Geotechnical Services Manual for Railroad Clients
A Consultant's Reference for Delivering Geotechnical Engineering Services Across North American Railroad Capital Programs
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Interface, strength and unit weight values for earth pressure and wall design (soldier pile and lagging walls). English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Friction coefficient, mass concrete on soil/rock | Clean sound rock | 0.7 | – | CB T11.1, p.208 | ||||
| Friction coefficient, mass concrete on soil/rock | Clean gravel, gravel–sand mixtures, coarse sand | 0.55 | 0.575 | 0.6 | – | CB T11.1, p.208 | ||
| Friction coefficient, mass concrete on soil/rock | Clean fine to medium sand, silty medium to coarse sand, silty or clayey gravel | 0.45 | 0.5 | 0.55 | – | CB T11.1, p.208 | ||
| Friction coefficient, mass concrete on soil/rock | Clean fine sand, silty or clayey fine to medium sand | 0.35 | 0.4 | 0.45 | – | CB T11.1, p.208 | ||
| Friction coefficient, mass concrete on soil/rock | Fine sandy silt, non-plastic silt | 0.3 | 0.325 | 0.35 | – | CB T11.1, p.208 | ||
| Friction coefficient, mass concrete on soil/rock | Very stiff and hard residual or overconsolidated clay | 0.4 | 0.45 | 0.5 | – | CB T11.1, p.208 | ||
| Friction coefficient, mass concrete on soil/rock | Stiff clay and silty clay | 0.3 | 0.325 | 0.35 | – | CB T11.1, p.208 | ||
| Friction coefficient, steel sheet piles | Clean gravel, gravel–sand mixtures, well-graded rock fill | 0.4 | – | CB T11.1, p.208 | ||||
| Friction coefficient, steel sheet piles | Clean sand, silty sand–gravel mixtures, single-size hard rock fill | 0.3 | – | CB T11.1, p.208 | ||||
| Friction coefficient, steel sheet piles | Silty sand, gravel or sand mixed with silt or clay | 0.25 | – | CB T11.1, p.208 | ||||
| Friction coefficient, steel sheet piles | Fine sandy silt, non-plastic silt | 0.2 | – | CB T11.1, p.208 | ||||
| Adhesion, steel sheet piles | Soft clay and clayey silt | 104 | 365.5 | 627 | psf | CB T11.1, p.208 | ||
| Adhesion, steel sheet piles | Stiff and hard clay and clayey silt | 627 | 940 | 1,253 | psf | CB T11.1, p.208 | ||
| Friction coefficient, formed concrete / concrete sheet piling | Clean gravel, gravel–sand mixtures, well-graded rock fill | 0.4 | 0.45 | 0.5 | – | CB T11.1, p.208 | ||
| Friction coefficient, formed concrete / concrete sheet piling | Clean sand, silty sand–gravel mixtures, single-size hard rock fill | 0.3 | 0.35 | 0.4 | – | CB T11.1, p.208 | ||
| Friction coefficient, formed concrete / concrete sheet piling | Silty sand, gravel or sand mixed with silt or clay | 0.3 | – | CB T11.1, p.208 | ||||
| Friction coefficient, formed concrete / concrete sheet piling | Fine sandy silt, non-plastic silt | 0.25 | – | CB T11.1, p.208 | ||||
| Adhesion, formed concrete / concrete sheet piling | Soft clay and clayey silt | 209 | 470 | 731 | psf | CB T11.1, p.208 | ||
| Adhesion, formed concrete / concrete sheet piling | Stiff and hard clay and clayey silt | 731 | 992 | 1,253 | psf | CB T11.1, p.208 | ||
| Coefficient of horizontal soil stress on pile shaft, Ks/Ko | Driven piles, large displacement | Coarse-grained soil | 1 | 1.5 | 2 | – | TOMLINSON T4.10, p.172 | |
| Coefficient of horizontal soil stress on pile shaft, Ks/Ko | Driven piles, small displacement | Coarse-grained soil | 0.75 | 1 | 1.25 | – | TOMLINSON T4.10, p.172 | |
| Coefficient of horizontal soil stress on pile shaft, Ks/Ko | Bored and cast-in-place piles | Coarse-grained soil | 0.7 | 0.85 | 1 | – | TOMLINSON T4.10, p.172 | |
| Coefficient of horizontal soil stress on pile shaft, Ks/Ko | Jetted piles | Coarse-grained soil | 0.5 | 0.6 | 0.7 | – | TOMLINSON T4.10, p.172 | |
| Pile–soil interface friction ratio, δ/φ' | Smooth (coated) steel / sand | 0.5 | 0.6 | 0.7 | – | TOMLINSON T4.11, p.172 | ||
| Pile–soil interface friction ratio, δ/φ' | Rough (corrugated) steel / sand | 0.7 | 0.8 | 0.9 | – | TOMLINSON T4.11, p.172 | ||
| Pile–soil interface friction ratio, δ/φ' | Precast concrete / sand | 0.8 | 0.9 | 1 | – | TOMLINSON T4.11, p.172 | ||
| Pile–soil interface friction ratio, δ/φ' | Cast-in-place concrete / sand | 1 | – | TOMLINSON T4.11, p.172 | ||||
| Pile–soil interface friction ratio, δ/φ' | Timber / sand | 0.8 | 0.85 | 0.9 | – | TOMLINSON T4.11, p.172 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Allowable rock–grout bond stress, cement-grouted anchor | Strong rock (UCS > 14,500 psi) | 152 | 177.5 | 203 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Medium rock (UCS 7,250–14,500 psi) | 102 | 127 | 152 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Weak rock (UCS 2,900–7,250 psi) | 51 | 76.5 | 102 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Granite, basalt | 80 | 112.5 | 145 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Dolomitic limestone | 65 | 83.5 | 102 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Soft limestone | 51 | 62 | 73 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Slates, strong shales | 44 | 54.5 | 65 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Weak shales | 7 | 25.5 | 44 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Sandstone | 44 | 65.5 | 87 | psi | WYLLIE T12.8, p.297 | ||
| Allowable rock–grout bond stress, cement-grouted anchor | Concrete | 65 | 98 | 131 | psi | WYLLIE T12.8, p.297 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Friction angle | Gravels | GW-SP | Very loose / loose | 30 | 32 | 34 | deg | LOOK T7.8, p.107 |
| Friction angle | Gravels | GW-SP | Medium dense | 34 | 36.5 | 39 | deg | LOOK T7.8, p.107 |
| Friction angle | Gravels | GW-SP | Dense | 39 | 41.5 | 44 | deg | LOOK T7.8, p.107 |
| Friction angle | Gravels | GW-SP | Very dense | 44 | 46.5 | 49 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Very loose / loose | 27 | 29.5 | 32 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Medium dense | 32 | 34.5 | 37 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Dense | 37 | 39.5 | 42 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Very dense | 42 | 44.5 | 47 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Loose, uniformly graded | 27 | 28.5 | 30 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Loose, well graded | 30 | 31 | 32 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Dense, uniformly graded | 37 | 38.5 | 40 | deg | LOOK T7.8, p.107 |
| Friction angle | Sands | GW-SP | Dense, well graded | 40 | 41 | 42 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Soft sedimentary | 30 | 35 | 40 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Hard sedimentary | 35 | 40 | 45 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Metamorphic | 35 | 40 | 45 | deg | LOOK T7.8, p.107 |
| Friction angle | Broken rock (compacted) | Rockfill | Igneous | 40 | 45 | 50 | deg | LOOK T7.8, p.107 |
| Friction angle from SPT | Clean medium sand | SP / SW | Very loose (N ≤ 4) | 28 | deg | LOOK T5.4, p.80 | ||
| Friction angle from SPT | Clean medium sand | SP / SW | Loose (N = 4–10) | 28 | 29 | 30 | deg | LOOK T5.4, p.80 |
| Friction angle from SPT | Clean medium sand | SP / SW | Medium dense (N = 10–30) | 30 | 35 | 40 | deg | LOOK T5.4, p.80 |
| Friction angle from SPT | Clean medium sand | SP / SW | Dense (N = 30–50) | 40 | 42.5 | 45 | deg | LOOK T5.4, p.80 |
| Friction angle from SPT | Clean medium sand | SP / SW | Very dense (N > 50) | 45 | 47.5 | 50 | deg | LOOK T5.4, p.80 |
| Friction angle | Uniform sand, round grains | Loose | 27 | deg | CB T6.4, p.159 | |||
| Friction angle | Uniform sand, round grains | Dense | 34 | deg | CB T6.4, p.159 | |||
| Friction angle | Well-graded sand, angular grains | Loose | 33 | deg | CB T6.4, p.159 | |||
| Friction angle | Well-graded sand, angular grains | Dense | 45 | deg | CB T6.4, p.159 | |||
| Friction angle | Sandy gravel | Loose | 35 | deg | CB T6.4, p.159 | |||
| Friction angle | Sandy gravel | Dense | 50 | deg | CB T6.4, p.159 | |||
| Friction angle | Silty sand | Loose | 27 | 30 | 33 | deg | CB T6.4, p.159 | |
| Friction angle | Silty sand | Dense | 30 | 32 | 34 | deg | CB T6.4, p.159 | |
| Friction angle | Inorganic silt | Loose | 27 | 28.5 | 30 | deg | CB T6.4, p.159 | |
| Friction angle | Inorganic silt | Dense | 30 | 32.5 | 35 | deg | CB T6.4, p.159 | |
| Friction angle (compacted) | Well-graded sand–gravel | GW | Compacted to standard Proctor MDD | 38 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Poorly graded sand–gravel | GP | Compacted to standard Proctor MDD | 37 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Silty gravels | GM | Compacted to standard Proctor MDD | 34 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Clayey gravels | GC | Compacted to standard Proctor MDD | 31 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Well-graded clean sand | SW | Compacted to standard Proctor MDD | 38 | deg | CB T6.5, p.159 | ||
| Friction angle (compacted) | Poorly graded clean sand | SP | Compacted to standard Proctor MDD | 37 | deg | CB T6.5, p.159 | ||
| Effective friction angle (compacted) | Silty sands, sand–silt mix | SM | Compacted to standard Proctor MDD | 34 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clayey sands, sand–clay mix | SC | Compacted to standard Proctor MDD | 31 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Silts and clayey silts | ML | Compacted to standard Proctor MDD | 32 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clays of low plasticity | CL | Compacted to standard Proctor MDD | 28 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clayey silts, elastic silts | MH | Compacted to standard Proctor MDD | 25 | deg | CB T6.3, p.158 | ||
| Effective friction angle (compacted) | Clays of high plasticity | CH | Compacted to standard Proctor MDD | 19 | deg | CB T6.3, p.158 | ||
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Soft – organic | 10 | 15 | 20 | deg | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Soft – non-organic | 15 | 20 | 25 | deg | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Stiff | 20 | 25 | 30 | deg | LOOK T7.9, p.107 |
| Effective friction angle (peak) | Cohesive soils | CL-CH / OL-OH | Hard | 25 | 27.5 | 30 | deg | LOOK T7.9, p.107 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Dry unit weight | Sands and gravels | GW-SP | Very loose | 89.1 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Very loose | 108.2 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands and gravels | GW-SP | Loose | 95.5 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Loose | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands and gravels | GW-SP | Medium dense | 108.2 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Medium dense | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands and gravels | GW-SP | Dense | 121 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Dense | 133.7 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands and gravels | GW-SP | Very dense | 133.7 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands and gravels | GW-SP | Very dense | 140 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands | SP / SW | Loose, uniformly graded | 89.1 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Loose, uniformly graded | 108.2 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands | SP / SW | Loose, well graded | 101.9 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Loose, well graded | 121 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands | SP / SW | Dense, uniformly graded | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Dense, uniformly graded | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Sands | SP / SW | Dense, well graded | 121 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Sands | SP / SW | Dense, well graded | 133.7 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Cohesive soils | CL-CH / OL-OH | Soft – organic | 50.9 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Soft – organic | 89.1 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Cohesive soils | CL-CH / OL-OH | Soft – non-organic | 76.4 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Soft – non-organic | 101.9 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Cohesive soils | CL-CH / OL-OH | Stiff | 101.9 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Stiff | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Cohesive soils | CL-CH / OL-OH | Hard | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Cohesive soils | CL-CH / OL-OH | Hard | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Broken rock – soft sedimentary (chalk, shale, siltstone, coal) | Rockfill | Compacted | 76.4 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – soft sedimentary (chalk, shale, siltstone, coal) | Rockfill | Compacted | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Broken rock – hard sedimentary (conglomerate, sandstone) | Rockfill | Compacted | 89.1 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – hard sedimentary (conglomerate, sandstone) | Rockfill | Compacted | 121 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Broken rock – metamorphic | Rockfill | Compacted | 114.6 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – metamorphic | Rockfill | Compacted | 127.3 | pcf | LOOK T7.3, p.104 | ||
| Dry unit weight | Broken rock – igneous | Rockfill | Compacted | 108.2 | pcf | LOOK T7.3, p.104 | ||
| Saturated unit weight | Broken rock – igneous | Rockfill | Compacted | 133.7 | pcf | LOOK T7.3, p.104 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Electrical resistivity | Fresh water | 1,000,000 | ohm-cm | FGE T24.5, p.363 | ||||
| Electrical resistivity | Sea water | 100 | 300 | 500 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Coarse sand and gravel, dry | 2,000,000 | 5,000,000 | 8,000,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Coarse sand and gravel, saturated | 100,000 | 300,000 | 500,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Sand, dry | 500,000 | 1,250,000 | 2,000,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Sand, saturated | 20,000 | 60,000 | 100,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Silt, dry | 40,000 | 120,000 | 200,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Silt, saturated | 3,000 | 11,500 | 20,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Clay, saturated | 1,500 | 2,250 | 3,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Sandstone | 10,000 | 405,000 | 800,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Granite, gneiss | 700,000 | 1,100,000 | 1,500,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Concrete, gabbro | 1,000,000 | 2,500,000 | 4,000,000 | ohm-cm | FGE T24.5, p.363 | ||
| Electrical resistivity | Quartzite | 500,000 | 750,000 | 1,000,000 | ohm-cm | FGE T24.5, p.363 | ||
| Groundwater aggressiveness – chloride | Groundwater | Mild | 0 | 500 | 1,000 | mg/L | FGE T24.4, p.361 | |
| Groundwater aggressiveness – sulfate / sulfite | Groundwater | Mild | 0 | 75 | 150 | mg/L | FGE T24.4, p.361 | |
| Groundwater aggressiveness – chloride | Groundwater | Moderate | 1,000 | 3,000 | 5,000 | mg/L | FGE T24.4, p.361 | |
| Groundwater aggressiveness – sulfate / sulfite | Groundwater | Moderate | 150 | 825 | 1,500 | mg/L | FGE T24.4, p.361 | |
| Groundwater aggressiveness – chloride | Groundwater | Severe | 5,000 | mg/L | FGE T24.4, p.361 | |||
| Groundwater aggressiveness – sulfate / sulfite | Groundwater | Severe | 1,500 | 5,750 | 10,000 | mg/L | FGE T24.4, p.361 | |
| Groundwater aggressiveness – sulfate / sulfite | Groundwater | Very severe | 10,000 | mg/L | FGE T24.4, p.361 | |||
| Indicator of corrosive groundwater | pH | Corrosive when below (corrosive) | 7 | – | UFC T3-3, p.3-5 | |||
| Indicator of corrosive groundwater | Dissolved oxygen | Corrosive when above | 2 | ppm | UFC T3-3, p.3-5 | |||
| Indicator of corrosive groundwater | Hydrogen sulfide | Corrosive when above | 1 | ppm | UFC T3-3, p.3-5 | |||
| Indicator of corrosive groundwater | Total dissolved solids | Corrosive when above | 1,000 | ppm | UFC T3-3, p.3-5 | |||
| Indicator of corrosive groundwater | Carbon dioxide | Corrosive when above | 50 | ppm | UFC T3-3, p.3-5 | |||
| Indicator of corrosive groundwater | Chlorides | Corrosive when above | 500 | ppm | UFC T3-3, p.3-5 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| E80 strip surcharge for lateral (Boussinesq) pressure | Track, 9-ft ties | A Class I railroad shoring guideline | 1,778 | psf | RRSHORE App. A, p.A-1 | |||
| E80 strip surcharge for lateral (Boussinesq) pressure | Track, 8.5-ft ties | Class I railroad pipeline specification | 1,882 | psf | RRPIPE1 T3.2.3, p.13 | |||
| Minimum distance, track centerline to trackside of shoring | Temporary shoring (a Class I railroad) | No excavation closer | 12 | ft | RRSHORE T6.1, §6.1 | |||
| Maximum horizontal movement of temporary shoring | Temporary shoring (a Class I railroad) | 12–18 ft from track centerline | 0.375 | in | RRSHORE T1, §8.6 | |||
| Maximum horizontal or vertical movement of rail | Temporary shoring (a Class I railroad) | 12–18 ft from track centerline | 0.25 | in | RRSHORE T1, §8.6 | |||
| Maximum horizontal movement of temporary shoring | Temporary shoring (a Class I railroad) | 18–24 ft from track centerline | 0.5 | in | RRSHORE T1, §8.6 | |||
| Maximum horizontal or vertical movement of rail | Temporary shoring (a Class I railroad) | 18–24 ft from track centerline | 0.25 | in | RRSHORE T1, §8.6 | |||
| Embedment factor of safety, temporary shoring | Temporary shoring (a Class I railroad) | 1.3 | – | RRSHORE text, §8.1 | ||||
| Anchored shoring – minimum embedment as multiple of calculated depth | Temporary shoring (a Class I railroad) | 1.5 | × | RRSHORE text, §8.1 | ||||
| Track dead load (rails, guardrails, fasteners) | Temporary shoring (a Class I railroad) | 200 | lb/ft | RRSHORE text, §7.2 | ||||
| Roadbed dead load (ballast with ties) | Temporary shoring (a Class I railroad) | 120 | pcf | RRSHORE text, §7.2 | ||||
| Minimum spoil pile height to include in design | Temporary shoring (a Class I railroad) | 2 | ft | RRSHORE text, §7.2 | ||||
| Track curvature above which centrifugal force must be added | Temporary shoring (a Class I railroad) | 3 | deg | RRSHORE text, §7.8 | ||||
| Steepest unshored slope on railroad property | Temporary shoring (a Class I railroad) | 2 | H per 1V | RRSHORE text, §10 | ||||
| Backfill compaction near shoring | Temporary shoring (a Class I railroad) | Modified Proctor (ASTM D1557), within 2% of optimum | 95 | % | RRSHORE T9.4, §9.4 |
| Estimate | Correlation | Limits / notes | Source |
|---|---|---|---|
| E80 lateral pressure on shoring (Boussinesq strip) | σh = (2q/π)(β − sin β cos 2α); q = 80,000/(5 × tie length) psf | β and α are angles to the edges of the tie strip; q = 1778 psf for 9-ft ties | RRSHORE App. A, p.A-1 |
| Grouted anchor bond length | Lb = T·FS / (π d τa) | T = design load, d = drill hole diameter, τa = allowable rock–grout bond stress (Table 12.8) | WYLLIE T12.8, p.297 |
| Mononobe–Okabe active earth pressure | PAE = ½γH²(1 − kv)KAE; KAE = cos²(φ−θ−β) / {cosθ cos²β cos(δ+β+θ)[1 + √(sin(φ+δ)sin(φ−θ−i)/(cos(δ+β+θ)cos(i−β)))]²}; θ = tan⁻¹[kh/(1−kv)] | β = wall back batter from vertical, i = backfill slope; no real solution when φ − θ − i < 0 | DASDYN Eq. 8.4–8.6, p.332–333 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
After a failure: see Forensic Investigation of Ground Failures (Chapter 17) for what to record, how to scope the investigation, back analysis and vibration claims.
Retaining structures are among the most consequential geotechnical elements in railroad capital programs. They support embankments, protect cut slopes, carry track surcharge loads, and define the geometric boundary of right-of-way through urban corridors, bridge approaches, and intermodal facilities. Failures are costly, disruptive, and — given the dynamic loading environment of heavy-haul freight — potentially catastrophic.
This chapter presents the geotechnical design framework for retaining structures in railroad service, organized around the requirements common to owner railroads and grounded in AREMA Manual for Railway Engineering (MRE) Chapter 8 retaining structure provisions and USACE EM 1110-1-1804. We address lateral earth pressure theory (Rankine, Coulomb, at-rest), surcharge loading from Cooper E-80 trains, wall type selection, global stability, drainage, seismic earth pressure by the Mononobe-Okabe method, and client-specific deliverable requirements. All equations are expressed in English units.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.
| ID | Correlation | Gives |
|---|---|---|
| IX-09 | At-rest earth pressure coefficient | K₀ |
| IS-04 | Friction angle of sand from SPT (Schmertmann form) | φ' |
| IS-05 | Friction angle of sand from SPT (Peck–Hanson–Thornburn) | φ' |
| IX-08 | Friction angle of NC clay from plasticity | φ' |
Railroad retaining walls differ from highway walls in three important ways:
AREMA MRE Chapter 8, Part 5 (Retaining Walls, Abutments and Piers) provides the design basis for railroad retaining walls. Owner railroads generally require AREMA Chapter 8 compliance as a minimum, with their own modifications. Wall design calculations are normally signed and sealed by a Professional Engineer licensed in the project state. Check walls seismically where the owner railroad or the building code requires it. In cold regions, check frost penetration for all walls.
For walls that cannot deflect (rigid basement walls, integral abutments, braced excavations), the at-rest coefficient is used:
K₀ = 1 − sin φ' (normally consolidated soils) [Jaky, 1944]
For overconsolidated soils:
K₀(OC) = K₀(NC) × OCR^(sin φ')
The at-rest horizontal earth pressure at depth z is:
σ_h0 = K₀ × γ × z (psf)
where:
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| K₀ | 1 − sin φ' (normally consolidated soils) [Jaky, 1944] | Another equation | K0 = 1 − sin φ' (NC), × OCRsin φ' for OC soil (Jaky; Mayne & Kulhawy). Field: DMT or self-boring pressuremeter. | 0.35–0.65 NC · by USCS group |
| K₀(OC) | K₀(NC) × OCR^(sin φ') | Another equation | K0 = 1 − sin φ' (NC), × OCRsin φ' for OC soil (Jaky; Mayne & Kulhawy). Field: DMT or self-boring pressuremeter. | 0.35–0.65 NC · by USCS group |
| γ | moist unit weight of retained soil (pcf) | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
| z | depth below top of retained earth (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| OCR | preconsolidation stress / OCR | Lab test (or correlation) | Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0. | OCR 1 (NC) to > 4 (heavily OC) · by USCS group |
Rankine theory assumes a smooth, vertical wall with a horizontal backfill surface. It is the most commonly applied method for preliminary design and is the usual starting point for walls with a vertical back and level backfill.
K_A = tan²(45° − φ'/2)
K_P = tan²(45° + φ'/2)
Active pressure at depth z:
σ_A = K_A × γ × z − 2c' × √K_A (psf)
Passive pressure at depth z:
σ_P = K_P × γ × z + 2c' × √K_P (psf)
For purely cohesionless backfill (c' = 0, the standard AREMA design assumption):
σ_A = K_A × γ × z
σ_P = K_P × γ × z
Total active force per linear foot of wall (triangular distribution):
P_A = ½ × K_A × γ × H² (lb/ft)
Acting at H/3 above the base for triangular pressure distribution.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| KA | intermediate value computed on this page | Another equation | Computed: K_A = tan²(45° − φ'/2) | project-specific |
| KP | intermediate value computed on this page | Another equation | Computed: K_P = tan²(45° + φ'/2) | project-specific |
| σA | intermediate value computed on this page | Another equation | Computed: σ_A = K_A × γ × z − 2c' × √K_A (psf) | project-specific |
| σP | intermediate value computed on this page | Another equation | Computed: σ_P = K_P × γ × z + 2c' × √K_P (psf) | project-specific |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| c' | effective cohesion | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
Coulomb theory accounts for wall friction (δ) and backfill slope angle (β). Use it for sloped backfills and battered walls:
K_A(Coulomb) = sin²(α + φ') / { sin²α × sin(α − δ) × [1 + √( sin(φ' + δ) × sin(φ' − β) / (sin(α − δ) × sin(α + β)) )]² }
where:
For the common case of a vertical wall (α = 90°) retaining horizontal fill (β = 0°):
K_A(Coulomb) = cos²φ' / { cos δ × [1 + √(sin(φ' + δ) × sin φ' / cos δ)]² }
Note: Coulomb passive pressure is non-conservative for walls with significant wall friction; use Rankine passive or log-spiral methods for passive resistance calculations.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| KA(Coulomb) | intermediate value computed on this page | Another equation | Computed: K_A(Coulomb) = sin²(α + φ') / { sin²α × sin(α − δ) × [1 + √( sin(φ' + δ) × sin(φ' − β) / (sin(α − δ) × sin(α + β)) )]² } | project-specific |
| α | angle of back face of wall with horizontal (= 90° for vertical wall) (degrees) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| φ' | effective friction angle of retained soil (degrees) | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| δ | wall friction angle (degrees) | Lab test (or fraction of φ') | Interface direct shear (ASTM D5321); otherwise δ = 0.6–1.0 φ' depending on the surface (steel, concrete, geosynthetic). | 0.6–1.0 φ' · by USCS group |
| β | slope angle of retained fill surface (degrees) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
In cohesive soils, tension cracking reduces the effective retained height. The tension crack depth is:
z_c = 2c' / (γ × √K_A) (ft)
For design, assume the tension crack is filled with water (worst case). The net active pressure diagram excludes the tension zone, and an additional hydrostatic pressure acts over depth z_c.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| c' | effective cohesion | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
AREMA MRE Chapter 8 allows train live load to be represented as an equivalent uniform surcharge on top of the retained fill for wall design:
q_LL = Cooper E-80 wheel load equivalent uniform pressure (psf)
For a rough first check of walls well away from the track, some designers use a uniform surcharge such as:
q_LL = 400 psf (simplified value; not an AREMA value)
Near the track this badly understates the load. AREMA represents the E-80 axle as a strip of about 1,882 psf (80 kips over 5 ft × 8.5 ft) and computes lateral pressure with the strip-load formula (see the box below and Section 7.1.3.1).
This is multiplied by an assumed DLF = 1.3 for dynamic effects, giving a design surcharge:
q_design = DLF × q_LL = 1.3 × 400 = 520 psf
The additional horizontal pressure from this surcharge using Rankine:
Δσ_A(surcharge) = K_A × q_design (psf, uniform with depth)
The resultant surcharge force per foot of wall:
ΔP_surcharge = K_A × q_design × H (lb/ft)
Acting at H/2 above the base (uniform pressure diagram).
For walls within 15 ft of the track centerline (measured horizontally), owner railroads may require a more detailed Boussinesq-based pressure distribution using the actual axle loads rather than the simplified equivalent surcharge.
For excavation support next to active track, a Class I railroad (Public Projects Manual, 2020) requires shoring to be designed for active earth pressure plus a live-load surcharge of 1,882 psf on a continuous strip 8.5 ft wide, with lateral pressure computed by the strip-load formula in AREMA MRE Chapter 8, Part 20. (1,882 psf equals an 80-kip E-80 axle spread over 5 ft of track length and 8.5 ft of width.) This is more than three times the 400-psf uniform value in Section 7.1.3 and, as a strip load, it concentrates pressure in the upper part of the wall. Use the owner’s criterion wherever it applies, and treat the 400-psf equivalent as a preliminary-sizing number only.

Other Class I railroad shoring rules: shoring may be omitted only if the excavation stays outside a 1H:1V line from the bottom corner of the tie and the track is on level ground or in a cut on stable soil. Excavating the toe of an embankment carrying track is not allowed without shoring. Full cofferdams (steel sheeting, or soldier piles and lagging, with wales and struts) are preferred; partial cofferdams open on the side away from the track are allowed where conditions dictate.
Source: A Class I railroad (2020). Public Projects Manual, December 2020 (shoring requirements adjacent to track)
The library's notes on lateral earth pressure give the Rankine and Coulomb coefficients; the railroad problem adds a large, concentrated surcharge from the track. A wall retaining track within a few feet of the tie ends carries more load from the train than from the soil itself, and the load peaks a few feet below the top of the wall, not at the base. The manual's practice for walls retaining track is soldier piles with lagging rather than MSE walls (Chapter 7.1 and the project preferences), and the same pressure diagram is used to size the piles and lagging.
Equation 7.1-1. Coulomb active coefficient (vertical wall back)
with δ = 0 and β = 0 this reduces to the Rankine value tan²(45° − φ/2).
Equation 7.1-2. Lateral pressure from a strip surcharge (Boussinesq)
where βs is the angle subtended by the strip at the point and α the angle to the strip centerline.
| Item | Default | Basis |
|---|---|---|
| Axle load | 80 kips | Cooper E80 design axle |
| Distribution along track | 5 ft | Axle spacing of the E80 driver group |
| Distribution across track | 8.5 ft | Tie length |
| Strip pressure qs | about 1,880 psf | 80,000 lb / (5 ft × 8.5 ft); add impact as the governing standard requires |
| Offset | Entered | Wall face to near end of ties |
| Load component | Thrust | Notes |
|---|---|---|
| Soil, Coulomb Ka = 0.275 | 3.02 kips/ft | φ' = 32°, δ = 21°, γ = 120 pcf |
| Railroad strip surcharge | 7.55 kips/ft | 1,880 psf over 8.5 ft, unyielding-wall solution |
| Total | 10.57 kips/ft | acting 6.79 ft above the base |
Without the train the same wall carries only 3.02 kips/ft, acting at H/3. The surcharge raises the resultant and more than triples the thrust, so the moment in the piles is governed by the railroad load. For a flexible soldier pile wall some designers use the half-space solution (half the surcharge pressure); the calculator offers both so the choice is explicit.
Open the earth pressure calculator →
Rankine or Coulomb coefficients, water, uniform surcharge and an E80-type strip surcharge; pressure diagram, thrust, resultant height and overturning moment.
These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.
Gravity walls resist sliding and overturning through their own mass. Common materials include mass concrete and dry-laid or mortared stone masonry. Practical retained height limit is approximately 12–15 ft for mass concrete.


Factor of Safety Against Sliding:
FS_sliding = (W × tan δ_base + c_base × B) / P_A_total ≥ 1.5 (AREMA Ch. 8)
where:


Factor of Safety Against Overturning:
FS_OT = ΣM_resisting / ΣM_overturning ≥ 2.0 (AREMA Ch. 8)
Resultant Eccentricity:
e = B/2 − (ΣM_resisting − ΣM_overturning) / ΣV (ft)
For no tension at the base, the middle-third rule requires:
e ≤ B/6
This is the usual requirement for gravity and cantilever walls on soil supporting track; confirm the owner railroad's criterion (rock foundations may allow more eccentricity).
Bearing Pressure at Toe:
q_toe = (ΣV/B) × (1 + 6e/B) (psf)
Bearing Pressure at Heel:
q_heel = (ΣV/B) × (1 − 6e/B) (psf)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| W | total vertical weight of wall + retained soil on heel (lb/ft) | Another equation | Area of the slice, wedge or wall section from the cross-section geometry × unit weight γ (from lab tests). | project-specific |
| δbase | friction angle at base (degrees) | Lab test (or fraction of φ') | Interface direct shear (ASTM D5321); otherwise δ = 0.6–1.0 φ' depending on the surface (steel, concrete, geosynthetic). | 0.6–1.0 φ' · by USCS group |
| cbase | base adhesion (psf) | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| B | base width (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| PAtotal | total active force including surcharge (lb/ft) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| e | void ratio = B/2 − ( ΣM_resisting − ΣM_overturning ) / ΣV (ft) | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |


Cantilever walls use a reinforced concrete stem and footing to resist overturning. The critical design section is at the base of the stem. Retained heights of 10–25 ft are typical.
Stem base moment (per foot of wall):
M_stem = (K_A × γ × H³/6) + (K_A × q_design × H²/2) (ft·lb/ft)
Minimum embedment depth for adequate passive resistance:
d_min is determined by setting FS_sliding ≥ 1.5 with the contribution of passive resistance over the embedded depth of the footing toe.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
MSE walls use reinforced fill to develop internal stability. They are commonly preferred for retained heights of 10–40 ft where ROW permits adequate fill width. MSE walls are commonly designed to AASHTO LRFD Bridge Design Specifications in addition to AREMA Chapter 8.





Internal stability checks include:
External stability checks (sliding, overturning, bearing) use the MSE mass as an equivalent gravity wall.
Owner railroads may require a minimum cover of unreinforced structural fill between the top reinforcement layer and the ballast for MSE walls next to live track; confirm it.
Soldier pile walls use steel H-piles driven or drilled at 6–8 ft spacing with timber lagging. They are commonly used for temporary shoring during cut construction and for permanent retained cuts in urban railroad corridors where MSE fill width is unavailable.

Required embedment depth below excavation for cantilever soldier piles (simplified method):
(1/6) × K_p × γ × d³ = P_A × (ȳ + d), per foot of wall, taking moments about the pile tip; ȳ = height of P_A above the excavation level. For discrete soldier piles, apply the passive resistance over an effective width of about 2–3 pile widths.
Solve iteratively for d; common practice increases d by 20–40% for design.
Size timber lagging for the span and soil type (FHWA GEC 4).
Sheet pile walls (steel) are used for waterfront structures, scour protection, and temporary cofferdams. Free-earth support method for cantilever sheet piles:

d_theoretical is determined by moment equilibrium; common practice increases d_theoretical by 20–40% (USACE instead factors the passive strength; see the box below).
Anchored sheet pile walls use tie rods to reduce embedment depth and moment demand. The anchor force:
T_A = P_A − P_P (horizontal force equilibrium, free-earth support)
Owner railroads may require coated or encapsulated steel sheet piles for permanent waterfront applications where tidal or chemically aggressive conditions exist.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
Soil nail walls are constructed top-down and are well suited to cuts in stiff clays, dense sands, and weathered rock. Nail design:
T_design = σ_h × S_v × S_h / FS_nail (lb)
Pullout resistance per unit length: Q_u = π × d_borehole × q_s (lb/ft) where q_s is the unit skin friction (psf)
FHWA GEC 7 (FHWA-NHI-14-007, 2015) recommends a global stability FS of 1.5 for permanent soil nail walls. AREMA Chapter 1 (Section 2.3.3) lists soil nail walls among slope repair methods and says they must be designed by an experienced engineer.
Where a ballast shoulder or fill slope has slumped away from the ties and there is no room or time for a conventional wall, a micropile–tieback facing can be built from the embankment crest within track windows. Two projects in the AREMA Committee 1 files, both by GeoStabilization International (2018), show the arrangement:






Why micropiles fit railroad sites (SHRP2): they can be drilled through any ground, including boulders, rubble fill and old ballast, at any angle, with small rigs, low noise and little spoil (low-headroom rigs work under 10 ft clearance). Capacity comes from grout-to-ground bond (toe resistance neglected), so tension and compression capacities are about equal. At least about 40% of the load is carried by the steel. Capacities commonly exceed 200 tons in soil and 500 tons in rock, and most are under 100 ft long. Limitations: high slenderness (check buckling in very soft or liquefiable soil), and the method depends on contractor drilling and grouting skill, so load testing is essential.
Composite gabion walls (gabion facing combined with tiebacks, soil nails, reinforced concrete beams or drilled shafts) are marketed on the same principle — less excavation behind the face than a gravity gabion or cantilever wall — which matters when the excavation would otherwise undermine the track.


Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files · GeoStabilization International (2018). Class I railroad Yard Culvert Wall — Micropile Cap (drawings). AREMA Committee 1 files · SHRP2 R02 / GeoTechTools (2012). Micro-piles — fact sheet


Section 7.1.4.5 increases the theoretical embedment by 1.3. EM 1110-2-2504 takes a different approach: it applies a strength-reduction factor to the passive side only (tan φeff = tan φ/FSP; ceff = c/FSP), uses best estimates elsewhere, and usually takes FSA = 1 unless wall deformation must be limited. It then solves directly for the penetration. The two approaches do not give the same depth; do not apply both.
Table 16-S1. Minimum FS on passive pressure for penetration depth (EM 1110-2-2504, Table 5-1, retaining walls)
| Loading case | Fine-grained soils | Free-draining soils |
|---|---|---|
| Usual | 2.00 Q-case; 1.50 S-case | 1.50 S-case |
| Unusual | 1.75 Q-case; 1.25 S-case | 1.25 S-case |
| Extreme | 1.50 Q-case; 1.10 S-case | 1.10 S-case |
Other USACE points relevant to track walls: in medium-dense or denser sand, the active state develops at about 0.1–0.2% of wall height (about ¼–½ in. for a 20-ft wall), while full passive needs about 2–4% (roughly 5–10 in.). This is why passive resistance should be discounted where track settlement is critical. For anchored walls, the Free Earth method gives stable walls with less penetration than Fixed Earth but overpredicts moment (use Rowe’s moment reduction). Initially place the anchor at ¼–⅓ of the exposed height below the top. Grouted anchors must lie entirely outside the active wedge and develop the tie-rod yield strength. Proof-test every anchor to 110% of required resistance and performance-test at least two to 150% of design capacity.
Source: U.S. Army Corps of Engineers (1994). Design of Sheet Pile Walls. EM 1110-2-2504
Lines along coasts, lakes and large rivers often depend on revetments, seawalls or bulkheads. EM 1110-2-1614 sizes armor stone by Hudson’s equation:
W = γrH3 / [KD(γr/γw − 1)3 cot θ]
where W is the armor unit weight (W50 for graded riprap) and H is the design wave height. Suggested KD for breaking waves: rough angular quarrystone, two layers, random 2.0 (1.2 for smooth rounded); graded riprap 2.2 (slopes 2.0–6.0 cot θ). A single layer of randomly placed rough stone is “do not use”, and graded riprap is not recommended where waves exceed 5 ft. For irregular waves on dumped riprap, the zero-damage stability number is Nsz = 1.14 cot1/6 θ with Hs.
Source: U.S. Army Corps of Engineers (1995). Design of Coastal Revetments, Seawalls, and Bulkheads. EM 1110-2-1614
For very tall embankment sides, Profillidis shows either a conventional retaining wall at the toe or reinforced soil: an assembly of good-quality granular backfill, metallic reinforcing bars or strips anchored in the fill, and a concrete facing. Reinforced soil is recommended particularly on poor and very poor subgrades (S1, S0) and allows very steep or vertical faces. A French cost comparison for railway projects found reinforced soil economically and technically advantageous over a retaining wall, especially at heights of 10–40 ft (Figure 7.1-13).











Caution for electrified lines. The book states that metallic-reinforced soil cannot be used on electrified railways, because return current corrodes the metal reinforcement and can lead to failure. Where a reinforced-soil wall is proposed near an electrified line or a DC transit system, address stray-current corrosion explicitly. Options include non-metallic (geosynthetic) reinforcement or a corrosion design that accounts for stray current.
After Profillidis (2014), §9.12.2, §9.13, Figs. 9.16–9.18. Full reference under Supplemental References.
Use a wall when a berm cannot be placed. Driven walls isolate the track from shallow-to-medium movement below but are not efficient against deep-seated failures. H-pile walls along the shoulder use piles about 4 ft apart. If movement continues, add a whaler so the piles act together; if it still moves, add soil anchors or tie back to piles on the far side of the grade. Rule of thumb: to hold 4 ft of unstable ground, embed at least 8 ft below the slip plane. At one Atlantic Canada site, a tidal bank retrogressing toward the track was treated with a temporary riprap toe berm and then a design combining 55-ft H-piles with a 40-ft sheet-pile wall.









After Geotechnology for Railroaders Program, Module 6.1; §05–07, §10. Full reference under Supplemental References.
Cretu et al. argue that risk assessment and value engineering (VE) belong together, because risk analysis characterizes the problems and VE generates the solutions. VE, also called value methodology, is a facilitated multidiscipline study built on function analysis. It asks what an element must do rather than what it is, and that is what separates it from simple cost cutting. For each high or moderate risk they add a function-based step to response planning:


Reducing a long risk narrative to a short function statement keeps the team focused on the thing that can actually be managed. It also tends to produce several candidate solutions instead of one.
For railroad work: Wall selection is a natural application. Suppose the risk is “soft clay below the planned cantilever wall may cause excessive rotation under E-80 surcharge.” The risk object is the foundation. The response functions might be “avoid foundation” (a lightweight-fill embankment or a pile-supported wall), “mitigate settlement” (ground improvement or preloading where a track window allows), “transfer design” (a performance-specified proprietary system) and “accept movement” (a flexible MSE or gabion wall with a resurfacing allowance). Screening these against track-outage limits, construction access from the right-of-way, and the railroad’s preferences for wall type gives a short list. The short list can then be ranked by weighted paired-comparison scoring and compared on a whole-life cost basis.
Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 157–162. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Soldier piles and lagging are this manual's standard wall next to track. Below the excavation the piles act as discrete elements, not a continuous wall, and the passive resistance per pile is more than the plane-strain value over the pile width. UK guidance (CIRIA C580, summarised in Pickles, 2012, pp. 995–996) gives the ultimate net resistance per pile when the spacing s is more than three pile widths b.
Equation 7.1-6. Ultimate passive resistance of a discrete pile, per unit depth
Pickles (2012), Eqs. 64.5–64.8, after Barton (1982) and Fleming et al. (1994). Divide by s for resistance per foot of wall. Kp = (1 + sinφ′)/(1 − sinφ′); valid for Kp = 3.0 to 5.3 (30° ≤ φ′ ≤ 43°). z is depth below the excavation and p′v the effective overburden there. Vol. II prints “≤” in both depth limits; the second limit of each pair is evidently ≥, where the deeper expression takes over.
Full active pressure is assumed on the retained side. The Kp² form is close to the 3Kp rule (Broms) used in many U.S. guidelines at Kp = 3 and higher at larger Kp; follow the governing railroad shoring guideline where it prescribes a method (Section 7.1.17).
Excavation unloads the clay in front of the wall; as negative pore pressures dissipate, the clay near the excavation base softens. Take the undrained strength as zero at the excavation level, rising to the design value at a depth L (Pickles, 2012, Eq. 64.4, p. 994):
Equation 7.1-7. Depth of softened clay below an excavation
cv = coefficient of consolidation; t = time the excavation is open. Use L of about 1.6 ft (0.5 m) where no groundwater recharge is possible.
For example, with cv = 0.1 ft²/day, L is about 4.1 ft after two weeks and about 10 ft after three months, which can remove much of the passive resistance a short embedment relies on. Also allow for unplanned over-excavation in front of the wall: 10% of the retained height, up to about 1.6 ft (0.5 m), in Eurocode practice (Pickles, 2012, p. 985).
Equation 7.1-8. Fixed anchor length from bond (skin friction)
Turner (2012), Eqs. 66.1–66.6, pp. 1017–1021. d = borehole diameter; L = fixed (bond) length; τ = grout–ground bond from load tests or published values; F = global factor (Vol. II recommends retaining the BS 8081 global factors).
Soldier piles in 2-ft drilled holes at 8-ft spacing support an excavation beside track. Below the excavation the soil is dense sand. Find the ultimate passive resistance per pile at 5 ft below the excavation and compare it with the 3Kp rule.
| Variable | Value | Description |
|---|---|---|
| b | 2 ft | Pile (drilled hole) width |
| s | 8 ft | Pile spacing (s > 3b = 6 ft) |
| φ′ | 34° | Sand below excavation |
| γ | 120 pcf | Unit weight (above groundwater) |
| z | 5 ft | Depth below excavation |
This is an ultimate value; apply the factor of safety or the reduced passive coefficient that the governing railroad shoring guideline requires before using it to find embedment.
In clay, replace this with the undrained form and reduce the strength near the excavation base by the softened depth L.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Global stability analysis (deep-seated failure of the entire wall-soil system) should be performed for walls retaining more than about 10 ft of fill and wherever weak soil underlies the wall. Use Bishop Simplified (Chapter 6.3) or Spencer's method for complex geometries.
Minimum global FS values (Table 7.1-1):
| Railroad | Long-Term FS (static) | Seismic FS | Submerged/Seepage FS | Source |
|---|---|---|---|---|
| Typical | 1.5 | 1.1 | 1.3 | Common practice; confirm with owner |
Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.
Case study: 7.1.16.1 Back-analysis of a failed wall: condemn 330 ft, or not? (Look 2023), in §16.16 Case Studies.

Hydrostatic pressure behind a wall can double or triple total lateral force. Drainage is not optional — it is a fundamental design requirement.
Hydrostatic pressure added to active pressure:
σ_w = γ_w × h_w (psf)
where h_w = height of water behind wall (ft); γ_w = 62.4 pcf.
Design requirement: All walls retaining granular fill must include continuous granular drainage blanket (≥ 12 in. thick, AASHTO No. 57 stone or equivalent), perforated pipe collector drain at the base, and weep holes through the wall face (4 in. diameter minimum, spaced ≤ 10 ft, per AREMA Ch. 8).
For walls in cold regions where freeze-thaw cycles are severe, insulated drainage blankets or thermally protected drains are needed to prevent pipe freeze.
A Geosynthetic Research Institute review estimated about 35,000 geosynthetic-reinforced MSE walls, about 30% of them block-faced SRWs. It examined 26 problem walls (12 serviceability, 14 collapses). In 25 of 26 the cause was poor backfill or poor construction and/or lack of inspection, and 20 of 26 had silt or clay backfill in the reinforced zone. The collapse mechanism was hydrostatic pressure: a crack admits water, the facing bulges, a block is dislodged, and the blocks above follow progressively until the facing and drainage gravel are lost.
| Sieve | Koerner (1994) | FHWA (1998) | NCMA (1997) |
|---|---|---|---|
| No. 4 | 100 | 100 | 20–100 |
| No. 40 | 0–60 | 0–60 | 0–60 |
| No. 200 | 0 | 0–15 | 0–35 |
Recommended reinforced-backfill gradations, % passing (GRI compilation).
Recommendations: prefer sand in the reinforced zone (gravel is acceptable but costs more and increases installation damage). If silt or clay is used it must be drained internally and externally, with particular attention to surface drainage. Design for hydrostatic pressure from all sources and directions. Suggested construction QA presence is 67% of construction time for noncritical permanent walls and 100% for critical walls; critical walls next to track should have full-time inspection. The same survey (1998 bid prices from 40 state DOTs) found geosynthetic MSE the least-cost wall type in every height class.
Source: Geosynthetic Research Institute (c. 2000). Geosynthetic Reinforced Segmental Retaining Walls (SRWs) (presentation; cost survey after J. Koerner et al., 1998)
For walls in seismically active zones where the owner railroad or the governing code requires a seismic check (commonly SDC C and D), add the seismic earth pressure increment to the static active pressure. Passenger railroads commonly require seismic design for mainline walls.
The Mononobe-Okabe (M-O) total active force:
P_AE = ½ × γ × H² × (1 − k_v) × K_AE (lb/ft)
where:
K_AE = cos²(φ' − θ − α) / { cosθ × cos²α × cos(δ + α + θ) × [1 + √(sin(φ' + δ) × sin(φ' − θ − β) / (cos(α + θ + δ) × cos(α − β)))]² }
and:
θ = arctan(k_h / (1 − k_v))
The seismic earth pressure increment:
ΔP_AE = P_AE − P_A (lb/ft)
Per Seed and Whitman (1970), this increment is assumed to act at 0.6H above the base:
M_AE = ΔP_AE × 0.6H + P_A × H/3 (ft·lb/ft)
| Railroad | Min. FS Slide | Min. FS OT | Wall Friction | Surcharge | Seismic Req. | Drain Req. | PE Seal State | Governing Std. |
|---|---|---|---|---|---|---|---|---|
| AREMA | 1.5 | 2.0 | δ = ⅔φ' (common) | E-80 strip load (Section 7.1.3.1) | SDC per code | Mandatory | Per state | AREMA MRE Ch. 8 |
Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.
A second main track on a Class I railroad located in the Shenandoah Valley of western Virginia needs a 20-ft cantilever wall where the slope is cut back. The example computes the earth pressure with Coulomb wall friction, adds the train surcharge, and checks sliding and overturning on a trial footing.


.jpg)
| Variable | Value | Description |
|---|---|---|
| H | 20 ft | Retained height |
| Backfill | φ′ = 34°, c′ = 0, γ = 120 pcf | Compacted granular fill |
| δ | 22.7° (2/3 φ′) | Wall friction |
| q | 520 psf | Train surcharge with DLF 1.3, simplified as uniform (Section 7.1.3.1 gives the strip load) |
| Base | φ′base = 30°; qallow = 4,000 psf | Dense sand |
| W | ≈ 24,000 lb/ft | Stem, footing and soil on the heel, B = 10 ft (from the wall geometry, not detailed here) |
| Targets | FSsliding ≥ 1.5; FSOT ≥ 2.0 |
KA = 0.254 and the total thrust is 8,738 lb/ft. Sliding passes at 1.58; overturning fails at B = 10 ft (1.43) and passes at B = 14 ft (2.12).
Cantilever walls usually take three to five geometry iterations; the heel is the most effective thing to lengthen because it adds both soil weight and lever arm. The uniform 520-psf surcharge understates the load where the track is close to the wall, so recheck sliding and overturning with the strip load (Section 7.1.3.1) once the track offset is fixed. Railroad walls next to track are usually soldier pile and lagging; a cantilever wall suits a cut transition like this one.
A 30-ft MSE wall supports an approach embankment at an intermodal expansion on a Class I railroad located in Kansas City. Each geogrid layer must carry the horizontal earth pressure over its tributary spacing, and must be anchored far enough behind the failure surface not to pull out.
| Variable | Value | Description |
|---|---|---|
| H | 30 ft | |
| Reinforced fill | φ′ = 36°, γ = 125 pcf | |
| Geogrid | Sv = 2.0 ft; Rc = 1.0; Le = 4.5 ft at z = 28 ft | |
| F*, α, C | 0.67 tanφ′ = 0.487; 0.8; 2 | FHWA GEC 11 defaults for geogrid |
| q | 520 psf | Train surcharge |
| L | 22 ft | Reinforcement length |
| qallow | 6,000 psf | Foundation |
Tmax = 2,090 lb/ft at z = 28 ft; pullout FS = 5.9; bearing 4,270 psf against 6,000 psf allowable.
The geogrid must also have a long-term design strength Tal above 2,090 lb/ft after the reduction factors for creep, installation damage and durability (FHWA GEC 11); that comes from the product data. The final design must also check eccentricity of the base reaction, global stability and settlement.
A 15-ft gravity wall on a Class I railroad located near Salem, Oregon, in Seismic Design Category D. The Seed-Whitman simplification adds a seismic increment to the static thrust and applies it higher on the wall, which is why seismic overturning so often governs.
| Variable | Value | Description |
|---|---|---|
| H | 15 ft | |
| Backfill | φ′ = 32°, γ = 120 pcf | |
| kh, kv | 0.25 and 0 | |
| KA | 0.307 (Rankine) | Coulomb with δ = 21.3° gives 0.275 |
| Target | FSOT ≥ 1.1 seismic (assumed) |
KAE ≈ 0.495; the seismic increment is 2,532 lb/ft, and the seismic overturning moment is about 43,500 ft-lb/ft, 2.1 times the static value.
The increment acts at 0.6H rather than H/3, so it nearly doubles the moment on its own. In Seismic Design Category D the seismic case usually governs the wall geometry; size the footing for FSOT ≥ 1.1 under this moment.
| Project | Client | Wall Type | H (ft) | Backfill φ' (°) | K_A | P_A (lb/ft) | q_surcharge (psf) | FS_slide | FS_OT | Seismic |
|---|---|---|---|---|---|---|---|---|---|---|
| Shenandoah Ext. | Class I | Cantilever RC | 20 | 34 | 0.254 | 6,096 | 520 | 1.58 | 2.12* | No |
| KC Intermodal | Class I | MSE Geogrid | 30 | 36 | 0.260 | 14,625 | 520 | 1.82 | 2.45 | No |
| Cascades Ext. | Class I | Gravity Conc. | 15 | 32 | 0.307 | 4,151 | 520 | 1.52 | 1.18 seismic | Yes |
| Passenger corridor Viaduct | Passenger | Soldier Pile | 25 | 30 | 0.333 | 12,500 | 520 | N/A | N/A | Yes |
| Prairie Yard | Class I | MSE Geogrid | 18 | 35 | 0.271 | 5,270 | 400 | 1.92 | 2.60 | No |
| Gulf Coast Ext. | Short line | Cantilever RC | 12 | 28 | 0.361 | 3,114 | 400 | 1.65 | 2.10 | No |
| Western Div. | Class I | Gravity Conc. | 10 | 30 | 0.333 | 2,000 | 400 | 1.80 | 2.50 | No |
*After widening the base to 14 ft. The first three rows come from Examples 16-1 to 16-3; the other rows are illustrative, not project records. P_A uses γ = 120 pcf (125 pcf for the KC row).





Case study: 7.1.16.2 Design detailing and analysis input: short case notes (Look 2023), in §16.16 Case Studies.
Jacob and Müller price a temporary anchored soldier pile wall by costing one complete bay, meaning one soldier pile and the lagging to the next pile. That bay cost is then spread over the exposed (visible) face area, which is the pay unit in their bill of quantities.

Example geometry, converted to US units:
The bay cost is built from:
Of the bay cost, lagging was about 28%, anchors about 25%, drilling about 25% and extraction about 8%. The bay cost divided by (17.4 ft × 9.8 ft) gives the cost per square foot of face. A 25% markup was applied.
The authors contrast this with sheet piling. Sheet piling is paid on the actual driven wall area rather than the exposed face. When it stays in place permanently, the full material cost is included.
For railroad work: Temporary soldier pile walls for culvert replacements, track-adjacent excavations and shoofly construction are often the largest cost of temporary works. A bay-based build-up shows the railroad how the price depends on several things:
The pay unit (exposed face, total wall area or lump sum) must be stated clearly in the special provision, together with who designs the system and the movement-monitoring limits.
Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 192–195. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Damage patterns to look for during inspection:
Inspection. Typical codes require special inspection of walls with more than 8 ft of retained height, and of 4- to 8-ft walls that carry a surcharge or a slope steeper than 3H:1V. Periodic inspection should look for loss of backfill, open joints and movement; voids from lost backfill fill with water and raise the pressure, so fill them promptly. Walls built against freshly cut slopes may lose strength as the cut material softens with time, so design for long-term strength.
Rating granular backfill. Brown’s suitability number, developed to rate backfill for vibroflotation, compares how readily granular materials densify:
SN = 1.7 √( 3/D502 + 1/D202 + 1/D102 ) with D in mm, or SN = 0.067 √( 3/D502 + 1/D202 + 1/D102 ) with D in in.
Ratings: 0–10 excellent, 10–20 good, 20–30 fair, 30–50 poor, over 50 unsuitable.
For railroad work: Add tilt, bowing, water staining and backfill loss to the wall entries of the earthworks inventory (Chapter 7.4) and record them as defects in the risk rating (Chapter 3.8). Railroad walls carry train surcharge, so the 4- to 8-ft walls next to track normally fall in the special-inspection group. The suitability number is a quick way to compare candidate free-draining backfills and stone column or vibro backfill (Chapter 7.2, Section 7.2.4).
Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 208, Retaining Walls. Full reference under Supplemental References.
Checklist · Part VII · Stabilization Methods
Pre-Design Phase
Analysis Phase
Deliverable Phase
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Topic | See Also |
|---|---|
| Bearing capacity of wall foundation | Chapter 6.1 |
| Settlement of wall foundation | Chapter 6.2 |
| Global slope stability of retained embankment | Chapter 6.3 |
| Seismic hazard and k_h determination | Chapter 6.5 |
| Drainage and seepage behind walls | Chapter 2.8 |
| Geotechnical Special Provisions (wall language) | Appendix C |
| Retaining wall section in final GDR | Chapter 8.4 |
| Foundation soil lab testing | Chapter 5.2 |
An 18-ft cantilever retaining wall will support the fill for a new main track next to an existing one, with granular backfill and the train surcharge shown. The engineer must compute the active earth pressure coefficient, the thrust from the soil and the added thrust from the train surcharge.
| Variable | Value | Description |
|---|---|---|
| H | 18 ft | |
| Backfill | φ′ = 32°, γ = 118 pcf | |
| q | 520 psf |
(a) 0.307. (b) 5,874 lb/ft. (c) 2,877 lb/ft.
The surcharge adds about half as much again as the soil and acts higher on the wall (H/2), so it contributes more than half as much again to the overturning moment.
A gravity retaining wall supports a railroad embankment above a road. The wall carries the vertical load and horizontal thrust shown on an 8-ft base with no shear key. The engineer must check the wall for sliding, compute the toe pressure, and check the middle-third rule.
| Variable | Value | Description |
|---|---|---|
| ΣV | 18,000 lb/ft | |
| B | 8 ft | |
| P | 7,200 lb/ft | |
| e | 1.2 ft | |
| φ′base | 30° | No key, no adhesion |
(a) FS = 1.44, short of 1.5: add a shear key. (b) 4,275 psf. (c) e = 1.2 ft ≤ 1.33 ft: no tension at the heel.
A shear key under the base mobilizes passive resistance; it is usually cheaper than widening the base for sliding alone.
A 16-ft railroad retaining wall in a seismic area carries the static active thrust shown, and the design horizontal seismic coefficient is 0.28. The engineer must compute the seismic increment by the Seed and Whitman method and the moment it adds to the overturning check.
The method of Example 7.1-3.
| Variable | Value | Description |
|---|---|---|
| kh | 0.28 | |
| H | 16 ft | |
| PA | 5,500 lb/ft | Static |
| γ | 120 pcf (assumed) |
(a) 0.210. (b) 3,226 lb/ft. (c) 30,970 ft-lb/ft added to the static moment.
Compare: the static moment is 5,500 × 16/3 = 29,330 ft-lb/ft, so the seismic case slightly more than doubles it.
A Class I railroad needs an access road wall below its main line, and a reinforced soil wall with geogrid reinforcement has been proposed (the track itself is not carried on the wall). At 22 ft depth the fill properties, spacing, embedment and surcharge are as shown. The engineer must find the horizontal stress, the reinforcement load and the pullout factor of safety.
The method of Example 7.1-2.
| Variable | Value | Description |
|---|---|---|
| Fill | γ = 122 pcf, φ′ = 35° | |
| z | 22 ft | |
| Sv, Rc | 2.0 ft; 1.0 | |
| Le | 5.0 ft | |
| F*, α, C | 0.80 tanφ′; 0.8; 2 | |
| q | 400 psf | Surcharge |
(a) 835 psf. (b) 1,670 lb/ft. (c) Pr ≈ 12,000 lb/ft, FS ≈ 7.2.
With both faces of the grid counted (C = 2), pullout is rarely critical at depth; it governs near the top of the wall, where σ′v is small. Check the top layers too.
A soldier pile wall supporting a railroad embankment has the static and seismic overturning moments shown, with required factors of safety of 2.0 and 1.15. The engineer must find the minimum resisting moment the wall must provide and say which case governs.
| Variable | Value | Description |
|---|---|---|
| MOT,static | 95,000 ft-lb/ft | Target FS 2.0 |
| MOT,seismic | 155,000 ft-lb/ft | Target FS 1.15 |
ΣMR ≥ 190,000 ft-lb/ft; the static case governs here.
The seismic moment is larger, but the lower factor of safety allowed for the rare event means static still governs. Lengthening the base, typically from about 11 to 14 ft for a 22-ft cantilever wall, provides the extra lever arm.
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S11 under Supplemental References.
Related section: 7.1.5 Global Stability of Retaining Structures
In an extreme 2008 rainfall, 79 ft of a ten-year-old retaining wall, about 6.6 ft high, failed. The client proposed to condemn the remaining 328 ft as well, a replacement of over AU$1 million, because a back-analysis of the failure using saturated soil mechanics, a single-stage failure and a high water table gave the intact wall a factor of safety below 1.2 (Look, 2016).
The failed and intact sections were not alike:
No groundwater had ever been seen at this elevated road, and residents reported the failure developed over two days. Coupling finite element seepage with limit equilibrium showed that rainfall reduced soil suction rather than raising a water table. The three back-analyses led to three conclusions for the intact wall:
The intact wall had since come through several large storms with no distress. Look’s lessons: saturated and unsaturated analyses can disagree; back-analysis carries its assumptions into the result; a factor of safety is a decision tool, not an end in itself; and analysis is not design. A slope above a wall can raise active pressure by a factor of three, so the lowest wall is not necessarily the lowest load.
For railroad work: before parameters from a failed retaining wall or cut are applied to the rest of a structure, compare catchment, back slope, water sources and soil depth section by section. Antecedent rainfall, not daily rainfall alone, is the trigger to compare.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §13.12, pp. 484–490. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 7.1.12 Practical Recommendations
Look closes the design chapter with several short cases where the analysis was right but the detail or the input was not:
For railroad work: side-hill fills are among the most common chronic slide sites on mountain and river-grade lines. When one is rebuilt, the benching or keying detail matters as much as the stability analysis. Surcharge and unloading near buried utilities that cross the right-of-way need their own deflection check.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §13.13, pp. 490–494. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Excavations for bridge footings, culverts, utilities and grade separations often sit within the zone where train loads push on the excavation support. Two Class I railroads publish joint guidelines for temporary shoring that supplement AREMA. They cover clearances, the Cooper E80 lateral load, deflection limits, embedment and allowable stresses, and what must be submitted. Consistent with Chapter 7.1, soldier piles with lagging and sheet piles are the usual systems; trench boxes are not accepted where railroad surcharge is present, and tiebacks under the track are discouraged because they obstruct future utilities and must be removed.
Equation 7.1-3. E80 lateral pressure, resultant and point of action (Boussinesq strip)
q = 80,000/(5 × b) psf; X1,2 = S ∓ b/2; θ = arctan(X/H); β = θ2 − θ1; α = (θ1 + θ2)/2; moment at depth H = R(H − z).
| Item | Requirement |
|---|---|
| Clearance | No excavation closer than 12 ft to track centerline; otherwise shift or remove the track |
| Deflection, shoring 12 to 18 ft from centerline | 3/8 in. shoring; 1/4 in. rail (horizontal or vertical) |
| Deflection, shoring 18 to 24 ft from centerline | 1/2 in. shoring; 1/4 in. rail |
| Embedment | Equilibrium depth × about 1.3 for temporary shoring; anchored systems at least 1.5 times calculated embedment |
| Cantilever sheet piles | At least 12 ft from centerline; granular soils or stiff clays only |
| Other loads | 2 ft spoil surcharge; track 200 lb/ft; ballast 120 pcf; centrifugal force where curvature exceeds 3° |
| Allowable stresses | Steel 0.55Fy bending, 0.35Fy shear; sheet piles 2/3 Fy; concrete f'c/3; anchor rods Fy/2; no temporary-load increase |
| Operations | Flagman for work within 25 ft of centerline; monitor top of rail and alignment throughout |




| Type | Description | Unit weight (pcf) | φ |
|---|---|---|---|
| 1 | Clean sand, gravel or broken stone | 105 | 33 to 42° (38° broken stone) |
| 2 | Coarse-grained with silt | 110 | 30° |
| 3 | Fine silty sand; clayey granular; residual soil with stones | 125 | 28° |
| 4 | Soft clay, organic silt, soft silty clay (engineer's approval) | 100 | 0 (c = 0) |
| 5 | Medium or stiff clay kept dry (engineer's approval) | 120 | 0 (c = 240 psf) |
| Result | Value |
|---|---|
| E80 pressure at 6 ft | 558 psf |
| E80 resultant / moment at 6 ft | 2,214 lb/ft / 4,944 ft-lb/ft |
| Total force with earth and spoil | 3,314 lb/ft |
| Total moment at excavation base | 7,584 ft-lb/ft |
| Check against the guideline chart: S = 16 ft, H = 10 ft | 411 psf; 2,964 lb/ft; 11,385 ft-lb/ft |
The E80 values reproduce the guideline sample (558 psf, 2,214 lb/ft, z = 3.77 ft, 4,940 ft-lb/ft) and Chart A (411 psf, 2,964 lb/ft, 11,385 ft-lb/ft at S = 16 ft, H = 10 ft).
Note that the train load contributes most of the force at this shallow depth and that the pressure peaks a few feet down rather than at the top. The deflection limit of 3/8 in. at 12 ft from the track usually governs the soldier pile size more than stress does.
Open the temporary shoring calculator →
E80 Boussinesq lateral pressure, resultant and moment, active earth and spoil pressure, and the clearance, deflection and embedment criteria for shoring next to track.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.
Steel sheet piles are the usual choice where a cut next to track has to be made quickly, in soft or water-bearing ground, or where the wall will be pulled when the work is done. A cantilever wall stands on its embedment alone: the soil in front of the toe pushes back as passive resistance, and a reverse pressure develops near the tip as the wall rotates about a point a little above it. The European sheet piling handbooks in the library simplify that reverse pressure, following Blum, into a single force at the theoretical toe. Embedment comes from moment equilibrium about that point, and the depth is then increased by about 20% so the reverse pressure can actually develop. For permanent railroad walls the manual still assumes soldier piles with lagging; sheet piles are covered here for temporary shoring and for sites where soldier piles cannot be drilled or driven.
Equation 7.1-4. Blum equilibrium for a cantilever wall in cohesionless soil
t = u + x (Blum allowance Δt = 0.2t, driven length 1.2t); Mmax = M0 + 0.385·Q0·√m
Here Q0 and M0 are the shear and moment from the active pressure at the point of zero net pressure, a distance u below the dredge line, and x is the depth from that point to the theoretical toe. The handbook's worked example, in metric units, gives m = 9.90 and n = 20.14, which solve to x = 3.88 m, so the embedment is t = u + x = 4.46 m, to which Blum's driving allowance Δt = 0.2t = 0.89 m is added. The calculator does not rely on the closed form. It integrates the factored active pressure (Coulomb, with wall friction), any uniform surcharge, and the Boussinesq strip pressure from an E80 axle group (80,000 lb spread over 5 ft by the tie length) when track is behind the wall, and it solves ΣM = 0 about the toe by bisection. With no surcharge and no wall friction the numerical solution matches the Blum result to within 0.1%.
| Item | Value used | Basis |
|---|---|---|
| Active pressure | Coulomb Kah with δa = 2/3φ | Handbook practice for steel against soil |
| Passive pressure | Kph with δp = 0 (Rankine) unless test data support more, divided by 1.5 | Partial factor on resistance |
| Driving allowance | Δt = 0.2t (Blum) | Allows the reverse pressure to develop |
| Track live load | E80 strip, Boussinesq | Chapter 7.1 temporary shoring sections |
| Clearance to track | No excavation within 12 ft of centerline | Railroad temporary shoring guidelines |
| Corrosion, natural soil | about 0.01 mm (0.0004 in.) per year per exposed face | EAU 2004, as cited in the handbook |
A 10 ft cut in sand (γ = 120 pcf, φ = 32°) with a 250 psf construction surcharge and no track: Kah/Kph = 0.256 / 3.255, equilibrium embedment 11.47 ft, embedment with the Blum allowance 13.76 ft, maximum moment 19,844 ft-lb/ft and a required section modulus of 7.2 in.³/ft at 33.3 ksi. Put the same wall 13 ft from track centerline with the E80 strip in place of the 250 psf surcharge and the embedment grows to 21.35 ft, the moment to 71,179 ft-lb/ft and the section modulus to 25.7 in.³/ft. Train load, not the soil, sets the section. For a permanent wall the 50-year corrosion loss at the handbook rate is 0.040 in. of total thickness, which reduces the section modulus that remains at the end of its life.
Open the cantilever sheet pile calculator →
Coulomb pressures, E80 strip surcharge, numerical moment equilibrium for embedment, the Blum driving allowance, maximum moment, required section modulus and corrosion loss.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads, clients and projects are not named.
Compacting backfill behind a rigid wall locks in horizontal stress that can exceed the at-rest value near the top of the wall. Wetting a compacted clay backfill that cannot expand sideways raises it further. Both matter for abutments, culvert headwalls and walls that do not yield enough to reach the active state.
Equation 7.1-5. Compaction-induced lateral pressure envelope
Pickles (2012), Eqs. 64.1–64.3 and Fig. 64.6, p. 985. P = effective line load per unit length of the roller (lb/ft); γ = unit weight of the fill. The envelope rises along σh = σv/K0 to σ′h,m at zcr, stays at σ′h,m to hc, then follows K0σv.
Take P from the roller manufacturer's data (static weight plus dynamic force, per unit width of drum). Light plant near the wall keeps P, and so the locked-in pressure, small.
A clay backfill compacted dry and dense behind an unyielding wall is therefore the worst case: high locked-in compaction pressure followed by swelling pressure when it gets wet. Use free-draining granular backfill behind rigid walls and drain it (Section 7.1.6), and compact the zone next to the wall with light plant.
A cast-in-place culvert headwall 14 ft high is backfilled with granular fill compacted by a roller whose effective line load is 2,000 lb/ft. Find the compaction pressure envelope and compare the resultant with the at-rest and active thrusts.
| Variable | Value | Description |
|---|---|---|
| H | 14 ft | Wall height |
| P | 2,000 lb/ft | Effective roller line load |
| γ | 120 pcf | Backfill unit weight |
| φ′ | 32° | Backfill friction angle |
The compaction envelope controls the upper half of the wall, where the at-rest pressure would be only 86 to 390 psf. For a rigid headwall that is the pressure to design the stem for.
Using lighter compaction plant within a few feet of the wall reduces P and the envelope with it. Add the railroad surcharge (Section 7.1.3.1) and water pressure separately; the earth-pressure calculator now plots this envelope.
Open the earth pressure calculator →
Now includes an optional compaction-induced pressure envelope for a roller line load.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Soldier piles with lagging are this manual’s standard wall for stabilizing a slope or shoring an excavation next to track: the piles are driven or set in drilled holes from the shoulder, the lagging goes in as the face is excavated, and nothing has to be built behind the wall under the track. A cantilever wall relies only on the embedment of the piles below the excavation, so it suits retained heights up to about 10 to 15 ft; above that, or where deflection limits are tight, tiebacks or rakers are added (Section 7.1.4.7 for anchor bond). The analysis differs from a sheet pile wall (Section 7.1.18) in two ways. Above the excavation the lagging collects earth and surcharge pressure over the full pile spacing and delivers it to each pile. Below the excavation the pile is a discrete element and mobilizes passive resistance over more than its own width.
Driving load per pile per foot of depth is w = s(Kaγz + Kaq + σE80) above the excavation and b(Kaσv + Kaq + σE80) below it, where σE80 is the Cooper E80 strip pressure of Section 7.1.17 (Eq. 7.1-3). Passive resistance below the excavation follows Eq. 7.1-6 (discrete pile) or the arching factor below, divided by a factor of safety. The embedment D0 is found from moment equilibrium about the toe and increased by 20% (some guidelines 30%) for the reverse pressure near the toe, as for the sheet pile wall.
Equation 7.1-9. Passive resistance of a soldier pile by the arching factor
Caltrans Trenching and Shoring Manual; d = depth below the excavation; b = flange width or drilled-hole diameter; s = spacing. Railroad temporary shoring commonly applies FS = 1.5 to passive resistance.
Equation 7.1-10. Timber lagging thickness
p = design pressure behind the lagging (psf), reduced for soil arching where permitted; l = clear span between flanges (ft); M in lb-in. per ft of height; Fb = allowable bending stress of the timber (psi).
The maximum moment per pile occurs at the point of zero shear below the excavation; the required section modulus is M/fb. Deflection, not strength, usually governs next to track: the railroad shoring guidelines limit horizontal movement within the track influence zone, so check deflection with a beam-on-spring or p-y model, and add anchors where the cantilever is too flexible.
A 10-ft cut for a drainage structure on a Class I railroad located in Georgia is shored with a cantilever soldier pile wall whose face is 16 ft from the nearest track centerline. Piles are set in 24-in. drilled holes at 8-ft centers, with timber lagging.
| Variable | Value | Description |
|---|---|---|
| H | 10 ft | Retained height |
| s, b | 8 ft; 24 in. = 2.0 ft | Spacing; hole diameter |
| Retained soil | γ = 120 pcf, φ′ = 32° | Above the excavation |
| Embedment soil | γ = 125 pcf, φ′ = 34° | Dense sand below |
| q | 250 psf | Construction and spoil surcharge |
| E80 | 80,000/(5 × 9) = 1,778 psf strip, 9 ft wide | Track centerline 16 ft from the wall |
| FSp | 1.5 | On passive resistance |
| fb, Fb | 33 ksi; 1,000 psi | Pile; timber lagging |
A cantilever wall works in strength with 30-ft piles, a section of at least 165 in.³ (for example a W21×83 at 171 in.³ set in the drilled hole) and 5-in. lagging.
The train surcharge more than doubles the load on the wall, and the cantilever will be flexible: at 10 ft retained and 16 ft from track, expect deflection near the railroad’s limit. Run a deflection check before submitting; if it fails, a single row of tiebacks at about 3 ft below the top cuts both moment and deflection sharply. Where the railroad accepts a 0.6 arching factor on lagging pressure, the computed lagging falls to about 3.7 in., and 4-in. rough-cut boards would do.
Open the soldier pile wall calculator →
Active pressure over the spacing and the pile width, uniform and E80 strip surcharges, passive resistance by the arching factor or Eq. 7.1-6 (with softened clay), embedment by moment equilibrium, maximum moment, section modulus and lagging thickness.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.
Trenches for pipes and culverts across or along the track, and excavations for pits, vaults and foundations, are often supported by sheeting or soldier piles with internal struts or rakers. Because the bracing is installed from the top down as the excavation deepens, the wall cannot yield enough to develop the active state near the top, and the earth pressure is not triangular. Terzaghi and Peck measured strut loads in braced cuts and drew envelopes (“apparent pressure diagrams”) that bound them. The envelopes are not true pressure distributions: they are a design device for strut loads, wales and the spans between struts.
Equation 7.1-11. Apparent earth pressure envelopes (Peck, 1969)
H = excavation depth; m = 1.0 except where soft clay continues below the base (m = 0.4). Add surcharge pressure (uniform and the E80 strip of Section 7.1.17) and water pressure below the water table.
Strut loads are found by treating the wall as hinged at each strut below the top one, so that each span is a simple beam between struts. The cantilever above the top strut is carried by the top strut, and the span below the lowest strut is supported by the soil at the base. The strut load is the reaction per foot of wall times the horizontal strut spacing, and the wale moment is about P·s/10 for a wale continuous over several struts.
A 20-ft trench for a culvert extension next to a Class I railroad located in Texas is supported by sheeting with three levels of struts at 4, 11 and 17 ft, spaced 12 ft apart horizontally. The soil is medium dense sand above the water table, and the contractor’s equipment surcharge is 250 psf.
| Variable | Value | Description |
|---|---|---|
| H | 20 ft | Excavation depth |
| Struts | 4, 11 and 17 ft; s = 12 ft | Depth; horizontal spacing |
| Soil | γ = 120 pcf, φ′ = 32° | Sand |
| q | 250 psf, Kq = 0.33 | Uniform surcharge |
Design the top struts for about 51 kips, the middle for 44 kips and the bottom for 30 kips, and the top wale for about 61 kip-ft.
If the trench is within the track influence zone, add the E80 strip pressure (enter the track distance in the calculator); it adds most load to the upper struts. Preload the struts to about half their design load to limit movement under the track, and monitor the track surface while the trench is open.
Open the braced excavation calculator →
Apparent pressure envelopes for sand, soft clay and stiff clay with uniform and E80 surcharges, strut loads at each level by the hinge method, the base reaction and the wale moment.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.
Bottom heave. In soft to medium clay, the weight of the soil beside a braced cut can push the clay up into the bottom of the excavation. Bjerrum and Eide give:
FS = cu Nc / (γ H + q) ≥ 1.5
cu = undrained strength of the clay below the base (psf); Nc = bearing capacity factor that depends on the cut depth to width and length to width (about 5.1 for a long shallow cut, rising toward 9 for deep, square cuts); γ = unit weight (pcf); H = cut depth (ft); q = surcharge beside the cut (psf). If FS is too low, drive the sheeting deeper into firmer soil or reduce the surcharge.
Secant and tangent pile walls are rows of drilled shafts that touch (tangent) or overlap (secant). Secant walls cut off groundwater; tangent walls do not.
OSHA sloping (29 CFR 1926 Subpart P). For excavations less than 20 ft deep without a designed protective system, the maximum allowable slope depends on soil type:
| Type | Unconfined compressive strength | Maximum slope (H:V) |
|---|---|---|
| Stable rock | — | Vertical |
| A | 1.5 tsf or more | ¾:1 |
| B | 0.5 to 1.5 tsf | 1:1 |
| C | 0.5 tsf or less; granular, submerged or seeping soil | 1½:1 |
Deeper excavations, and any protective system outside the standard tables, must be designed by a registered professional engineer.
For railroad work: Soil that is fissured or subject to vibration from heavy traffic or similar sources cannot be classed as Type A, so excavations beside operating track are normally Type B or C and need flatter slopes or shoring designed for the train surcharge (Section 7.1.17). Check bottom heave for any braced cut in soft clay beside track, where the surcharge q includes the track and train load.
Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 209 (Support of Excavation) and Chapter 507 (Excavations). Full reference under Supplemental References.
Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.
Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.
File locations for these documents are listed under Supplemental References.
Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. The Case Studies section summarizes case studies from item S11 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.
The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.