↑ Parent Menu⌂ Main Menu
← Chapter 3.8 Risk Ratings and Ground Hazard Risk Assessment
GHRM
Railway Ground Hazard Risk Management · 3.0 · Risk Management
Sections · open a dropdown to go to a section or subsection

3.8.46 Practice Questions

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.46 Practice Questions
Each question is worked in the same five parts as the examples. Try the question from the Given and Required before opening the steps. Questions 3.8-1 to 3.8-4 cover the failure mechanisms and 3.8-5 to 3.8-8 the risk ratings. Questions 3.8-1, 3.8-4 and 3.8-8 are reasoning questions; their steps are the chain of reasoning rather than a chain of equations.
Question 3.8-1: Predisposing Condition, Preparatory Factor or Trigger

Problem Statement

A Class I railroad is preparing a hazard register for a line through hilly clay country. Four factors are being entered for one embankment: a sensitive clay deposit, a culvert corroding over 20 years, a 100-year storm, and tonnage on the line doubling over a decade. The engineer must classify each as a predisposing condition, a preparatory factor or a trigger.

Classifying each factor correctly matters because each kind calls for a different response: a predisposing condition is designed around, a preparatory factor is stopped, and a trigger is watched.

(a) Sensitive clay depositclass = ?(b) Culvert corroding 20 yrclass = ?(c) 100-year stormclass = ?(d) Tonnage doubling, 10 yrclass = ?Predisposing: fixed by the sitePreparatory: slowly erodes the marginTrigger: causes failure at a given momentClassify (a) to (d)GivenFour factors at one embankmentCriteria: Section 3.8.1RequiredClass of each factor (a) to (d)Black = given; red = required
Given and required for Question 3.8-1.

Given

VariableValueDescription
(a)A sensitive clay depositFactor to classify
(b)A culvert corroding over 20 yearsFactor to classify
(c)A 100-year stormFactor to classify
(d)Tonnage on the line doubling over a decadeFactor to classify
CriteriaSection 3.8.1Predisposing: fixed by the site. Preparatory: slowly erodes the margin over time. Trigger: the event that causes failure at a given moment.

Required

  • The class of each factor (a) to (d)

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Does the factor change with time?
(a) No: predisposing. (b), (c), (d) change: go on.
Spot check: Sensitive clay is a property of the deposit; nothing the railroad does changes it.
↓
Step 2 · Does it act slowly or at one moment?
(b) and (d) act slowly: preparatory. (c) acts at one moment: trigger.
Spot check: A corroding culvert and rising tonnage reduce the margin a little each year; a storm is a single event.
↓
Solution
(a) predisposing; (b) preparatory; (c) trigger; (d) preparatory.

Solution

(a) Predisposing condition. (b) Preparatory factor. (c) Trigger. (d) Preparatory factor.

Tonnage is usually preparatory, because it wears the margin down over years. It can also act as a trigger when a single step change, such as heavier cars introduced at once, pushes a marginal subgrade past its limit. The classification therefore depends on how fast the change happens, not only on what it is.

Question 3.8-2: Saturated Fraction That Brings the Slope to Failure

Problem Statement

The railroad embankment slope of Example 3.8-1 is to be instrumented with piezometers, and the railroad wants an alarm level. The engineer must find the saturated fraction of the slipping depth at which the slope reaches a factor of safety of 1.0, and the corresponding height of water above the slip surface.

Example 3.8-1 gave the factor of safety for three water levels. This question turns the calculation around and asks how high the water must rise for the slope to fail, which is the number a monitoring program would set its alarm against.

slip surfacez = 6 ft (vertical, arrow)β = 26.6° (2H:1V)water height m·z = ? (red)m at FS = 1.0 = ?Givenτd = 288 psf; σ = 576 psfc′ = 50 psf; tanφ′ = 0.625u = 299.5 m psfTarget FS = 1.0RequiredSaturated fraction m at FS = 1.0Water height m × z (alarm level)Black = given; red = required
Given and required for Question 3.8-2.

Given

VariableValueDescription
SlopeAs Example 3.8-1τd = 288 psf; σ = 576 psf; c′ = 50 psf; tanφ′ = 0.625
u299.5 m psfPore pressure as a function of the saturated fraction m (Example 3.8-1, Step 4)
FS1.0Target condition: limiting equilibrium

Required

  • The saturated fraction m at which FS = 1.0
  • The height of water above the slip surface, m × z

Equations

  1. Eq. 1: FS = [c′ + (σ − u) tanφ′] / τd — infinite-slope factor of safety
  2. Eq. 2: u = 299.5 m — pore pressure for this slope

Steps

Step 1 · Set FS = 1.0 and substitute Eq. 2 into Eq. 1
50 + (576 − 299.5 m) × 0.625 = 288
410 − 187.2 m = 288
↓
Step 2 · Solve for m
m = (410 − 288) / 187.2 = 122 / 187.2
m = 0.65
Spot check: Back-substitute: u = 299.5 × 0.65 = 195 psf; [50 + (576 − 195) × 0.625] / 288 = 288 / 288 = 1.00.
↓
Step 3 · Height of water above the slip surface
Uses: m, z = 6 ft
0.65 × 6
About 3.9 ft above the slip surface
↓
Solution
m = 0.65: failure when water rises to about two-thirds of the slip depth.

Solution

m = 0.65. The slope fails when the water table rises to about two-thirds of the slipping depth, about 3.9 ft above the slip surface.

The answer falls between the half-saturated case (FS = 1.10) and the fully saturated case (FS = 0.77) of Example 3.8-1, as it must. A piezometer at this site would set its warning level well below m = 0.65, for example at m = 0.4 to 0.5, so there is time to act before failure.

Question 3.8-3: A Long, Moderate Storm Against the Caine Threshold

Problem Statement

A Class I railroad uses a rainfall threshold to decide when to send patrols ahead of trains on a line with a history of debris flows. A storm delivered 3.0 in. of rain over 24 hours. The engineer must compute the average intensity and decide whether the storm exceeded the Caine threshold.

A long storm can deliver more rain than a short one and still fall below the threshold, because the threshold intensity drops as the duration grows. This question checks a 24-hour storm.

0.1110100Duration D (hr, log)Intensity I (in./hr, log)0.010.1110Caine (1980): I = 0.58 D−0.39D = 24 hr: I = ? Exceeds?GivenP = 3.0 in.D = 24 hrI = 0.58 D−0.39 (in./hr)RequiredAverage intensity and threshold at 24 hrIs the threshold exceeded?Black = given; red = required
Given and required for Question 3.8-3.

Given

VariableValueDescription
P3.0 in.Storm rainfall
D24 hrStorm duration
ThresholdI = 0.58 D−0.39Caine (1980), in./hr

Required

  • Average intensity and the threshold at 24 hours
  • Whether the storm exceeds the threshold

Equations

  1. Eq. 1: I = P / D — average intensity
  2. Eq. 2: It = 0.58 D−0.39 — threshold intensity

Steps

Step 1 · Storm intensity I (Eq. 1)
I = 3.0 / 24
I = 0.125 in./hr
Spot check: 0.125 × 24 = 3.0 in.
↓
Step 2 · Threshold intensity It (Eq. 2)
240.39 = 3.45; It = 0.58 / 3.45
It = 0.17 in./hr
Spot check: ln 24 = 3.18; 0.39 × 3.18 = 1.24; e1.24 = 3.45.
↓
Step 3 · Compare
0.125 in./hr against 0.17 in./hr
I < It: the storm does not exceed the threshold
Spot check: Ratio 0.125 / 0.17 = 0.74.
↓
Solution
The storm does not exceed the threshold (0.125 < 0.17 in./hr).

Solution

No. At 0.125 in./hr the storm is below the 24-hour threshold of 0.17 in./hr.

This storm delivers 50% more rain than the one in Example 3.8-2 and still falls below the threshold. The comparison shows why intensity, not total rainfall, governs. It does not close the matter: wet antecedent conditions or a locally calibrated threshold could still call for a response.

Question 3.8-4: Why Diagnose the Mechanism Before the Repair

Problem Statement

A Class I railroad has had a series of slides at one cut and wants to order a repair quickly, before the cause has been studied. The engineer must explain why the failure mechanism, and not only the trigger, should be diagnosed before a repair is selected.

This is a reasoning question. It is answered from the principles of Section 3.8.1 and the control hierarchy of Section 1.1.9.

Same symptomtrack dip / slideMechanism Ae.g. seepageMechanism Be.g. weak layerMechanism Ce.g. erosionRepair A?Repair B?Repair C?Why diagnose the mechanism first?GivenRepeated slides at one cutPrinciple 1: one symptom, many mechanismsPrinciple 2: remove the hazard ranks above managing exposureRequiredWhy the mechanism, not just the trigger, must be diagnosed firstBlack = given; red = required
Given and required for Question 3.8-4.

Given

VariableValueDescription
Principle 1Section 3.8.13The same symptom can come from different mechanisms.
Principle 2Section 1.1.9Controls that remove or reduce the hazard rank above those that only manage exposure.

Required

  • Why the mechanism, and not just the trigger, must be diagnosed before a repair is selected

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · What does a repair act on?
A repair works only if it acts on the mechanism that is failing the ground.
↓
Step 2 · What happens if the mechanism is wrong?
Money is spent and the hazard stays. Example: undercutting ballast where the cause is a deep-seated slide.
↓
Step 3 · What happens if only the trigger is managed?
The hazard stays in place, and the railroad relies on patrols and slow orders indefinitely.
↓
Solution
Diagnose the mechanism, or the repair may treat the wrong problem.

Solution

Because the same symptom can come from different mechanisms, and a repair aimed at the wrong one spends money without reducing the hazard.

Managing only the trigger, with patrols or speed restrictions, leaves the hazard in place and commits the railroad to those restrictions indefinitely. Inclinometers and piezometers cost little compared with a buttress built for the wrong failure surface, which is why Section 3.8.16 recommends confirming the mechanism with instruments before committing capital.

Question 3.8-5: Current Frequency When the Defects Are Light

Problem Statement

A Class I railroad located in Kentucky has a side-hill fill on a main line where the desk study gives a geospatial frequency Fg = 4 and a severity S = 3. The geometry records show defects reported more than once but not returning between surfacing cycles (D = 3). The roadmaster asks what the rating would be if the records had shown no defects at all (D = 1).

The current frequency index is not the higher of Fg and D. Table 3.8-11 caps susceptibility without movement at Forming, and amplifies light defects at a highly susceptible site. This question exercises both rules.

51015202548121620369121524681012345D = 3D = 1Severity S →Frequency F →GivenF​g = 4 (desk)S = 3, SeriousCase 1: D = 3 (Present)Case 2: D = 1 (None)RequiredF​c for each case (Table 3.8-11)R and rating for each caseWhy the two differBlack = given; red = required
Given and required for Question 3.8-5.

Given

VariableValueDescription
Fg4Geospatial frequency from the desk study
S3Serious: main line with light traffic
D3 or 1Defect rating, case 1 and case 2 (Table 3.8-10)
RuleEquation 3.8-3Fc = the greater of D and the lesser of (Fg, 3), plus 1 where D ≥ 3 and Fg ≥ D + 1

Required

  • Fc, R and the rating for D = 3 and for D = 1
  • The reason for the difference

Equations

  1. Eq. 1: Fc = max[D, min(Fg, 3)] (+1 if D ≥ 3 and Fg ≥ D + 1) — Equation 3.8-3, Table 3.8-11
  2. Eq. 2: R = Fc × S — risk score, Table 3.8-16

Steps

Step 1 · Case 1, D = 3 (Eq. 1)
Uses: Fg, D
max[3, min(4, 3)] = 3; D ≥ 3 and Fg = 4 ≥ D + 1 = 4, so add 1
Fc = 4, Emerging
Spot check: Table 3.8-11, row Fg = 4, column D = 3 reads 4.
↓
Step 2 · Case 1 rating (Eq. 2)
Uses: Fc, S
R = 4 × 3
R = 12, High
Spot check: 12 is the lower edge of High.
↓
Step 3 · Case 2, D = 1 (Eq. 1)
Uses: Fg, D
max[1, min(4, 3)] = 3; D < 3, no amplification
Fc = 3, Forming
Spot check: Table 3.8-11, row 4, column 1 reads 3: the cap.
↓
Step 4 · Case 2 rating (Eq. 2)
Uses: Fc, S
R = 3 × 3
R = 9, Elevated
Spot check: One level lower than case 1 from a single step in F.
↓
Solution
D = 3: Fc = 4, R = 12 High. D = 1: Fc = 3, R = 9 Elevated.

Solution

With D = 3 the site is Emerging and High (12); with no defects it is Forming and Elevated (9). Without evidence of movement, a susceptible setting can only make a site Forming: Emerging and Occurring require signs at the track (Table 3.8-14). Light defects at a site that susceptible are taken as the start of a response that will be tested again soon, so the rating is raised one level. The desk rating with D = 1 is a reason to visit early, not proof of activity.

Question 3.8-6: Live Rating During a River Rise

Problem Statement

A Class I railroad located in Iowa has a fill along a river whose static rating is Forming (F0 = 3) and Critical (S = 4). A spring storm is forecast. The paired gauge is forecast to reach action stage (Watch), and the forecast 24-hour rainfall is 60% of the site threshold (Watch). Soil moisture is normal. The dispatcher asks for the live rating and the response.

The live rating raises F by the increments of Table 3.8-32 while indicators are at Watch or Warning. S does not change with the weather.

51015202548121620369121524681012345staticliveSeverity S →Frequency F →GivenStatic: F​0 = 3, S = 4 (R = 12, High)River forecast at action stage: WatchRainfall at 60% of threshold: WatchSoil moisture: NormalRequiredIncrement and F​liveR​live and ratingResponse and when to drop itBlack = given; red = required
Given and required for Question 3.8-6.

Given

VariableValueDescription
F0, S3, 4Static rating: R = 12, High
RiverForecast at action stageWatch (Table 3.8-31)
Rainfall60% of the site thresholdWatch: half the threshold up to the threshold
Soil moistureNormalNo increment
RuleTable 3.8-32+1 for one Watch; +2 for two or more Watch or any Warning; F = 5 on river or rain Warning where F0 ≥ 4; maximum 5

Required

  • The increment, Flive, Rlive and the rating
  • The response, and when the live rating may be dropped

Equations

  1. Eq. 1: Flive = min(5, F0 + increment) — Table 3.8-32
  2. Eq. 2: Rlive = Flive × S — read from Table 3.8-16

Steps

Step 1 · Count the indicators
Uses: River, rainfall, soil moisture
Two indicators at Watch; none at Warning
Increment = +2
Spot check: The “set F to 5” rule does not apply: no Warning, and F0 = 3 is below 4.
↓
Step 2 · Live frequency (Eq. 1)
Uses: F0, increment
min(5, 3 + 2)
Flive = 5
Spot check: The maximum is not exceeded, so no truncation.
↓
Step 3 · Live rating (Eq. 2)
Uses: Flive, S
Rlive = 5 × 4
Rlive = 20, Severe
Spot check: Reported as a jump: High → Severe (Section 3.8.26.4).
↓
Step 4 · Response and hold
Uses: Table 3.8-17; Section 3.8.26.5
Act now: protect the track and restrict operations until inspected
Hold until the river is below action stage and 48 h after the crest or end of rain
Spot check: Fills along rivers often fail on the falling limb, so the rating is not dropped at the crest.
↓
Solution
Flive = 5; Rlive = 20, Severe (jump from High).

Solution

Two Watch indicators raise F from 3 to 5, and the rating jumps from High (12) to Severe (20). The response is to act now: inspect before and after the crest and restrict operations until the site has been checked. The rating is held until the river is back below action stage and at least 48 hours have passed, because many embankments fail as the water falls. Wet ground and heavy rain together are treated as more than either alone, which is why two Watches count as much as one Warning.

Question 3.8-7: Credit for a Solution Proposed from the Desk

Problem Statement

A Class I railroad located in Pennsylvania has a fill rated Emerging (F = 4) and Critical (S = 4). The consultant proposes a drained toe berm from a desk study only; no borings have been drilled. Rescored as built, the berm gives Fsol = 1. The program manager wants to enter the solution rating in the capital plan.

Table 3.8-80 caps the risk reduction a solution can claim according to the level of investigation behind it, so that an unproven fix does not outrank a proven one.

51015202548121620369121524681012345currentuncappedcappedSeverity S →Frequency F →GivenCurrent: F = 4, S = 4 (R = 16, High)Berm as built: F​sol = 1, S = 4Investigation level: desk study onlyCap: desk study, at most one levelRequiredUncapped solution ratingCapped solution rating to reportWhat earns full creditBlack = given; red = required
Given and required for Question 3.8-7.

Given

VariableValueDescription
F, S4, 4Current rating: R = 16, High
Fsol1Rescored as the berm would perform once built (Section 3.8.37.2)
InvestigationDesk study onlyNo subsurface investigation or analysis
CapTable 3.8-80Desk study: at most one level; field reconnaissance: two; subsurface investigation and analysis: full credit

Required

  • The uncapped solution rating
  • The capped solution rating to report
  • What would earn full credit

Equations

  1. Eq. 1: R = F × S — risk score and rating, Table 3.8-16

Steps

Step 1 · Uncapped rating (Eq. 1)
Uses: Fsol, S
R = 1 × 4
R = 4, Guarded
Spot check: High to Guarded is a drop of two levels (High, Elevated, Guarded).
↓
Step 2 · Apply the cap
Uses: Table 3.8-80
Desk study allows one level: High → Elevated at best
Capped rating: Elevated
Spot check: Two levels claimed, one allowed.
↓
Step 3 · Report it
Uses: Section 3.8.43
Enter the lowest F that gives Elevated with S = 4: F = 2, R = 8, with the reason
R = 8, Elevated (capped: desk study)
Spot check: 2 × 4 = 8 is Elevated; 1 × 4 = 4 would not be allowed.
↓
Solution
Report Elevated (R = 8), capped from Guarded (4) until borings and analysis confirm the mechanism.

Solution

As built the berm would rate Guarded (4), but from a desk study it may claim only one level of reduction, so the solution rating entered in the plan is Elevated (8), marked as capped. Without a confirmed mechanism and ground model, the berm could be treating the wrong problem. A subsurface investigation and stability analysis that confirm the slip surface and the drained strength earn the full credit, and the solution rating then moves to Guarded. The cap is what keeps an unproven idea from outranking a proven design in the capital plan.

Question 3.8-8: Ranking Two Sites with the Same Score

Problem Statement

A Class I railroad located in Ohio has two sites on the same subdivision, each with a risk score of 12. Site A is Emerging (F = 4) with a Serious consequence (S = 3). Site B is Forming (F = 3) with a Critical consequence (S = 4). There is money to stabilize one site this year, and the manager asks which comes first.

R places a site in a rating; it does not measure risk in proportion. Table 3.8-77 gives the rule for ordering sites within a rating.

51015202548121620369121524681012345ABSeverity S →Frequency F →GivenSite A: F = 4, S = 3, R = 12Site B: F = 3, S = 4, R = 12Both HighRule: within a rating, rank by F, then SRequiredWhich site ranks firstWhen the order would changeBlack = given; red = required
Given and required for Question 3.8-8.

Given

VariableValueDescription
Site AF = 4, S = 3Emerging; Serious
Site BF = 3, S = 4Forming; Critical
RuleTable 3.8-77Use R only to place a site in a rating; within a rating, rank by F, then S
AdjustmentsSection 3.8.22.4C floor, “consequence governs” and the engineer’s one-level raise

Required

  • Which site ranks first and why
  • What would change the order

Equations

No equation is needed; the answer follows from the rules listed under Given.

Steps

Step 1 · Place both in a rating
Uses: R
Both R = 12
Both High
Spot check: 3×4 and 4×3 are both in the High list of Table 3.8-72.
↓
Step 2 · Rank within the rating
Uses: Table 3.8-77
Compare F first: A = 4, B = 3
Site A ranks first
Spot check: A is already moving (Emerging); B has the conditions for failure but no movement yet.
↓
Step 3 · Check the adjustments
Uses: Section 3.8.22.4
Does B carry a 5 on C2 or C3, or a reason for the one-level raise (no safe escape, shared trigger)?
If so, B rises to Severe and ranks first
Spot check: A one-level raise on B gives Severe, which outranks any High.
↓
Solution
Site A first, unless an adjustment raises Site B to Severe.

Solution

Site A ranks first: both are High, and within a rating the site with the higher F comes first. A is failing now, so the benefit of fixing it is gained soonest (Figure 3.8-42 shows how quickly the chance of failure builds with exposure). Site B’s higher consequence is not ignored: it should be monitored and placed first in the next program, and if the hazardous materials traffic, what lies below the fill or a shared trigger justifies the engineer’s one-level raise, B becomes Severe and moves ahead of A. Write the reason for the order in the rationale either way (Section 3.8.43).

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

← Previous · 3.0 Risk Management Chapter 3.7 — Cost Estimates
Next · 3.0 Risk Management → Chapter 3.9 — Geotechnical Investigation Planning and Scope