Chapter 4.1 — Borings and Sampling

Borings and sampling form the physical backbone of every geotechnical investigation we conduct for railroad clients.
Authors: Daniel P. Colwell and Mario Ruel

Primary Reference: USACE EM 1110-1-1804, Geotechnical Investigations, 1 January 2001, Chapters 8–9 Railroad Standards: AREMA MRE Chapter 1 & 8; the owner railroad's current engineering standards

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

SPT-based consistency and density descriptors and in situ test variability. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Consistency, density and SPT (60 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Undrained shear strengthClayCL-CHVery soft251psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHSoft251386.5522psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHFirm5227831,044psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHStiff1,0441,5662,088psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHVery stiff2,0883,1324,177psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHHard4,177psfLOOK T2.14 / 5.3, p.50
Unconfined compressive strengthCohesive soilCL-CHVery soft (N < 2)0.25tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHSoft (N = 2–4)0.250.3750.5tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHMedium stiff (N = 4–8)0.50.751tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHStiff (N = 8–15)11.52tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHVery stiff (N = 15–30)234tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHHard (N > 30)468tsfIDOT T4.4.6.1.2-2, p.119
SPT N-valueCohesive soilCL-CHVery soft00.51blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHSoft234blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHMedium stiff56.58blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHStiff91215blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHVery stiff162330blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHHard3145.560blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHVery hard60blows/ftGEC5 T23, p.137
SPT N-valueGranular soilGW-SMVery loose4blows/ftLOOK T2.15, p.50
Relative densityGranular soilGW-SMVery loose15%LOOK T2.15, p.50
SPT N-valueGranular soilGW-SMLoose4710blows/ftLOOK T2.15, p.50
Relative densityGranular soilGW-SMLoose152535%LOOK T2.15, p.50
SPT N-valueGranular soilGW-SMMedium dense102030blows/ftLOOK T2.15, p.50
Relative densityGranular soilGW-SMMedium dense355065%LOOK T2.15, p.50
SPT N-valueGranular soilGW-SMDense304050blows/ftLOOK T2.15, p.50
Relative densityGranular soilGW-SMDense657585%LOOK T2.15, p.50
SPT N-valueGranular soilGW-SMVery dense50blows/ftLOOK T2.15, p.50
Relative densityGranular soilGW-SMVery dense85%LOOK T2.15, p.50
Undrained shear strengthClayCL-CHVery soft418psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHSoft418626.5835psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHFirm8351,2001,566psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHStiff1,5662,3503,133psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHVery stiff3,1334,7006,266psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHHard6,266psfCRAIG T4.1, p.121
Density index (relative density)SandSP-SWVery loose (N = 0–4)07.515%CRAIG T8.3, p.309
Normalized SPT valueSandSP-SWVery loose (N = 0–4)01.53blows/ftCRAIG T8.3, p.309
Density index (relative density)SandSP-SWLoose (N = 4–10)152535%CRAIG T8.3, p.309
Normalized SPT valueSandSP-SWLoose (N = 4–10)35.58blows/ftCRAIG T8.3, p.309
Density index (relative density)SandSP-SWMedium dense (N = 10–30)355065%CRAIG T8.3, p.309
Normalized SPT valueSandSP-SWMedium dense (N = 10–30)816.525blows/ftCRAIG T8.3, p.309
Density index (relative density)SandSP-SWDense (N = 30–50)657585%CRAIG T8.3, p.309
Normalized SPT valueSandSP-SWDense (N = 30–50)2533.542blows/ftCRAIG T8.3, p.309
Density index (relative density)SandSP-SWVery dense (N > 50)8592.5100%CRAIG T8.3, p.309
Normalized SPT valueSandSP-SWVery dense (N > 50)425058blows/ftCRAIG T8.3, p.309
Presumed allowable bearing value (BS 8004)Dense gravel, or dense sand and gravelGW, GP, SWFooting width ≥ 3.3 ft; groundwater ≥ B below base12.5ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Medium dense gravel, or sand and gravelGW, GP, SWFooting width ≥ 3.3 ft; groundwater ≥ B below base4.28.312.5ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Loose gravel, or sand and gravelGW, GP, SWFooting width ≥ 3.3 ft; groundwater ≥ B below base4.2ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Compact sandSW, SPFooting width ≥ 3.3 ft; groundwater ≥ B below base6.3ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Medium dense sandSW, SPFooting width ≥ 3.3 ft; groundwater ≥ B below base2.14.26.3ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Loose sandSW, SPFooting width ≥ 3.3 ft; groundwater ≥ B below base2.1ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Very stiff boulder clay and hard clayCL, CHFooting width ≥ 3.3 ft; groundwater ≥ B below base6.39.412.5ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Stiff clayCL, CHFooting width ≥ 3.3 ft; groundwater ≥ B below base3.14.76.3ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Firm clayCL, CHFooting width ≥ 3.3 ft; groundwater ≥ B below base1.62.353.1ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Soft clay and siltCL, CH, MLFooting width ≥ 3.3 ft; groundwater ≥ B below base1.6ksfCURTIN T1.1, p.5
Undrained strength of clay from hand-sample identificationClayVery softExtrudes between fingers420psfATKINSON T5.2, p.61
Undrained strength of clay from hand-sample identificationClaySoftEasily molded in fingers420630840psfATKINSON T5.2, p.61
Undrained strength of clay from hand-sample identificationClayFirmMolded by strong finger pressure8401,2051,570psfATKINSON T5.2, p.61
Undrained strength of clay from hand-sample identificationClayStiffCannot be molded in fingers1,5701,8302,090psfATKINSON T5.2, p.61
Undrained strength of clay from hand-sample identificationClayVery stiffCan be indented by thumbnail3,130psfATKINSON T5.2, p.61
Open this set in the database ↗
CPT–SPT ratio by soil behavior type (9 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
CPT–SPT ratio (qc/pa)/N60Sensitive fine-grainedSBT zone 12–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Organic soils – claySBT zone 21–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Clays – silty clay to claySBT zone 31.5–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Silt mixtures – clayey silt to silty claySBT zone 42–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Sand mixtures – silty sand to sandy siltSBT zone 53–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Sands – clean sand to silty sandSBT zone 65–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Dense sand to gravelly sandSBT zone 76–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Very stiff sand to clayey sand (OC or cemented)SBT zone 85–ROB T5, p.41
CPT–SPT ratio (qc/pa)/N60Very stiff fine-grained (OC or cemented)SBT zone 91–ROB T5, p.41
Open this set in the database ↗
In situ test measurement error (12 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of variation of in situ testStandard penetration testEquipment + procedure + random153045%LOOK T10.3, p.137
Coefficient of variation of in situ testMechanical cone penetration testEquipment + procedure + random152025%LOOK T10.3, p.137
Coefficient of variation of in situ testSelf-boring pressuremeterEquipment + procedure + random152025%LOOK T10.3, p.137
Coefficient of variation of in situ testVane shear testEquipment + procedure + random101520%LOOK T10.3, p.137
Coefficient of variation of in situ testPressuremeter, preboredEquipment + procedure + random101520%LOOK T10.3, p.137
Coefficient of variation of in situ test – measurement errorStandard penetration test (SPT)Total probable range153045%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorMechanical cone (MCPT)Total probable range151525%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorElectric cone (ECPT)Total probable range5715%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorVane shear test (VST)Total probable range101420%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorDilatometer (DMT)Total probable range51115%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorPressuremeter, prebored (PMT)Total probable range101620%FGE T31.5, p.480
Coefficient of variation of in situ test – measurement errorSelf-boring pressuremeter (SBPMT)Total probable range151925%FGE T31.5, p.480
Open this set in the database ↗
Scale of fluctuation (sets boring and test spacing) (28 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Vertical scale of fluctuationClay – suLab testing2.615.428.2ftFGE T31.6, p.484
Vertical scale of fluctuationClay – suVane shear6.613.420.3ftFGE T31.6, p.484
Horizontal scale of fluctuationClay – suVane shear150.9173.9196.9ftFGE T31.6, p.484
Vertical scale of fluctuationSand, clay – qcCPT0.35.059.8ftFGE T31.6, p.484
Horizontal scale of fluctuationSand, clay – qcCPT9.8136.2262.5ftFGE T31.6, p.484
Vertical scale of fluctuationOffshore soils – qcCPT11.151.3ftFGE T31.6, p.484
Horizontal scale of fluctuationOffshore soils – qcCPT45.985.3124.7ftFGE T31.6, p.484
Vertical scale of fluctuationClay – qtCPTu0.71.151.6ftFGE T31.6, p.484
Horizontal scale of fluctuationClay – qtCPTu75.5146216.5ftFGE T31.6, p.484
Vertical scale of fluctuationCohesive-behavior soils – qc1NCPT0.31.152ftFGE T31.6, p.484
Vertical scale of fluctuationIntermediate-behavior soils – qc1NCPT12.153.3ftFGE T31.6, p.484
Vertical scale of fluctuationCohesionless-behavior soils – qc1NCPT1.32.453.6ftFGE T31.6, p.484
Vertical scale of fluctuationSand – fsCPT4.3ftFGE T31.6, p.484
Vertical scale of fluctuationCohesive-behavior soils – IcCPT0.71.151.6ftFGE T31.6, p.484
Vertical scale of fluctuationIntermediate-behavior soils – IcCPT2ftFGE T31.6, p.484
Vertical scale of fluctuationCohesionless-behavior soils – IcCPT12.453.9ftFGE T31.6, p.484
Vertical scale of fluctuationSand – NSPT7.9ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – wLab testing5.223.541.7ftFGE T31.6, p.484
Horizontal scale of fluctuationClay, loam – wLab testing557.8ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – wLLab testing5.216.928.5ftFGE T31.6, p.484
Vertical scale of fluctuationClay, loam – γLab testing7.916.925.9ftFGE T31.6, p.484
Vertical scale of fluctuationOrganic silty clay – eLab testing9.8ftFGE T31.6, p.484
Vertical scale of fluctuationOrganic silty clay – σ′pLab testing2ftFGE T31.6, p.484
Horizontal scale of fluctuationOrganic silty clay – σ′pLab testing590.6ftFGE T31.6, p.484
Vertical scale of fluctuationSand – ln(Dr)SPT12.1ftFGE T31.6, p.484
Horizontal scale of fluctuationSand – ln(Dr)SPT219.8ftFGE T31.6, p.484
Vertical scale of fluctuationSand – n–21.3ftFGE T31.6, p.484
Horizontal scale of fluctuationSand – n–10.8ftFGE T31.6, p.484
Open this set in the database ↗
Railroad investigation requirements (Class I railroads, track spacing) (9 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Boring spacing along track alignmentSubgrade strength zone: Very high to highNew track or rehabilitation500ftLI16 T8.1, p.358
Boring spacing along track alignmentSubgrade strength zone: MediumNew track or rehabilitation200ftLI16 T8.1, p.358
Boring spacing along track alignmentSubgrade strength zone: Low to very lowNew track or rehabilitation100ftLI16 T8.1, p.358
Casing diameter requiring test borings under trackClass I railroad pipeline crossingsBorings each side of track on the crossing centerline48inRRPIPE1 T3.1.1, p.11
Class I railroad public project investigationBoring series spacing along line1,320ftRRGEO text, p.1
Class I railroad public project investigationBorings per series3eachRRGEO text, p.1
Class I railroad public project investigationCut-section boring depth below proposed ditch flowline5ftRRGEO text, p.1
Bridge boring depth (Class I railroad)Below spread footing2× footing widthRRBRG text, p.1
Bridge boring depth (Class I railroad)Below estimated pile tipFrom preliminary static analysis10ftRRBRG text, p.1
Open this set in the database ↗
References (12)
  1. ATKINSON – Atkinson, J. (2007). The Mechanics of Soils and Foundations, 2nd ed. Taylor & Francis.
  2. RRBRG – Ruel, M. (2003). General Requirements for Geotechnical Investigations for Bridge Construction Projects (a Class I railroad).
  3. CRAIG – Craig, R.F. (2004). Craig's Soil Mechanics, 7th ed. Spon Press.
  4. RRPIPE1 – A Class I railroad (2018). Specifications for the Design and Construction of Pipeline Occupancies (revised June 5, 2018).
  5. CURTIN – Curtin, W.G., Shaw, G., Parkinson, G.I., Golding, J.M. & Seward, N.J. (2006). Structural Foundation Designers' Manual, 2nd ed. Blackwell.
  6. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
  7. GEC5 – Sabatini, P.J. et al. (2002). FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017)), Geotechnical Engineering Circular No. 5: Evaluation of Soil and Rock Properties.
  8. IDOT – Illinois DOT (2015). Geotechnical Manual.
  9. LI16 – Li, D., Hyslip, J., Sussmann, T. & Chrismer, S. (2016). Railway Geotechnics. CRC Press / Taylor & Francis.
  10. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.
  11. ROB – Robertson, P.K. & Cabal, K.L. (2010). Guide to Cone Penetration Testing for Geotechnical Engineering, 4th ed. Gregg Drilling & Testing.
  12. RRGEO – A Class I railroad. Public Projects – Geotechnical Requirements.

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
Executive Summary

Borings and sampling form the physical backbone of every geotechnical investigation we conduct for railroad clients. Whether we are planning a simple passing siding for a short line, upgrading a high-density mainline corridor for the owner railroads, or characterizing a soft-ground embankment for high-speed passenger corridor, the quality of subsurface data we deliver is only as good as the drilling methods, sampling protocols, and documentation we employ in the field. This chapter covers the full spectrum of boring techniques used in railroad geotechnical practice — hollow-stem auger, mud rotary, air rotary, and diamond core drilling — alongside standard sampling methods including the Split-Spoon Sampler (SPT), Shelby tube, piston sampler, and rock coring. Emphasis is placed on the complete SPT correction chain required for quantitative analysis, the preservation of sample quality for laboratory testing, and the documentation standards expected by Class I carriers and regional railroads alike. Worked calculation examples, a fully annotated boring log, and a representative laboratory data table are provided. The chapter closes with a field operations checklist, practical recommendations developed from active railroad project experience, and five practice questions with complete answers.

Field Density Test - Core Cutter
Field Density Test - Core Cutter
Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
IS-01SPT energy & procedure correctionN₆₀
IS-02SPT overburden normalization (sands)(N₁)₆₀
RK-10UCS from point load indexσ꜀
IS-03Relative density of sand from SPTDᵣ
IS-05Friction angle of sand from SPT (Peck–Hanson–Thornburn)φ'
IS-07Undrained shear strength of clay from SPTSᵤ
RK-04RQD from volumetric joint countRQD
4.1.1 Background — Why Boring Quality Drives Railroad Deliverable Value

For railroad clients, a boring log is not merely a field record — it is a legal and contractual document. Owner railroads commonly require subsurface investigation records in an approved format, retained for the life of the facility. Confirm the owner railroad's minimum boring log content and sample chain-of-custody requirements when the work is scoped. When our boring logs and sample records are weak, inaccurate, or incomplete, we expose both the client and our firm to design liability, change order disputes, and construction failures.

AREMA's Manual for Railway Engineering (MRE), Chapter 1, Part 1 (Section 2.1, Exploration and Testing), gives guidance on investigations for roadbed and earthwork. AREMA Chapters 8 and 15 define the Cooper E-80 live load and impact allowances for structures, and this manual uses dynamic load factors of about 1.3 to 1.5 for track substructure (Chapter 2.3). Subsurface data must cover the depths these loads influence for the track and structure configuration at hand. Our boring programs must be designed with these loading demands explicitly in mind, and the report should state how each boring depth was chosen.

Boring logs should meet the minimum data requirements of ASTM D5434 and be accompanied by a chain-of-custody record for all SPT and undisturbed samples. Record water content at every sample interval and describe drilling fluid returns during mud rotary drilling.

Our commitment to boring quality is therefore both a technical and a business imperative. A well-executed boring program, thoroughly documented and delivered in the client's preferred format, is a direct competitive advantage in railroad geotechnical practice.

Sampling for UIC subgrade classification

The UIC subgrade classes ( Chapter 2.3, Section 2.3.4 ) are assigned from a short list of parameters. If track-subgrade borings are to support that classification, or a comparison with it, the sampling plan must recover them through the top 6.5 ft of subgrade, the depth Profillidis gives as mechanically affected by train loading:

  • fines content (% finer than about 60 µm), with breaks at 5%, 15% and 40%: bag or jar samples for gradation from every stratum change;
  • plasticity index (PI > 7 is a class break for silty sands and schists): samples for Atterberg limits;
  • rock quality as Los Angeles abrasion (breaks at LA 30 and 40) and susceptibility to weathering: core or bulk rock suitable for LA testing;
  • moisture condition and groundwater, which move a soil up or down a class (“good” vs. “bad” hydrogeology): water levels, moisture contents and seasonal observations;
  • problem materials that make a soil S0 regardless of strength: organics, soluble rock (gypsum, rock salt), quick clay, contaminated ground.

After Profillidis (2014), §7.2, §9.5, Table 9.2. Full reference under Supplemental References.

4.1.2 Drilling Method Selection
4.1.2.1 Hollow-Stem Auger (HSA)

Hollow-stem auger drilling is the preferred method for most railroad embankment, subgrade, and shallow foundation investigations where soil conditions permit. HSA allows continuous sample recovery through the auger stem without removing the drill string, minimizing borehole disturbance and reducing the risk of borehole collapse in granular soils above the water table.

Borehole Drilling Explained
Borehole Drilling Explained
Types of Drilling
Types of Drilling
Geotechnical Drilling
Geotechnical Drilling

Applicable client contexts:

  • Short-line embankment investigations in the eastern United States, where alluvial silts and clays are common above bedrock at manageable depths (typically 30–60 ft)
  • Class I railroad mainline subgrade investigations in Piedmont and coastal plain soils, where HSA provides reliable SPT and Shelby tube access through the silty and sandy overburden
  • Class I railroad investigations in glacial till and lacustrine deposits across the Upper Midwest and Canada, where HSA advances efficiently before encountering refusal on till or glacial erratics

Limitations: HSA is not appropriate in running sands below the water table (where heave into the auger stem is common), in hard or cemented soils, in rock, or where boring depths exceed approximately 100–120 ft. In these conditions, mud rotary or air rotary methods are substituted.

Equipment specifications:

  • Auger inside diameter (ID): 3¼ in. typical for SPT sampling
  • Auger ID for 3-in. Shelby tube sampling: 4¼ in. or larger
  • Auger flights: continuous, 5-ft sections
4.1.2.2 Mud Rotary

Mud rotary drilling uses a pressurized fluid — typically a bentonite-water slurry — to cool the bit, carry cuttings to the surface, and stabilize the borehole wall. It is the preferred method for deep investigations (greater than approximately 100 ft), for offshore or waterway bridge site investigations, and for any condition where borehole stability cannot be maintained with HSA.

Historical vs New Site Boreholes
Historical vs New Site Boreholes

Applicable client contexts:

  • Class I railroad bridge investigations over major river crossings, where boring depths of 80–200 ft are common and borehole stability in granular alluvium is critical
  • Passenger bridge and tunnel portal investigations along the passenger corridor, where highly variable urban subsurface conditions — fill, organic deposits, buried utilities — require the stability control that drilling mud provides
  • Class I railroad investigations in soft lacustrine clays and glacial lake sediments across Manitoba and Saskatchewan, where HSA refusal is rare but borehole wall instability without mud support is a persistent challenge
Subsurface Conditions Encountered During Drilling
Subsurface Conditions Encountered During Drilling

Critical operational note for railroad right-of-way: All drilling fluid returns must be captured and removed from the ROW. Drilling mud discharged onto active track subgrade will breach most railroad right-of-way agreements and can lead to suspension of field work. We require closed-loop mud pits or portable fluid containment systems on all mud rotary jobs conducted within 50 ft of active track.

4.1.2.3 Air Rotary

Air rotary drilling uses compressed air (and in some cases air-foam mixtures) to circulate cuttings and cool the bit. It is the preferred method in rock or very hard soils where drilling fluid is impractical, and is commonly used to advance through casing in overburden before transitioning to diamond core in the rock zone.

Applicable client contexts:

  • Class I railroad investigations in the Appalachian and Piedmont physiographic provinces, where shallow rock is common and air rotary efficiently advances through weathered residual soils before rock coring begins
  • Class I railroad investigations in the Precambrian Shield of northern Ontario and Quebec, where thin overburden over hard granite requires rapid air rotary advancement followed by NQ or HQ coring
  • Short-line investigations for quarry spur and aggregate loading facility foundations in limestone terrain, where rock quality (RQD) and solution feature assessment are primary investigation objectives
4.1.2.4 Diamond Core Drilling

Diamond core drilling recovers continuous cylindrical cores of intact rock for geomechanical characterization. Core drilling is required for any railroad structure with rock-socketed drilled shaft foundations, for tunnel portal and cut investigations, and for any project where bearing on rock or side resistance in rock is a foundation design parameter.

Core barrel sizes used in railroad practice:

SizeOD (in.)Core Diameter (in.)Typical Use
NQ2.981.88Deep exploration; limited recovery in fractured rock
HQ3.782.50Standard size for most railroad bridge foundations
PQ4.833.35Large-diameter cores; used for tunnel and major structure investigations

Some owner railroads require HQ-size core or larger for bridge foundation investigations where drilled shafts are anticipated; confirm when the work is scoped.

Shallow and deep sampling along the track

Shallow subgrade samples are taken with shovels, backhoes or hand augers; hand-auger depth is limited by how easily the auger can be pulled, so a powered auger sometimes advances the hole. Deep embankment sampling uses a drilling contractor: split-spoon SPT (ASTM D1586; 2-in. sampler driven 18 in. by a 140-lb hammer falling 30 in.) and Shelby tubes (ASTM D1587, withdrawn 2024; 3-in. × 30-in. thin-wall tube pushed hydraulically). For mud spots and soft track, a hand-dug trench across the shoulder is often the fastest way to see the layering, the water and the failure zone. At one Class I railroad subgrade repair, test pits confirmed subgrade conditions before the toe berm and cross trenches were designed.

Figure 4.1-6. Hand-auger sample retrieval.
Figure 4.1-6. Hand-auger sample retrieval.
Figure 4.1-7. Split-spoon samplers and a sample drawn from a borehole beside the track (courtesy Dr. E. Selig).
Figure 4.1-7. Split-spoon samplers and a sample drawn from a borehole beside the track (courtesy Dr. E. Selig).
Figure 4.1-8. A sample tube in a hand-dug test pit.
Figure 4.1-8. A sample tube in a hand-dug test pit.
Figure 4.1-9. A drilling crew sampling the subgrade beside the track.
Figure 4.1-9. A drilling crew sampling the subgrade beside the track.
Figure 4.1-10. Hand-dug trench investigating a mud spot.
Figure 4.1-10. Hand-dug trench investigating a mud spot.
Figure 4.1-11. Test pit at a Class I railroad subgrade repair.
Figure 4.1-11. Test pit at a Class I railroad subgrade repair.

After Geotechnology for Railroaders Program, Module 2, Module 3, Module 6.2; Module 2 §10; Module 3 §11; Module 6.2 §02. Full reference under Supplemental References.

Case study: 4.1.14.1 Auger versus core: when crushed rock is logged as soil (Look 2023), in Section 4.1.14 Case Studies.

4.1.3 Standard Penetration Test (SPT) — Procedure and Corrections
4.1.3.1 SPT Procedure (ASTM D 1586)

The Standard Penetration Test is the single most important field test in railroad geotechnical practice. Nearly every design parameter used in embankment stability, foundation bearing capacity, settlement, and liquefaction analysis for our railroad clients is either directly derived from SPT N-values or calibrated against them. Executing the SPT correctly — and applying the complete correction chain before using N-values in analysis — is a non-negotiable quality standard.

Standard Penetration Test
Standard Penetration Test

Procedure:

  1. Advance the borehole to the test depth using the selected drilling method.
  2. Insert a split-barrel sampler (1.375 in. ID, 2.0 in. OD, 18-in. barrel) to the bottom of the borehole.
  3. Apply a seating drive: drive the sampler 6 in. using a 140-lb hammer falling 30 in. Record blow count for seating (not used in N calculation).
  4. Apply the test drive: drive the sampler an additional 12 in. in two 6-in. increments. Record blow counts for each 6-in. increment.
  5. The SPT N-value (blows/ft) is the sum of blow counts for the final 12 in. of penetration.
  6. Retrieve the sampler. Record sample length, soil description, and any subsamples retained for laboratory testing.

Refusal: If 50 blows are required for less than 6 in. of penetration, the test is terminated and recorded as refusal at the applicable penetration depth.

4.1.3.2 SPT Energy Correction

The raw SPT N-value is meaningless for quantitative analysis without correction to a standard energy level of 60% of the theoretical free-fall energy. The corrected value, designated N₆₀, is calculated as:

N60 = Nraw × Em × CB × CR × CS0.60

Where:

  • E_m = hammer energy ratio (energy delivered / theoretical energy). Automatic trip hammer: E_m ≈ 0.80–0.85; safety hammer (rope-and-cathead): E_m ≈ 0.55–0.60; donut hammer: E_m ≈ 0.45.
  • C_B = borehole diameter correction: 1.00 for 2.5–4.5 in. borehole; 1.05 for 6 in.; 1.15 for 8 in. (Skempton 1986)
  • C_R = rod length correction (Youd et al. 2001): 0.75 for rod length < 10 ft; 0.80 for 10–13 ft; 0.85 for 13–20 ft; 0.95 for 20–33 ft; 1.00 for > 33 ft. Rod length includes the stick-up above the ground surface.
  • C_S = sampler correction: 1.00 for a standard sampler, or a sampler with room for liners used with the liners in place; 1.1–1.3 for a sampler with room for liners used without them.

Measure and report hammer energy for each SPT rig (ASTM D4633, withdrawn 2025). Measure energy for each rig with an SPT analyzer (for example a PDA with instrumented rods) at the start of each field mobilization, and report the measured E_m values in the investigation report.

SPT N Values and Trends
SPT N Values and Trends
Inputs for the equations in this section (5)
SymbolWhat it isComes fromHow to get itTypical range
N60SPT blow count = N_raw × E_m × C_B × C_R × C_S 0.60Field testStandard Penetration Test (ASTM D1586); measure hammer energy (ASTM D4633, withdrawn 2025) to correct to N60.loose sand 4–10, dense 30–50 blows/ft · by USCS group
Emhammer energy ratio (energy delivered / theoretical energy)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.≈ 0.80–0.85
CBborehole diameter correction: 1.00 for 2.5–4.5 inTest setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
CRrod length correction: 0.75 for rod length < 10 ftChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
CSsampler correction: 1.00 for split spoon without linerTest setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
4.1.3.3 Overburden Stress Correction

For liquefaction and relative density analyses, N₆₀ is further corrected to a reference overburden stress of one atmosphere (P_a = 2,117 psf, about 1.06 tsf) to yield (N₁)₆₀:

CN = √Paσ'v ≤ 1.7
(N1)60 = CN × N60

Where:

  • P_a = atmospheric pressure = 2,117 psf (about 1.06 tsf)
  • σ'_v = vertical effective stress at the test depth (psf)

Note: C_N is capped at 1.7 (Youd et al. 2001) to prevent unrealistically high corrections at low effective stress (shallow depth).

Inputs for the equations in this section (4)
SymbolWhat it isComes fromHow to get itTypical range
CNintermediate value computed on this pageAnother equationComputed: C_N = √ P_a σ'_v ≤ 1.7project-specific
(N1)60SPT blow count = C_N × N60Field testStandard Penetration Test (ASTM D1586); measure hammer energy (ASTM D4633, withdrawn 2025) to correct to N60.loose sand 4–10, dense 30–50 blows/ft · by USCS group
Paatmospheric pressure = 2,117 psf = 1.0 tsfConstantPhysical constant or standard value.project-specific
σ'vvertical effective stress at the test depth (psf)Another equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
4.1.3.4 SPT Relative Density and Consistency Correlations
MaterialN₆₀ (blows/ft)Relative Density / Consistency
Sand0–4Very Loose
Sand4–10Loose
Sand10–30Medium Dense
Sand30–50Dense
Sand> 50Very Dense / Refusal
Clay0–2Very Soft
Clay2–4Soft
Clay4–8Medium Stiff
Clay8–15Stiff
Clay15–30Very Stiff
Clay> 30Hard
Supplemental reference

Field errors that bias N-values

Energy and rod corrections cannot fix a badly run test. GEC 5 (after Kulhawy and Mayne, 1990) lists the field causes and which way they push N:

Table 6-S3. Factors affecting SPT results

CauseEffectInfluence on N
Inadequate cleaning of holeTest not in original soil; trapped soil compressed in samplerIncreases
Water head not maintained in boreholeBottom of hole becomes quickDecreases
Careless measure of dropEnergy varies, usually lowIncreases
Hammer weight inaccurateEnergy varies 5–7% commonlyEither
Hammer strikes collar eccentricallyEnergy reducedIncreases
No free fall (stiff rope, ungreased sheave, > 2 turns on cathead)Energy reducedIncreases
Sampler driven above bottom of casingDriven in disturbed, densified soilIncreases greatly
Non-standard samplerCorrelations invalidEither
Coarse gravel or cobblesSampler plugged or impededIncreases
Bent drill rodsEnergy transfer inhibitedIncreases

Note that most errors increase N — i.e., they are unconservative. GEC 5 also notes that Skempton’s tabulated energy ratios (donut 0.5–1.0, safety 0.7–1.2, automatic 0.8–1.5 as CE = ER/60) are guidance only; measure ER per ASTM D4633 (withdrawn 2025).

Source: Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017))

Case study: 4.1.14.2 SPT field values: counting error and three rigs on one site (Look 2023), in Section 4.1.14 Case Studies.

Supplemental reference · Carter & Bentley (2016), §3.3

Two More SPT Corrections: Fine Sand Below the Water Table, and Dynamic Probes

Silts and fine sands below the water table. In very fine sand and silt below the water table, the sampler drives faster than the pore water can drain. Dense soils dilate and develop suction, so the blow count reads high. The correction attributed to Terzaghi, and recommended by Tomlinson, reduces blow counts above 15:

N′ = 15 + ½ (N − 15)  for N > 15; no correction for N ≤ 15

Apply it to the field N in saturated silts and very fine or silty sands before the energy and overburden corrections, when the N value will be used for relative density, friction angle or bearing. Do not apply it when using the liquefaction methods, which were calibrated on N values without it.

Which N the density table applies to. The Terzaghi and Peck relative-density limits for sand in Section 4.1.3.4 (0–4, 4–10, 10–30, 30–50, over 50) are good average values for normally consolidated natural sands once the blow counts are corrected for both energy and overburden, that is, for (N1)60 (Skempton 1986). Use (N1)60 with that table for sand; the clay consistency rows are read with N60.

Dynamic probes. Continuous dynamic probes are driven without a borehole and record blows per 4 in. (100 mm). The super-heavy probe (DPSH) has the SPT hammer, drop and diameter, so three consecutive 4-in. counts add up to an equivalent N. For other probes, an equivalent N in granular soil follows from assuming that penetration is proportional to the energy per blow and inversely proportional to the cone area:

NSPT = (Mp Fp As Ps) / (Ms Fs Ap Pp) × probe blows

where M and F are the hammer weight and drop, A is the end area, P is the penetration per recorded count, and subscripts s and p refer to the SPT (140 lb, 30 in., about 3.0 in.², 12 in.) and the probe. For the heavy probe (DPH: 110 lb, 19.7 in., 1.72-in. cone of 2.33 in.², counted per 4 in.) this gives N ≈ 2 × DPH blows per 4 in. There is no such equivalence in clay, where the probe’s rod friction and the soil’s rate effects differ; use probe results in clay only with correlations calibrated to that probe.

For railroad work: Fine sands and silts below the water table are common in floodplain approaches, culvert and bridge foundations, and tracks on old lake beds. Note on the boring log where the Terzaghi correction was applied, so later users do not apply it twice or leave it out of a liquefaction check. Dynamic probes are a quick way to fill gaps between borings along a track shoulder or embankment toe. Correlate them to the SPT at one or two borings on the job before using the conversion, and stop the probe where rod friction builds up in clay.

Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §3.3.2–3.3.3, Eqs. 3.13 and 3.15. Summarized and paraphrased; probe dimensions converted to US units. Full reference under Supplemental References.

Example 4.1-4: Correcting N in Fine Silty Sand Below the Water Table

A culvert under a main line of a Class I railroad located in Louisiana is to be replaced with a jacked pipe. A boring at the jacking pit found fine silty sand below a water table 8 ft deep. At 25 ft an automatic hammer with a measured energy ratio of 82% recorded N = 31, with 3 ft of rod stick-up. A heavy dynamic probe (DPH) pushed beside the boring recorded 14 blows per 4 in. at the same depth. The engineer must correct the blow count, classify the density of the sand for the jacking-pit design, and check the probe against the boring.

silty sand, γ = 120 pcf fine silty sand, γ = 125 pcf (saturated) WT 8 ft Boring N = 31 at 25 ft, ER = 82% DPH probe14 blows / 4 in. 25 ft (N1)60 = ? density = ? GivenN = 31 at 25 ft; ER = 82%Rod length 28 ft; standard sampler4-in. borehole; WT at 8 ftγ = 120 pcf above, 125 pcf belowDPH: 14 blows per 4 in. RequiredFine-sand correction N′N60 and (N1)60Density classProbe-equivalent N Black = given; red = required
Given and required for Example 4.1-4.

Given

VariableValueDescription
N31Field blow count at 25 ft, fine silty sand below the water table
Em0.82Measured hammer energy ratio (automatic hammer)
Rod length28 ft25 ft plus 3 ft stick-up: CR = 0.95
CB, CS1.00, 1.004-in. borehole; standard sampler
Water table8 ftγ = 120 pcf above, 125 pcf below; γw = 62.4 pcf
DPH14 blows per 4 in.Heavy dynamic probe beside the boring, same depth

Required

  • (a) Blow count corrected for fine sand below the water table
  • (b) N60 and (N1)60
  • (c) Relative density class, with and without the fine-sand correction
  • (d) Equivalent N from the dynamic probe

Equations

  1. Eq. 1: N′ = 15 + ½(N − 15) — for N > 15
  2. Eq. 2: N60 = N Em CB CR CS / 0.60
  3. Eq. 3: (N1)60 = CN N60, CN = √(2,117/σ′v) ≤ 1.7
  4. Eq. 4: N ≈ 2 × DPH blows per 4 in.

Steps

Step 1 · (a) Fine-sand correction (Eq. 1)
15 + 0.5 × (31 − 15)
N′ = 23
↓
Step 2 · (b) N60 (Eq. 2)
23 × 0.82 × 1.00 × 0.95 × 1.00 / 0.60
N60 = 29.9
↓
Step 3 · (b) Effective stress at 25 ft
σv = 8 × 120 + 17 × 125 = 3,085 psf; u = 17 × 62.4 = 1,061 psf
σ′v = 2,024 psf
↓
Step 4 · (b) (N1)60 (Eq. 3)
CN = √(2,117/2,024) = 1.02; 1.02 × 29.9
(N1)60 = 31
↓
Step 5 · (c) Density class (Section 4.1.3.4, read with (N1)60)
With the correction: 31, at the boundary of medium dense and dense. Without it: 31 × 0.82 × 0.95/0.60 × 1.02 = 41
Medium dense to dense (corrected) vs. dense (uncorrected)
Spot check: the ratio of the two results, 41.2/30.5 = 1.35, equals 31/23, the size of the fine-sand correction.
↓
Step 6 · (d) Probe check (Eq. 4)
2 × 14
N ≈ 28, close to the field N of 31
↓
Solution
N′ = 23; N60 = 30; (N1)60 = 31; design as medium dense.

Solution

(a) N′ = 23. (b) N60 = 30 and (N1)60 = 31. (c) Medium dense to dense with the fine-sand correction; dense without it. (d) The probe gives N ≈ 28, which agrees with the field blow count.

For the jacking-pit design, take the sand as medium dense. The uncorrected value would overstate the friction angle by a few degrees and understate the face pressure needed to keep the silty sand from running into the pipe. Fine silty sand below the water table is also the soil most likely to flow into a jacking pit or under a pipe face, so the dewatering and face-support plan matters more than the exact density class. Record on the log that the Terzaghi correction was used for the design values. Use the uncorrected N60 for any liquefaction check. Because the probe agrees with the boring, further probes can fill in the profile along the pipe alignment between borings.

4.1.4 Undisturbed Sampling — Shelby Tube and Piston Sampler
4.1.4.1 Shelby Tube Sampling (ASTM D 1587)

Thin-walled Shelby tube samples are the standard method for recovering nominally undisturbed specimens of soft to medium stiff cohesive soils for consolidation, triaxial, and direct shear testing. The degree of sample disturbance is quantified by the Area Ratio (AR):

Storage of Samples
Storage of Samples
AR = De2 - Di2Di2 × 100%

Where:

  • D_e = outside diameter of the tube cutting edge (in.)
  • D_i = inside diameter of the tube (in.)

For a standard 3-in. OD Shelby tube with 2.875-in. ID:

AR = (3.0)2 - (2.875)2(2.875)2 × 100% = 9.000 - 8.2668.266 × 100% = 8.9%

An area ratio of 10% or less is the usual criterion for undisturbed sampling (Hvorslev; see Section 4.1.16). Standard 3-in. thin-walled tubes (ASTM D1587, withdrawn 2024) meet it.

Sample Quality Designation (SQD) per Lunne et al. (1997) for clays with OCR 1–2, based on the void ratio change (Δe/e₀) when the specimen is reloaded to the in situ stress in the consolidation test:

Δe/e₀Sample Quality
< 0.04Very good to excellent
0.04–0.07Good to fair
0.07–0.14Poor
> 0.14Very poor

Report sample quality (SQD) for Shelby tube samples used in consolidation analysis. Where undrained strength of soft clay governs design, specify fixed-piston samplers rather than open push tubes.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
ARintermediate value computed on this pageAnother equationComputed: AR = D_e^2 - D_i^2 D_i^2 × 100%project-specific
Deoutside diameter of the tube cutting edge (in.)Test setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
Diinside diameter of the tube (in.)Test setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
4.1.4.2 Fixed-Piston Sampler

The fixed-piston sampler uses a piston held stationary at the base of the borehole while the sample tube is advanced by hydraulic push, creating a partial vacuum that retains the sample and prevents water entry. Piston samples typically have lower disturbance than conventional push tubes and are preferred for marine and lacustrine soft clay investigations where sample quality is paramount.

Hvorslev fixed-piston sampler.
Supplemental Figure 6-S1. Hvorslev fixed-piston sampler. Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804.
Pitcher double-tube core barrel sampler &mdash; a spring-loaded inner tube that projects ahead of the cutting bit in soft soil and retracts in hard soil; useful in stiff clays and weak rock where Shelby tubes cannot be pushed.
Supplemental Figure 6-S2. Pitcher double-tube core barrel sampler — a spring-loaded inner tube that projects ahead of the cutting bit in soft soil and retracts in hard soil; useful in stiff clays and weak rock where Shelby tubes cannot be pushed. Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804.
Supplemental reference

Materials that defeat standard sampling

GEC 5 (Table 47) flags soils and soft rocks where conventional SPT and tube sampling give misleading results. The ones that show up most often on railroad corridors:

MaterialSampling difficultyEngineering concern
Colluvium and talusThin weak lenses; rock fragments prevent sampling; boulders preclude drillingThin weak layer and water at the colluvium/rock contact control slope stability; talus may sit at FS ≈ 1. Use test pits, trenches, and surface-wave geophysics for talus thickness.
Shale, claystone and other degradable rockRock-like in place, needs coring; drilling water starts degradationRockfill or cut faces degrade on wetting; slope stability decreases progressively.
Cemented sandsHigh blow counts / refusal look like dense sand; coring water may dissolve binderBrittle; collapse if the cement is soluble; long-term strength may drop to uncemented sand.
Sensitive (quick) claysMetastable structure makes undisturbed sampling difficult; may need foil or block samplerCan fail with little or no warning.

For these materials, plan test pits or block samples, triple-tube coring, or in-situ tests (Chapter 5.1) rather than relying on SPT and Shelby tubes.

Source: Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017))

4.1.5 Rock Core Recovery and RQD
4.1.5.1 Core Recovery

Total Core Recovery (TCR) is the length of core recovered expressed as a percentage of the length drilled:

TCR vs SCR vs RQD
TCR vs SCR vs RQD
TCR = Length of core recovered (ft)Length of core run (ft) × 100%
Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
TCRLength of core recovered (ft) Length of core run (ft) × 100%Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
4.1.5.2 Rock Quality Designation (RQD)

RQD quantifies the degree of fracturing in a rock mass. It is defined as the percentage of a core run consisting of intact pieces 4 inches or longer in length:

RQD = ∑ lengths of intact core pieces ≥ 4 in.Total length of core run × 100%
RQD (%)Rock Quality
0–25Very Poor
25–50Poor
50–75Fair
75–90Good
90–100Excellent

Measure RQD on every core run and report it on the boring log alongside TCR, hardness (field estimate) and the visual rock description. Photograph all core boxes before and after the geologist's review, and submit the photos with the boring data package.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
RQD∑ lengths of intact core pieces ≥ 4 inField mapping / core loggingFrom core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water).see rating tables
Supplemental reference

Measuring RQD consistently

USBR’s field rules (after Deere) remove most of the logger-to-logger scatter in RQD:

  • Count only pieces of solid core ≥ 4 in., measured along the centerline of the core, regardless of core diameter.
  • Fit pieces broken by handling or drilling (mechanical breaks) back together and count them as one piece if they make the 4-in. length. Log mechanical breaks separately from natural fractures.
  • Record RQD per run (not per box), with the run length as the denominator.
  • Best applied to N-size or larger core; may not be meaningful for very low-strength, fissile or foliated rock that breaks along foliation.
  • RQD can be estimated at outcrops or cut faces from the volumetric joint count: RQD ≈ 115 − 10.8 Jv (Jv = volumetric joint count, joints per ft summed over three directions), or from line surveys that simulate a 5- or 10-ft run. Oriented line surveys include all fracture orientations and avoid the directional bias of vertical core — useful for rock cut slopes.
RQD computation example: sum of solid pieces &ge; 0.33 ft (4 in.), excluding mechanical breaks (MB), divided by run length &mdash; here 2.4 / 4.7 &times; 100 = 51%. BJ = bedding joint, JT = joint.
Supplemental Figure 6-S5. RQD computation example: sum of solid pieces ≥ 0.33 ft (4 in.), excluding mechanical breaks (MB), divided by run length — here 2.4 / 4.7 × 100 = 51%. BJ = bedding joint, JT = joint. Source: U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I, Ch. 5 (Discontinuities), p. 96.

Table 6-S1. USBR fracture density descriptors (excludes mechanical breaks)

CodeDescriptorCriteria
FD0UnfracturedNo observed fractures
FD1Very slightly fracturedCore mostly in lengths > 3 ft
FD3Slightly fracturedMostly 1–3 ft, few scattered lengths < 1 ft or > 3 ft
FD5Moderately fracturedMostly 0.33–1.0 ft, most about 0.67 ft
FD7Intensely fracturedAverage 0.1–0.33 ft with fragmented intervals
FD9Very intensely fracturedMostly chips and fragments with a few short core lengths

Even-numbered codes (FD2, FD4, FD6, FD8) are used for intervals “in between” two descriptors. Report fracture frequency (natural fractures per foot) alongside RQD; a full entry reads, for example, “Slightly fractured (FD3), core in 0.8–4.7 ft lengths, mostly 1.7 ft; 25% bedding joints / 75% joints.”

Source: U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I, Ch. 5 (Discontinuities)

Supplemental reference

Core barrel selection

Table 6-S2. Rock core drilling methods (GEC 5, Table 5(b), after Day, 1999)

MethodSampleBest applicationLimitations
Rotary coring, conventional double tube (ASTM D2113, withdrawn 2023)0.9–4 in. core up to 10 ft long; standard 2.1 in. (NX-class)Continuous core in sound rockCore lost in fractured or variable rock; bedding and joint dip visible but not strike
Wire-line coring1.1–3.3 in. core, 5–10 ft runsFractured rock (less caving during core removal); deep holes with faster cycle timeSame core-loss and orientation limits
Triple-tube with plastic liner1.1–2.1 in. core encased in linerSwelling clays, shales and soft rock that swell or slake in airSmaller sample; more complex equipment

For railroad cut slopes and bridge foundations in shale, specify triple-tube (split inner tube or liner) coring: shale and claystone that slake on contact with drilling water are routinely logged as “poor RQD” when the fracturing is actually drilling-induced.

Source: Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017))

Typical diamond coring bit.
Supplemental Figure 6-S4. Typical diamond coring bit. Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804.
4.1.6 Worked Calculation Examples
The three examples cover the corrections and ratios that turn field records into design numbers: SPT corrections, the area ratio of a sampling tube, and RQD. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 4.1-1: SPT Corrections for a Bridge Approach Embankment

A boring for a bridge approach embankment replacement on a Class I railroad located in western Kansas passes through silty sand into medium-dense alluvial sand. The raw blow count is corrected first for energy and equipment, giving N60, and then for overburden, giving (N1)60, which is the value most correlations for sand expect.

Embankment / sandSand051015202530Depth (ft)GWT 8 ftN = 18 blows/ft at 20 ftN60, (N1)60, Dr = ?Automatic trip hammer, 4-in. HSAGivenN = 18 at 20 ftEm = 0.82; CB = 1.00CR = 0.95; CS = 1.00γ = 120 / 122 pcf; GWT 8 ftRequiredN60 (N1)60 Relative densityBlack = given; red = required
Given and required for Example 4.1-1.

Given

VariableValueDescription
N18 blows/ftRaw blow count at 20 ft
Em0.82Automatic trip hammer
CB1.004-in. hollow-stem auger hole
CR0.95About 23 ft of rod (20 ft plus 3 ft of stick-up)
CS1.00Split spoon without liner
γ120 pcf above, 122 pcf below the water table
zw8 ftWater table

Required

  • N60
  • (N1)60 and relative density

Equations

  1. Eq. 1: N60 = N Em CB CR CS / 0.60 — energy and procedure correction
  2. Eq. 2: σ′v = σv − γw(z − zw) — effective stress at the test depth
  3. Eq. 3: CN = (2,117/σ′v)0.5 ≤ 1.7; (N1)60 = CN N60 — overburden normalization

Steps

Step 1 · N60 (Eq. 1)
18 × 0.82 × 1.00 × 0.95 × 1.00 / 0.60 = 18 × 1.298
N60 = 23.4, use 23
↓
Step 2 · σ′v at 20 ft (Eq. 2)
σv = 8(120) + 12(122) = 2,424 psf; u = 12(62.4) = 749 psf
σ′v = 1,675 psf
↓
Step 3 · CN and (N1)60 (Eq. 3)
(2,117/1,675)0.5 = 1.124; 1.124 × 23
(N1)60 = 26
Spot check: CN is just above 1 because the effective stress is a little below one atmosphere (2,117 psf).
↓
Solution
N60 = 23; (N1)60 = 26.

Solution

N60 = 23 and (N1)60 = 26, at the medium dense to dense boundary (Dr about 65 to 75%).

The automatic hammer delivers more energy than the 60% standard, so the corrected count is higher than the raw one. Sand this dense has moderate to high liquefaction resistance, but it should still be screened formally with the site’s design ground motion (Chapter 6.5).

Example 4.1-2: Area Ratio of a Push Tube in Soft Clay

Soft marine clay is to be sampled at 22 to 26 ft for a passenger bridge approach rehabilitation. The crew has a 3.5-in. push tube. Its area ratio says how much soil the tube displaces; the project specification says which sampler must be used.

cutting shoeDe = 3.50 in.Di = 3.375 in.Section at the shoeArea ratio = ? Acceptable?GivenDe = 3.50 in.Di = 3.375 in.Piston sampling required for soft clayRequiredArea ratio Ar Is the tube acceptable?Black = given; red = required
Given and required for Example 4.1-2.

Given

VariableValueDescription
De3.50 in.Outside diameter at the cutting shoe
Di3.375 in.Inside diameter at the cutting shoe
SpecPiston sampling required for soft clay used for undrained strengthProject specification

Required

  • Area ratio and whether the tube is acceptable

Equations

  1. Eq. 1: AR = (De² − Di²) / Di² × 100% — area ratio; ASTM D1587 (withdrawn 2024) requires 10% or less

Steps

Step 1 · AR (Eq. 1)
(12.25 − 11.39) / 11.39 × 100 = 0.86 / 11.39 × 100
AR = 7.5% < 10%: meets ASTM D1587 (withdrawn 2024)
↓
Step 2 · Specification
Piston sampler required regardless of AR
↓
Solution
AR = 7.5%, geometrically acceptable, but a piston sampler is still required.

Solution

AR = 7.5%, so the tube meets ASTM D1587 (withdrawn 2024). The specification still requires a fixed-piston sampler for soft clay strength samples.

Area ratio controls one kind of disturbance; the piston controls another, by holding the sample in the tube during withdrawal. Record the requirement in the pre-field plan and procure the piston sampler before mobilization.

Example 4.1-3: RQD and Recovery of a Sandstone Core Run

A 10-ft HQ core run in sandstone for a bridge scour and foundation investigation on a Class I railroad located in the Appalachians. RQD counts only sound pieces at least 4 in. long; recovery counts everything that came up.

HQ sandstone core run79.56.584.5not recoveredRun = 120 in. (10 ft); recovered 45.0 in.Pieces (in.): 7, 2.5, 9.5, 1, 6.5, 8, 0.5, 4.5, 3, 2.5RQD = ? TCR = ? Rock quality?GivenRun 10 ft = 120 in. (HQ)Ten pieces, total 45.0 in.RQD counts pieces ≥ 4 in.RequiredRQD and TCRRock quality and foundation meaningBlack = given; red = required
Given and required for Example 4.1-3.

Given

VariableValueDescription
Run10 ft = 120 in.HQ core
Pieces7.0, 2.5, 9.5, 1.0, 6.5, 8.0, 0.5, 4.5, 3.0, 2.5 in.Measured in the core box; total 45.0 in.

Required

  • RQD and TCR
  • Rock quality and what it means for the foundation

Equations

  1. Eq. 1: RQD = Σ (pieces ≥ 4 in.) / run length × 100% — ASTM D6032
  2. Eq. 2: TCR = recovered length / run length × 100% — total core recovery

Steps

Step 1 · Pieces ≥ 4 in.
7.0 + 9.5 + 6.5 + 8.0 + 4.5
35.5 in.
↓
Step 2 · RQD (Eq. 1)
35.5 / 120
RQD = 30%
↓
Step 3 · TCR (Eq. 2)
45.0 / 120
TCR = 37.5%
Spot check: All ten pieces sum to 45.0 in.
↓
Solution
RQD = 30% (poor); TCR = 37.5%.

Solution

RQD = 30%, poor rock; TCR = 37.5%.

Low RQD with low recovery points to highly fractured sandstone, probably a weathered or fault-adjacent zone. Have a geologist review the core box photographs and describe the fractures before foundation design proceeds. This rock is unlikely to suit end bearing without a deep socket into competent rock below.

4.1.7 Annotated Sample Boring Log

Project: Bridge Replacement — a Class I railroad line located in Virginia Boring: B-2 Date: April 15, 2026 Driller/Rig: drilling subcontractor, track-mounted rig Drilling Method: HSA (0–42 ft), Mud Rotary (42–65 ft) Hammer Type: Automatic Trip (E_m = 0.83, measured by PDA; N₆₀ uses C_R by rod length with 3 ft of stick-up) Water Table: Encountered at 18.0 ft during drilling; stabilized at 16.5 ft after 30 minutes

Pile Boring Log
Pile Boring Log
Depth (ft)SampleBlows (6"/6"/6")N_rawN₆₀Soil DescriptionLab Tests
0–2SS-13/4/488Brown medium sand, trace gravel; fill—
5–6.5SS-25/6/71313Brown silty fine sand; medium dense; moistSieve
10–11.5SS-38/10/122226Gray silty sand; medium dense; moistSieve, Atterberg
15–16.5ST-1Push——Gray-brown firm silty clay; push recovery 18 in.Consol, UU Tri
20–21.5SS-412/15/183343Gray sandy gravel; dense; wet; below GWT—
25–26.5SS-518/22/254762Gray sandy gravel; very dense; wet—
30–31.5SS-650/4"R—Refusal: 50 blows for 4 in. of penetration—
35–36.5CS-1Core runTCR=75%—Gray medium sandstone; RQD=55%; moderately fracturedUnconf. Comp.
40–41.5CS-2Core runTCR=92%—Gray-brown sandstone; RQD=88%; slightly fractured—

SS = Split Spoon; ST = Shelby Tube; CS = Core Sample; R = Refusal; GWT = Groundwater Table; Consol = Consolidation; UU Tri = Unconsolidated-Undrained Triaxial; Unconf. Comp. = Unconfined Compression

Figure 4.1-1 Placeholder: Full-scale boring log in a typical railroad format, showing graphical soil profile, blow count vs. depth plot, water level indicators, and sample retention summary. [Insert CAD or boring log software output here.]

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
4.1.8 Representative Laboratory Data Table — Chapter 4.1 Samples
SampleDepth (ft)Soil Descriptionw_n (%)LL (%)PL (%)PIγ_d (pcf)USCSLab Tests Completed
SS-310–11.5Silty fine sand14.222184104SC-SMSieve, Atterberg
ST-115–16.5Silty clay38.748242482CLConsol, UU Tri
SS-420–21.5Sandy gravel8.1NPNPNP118GW-GMSieve
CS-135–36.5Sandstone core—————RockUnconf. Comp.
Water Content Test
Water Content Test
4.1.9 Reference Photographs
Standard Penetration Test
Standard Penetration Test
TCR vs SCR vs RQD
TCR vs SCR vs RQD
BOREHOLE DRILLING EXPLAINED
BOREHOLE DRILLING EXPLAINED
4.1.10 Practical Recommendations
  1. Energy calibration at every mobilization. Do not assume a fixed E_m for any rig or hammer configuration. Measure hammer energy with an instrumented anvil at the start of each field mobilization and after any hammer change. Record energy measurements for all SPT borings, on every railroad project, as a quality floor.
  2. Casing in heaving sands. When HSA reveals running sand conditions below the water table, advance steel casing before continuing SPT sampling. Heave into the auger stem produces N-values that are artificially low and results in unconservative design parameters for foundations and retaining structures. This is especially important for Class I railroad projects in the alluvial Great Plains, where highly permeable sandy gravels are common below shallow water tables.
  3. Shelby tube conditioning before push. Clean the borehole base of disturbed cuttings before inserting the Shelby tube by washing and bailing. Any disturbed material at the base of the borehole enters the tube first, contaminating the upper portion of the sample and degrading consolidation test results. Document borehole conditioning in the field log for every undisturbed sample.
  4. Core box photography protocol. Photograph core boxes immediately after recovery and before any handling or logging. Photograph again after geologist marking with depth lines and piece numbers. Submit both sets of photographs. Keep this two-step photographic record on every project. Establish this habit across all clients — it protects us in the event of sample loss or dispute.
  5. ROW and RWP compliance — pre-field confirmation. Confirm that all field personnel hold current Roadway Worker Protection certification for the specific railroad before mobilization. Owner railroads may require RWP training from their own approved provider, and a certification from one railroad may not be accepted by another. Short lines vary by property — confirm requirements with the local operating division engineering contact before each mobilization. Failure to confirm RWP certification prior to field work is a contract compliance failure, not merely a safety matter, and is grounds for termination of on-site access.
  6. Drilling fluid management on the owner railroads. Document drilling fluid type, additives and disposal method in the field log and the investigation report. Use low-toxicity, biodegradable additives wherever possible. On the railroad's projects in areas subject to provincial environmental regulation, submit a fluid management plan to the client's environmental coordinator before field mobilization.
Supplemental reference

Block samples and the Swedish foil sampler

Hunt describes two sampling methods for soils that thin-walled tubes handle poorly:

  • Block samples from test pits. Particularly useful in residual soils that are hard to tube-sample. The block is hand-trimmed from the pit wall with a knife, coated with paraffin on the exposed faces, cut loose, turned over and coated on the remaining face, then boxed for shipment. Weaker soils with some cohesion are trimmed into small cylinders instead. On the right-of-way, a test pit in the embankment slope or track zone needs the same flagging and track-protection approvals as a boring, plus a backfill and compaction plan the railroad accepts.
  • Swedish foil sampler. Produces continuous high-quality samples (tube typically 8 ft long) in soft, sensitive clays. Thin steel foils unreel from the cutting edge and line the sample so that it does not rub against the tube wall. Its main use is locating the shear zone in a slope failure — a direct application to railroad embankment slides on soft clay.
Block samples in various stages of trimming and sampling.
Supplemental Figure 6-S3. Block samples in various stages of trimming and sampling. Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804.

Source: Hunt, R. E. (2005). Geotechnical Investigation Methods: A Field Guide for Geotechnical Engineers. CRC Press

Project management · Haidar (2016)

Estimating Drilling Program Durations from Quantity and Production Rate

Haidar gives the basic duration relation used in CPM scheduling:

Activity duration = Work quantity ÷ Production rate (Haidar Eq. 3.1)

The time unit (hours, shifts, days) may be anything, provided it is used consistently throughout the schedule. He notes that the estimates need not be exact. When every duration is reasonable, over- and under-estimates tend to offset, and spending too much effort refining individual durations makes the schedule harder to build without making it better. He lists the factors that control how accurate an estimate will be: number of projects, complexity, design duration, construction method, resource availability, work quantity, labor and equipment productivity, quality of field management, geography and site conditions, and concurrent activities. He recommends getting each estimate from the person who will manage the work.

On logic, Haidar recognizes three relationships: predecessor, successor, and concurrent (independent). Concurrent means only that neither activity depends on the other, not that they must run at the same time. There is usually more than one correct sequence, and choosing among them requires knowing how the work is actually built.

For railroad work: split the drilling quantity by method, because production differs widely. Soil drilling with SPT intervals, Shelby tube sampling, rock coring and in-hole testing each need their own quantity and rate. Production rates should come from the firm’s own driller records for similar ground and access, not from catalog figures. Express the rate per effective hour under track protection. As an illustration only: 480 ft of soil drilling at 30 ft per effective hour is 16 effective hours. If a track window yields about 5 effective hours after protection setup, moves between holes and clearing, the work needs 4 windows. Add separate activities for rock coring, grouting or backfill, and the move-in and move-out of each site. Off-track work, such as CPT soundings from an access road or borings at the embankment toe, is often concurrent with on-track borings and can fill time when windows are cancelled. Record actual footage and hours each shift so that the next program’s production rates are better than this one’s.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 64–66. Summarized and paraphrased. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
4.1.11 Field Operations Checklist — Borings and Sampling

Checklist · Part V · Subsurface Exploration

Field Operations Checklist — Borings and Sampling

Pre-Mobilization0 of 7
During Drilling0 of 10
Post-Field0 of 5

McKinnon (2012) builds on the accident ratio: for every serious injury there are larger numbers of minor injuries, more property-damage events, many near misses, and beneath those a broad base of high-risk acts and conditions. Heinrich (1931) reported 1 serious injury : 29 minor injuries : 300 no-injury accidents. Bird and Germain (1966), from nearly 2 million reported accidents, gave 1 serious : 10 minor : 30 property damage : 600 near misses. A British Tye-Pearson study gave 1 : 3 : 50 first aid : 80 damage : 400 near misses, and the U.K. HSE (1993) gave 1 : 11 : 441. McKinnon stresses that the exact numbers matter less than the conclusion: near misses are far more frequent than injuries, and often the only difference between the two is luck.

Because near misses share the same causes as accidents, they are free warnings. McKinnon’s system (recognition, reporting, risk ranking, investigation and remedy) does not investigate every report. Each near miss is ranked on a simple matrix of potential loss severity versus probability of recurrence. Events in the high–high cell are investigated as rigorously as a serious injury, as are high–medium-high and medium-high–medium-high events; lower-ranked reports are tracked and addressed once the high-potential ones are under control. He cites the “critical few” principle: perhaps 20% of near misses hold 80% of the loss potential. A no-blame policy is essential, since programs fail when reporting leads to discipline. He notes that rail has adopted this model through CIRAS, a confidential reporting system used in Britain.

For railroad work: Add near-miss reporting to the borings and sampling field checklist. Drilling on the right-of-way combines rotating equipment and overhead or buried utilities with train movements and roadway worker protection, so close calls such as a rig mast near the foul envelope, an unannounced train during setup, or a mislocated utility should be recorded on the daily report, ranked, and discussed at the next job briefing. The railroad’s own close-call program (for example FRA’s C3RS on participating carriers) may also apply; follow the client’s reporting rules.

Source: McKinnon, R. C. (2012). Safety Management: Near Miss Identification, Recognition, and Investigation. Boca Raton, FL: CRC Press (Taylor & Francis), pp. 12–17, 24–26. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Ticks are saved in this browser.
Plain text version

Pre-Mobilization

  • [ ] RWP certification confirmed for all field personnel (client-specific)
  • [ ] Boring layout plan approved by client engineering contact
  • [ ] Track protection form or ROW access agreement executed
  • [ ] Drilling fluid management plan submitted
  • [ ] Core boxes, sample containers, wax/end caps, and chain-of-custody forms staged
  • [ ] SPT energy measurement device calibrated and staged (confirm whether the owner railroad requires measured energy)
  • [ ] Emergency contact list posted (client dispatcher, project manager, safety officer)

During Drilling

  • [ ] Borehole diameter and drilling method recorded on log
  • [ ] Hammer type and energy ratio recorded on log (measured E_m where required)
  • [ ] Rod length recorded at each SPT interval for C_R correction
  • [ ] SPT seating drive and test drive blow counts recorded separately
  • [ ] Borehole conditioning documented before each Shelby tube push
  • [ ] Sample lengths measured and recorded immediately after recovery
  • [ ] Chain-of-custody form completed for each sample
  • [ ] Core boxes labeled and photographed (pre- and post-logging)
  • [ ] Drilling fluid returns observed and documented (mud rotary)
  • [ ] Water table encountered depth and stabilized depth recorded

Post-Field

  • [ ] Samples packaged and transported under chain-of-custody to laboratory
  • [ ] Boring logs drafted within 48 hours of field completion
  • [ ] Energy calibration data attached to boring log submittal
  • [ ] Core box photographs uploaded to client data portal
  • [ ] Field notes, drillers' logs, and geologist logs archived per client data retention requirements
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
4.1.12 Cross-References
TopicSee Chapter
Boring location and depth planningChapter 3.9
SPT-based classificationChapter 2.2
In situ testing (CPT, VST, PMT)Chapter 5.1
Groundwater measurements during drillingChapter 2.8
Foundation bearing capacity from SPTChapter 6.1
Settlement analysis from consolidation samplesChapter 6.2
Liquefaction screening using (N₁)₆₀Chapter 6.5
Laboratory testing of recovered samplesChapter 5.2
Boring log reporting and submittalChapter 8.4
4.1.13 Practice Questions — Chapter 4.1
Each question is worked in the same five parts as the examples. Question 4.1-4 is a planning question, so its steps are a chain of decisions rather than equations.
Question 4.1-1: SPT Corrections With a Donut Hammer

Problem Statement

A boring for a railroad bridge abutment on a Class I railroad located in Nebraska was drilled with a donut hammer, although the owner (assumed) requires automatic hammers on bridge borings. At 35 ft the raw blow count in sand is 24. The engineer must correct the blow count, describe the sand, and decide what to do about the hammer requirement before the data are used for abutment design.

Sand, γ = 118 pcfSand, γ = 125 pcf010203040Depth (ft)GWT 12 ftN = 24 blows/ft at 35 ftN60, (N1)60, Dr = ?Donut hammer, 5-in. hole (Nebraska abutment)GivenN = 24 at 35 ftEm = 0.45 (donut)CB, CR, CS = 1.05, 1.00, 1.00GWT 12 ftOwner: automatic hammers on bridgesRequired(a) N60 (b) (N1)60 (c) Relative density(d) Action on hammer ruleBlack = given; red = required
Given and required for Question 4.1-1.

Given

VariableValueDescription
N24 blows/ft at 35 ftRaw blow count
Em0.45Donut hammer
CB, CR, CS1.05, 1.00, 1.005-in. hole; 35 ft of rod; no liner
γ118 pcf to 12 ft; 125 pcf belowWater table at 12 ft
Owner rule (assumed)Automatic hammers on bridge borings

Required

  • (a) N60
  • (b) (N1)60
  • (c) Relative density
  • (d) Action on the hammer requirement

Equations

  1. Eq. 1: N60 = N Em CB CR CS / 0.60 — energy and procedure correction
  2. Eq. 2: σ′v = σv − γw(z − zw) — effective stress at the test depth
  3. Eq. 3: CN = (2,117/σ′v)0.5 ≤ 1.7; (N1)60 = CN N60 — overburden normalization

Steps

Step 1 · (a) N60
24 × 0.45 × 1.05 / 0.60
18.9, use 19
↓
Step 2 · σ′v
12(118) + 23(125) = 4,291 psf; u = 23(62.4) = 1,435 psf
2,856 psf
↓
Step 3 · (b) (N1)60
CN = (2,117/2,856)0.5 = 0.861; 0.861 × 19
16
↓
Step 4 · (c) Density
Medium dense
↓
Step 5 · (d) Hammer
The energy correction already accounts for the donut hammer; the problem is reliability, not scale.
↓
Solution
N60 = 19; (N1)60 = 16; medium dense; redrill controlling borings.

Solution

(a) N60 = 19. (b) (N1)60 = 16. (c) Medium dense. (d) Report with a data-quality caveat, notify the railroad, and redrill borings that control design with a calibrated automatic hammer.

Do not scale the donut-hammer count up as if it had been driven with an automatic hammer: an automatic hammer in the same sand would have given about 13 blows and the same N60. Donut-hammer energy is highly variable and seldom measured, so the assumed 0.45 carries a large uncertainty.

Question 4.1-2: Area Ratio and Recovery of a Shelby Tube

Problem Statement

On a passenger corridor project, a Shelby tube was pushed 18 in. into soft organic clay beneath a track embankment and came back with 14.5 in. of sample. The specification calls for piston sampling in soft clay. The field engineer must check the tube geometry and recovery and decide whether the sample can go to the laboratory for strength testing.

A Shelby tube in soft organic clay on a passenger corridor project. Recovery as well as area ratio says whether the sample is fit for strength testing.

cutting shoeDe = 3.0 in.Di = 2.875 in.Section at the shoeAr = ? Recovery ratio = ? Field action?18 in.recovery 14.5 in.GivenDe = 3.0 in.; Di = 2.875 in.Push 18 in.; recovery 14.5 in.Spec: piston sampling in soft clayRequired(a) Area ratio(b) Recovery ratio and meaning(c) Field actionBlack = given; red = required
Given and required for Question 4.1-2.

Given

VariableValueDescription
De, Di3.0 in.; 2.875 in.At the cutting shoe
Push, recovery18 in.; 14.5 in.
SpecPiston sampling for soft clay

Required

  • (a) Area ratio
  • (b) Sample recovery ratio and its meaning
  • (c) Field action

Equations

  1. Eq. 1: AR = (De² − Di²) / Di² × 100% — area ratio; ASTM D1587 (withdrawn 2024) requires 10% or less
  2. Eq. 2: SRR = recovered / pushed × 100%

Steps

Step 1 · (a) AR
(9.000 − 8.266) / 8.266
8.9% < 10%: acceptable
↓
Step 2 · (b) SRR
14.5 / 18
80.6%: below the 85 to 90% expected
↓
Step 3 · (c) Action
Index tests only; resample with a fixed piston
↓
Solution
AR 8.9%; SRR 81%; resample with a piston.

Solution

(a) AR = 8.9%, acceptable. (b) SRR = 81%, which suggests sample loss or compression near the base. (c) Keep the sample for water content and index tests and resample the interval with a fixed-piston sampler.

Low recovery in soft organic clay usually means soft material piped past the valve or gas-rich clay compressed during withdrawal. Record the deviation and the corrective action in the field log.

Question 4.1-3: RQD in Weathered Limestone and End Bearing

Problem Statement

A short-line railroad located in Missouri is replacing a timber trestle and wants to know whether a pile or shaft can end-bear on limestone. The first 10-ft HQ core run in weathered limestone recovered ten pieces totaling 40.5 in. The engineer must compute the rock quality from the core and recommend whether end bearing at this level is reasonable.

Weathered limestone, first HQ run58.567.54.5not recoveredRun = 120 in. (10 ft); recovered 40.5 in.Pieces (in.): 2.5, 5, 0.5, 8.5, 1, 6, 3, 7.5, 2, 4.5RQD, TCR = ? End bearing reasonable?GivenRun 120 in.Ten pieces, total 40.5 in.Trestle replacement (Missouri)Required(a) RQD and TCR(b) Rock quality(c) End bearing recommendationBlack = given; red = required
Given and required for Question 4.1-3.

Given

VariableValueDescription
Run120 in.
Pieces2.5, 5.0, 0.5, 8.5, 1.0, 6.0, 3.0, 7.5, 2.0, 4.5 in.Total recovered 40.5 in.

Required

  • (a) RQD and TCR
  • (b) Rock quality
  • (c) Recommendation for end bearing

Equations

  1. Eq. 1: RQD = Σ (pieces ≥ 4 in.) / run length × 100% — ASTM D6032
  2. Eq. 2: TCR = recovered length / run length × 100% — total core recovery

Steps

Step 1 · (a) Pieces ≥ 4 in.
5.0 + 8.5 + 6.0 + 7.5 + 4.5 = 31.5 in.
RQD = 26%; TCR = 40.5/120 = 34%
↓
Step 2 · (b) Quality
Poor; highly fractured or cavity-bearing
↓
Step 3 · (c) Recommendation
Core through the zone; check for karst; socket in competent rock (RQD > 50%) if found at reasonable depth
↓
Solution
RQD 26%, TCR 34%: poor rock; do not plan on end bearing here.

Solution

(a) RQD = 26%, TCR = 34%. (b) Poor rock. (c) End bearing here risks punching into voids or soft infill.

Advance the boring through the weathered zone, watch for loss of drilling fluid and rod drops that mark karst, and redesign for drilled shafts socketed into competent rock if it is found at an acceptable depth. Bearing resistance on fractured rock (RQD 25 to 50%) is much lower than on competent rock (Chapter 6.1).

Question 4.1-4: Emergency Drilling for a Suspected Sinkhole

Problem Statement

A track geometry deviation appeared overnight on a Class I railroad main line in karst country, and a sinkhole is suspected. A 10-mph slow order is in place and the railroad wants borings within 48 hours. The engineer must choose the drilling method, set the minimum boring program, and agree the documentation needed for an emergency investigation.

Pinnacled limestone (karst)Main line: overnight cross-level dip, 10-mph slow ordervoid?Drilling method = ? Boring program = ? Documentation = ?Borings needed within 48 hoursGivenSudden surface and cross-level deviationSuspected sinkhole / collapseTimeline 48 hoursRequired(a) Drilling method(b) Emergency documentation(c) Minimum boring programBlack = given; red = required
Given and required for Question 4.1-4.

Given

VariableValueDescription
SymptomSudden surface and cross-level deviationOvernight
Suspected causeSinkhole or soft ground collapse
Timeline48 hours

Required

  • (a) Drilling method
  • (b) Documentation for an emergency investigation
  • (c) Minimum boring program

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · (a) Method
Hollow-stem auger, with mud rotary and casing as backup; no air rotary, which can destabilize a cavity
↓
Step 2 · (b) Documentation
Preliminary report within 24 hours; daily briefings; immediate notice of any condition affecting track safety; chain of custody for samples
↓
Step 3 · (c) Program
Three borings on the track centerline: at the deviation and 25 ft either side; 30 ft or 10 ft into competent material; SPT every 2.5 ft in the top 15 ft; tubes in soft cohesive soil
↓
Solution
HSA with mud rotary backup; three borings; reporting agreed up front.

Solution

(a) Hollow-stem auger with mud rotary backup. (b) Agree the reporting schedule and safety notifications with the railroad before drilling. (c) Three borings, at the deviation and 25 ft either side, to 30 ft or 10 ft into competent material.

Air pressure in a hole beside a marginal cavity can trigger the collapse the investigation is trying to find, which is why air rotary is ruled out. Deliver preliminary logs and a geohazard assessment by the end of day 2.

Question 4.1-5: Core Size, RQD and Presentation for a Dolomite Bridge Foundation

Problem Statement

A Class I railroad located on the Assiniboine River in Manitoba is replacing a river bridge. Dolomite is expected at about 50 ft and the specification calls for HQ core. The first 10-ft run in rock recovered eight pieces totaling 67 in. The engineer must report the core size, compute the rock quality, and say how the data should be presented and tested for the foundation design.

Dolomite at about 50 ft, first HQ run118143.595.58.57.5not recoveredRun = 120 in. (10 ft); recovered 67.0 in.Pieces (in.): 11, 8, 14, 3.5, 9, 5.5, 8.5, 7.5HQ diameter = ? RQD, TCR = ? Presentation, UCS?GivenCore size HQ (specification)Run 120 in.; eight piecesTotal recovered 67.0 in.Required(a) HQ core diameter(b) RQD and TCR(c) How to present them(d) UCS testingBlack = given; red = required
Given and required for Question 4.1-5.

Given

VariableValueDescription
CoreHQSpecification
Run120 in.First run in dolomite
Pieces11.0, 8.0, 14.0, 3.5, 9.0, 5.5, 8.5, 7.5 in.Total recovered 67.0 in.

Required

  • (a) HQ core diameter
  • (b) RQD and TCR
  • (c) How to present them
  • (d) UCS testing

Equations

  1. Eq. 1: RQD = Σ (pieces ≥ 4 in.) / run length × 100% — ASTM D6032
  2. Eq. 2: TCR = recovered length / run length × 100% — total core recovery

Steps

Step 1 · (a) HQ core
2.50-in. diameter
↓
Step 2 · (b) RQD and TCR
Pieces ≥ 4 in. = 63.5 in.; 63.5/120; 67.0/120
RQD = 53% (fair); TCR = 56%
↓
Step 3 · (c) Presentation
Run-by-run RQD and TCR columns; RQD bar chart beside the log; core photo numbers; flag runs below 25%
↓
Step 4 · (d) UCS
At least three specimens per rock unit (ASTM D7012)
↓
Solution
2.50 in.; RQD 53%, TCR 56%; run-by-run columns; three UCS tests per unit.

Solution

(a) 2.50 in. (b) RQD = 53% (fair), TCR = 56%. (c) Run-by-run columns with an RQD chart and photo references. (d) At least three UCS specimens per rock unit.

RQD close to TCR means nearly all recovered core is sound; the concern is the 44% that did not come up, which may be soft seams, solution features or drilling problems. Review the drilling record before interpreting the loss. For dolomite with qu of 5,000 to 20,000 psi, bearing rarely governs; socket geometry and uplift usually do.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
  • IS-02 SPT overburden normalization (sands) (N₁)₆₀Use: Cohesionless soils; normalizes to σ'v0 = 1 atm. Cap of 1.7 recommended by NCEER workshop. Limits: Not applicable to clays. Unreliable at σ'v0 > ~4,200 psf, about 2 tsf (other CN forms preferred at depth).
4.1.14 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental References.

Case Study 6.14.1 — Auger versus core: when crushed rock is logged as soil
Case study · Look (2023) §2.6

Related section: 4.1.2 Drilling Method Selection

During construction a project manager ordered extra probe holes and concluded that a different, softer material had been found. It had not. The probes were drilled with a tungsten-carbide (TC) bit auger, while the design borings had been cored. Low- to medium-strength basalt with natural fractures at roughly 4 in spacing was crushed by the heavy rig, and the cuttings came up as “soil” graded through the No. 8, No. 30 and No. 40 sieves. Side by side with the adjacent core, the probe hole produced a new “soil” stratigraphy that conflicted with the design rock profile.

Look notes two related habits. Highly weathered rock is often described as soil in any case, and the material just above the start of coring is usually logged conservatively as a weaker grade because the SPT or wash sample there is less informative than core. Visual strength classification, point load index and other rock testing should be done on the core.

For railroad work: when probe holes, auger refusals or contractor holes are used to check rock levels for cuts, culvert footings or pile toes, record the drilling method on every log and compare like with like. A change of drilling technique is not a change of material.

Measurement while drilling for piezometric levels
Measurement while drilling for piezometric levels
Moderately weathered basalt: tungsten-carbide (TC) bit cuttings sieved to No. 8, No. 30 and No. 40 look like soil; the core from the adjacent hole is rock.
Figure 6-LK1. Moderately weathered basalt: tungsten-carbide (TC) bit cuttings sieved to No. 8, No. 30 and No. 40 look like soil; the core from the adjacent hole is rock. Source: Look (2023), Figure 2.6-1, p. 69.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §2.6, pp. 68–70. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • RK-10 UCS from point load index σ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).
Case Study 6.14.2 — SPT field values: counting error and three rigs on one site
Case study · Look (2023) §6.12

Related section: 4.1.3 Standard Penetration Test (SPT) — Procedure and Corrections

An SPT N-value is reported as “factual”, but only whole blows can be counted, and the 6 in increments are judged against a chalk mark 0.2–0.39 in. wide in the under-7-second window between blows. That reading error alone is 7%–13% per increment. Digitally measured increments with a 6 in. target averaged 5.8 in. with a standard deviation of 0.63 in. (range 4.3–7.5 in.), a coefficient of variation of 11%–15%. The two test increments partly compensate; the error carried over from the seating drive matters more.

On a large investigation with three rigs, hammer energy and rod length were measured on Rigs 1 and 2. Rig 1 needed a correction factor of about 1.5, so its design strength and modulus rose by 50%. Rig 2 needed almost none. Rig 3 was never measured and was assumed to be 1.0. Across the 1,120 tests, 18% of N-values below 50 changed density class once corrected.

Look’s recommendation is that every rig carry a current energy certificate, as a laboratory carries accreditation, so the cost is shared across projects and firms that measure energy are not undercut by those that do not.

Table 6-LK1. Change in density class after energy correction, 1,120 SPTs at one site (after Look 2023, Table 3.1.19)

Density classOriginal NEnergy-corrected N60% changed
Very loose (< 4)45434%
Loose (< 10)17916211%
Medium dense (< 30)44635425%
Dense (< 50)7717418%
Very dense (≥ 50), excl. rock5064n/a

For railroad work: ask for the hammer energy ratio with every boring subcontract and record the rig on each log. Liquefaction screening, pile capacity and bearing checks on railroad bridges all use corrected N60; an uncorrected value from an unmeasured rig is not a design value.

Energy correction for three rigs at the same site; Rig 3 was never measured and a correction of 1.0 was assumed.
Figure 6-LK2. Energy correction for three rigs at the same site; Rig 3 was never measured and a correction of 1.0 was assumed. Source: Look (2023), Figure 3.1.12-2, p. 195.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §6.12, pp. 194–196. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

4.1.15 Boring Programs for Track Widening and New Track

New sidings, second main tracks and grade raises run for miles along an existing embankment, and the boring program has to sample the existing roadbed, the embankment and the cut slopes as well as the ground beneath. AREMA Chapter 1, Part 1, notes that new construction next to existing track may need only a few widely spaced borings unless problem areas show up, while creeping failures under existing track need exploration deep enough to intercept the failure plane, supplemented by trenches, test pits, inclinometers, piezometers and CPT. A Class I railroad's public projects geotechnical requirements turn this into a pattern, used by the calculator.

4.1.15.1 The boring series

Table 4.1-1. Corridor boring pattern (railroad public projects requirements)
LocationBoringsDepth
Each quarter mile, representing the prevailing cut or fillTop of existing grade (between edge of ballast and shoulder), midslope, ditch line just off the toeTo stable track and embankment subgrade or foundation
Cut sectionsAdd one boring at the top of the cut slope, near the right-of-way lineCut height plus 5 ft below the proposed ditch flowline; bulk samples for classification and modified Proctor
Culverts to be extendedOne at each endFor sub-excavation and stabilization advice to limit differential settlement
Bridges, walls and unique structuresAs the structure requiresPer structure design

The report should also give stripping depth, sub-excavation, benching, compaction, ditch depth and grade, subballast thickness by the AREMA method, and stable fore and back slopes from stability analysis.

4.1.15.2 Worked example: three-mile second main track

Table 4.1-2. 13 series (40% in cut), 4 culvert extensions, 4 structure borings (calculator output)
ResultValue
Boring series13
Total borings56
Total footage1,280 ft
Average depth22.9 ft

Borings on top of grade sit within a few feet of the live track, so each needs flagging and track time; in this example 13 of the 56 borings are of that kind. The logs should record ballast, subballast and fouling thicknesses, which feed Chapters 2.1 and 6.4. A geotechnical engineer should walk the corridor first and move or add borings where the reconnaissance shows soft ground, seepage or slope movement.

Open the corridor boring calculator →
Quarter-mile boring series, top-of-cut borrow borings, culvert-end and structure borings, with counts and footage.

4.1.15.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

4.1.16 Sample Disturbance: Sampler Geometry and Recovery

A strength or consolidation test is only as good as the sample. The Corps of Engineers' Geotechnical Investigations manual (EM 1110-1-1804, Appendix F) summarizes Hvorslev's classic criteria for sampler design. The area ratio, the volume of soil displaced by the cutting shoe relative to the sample, may be the most important single factor. Inside clearance lets the sample enter without wall friction. Outside clearance should be small, or wall friction can cause a bearing failure below the shoe. Sample length should be limited, the tube pushed in one fast, continuous stroke rather than driven, and recovery recorded. The manual also lists the usual causes of poor recovery: pressure above the sample from poor venting, suction below the tube as it is pulled, and failure to shear the sample off at the shoe.

4.1.16.1 Criteria

Equation 4.1-1. Hvorslev's sampler ratios (EM 1110-1-1804, Eqs. 2-1 to 2-3)

Ca = (Dw² − De²)/De²;   Ci = (Ds − De)/De;   Co = (Dw − Dt)/Dt
Table 4.1-3. Recommended limits (Hvorslev, as summarized in EM 1110-1-1804)
ItemRecommendation
Area ratio CaPreferably below 10 to 15%. ISSMFE (1966) accepted 5 to 20% with the edge taper reduced from 15° to 9°
Inside clearance Ci0 to 1% for very short samples; 0.5 to 3% for medium length; 0.75 to 1.5% for L/D of 6 to 8
Outside clearance CoUnder 2 to 3% in cohesive soil; zero in cohesionless soil
Length to diameter5 to 10 in cohesionless soil; 10 to 20 in cohesive soil
AdvancePush with a fast, continuous, uniform motion; driving causes the greatest disturbance
RecoveryVent the tube, rotate one or two turns to shear the sample, or use a piston sampler

4.1.16.2 Worked example

A standard 3 in. thin-wall tube of 16 gauge steel has an area ratio of 9.3% and a 2 in. tube of 18 gauge 10.6%. Both are within Hvorslev's preferred range. The standard split spoon used for the SPT has an area ratio of 111.6%, so its samples are disturbed and suitable only for index tests. A 24 in. push that recovers 21 in. gives 88% recovery and a warning to find out why. The nominal tubes show zero inside clearance; tubes with a rolled or swaged cutting edge give the 0.75 to 1.5% Hvorslev suggests, so measure the actual shoe.

On the boring log, record the sampler, how it was advanced, the length pushed and the length recovered for every sample. When laboratory strengths look low or consolidation curves show no clear break, check sample quality before concluding that the clay is weak.

Open the sampler disturbance calculator →
Hvorslev's area ratio, inside and outside clearance, length-to-diameter ratio and recovery, compared with the recommended limits, with common samplers for comparison.

4.1.16.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • U.S. Army Corps of Engineers, Geotechnical Investigations, EM 1110-1-1804 (2001): Appendix F, sample quality and the parameters that affect sample disturbanceOfficial page ↗
  • N. Simons, B. Menzies and M. Matthews, A Short Course in Geotechnical Site Investigation: sampling methods and sample qualityFind source ↗
  • B.G. Look, Handbook of Geotechnical Investigation and Design Tables (2007): sampling and testing in site investigationsFind source ↗
4.1.17 Rock Core Logging: Recovery, RQD and First Estimates of Rock Properties

Where borings for a bridge, wall or rock cut reach rock, two numbers from each core run carry most of the information: the recovery ratio, and the rock quality designation (RQD). RQD is the total length of pieces 4 in. or longer divided by the length cored. Das's Principles of Geotechnical Engineering defines both and gives Deere's descriptions from Excellent to Very poor. Look's Handbook of Geotechnical Investigation and Design Tables carries RQD into first estimates of rock mass strength and allowable bearing pressure, and into a check from joint counts on exposures. The Corps of Engineers' EM 1110-1-1804 asks for RQD on every run, with core loss shown on the log at its most likely depth. It points out that the weak, fractured zones where recovery is poorest are usually the critical ones for foundations and stability, and that larger core barrels improve recovery in them.

4.1.17.1 Definitions and correlations

Table 4.1-4. Rock quality from RQD, with first-approximation properties
RQD (%)Quality (Deere)Allowable bearing (Peck, Hansen and Thorburn), MPa (ksf)Rock mass (Kulhawy and Goodman)
90–100Excellent20–30 (418–627)Design compressive strength 0.33–0.8qu; c = 0.1qu; φ = 30–60° (RQD over 70)
75–90Good12–20 (251–418)
50–75Fair6–12 (125–251)Design compressive strength 0.33qu; c = 0.1qu; φ = 30° (RQD up to 70)
25–50Poor3–6 (63–125)
0–25Very poor1–3 (21–63)

Bearing values are limited to the uniaxial strength of the rock or the allowable stress of the concrete; Look notes the RQD method is common but not suitable for detailed design. Sources: Das Table 18.7; Look Tables 9.13 and 22.1.

Table 4.1-5. Core barrel sizes (Das Table 18.6)
DesignationBit outside diameter, in. (mm)Core diameter, in. (mm)
EX1-7/16 (36.5)7/8 (22.2)
AX1-7/8 (47.6)1-1/8 (28.6)
BX2-5/16 (58.7)1-5/8 (41.3)
NX2-15/16 (74.6)2-1/8 (54.0)

4.1.17.2 Worked example

Three 5 ft runs in a bedded limestone recover 57.5, 57 and 37.5 in. of core. The pieces 4 in. or longer total 47, 57 and 23.5 in., so the runs have RQDs of 78%, 95% and 39%. Overall the RQD is 71% and the recovery 84%, but the third run (39%) is a poor zone that a single average would hide. The first-approximation allowable bearing for the average is 125 to 251 ksf. A footing or pile tip should be designed on the weakest zone it will bear on, and that zone should be checked with laboratory strength tests.

Photograph every core box wet, with a scale and run markers, before logging. Note any core lost and where. Lost core is usually the weakest rock, and recovery below about half signals highly fractured rock (Das).

Open the core RQD calculator →
Recovery and RQD run by run and overall, Deere's quality description, first-approximation rock mass properties and allowable bearing pressure, and an RQD check from a volumetric joint count.

4.1.17.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • B.M. Das, Principles of Geotechnical Engineering, 7th edition: Section 18.7, rock coring, recovery ratio, RQD (Eqs. 18.34 and 18.35, Tables 18.6 and 18.7)Find source ↗
  • B.G. Look, Handbook of Geotechnical Investigation and Design Tables (2007): Tables 9.13, 18.11 and 22.1, rock properties and bearing pressure from RQD and joint countFind source ↗
  • U.S. Army Corps of Engineers, Geotechnical Investigations, EM 1110-1-1804 (2001): rock coring, logging of core loss and RQD per runOfficial page ↗
Supplemental reference · Rajapakse (2016), Ch. 32

Joint Orientation From Oriented Core: Dip, Strike, Dip Direction and Poles

RQD says how broken the rock is, but not which way the breaks run. For a rock cut, tunnel portal or rock-socketed foundation, joint orientation decides whether blocks can slide or topple out of the face (kinematic analysis, Chapter 2.7 and Chapter 6.3). Joint orientation can only be measured from core if the core is oriented.

Oriented coring. A knife in the core barrel cuts a continuous scribe line along the core. Before coring, the driller sets the knife on a known bearing, usually north, with a compass. Proprietary orientation tools do the same with a reference mark. Because the core does not rotate in the barrel, the scribe line stays a fixed reference. For each joint, the logger draws the horizontal line across the joint surface and measures the clockwise angle from the reference line to it: that is the strike. The dip is the angle between the joint surface and the horizontal, measured down the steepest line.

Notation. With the right-hand rule, place the right hand palm down on the joint with the fingers pointing down-dip; the thumb gives the strike direction, so the dip direction is strike + 90°. The same joint can be written three ways, and they are easily confused:

  • Strike/dip (right-hand rule): 070/40.
  • Dip/dip direction: 40/160, the form most rock-slope software uses.
  • Dip/strike, as Rajapakse writes it: 40/070. The dip is given in two digits and the strike in three.

State the convention on every log and in every table of joint data.

Poles. Each joint plane can be represented by its pole, the line normal to the plane, plotted on the lower hemisphere of a stereonet. The pole trends opposite the dip direction (dip direction ± 180°) and plunges at 90° minus the dip. Clusters of poles define the joint sets used in kinematic analysis.

Apparent dip. On a section that is not parallel to the dip direction, such as a cut face or a cross section drawn square to the track, a joint appears flatter than its true dip:

tan α = tan δ × cos β

where α = apparent dip, δ = true dip and β = angle between the section and the dip direction.

For railroad work: Specify oriented core in borings for new or widened rock cuts, portals and high rock-socketed foundations, where surface mapping cannot reach the rock. Set acoustic or optical televiewer logging as an alternative in holes that stay open. Have the driller record the reference bearing and the borehole inclination for every run. Core from an inclined hole must be rotated back to true orientation before plotting.

Source: Rajapakse, R. (2016). Geotechnical Engineering Calculations and Rules of Thumb, 2nd ed. Oxford: Butterworth-Heinemann, Ch. 32 (dip angle and strike; oriented rock coring; concept of the pole). Summarized and paraphrased; the alternative notations, apparent-dip relation and recommendations for railroad work are standard practice added by the authors of this manual.

Example 4.1-5: Joint Orientation From Oriented Core for a Rock Cut

A Class I railroad located in Pennsylvania plans to widen a sandstone cut on the north side of its main line. The new face will dip 70° toward 170°. An oriented NX core from a vertical boring behind the face shows a persistent joint set. The logger recorded it as 40/070 in dip/strike notation, using the right-hand rule. Laboratory tilt tests give a joint friction angle of 30°. The engineer must convert the joint to dip direction and pole, find its apparent dip on a cross section square to the track, and make a first check of whether planar sliding out of the new face is possible.

track face 70° joint daylights in face(true dip 40°) apparent dip = ? oriented core Section looking east; section bearing 170° GivenJoint 40/070 (dip/strike, RHR)Face dips 70° toward 170°Joint friction angle 30°Section square to track: 170° RequiredDip direction; strike/dip formPole trend and plungeApparent dip on the sectionPlanar sliding possible? Black = given; red = required
Given and required for Example 4.1-5.

Given

VariableValueDescription
Joint40/070Dip 40°, strike 070° (right-hand rule), from oriented core in a vertical hole
Face70° toward 170°Planned cut face
φj30°Joint friction angle (tilt test)
SectionBearing 170°Cross section square to the track

Required

  • (a) Dip direction, and the joint in strike/dip and dip/dip-direction forms
  • (b) Pole trend and plunge
  • (c) Apparent dip on the cross section
  • (d) Whether planar sliding out of the face is kinematically possible

Equations

  1. Eq. 1: Dip direction = strike + 90° — right-hand rule
  2. Eq. 2: Pole trend = dip direction ± 180°; plunge = 90° − dip
  3. Eq. 3: tan α = tan δ cos β
  4. Eq. 4: Planar sliding needs dip direction within about 20° of the face dip direction, and φj < δ < face dip.

Steps

Step 1 · (a) Dip direction (Eq. 1)
070 + 90
160°: strike/dip 070/40; dip/dip direction 40/160
↓
Step 2 · (b) Pole (Eq. 2)
160 + 180 = 340; 90 − 40 = 50
Pole trends 340°, plunges 50°
↓
Step 3 · (c) Apparent dip (Eq. 3)
β = 170 − 160 = 10°; tan α = tan 40° × cos 10° = 0.839 × 0.985 = 0.826
α = 39.6°
Spot check: with the section only 10° off the dip direction, the apparent dip should be just under the true 40°.
↓
Step 4 · (d) Planar check (Eq. 4)
|170 − 160| = 10° ≤ 20°; 30° < 40° < 70°
All three conditions met: planar sliding is possible
↓
Solution
40/160; pole 340/50; apparent dip 39.6°; joint daylights and can slide.

Solution

(a) Dip direction 160°; the joint is 070/40 in strike/dip and 40/160 in dip/dip-direction form. (b) The pole trends 340° and plunges 50°. (c) On the cross section square to the track it dips 39.6°. (d) It strikes nearly parallel to the face, daylights in it, and dips more steeply than its friction angle, so planar sliding toward the track is kinematically possible.

A single joint is only a first check. Plot all the oriented-core and face-mapping data on a stereonet, define the sets, and run the full kinematic and limit-equilibrium analysis (Chapters 2.7 and 6.3), including water pressure in the joints and train vibration. Options for this set are a flatter face (at or below about 40°, which needs much more excavation), rock bolts or dowels across the set, or a rockfall catchment sized for the blocks it can release. Record on the boring logs that the joint data are in dip/strike notation. A designer who reads 40/070 as dip/dip direction would put the joint dipping toward 070°, about 100° away from the face, and conclude wrongly that it cannot slide out.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

Supplemental references

  • U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I, Ch. 5 (Discontinuities)Find source ↗Library entry
  • Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017))Find source ↗Library entry
  • Hunt, R. E. (2005). Geotechnical Investigation Methods: A Field Guide for Geotechnical Engineers. CRC PressFind source ↗
  • U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804Official page ↗
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §2.6, §6.12Find source ↗Library entry

File locations for these documents are listed under Supplemental References.

Project management sources

  • Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International PublishingFind source ↗
  • McKinnon, R. C. (2012). Safety Management: Near Miss Identification, Recognition, and Investigation. Boca Raton, FL: CRC Press (Taylor & Francis)Find source ↗
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. The Case Studies section summarizes case studies from item S12 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I, Ch. 5 (Discontinuities)Find source ↗Library entry
  2. Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017))Find source ↗Library entry
  3. Hunt, R. E. (2005). Geotechnical Investigation Methods: A Field Guide for Geotechnical Engineers. CRC PressFind source ↗
  4. U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804Find source ↗
  5. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  6. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  7. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §2.6, §6.12Find source ↗Library entry
  8. Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing. Used on this page for project-management materialFind source ↗
  9. McKinnon, R. C. (2012). Safety Management: Near Miss Identification, Recognition, and Investigation. Boca Raton, FL: CRC Press (Taylor & Francis). Used on this page for project-management materialFind source ↗