground hazard sites
Driving mechanism (Section 3.8.23.3)Typical triggersHow the trigger actsData used to rate and monitor it
Slope-drivenProlonged or intense rainfall; snowmelt; rapid drawdown; toe excavation; added load (new track, fill, stockpiles); earthquakeRaises pore pressure or removes or loads the slope, lowering the factor of safety below 1.0Rainfall and antecedent wetness, snowmelt, river stage, construction records, seismic hazard maps
Scour-drivenFlood crest; ice jam; debris on a pier or culvert inlet; channel migrationRemoves support at the toe, abutment or culvert outlet; oversteepens the bankRiver gauges and flood categories, flow percentile, high-water marks, imagery sequence
Drainage-drivenStorm exceeding culvert or ditch capacity; blockage by debris, sediment or beavers; frozen culvertPonds water against or within the fill; saturates and softens it; causes piping or overtoppingCulvert capacity storm, 24-hour rainfall, beaver activity, inspection records
Subgrade-drivenWet season; spring thaw after deep frost; increased tonnage or axle loadSoftens the subgrade; causes pumping, ballast pockets and loss of bearingFrost depth and thaw, soil moisture, tonnage records, geometry exception frequency
Subsidence-drivenHeavy rainfall or a broken pipe in karst; groundwater drawdown; mine void migration; wetting of collapsible soilWashes soil into voids or collapses a void roof; collapses the soil structureKarst and mine maps, rainfall, utility records, InSAR where available
Rock and debrisFreeze-thaw cycles; intense rainfall; root wedging; wildfire followed by rain; earthquakeOpens joints and loosens blocks; mobilizes debris flowsFreeze-thaw cycle counts, rainfall intensity, burn area maps, rockfall records

Where two triggers act together, for example a flood that scours the toe followed by drawdown that fails the slope, record both and name the one that starts the sequence as the primary trigger.

3.8.18.3 Trigger Rating (T)

The trigger rating scores how often the primary trigger reaches the level that this site has shown, or can be expected, to respond to. The levels use the same annual frequency bands as the frequency index (Table 3.8-14), so a trigger and a failure can be compared directly.

Table 3.8-9. Trigger rating levels and rationale
TLevelHow often the trigger reaches the site's response levelRationale
5Acting nowThe trigger is acting, or reaches the response level one or more times a year (for example, water ponds against the fill in most wet seasons)A trigger that is present every year leaves no margin: any susceptibility the site has will be tested every year, so failure frequency is limited only by the ground.
4FrequentAbout 1 in 1 to 1 in 5 years (for example, the paired gauge reaches minor flood stage most years; the culvert overtops in a 2- to 5-year storm)Events in this band are more likely than not to occur within a five-year maintenance or budget cycle (about 67% at the 1-in-5 edge, Section 3.8.30); the site will meet its trigger before most programs could fix it.
3OccasionalAbout 1 in 5 to 1 in 25 years (for example, a 10-year storm exceeds the culvert capacity)Likely within the working life of a track structure and of the people managing it; a credible design and planning event.
2RareAbout 1 in 25 to 1 in 100 yearsWithin the range of events that railroad drainage and slopes are commonly designed for; failure from this trigger alone is unusual.
1RemoteLess than 1 in 100 years, or no credible trigger for the site's mechanismBeyond the usual design event; the site needs an extreme or unrecognized event to fail.

Use the site's own response level (the stage, rainfall or thaw at which it has responded before) where it is known (Section 3.8.23.7). Where it is not known, use the design capacity (culvert capacity storm, flood stage at the toe) and score T no lower than 3 until the record shows otherwise. The trigger elements and their levels are in Section 3.8.27.2.

3.8.18.4 The Trigger Narrative

Every rating begins with a short narrative, written before the numbers, that links the site, the trigger and the evidence. It is the first thing a reviewer reads and the test the numbers must pass: if the narrative and the ratings disagree, one of them is wrong.

Trigger narrative template. At [site], [preparatory conditions] make the [fill, cut or slope] susceptible to [failure mode] by a [driving mechanism] mechanism. Failure is most likely to be triggered by [primary trigger] when [response level or threshold], which occurs about [frequency] (T = [1–5]). The site has responded to this trigger [history of defects and failures]. Today, [current conditions and defects]; the current risk is therefore [rating]. The risk can be reduced by [removing the trigger, increasing resistance, or reducing exposure].

The narrative also sets the live rating: the trigger and its response level become the site's thresholds for the live rating of Section 3.8.26.