A static hazard rating describes a site or segment under its usual, long-term conditions. It is built from information that changes slowly, if at all: where the line runs, what it is built on, what it carries, and its record of past trouble. Static ratings are used to choose which segments get a desktop study, to rank sites for field assessment, and to set the baseline that the live rating (Section 3.8.26) raises during weather events. They change only when new information arrives: a new data release, a field visit, a repair or a new failure.
Two static ratings are used, at two scales:
The Federal Railroad Administration introduced the Composite Hazard Index (CHI) to short line and regional railroads in an American Short Line and Regional Railroad Association (ASLRRA) webinar, Evaluating Railroad Infrastructure Exposure to Natural Hazards Using FRA’s Composite Hazard Index. The CHI is a screening index: it combines several natural hazard measures into one value for each segment of the rail network, so that segments can be compared and ranked by their exposure.
Underlying data. The federal hazard exposure data released for the rail network show what such an index is built from. The Bureau of Transportation Statistics (BTS) Hazard Exposure: Select North American Rail Network Lines layer (beta, October 2025) attaches hazard values to every main line and operational line segment of the North American Rail Network, across the 50 states and the District of Columbia. For each segment it carries:
The BTS layer reports each hazard separately and does not combine them; the CHI does the combining. At the time of writing, FRA had not published the CHI method (which inputs are used, how each is normalized and how they are weighted) in a form available for review. Before relying on a CHI value, confirm its inputs and weighting against FRA’s documentation.
Related research. A companion approach links recorded events, rather than modeled likelihood, to rail segments. Researchers at Oregon State University, working through the Mineta Transportation Institute, assigned flood, landslide and extreme heat and cold events from 2000 to 2023 to individual segments (flash floods by watershed hydrologic unit, riverine floods by river corridor, heat and cold by NWS forecast zone, landslides by proximity to the track) and checked the result against FRA accident records with weather-related cause codes, such as T002 for washout, rain, slide or flood damage to track. Their dataset is public and gives each segment a count of the events it has actually experienced. Where it is available, that count is the network-scale counterpart of the instability rating.
What the CHI does well. It covers the whole network on one consistent basis, needs no site work, and puts weather, flood, wildfire and ground hazards on the same footing. That makes it well suited to choosing which subdivisions and segments get a desktop study first, and to showing a funding agency that a line is more exposed than most.
What it cannot do. It describes exposure, not condition:
The CHI works from the network down; the situational, instability and live ratings work from the site and its trigger up. They answer different questions and are best used together. Table 3.8-28 compares them.
| Aspect | FRA Composite Hazard Index (network static) | Situational and instability ratings (site static) | River gauge monitoring (live) |
|---|---|---|---|
| Question answered | Which segments of the network are most exposed to natural hazards? | What makes this site susceptible, and what has happened here? | Is a water trigger happening now, or forecast, at this site? |
| Spatial unit | Rail network segment; hazard values mostly from tract, county or regional grids | Site circle or affected limits | Gauge point, applied to the sites paired with it |
| Time basis | Long-term: annualized frequency and modeled likelihood; static between releases | Historical record plus railroad records; static between visits | Real time (typically every 15 minutes to hourly) with NWS forecasts |
| Hazards covered | Weather and climate hazards, riverine and coastal flooding, wildfire, landslide index, sinkholes, storm surge | Geology, soils, slope, landslides, karst, mines, flooding, drainage, storms, frost, ground moisture, accidents | Riverine flooding, scour, backwater; ice jams where reported |
| Railroad condition and defects | Not included | Included, from railroad records (L6 and defect history) | Not included |
| Output | One index value per segment, for ranking | Attribute scores, Fp, Sp and a preliminary rating | Stage and flow against flood categories and percentiles; live rating |
| Effort | Low: look-up | Moderate: analyst time for each site | Low once set up; thresholds need calibrating |
| Main limitation | Exposure, not condition; regional resolution; method to be confirmed | Starts from flagged sites; depends on map scale and record completeness | Point measurement; ungauged drainages; water triggers only |
Using them together.
The preliminary site rating brings the two desk ratings together on the matrix of Table 3.8-16:
Rp = Fp × Sp
where Fp is read from Table 3.8-11 using the geospatial frequency (situational and instability attributes bounded by the trigger rating) and the defect rating from the records (Section 3.8.24.3) and Sp from the consequence attributes (Section 3.8.23.6). The rating is labeled preliminary until the EIC confirms or changes it in the field. Keep the attribute scores, LS, L, T, Fg, D, C and the trigger narrative with the site record: they show the field engineer why the site ranked where it did, and they let a program rank sites that share the same rating, by L × C.
Once a site has been assessed, its field rating replaces the preliminary rating as its static rating. It remains the static rating, and the baseline for the live rating, until the next visit, a repair or a new failure.
The preliminary rating sets how soon the site is visited and how much effort goes into the field assessment. The level of effort rises with the rating, so that borings and instruments go to the sites that need them.
| Preliminary rating | Priority | Field assessment | Level of effort | Monitoring until visited |
|---|---|---|---|---|
| Severe | 1 | Notify the railroad the same day; visit within days | Full assessment; plan exploration and instrumentation from the visit | Inspection after every trigger event; recommend operating restrictions until visited |
| High | 1 | Within two weeks | Full assessment; borings likely | Increased track inspection; gauge or rainfall trigger set |
| Elevated | 2 | Within the program cycle (typically 30 to 90 days) | Full assessment; exploration scoped from the findings | Routine inspection with trigger levels |
| Guarded | 3 | As the program allows; may be confirmed from track video or a hi-rail pass | Walk-through; full assessment if anything is found | Watch list; re-screen after a trigger event |
| Low | – | Not required | Desktop record only | Re-screen with the network screening or after an event |
For a program of many sites, the static rating also starts the sorting that the field assessment finishes. After the visit, sites usually fall into three groups: those ready to move to construction, those that need design, exploration or permits first, and those that can be monitored and deferred. The preliminary rating gives the first cut at that sorting; the field ratings and alternatives (Section 3.8.42) settle it.
The desk ratings of Examples 3.8-Y2 and 3.8-Y3 combine into the preliminary rating that scheduled the visit; the field rating of Example 3.8-3 then confirms or replaces it.
| Variable | Value | Description |
|---|---|---|
| Fp | 4 | Example 3.8-5 |
| Sp | 4 | Example 3.8-4 |
| Fc, S | 4, 4 | Field rating, Example 3.8-3 |
Rp = 16, High (preliminary), confirmed in the field at R = 16, High. From the date of the visit, High is the site’s static rating and the baseline for its live rating (Section 3.8.26).