Every proposed solution is rated for how much it will reduce the risk, in three stages: the solution as conceived (this section), the design and construction that turn it into works (Section 3.8.38), and the post-stabilization implementation that proves it performs (Section 3.8.39). The risk reduction is the difference between the current risk and the rating at each stage. Rating all three keeps a good idea from being credited as if it were already built and proven. Figure 3.8-47 follows the worked example of Section 3.8.41 through the stages.
A solution can reduce risk in only three ways, and the solution rating credits each one through the input it changes:
| Way of reducing risk | Examples | Input changed | Rationale | Typical rescoring (starting values; confirm for the site) |
|---|---|---|---|---|
| Remove or reduce the trigger | Upsize or clean a culvert; divert water; add ditches and subdrains; control beavers; lower groundwater | T, and the hydrology and drainage attributes L4 and L5 | If the trigger reaches the site less often, failure cannot be more frequent than the new trigger rating (Equation 3.8-2). | Culvert sized for the 100-year event: T7 → 1, T8 → 2, L5.1 and L5.2 → 1. Ditches regraded and cleaned: T8 → 2, L5.3 → 1. Horizontal or lateral drains: T9 → 2, L5.4 → 1; because they drain the fill internally they also earn D = 1. |
| Increase resistance | Berms; shear keys; soldier pile walls; ground improvement; riprap and scour countermeasures; rock bolting | The situational attributes (L1–L3) through the design factor of safety (Table 3.8-81) | Raising the margin against failure means a larger trigger is needed, which lowers the frequency of failure. | Riprap or a scour countermeasure for the design flood: T4 → 1, L4.3 → 2. Soldier pile or other retaining wall: L3.2 → 1. Free-draining rock buttress or regrade: L3.2 → 2. Subgrade undercut with a drained granular section: L1.1, L1.4 and L5.4 → 1. Each earns D = 1 (Section 3.8.37.2). |
| Reduce exposure or consequence | Realign the track away from the slope; protective structures; detection linked to operating rules (slide fences, monitoring with alarms and slow orders) | S | The ground may still fail, but a failure reaches less or is caught before a train meets it. | T, L and D unchanged. Detection linked to an operating response: S one level lower while the response is in force (SOL2 = 4). Realignment or a protective structure: S rescored for what a failure would now reach, with the reason written. |
The typical rescoring gives starting values, and it is what the Risk Assessment App suggests when an alternative is selected. Each element takes the lower of its current score and the value shown. Replace the values with the site’s own scores where the design or the conditions differ, rescore only the elements the solution actually changes, and never rescore L6.
For each solution, rate the site as it would be once the solution works as intended. Rescore only the inputs the solution changes (Table 3.8-79); every other input keeps its current value. Work through the steps in order:
| Rule | Rationale |
|---|---|
| Investigation level caps the credit. Desk study only: the solution may lower the rating by at most one level. Field reconnaissance, or limited borings without analysis: by at most two levels. Subsurface investigation and analysis: full credit (SOL3, Table 3.8-49). | Without a confirmed mechanism and ground model, the solution may treat the wrong problem; the cap stops unproven solutions from outranking proven ones. |
| Monitoring and operating rules do not lower F. Detection linked to an operating response (alarms, inspections, slow orders) may lower S by one level, and only while the response is in force. | Monitoring does not change how often the ground fails; it changes whether a train meets the failure. |
| Maintenance-dependent solutions (culverts, ditches, subdrains, beaver control) get full credit only with a maintenance plan (Section 3.8.39). | Drainage that is not maintained silts up and returns the site to its trigger. |
| On a site with recurring or active defects (D = 4 or 5), a solution that removes only the trigger keeps the current D in its solution rating. The credit is earned at the post-stabilization stage once movement has stopped. | Removing the trigger does not restore the strength the fill has already lost. Until the track shows the movement has stopped, the defects are still the best evidence of frequency. |
| A solution that leaves the site at High or above is interim, and is labeled as such. | It manages the risk until a permanent solution is built; it does not resolve it (Section 3.8.22.7). |
| S is lowered only where the solution changes what a failure would reach, with the reason written. | Severity belongs to the site and its traffic; most stabilization works lower F, not S. |