Railroad Geotechnical Services Manual | Primary Source: USACE EM 1110-1-1804 All equations and parameters expressed in English (Imperial) units throughout.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Strength and unit weight values for preliminary slope stability models. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Friction angle | Gravels | GW-SP | Very loose / loose | 30 | 32 | 34 | deg | LOOK T7.8, p.107 |
| Friction angle | Gravels | GW-SP | Medium dense | 34 | 36.5 | 39 | deg | LOOK T7.8, p.107 |
| Friction angle | Gravels | GW-SP | Dense | 39 | 41.5 | 44 | deg | LOOK T7.8, p.107 |
| Friction angle | Gravels | GW-SP | Very dense | 44 | 46.5 | 49 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Very loose / loose | 27 | 29.5 | 32 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Medium dense | 32 | 34.5 | 37 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Dense | 37 | 39.5 | 42 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Very dense | 42 | 44.5 | 47 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Loose, uniformly graded | 27 | 28.5 | 30 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Loose, well graded | 30 | 31 | 32 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Dense, uniformly graded | 37 | 38.5 | 40 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Dense, well graded | 40 | 41 | 42 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Soft sedimentary | 30 | 35 | 40 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Hard sedimentary | 35 | 40 | 45 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Metamorphic | 35 | 40 | 45 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Igneous | 40 | 45 | 50 | deg | LOOK T7.8, p.107 |
| Friction angle | Uniform sand, round grains | Loose | 27 | deg | CB T6.4, p.159 | |||
| Friction angle | Uniform sand, round grains | Dense | 34 | deg | CB T6.4, p.159 | |||
| Friction angle | Well-graded sand, angular grains | Loose | 33 | deg | CB T6.4, p.159 | |||
| Friction angle | Well-graded sand, angular grains | Dense | 45 | deg | CB T6.4, p.159 | |||
| Friction angle | Sandy gravel | Loose | 35 | deg | CB T6.4, p.159 | |||
| Friction angle | Sandy gravel | Dense | 50 | deg | CB T6.4, p.159 | |||
| Friction angle | Silty sand | Loose | 27 | 30 | 33 | deg | CB T6.4, p.159 | |
| Friction angle | Silty sand | Dense | 30 | 32 | 34 | deg | CB T6.4, p.159 | |
| Friction angle | Inorganic silt | Loose | 27 | 28.5 | 30 | deg | CB T6.4, p.159 | |
| Friction angle | Inorganic silt | Dense | 30 | 32.5 | 35 | deg | CB T6.4, p.159 | |
| Friction angle (compacted) | Well-graded sand–gravel | GW | Compacted to standard Proctor MDD | 38 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Poorly graded sand–gravel | GP | Compacted to standard Proctor MDD | 37 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Silty gravels | GM | Compacted to standard Proctor MDD | 34 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Clayey gravels | GC | Compacted to standard Proctor MDD | 31 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Well-graded clean sand | SW | Compacted to standard Proctor MDD | 38 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Poorly graded clean sand | SP | Compacted to standard Proctor MDD | 37 | deg | CB T6.5, p.159 | ||
| Effective friction angle (compacted) | Silty sands, sand–silt mix | SM | Compacted to standard Proctor MDD | 34 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clayey sands, sand–clay mix | SC | Compacted to standard Proctor MDD | 31 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Silts and clayey silts | ML | Compacted to standard Proctor MDD | 32 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clays of low plasticity | CL | Compacted to standard Proctor MDD | 28 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clayey silts, elastic silts | MH | Compacted to standard Proctor MDD | 25 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clays of high plasticity | CH | Compacted to standard Proctor MDD | 19 | deg | CB T6.3, p.158 | ||
| Effective cohesion (peak) | Cohesive soils | CL-CH / OL-OH | Soft – organic | 104 | 156.5 | 209 | psf | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Soft – organic | 10 | 15 | 20 | deg | LOOK T7.9, p.107 |
| Effective cohesion (peak) | Cohesive soils | CL-CH / OL-OH | Soft – non-organic | 209 | 313.5 | 418 | psf | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Soft – non-organic | 15 | 20 | 25 | deg | LOOK T7.9, p.107 |
| Effective cohesion (peak) | Cohesive soils | CL-CH / OL-OH | Stiff | 418 | 731 | 1,044 | psf | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Stiff | 20 | 25 | 30 | deg | LOOK T7.9, p.107 |
| Effective cohesion (peak) | Cohesive soils | CL-CH / OL-OH | Hard | 1,044 | 1,566 | 2,088 | psf | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Hard | 25 | 27.5 | 30 | deg | LOOK T7.9, p.107 |
| Undrained shear strength (compacted) | Silts, sands, sand–silt mix | SM | As compacted (standard Proctor MDD) | 1,044 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Silts, sands, sand–silt mix | SM | Saturated after compaction | 418 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clayey sands, sandy clay mix | SC | As compacted (standard Proctor MDD) | 1,566 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clayey sands, sandy clay mix | SC | Saturated after compaction | 209 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Silts and clayey silts | ML | As compacted (standard Proctor MDD) | 1,358 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Silts and clayey silts | ML | Saturated after compaction | 209 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clays of low plasticity | CL | As compacted (standard Proctor MDD) | 1,775 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clays of low plasticity | CL | Saturated after compaction | 313 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clayey silts, elastic silts | MH | As compacted (standard Proctor MDD) | 1,462 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clayey silts, elastic silts | MH | Saturated after compaction | 418 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clays of high plasticity | CH | As compacted (standard Proctor MDD) | 2,088 | psf | CB T6.1, p.145 | ||
| Undrained shear strength (compacted) | Clays of high plasticity | CH | Saturated after compaction | 209 | psf | CB T6.1, p.145 | ||
| Peak strength, overconsolidated clay joint infill | Overconsolidated clays | CH | Peak | c ≈ 3,759 psf; φ = 12–18° | LOOK T9.17, p.134 | |||
| Residual strength, overconsolidated clay | Overconsolidated clays | CH | Residual | 10 | 13 | 16 | deg | LOOK T9.17, p.134 |
| Drained friction angle | Sand | SP-SW | Rounded grains, loose | 27 | 28.5 | 30 | deg | DASP T12.1, p.383 |
| Drained friction angle | Sand | SP-SW | Rounded grains, medium | 30 | 32.5 | 35 | deg | DASP T12.1, p.383 |
| Drained friction angle | Sand | SP-SW | Rounded grains, dense | 35 | 36.5 | 38 | deg | DASP T12.1, p.383 |
| Drained friction angle | Sand | SP-SW | Angular grains, loose | 30 | 32.5 | 35 | deg | DASP T12.1, p.383 |
| Drained friction angle | Sand | SP-SW | Angular grains, medium | 35 | 37.5 | 40 | deg | DASP T12.1, p.383 |
| Drained friction angle | Sand | SP-SW | Angular grains, dense | 40 | 42.5 | 45 | deg | DASP T12.1, p.383 |
| Drained friction angle | Gravel with some sand | GW-GP | 34 | 41 | 48 | deg | DASP T12.1, p.383 | |
| Drained friction angle | Silts | ML | 26 | 30.5 | 35 | deg | DASP T12.1, p.383 | |
| Critical-state friction angle | Gravel | GW-GP | Critical state | 30 | 32.5 | 35 | deg | BUDHU T10.3, p.300 |
| Peak friction angle | Gravel | GW-GP | Peak | 35 | 42.5 | 50 | deg | BUDHU T10.3, p.300 |
| Critical-state friction angle | Gravel and sand with fine-grained soils | GM-SC | Critical state | 28 | 30.5 | 33 | deg | BUDHU T10.3, p.300 |
| Peak friction angle | Gravel and sand with fine-grained soils | GM-SC | Peak | 30 | 35 | 40 | deg | BUDHU T10.3, p.300 |
| Critical-state friction angle | Sand | SW-SP | Critical state | 27 | 32 | 37 | deg | BUDHU T10.3, p.300 |
| Peak friction angle | Sand | SW-SP | Peak | 32 | 41 | 50 | deg | BUDHU T10.3, p.300 |
| Critical-state friction angle | Silt or silty sand | ML / SM | Critical state | 24 | 28 | 32 | deg | BUDHU T10.3, p.300 |
| Peak friction angle | Silt or silty sand | ML / SM | Peak | 27 | 31 | 35 | deg | BUDHU T10.3, p.300 |
| Critical-state friction angle | Clays | CL-CH | Critical state | 15 | 22.5 | 30 | deg | BUDHU T10.3, p.300 |
| Peak friction angle | Clays | CL-CH | Peak | 20 | 25 | 30 | deg | BUDHU T10.3, p.300 |
| Residual friction angle | Clays | CL-CH | Residual | 5 | 10 | 15 | deg | BUDHU T10.3, p.300 |
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 10 | 0.685 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 10 | 0.958 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 20 | 0.606 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 20 | 0.878 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 30 | 0.535 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 30 | 0.816 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 40 | 0.472 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 40 | 0.772 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 50 | 0.417 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 50 | 0.746 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 60 | 0.37 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 60 | 0.738 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Significant number of equivalent stress cycles vs earthquake magnitude | Liquefaction analysis | M = 7.0 | 10 | cycles | DASDYN T10.2, p.435 | |||
| Significant number of equivalent stress cycles vs earthquake magnitude | Liquefaction analysis | M = 7.5 | 20 | cycles | DASDYN T10.2, p.435 | |||
| Significant number of equivalent stress cycles vs earthquake magnitude | Liquefaction analysis | M = 8.0 | 30 | cycles | DASDYN T10.2, p.435 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Saturated unit weight | Sands and gravels | GW-SP | Very loose | 108.2 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Loose | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Medium dense | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Dense | 133.7 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Very dense | 140 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Loose, uniformly graded | 108.2 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Loose, well graded | 121 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Dense, uniformly graded | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Dense, well graded | 133.7 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Soft – organic | 89.1 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Soft – non-organic | 101.9 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Stiff | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Hard | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – soft sedimentary (chalk, shale, siltstone, coal) | Rockfill | Compacted | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – hard sedimentary (conglomerate, sandstone) | Rockfill | Compacted | 121 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – metamorphic | Rockfill | Compacted | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – igneous | Rockfill | Compacted | 133.7 | pcf | LOOK T7.3, p.104 | ||
| Bulk (saturated) unit weight | Sand and gravel | GW-SP | Very loose | 108.2 | 111.4 | 114.6 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Sand and gravel | GW-SP | Loose | 114.6 | 117.8 | 121 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Sand and gravel | GW-SP | Medium dense | 121 | 124.2 | 127.3 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Sand and gravel | GW-SP | Dense | 127.3 | 133.7 | 140 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Sand and gravel | GW-SP | Very dense | 140 | 143.2 | 146.4 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Poorly graded sands | SP | Natural | 108.2 | 114.6 | 121 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Well-graded sands | SW | Natural | 114.6 | 130.5 | 146.4 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Well-graded sand–gravel mixtures | GW / SW | Natural | 121 | 133.7 | 146.4 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Clay – unconsolidated muds | OH / CH | Natural | 101.9 | 105.1 | 108.2 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Clay – soft, open-structured | CL-CH | Natural | 108.2 | 114.6 | 121 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Clay – firm or stiff, normally consolidated | CL-CH | Natural | 114.6 | 127.3 | 140 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Glacial till (boulder clay) | CL / SC / GC | Natural | 127.3 | 140.1 | 152.8 | pcf | CB T3.1, p.79 |
| Bulk (saturated) unit weight | Tropical red clays | CL-MH | Natural | 108.2 | 120.9 | 133.7 | pcf | CB T3.1, p.79 |
| Natural water content (saturated) | Loose uniform sand | Natural state | 30 | % | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Dense uniform sand | Natural state | 16 | % | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Loose angular-grained silty sand | Natural state | 25 | % | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Dense angular-grained silty sand | Natural state | 15 | % | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Stiff clay | Natural state | 21 | % | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Soft clay | Natural state | 30 | 40 | 50 | % | DASP T3.2, p.76 | |
| Natural water content (saturated) | Loess | Natural state | 25 | % | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Soft organic clay | Natural state | 90 | 105 | 120 | % | DASP T3.2, p.76 | |
| Natural water content (saturated) | Glacial till | Natural state | 10 | % | DASP T3.2, p.76 | |||
| Saturated unit weight | Gravel | 127.3 | 133.7 | 140 | pcf | BUDHU T4.1, p.71 | ||
| Saturated unit weight | Sand | 114.6 | 120.9 | 127.3 | pcf | BUDHU T4.1, p.71 | ||
| Saturated unit weight | Silt | 114.6 | 120.9 | 127.3 | pcf | BUDHU T4.1, p.71 | ||
| Saturated unit weight | Clay | 101.9 | 121 | 140 | pcf | BUDHU T4.1, p.71 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Coefficient of variation – inherent variability | Sand and clay – Effective friction angle | Kulhawy et al. (2000), 48 data groups | 4 | 13.9 | 50 | % | FGE T31.3, p.479 | |
| Coefficient of variation – inherent variability | Sand – Effective friction angle | SW-SM | Kulhawy et al. (2000), 32 data groups | 4 | 9 | 15 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – Effective friction angle | CL-CH | Kulhawy et al. (2000), 16 data groups | 10 | 23.5 | 50 | % | FGE T31.3, p.479 |
| Coefficient of variation – inherent variability | Clay – Undrained shear strength | CL-CH | Kulhawy et al. (2000), 100 data groups | 6 | 31.5 | 80 | % | FGE T31.3, p.479 |
| Coefficient of variation – lab measurement error | Clay, silt – Undrained strength, triaxial compression su(TC) | CL-ML | Phoon & Kulhawy (1999a) | 8 | 19 | 38 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay, silt – Undrained strength, direct shear su(DS) | CL-ML | Phoon & Kulhawy (1999a) | 19 | 20 | 20 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay – Undrained strength, lab vane su(LV) | CL-CH | Phoon & Kulhawy (1999a) | 5 | 13 | 37 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay, silt – Friction angle, triaxial φ′(TC) | CL-ML | Phoon & Kulhawy (1999a) | 7 | 24 | 56 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay, silt – Friction angle, direct shear φ′(DS) | CL-ML | Phoon & Kulhawy (1999a) | 3 | 13 | 29 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Sand – Friction angle, direct shear φ′(DS) | SW-SM | Phoon & Kulhawy (1999a) | 13 | 14 | 14 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Sand, silt – tan φ′, triaxial | SM-ML | Phoon & Kulhawy (1999a) | 2 | 8 | 22 | % | FGE T31.4, p.480 |
| Coefficient of variation – lab measurement error | Clay – tan φ′, direct shear | CL-CH | Phoon & Kulhawy (1999a) | 6 | 14 | 22 | % | FGE T31.4, p.480 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UC) | CL-CH | Direct (lab) | 20 | 37.5 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UU) | CL-CH | Direct (lab) | 10 | 22.5 | 35 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(CIUC) | CL-CH | Direct (lab) | 20 | 32.5 | 45 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(field) | CL-CH | Vane shear | 15 | 32.5 | 50 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UU) | CL-CH | From CPT qT | 30 | 35 | 40 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(CIUC) | CL-CH | From CPT qT | 35 | 42.5 | 50 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(UU) | CL-CH | From SPT N | 40 | 50 | 60 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su | CL-CH | From DMT KD | 30 | 42.5 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Undrained strength su(field) | CL-CH | From PI | 30 | 42.5 | 55 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay, sand – Effective friction angle φ′ | Direct (lab) | 7 | 13.5 | 20 | % | FGE T31.7, p.485 | |
| Coefficient of variation – design parameter (point) | Sand – Effective friction angle φ′(TC) | SW-SM | From CPT qT | 10 | 12.5 | 15 | % | FGE T31.7, p.485 |
| Coefficient of variation – design parameter (point) | Clay – Constant-volume friction angle φ′cv | CL-CH | From PI | 15 | 17.5 | 20 | % | FGE T31.7, p.485 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| COV of factor of safety | Earth structures – Category I | State-of-the-practice design, construction and operation; usually high consequence | 7.2 | % | FGE T31.1, p.476 | |||
| COV of factor of safety | Earth structures – Category II | Standard engineering practice; most ordinary facilities | 10.9 | % | FGE T31.1, p.476 | |||
| COV of factor of safety | Earth structures – Category III | No site-specific design, substandard construction or operation; temporary or low consequence | 17.4 | % | FGE T31.1, p.476 | |||
| COV of factor of safety | Earth structures – Category IV | Little or no engineering | 31.6 | % | FGE T31.1, p.476 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Presumptive minimum slope for new fill | Rockfill | Compacted to high relative density | 1.5 | H per 1V | LI16 T7.2, p.314 | |||
| Presumptive minimum slope for new fill | Sand and gravel | Compacted to high relative density | 1.8 | H per 1V | LI16 T7.2, p.314 | |||
| Presumptive minimum slope for new fill | Sand | Compacted to high relative density | 2 | H per 1V | LI16 T7.2, p.314 | |||
| Presumptive minimum slope for new fill | Fine-grained clay and silt | Compacted to high relative density | 2.5 | 2.75 | 3 | H per 1V | LI16 T7.2, p.314 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk negligible | Safety risk negligible | 1.3 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk negligible | Safety risk negligible | 1.1 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk negligible | Safety risk negligible | 1.4 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk negligible | Safety risk negligible | 1.3 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk negligible | Safety risk low | 1.35 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk negligible | Safety risk low | 1.15 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk negligible | Safety risk low | 1.45 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk negligible | Safety risk low | 1.35 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk negligible | Safety risk high | 1.4 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk negligible | Safety risk high | 1.2 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk negligible | Safety risk high | 1.5 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk negligible | Safety risk high | 1.4 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk low | Safety risk negligible | 1.35 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk low | Safety risk negligible | 1.15 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk low | Safety risk negligible | 1.45 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk low | Safety risk negligible | 1.35 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk low | Safety risk low | 1.4 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk low | Safety risk low | 1.2 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk low | Safety risk low | 1.5 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk low | Safety risk low | 1.4 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk low | Safety risk high | 1.45 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk low | Safety risk high | 1.25 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk low | Safety risk high | 1.55 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk low | Safety risk high | 1.45 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk high | Safety risk negligible | 1.4 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk high | Safety risk negligible | 1.2 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk high | Safety risk negligible | 1.5 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk high | Safety risk negligible | 1.4 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk high | Safety risk low | 1.45 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk high | Safety risk low | 1.25 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk high | Safety risk low | 1.55 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk high | Safety risk low | 1.45 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, cut slope – first-time failure | Environmental/economic risk high | Safety risk high | 1.5 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, cut slope – reactivation failure | Environmental/economic risk high | Safety risk high | 1.3 | – | TRENTER T13.3, p.203 | |||
| Possible factor of safety, embankment fill | Environmental/economic risk high | Safety risk high | 1.6 | – | TRENTER T13.4, p.206 | |||
| Possible factor of safety, embankment foundation | Environmental/economic risk high | Safety risk high | 1.5 | – | TRENTER T13.4, p.206 | |||
| Indicative probability of slope failure vs factor of safety | Slopes | FS = 0.8 | 100 | % | LOOK23 T9.5, p.285 | |||
| Indicative probability of slope failure vs factor of safety | Slopes | FS = 1.0 | 50 | % | LOOK23 T9.5, p.285 | |||
| Indicative probability of slope failure vs factor of safety | Slopes | FS = 1.2 | 10 | % | LOOK23 T9.5, p.285 | |||
| Indicative probability of slope failure vs factor of safety | Slopes | FS = 1.4 | 1 | % | LOOK23 T9.5, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk negligible | Risk to life negligible | 1.1 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk negligible | Risk to life low | 1.2 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk negligible | Risk to life high | 1.4 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk low | Risk to life negligible | 1.2 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk low | Risk to life low | 1.3 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk low | Risk to life high | 1.5 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk high | Risk to life negligible | 1.4 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk high | Risk to life low | 1.5 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, new slope (GEO 1984) | Economic risk high | Risk to life high | 1.5 | – | LOOK23 T9.6, p.285 | |||
| Required factor of safety, embankment dam | Steady seepage, maximum pool | 1.5 | – | LOOK23 T9.12, p.291 | ||||
| Required factor of safety, embankment dam | Sudden drawdown from maximum pool | 1.1 | – | LOOK23 T9.12, p.291 | ||||
| Required factor of safety, embankment dam | Sudden drawdown from spillway crest | 1.3 | – | LOOK23 T9.12, p.291 | ||||
| Required factor of safety, embankment dam | End of construction, reservoir empty | 1.3 | – | LOOK23 T9.12, p.291 | ||||
| Required factor of safety, embankment dam | Earthquake, maximum pool (pseudo-static) | 1.1 | – | LOOK23 T9.12, p.291 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Typical excavated slope batter – permanent | Massive rock | Permanent | 1H:2V (0.5H:1V, 63°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – temporary | Massive rock | Temporary | 0.5H:1V to vertical | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – permanent | Well jointed, bedded or weathered rock | Permanent | 1H:1V (45°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – temporary | Well jointed, bedded or weathered rock | Temporary | 1H:1V (45°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – permanent | Gravel | Permanent | 1.5H:1V (34°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – temporary | Gravel | Temporary | 1.5H:1V (34°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – permanent | Sand | Permanent | 2H:1V (26°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – temporary | Sand | Temporary | 1.5H:1V (34°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – permanent | Clayey sand | Permanent | 1.5H:1V (34°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – temporary | Clayey sand | Temporary | 1H:1V (45°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – permanent | Intact clay (not fissured) | Permanent | 2.5H:1V (22°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical excavated slope batter – temporary | Intact clay (not fissured) | Temporary | 1H:1V (45°) | H:V | LOOK23 T9.13, p.291 | |||
| Typical fill slope batter | Rock fill | 1.5H:1V to 1H:1V | H:V | LOOK23 T9.14, p.292 | ||||
| Typical fill slope batter | Gravel | 1.5H:1V (34°) | H:V | LOOK23 T9.14, p.292 | ||||
| Typical fill slope batter | Soils | 2H:1V (26°) | H:V | LOOK23 T9.14, p.292 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 10 | 0.685 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 10 | 0.958 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 20 | 0.606 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 20 | 0.878 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 30 | 0.535 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 30 | 0.816 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 40 | 0.472 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 40 | 0.772 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 50 | 0.417 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 50 | 0.746 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter a | Fine-grained soil | PI = 60 | 0.37 | – | CASTELLANOS T6.4 / Eq. 6.15, p.184 | |||
| Fully softened strength envelope τ/pa = a (σ'/pa)^b – parameter b | Fine-grained soil | PI = 60 | 0.738 | – | CASTELLANOS T6.4 / Eq. 6.16, p.184 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Friction angle of rock discontinuity (clean, planar) | Schists (high mica), shale, marl | Low friction | 20 | 23.5 | 27 | deg | WYLLIE T4.1, p.81 | |
| Friction angle of rock discontinuity (clean, planar) | Sandstone, siltstone, chalk, gneiss, slate | Medium friction | 27 | 30.5 | 34 | deg | WYLLIE T4.1, p.81 | |
| Friction angle of rock discontinuity (clean, planar) | Basalt, granite, limestone, conglomerate | High friction | 34 | 37 | 40 | deg | WYLLIE T4.1, p.81 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Stronger rock (G1–G2) | Joints: Rough, fresh | 60 | 62.5 | 65 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Weaker rock (G3–G4) | Joints: Rough, fresh | 50 | 55 | 60 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Stronger rock (G1–G2) | Joints: Rough, slightly weathered | 60 | 62.5 | 65 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Weaker rock (G3–G4) | Joints: Rough, slightly weathered | 50 | 55 | 60 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Stronger rock (G1–G2) | Joints: Smooth, moderately weathered | 50 | 55 | 60 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Weaker rock (G3–G4) | Joints: Smooth, moderately weathered | 45 | 47.5 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Stronger rock (G1–G2) | Joints: Polished/slickensided or infilled | 45 | 47.5 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – interlocked; Weaker rock (G3–G4) | Joints: Polished/slickensided or infilled | 40 | 45 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Stronger rock (G1–G2) | Joints: Rough, fresh | 45 | 47.5 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Weaker rock (G3–G4) | Joints: Rough, fresh | 40 | 45 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Stronger rock (G1–G2) | Joints: Rough, slightly weathered | 45 | 47.5 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Weaker rock (G3–G4) | Joints: Rough, slightly weathered | 40 | 45 | 50 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Stronger rock (G1–G2) | Joints: Smooth, moderately weathered | 40 | 42.5 | 45 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Weaker rock (G3–G4) | Joints: Smooth, moderately weathered | 35 | 37.5 | 40 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Stronger rock (G1–G2) | Joints: Polished/slickensided or infilled | 40 | 42.5 | 45 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Blocky – disturbed; Weaker rock (G3–G4) | Joints: Polished/slickensided or infilled | 35 | 37.5 | 40 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Disintegrated; Weaker rock (G3–G4) | Joints: Rough, fresh | 35 | 37.5 | 40 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Disintegrated; Weaker rock (G3–G4) | Joints: Rough, slightly weathered | 35 | 37.5 | 40 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Disintegrated; Weaker rock (G3–G4) | Joints: Smooth, moderately weathered | 35 | 37.5 | 40 | deg | HEARN C2.5, p.153 | |
| Indicative cut slope angle in rock mass (no adverse structure) | Disintegrated; Weaker rock (G3–G4) | Joints: Polished/slickensided or infilled | 35 | 37.5 | 40 | deg | HEARN C2.5, p.153 |
| Estimate | Correlation | Limits / notes | Source |
|---|---|---|---|
| Probability of failure from mean FS and its COV | pf = P(FS < 1) ≈ Φ(−ln μFS / θ) (FS lognormal, θ = COV of FS small) | Reproduces Silva et al. (2008) curves; θ ≈ 0.07–0.32 by structure category | FGE text, p.475 |
| Forensic rejection criterion for an observed FS | FS* = exp[√ln(1 + θ²) · (β − 1.645/√n)]; observed FS < FS* → the target β was not achieved | θ = COV of FS, n = number of observed FS. Example: β = 3, θ = 0.3, n = 1 → FS* ≈ 1.5 | FGE Eq. 31.5, p.472 |
| Total measurement error | COVtotal = √(COVequipment² + COVprocedure² + COVrandom²) | Kulhawy & Trautmann (1996) | FGE 31.5, p.480 |
| Fully softened strength from PI (curved envelope) | τFS/pa = a (σ'n/pa)^b; a = 0.00004 PI² – 0.0091 PI + 0.7716; b = 0.00009 PI² – 0.0107 PI + 1.0561 | pa = 2,116 psf; σ(a) = 0.0247, σ(b) = 0.0407 (mean – 1σ ≈ 16% chance of lower value) | CASTELLANOS Eq. 6.15–6.16, p.184 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
After a failure: see Forensic Investigation of Ground Failures (Chapter 17) for what to record, how to scope the investigation, back analysis and vibration claims.
Slope stability governs the design of railroad embankments, cut slopes, and side-hill fills across railroad networks. An embankment failure — whether a rotational slide in soft foundation clay, a translational wedge along a shale bedding plane, or a surficial slump after heavy rainfall — can result in track loss, derailment, emergency speed restriction, and weeks of service disruption. This chapter develops the complete slope stability analysis framework: the Bishop Simplified method for circular failure surfaces, the Janbu Generalized method for non-circular surfaces, pseudo-static seismic analysis, tension crack depth, progressive failure in strain-softening clays, and cut slope design in rock. Minimum factors of safety follow USACE EM 1110-2-1902 as the primary criterion, supplemented by AREMA MRE Chapter 8 and the owner railroad's requirements. Three worked examples address a Class I railroad embankment located in Appalachia over residual clay, a Class I railroad staged construction embankment over soft foundation soil, and a Class I railroad cut slope located in the prairies in glacial till. A full slope stability analysis checklist, representative design tables, and five practice questions with complete answers are provided.
The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.
| ID | Correlation | Gives |
|---|---|---|
| IS-25 | Field vane strength correction | Sᵤ (field) |
| IX-06 | Normalized undrained strength from plasticity | Sᵤ/σ' |
| IX-07 | SHANSEP undrained strength ratio | Sᵤ |
| IX-08 | Friction angle of NC clay from plasticity | φ' |
| IS-07 | Undrained shear strength of clay from SPT | Sᵤ |
| IS-14 | Undrained shear strength from CPT | Sᵤ |
| RK-06 | Slope Mass Rating | SMR |
| RK-07 | Generalized Hoek–Brown criterion | m_b, s, a |
| RK-09 | Joint shear strength (Barton–Bandis) | τ |
Slope failures impose direct costs on railroad operations through emergency repair, traffic rerouting, crane mobilization, and environmental spill response. They impose indirect costs through locomotive speed restrictions, customer delivery failures, and regulatory scrutiny. The Federal Railroad Administration does not prescribe slope stability factors of safety directly, but 49 CFR Part 213 mandates that track geometry be maintained within class tolerances — a failed or deforming slope that moves the track out of tolerance triggers an immediate slow order or line closure under FRA authority.


Common practice is FS ≥ 1.5 for long-term static conditions on new embankments (Table 6.3-1). Emergency repair slopes are sometimes accepted temporarily at FS = 1.1–1.2 pending permanent stabilization, with the owner railroad's approval.
| Earthwork | Material | Slope |
|---|---|---|
| Cut | Silt | 2.5–3 : 1 |
| Cut | Muddy (silty) sand | 2–3 : 1 |
| Cut | Gravel | 1.5–2 : 1 |
| Cut | Stable clay | 1–1.5 : 1 |
| Embankment | Usual soils | 1.5–2 : 1 |
| Embankment | Gravel, sand | 2 : 1 |
| Embankment | Erosion-prone soils | 2 : 1 |
Values quoted by Profillidis from Bowles. Starting points only; the factors of safety in this chapter govern.
Profillidis emphasizes studying the geological formation along a cut, especially its joint pattern, so as to disturb the existing equilibrium as little as possible; protecting slopes with vegetation; providing slope drainage to prevent softening; and checking the foundation beneath an embankment as well as the fill. Where the ground slope exceeds 1:10, he recommends benching the embankment base (Chapter 2.1, §2.1.2).
After Profillidis (2014), §9.12; values after Bowles (2001). Full reference under Supplemental References.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
Railroad slopes exhibit four primary failure modes that drive the selection of analytical method:


A review of embankment failures on Britain’s national rail network (August 2003 – December 2009), carried out for RSSB, separates mechanisms by how much railway traffic contributes (Figure 13-S1):

Table 13-S1. Common embankment failure mechanisms and the role of traffic (RSSB 1386, Table 2.1, condensed)
| Mechanism | Impact on track | Traffic influence | Likely triggers |
|---|---|---|---|
| Deep-seated failure through/below toe, daylighting next to track | Catastrophic | Small | Loss of shear strength, high pore pressure |
| Deep-seated failure daylighting on the slope | Small lateral/vertical deformation | Small | Loss of shear strength, high pore pressure |
| Shallow slips daylighting near the crest | Small to medium; loss of lateral support | Small to medium | Tension cracks, seasonal deformation, high pore pressure |
| Unravelling of ballast/ash shoulder | Excessive deformation | Large | Vibration, dry summer |
| Shear failure through fill below ballast | Small to catastrophic | Large | Heavy traffic, high pore pressure |
| Plastic deformation of fill; subgrade failure (e.g., ballast pumping) | Local subsidence, loss of support | Large | Heavy or more frequent traffic, high pore pressure |
| Seasonal shrink–swell (high-water-demand trees) | Small to medium | Small | Dry summer |
| Wash-out | Small to catastrophic | Small | Surface flow, erosion channels |



Key findings: ultimate-limit-state slips peaked in winter (wet ground), serviceability failures in late summer (desiccation), and failures were concentrated in medium- to high-plasticity fills. No correlation was found between large catastrophic failures and changes in traffic loading. Instead, traffic produces a fatigue-type mechanism that shows up as rising maintenance and poor trackbed performance rather than as a reported slip, so track maintenance records are the best indicator. The report also flags embankment–structure transitions and “hard spots” (culverts, walls) as stress concentrators that deserve more attention than they have received. Its preliminary models used only the static axle load, citing literature that the dynamic component is negligible at moderate speeds.
Source: Mott MacDonald (2011). The Effects of Railway Traffic on Embankment Stability. RSSB Research Project 1386 (Revised), Rail Safety and Standards Board
| Category | Field signature | Typical response |
|---|---|---|
| 1.1 Scarp far below track | Tension crack on lower slope; shallow creep shown by leaning poles, fences, trees | Walk the slope; monitor and plan mitigation |
| 1.2 Scarp at shoulder | Crack in or at the toe of ballast; surfacing and cross-level defects | Instability retrogressing toward the track; investigate and act |
| 1.3 Scarp directly below track | Main slide body at ballast level; slow or rapid | Drainage/subdrainage, geometry (flatten, berm, divert) or structure (walls, nails) |
| 1.4 Scarp uphill of track (very deep) | Cross-level drops toward the high side | Large toe berm about 1/3 of slide height; walls do not work |
| 2.1 Uphill toe falling on or pushing track | Crack far above; toe bulge in ditch | Gravity or anchored wall; dewatering |
| 2.2 Uphill toe heaving track | Track lifted and shifted sideways | Gravity or anchored wall; dewatering |
| 2.4 Slide taking track down | “Whole hill moving”; up to about 60 ft deep; reactivated old slides | Very difficult; major engineering |



After Geotechnology for Railroaders Program, Module 5; §03–07. Full reference under Supplemental References.
Failures on operating lines fall into four locations, each with its own usual trigger and fix:
Sidehill fills are the most critical. They slide through the fill or the natural hillside soil, often long after construction, and the trigger is commonly a change in drainage. Correct the drainage before failure, not after.
Train load in stability analysis. A loaded 100-ton car is roughly 1,400 psf over the 8.5-ft tie length. Embankment geometry reduces the track’s bearing factor of safety by up to about 30% compared with flat ground (Chapter 6.1, Table 11-SW1).
After Selig & Waters (1994), chs. 10 and 11. Full reference under Supplemental References.
All limit equilibrium methods divide the failure mass into vertical slices and apply static equilibrium to the slice forces. They differ in which inter-slice forces they include and which equilibrium equations they satisfy:
| Method | Satisfies Moment Eq. | Satisfies Force Eq. | Inter-Slice Forces | Best Use |
|---|---|---|---|---|
| Ordinary (Fellenius) | Yes (moment) | No | Neglected | Quick check only; underestimates FS |
| Bishop Simplified | Yes | Vertical only | Horizontal only | Circular surfaces, most railroad practice |
| Janbu Simplified | No | Yes | Horizontal only | Non-circular; requires correction factor |
| Janbu Generalized | Yes | Yes | Full (specified) | Non-circular, compound |
| Spencer | Yes | Yes | Constant inclination | Rigorous; all surface types |
| Morgenstern-Price | Yes | Yes | Variable (f(x)) | Most rigorous; complex cases |
The Bishop Simplified method (1955) satisfies overall moment equilibrium and vertical force equilibrium for each slice. It is the standard method for circular failure analysis in railroad embankment design.
For a failure mass divided into n vertical slices, each of width b and height h at its center:
FS = Σ [1/mα,i · (c'i·bi + (Wi − ui·bi) tan φ'i)] / Σ Wi·sin αi
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| c' | effective cohesion | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
mα,i = cos αi · [1 + (tan αi · tan φ'i) / FS]
Where:
Because FS appears on both sides of Equation 6.3-1, the solution is iterative: assume FS, compute m_α, compute new FS, repeat until convergence (typically 3–5 iterations).
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| c' | effective cohesion at slice base (psf) | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| φ' | effective friction angle at slice base (°) | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| Wi | total weight of slice i (lb/ft of embankment width) | Another equation | Area of the slice, wedge or wall section from the cross-section geometry × unit weight γ (from lab tests). | project-specific |
| ui | pore water pressure at slice base (psf) | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
| u | vertical stress / pore pressure = γ_w × h_w where h_w = piezometric head above slice base | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
| bi | slice width (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| αi | inclination of slice base from horizontal (° | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
Wi = γavg,i · hi · bi · 1 ft (per unit width, kips/ft or lb/ft)
Where γ_avg,i = weighted average unit weight of materials in slice i (pcf); h_i = average slice height (ft).
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| hi | average slice height (ft). | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
For preliminary and parametric analysis, pore pressure is expressed as a fraction of total overburden:
ru = u / (γ · h) = pore pressure / total vertical stress
Typical r_u values: 0 for fully drained slope; 0.25–0.35 for partially drained embankment fill; 0.50 for steady-state seepage with phreatic surface at the slope surface (worst case). USACE EM 1110-2-1902 specifies that steady-state seepage with drawdown must be analyzed separately from the static long-term case.

| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
For a planar or compound failure surface, Janbu Simplified satisfies horizontal force equilibrium:
FS = f₀ · Σ [1/nα,i · (c'i·bi + (Wi − ui·bi)·tan φ'i)] / Σ Wi·tan αi
Where bi = horizontal width of slice i. With nα written as cos²α (Eq. 6.3-6), the cohesion term uses the slice width bi, not the base length li (li = bi sec αi).
Source: Janbu, N. (1973), "Slope stability computations," Embankment-Dam Engineering, Wiley, 47–86; Duncan, J.M., Wright, S.G. and Brandon, T.L. (2014), Soil Strength and Slope Stability, 2nd ed., Wiley.

| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| bi | horizontal width of slice i. With n_α written as cos²α (Eq. 6.3-6), the cohesion term uses the slice width b_i, not the base length l_i (l_i | Another equation | Computed: b_i = b_i sec α_i). | project-specific |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| c' | effective cohesion | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
nα,i = cos²αi · [1 + (tan αi · tan φ'i)/FS]
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
f₀ = 1 + b1 · [d/L − 1.4(d/L)²]
Where d = maximum depth of failure surface below a chord connecting the crest and toe (ft); L = horizontal distance of the failure surface (ft); b1 = 0.69 for cohesion-only soils (φ = 0, undrained clay); 0.31 for friction-only soils (c' = 0); 0.50 for soils with both c' and φ' (also used when the surface crosses more than one soil type). f₀ corrects for inter-slice shear forces neglected in the simplified formulation.
Source: Janbu (1973); Abramson, L.W., Lee, T.S., Sharma, S. and Boyce, G.M. (2002), Slope Stability and Stabilization Methods, 2nd ed., Wiley, f₀ chart after Janbu.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| d | maximum depth of failure surface below a chord connecting the crest and toe (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| L | horizontal distance of the failure surface (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| b1 | 0.69 for cohesion-only soils (φ = 0, undrained clay) | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
In cohesive soils, a tension crack develops at the crest of the failure mass to a theoretical depth:
zc = 2c' / (γ · √Ka) = 2su / γ (for φ' = 0, undrained)
Where K_a = tan²(45 − φ'/2). For φ' = 0: z_c = 2s_u / γ. The tension crack reduces the effective length of the failure arc and, when water-filled, adds a destabilizing hydrostatic pressure. EM 1110-2-1902 discusses how to include tension cracks; for embankments and cuts in cohesive soil, check the case with the crack full of water.
Water pressure in tension crack:
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| c' | effective cohesion | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
Pw = 0.5 · γw · zc² (lb/ft, acts horizontally into failure mass)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| w | water content | Lab test | Oven-dry water content of samples (ASTM D2216); field check by microwave (D4643) or nuclear gauge (D6938). | gravels/sands 3–25%, clays 15–70% · by USCS group |
EM 1110-2-1902 recommends the infinite slope method for slopes of cohesionless material, where the critical surface lies parallel to and just below the face. With c′ = 0, slope angle β and ru = u/γz:
F = (cos2β − ru) tan φ′ / (cos β sin β)
A circular search in the same material converges on a very shallow, large-radius circle with the same FS. USACE cautions that the lowest FS is often such a shallow surface, while deeper surfaces carry the real consequence. For a granular embankment over soft clay, report the deeper surfaces that could take out the track even when a skin slide has a lower FS. In the other direction, shallow fully-softened slides in clay fills (above) are exactly the ones that undercut ballast shoulders.
Source: U.S. Army Corps of Engineers (2003). Slope Stability. EM 1110-2-1902
Two hand methods cover a large share of railroad slope problems and give a quick check on computer results. The infinite slope applies where the slip surface is shallow and parallel to the face: colluvium or residual soil over rock, weathered surfaces of fill slopes, and the surficial slides that close ditches after heavy rain. The planar slide applies to rock cuts where a joint or bedding plane dips out of the face more gently than the face itself. The handbook chapter on slopes in the library notes that the ordinary method of slices was itself developed by Fellenius to analyze failures along Swedish railways in the 1920s; the rock method follows Hoek and Bray and Wyllie and Mah's Rock Slope Engineering.
Equation 6.3-16. Infinite slope with seepage parallel to the slope
where z is the vertical depth to the slip plane, β the slope angle, and m the height of the water table above the slip plane as a fraction of z.
Equation 6.3-17. Planar rock slide with a water-filled tension crack
A = (H − z)/sinψp; W = ½γH²[(1 − (z/H)²) cotψp − cotψf]; U = ½γwzwA; V = ½γwzw²
Both equations show the same lesson: water, not geometry, is usually what changes between a stable slope and a failure. In the infinite slope, raising m from 0 to 1 roughly halves the frictional resistance of a cohesionless slope. In the rock slide, water in the tension crack both pushes the block (V) and lifts it (U). The calculator plots the factor of safety against water level for this reason, and adds a pseudo-static seismic coefficient and a bolt force for the rock case.
| Case | Inputs | Result |
|---|---|---|
| 2H:1V fill slope, shallow slide | z = 5 ft, γ = 120 pcf, c' = 50 psf, φ' = 30°, water at 0.6 z | FS = 1.00; dry FS = 1.36; FS = 1.0 when m = 0.60 |
| 35-ft rock cut, face 70°, joint 30° | γ = 160 pcf, c = 0, φ = 33°, 10-ft tension crack | FS = 1.12 dry, 1.02 with the crack half full, 0.90 full; bolt force for FS 1.5 with the crack half full 19.00 kips/ft |
The joint dips 3° less than its friction angle, so the cut stands dry with little margin; half a crack of water takes it to about 1.0 and a full crack to failure. Drainage holes behind the crest and a clean crest ditch are often worth more than bolting in such a cut. Where bolting is needed, the calculator reports the force per foot of slope for a factor of safety of 1.5.
Open the slope stability calculator →
Infinite slope with seepage and planar rock slide with tension crack, water, seismic coefficient and bolt force; FS plotted against water level.
These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.
An infinite-slope or planar check (Section 6.3.3.6) is enough for shallow sloughs and for rock sliding on a single plane. A track embankment on soft ground, however, usually fails on a deep curved surface that cuts through the fill and into the foundation, and the train load on the crest is part of what drives it. Duncan, Wright and Brandon's Soil Strength and Slope Stability treats the Simplified Bishop method as the standard procedure for circles. It satisfies moment equilibrium and vertical force equilibrium for each slice, and for circular surfaces its results are close to those of Spencer's fully rigorous method. The book also gives eight verification problems with published answers, and the calculator here was checked against two of them.
Equation 6.3-18. Simplified Bishop factor of safety
mα = cosα + sinα tanφ′/F (solved by iteration)
W is the slice weight summed through the layers, Q the train load carried by the slice, u the pore pressure at the base from the piezometric line, and kh an optional pseudo-static coefficient. Undrained (φ = 0) layers carry c = su. The calculator searches a grid of 17 × 17 centers with 31 radii each, from shallow circles in the fill to circles tangent to the base of the deepest layer, and then refines around the five lowest centers. It discards circles where mα drops below 0.2, because the Simplified Bishop result is unreliable there. Two strength issues from the library apply to railroad fills. First, compacted high-plasticity clay fills lose strength toward the fully softened value over years of wetting and drying; the ASCE fully softened strength white paper recommends that value for long-term analysis of cut and compacted clay slopes. Second, shallow failures in partly saturated fill depend on suction that rain removes, as Lu and Likos describe, so the dry-weather strength is not the design strength.
| Problem | Published F (Simplified Bishop) | Calculator |
|---|---|---|
| Example 1: 31.5 ft vertical cut in clay, su = 1,050 psf, γ = 120 pcf | 1.06 (programs and Taylor chart) | 1.07 (grid search) |
| Example 4: 100 ft sand fill (φ = 40°) on 50 ft of clay (su = 2,500 psf), published critical circle | 1.22 to 1.23 | 1.23 (same circle) |
A 15 ft embankment with 2H:1V side slopes and the track centerline 10 ft from the crest edge rests on 25 ft of soft clay (su = 600 psf) over stiff clay. Groundwater is 2 ft below original ground. The fill has c′ = 100 psf and φ′ = 28°. With the E80 strip load (1,882 psf over the 8.5 ft tie length), the critical circle passes through the soft clay and the minimum factor of safety is 1.19 (center at x, y = −20.6, 19.1 ft; radius 31.4 ft). Without the train the same section gives 1.80, and with kh = 0.1 under the train it falls to 0.99. For soft-ground embankments the governing condition is usually the loaded track, short term, on undrained foundation strength.
Open the Bishop circular slip calculator →
Layered Simplified Bishop analysis with a piezometric line, an E80 strip load on the track, an optional seismic coefficient and a grid search for the critical circle, plotted on the section.
Duncan, Wright and Brandon's verification problems show how much the choice of method matters. Where φ = 0 and the surface is circular, every method that satisfies moment equilibrium gives the same answer. With frictional soils, the Ordinary Method of Slices runs about 10% low because it underestimates the normal stress on the slice bases. The Simplified Janbu method, used without its correction factor, also runs low. Spencer's method and the Simplified Bishop method agree closely.
| Procedure | Example 3: Bradwell excavated slope (φ = 0) | Example 4: sand fill on clay |
|---|---|---|
| Spencer | 1.76 | 1.19 to 1.20 |
| Simplified Bishop | 1.76 | 1.22 to 1.23 |
| Simplified Janbu, no correction | 1.63 | 1.07 to 1.08 |
| Simplified Janbu, corrected | 1.76 | 1.16 to 1.17 |
| Ordinary Method of Slices (spreadsheet, critical circle) | 1.76 | 1.08 |
| Corps of Engineers' Modified Swedish | 1.80 | – |
| Finite element strength reduction | 1.79 | 1.19 |
The Bradwell slope failed about five days after excavation despite F = 1.76. Skempton and LaRochelle traced the failure to fissures and to strength measured on small samples. A correct method cannot make up for the wrong strength.
| Basis | Condition | Required F |
|---|---|---|
| Duncan, Wright and Brandon, Table 13.1 | Repair cost comparable to the extra cost of a more conservative slope; small uncertainty / large uncertainty | 1.25 / 1.5 |
| Repair cost much greater than the extra cost of a more conservative slope; small uncertainty / large uncertainty | 1.5 / 2.0 or more | |
| Corps of Engineers (embankment and excavation slopes) | End of construction | 1.3 |
| Long-term steady seepage | 1.5 | |
| Rapid drawdown | 1.0 to 1.2 |
A slide that takes out main track usually costs far more to repair, and to recover traffic, than building the slope more conservatively, so the 1.5 to 2.0 row is the one that normally applies.
The worked example was rerun with the soft clay's undrained strength varied from 400 to 1,000 psf, with and without the E80 strip load. As the clay strength rises, the critical circle moves up out of the clay into the fill. From there on the factor of safety stops rising: about 1.43 under the train and 1.84 without it, set by the fill itself. With the train, F reaches 1.3 only at an undrained strength of about 650 psf, and never reaches 1.5 because the fill governs. Testing the clay more thoroughly cannot raise the result above the fill's limit; flattening the slope or strengthening the fill can.
| su (psf) | F with E80 | F without train |
|---|---|---|
| 400 | 0.81 | 1.22 |
| 500 | 1.00 | 1.52 |
| 600 | 1.19 | 1.80 |
| 700 | 1.37 | 1.84 |
| 800 | 1.43 | 1.84 |
| 900 | 1.43 | 1.84 |
| 1000 | 1.43 | 1.84 |
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.
For railroad slopes in seismically active regions (the western United States, the Cascades and Rockies, and the Northeast passenger corridor), a pseudo-static horizontal force is applied to the failure mass to represent earthquake loading.
Feq = kh · W
Where:
The pseudo-static force F_eq is added to the driving moments/forces in the Bishop or Janbu equations. With k_h = 0.5 a_max/g, Hynes-Griffin and Franklin (1984) accept FS ≥ 1.0. EM 1110-2-1902 refers earthquake analysis to ER 1110-2-1806. Assume the owner railroad requires FS ≥ 1.1 pseudo-static.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| kh | horizontal seismic coefficient = a_max / g × 0.5 (USACE EM 1110-2-1902 recommendation | Field or lab test | Field: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only. | clean sand 1–100, clay < 0.001 ft/day · by USCS group |
| amax | peak ground acceleration (g) from USGS hazard map at the site | Published hazard / climate data | USGS seismic design data / ASCE 7 hazard tool for the site location and site class (from Vs30 or SPT). | project-specific |
| W | total weight of failure mass (lb/ft) | Another equation | Area of the slice, wedge or wall section from the cross-section geometry × unit weight γ (from lab tests). | project-specific |
FS = Σ [1/mα,i · (c'i·bi + (Wi − ui·bi)·tan φ'i)]
/ Σ (Wi·sin αi + kh·Wi·yi/R)
Where R = failure circle radius (ft) and y_i = vertical distance from the circle center down to the centroid of slice i (ft), the moment arm of the horizontal force k_h·W_i.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| R | failure circle radius (ft) and R_m = moment arm for the pseudo-static force (approximately equal to the height of the centroid of the failur | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| c' | effective cohesion | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
USACE EM 1110-2-1902 (2003) provides the standard minimum FS criteria used as a baseline:
| Loading Condition | Min FS |
|---|---|
| End-of-construction (undrained) | 1.3 |
| Long-term static (drained) | 1.5 |
| Steady-state seepage | 1.5 |
| Rapid drawdown | 1.1–1.3 (USACE) |
| Pseudo-static seismic | 1.0 (Hynes-Griffin and Franklin 1984) |
| Residual (progressive failure) | 1.2 (common practice; not in USACE) |
| Emergency repair (temporary) | 1.1 (owner decision; not in USACE) |
Owner railroads may require higher values where a failure would have severe consequences, such as on high-speed passenger lines. Confirm them when the work is scoped.
Table 6.3-1 lists a “USACE Min FS” column, but EM 1110-2-1902 prescribes values only for new earth and rock-fill dams (Table 2.1-1): 1.3 at end of construction (including staged construction), 1.5 for long-term steady seepage, 1.4 at maximum surcharge pool, and 1.1–1.3 for rapid drawdown (1.1 from maximum surcharge pool, 1.3 from maximum storage pool; 1.4–1.5 where drawdown is routine, as in pumped storage). The manual does not tabulate pseudo-static, residual or emergency-repair values; for earthquake loading it refers to ER 1110-2-1806. Cite those rows to the owner railroad's standards or to project-specific judgment, not to USACE.
For “other slopes” — and EM 1110-2-1902 names railway embankments explicitly — USACE says FS should reflect both the uncertainty in strength and pore pressure and the consequence of failure. Where both are small, about 1.3 or even less can be acceptable. Where either grows, a larger FS is needed, and “large uncertainties coupled with large consequences of failure represent an unacceptable condition, no matter what the calculated value of the factor of safety.” Typical minimums are about 1.3 for end of construction and multistage loading, 1.5 for long-term loading, and 1.1–1.3 for infrequent rapid drawdown.
Cuts get weaker with time. For excavated slopes, the long-term condition is normally critical because pore pressures rise and the soil swells and weakens after excavation. A cut in low-permeability soil can stand temporarily yet be unstable in the long term; USACE calls this inherently dangerous and allows it only with detailed study and the observational method.
Source: U.S. Army Corps of Engineers (2003). Slope Stability. EM 1110-2-1902
In overconsolidated clays and clay shales, the post-failure (residual) strength is significantly lower than peak strength. The residual friction angle φ'_r is measured by ring shear test (ASTM D6467) or repeated direct shear at large displacement.

τ_r = c'_r + σ'_n · tan φ'_r
For Cretaceous clay shales (the northern plains and prairies; Appalachia): c'_r ≈ 0 psf; φ'_r = 8°–14° (Skempton 1985; ring shear data). This is dramatically lower than peak φ' = 24°–30°, meaning a slope designed at FS = 1.5 using peak strength may fail over decades at FS < 1.0 using residual strength as progressive straining reduces the mobilized angle along the surface.
Analyze cut slopes in clay shale with residual strength parameters; FS ≥ 1.2 is a common minimum. The same applies in Appalachian shale territory. The consultant must confirm whether the soil has experienced previous shearing (by identifying pre-existing slickensides in core samples or split spoon) — if slickensides are present, residual strength governs.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| φ'r | 8°–14° (Skempton 1985 | Lab test (or correlation) | Ring shear (ASTM D6467) or reversal direct shear (D3080); or Stark correlations with LL and clay fraction. | CH 6–15°, CL 12–25° · by USCS group |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
Section 6.3.6 moves directly from peak to residual strength. The intermediate fully softened strength (FSS) — close to the peak strength of the soil in a normally consolidated state — is the one that governs first-time slides in two situations common on railroads: (1) cuts in overconsolidated, fissured clays and clay shales, and (2) compacted clay embankments exposed to wet–dry cycles. The USACE/ASCE white paper notes that 3H:1V–4H:1V slopes 15–25 ft high routinely compute FS > 1.5 (often > 2) with peak strengths, yet many have failed, implying FS ≈ 1. One case describes a compacted fill slope that failed after about six years on a shallow surface, with back-analysis matching the FSS.

Source: Stark, T. D. et al. (2016). Development and Use of Fully Softened Shear Strength in Slope Stability Analyses, Third Draft. USACE / ASCE FSS Subcommittee

Large failures in fractured crystalline rock develop over long periods. Preparatory factors slowly weaken the rock mass by breaking intact rock bridges between joints, until a trigger such as heavy rain, snowmelt or an earthquake, or sometimes no identifiable trigger at all, completes the failure. Examples are deep weathering, pore-pressure cycling and daily and seasonal temperature cycles (Loew et al., in Feng 2017). The Randa slope in the Swiss Alps collapsed in 1991 with no trigger identified, and its remaining unstable part has been monitored since. The monitoring lessons are:
For railroad work: Mountain lines run beneath high rock slopes that weaken slowly in this way. Rockfall history and slow crack opening are the warning signs. Where a large block or slope above the track shows measurable movement, separate the seasonal (thermal and groundwater) component from the trend before setting alarm levels, or the alarms will trip every spring and fall. Use the trend in velocity and acceleration, not a single displacement value, to judge whether failure is approaching (Section 5.3.21 for trigger-action plans).
Source: Loew, Gischig, Glueer, Seifert and Moore, “Multidisciplinary monitoring of progressive failure processes in brittle rock slopes,” in Feng (ed.) (2017), Ch. 20. Summarized and paraphrased. Full reference under S17.
For rock cut slopes in Appalachia, Montana and Idaho, and the Rocky Mountains, kinematic analysis of joint and bedding plane orientations governs slope geometry over soil mechanics methods.
FS = (c'_j · A + (W·cos αp − U − V·sin αp) · tan φ'_j)
/ (W·sin αp + V·cos αp)
Where:
| Rock Type | c'_j (psf) | φ'_j (°) | Notes |
|---|---|---|---|
| Clean sandstone joint | 0–500 | 28–35 | West Virginia and Montana cuts |
| Clay-filled shale parting | 0–200 | 8–16 | Clay shale; use residual |
| Limestone bedding plane | 0–1,000 | 32–40 | Gulf Coast carbonate |
| Granite exfoliation joint | 0 | 35–42 | Sierra Nevada |
| Weathered basalt | 0–500 | 25–32 | Pacific Northwest |
Kinematic feasibility of planar, wedge, and toppling failure must be evaluated by stereographic projection (stereonet analysis) using joint orientation data collected during field mapping. This analysis is summarized below and should be performed for every rock cut slope.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| c'j | joint cohesion (psf | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| A | area of failure plane per unit width (ft²/ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| W | weight of sliding block (lb/ft) | Another equation | Area of the slice, wedge or wall section from the cross-section geometry × unit weight γ (from lab tests). | project-specific |
| U | water uplift force on failure plane = 0.5 γ_w h_w A (lb/ft) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| hw | water height in tension crack | Field measurement | Groundwater level from boring logs, observation wells or piezometers (ASTM D5092 / D4750); design with the seasonal high level. | project-specific |
| V | water force in tension crack = 0.5 γ_w z_w² (lb/ft) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| zw | water depth in crack | Field measurement | Groundwater level from boring logs, observation wells or piezometers (ASTM D5092 / D4750); design with the seasonal high level. | project-specific |
| αp | dip angle of failure plane (°) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| φ'j | joint friction angle (°) | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
Section 6.3.7 leaves stereonet analysis out of scope. The screening rules are short enough to apply to every railroad rock cut. Following Wyllie and Mah (2004), with face dip ψf and dip direction αf:
Wyllie and Mah note it is rarely possible to change an alignment enough to avoid an adverse structure; the choice is usually to flatten that face or reinforce it.
A California study of 308 highway rock falls (McCauley et al., 1985, reported by Wyllie and Mah) found that water-related causes account for 68% (rain 30%, freeze–thaw 21%, snowmelt 8%, channeled runoff 7%, plus differential erosion, springs and tree roots), and 85% when adverse geology is added. On a major western Canadian railroad, about 70% of 25 years of recorded falls occurred in winter, and falls smaller than about 1.3 yd³ occurred up to 50 times a year, while 13,100 yd³ slides recurred every 10–50 years. Many railroad cuts were blasted more than a century ago with techniques that damaged the rock, and have since weathered. Schedule scaling and inspection for late fall and early spring, and treat drainage as a primary rock-fall control.

Source: Wyllie, D. C. and Mah, C. W. (2004). Rock Slope Engineering: Civil and Mining, 4th ed. Spon Press
Active high-tensile mesh. Draped mesh only guides falling rock to the ditch; a pretensioned mesh pinned with a grid of soil or rock nails actively holds the surface layer. The Geobrugg TECCO system (presented at the Appalachian geohazards conference) uses wire of more than 256 ksi, giving mesh tensile strength of about 10.2 kips/ft, compared with about 3 kips/ft for common steel wire mesh and 2.75 kips/ft for a PET geogrid. The design (RUVOLUM concept) checks (1) sliding of the surface layer parallel to the slope and (2) local failure between nails, and sets the maximum nail spacing. It does not replace a global stability analysis (e.g., Bishop) of deeper surfaces. The presentation cites failed alternatives — shotcrete facing replaced after about 10 years and soft geogrid facing that failed by creep, cutting at sharp edges and overload.



Load transfer in grouted bolts and cables. Wang, Hagan and Cao (2016) summarize laboratory work on fully grouted reinforcement:

Source: Amend, F. Slope Stabilization with High Tensile Wire Mesh. Geohazards in Transportation in the Appalachian Region Conference, Geobrugg North America · Wang, S., Hagan, P. C. and Cao, C. (2016). Advances in Rock-Support and Geotechnical Engineering. Butterworth-Heinemann

| Strategy | Methods | Notes |
|---|---|---|
| Stabilizing | Drainage, trimming, scaling, shotcrete, bolting; retaining walls; stabilizing berms; horizontal drains | Highest safety and reliability impact; cost varies; scaled-rock disposal can be a problem |
| Protecting | Catchment nets; barrier walls; lock blocks; rock sheds (~$1–10M); tunnels (~$3–50M); flumes (~$600K); rock mesh (~$100–250K) | Nets for confined chutes and unscalable sources; keep catch ditches and wall accumulation zones clean |
| Warning | Slide-detector fences; mercury and tip-over switches; temporary radio units | A warning layer, not a fix: about 90% of trips prove passable; maintenance burden and false positives |



One near-miss shows the limit of warning devices: the fence tripped as designed, but the train could not stop on the grade. Use engineering-grade concrete for lock blocks and source matching keys. Mark already-documented fallen rocks with an X.
After Geotechnology for Railroaders Program, Module 6.4; §02–04. Full reference under Supplemental References.
Production blasting breaks rock beyond the design line (overbreak), opens joints behind the face and loosens blocks. A blasted face therefore has lower effective joint strength and a higher long-term rockfall rate than the same rock cut by machine. Two controlled perimeter methods limit the damage:
A good controlled face shows half-barrels (half of each perimeter hole) along most of its height. Terrestrial laser scanning of each lift gives a difference model of the as-built face against the design. That shows overbreak and underbreak and lets the half-barrel count and the remaining catchment width be measured without anyone on the face (Feng, Wang and Röshoff, in Feng 2017).
In the Hoek-Brown criterion, blast damage enters through the disturbance factor D. Use D ≈ 0.7 for a well-controlled face and up to 1.0 for heavy production blasting. Example 2.7-5 in Chapter 2.7, Section 2.7.17 shows that D = 0.7 cuts the rock mass modulus to about a fifth of the intact value. Blast damage is limited to a zone near the face, so apply the reduced strength to that zone rather than to the whole slope.
For railroad work: Specify controlled perimeter blasting for every permanent cut face within rockfall reach of track. Typical specification items:
(1) a test section before production;
(2) perimeter-hole spacing and diameter shown on the blast plan;
(3) a face acceptance criterion, such as half-barrels visible over a set percentage of the face;
(4) scaling and inspection after each lift.
In stability checks for blasted faces, take joint cohesion as zero, use the disturbed-zone strength near the face, and plan scaling and bolting for the loosened zone. Overbreak narrows the catchment ditch, so check the as-built ditch width against the design after each lift. A face cut without perimeter control should carry a higher rockfall frequency rating until scaling and inspection show otherwise. Vibration limits and monitoring for blasting near track and structures are in Chapter 5.3, Section 5.3.27.
Source: Austin Powder Company (2002), glossary; FHWA (1991); Feng (ed.) (2017), Ch. 18. Summarized and paraphrased. Full references under S15, S16, S17.
A standard pull test loads a bolt at the head until it holds the proof load or slips. For a fully grouted bolt it says little: the load is carried by the first foot or two of grout, so the test proves the head and the upper bond, not the anchorage along the bolt (Spearing et al., in Feng 2017). Two better tools are:
SEPTs repeated at 0, about 130 and about 190 to 270 days after installation in coal mine roofs found that the grip factor generally increased with time while the anchorage stiffness generally decreased (Chugh et al., in Feng 2017). A bolt that passes an early pull test can therefore become softer with time and allow more movement before it carries load.
For railroad work: Most railroad rock bolts and dowels are installed on cut faces and portals, are rarely retested, and sit in wet, freeze-thaw exposure. Specify proof testing of tensioned bolts. For fully grouted dowels, add SEPTs on sacrificial bolts in each rock type at installation, and repeat a few after a year or more where the bolts protect the track. Record the grip factor and stiffness as well as pass or fail. Include bolt heads, plates, grout cover and corrosion in the rock slope inspection cycle (Chapter 7.4), because a bolt that has lost its plate or rusted through its head no longer holds the block.
Source: Spearing, Kostecki and Jessu, “The needs and technologies for measuring the in situ performance of rock bolts,” Ch. 5; Chugh, Gurley and Bell, “Longer-term performance of grouted bolts in different lithologies in Illinois mines,” Ch. 8; in Feng (ed.) (2017). Summarized and paraphrased; units converted. Full reference under S17.
Tunnel portals: stability of portal faces and the slopes above tunnels, rockfall at portals and portal extensions are covered in Chapter 6.6, Section 6.6.6.
Embankments in the Missouri River valley and other river-crossing embankments are subject to rapid drawdown — when a river in flood recedes quickly, the phreatic surface within the embankment lags behind the external water level, creating a destabilizing outward seepage gradient.

The three-stage approach per USACE EM 1110-2-1902 Appendix G:
For free-draining sands and gravels (k of about 10⁻³ cm/s or more, roughly 3 ft/day), drained strengths can be used at the lowered pool because drainage occurs faster than drawdown. For clays (k below about 10⁻⁶ cm/s, roughly 0.003 ft/day), undrained (CU-based) strengths apply throughout.
While a pond is high, its weight helps hold the slope despite saturation. When it drops quickly, that support disappears while the fill is still saturated, and seepage reverses outward. Field guidance is that the slope stays at its least stable for about 12 hours after drawdown, recovering over 12–24 hours as the bank drains. Monitor for at least that long, and for at least three days where the drop is 2 ft or more. Beaver-dam or culvert releases create the same condition. The Nakina derailment of 1992, in which two employees were killed, was a rapid-drawdown failure beneath a moving train.

After Geotechnology for Railroaders Program, Module 7.1, Module 4, Module 6.5; Module 7.1 §06; Module 4 §10. Full reference under Supplemental References.
Case study: 6.3.16.1 Flood drawdown failures along the Brisbane River (Look 2023), in §13.16 Case Studies.
Use strength parameters measured in the site investigation. Appendix D gives typical ranges for checking them.



A 20-ft fill is proposed over residual clay derived from shale on a Class I railroad located in West Virginia. The example works one trial circle by hand with five slices, to show the mechanics of the Bishop method and why it must be iterated; a program then searches hundreds of circles for the critical one.
| Variable | Value | Description |
|---|---|---|
| Fill | c′ = 100 psf, φ′ = 30°, γ = 120 pcf | Slices 1 and 2 |
| Foundation | c′ = 200 psf, φ′ = 22°, γ = 115 pcf | Slices 3 to 5 |
| Slices | b = 6, 8, 8, 8, 6 ft; W = 2,880, 11,520, 17,464, 12,880, 4,140 lb/ft; α = −15°, 0°, 12°, 28°, 42° | Trial circle R = 38 ft |
| u | 0, 0, 375, 624, 0 psf | Phreatic surface at one-third height |
| Target | FS ≥ 1.5 (assumed owner requirement) |
FS = 2.18 for this trial circle.
The trial value is not the design answer. The critical circle, found by moving the center and radius in a program such as SLOPE/W or SLIDE, gives the minimum, and that is what is compared with 1.5. The hand calculation is worth doing once per project to check the program’s slice forces and pore pressures; submit the search output for independent review where the owner railroad requires it.
A siding extension on a Class I railroad located in Washington puts 12 ft of fill with 1.5H:1V slopes on soft saturated fat clay. At the end of construction the clay is undrained, so the analysis uses su with φ = 0, and both the slope and the bearing capacity of the base are checked.
| Variable | Value | Description |
|---|---|---|
| H | 12 ft | Fill height |
| γfill | 120 pcf | |
| Clay | su = 700 psf; γ = 103 pcf | Soft CH |
| Slope | 1.5H:1V (β ≈ 34°); deep firm layer | |
| Ns | 5.52 | Taylor chart (Coduto 2001) |
| Target | FS ≥ 1.4 at end of construction (assumed) |
The slope gives FS = 2.68 and the base FS = 2.50, so base capacity governs; both exceed 1.4.
Taylor’s chart assumes a homogeneous slope, so it is an approximation here. The result depends directly on su: at 300 psf the embankment would need staged lifts with piezometers and settlement plates (Chapter 5.3). Confirm the strength with at least two CPTu soundings at each embankment over about 8 ft high on soft ground; zones below 500 psf call for staging.
A 25-ft cut in Cretaceous clay shale on a Class I railroad main line located in Saskatchewan. Clay shale cuts often stand at first and then fail as the shale softens toward its residual strength, so the cut is checked at both strengths for a shallow slide parallel to the face.
| Variable | Value | Description |
|---|---|---|
| Peak | c′ = 300 psf, φ′ = 22° | |
| Residual | c′r = 0, φ′r = 9° | Ring shear |
| γsat | 130 pcf; γ′ = 67.6 pcf | |
| Slope | 2H:1V, β = 26.6° | |
| z | 4 ft | Depth of the shallow slide |
| Water | At the surface (worst case) |
FS = 1.86 at peak strength but 0.17 at residual. At residual, FS = 1.2 needs a slope of about 14.5H:1V wet or 7.5H:1V fully drained.
Neither slope is practical for a 25-ft cut. Residual strength governs only where a shear surface already exists (Section 6.3.6); where none is found, check first-time sliding with the fully softened strength and design with drainage (horizontal drains), berms or reinforcement. Instrument clay shale cuts deeper than about 15 ft with survey monuments and inclinometers, read at least annually.



Consider remedial measures in this order: (1) drainage and subdrainage; (2) geometry, meaning a toe berm, flattening or moving the track; (3) structural support; (4) improving soil properties. Warning devices supplement these.











One slide in western Canada (April 2013) is typical of most slides seen along the track. Snowmelt ran down small gullies, disappeared into the fill, raised pore pressure and took out the embankment. The repair keyed in a toe, rebuilt a 2:1 slope about 50 ft high from air-dumped fill, and added culverts.
After Geotechnology for Railroaders Program, Module 6.1, Module 7.1; Module 6.1 §02–04; Module 7.1 §05. Full reference under Supplemental References.
PERT handles uncertain durations by asking for three estimates per activity: optimistic a, most likely m and pessimistic b. A beta distribution gives the expected time t = (a + 4m + b) ÷ 6 and variance σ² = [(b − a) ÷ 6]². A forward pass gives the early start and finish (ES = largest EF of the predecessors; EF = ES + t), and a backward pass gives the late times (LF = smallest LS of the successors; LS = LF − t). Slack is LS − ES; activities with zero slack form the critical path. Project variance is the sum of the variances of the critical activities. Treating completion time as normally distributed, the probability of finishing by deadline D follows from Z = (D − T) ÷ σ.

Table 13-PM1. Worked example time estimates, weeks (after Swearingen n.d., slide PMT-17)
| Activity | a | m | b | t | σ² | Slack |
|---|---|---|---|---|---|---|
| A | 1 | 2 | 3 | 2 | 0.11 | 0 |
| B | 2 | 3 | 4 | 3 | 0.11 | 1 |
| C | 1 | 2 | 3 | 2 | 0.11 | 0 |
| D | 2 | 4 | 6 | 4 | 0.44 | 1 |
| E | 1 | 4 | 7 | 4 | 1.00 | 0 |
| F | 1 | 2 | 9 | 3 | 1.78 | 6 |
| G | 3 | 4 | 11 | 5 | 1.78 | 0 |
| H | 1 | 2 | 3 | 2 | 0.11 | 0 |
In the slides’ example, a foundry has 16 weeks to install a pollution-control system. The critical path A–C–E–G–H gives T = 15 weeks with variance 3.11, so σ = 1.76 weeks. Then Z = (16 − 15) ÷ 1.76 = 0.57, which corresponds to about a 71.6% chance of meeting the deadline.
For railroad work: slope repairs often have to be finished before a wet season, a freeze-up or a planned outage. Use wide pessimistic estimates for activities controlled by subsurface conditions, such as soldier pile or anchor drilling in uncertain rock, dewatering, or excavation below the slide plane. Use narrow ranges for routine tasks. If the computed probability is low, change the plan (more rigs, a second shift, a staged repair that restores track first) instead of only reporting the risk. The method assumes a single critical path. Where a near-critical path also carries large variance, the true chance of finishing on time is lower than the calculation shows, so check those paths as well.

Source: Swearingen, J. (n.d.). The Basics of Project Management Techniques [lecture slides PMT-1 to PMT-40; author from document properties], slides PMT-13 to PMT-34. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
The Swearingen example of Table 13-PM1. PERT turns three duration estimates per activity into an expected duration and a variance, and the critical path into a probability of meeting a deadline.
| Variable | Value | Description |
|---|---|---|
| Critical path | A–C–E–G–H | Figure 13-PM1 |
| Estimates | A 1/2/3; C 1/2/3; E 1/4/7; G 3/4/11; H 1/2/3 weeks | a / m / b |
| Deadline | 16 weeks |
Expected duration 15 weeks with σ = 1.76 weeks; about a 72% chance of finishing within 16 weeks.
Activity G contributes over half the variance; narrowing its range (by investigating the ground it depends on, for example) raises the probability more than shortening any other activity. On slope repairs before a wet season, use wide pessimistic estimates for work controlled by subsurface conditions.
Slope design relies on expert judgment wherever data are thin, for example in the location of the failure surface, residual strength, piezometric level or the effect of a drainage fix. Cretu et al. summarize the cognitive biases that distort such judgments and how a facilitator can counter them. The overconfidence effect is the tendency to give ranges that are too narrow. One study they cite asked seven very experienced geotechnical engineers to bracket the embankment height that would fail a clay foundation, using bounds intended to have a 50 percent chance of containing the true value. None of the seven ranges captured the actual failure height. Anchoring means that the first number spoken pulls later estimates toward it. Availability means that vivid recent events seem more probable than they are. Motivational bias covers people shading estimates to protect a past position, a budget or a client relationship, and subordinates deferring to superiors in the room. Optimism bias covers people underrating threats on projects they control.

The authors give these countermeasures. Explain the biases to the group before eliciting values. Ask for the worst credible outcome first, then the best case (which may not be “nothing”), then the most likely. Push explicitly for wider bounds. Collect estimates from junior staff or consultants separately and present them to management anonymously. Show the resulting distribution on screen so the experts can confirm that it says what they meant. Base estimates on personal experience, lessons learned, outside expert opinion and empirical records, and use the empirical records first when they exist.
For railroad work: When back-analysis or design inputs rest on judgment, run a short structured elicitation and document it. This applies to the depth of a slip surface between inclinometer readings, the residual friction angle of a slickensided clay, or the water level to assume for a ditch-line slide. Ask for the worst credible case first, record low/most-likely/high values with their reasons, and carry the full range into sensitivity or probabilistic stability runs. A single “engineering judgment” value tends to understate the uncertainty in the factor of safety. Railroad staff who have watched a site for years are valuable sources. Interview them separately from their managers, and treat their recollection of the last movement as an anchor to test, not a bound.
Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 111–121. Summarized and paraphrased. Full reference under Supplemental References.
Jacob and Müller show how a change is priced when the work as bid cannot be performed as described. The approach is not to negotiate a new lump sum. Instead, the original bid calculation is reopened, and only the parts of the item that changed are replaced. The original surcharge rates are kept.
In their example, half of a 131,000 CY excavate-haul-place item (65,400 CY) turns out to be contaminated. That portion must go to an owner-designated disposal site instead of into the on-site fill. The changed item is rebuilt as follows:
The new unit price came out about 3% above the original. The change can be paid either as a new item or as a price difference applied to the affected quantity. The authors prefer the difference method, because it shows exactly which costs were added and which were dropped.
They also list follow-on effects that may need their own pricing:
Underlying this is their split between time-variable and time-fixed site costs.
Keeping the two separate in the estimate is what makes delay and disruption costs calculable later.
For railroad work: Embankment and slide repairs regularly reveal conditions that change the work after award. Examples are contaminated or fouled-ballast spoil that cannot be reused, deeper failure surfaces, and wet borrow. Repricing from the contractor’s bid build-up only works if the contract requires that build-up to be submitted or escrowed. It also needs bid items split finely enough (excavation, haul, placement, disposal) to be reopened. For delay caused by lost track windows or a slower restoration of track speed, price the time-variable site costs per day in advance. That gives the railroad and contractor an agreed basis for standby and extension costs.
Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 12–14, 205–208. Summarized and paraphrased. Full reference under Supplemental References.
Pratt sets two rules for measuring earthwork. First, measure in bank measure: the actual in-place dimensions, with no allowance for swell or compaction. Those factors are applied later, when the work is priced. Second, keep each excavation category and each material separate, and measure disposal of surplus as total excavation minus common backfill.
He gives two manual methods for volumes. The grid method takes the cut or fill depth at each grid node and weights it by the area that node represents: one quarter-cell at a corner, two on an edge, and four in the interior. The section method suits long, narrow work such as road and railroad construction. Cross sections are plotted at regular stations, the cut and fill areas are measured at each section, and the volumes come from the average-end-area relation:

V = station spacing × (A1/2 + AN/2 + sum of the intermediate areas)
His example uses five stations 20 ft apart. The cut areas are 108, 40, 73, 91 and 0 ft², and the fill areas are 245, 248, 195, 195 and 328 ft². That gives 5,160 ft³ (191 CY) of cut and 18,490 ft³ (685 CY) of fill. All the cut is reused, so about 494 CY of fill must be imported. Accuracy depends mainly on how faithfully the section profiles are plotted, and closer station spacing improves it.
For railroad work: a slide or washout repair is a short, long-and-narrow job of exactly this kind. A reasonable procedure is:
Each material has its own swell and compaction behavior and its own haul. Report the volumes in bank measure, state the section spacing and the survey date, and keep the section sheets in the calculation appendix. A slide that is still moving changes the existing-ground line, so the quantities will need updating before the bid.
Source: Pratt, D. J. (2011). Fundamentals of Construction Estimating, 3rd ed. Clifton Park, NY: Delmar Cengage Learning, pp. 57, 59–64. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Checklist · Part VI · Geotechnical Analysis
Pre-Analysis
Analysis Execution
Deliverables
A railroad has four slope problems on one subdivision: a rotational slump in an embankment, a translational slide of weathered soil on a rock cut, a compound slide along a weak layer, and a slow progressive failure in clay shale. The engineer must choose an appropriate analysis method for each failure mode and justify the choice.
| Variable | Value | Description |
|---|---|---|
| Modes | Rotational, translational, compound, progressive | |
| Rule | USACE EM 1110-2-1902: justify the method from the expected surface geometry |
No equation is needed; the answer follows from the criteria listed under Given.
Rotational: Bishop or Spencer. Translational: infinite slope or a planar Janbu surface. Compound: Janbu generalized, Spencer or Morgenstern-Price. Progressive: any of these with fully softened or residual strength.
The choice of strength matters as much as the choice of method: a rigorous method with peak strength in a clay shale is less safe than a simple one with residual strength.
A Class I railroad wants to build a 10-ft fill for a new siding over a clay foundation with the undrained strength shown, and the owner requires a factor of safety of at least 1.4. Using Taylor’s stability number, the engineer must check the fill and find the minimum undrained strength the foundation must have.
The method of Example 6.3-2.
| Variable | Value | Description |
|---|---|---|
| su | 500 psf | |
| γfill | 118 pcf | |
| H | 10 ft | |
| Ns | 5.52 | |
| Target | FS ≥ 1.4 |
FS = 2.34, comfortably above 1.4. The slope would reach 1.4 at su ≈ 300 psf.
Confirm with CPTu soundings that su exceeds 300 psf throughout the foundation, and check the base bearing capacity as in Example 6.3-2, which may govern.
A cut through clay shale on a Class I railroad has failed twice since it was widened, each time along the same surface. The repair design is being prepared from laboratory strength tests that report both peak and residual angles. The engineer must explain the difference between the two and why the residual strength governs the repair.
| Variable | Value | Description |
|---|---|---|
| Peak φ′ | 20° to 28° | Clay shale |
| Residual φ′r | 6° to 14° | After large displacement |
No equation is needed; the answer follows from the criteria listed under Given.
Peak strength belongs to the intact fabric; residual strength is what remains after the plates have aligned along a slip surface. Clay shale cuts are designed for residual where a shear surface exists, because they fail progressively as the strength falls.
A cut that shows FS = 1.8 at peak, as in Example 6.3-3, can fall below 1.0 at residual. Railroad cuts through prairie clay shale have a long record of exactly this delayed failure.
Open tension cracks have appeared along the crest of a 30-ft clay cut above a Class I railroad main line, and heavy rain is forecast. The engineer must estimate how deep the cracks can extend and the horizontal water force they would add to the slide mass if they fill with water.
| Variable | Value | Description |
|---|---|---|
| H | 30 ft | Cut height |
| c′, φ′ | 150 psf; 18° | |
| γ | 122 pcf |
The crack extends about 3.4 ft; full of water it pushes on the sliding mass with about 357 lb per foot of slope.
The force is added to the driving side of the analysis and the crack depth is excluded from the resisting slip length. USACE EM 1110-2-1902 requires both for cohesive cut slopes; the water-filled case after a storm is often the critical one.
A railroad embankment slope in a seismic area is being checked for the design earthquake. The failure mass weighs 45,000 lb per foot of track, the peak ground acceleration is 0.25g, and the pseudo-static analysis gave the factor of safety shown against an owner target (assumed) of 1.1. The engineer must find the seismic coefficient and force and say whether the slope is acceptable.
| Variable | Value | Description |
|---|---|---|
| amax | 0.25g | |
| W | 45,000 lb/ft | Failure mass |
| FS | 1.05 | Computed pseudo-static FS |
| Target | 1.1 (assumed owner requirement) |
kh = 0.125 and the seismic force is 5,625 lb/ft. FS = 1.05 is below the 1.1 target.
The half-PGA coefficient assumes up to about 1 m (3 ft) of displacement is acceptable, which it is not under track. Either improve the slope (flatter, buttressed or drained) or estimate the permanent displacement with a Newmark analysis (Chapter 6.5) and compare it with what the track can tolerate.
| Topic | Chapter |
|---|---|
| Shear strength parameters (c', φ', su) from lab testing | Chapter 5.2 |
| VST and CPTu undrained strength for soft foundation clay | Chapter 5.1 |
| Soil classification for strength assignment | Chapter 2.2 |
| Groundwater and pore pressure data for slope analysis | Chapter 2.8 |
| Settlement of consolidating embankment during staged construction | Chapter 6.2 |
| Seismic hazard, amax, and site amplification factors | Chapter 6.5 |
| Ground improvement for embankment stability (PVDs, DSM, stone columns) | Chapter 7.2 |
| Retaining wall design at slope toe or crest | Chapter 7.1 |
| Slope failure at track subgrade — failure mode identification | Chapter 2.3 |
| Instrumentation: inclinometers, settlement plates, piezometers | Chapter 5.3 |
| Slope stability documentation in geotechnical reports | Chapter 8.4 |
| Ring shear, triaxial, and direct shear test interpretation | Chapter 5.2 |
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S10 under Supplemental References.
Related section: 6.3.8 Rapid Drawdown Analysis
Look and Thorley (2011) studied riverbank failures in Brisbane during the 2011 floods. The annual probability of flood-induced riverbank failure was 2.7 × 10−3, with a further 1.25 × 10−3 for erosion-related failures. Because the floods submerged much of the alluvial bank, drawdown failures should recur at a similar rate with each comparable event. No deaths or injuries came from riverbank failures in 2011, or in the comparable 1974 flood.
The mechanism was sudden drawdown after the flood peak: excess pore pressure remained in the bank while strength softened, so the failure line fell as the load rose.
A practical lesson came from the council’s lead engineer. Traffic was stopped on the six-lane road along the top of the banks to unload the crest, and the emergency crews then parked their vehicles on the empty road, replacing moving traffic with static load.
For railroad work: the post-flood period is when river-bank and embankment-toe slides develop, so inspections should continue through the recession, not stop at the peak. If a crest is being unloaded, the instruction has to cover equipment staging, and train restrictions should not be replaced with parked work equipment.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §9.7, pp. 302–304. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this part of the analysis, gathered here from across the manual in the November 2026 restructure: 4 tools (1 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).
Each app runs in a web browser on a desktop or a phone, with nothing to install. How to use the apps (1.0.3).
| Slope Stability & Seismic | |||
|---|---|---|---|
| SS | Residual & Fully Softened Strength CorrelationsUsed in Chapter 3.8, 3.8.3 Embankment and Slope Failure Mechanisms; Chapter 6.3, 6.3.6 Residual Strength and Progressive Failure | Calculator ▸ | Guide |
| SS | Slope Stability — Effective StressUsed in Chapter 6.3, 6.3.3 Limit Equilibrium Methods | guide only | Guide |
| SS | Slope Stability — Total StressUsed in Chapter 6.3, 6.3.3 Limit Equilibrium Methods | guide only | Guide |
| SS | Staged Slope Stability — Pore PressureUsed in Chapter 6.3, 6.3.3 Limit Equilibrium Methods | guide only | Guide |
Calculator: Infinite Slope and Rock Plane Slide (Section 6.3.3.6)
Calculator: Circular Slip (Simplified Bishop) (Section 6.3.3.7)
Vegetation helps a slope in three ways: it shields the surface from erosion, its roots reinforce the soil, and transpiration removes water. The effect is seldom counted in design, but for shallow slides it can decide the answer (Nowak, 2012, Section 70.5, p. 1057).
| Vegetation | General range, kPa | General range, psf | Maximum reported, psf |
|---|---|---|---|
| Grasses and shrubs | 2 to 6 | 40 to 125 | 1,250 |
| Deciduous trees | 3 to 10 | 65 to 210 | 1,320 |
| Coniferous trees | 3 to 6 | 65 to 125 | 1,970 |
Nowak (2012), Table 70.7, p. 1057, data from Norris et al. (2008). Use the general range; the maxima are single records.
A grassed cut slope in silty clay stands at 30°. Check a 4-ft-deep slope-parallel slip with and without root cohesion, ignoring suction and seepage.
| Variable | Value | Description |
|---|---|---|
| β | 30° | Slope angle |
| d | 4 ft | Slip depth (within the root zone) |
| γ | 120 pcf | Unit weight |
| φ′ | 28° | Effective friction angle |
| c′ | 0 | Effective cohesion of the soil |
| c′R | 100 psf | Root cohesion, grasses and shrubs (Table 6.3-12) |
The grass is what holds this slope. A shallow slip is likely wherever the cover is lost (fire, herbicide, ditching that strips the toe) or where a slip would be deeper than the roots.
Do not use root cohesion to justify a new steep slope. Use it to explain why an existing slope stands and to rank the risk of losing the cover; check the case with c′R = 0 and with the wet-season water table (Section 6.4.11).
Open the rainfall and suction calculator →
Now includes root cohesion applied over a chosen root depth.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.
Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.
File locations for these documents are listed under Supplemental References.
Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S9 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S10 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.
The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.