3.8.38 Risk Reduction Ratings: Design and Construct

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.38 Risk Reduction Ratings: Design and Construct

The design and construction stage rates two things: the reduction the design actually earns, and the risk while the work is built.

3.8.38.1 Design Rating (Fdes)

The design rating replaces the judgment of the solution rating with the design criteria the works meet. The levels follow the indicative annual frequencies of Table 3.8-14, so a design event and a frequency index mean the same thing.

Table 3.8-81. Frequency index credited by the design and rationale
MechanismDesign criterion metFdesRationale
SlopeLong-term static factor of safety ≥ 1.5 under the design groundwater, with the trigger controlled (Section 6.3.5)1The commonly accepted long-term margin; a much larger event than the design condition is needed to fail the slope.
SlopeFactor of safety 1.3 to under 1.52Adequate for many conditions but with less margin for unknowns in strength and groundwater.
SlopeFactor of safety 1.1 to under 1.33Marginal; acceptable only as a temporary or short-term condition.
SlopeFactor of safety under 1.1no creditNot distinguishable from limiting equilibrium given normal uncertainty.
Hydraulic (culvert, channel, scour)Capacity and countermeasures for the 100-year event or larger, with scour checked at the 500-year event1Matches the Inactive band (less than 1 in 100 years) and common practice for scour-critical structures.
HydraulicDesign event 25- to 100-year2Matches the Dormant band.
HydraulicDesign event 5- to 25-year3Matches the Forming band.
HydraulicDesign event under 5-yearno creditThe trigger will still reach the site within a normal maintenance cycle.
SubgradeSubgrade and track section meet the design criteria of Chapter 2.3 for the traffic, with drainage1 to 21 where drainage and bearing both meet the criteria with margin; 2 where they depend on maintenance.
SubsidenceVoids treated and verified, or the track bridged over the zone2 (1 if bridged or relocated)Treatment addresses known voids; new ones can still form nearby.
Rock and debrisScaling, bolting or catchment designed for the design block size and energy2 (1 if all mapped blocks are stabilized and the catchment is verified)Catchment manages, but does not prevent, release.

Where several mechanisms apply, use the highest Fdes among them. Fdes may not be lower than the solution rating's Fsol unless the design shows why.

3.8.38.2 Construction-Stage Rating

Construction can raise the risk before it lowers it: a culvert trench cut through a fill, an excavation at the toe, or heavy equipment on a marginal slope all reduce resistance for a time. The construction-stage rating is the risk during the work:

Equation 3.8-15. Construction-stage frequency
Fcon = Fc + 1 (maximum 5) where the work temporarily reduces resistance or adds load; otherwise Fcon = Fc
  • Temporary measures that change what a failure would reach (track out of service, slow orders with monitoring, temporary shoring designed for the stage) may lower S for the construction stage by one level, as in Table 3.8-80.
  • A construction stage rated Severe requires the track to be protected or out of service for that stage.
  • Record the expected duration of construction; the current risk continues until the works are complete.