3.8.41 Worked Example

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.41 Worked Example

A hypothetical main line fill, used only to illustrate the method. Alternative A assumes a subsurface investigation and analysis have been completed, so it earns full credit under Table 3.8-80.

Example 3.8-14: Current Risk and Risk Reduction for Three Alternatives

At a 22-ft fill of lean clay across a creek, a partly blocked 48-in. culvert makes the fill susceptible to softening and slope movement by a drainage-driven mechanism. The site was buttressed with a berm 15 years ago; today the track has been surfaced twice in 12 months and a bulge is forming downstream. The current risk is rated, and three alternatives are carried through the three risk reduction stages of Sections 3.8.37 to 3.8.39.

Main track48-in. culvert, partly blockedponded water (left)22 ftold berm, bulgeGivenLean clay fill; creek; blocked culvert; old bermL1–L5 = 4, 3, 3, 4, 5 (L5 × 2); L6 = 3Ponding about every 3 yr: T = 4Surfaced twice in 12 months; fresh bulgeMain line, moderate to heavy freight: S = 4RequiredCurrent risk R​cSolution, design/construct and post-stabilization ratings for A, B and CRisk reduction of eachBlack = given; red = required
Given and required for Example 3.8-14.

Given

VariableValueDescription
L1–L5, weights4, 3, 3, 4, 5; L5 weighted 2Lean clay fill; creek near the toe; blocked culvert
L63Past berm 15 years ago
T4Ponding about every 3 years
D4Same defects return between surfacing cycles; fresh bulge
S4, CriticalMain line, moderate to heavy freight
AlternativesA: replace culvert (100-yr), toe drain and berm; B: clean culvert only; C: monitoring with slow ordersInvestigation complete for A: full credit (Table 3.8-80)

Required

  • The current risk Rc
  • The solution, design and construct, and post-stabilization ratings of A, B and C
  • The risk reduction each one earns

Equations

  1. Eq. 1: L = (ΣwiLi + L6) / (Σwi + 1) — Equation 3.8-2
  2. Eq. 2: Fg = lesser of (L, T) — geospatial frequency
  3. Eq. 3: Fc from Fg and D — Table 3.8-11
  4. Eq. 4: R = F × S — risk score and rating, Table 3.8-16
  5. Eq. 5: ΔR = Rc − Rstage — risk reduction at each stage

Steps

Step 1 · Overall likelihood (Eq. 1)
Uses: L1–L6
L = (4 + 3 + 3 + 4 + 2 × 5 + 3) / 7 = 27 / 7
L = 3.86 → 4
Spot check: Weights sum to 7: five attributes, L5 counted twice, plus L6.
↓
Step 2 · Geospatial and current frequency (Eq. 2, 3)
Uses: L, T, D
Fg = lesser of (4, 4) = 4; Table 3.8-11, row 4, column 4
Fc = 4
Spot check: Fg is not ≥ D + 1, so no amplification.
↓
Step 3 · Current risk (Eq. 4)
Uses: Fc, S
Rc = 4 × 4
Rc = 16, High: act soon
Spot check: Table 3.8-17: slow order or increased inspection; stabilize in the next program.
↓
Step 4 · Solution ratings (Eq. 2–4)
Uses: Alternatives
A: T 4→1, L5 5→1, D expected 1 → F = 1. B: T 4→3, L5 5→3, Fg = 3, D stays 4 → F = 4. C: F stays 4, S 4→3 while in force
A: 4 Guarded; B: 16 High (interim); C: 12 High (interim)
Spot check: B: Table 3.8-11, row 3, column 4 gives 4, so the defects still govern.
↓
Step 5 · Design, construction and post-stabilization
Uses: Design criteria, work window
A: Fdes = 1; trench through fill Fcon = 5 with track out of service S = 3; provisional Fpost = 2, then 1 after a wet season with no movement and a maintenance plan
A: 15 High for the work window; 8 Elevated provisional; 4 Guarded verified
Spot check: 5 × 3 = 15 is High, which is why the work window is planned with the railroad.
↓
Step 6 · Risk reduction (Eq. 5)
Uses: Rc, verified ratings
A: 16 − 4; B: 16 − 16; C: no change in F
A: 12 points, two levels, once verified; B: none while defects continue; C: one level in S, interim
Spot check: Only A changes the rating band permanently.
↓
Solution
Rc = 16 High; A verified 4 Guarded; B 16 and C 12, both interim.

Table 3.8-83 records the current-risk inputs as they appear on the report.

Table 3.8-83. Worked example: current risk
InputValueReason
L1 to L5 (L5 weighted 2), L64, 3, 3, 4, 5 (×2), 3Lean clay fill; creek near the toe; blocked culvert; past berm
L(4 + 3 + 3 + 4 + 10 + 3) / 7 = 3.86 → 4Equation 3.8-2
T4Ponding about every 3 years
Fglesser of 4 and 4 = 4
D4Same defects return between surfacing cycles; fresh bulge
Fc4 (Table 3.8-11)Evidence governs; no amplification (Fg is not ≥ D + 1)
S4 CriticalMain line, moderate to heavy freight traffic
Current riskRc = 16, HighAct soon: slow order or increased inspection; stabilize in the next program

Solution

Table 3.8-84. Worked example: risk reduction ratings for three alternatives
StageA. Replace culvert (100-year capacity), toe drain and bermB. Clean culvert onlyC. Monitoring with slow orders
SolutionT 4→1, L5 5→1; D expected 1; Fsol = 1; S = 4; R = 4 GuardedT 4→3, L5 5→3; L = 3; Fg = 3; D stays 4 until movement stops; Fsol = 4; R = 16 High (interim)F unchanged 4; S 4→3 while the response is in force; R = 12 High (interim)
Design and constructCulvert for 100-year event; slope FS 1.5 with drained berm: Fdes = 1. Culvert trench through fill: Fcon = 5; with track out of service S = 3; R = 15 High for the work windowNo design; maintenance item: Fdes = FsolNot applicable
Post-stabilizationProvisional Fpost = 2; R = 8 Elevated. After one wet season with no movement and a culvert maintenance plan: Fpost = 1; R = 4 GuardedR = 16 High until defects stopR = 12 High while in force
Risk reductionHigh (16) to Guarded (4): 2 levels, 12 points, once verifiedNone while defects continueNone in F; one level in S, interim only

The site is High (16). Alternative A reaches a verified Guarded (4), a reduction of 12 points and two levels; B and C remain High and are interim. A is the only alternative that acts on the trigger and the resistance, and the only one that reaches a verified Guarded rating. B treats part of the trigger but not the movement already under way, so the defects, and the rating, stay. C manages exposure while a permanent fix is designed and is labeled interim.