3.8.1 Mechanism, Condition and Trigger

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.1 Mechanism, Condition and Trigger

Ground failures rarely have a single cause. It is useful to separate three groups of factors:

FactorDefinitionRailroad ExamplesCan the Railroad Change It?
Predisposing conditionsInherent site characteristics that make failure possibleSoft or sensitive clay, steep slope, fouled ballast over plastic clay, soluble bedrock, loose saturated sandOnly by engineering works (improvement, regrading, replacement)
Preparatory (progressive) factorsProcesses that reduce the margin of safety over timeBallast fouling, subgrade softening, toe erosion, weathering, rising tonnage, culvert corrosion, creepYes — through maintenance, drainage and inspection
TriggersThe event that tips a marginal site into failureIntense or prolonged rainfall, snowmelt, flood, rapid drawdown, earthquake, toe excavation, blocked culvertRarely — but exposure can be managed (slow orders, patrols, warning systems)
Factor of Safety vs. Probability of Failure
Factor of Safety vs. Probability of Failure

The factor of safety concept from Chapter 1.1 ties these together. Predisposing conditions set the starting factor of safety, preparatory factors erode it, and the trigger is whatever finally pushes it below 1.0. A site with a large margin survives the same storm that fails a marginal site next to it. This is why a risk program targets sites whose margin is being eroded, not just sites that have already failed.

Project management · Bissonette (2016)

Cause–Risk–Effect Statements (Risk Metalanguage)

Bissonette separates three things that risk registers often blur. A cause is a fact or existing condition. A risk is an uncertain event that may or may not happen. An effect is the possible impact on one or more project objectives (schedule, cost, scope or quality). To keep them apart he uses a fixed sentence form, or risk metalanguage:

As a result of <CAUSE>, <RISK> may occur, which will lead to <EFFECT>.

The short version for a register title is “<RISK> due to <CAUSE>.” One of his examples reads: “As a result of more than expected test failures, more design/build/test cycles may occur, which will lead to schedule delays and added project costs.” Its register title is “More design/build/test cycles due to more than expected test failures.” Writing every risk this way shows which part can be measured or controlled, whether the cause or the event. It also indicates which objective the impact rating should refer to. The same form keeps a known condition, which is a fact to design for, from being logged as though it were uncertain.

For railroad work: The metalanguage lines up with this chapter’s condition–mechanism–trigger framework. The cause is the condition plus the trigger, the risk is the mechanism being activated, and the effect is the consequence to track or to the project. For example: “As a result of a high-plasticity clay subgrade with a clogged ditch line (condition) and sustained wet-season rainfall (trigger), progressive shear and heave of the subgrade may occur (mechanism), which will lead to repeated surfacing, a slow order and possible mud-pumping derailment risk (effect).” The register title becomes “Subgrade shear failure due to saturated CH subgrade and blocked drainage.” Writing hazard and project risks in this form makes plain which field observation would confirm the cause and which treatment targets the trigger. It also makes the risk register consistent with the diagnostic tables in this chapter.

How Rainfall Becomes Floods
How Rainfall Becomes Floods

Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 2.1, “Causes Versus Risks” (unpaginated e-book; PDF pp. 38–40). Summarized and paraphrased. Full reference under Supplemental References.