3.8.9 Traffic-Induced Settlement of Ballast and Subgrade

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.9 Traffic-Induced Settlement of Ballast and Subgrade

Repeated axle loads are a trigger in their own right. Each passing axle adds a small permanent strain in the ballast and in any soft fine-grained subgrade, and the sum shows up as loss of track surface and, in the subgrade, as ballast pockets and progressive shear failure. A UK research study of traffic effects on embankments found that the factors that matter most are axle load, the plasticity of the clay fill, and the thickness of ballast and ash cover over it. This section gives the power-law models used to predict the settlement and a diagnostic chart for drainage-related subgrade failure.

3.8.9.1 Settlement models and failure diagnosis

Equation 3.8-1. Ballast and subgrade cumulative strain

Ballast: εp = ε1 Nb, with ε1 ≈ 0.22% and b ≈ 0.21; N = MGT × 106 × 2,000/(2P)

Subgrade: εp = a(σd/σs)mNb (parameters a, b and m from the soil-type table in Chapter 2.1), N = MGT × 106 × 2,000/(4P); settlement = strain × layer thickness.

Both laws flatten with time. New ballast and newly compacted subgrade settle quickly at first. In an established track the ballast settles after each tamping as it recompacts (only the disturbed upper 6 in. or so), while the subgrade, after many years of traffic, settles at an almost constant small rate. A soft subgrade therefore dominates the settlement of new construction, and the ballast dominates once the line is established.

Table 3.8-4. Embankment vulnerability screen by share of high-plasticity clay fill (UK study)
High-plasticity clay fillVulnerability to traffic loading
Less than 10%Low
10 to 40%Moderate
40 to 90%High
90% or moreVery high

The screen uses fill plasticity only. Axle load, ballast thickness, track geometry, drainage, fill strength and hard spots (culverts, walls) must also be reviewed.

Table 3.8-5. Drainage-related subgrade failure: causes and signs (after a published fault-chart study)
FailureMechanismField signs
Progressive shear failureSubgrade surface remolded by repeated overstress; soil squeezes outward and upwardHeave at the ballast shoulder, depression under the track, water trapped beneath
Excessive plastic deformationCompaction and shear of a soft layer of substantial depthBallast pocket; little shoulder heave
Attrition with mud pumpingBallast grinds the wet subgrade surface into slurryWet spots, fines on the ballast surface, rapid loss of geometry
Other modesLiquefaction of saturated silt and fine sand; slope failure; consolidation; frost heave and thaw softening; swell-shrink; slope erosion; collapse on wettingSee Chapters 2.4 to 2.6, 6.2, 6.3 and 6.5

The fault chart splits causes into the train loading regime and the environment (rain, flooding, poor or poorly maintained drainage) and links them to subgrade failure, drainage deterioration and embankment or cut slope failure.

3.8.9.2 Worked example: soft CH subgrade under 75 MGT per year

Table 3.8-6. 33-kip wheels, 75 MGT/yr, 18 in. of soft CH at σd/σs = 0.6 (calculator output)
CaseFirst-year settlement
New ballast, 12 in. recompacting0.57 in.
Established ballast after tamping, 6 in. disturbed0.29 in.
New subgrade0.78 in.
Subgrade after 20 years of the same traffic0.012 in.

The ballast and new-subgrade values match the textbook example (0.57, 0.29 and 0.78 in.).

New construction on this soft clay would lose more surface from the subgrade than from the ballast in its first year. Twenty years on, the subgrade contribution is a few hundredths of an inch per year and surfacing cycles are governed by the ballast. If such a site keeps needing surfacing, the cause is more likely the ballast and drainage than continued subgrade consolidation (Chapter 6.4).

Open the traffic settlement calculator →
Ballast and subgrade settlement by year for a given tonnage and wheel load, for new or established track, with the fill-plasticity vulnerability screen.

3.8.9.3 Sources in the library

Paraphrased from these documents in the reference library.

  • Railway Geotechnics (Li, Hyslip, Sussmann and Chrismer, 2016), Chapter 4: ballast and subgrade deformation models and the track settlement example.Find source ↗
  • The Effects of Railway Traffic on Embankment Stability (UK rail safety research report, 2011): failure modes, axle load and fill plasticity, vulnerability classes.Find source ↗
  • Railway Track Subgrade Failure Mechanisms Using a Fault Chart Approach (Procedia Engineering, 2015).Find source ↗Library entry
  • An Empirical Rail Track Degradation Model (thesis), Ballast folder.Find source ↗
← Previous · 3.0 Risk Management Chapter 3.7 — Cost Estimates
Next · 3.0 Risk Management → Chapter 3.9 — Geotechnical Investigation Planning and Scope