The current risk combines two independent lines of evidence: the geospatial risk, which says what the location, its conditions and its trigger make likely, and the defect rating, which says what the track and the ground are actually showing. Neither is enough alone. A susceptible site with a frequent trigger can be sound today, and a site that looks benign on every map can be moving. The two are combined into the current frequency index Fc, which with the severity S gives the current risk rating.
The geospatial frequency is assembled at the desk from mapped and recorded data: the situational likelihood attributes L1 to L5 (soils, geology, slope geometry, hydrology, drainage), weighted for the driving mechanism, and the historic instability attribute L6, exactly as in Sections 3.8.23.4 and 3.8.24.3 (element criteria in Sections 3.8.27.3 and 3.8.27.4). It is then bounded by the trigger rating:
Rationale. A site cannot fail more often than the event that triggers it. Bounding L by T keeps a highly susceptible site with no credible trigger from rating as if it failed every year, and it makes the trigger narrative part of the number. Where the trigger is uncertain, T is scored no lower than 3 (Table 3.8-9), so the bound never hides an unrecognized trigger.
The defect rating scores the evidence that the ground is responding: track geometry defects and slow orders at the site, and the instability indicators recorded in the field (Table 3.8-25). Defect frequency is the best single measure of how fast a condition is developing (Section 3.8.24.4).
| D | Level | Defect and indicator evidence | Rationale |
|---|---|---|---|
| 5 | Active | Geometry defects return within weeks of surfacing; standing slow order or track removed from service; active cracking, bulging, settlement or erosion that is visibly progressing | The failure is under way; this is the field evidence that defines an Occurring frequency index (Table 3.8-14). |
| 4 | Recurring | The same defect returns between surfacing cycles (surfaced two or more times in 12 months at the same location), or a slow order in the last 12 months; fresh tension cracks or a growing bulge | Movement is continuing and outpacing maintenance; this is the evidence that defines Emerging. |
| 3 | Present | Defects reported more than once in the record but not returning between cycles, or indicators present (seepage, standing water at the toe, old cracks, a narrow shoulder) without signs of progress | The conditions for failure are showing at the surface, but movement is not demonstrated; consistent with Forming. |
| 2 | Historic | Past failures or repairs at the site, or a single defect in the record, with no current indicators | The site has failed before and may again under a large trigger; consistent with Dormant. |
| 1 | None | No defects in the record and no indicators in the field | No evidence that the ground has responded; frequency can be judged only from the geospatial rating. |
Record each defect with its measurement (in inches) and its frequency, as in Block 2 of the Ground Hazard Risk Assessment Report (Section 3.8.24.4). At the desk, D is scored from the defect and slow order records; in the field it is confirmed or changed from what is seen. The defect elements and their levels are in Section 3.8.27.5.
The rule has three parts, each with a reason:
| Geospatial Fg ↓ / Defect D → | D = 1 None | D = 2 Historic | D = 3 Present | D = 4 Recurring | D = 5 Active |
|---|---|---|---|---|---|
| Fg = 5 | 3 | 3 | 4 | 5 | 5 |
| Fg = 4 | 3 | 3 | 4 | 4 | 5 |
| Fg = 3 | 3 | 3 | 3 | 4 | 5 |
| Fg = 2 | 2 | 2 | 3 | 4 | 5 |
| Fg = 1 | 1 | 2 | 3 | 4 | 5 |
Read the row for Fg and the column for D. Where D is at or above Fg the defects govern; with little or no defect evidence the cap of 3 applies; the cells Fg = 4 or 5 with D = 3, and Fg = 5 with D = 4, carry the one-level amplification.
The current frequency index is the rating under usual conditions. During a weather or river event the live rating of Section 3.8.26 raises it while the trigger's threshold is exceeded, and returns it to Fc when the event has passed and the site has been checked. The trigger named in the narrative is the trigger the live rating watches.