Every rating in this chapter is built from two questions: how likely is the ground to fail, and how bad would a failure be? The first is answered by the frequency index (F); the second by the hazard severity (S). Each is scored on five levels, and the two are combined into a risk score and a risk rating. The situational, instability, static and live ratings in the sections that follow are not separate systems: they are different ways of arriving at F and S, and they all end on the same matrix. A site rated Elevated at the desk, on a live map or on the field form means the same thing in every case. Figure 3.8-39 shows how the pieces fit together.
Every scale in this chapter runs from 1 to 5, and risk increases with the number. This holds for the situational and instability attributes (L1 to L6 and C1 to C5), the frequency index, the hazard severity, the live frequency index and the risk rating itself. Where the evidence for an attribute is missing, it is scored 3, the middle of the scale, and flagged for the field visit. Table 3.8-13 shows where each scale is used.
| Scale | Symbol | Range | Set from | Section |
|---|---|---|---|---|
| Situational likelihood attributes | L1–L5 | 1–5 each | Location and inherent conditions: soils, geology, slope, hydrology, drainage | 3.8.23 |
| Consequence attributes | C1–C5 | 1–5 each | Track, traffic, train type, what lies below, size of failure, redundancy | 3.8.23 |
| Instability attribute and defect rating | L6, D | 1–5 each | Past failures; geometry defects, slow orders and field indicators (Table 3.8-10) | 3.8.24 |
| Frequency index | F (preliminary Fp) | 1–5 | Geospatial frequency Fg (L1–L6 bounded by trigger rating T) with defect rating D, Table 3.8-11; desk D from records, field D from indicators | 3.8.22.2, 3.8.24, 3.8.25; 3.8.19 |
| Hazard severity | S (preliminary Sp) | 1–5 | Desk: C1–C5. Field: exposure confirmed in Block 1 | 3.8.22.3, 3.8.23 |
| Live frequency index | Flive | 1–5 | F raised by live weather, river and ground data | 3.8.26 |
| Risk score | R = F × S | 1–25 | Product of the two scales; used only to place the site in a rating | 3.8.22.4 |
| Risk rating | — | Low (1) to Severe (5) | Risk matrix, Table 3.8-16 | 3.8.22.4 |
The frequency index describes the state of the hazard, which sets how often a failure can be expected. The worksheet calls this scale the Annual Failure Frequency Index. It is selected from the evidence of instability (Section 3.8.24); the indicative annual frequencies in Table 3.8-14 help when two levels seem to fit.
| Level | F | Field evidence | Indicative annual frequency of failure |
|---|---|---|---|
| Occurring | 5 | Failure under way: movement, settlement or erosion is active and the track is already affected; repeated slow orders or surfacing | 1 or more per year |
| Emerging | 4 | Clear signs developing: fresh tension cracks, a growing bulge, or geometry defects that return between surfacing cycles | About 1 in 1 to 1 in 5 years |
| Forming | 3 | Conditions for failure present (water against the embankment, an over-steepened slope, a blocked culvert), but the ground is not yet moving | About 1 in 5 to 1 in 25 years |
| Dormant | 2 | Evidence of past instability, but no sign that it is active now; a trigger such as extreme rainfall could reactivate it | About 1 in 25 to 1 in 100 years |
| Inactive | 1 | No evidence of instability, or the cause has been removed | Less than 1 in 100 years |
The hazard severity describes the consequence if the failure happens. It is judged from the exposure of the site: traffic, speed, train type, the number of tracks, the population density factor and what lies below and beside the track. At the desk it comes from the consequence attributes of Section 3.8.23; in the field it is confirmed from Block 1 of the report. Where the consequence and the typical setting point to different levels, the consequence governs.
| Level | S | Consequence of failure | Typical setting |
|---|---|---|---|
| Catastrophic | 5 | Derailment or loss of track support likely to cause fatalities, a hazardous materials release or loss of a structure | Main line with passenger or hazardous materials traffic, over water, a road or a populated area; outage longer than a week |
| Critical | 4 | Derailment or main line outage likely; serious injury possible; major property damage | Main line, moderate to heavy traffic; outage of several days |
| Serious | 3 | Track out of service or under a restrictive slow order; damage confined to railroad property | Main line with light traffic, or busy siding; outage of hours to a day |
| Minor | 2 | Geometry defect needing surfacing or a temporary slow order; no derailment expected | Secondary, industry or yard track |
| Low | 1 | Maintenance-level effect only; no effect on train operations | Any track |
Severity is a property of the site and what it carries, not of the weather or the state of the ground. It does not change in a live event (Section 3.8.26) and usually does not change when a site is stabilized; it changes only when the traffic, the track or the exposure changes.
The risk score is the product of the two scales:
R = F × S (1 to 25)
The score has one job: to place the site in one of five risk ratings. Table 3.8-16 gives the rating for every combination of F and S. Because R is a product, neither scale can be ignored: a Catastrophic site stays at Elevated or above until the cause is removed (Inactive), and a site with Low severity never rates above Guarded.
| Frequency index (F) | Hazard severity (S) | ||||
|---|---|---|---|---|---|
| Catastrophic (5) | Critical (4) | Serious (3) | Minor (2) | Low (1) | |
| Occurring (5) | Severe25 | Severe20 | High15 | Elevated10 | Guarded5 |
| Emerging (4) | Severe20 | High16 | High12 | Elevated8 | Guarded4 |
| Forming (3) | High15 | High12 | Elevated9 | Elevated6 | Guarded3 |
| Dormant (2) | Elevated10 | Elevated8 | Elevated6 | Guarded4 | Low2 |
| Inactive (1) | Guarded5 | Guarded4 | Guarded3 | Low2 | Low1 |
The product weights F and S equally. The extra weight on consequence that Section 1.1.2 calls for comes from three rules for selecting S: the consequence floor in the situational rating (Section 3.8.23.6), “the consequence governs” (Table 3.8-15), and the engineer’s one-level adjustment (Section 3.8.22.6).
Each rating carries a required response and a category from the risk resolution matrix of Section 1.1.7, so a site rated in this chapter can be carried directly into a railroad’s corridor-level risk register.
| Level | Rating | Risk score R | Required response | Category (Section 1.1.7) |
|---|---|---|---|---|
| 5 | Severe | 20–25 | Act now: on-site protection and operating restrictions; immediate stabilization | Unacceptable |
| 4 | High | 12–16 | Act soon: slow order or increased inspection; stabilization in the next program | Unacceptable |
| 3 | Elevated | 6–10 | Plan: monitor, design and schedule stabilization | Tolerable with Mitigation |
| 2 | Guarded | 3–5 | Watch: routine inspection with defined trigger levels | Tolerable with Mitigation |
| 1 | Low | 1–2 | No action beyond routine inspection | Tolerable |
The same six steps are used whether the rating is made at the desk, on a live map or in the field. Only the source of F and S changes.
Each stabilization alternative is rated on the same matrix, as the site would be once that alternative is built. Most stabilization work lowers F by removing the cause (a drained embankment moves from Forming to Dormant or Inactive), while S usually stays the same because the track, traffic and setting do not change. An alternative that lowers S, such as track realignment away from the top of the slope, should say why. An alternative that leaves the site at High or above is at best an interim measure and should be labeled as one. Reading the current rating against the alternative ratings and the cost ranges of Section 3.8.42.6 gives the railroad the cost of each step of risk reduction.
Each alternative is rated in the three stages of Sections 3.8.37 to 3.8.39: the solution rating, as the site would be once the alternative works as intended (Section 3.8.37); the design rating earned by the design criteria, with a construction-stage rating for the risk while the work is built (Section 3.8.38); and the post-stabilization rating, provisional until the works have performed through a triggering event and are maintained, then verified (Section 3.8.39). The ratings in Table 3.8-18 are solution ratings; the field report carries them, and the design and post-stabilization ratings are added as each alternative is designed, built and verified.
A single main track runs on the outside of a curve, on a 25-ft fill across a creek floodplain. The site is rated on the report as found, and three stabilization alternatives are rated as the site would be once each works. One site carried through four examples: the field rating and its alternatives here, then the desk ratings that came before the visit in Sections 3.8.23 to 3.8.25.
| Variable | Value | Description |
|---|---|---|
| Site | Single main track on a curve; 25-ft fill across a creek floodplain | Setting |
| Traffic | 28 trains a day including hazardous materials; 50 mph | Exposure for S |
| Drainage | 36-in. culvert half blocked; water about 3 ft higher on the left | Trigger evidence |
| Field indicators | Seepage at mid-slope; fresh tension cracks along the left shoulder | Defect evidence |
| Records | Four cross level exceptions since the last slow order | Defect evidence |
| Fg | 4 | Geospatial frequency from the desk (Section 3.8.24.7) |
| Alternatives | 1: clear culvert and regrade ditches; 2: Alternative 1 plus lateral drains and toe berm; 3: soldier piles and lagging | To be rated |
| Condition | Frequency index | Hazard severity | R | Rating |
|---|---|---|---|---|
| Current condition | Emerging (4) | Critical (4) | 16 | High |
| Alternative 1: clear culvert and regrade ditches (interim) | Emerging (4) | Critical (4) | 16 | High |
| Alternative 2: Alternative 1 plus lateral drains and toe berm | Inactive (1) | Critical (4) | 4 | Guarded |
| Alternative 3: soldier piles and lagging along the shoulder | Inactive (1) | Critical (4) | 4 | Guarded |
The site rates High (Emerging 4 × Critical 4 = 16). Alternative 1 stays High and is an interim measure; Alternatives 2 and 3 both reach Guarded (4).
Alternative 1 is quick and inexpensive and removes the ponding, but the fill is already cracked and the defects are recurring (D = 4). Removing the trigger alone does not earn a lower defect rating, so its solution rating stays High (Section 3.8.37.2). If a wet season then passes with no movement, its post-stabilization rating can fall to Dormant and Elevated (R = 8), the same treatment the clean-culvert alternative receives in Section 3.8.41. Alternative 2 costs less than Alternative 3 and is built in about 3 months, against more than a year (Section 3.8.42.8). The recommendation is Alternative 1 now, followed by Alternative 2.
The same site is followed through the desk in Sections 3.8.23 to 3.8.25, to show how its preliminary rating is assembled before the visit. With the scales defined, the next section turns to the first input: what the site’s location and inherent conditions make possible.