3.8.33 Small Data Sets: Confidence Limits, Sample Size and Goodness of Fit

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.33 Small Data Sets: Confidence Limits, Sample Size and Goodness of Fit

Risk assessments are built on small data sets: a handful of strength tests, a few years of monitoring, a failure record with few or no failures in it. Small samples give means and rates that are themselves uncertain. This section gives the tools to state that uncertainty, to decide how many more tests are worth doing, to interpret a record with no events, and to check whether an assumed distribution fits the data.

3.8.33.1 Confidence limits on a mean

Equation 3.8-11. Confidence limits on a mean from n tests (Student’s t)

two-sided: x̄ ± tα/2, n−1 s/√n;   one-sided lower limit: x̄ − tα, n−1 s/√n

x̄, s = sample mean and standard deviation (n − 1 in the denominator of s); t from Table 3.8-64. A one-sided 95% lower limit on the mean is the “cautious estimate of the mean” used in limit state codes for properties that govern over a large volume of ground. For a property that governs locally, use a lower fractile of the individual values instead, such as x̄ − s or x̄ − 1.645 s.

Table 3.8-64. Student’s t multipliers
Degrees of freedom n − 1One-sided 90% (t0.10)One-sided 95% (t0.05), two-sided 90%Two-sided 95% (t0.025)
13.0786.31412.706
21.8862.9204.303
31.6382.3533.182
41.5332.1322.776
51.4762.0152.571
61.4401.9432.447
71.4151.8952.365
81.3971.8602.306
91.3831.8332.262
101.3721.8122.228
151.3411.7532.131
201.3251.7252.086
301.3101.6972.042
∞ (normal z)1.2821.6451.960

With two or three tests t is so large that the lower limit is often meaningless, which is the statistical reason for testing each layer that matters at least five or six times (Chapter 5.2).

3.8.33.2 How many tests

Equation 3.8-12. Number of tests for a required precision of the mean

n ≥ (tα/2, n−1 s / E)²   (first estimate with z: n ≈ (1.645 s/E)² for 90%)

E = acceptable half-width of the confidence interval, in the units of the property; s from the tests so far or from a published COV (Table 3.9-9) times the expected mean. Because t depends on n, solve by trial. Halving E multiplies the number of tests by about four.

3.8.33.3 A record with no failures

Equation 3.8-13. Upper confidence bound on an event rate when none has been observed

pU = 1 − α1/m ≈ −ln(α)/m;   95%: pU ≈ 3/m;   90%: pU ≈ 2.3/m

m = number of independent trials, such as site-years or structure-years of record. The approximation is the “rule of three.” It treats every site-year as alike; a group that mixes high and low hazard sites can hide a few bad sites behind many good ones.

No failures in a record does not mean a probability of zero. A site with 20 years of quiet history can still have a 1 in 7 annual chance of failure at 95% confidence (3/20), which is a frequency index of F = 3 (Table 3.8-14) on the record alone. Field evidence is what moves it lower.

3.8.33.4 Checking the distribution: goodness of fit

Before rates or extreme values are extrapolated, check that the assumed distribution fits the record. The chi-squared test groups the data into k classes, compares the observed counts Oi with the counts Ei expected from the fitted distribution, and computes χ² = Σ(Oi − Ei)²/Ei. The fit is rejected at significance α if χ² exceeds the tabulated value for k − 1 − r degrees of freedom, where r is the number of parameters estimated from the data; keep Ei at 5 or more by merging classes. The Kolmogorov–Smirnov test compares the cumulative curves directly and works better for the small samples common in geotechnical work. A quick graphical check is to plot the data on probability paper (normal, lognormal or Gumbel): a straight line supports the model, and curvature at the tail warns against extrapolating far beyond the record. For Poisson counts, a variance much larger than the mean (for example, counts by year of 0, 0, 5, 0, 1, 0, 6) indicates clustering by storm, and the count should be by storm event.

3.8.33.5 Trends and regression

Monitoring data in a risk assessment are usually fitted with a straight line: settlement against log time, inclinometer displacement against date, crack width against season. Least squares gives the slope and intercept; the standard error of the slope gives its confidence interval (t with n − 2 degrees of freedom), and a slope whose interval includes zero has not been shown to be a trend. Extrapolating a fitted line to a future date carries a prediction interval that widens with distance from the data, so a forecast of when movement will reach an action level should be stated with its range (Chapter 4.5, the observational method).

3.8.33.6 Worked example

Example 3.8-10: Six Strength Tests and No Recorded Failures: How Much Do They Tell Us?

Problem Statement

A Class I railroad located in Mississippi is rating a 22-ft embankment on a soft clay foundation for a speed increase. Six unconsolidated-undrained (UU) triaxial tests on the foundation clay are available (Figure 3.8-45). The railroad’s records show no failures in 25 years on 48 embankments of similar height on the same formation. The engineer must state the design strength with its uncertainty, decide whether more testing is needed, and say what the clean failure record actually proves.

8009001,0001,1001,2001,300mean 1,10395% lower limit = ?mean − s = ?Undrained shear strength su (psf)Records: 48 similar fills, 25 years, no failuresGiven6 UU tests, s​u (psf):1,150; 980; 1,320;870; 1,060; 1,240Target: mean within ±10% at 90% confidence48 fills × 25 yr, 0 failuresRequired(a) x̄, s, COV(b) 95% lower limit on mean(c) Tests for ±10%(d) Upper bound on the annual failure rate
Figure 3.8-45. Example 3.8-10: six undrained strength results for an embankment foundation clay, and the failure record for similar fills.

Given

VariableValueDescription
su1,150; 980; 1,320; 870; 1,060; 1,240 psfUU test results, n = 6
E±10% of the meanRequired precision of the mean
Confidence90% two-sided (precision); 95% one-sided (lower limit)Confidence levels chosen for the rating
m48 fills × 25 years = 1,200 fill-yearsExposure in the failure record, with zero failures

Required

  • (a) Sample mean, standard deviation and COV, compared with published values
  • (b) One-sided 95% lower confidence limit on the mean, and the mean minus one standard deviation
  • (c) Number of tests needed to know the mean within ±10% at 90% confidence
  • (d) The 95% upper bound on the annual failure rate from the clean record

Equations

  1. x̄ = Σx/n; s = √[Σ(x − x̄)²/(n − 1)]; COV = s/x̄
  2. Eq. 3.8-11: x̄ − tα, n−1 s/√n (one-sided lower limit)
  3. Eq. 3.8-12: n ≥ (tα/2, n−1 s / E)² (solve by trial)
  4. Eq. 3.8-13: pU = 1 − α1/m ≈ 3/m for α = 0.05

Steps

Step 1 · (a) Sample statistics
Σx = 6,620; x̄ = 6,620/6; Σ(x − x̄)² = 139,333; s = √(139,333/5)
x̄ = 1,103 psf; s = 167 psf; COV = 15%
Spot check: 15% lies within the 13 to 40% range for undrained strength in Table 3.9-9 ✓.
↓
Step 2 · (b) Lower limit on the mean (Eq. 3.8-11)
t0.05, 5 = 2.015 (Table 3.8-64); 1,103 − 2.015 × 167/√6 = 1,103 − 137
95% lower limit = 966 psf; x̄ − s = 936 psf
↓
Step 3 · (c) Tests for ±10% (Eq. 3.8-12)
E = 110 psf. n = 8: t = 1.895, (1.895 × 167/110)² = 8.2 > 8, no. n = 9: t = 1.860, (1.860 × 1.513)² = 7.9 ≤ 9, yes
n = 9: three more tests
Spot check: with n = 9, half-width = 1.860 × 167/3 = 104 psf ≤ 110 psf ✓.
↓
Step 4 · (d) Zero-failure bound (Eq. 3.8-13)
m = 1,200 fill-years; 1 − 0.051/1,200
pU = 0.0025 a year, about 1 in 400; 3/1,200 gives the same
↓
Solution
Mean 1,103 psf (COV 15%); use 966 psf as the 95% lower limit on the mean; three more tests would pin the mean within ±10%. The clean record limits the annual failure rate of similar fills to about 1 in 400 or less, at 95% confidence.

Solution

Mean 1,103 psf (COV 15%); use 966 psf as the 95% lower limit on the mean; three more tests would pin the mean within ±10%. The clean record limits the annual failure rate of similar fills to about 1 in 400 or less, at 95% confidence.

Six tests give a mean of 1,103 psf, but with six results the true mean could reasonably be as low as 966 psf, and that is the value to carry into the stability check for the speed increase. It is close to the mean minus one standard deviation (936 psf) recommended by GEC 5 (Section 3.9.15), but the two measure different things: the confidence limit describes uncertainty in the average strength along the failure surface, which governs a large slide, while the mean minus one standard deviation covers the scatter of individual values, which matters for a short, local failure. Three more tests would narrow the uncertainty enough to justify a design strength nearer the mean; at a few hundred dollars a test against a berm or a slower speed, that is usually worth doing.

The clean record is evidence, but weaker evidence than it looks. With 1,200 fill-years and no failures, the true annual failure rate could still be as high as about 1 in 400 at 95% confidence (the “rule of three”), which is frequency index F = 1 (less than 1 in 100 years, Table 3.8-14) for the group. It does not prove that this embankment, under faster and heavier traffic, will behave the same; it shows that similar fills under past loading have rarely failed. Use it as the prior in a Bayesian update (Section 3.8.31) and let the site-specific strength and stability analysis carry the rating.

Open the small data set confidence and number of tests calculator →

For railroad work: State design parameters with their number of tests and confidence limits, not as single values, and report any failure rate with its record length. When a client cites a clean history as the reason not to act, convert it to an upper bound with Eq. 3.8-13; the exposure of the record, not the absence of failures, is what decides how much it proves. Combine these results with the Taylor series probability of failure in Section 3.9.15.

Sources: Soong, T. T. (2004). Fundamentals of Probability and Statistics for Engineers. Chichester: John Wiley & Sons Find source ↗, Ch. 9 (sample statistics, interval estimation and the t-distribution), Ch. 10 (chi-squared and Kolmogorov–Smirnov goodness-of-fit tests), Ch. 11 (linear regression and confidence intervals for regression coefficients); “Appendix: Mathematics, Symbols, and Physical Constants.” In W. F. Chen and J. Y. R. Liew (eds.), The Civil Engineering Handbook, 2nd ed. Boca Raton, FL: CRC Press (2003) Find source ↗ (tables of the t, χ² and normal distributions).