3.8.31 Combining Probabilities: Conditional Probability, Bayes’ Theorem and Event Trees

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.31 Combining Probabilities: Conditional Probability, Bayes’ Theorem and Event Trees

Ground hazard ratings combine probabilities all the time: a trigger and a susceptible slope, a failure and a train arriving before it is found, a detector that works or does not. The rules for combining them are few, but applying them in the wrong order gives answers that are off by an order of magnitude. This section sets out the notation and rules used in the manual and shows the one rule most often missed in practice, Bayes’ theorem.

Table 3.8-62. Symbols used in the probability and statistics of risk assessments (Greek letters after the CRC handbook appendix)
SymbolNameMeaning in this manual
P(A)–Probability of event A, from 0 (impossible) to 1 (certain)
ĀcomplementNot A; P(Ā) = 1 − P(A)
A ∪ B, A ∩ Bunion, intersectionA or B (or both); A and B
P(A | B)conditional probabilityProbability of A given that B has happened
μ, σmu, sigmaMean and standard deviation of a population or distribution
x̄, s–Mean and standard deviation of a sample (test results)
COV = σ/μcoefficient of variationScatter relative to the mean (Table 3.9-9)
λlambdaRate of events per year, or per mile per year
T, p = 1/T–Return period (years) and annual probability (Section 3.8.30)
βbetaReliability index: distance from the mean to failure in standard deviations
Φ(z)PhiStandard normal cumulative probability; Pf = Φ(−β)
αalphaSignificance level (for example 0.05 for 95% confidence); also the Gumbel scale parameter
χ²chi-squaredGoodness-of-fit statistic (Section 3.8.33)
tα, n−1Student’s tMultiplier for confidence limits from n tests (Table 3.8-64)

3.8.31.1 Rules for combining probabilities

Equation 3.8-7. Addition, multiplication and total probability

P(A ∪ B) = P(A) + P(B) − P(A ∩ B);   P(A ∩ B) = P(A | B) P(B)
independent events: P(A ∩ B) = P(A) P(B);   at least one of n: P = 1 − Π(1 − pi)
total probability: P(A) = Σ P(A | Bi) P(Bi) over mutually exclusive Bi

Multiply probabilities only along a chain of events (a trigger, then a failure, then a train on it), and only after making each one conditional on the event before it. Add only for events that cannot happen together, or subtract the overlap. Most errors come from multiplying events that are not independent, such as rainfall and high groundwater at the same site.

Equation 3.8-8. Bayes’ theorem: updating a probability with new evidence

P(Bi | A) = P(A | Bi) P(Bi) / Σj P(A | Bj) P(Bj)

P(Bi) is the prior probability (before the evidence), P(A | Bi) the likelihood of the evidence if Bi is true, and P(Bi | A) the updated (posterior) probability.

Bayes’ theorem is how a rating should change when new evidence arrives. A detector trip, a tension crack found on patrol, an inclinometer reading or a borehole that does not find the karst void are all evidence with known or estimable reliability. The updated probability depends on how common the condition was before the evidence, not only on how good the evidence is: a reliable test for a rare condition still produces mostly false alarms, as Example 3.8-8 shows. Conversely, a clean inspection of a site with a high prior probability of instability lowers that probability less than intuition suggests if the inspection would often miss the early signs.

3.8.31.2 Event trees

An event tree follows a hazard from its initiating event to its consequence through a series of branches, each with a conditional probability: for a rock cut, rock reaches the track, the rock is large enough to derail a train, the rock is not detected, and a train arrives before the track is cleared. The annual probability of a derailment is the annual rate of the initiating event times the product of the conditional probabilities along the branch. Because the branches multiply, the weakest assumption controls the answer; show the tree in the report so that the reviewer can see which branch probability carries the result, and test it at half and double its value, as for the life-cycle cost (Section 3.8.40). Fault trees run the other way, from a top event back to the combinations of causes (AND and OR gates) that could produce it, and suit detector, signal and drainage systems with several components.

3.8.31.3 Worked example

Example 3.8-8: Slide Detector Fence: How Often Is a Trip a Real Rockfall?

Problem Statement

A Class I railroad located in Oregon protects a 0.4-mi rock cut with a slide detector fence wired to the block signals. A trip drops the signals to stop, and the next train must proceed at restricted speed while the track is inspected. Train crews and dispatchers complain that most trips turn out to be nothing. The rock cut is being rated, and the engineer must say how much protection the fence actually gives, how often a trip is real, and whether reducing false trips is worth paying for.

1,000storm daysP(R) = 0.020.98Rock: 20No rock: 9800.950.050.050.95Trip: 19No trip: 1Trip: 49No trip: 931Trips = 19 + 49 = 68; real = 19 of 68 = ?Given60 storm days a yearP(rock on track) = 0.02 per storm dayDetection P(T|R) = 0.95False trip P(T|R̄) = 0.05Improved fence: 0.01Required(a) P(trip) per storm day(b) P(rock | trip)(c) P(rock | no trip)(d) Effect of fewer false trips
Figure 3.8-43. Example 3.8-8: probability tree for a rock cut protected by a slide detector fence, shown as counts in 1,000 storm days.

Given

VariableValueDescription
n60 storm days a yearDays with heavy rain, freeze-thaw or high wind, when rockfall and false trips occur
P(R)0.02 per storm dayChance that rock reaches the track on a storm day (from the rockfall log)
P(T | R)0.95Chance the fence trips when rock reaches the track (detection rate)
P(T | R̄)0.05Chance of a false trip on a storm day with no rock (trees, snow load, animals, broken wire)
P(T | R̄)new0.01False-trip rate after replacing the wire and clearing the trees

Required

  • (a) Probability of a trip on a storm day, and trips per year
  • (b) Probability that rock is on the track, given a trip
  • (c) Probability that rock is on the track with no trip, and missed rockfalls per year
  • (d) The answer to (b) with the false-trip rate cut to 0.01

Equations

  1. Eq. 3.8-7 (total probability): P(T) = P(T|R)P(R) + P(T|R̄)P(R̄)
  2. Eq. 3.8-8 (Bayes’ theorem): P(R|T) = P(T|R)P(R) / P(T)
  3. P(R|T̄) = [1 − P(T|R)]P(R) / [1 − P(T)]

Steps

Step 1 · (a) Chance of a trip (Eq. 3.8-7)
0.95 × 0.02 + 0.05 × 0.98 = 0.019 + 0.049
P(T) = 0.068 per storm day; 60 × 0.068 = 4.1 trips a year
Spot check: the tree in Figure 3.8-43 gives 68 trips in 1,000 storm days ✓.
↓
Step 2 · (b) Rock given a trip (Eq. 3.8-8)
0.019 / 0.068
P(R|T) = 0.28: about 1 trip in 3.6 is real
Spot check: 19 real trips out of 68 in the tree ✓.
↓
Step 3 · (c) Rock with no trip
0.05 × 0.02 / (1 − 0.068) = 0.001 / 0.932
P(R|T̄) = 0.0011 per storm day; 60 × 0.02 × 0.05 = 0.06 missed rockfalls a year (about 1 in 17 years)
↓
Step 4 · (d) Fewer false trips
P(T) = 0.019 + 0.01 × 0.98 = 0.0288; P(R|T) = 0.019 / 0.0288
P(R|T) = 0.66; trips fall to 1.7 a year
Spot check: the real trips (1.14 a year) are unchanged; only the false ones (2.9 a year to 0.6 a year) drop.
↓
Solution
About 28% of trips are real rockfalls today; cutting false trips to 1% makes about 66% real, without changing how many real rockfalls are caught.

Solution

About 28% of trips are real rockfalls today; cutting false trips to 1% makes about 66% real, without changing how many real rockfalls are caught.

The fence works: it catches about 95% of the rockfalls that reach the track, leaving roughly one undetected rockfall in 17 years, and that residual figure, not the trip count, is what the rating should carry as the likelihood of a train meeting rock. The complaint from the crews is also correct: with rockfall rare and false trips common, most trips are false even though the fence is a good detector. That is Bayes’ theorem at work, and it is the same reason a screening test for a rare condition gives many false positives. The risk is behavioral: when most trips are false, crews start to treat a trip as a nuisance. Every trip must still be handled as real, and the fence should be maintained to keep the false-trip rate low, because trust in the alarm is part of the protection. Cutting the false-trip rate from 5% to 1% roughly doubles the share of trips that are real and saves about 2.4 restricted-speed inspections a year, which can be set against the maintenance cost in the life-cycle comparison (Section 3.8.40). Record the detection rate and the false-trip rate from the signal logs; they are the inputs that make this calculation site-specific.

Open the detector and inspection evidence (Bayes) calculator →

For railroad work: Treat a probability in a rating as a statement about the evidence available when it was made. When an inspection, a monitoring reading or a detector record arrives, update it explicitly (Eq. 3.8-8) and record the prior, the evidence and the result in the rationale (Section 3.8.43). Keep detector logs that separate real trips from false ones; without them the reliability of the protection cannot be stated.

Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 2 (Sections 2.3 and 2.4, statistical independence and conditional probability, including Bayes’ theorem); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (Greek alphabet; probability definitions and theorems).