3.8.43 Documenting the Rationale

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.43 Documenting the Rationale

Every rating is recorded so that a reviewer can follow it without the engineer present, and so that the next assessment of the site starts from the reasons, not just the numbers.

  • The trigger narrative (Section 3.8.18.4), written first.
  • For T, each of L1 to L6, D and S: the level chosen and a one-line reason, with the source (record, map, photo number, measurement).
  • Fg, Fc, Rc and the current rating, with any one-level adjustment and its reason.
  • For each alternative: the solution, design, construction-stage, provisional and verified ratings, the input each changes and why, and any cap from Table 3.8-80.
  • The maintenance plan and the monitoring that will verify the residual rating.
  • No client-confidential data: use generic site descriptions in any rating that leaves the client's records.

Table 3.8-91 shows a completed record for the culvert fill site carried through Examples 3.8-3 to 3.8-6. Each line gives the level and the evidence behind it, so a reviewer can check the rating, and the next assessment can see which inputs have changed. Write the reason as the evidence, not as a restatement of the level: “four cross level exceptions returning between cycles” can be checked; “defects recurring” cannot.

Table 3.8-91. Example rationale record for the culvert fill site of Examples 3.8-3 to 3.8-6
ItemLevelReason and source
Trigger narrative—A half-blocked 36-in. culvert under a 25-ft lean clay fill ponds water against the left slope in most wet years; the fill is cracked and its defects recur. Failure is most likely to be triggered by a storm exceeding the culvert. Current risk High; reducible by restoring drainage and adding resistance.
T4Ponding in most wet years; imagery 2019–2025; water 3 ft higher on the left at the visit (photos 4–7)
L1–L54, 3, 3, 5, 4 (L5 × 2)Soil survey and old boring (lean clay over alluvium and shale); lidar (25 ft, 2H:1V); floodplain map; culvert half blocked (photo 3)
L64Shoulder slump repaired 12 years ago (railroad repair record)
D4Four cross level exceptions since the last slow order, returning between cycles (geometry reports); fresh tension cracks, left shoulder (photos 8–9)
Fg, Fc4, 4L = 27/7 = 3.86 → 4, not capped by T; Table 3.8-11, row 4, column 4
S4Main line, 28 trains a day with hazardous materials, 50 mph; creek and farmland below; detour available
Rc, rating16, HighNo one-level adjustment: crew escape route available; no shared trigger with nearby sites
Alternative 116, High (interim)Removes the trigger only; D kept at 4 until a wet season passes with no movement (Section 3.8.37.2)
Alternative 24, GuardedDrains the fill and adds resistance; D expected 1. Investigation level: field reconnaissance, so a two-level reduction is the most that may be claimed; High to Guarded is two levels and is allowed (Table 3.8-80)
Maintenance and monitoring—Culvert inspection twice a year and after storms above the site threshold; crack gauges read monthly through the first wet season to verify the post-stabilization rating
Record the investigation level with every solution rating. It decides how much credit the solution may claim (Table 3.8-80), and it is the first thing a reviewer will ask about a large reduction.