The frequency index asks how often a site will fail; design asks how often is acceptable. Wyllie and Mah point out that probabilistic design needs accepted ranges of probability of failure, just as deterministic design has accepted factors of safety, and they reproduce Whitman's chart of annual probability of failure against lives lost for a range of engineered works. Look adds that a probability is easier for owners and other disciplines to understand than a factor of safety. He also notes that a higher factor of safety does not by itself mean a lower probability of failure (his example compares 1.3 and 1.4), and that existing and new slopes must be judged by different criteria. Hearn quotes the Norwegian national guidelines, which set a maximum annual probability of failure for each consequence class, and cautions that the approach needs good records of the triggering events. This section brings those benchmarks together and connects them to the factor of safety through the reliability method of Section 3.9.15.
Equation 3.8-14. From factor of safety to annual and lifetime probability
pannual ≈ Pf / Tc; Plife = 1 − (1 − pannual)n
Pf is the probability that F is below 1.0 under the condition analyzed (for example, the 10-year storm water level), with the most likely factor of safety F and its coefficient of variation VF from Section 3.9.15. If failure is credible only when that condition occurs, dividing by its return period Tc gives a first estimate of the annual probability. Conditions more severe than the one analyzed add to it, so the estimate is a lower bound unless they are analyzed too.
| Source | Situation | Probability of failure |
|---|---|---|
| Norwegian guidelines (Nilsen 2000, in Hearn Table C3.5), annual | Consequence class 1 minor / 2 medium / 3 major | 10−2 / 10−3 / less than 10−4 |
| Skipp (1992), in Look Table 10.14, annual, rock slopes | Catastrophic / major / moderate / minor failure | 1 × 10−4 / 5 × 10−4 / 1 × 10−3 / 5 × 10−3 (minor: unmonitored permanent urban slopes with free access) |
| Santamarina and others (1992), in Look Table 10.15 | Existing large highway cut, no potential life loss, minor costs | 1 to 2 × 10−2 (under 10−2 for a new cut) |
| Acceptable in most cases, no potential life loss / acceptable for all slopes, potential life loss / unnecessarily low | 10−3 / 10−4 / under 10−5 | |
| Whitman (1984), in Wyllie and Mah Figure 1.11, annual | Closely managed mine slopes, little risk to life / dams with several hundred lives at risk | 10−1 to 10−2 / 10−4 to 10−5 |
| AGS (2000), in Look Table 10.13, annual risk of loss of life | Existing slope: person most at risk / average / new slope: person most at risk / average | 10−4 / 10−5 / 10−5 / 10−6 |
The AGS values are tolerable risks to an individual's life, not probabilities of slope failure; the individual risk is the failure probability multiplied by the chance that the person is present and is killed.
| Economic risk | Risk to life negligible | Low | High |
|---|---|---|---|
| New slopes: negligible | over 1.1 | 1.2 | 1.4 |
| New slopes: low | 1.2 | 1.3 | 1.5 |
| New slopes: high | 1.4 | 1.5 | 1.6 |
| Existing slopes (any economic risk) | over 1.1 | 1.2 | 1.3 |
A new main-line fill slope is analyzed for the 10-year storm water level and gives a most likely factor of safety of 1.3. The analysis is turned into an annual probability of failure so that it can be compared with consequence-based benchmarks, not only with a target factor of safety.
| Variable | Value | Description |
|---|---|---|
| F | 1.3 | Most likely factor of safety for the 10-year water level |
| VF | 15% | Coefficient of variation of F |
| Tc | 10 years | Return period of the condition analyzed |
| N | 50 years | Service life |
| Limits | 10−3/yr; F = 1.5 | Norwegian medium-consequence limit; GEO factor of safety for high economic, low life risk |
At F = 1.3 and a COV of 15%, the annual probability of failure is about 4.6 × 10−3 (1 in 217 years), or 20.6% over 50 years. That fails the Norwegian medium-consequence limit of 10−3 and the GEO factor of 1.5. Raising F to 1.5 at the same uncertainty gives about 4.1 × 10−4; the 10−3 limit is reached at F of about 1.43, so here the GEO value is the stricter of the two.
Open the acceptable probability of failure calculator →
Annual probability of failure, entered or estimated from a factor of safety, its COV and the return period of the condition analyzed, with the lifetime probability, the F band, the Norwegian and Skipp benchmarks and the GEO factor of safety for the consequence.
The table shows how strongly the annual probability depends on the uncertainty in F as well as on F itself. At a coefficient of variation of 10%, a factor of safety of 1.3 already gives an annual probability below 10−3. At 20%, even a factor of 1.6 gives slightly more than 10−3. The investigation and testing that narrow the uncertainty (Section 3.9.15) are worth as much as a higher factor of safety, and Look's warning about comparing factors of safety alone follows directly.
| F (most likely) | COV of F = 10% | 15% | 20% |
|---|---|---|---|
| 1.3 | 4.9 × 10−4 | 4.6 × 10−3 | 1.1 × 10−2 |
| 1.4 | 4.4 × 10−5 | 1.5 × 10−3 | 5.5 × 10−3 |
| 1.5 | 3.0 × 10−6 | 4.1 × 10−4 | 2.6 × 10−3 |
| 1.6 | 1.6 × 10−7 | 1.0 × 10−4 | 1.1 × 10−3 |
| 1.8 | 2.6 × 10−10 | 5.5 × 10−6 | 2.1 × 10−4 |
| 2.0 | 2.6 × 10−13 | 2.4 × 10−7 | 3.4 × 10−5 |
The figure plots the same results as the logarithm of the annual probability. The dashed black line is the Norwegian limit for a medium consequence (10−3); the dashed grey line is the limit for a major consequence (10−4).
Paraphrased from these documents in the reference library.