Every rating is recorded so that a reviewer can follow it without the engineer present, and so that the next assessment of the site starts from the reasons, not just the numbers.
Table 3.8-91 shows a completed record for the culvert fill site carried through Examples 3.8-3 to 3.8-6. Each line gives the level and the evidence behind it, so a reviewer can check the rating, and the next assessment can see which inputs have changed. Write the reason as the evidence, not as a restatement of the level: “four cross level exceptions returning between cycles” can be checked; “defects recurring” cannot.
| Item | Level | Reason and source |
|---|---|---|
| Trigger narrative | — | A half-blocked 36-in. culvert under a 25-ft lean clay fill ponds water against the left slope in most wet years; the fill is cracked and its defects recur. Failure is most likely to be triggered by a storm exceeding the culvert. Current risk High; reducible by restoring drainage and adding resistance. |
| T | 4 | Ponding in most wet years; imagery 2019–2025; water 3 ft higher on the left at the visit (photos 4–7) |
| L1–L5 | 4, 3, 3, 5, 4 (L5 × 2) | Soil survey and old boring (lean clay over alluvium and shale); lidar (25 ft, 2H:1V); floodplain map; culvert half blocked (photo 3) |
| L6 | 4 | Shoulder slump repaired 12 years ago (railroad repair record) |
| D | 4 | Four cross level exceptions since the last slow order, returning between cycles (geometry reports); fresh tension cracks, left shoulder (photos 8–9) |
| Fg, Fc | 4, 4 | L = 27/7 = 3.86 → 4, not capped by T; Table 3.8-11, row 4, column 4 |
| S | 4 | Main line, 28 trains a day with hazardous materials, 50 mph; creek and farmland below; detour available |
| Rc, rating | 16, High | No one-level adjustment: crew escape route available; no shared trigger with nearby sites |
| Alternative 1 | 16, High (interim) | Removes the trigger only; D kept at 4 until a wet season passes with no movement (Section 3.8.37.2) |
| Alternative 2 | 4, Guarded | Drains the fill and adds resistance; D expected 1. Investigation level: field reconnaissance, so a two-level reduction is the most that may be claimed; High to Guarded is two levels and is allowed (Table 3.8-80) |
| Maintenance and monitoring | — | Culvert inspection twice a year and after storms above the site threshold; crack gauges read monthly through the first wet season to verify the post-stabilization rating |