Chapter 7.1 — Retaining Structures

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel

Geotechnical Services Manual for Railroad Clients

A Consultant's Reference for Delivering Geotechnical Engineering Services Across North American Railroad Capital Programs

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Interface, strength and unit weight values for earth pressure and wall design (soldier pile and lagging walls). English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Interface friction and adhesion (28 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Friction coefficient, mass concrete on soil/rockClean sound rock0.7–CB T11.1, p.208
Friction coefficient, mass concrete on soil/rockClean gravel, gravel–sand mixtures, coarse sand0.550.5750.6–CB T11.1, p.208
Friction coefficient, mass concrete on soil/rockClean fine to medium sand, silty medium to coarse sand, silty or clayey gravel0.450.50.55–CB T11.1, p.208
Friction coefficient, mass concrete on soil/rockClean fine sand, silty or clayey fine to medium sand0.350.40.45–CB T11.1, p.208
Friction coefficient, mass concrete on soil/rockFine sandy silt, non-plastic silt0.30.3250.35–CB T11.1, p.208
Friction coefficient, mass concrete on soil/rockVery stiff and hard residual or overconsolidated clay0.40.450.5–CB T11.1, p.208
Friction coefficient, mass concrete on soil/rockStiff clay and silty clay0.30.3250.35–CB T11.1, p.208
Friction coefficient, steel sheet pilesClean gravel, gravel–sand mixtures, well-graded rock fill0.4–CB T11.1, p.208
Friction coefficient, steel sheet pilesClean sand, silty sand–gravel mixtures, single-size hard rock fill0.3–CB T11.1, p.208
Friction coefficient, steel sheet pilesSilty sand, gravel or sand mixed with silt or clay0.25–CB T11.1, p.208
Friction coefficient, steel sheet pilesFine sandy silt, non-plastic silt0.2–CB T11.1, p.208
Adhesion, steel sheet pilesSoft clay and clayey silt104365.5627psfCB T11.1, p.208
Adhesion, steel sheet pilesStiff and hard clay and clayey silt6279401,253psfCB T11.1, p.208
Friction coefficient, formed concrete / concrete sheet pilingClean gravel, gravel–sand mixtures, well-graded rock fill0.40.450.5–CB T11.1, p.208
Friction coefficient, formed concrete / concrete sheet pilingClean sand, silty sand–gravel mixtures, single-size hard rock fill0.30.350.4–CB T11.1, p.208
Friction coefficient, formed concrete / concrete sheet pilingSilty sand, gravel or sand mixed with silt or clay0.3–CB T11.1, p.208
Friction coefficient, formed concrete / concrete sheet pilingFine sandy silt, non-plastic silt0.25–CB T11.1, p.208
Adhesion, formed concrete / concrete sheet pilingSoft clay and clayey silt209470731psfCB T11.1, p.208
Adhesion, formed concrete / concrete sheet pilingStiff and hard clay and clayey silt7319921,253psfCB T11.1, p.208
Coefficient of horizontal soil stress on pile shaft, Ks/KoDriven piles, large displacementCoarse-grained soil11.52–TOMLINSON T4.10, p.172
Coefficient of horizontal soil stress on pile shaft, Ks/KoDriven piles, small displacementCoarse-grained soil0.7511.25–TOMLINSON T4.10, p.172
Coefficient of horizontal soil stress on pile shaft, Ks/KoBored and cast-in-place pilesCoarse-grained soil0.70.851–TOMLINSON T4.10, p.172
Coefficient of horizontal soil stress on pile shaft, Ks/KoJetted pilesCoarse-grained soil0.50.60.7–TOMLINSON T4.10, p.172
Pile–soil interface friction ratio, δ/φ'Smooth (coated) steel / sand0.50.60.7–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Rough (corrugated) steel / sand0.70.80.9–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Precast concrete / sand0.80.91–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Cast-in-place concrete / sand1–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Timber / sand0.80.850.9–TOMLINSON T4.11, p.172
Open this set in the database ↗
Rock anchor (tieback) allowable rock–grout bond stress (10 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Allowable rock–grout bond stress, cement-grouted anchorStrong rock (UCS > 14,500 psi)152177.5203psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorMedium rock (UCS 7,250–14,500 psi)102127152psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorWeak rock (UCS 2,900–7,250 psi)5176.5102psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorGranite, basalt80112.5145psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorDolomitic limestone6583.5102psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorSoft limestone516273psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorSlates, strong shales4454.565psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorWeak shales725.544psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorSandstone4465.587psiWYLLIE T12.8, p.297
Allowable rock–grout bond stress, cement-grouted anchorConcrete6598131psiWYLLIE T12.8, p.297
Open this set in the database ↗
Granular friction angle (47 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Friction angleGravelsGW-SPVery loose / loose303234degLOOK T7.8, p.107
Friction angleGravelsGW-SPMedium dense3436.539degLOOK T7.8, p.107
Friction angleGravelsGW-SPDense3941.544degLOOK T7.8, p.107
Friction angleGravelsGW-SPVery dense4446.549degLOOK T7.8, p.107
Friction angleSandsGW-SPVery loose / loose2729.532degLOOK T7.8, p.107
Friction angleSandsGW-SPMedium dense3234.537degLOOK T7.8, p.107
Friction angleSandsGW-SPDense3739.542degLOOK T7.8, p.107
Friction angleSandsGW-SPVery dense4244.547degLOOK T7.8, p.107
Friction angleSandsGW-SPLoose, uniformly graded2728.530degLOOK T7.8, p.107
Friction angleSandsGW-SPLoose, well graded303132degLOOK T7.8, p.107
Friction angleSandsGW-SPDense, uniformly graded3738.540degLOOK T7.8, p.107
Friction angleSandsGW-SPDense, well graded404142degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillSoft sedimentary303540degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillHard sedimentary354045degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillMetamorphic354045degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillIgneous404550degLOOK T7.8, p.107
Friction angle from SPTClean medium sandSP / SWVery loose (N ≤ 4)28degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWLoose (N = 4–10)282930degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWMedium dense (N = 10–30)303540degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWDense (N = 30–50)4042.545degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWVery dense (N > 50)4547.550degLOOK T5.4, p.80
Friction angleUniform sand, round grainsLoose27degCB T6.4, p.159
Friction angleUniform sand, round grainsDense34degCB T6.4, p.159
Friction angleWell-graded sand, angular grainsLoose33degCB T6.4, p.159
Friction angleWell-graded sand, angular grainsDense45degCB T6.4, p.159
Friction angleSandy gravelLoose35degCB T6.4, p.159
Friction angleSandy gravelDense50degCB T6.4, p.159
Friction angleSilty sandLoose273033degCB T6.4, p.159
Friction angleSilty sandDense303234degCB T6.4, p.159
Friction angleInorganic siltLoose2728.530degCB T6.4, p.159
Friction angleInorganic siltDense3032.535degCB T6.4, p.159
Friction angle (compacted)Well-graded sand–gravelGWCompacted to standard Proctor MDD38degCB T6.5, p.159
Friction angle (compacted)Poorly graded sand–gravelGPCompacted to standard Proctor MDD37degCB T6.5, p.159
Friction angle (compacted)Silty gravelsGMCompacted to standard Proctor MDD34degCB T6.5, p.159
Friction angle (compacted)Clayey gravelsGCCompacted to standard Proctor MDD31degCB T6.5, p.159
Friction angle (compacted)Well-graded clean sandSWCompacted to standard Proctor MDD38degCB T6.5, p.159
Friction angle (compacted)Poorly graded clean sandSPCompacted to standard Proctor MDD37degCB T6.5, p.159
Effective friction angle (compacted)Silty sands, sand–silt mixSMCompacted to standard Proctor MDD34degCB T6.3, p.158
Effective friction angle (compacted)Clayey sands, sand–clay mixSCCompacted to standard Proctor MDD31degCB T6.3, p.158
Effective friction angle (compacted)Silts and clayey siltsMLCompacted to standard Proctor MDD32degCB T6.3, p.158
Effective friction angle (compacted)Clays of low plasticityCLCompacted to standard Proctor MDD28degCB T6.3, p.158
Effective friction angle (compacted)Clayey silts, elastic siltsMHCompacted to standard Proctor MDD25degCB T6.3, p.158
Effective friction angle (compacted)Clays of high plasticityCHCompacted to standard Proctor MDD19degCB T6.3, p.158
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHSoft – organic101520degLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHSoft – non-organic152025degLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHStiff202530degLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHHard2527.530degLOOK T7.9, p.107
Open this set in the database ↗
Unit weight (34 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Dry unit weightSands and gravelsGW-SPVery loose89.1pcfLOOK T7.3, p.104
Saturated unit weightSands and gravelsGW-SPVery loose108.2pcfLOOK T7.3, p.104
Dry unit weightSands and gravelsGW-SPLoose95.5pcfLOOK T7.3, p.104
Saturated unit weightSands and gravelsGW-SPLoose114.6pcfLOOK T7.3, p.104
Dry unit weightSands and gravelsGW-SPMedium dense108.2pcfLOOK T7.3, p.104
Saturated unit weightSands and gravelsGW-SPMedium dense127.3pcfLOOK T7.3, p.104
Dry unit weightSands and gravelsGW-SPDense121pcfLOOK T7.3, p.104
Saturated unit weightSands and gravelsGW-SPDense133.7pcfLOOK T7.3, p.104
Dry unit weightSands and gravelsGW-SPVery dense133.7pcfLOOK T7.3, p.104
Saturated unit weightSands and gravelsGW-SPVery dense140pcfLOOK T7.3, p.104
Dry unit weightSandsSP / SWLoose, uniformly graded89.1pcfLOOK T7.3, p.104
Saturated unit weightSandsSP / SWLoose, uniformly graded108.2pcfLOOK T7.3, p.104
Dry unit weightSandsSP / SWLoose, well graded101.9pcfLOOK T7.3, p.104
Saturated unit weightSandsSP / SWLoose, well graded121pcfLOOK T7.3, p.104
Dry unit weightSandsSP / SWDense, uniformly graded114.6pcfLOOK T7.3, p.104
Saturated unit weightSandsSP / SWDense, uniformly graded127.3pcfLOOK T7.3, p.104
Dry unit weightSandsSP / SWDense, well graded121pcfLOOK T7.3, p.104
Saturated unit weightSandsSP / SWDense, well graded133.7pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHSoft – organic50.9pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHSoft – organic89.1pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHSoft – non-organic76.4pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHSoft – non-organic101.9pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHStiff101.9pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHStiff114.6pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHHard114.6pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHHard127.3pcfLOOK T7.3, p.104
Dry unit weightBroken rock – soft sedimentary (chalk, shale, siltstone, coal)RockfillCompacted76.4pcfLOOK T7.3, p.104
Saturated unit weightBroken rock – soft sedimentary (chalk, shale, siltstone, coal)RockfillCompacted114.6pcfLOOK T7.3, p.104
Dry unit weightBroken rock – hard sedimentary (conglomerate, sandstone)RockfillCompacted89.1pcfLOOK T7.3, p.104
Saturated unit weightBroken rock – hard sedimentary (conglomerate, sandstone)RockfillCompacted121pcfLOOK T7.3, p.104
Dry unit weightBroken rock – metamorphicRockfillCompacted114.6pcfLOOK T7.3, p.104
Saturated unit weightBroken rock – metamorphicRockfillCompacted127.3pcfLOOK T7.3, p.104
Dry unit weightBroken rock – igneousRockfillCompacted108.2pcfLOOK T7.3, p.104
Saturated unit weightBroken rock – igneousRockfillCompacted133.7pcfLOOK T7.3, p.104
Open this set in the database ↗
Corrosion screening: resistivity and groundwater aggressiveness (26 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Electrical resistivityFresh water1,000,000ohm-cmFGE T24.5, p.363
Electrical resistivitySea water100300500ohm-cmFGE T24.5, p.363
Electrical resistivityCoarse sand and gravel, dry2,000,0005,000,0008,000,000ohm-cmFGE T24.5, p.363
Electrical resistivityCoarse sand and gravel, saturated100,000300,000500,000ohm-cmFGE T24.5, p.363
Electrical resistivitySand, dry500,0001,250,0002,000,000ohm-cmFGE T24.5, p.363
Electrical resistivitySand, saturated20,00060,000100,000ohm-cmFGE T24.5, p.363
Electrical resistivitySilt, dry40,000120,000200,000ohm-cmFGE T24.5, p.363
Electrical resistivitySilt, saturated3,00011,50020,000ohm-cmFGE T24.5, p.363
Electrical resistivityClay, saturated1,5002,2503,000ohm-cmFGE T24.5, p.363
Electrical resistivitySandstone10,000405,000800,000ohm-cmFGE T24.5, p.363
Electrical resistivityGranite, gneiss700,0001,100,0001,500,000ohm-cmFGE T24.5, p.363
Electrical resistivityConcrete, gabbro1,000,0002,500,0004,000,000ohm-cmFGE T24.5, p.363
Electrical resistivityQuartzite500,000750,0001,000,000ohm-cmFGE T24.5, p.363
Groundwater aggressiveness – chlorideGroundwaterMild05001,000mg/LFGE T24.4, p.361
Groundwater aggressiveness – sulfate / sulfiteGroundwaterMild075150mg/LFGE T24.4, p.361
Groundwater aggressiveness – chlorideGroundwaterModerate1,0003,0005,000mg/LFGE T24.4, p.361
Groundwater aggressiveness – sulfate / sulfiteGroundwaterModerate1508251,500mg/LFGE T24.4, p.361
Groundwater aggressiveness – chlorideGroundwaterSevere5,000mg/LFGE T24.4, p.361
Groundwater aggressiveness – sulfate / sulfiteGroundwaterSevere1,5005,75010,000mg/LFGE T24.4, p.361
Groundwater aggressiveness – sulfate / sulfiteGroundwaterVery severe10,000mg/LFGE T24.4, p.361
Indicator of corrosive groundwaterpHCorrosive when below (corrosive)7–UFC T3-3, p.3-5
Indicator of corrosive groundwaterDissolved oxygenCorrosive when above2ppmUFC T3-3, p.3-5
Indicator of corrosive groundwaterHydrogen sulfideCorrosive when above1ppmUFC T3-3, p.3-5
Indicator of corrosive groundwaterTotal dissolved solidsCorrosive when above1,000ppmUFC T3-3, p.3-5
Indicator of corrosive groundwaterCarbon dioxideCorrosive when above50ppmUFC T3-3, p.3-5
Indicator of corrosive groundwaterChloridesCorrosive when above500ppmUFC T3-3, p.3-5
Open this set in the database ↗
Railroad temporary shoring criteria (a Class I railroad) and E80 surcharge (15 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
E80 strip surcharge for lateral (Boussinesq) pressureTrack, 9-ft tiesA Class I railroad shoring guideline1,778psfRRSHORE App. A, p.A-1
E80 strip surcharge for lateral (Boussinesq) pressureTrack, 8.5-ft tiesClass I railroad pipeline specification1,882psfRRPIPE1 T3.2.3, p.13
Minimum distance, track centerline to trackside of shoringTemporary shoring (a Class I railroad)No excavation closer12ftRRSHORE T6.1, §6.1
Maximum horizontal movement of temporary shoringTemporary shoring (a Class I railroad)12–18 ft from track centerline0.375inRRSHORE T1, §8.6
Maximum horizontal or vertical movement of railTemporary shoring (a Class I railroad)12–18 ft from track centerline0.25inRRSHORE T1, §8.6
Maximum horizontal movement of temporary shoringTemporary shoring (a Class I railroad)18–24 ft from track centerline0.5inRRSHORE T1, §8.6
Maximum horizontal or vertical movement of railTemporary shoring (a Class I railroad)18–24 ft from track centerline0.25inRRSHORE T1, §8.6
Embedment factor of safety, temporary shoringTemporary shoring (a Class I railroad)1.3–RRSHORE text, §8.1
Anchored shoring – minimum embedment as multiple of calculated depthTemporary shoring (a Class I railroad)1.5×RRSHORE text, §8.1
Track dead load (rails, guardrails, fasteners)Temporary shoring (a Class I railroad)200lb/ftRRSHORE text, §7.2
Roadbed dead load (ballast with ties)Temporary shoring (a Class I railroad)120pcfRRSHORE text, §7.2
Minimum spoil pile height to include in designTemporary shoring (a Class I railroad)2ftRRSHORE text, §7.2
Track curvature above which centrifugal force must be addedTemporary shoring (a Class I railroad)3degRRSHORE text, §7.8
Steepest unshored slope on railroad propertyTemporary shoring (a Class I railroad)2H per 1VRRSHORE text, §10
Backfill compaction near shoringTemporary shoring (a Class I railroad)Modified Proctor (ASTM D1557), within 2% of optimum95%RRSHORE T9.4, §9.4
Open this set in the database ↗
References (9)
  1. CB – Carter, M. & Bentley, S.P. (2016). Soil Properties and their Correlations, 2nd ed. Wiley.
  2. RRPIPE1 – A Class I railroad (2018). Specifications for the Design and Construction of Pipeline Occupancies (revised June 5, 2018).
  3. DASDYN – Das, B.M. & Ramana, G.V. (2011). Principles of Soil Dynamics, 2nd ed. Cengage Learning.
  4. FGE – Rao, V.V.S. & Sivakumar Babu, G.L., eds. (2016). Forensic Geotechnical Engineering. Developments in Geotechnical Engineering. Springer India.
  5. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.
  6. TOMLINSON – Tomlinson, M. & Woodward, J. (2008). Pile Design and Construction Practice, 5th ed. Taylor & Francis.
  7. UFC – U.S. Department of Defense (2004). UFC 3-220-05, Dewatering and Groundwater Control (16 January 2004).
  8. RRSHORE – Two Class I railroads (2004). Guidelines for Temporary Shoring (published October 25, 2004).
  9. WYLLIE – Wyllie, D.C. & Mah, C.W. (2004). Rock Slope Engineering: Civil and Mining, 4th ed. Spon Press.
Correlations (3)
EstimateCorrelationLimits / notesSource
E80 lateral pressure on shoring (Boussinesq strip)σh = (2q/π)(β − sin β cos 2α); q = 80,000/(5 × tie length) psfβ and α are angles to the edges of the tie strip; q = 1778 psf for 9-ft tiesRRSHORE App. A, p.A-1
Grouted anchor bond lengthLb = T·FS / (π d τa)T = design load, d = drill hole diameter, τa = allowable rock–grout bond stress (Table 12.8)WYLLIE T12.8, p.297
Mononobe–Okabe active earth pressurePAE = ½γH²(1 − kv)KAE; KAE = cos²(φ−θ−β) / {cosθ cos²β cos(δ+β+θ)[1 + √(sin(φ+δ)sin(φ−θ−i)/(cos(δ+β+θ)cos(i−β)))]²}; θ = tan⁻¹[kh/(1−kv)]β = wall back batter from vertical, i = backfill slope; no real solution when φ − θ − i < 0DASDYN Eq. 8.4–8.6, p.332–333
All correlations ↗

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

After a failure: see Forensic Investigation of Ground Failures (Chapter 17) for what to record, how to scope the investigation, back analysis and vibration claims.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
7.1.0 Executive Summary

Retaining structures are among the most consequential geotechnical elements in railroad capital programs. They support embankments, protect cut slopes, carry track surcharge loads, and define the geometric boundary of right-of-way through urban corridors, bridge approaches, and intermodal facilities. Failures are costly, disruptive, and — given the dynamic loading environment of heavy-haul freight — potentially catastrophic.

This chapter presents the geotechnical design framework for retaining structures in railroad service, organized around the requirements common to owner railroads and grounded in AREMA Manual for Railway Engineering (MRE) Chapter 8 retaining structure provisions and USACE EM 1110-1-1804. We address lateral earth pressure theory (Rankine, Coulomb, at-rest), surcharge loading from Cooper E-80 trains, wall type selection, global stability, drainage, seismic earth pressure by the Mononobe-Okabe method, and client-specific deliverable requirements. All equations are expressed in English units.

Rankine's Lateral Earth Pressure
Rankine's Lateral Earth Pressure
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-09 At-rest earth pressure coefficient K₀Use: Uncemented soils on primary unloading. Limits: Not valid on reloading or for compacted fills, where K0 is governed by compaction stresses. Cap at passive limit.
Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
IX-09At-rest earth pressure coefficientK₀
IS-04Friction angle of sand from SPT (Schmertmann form)φ'
IS-05Friction angle of sand from SPT (Peck–Hanson–Thornburn)φ'
IX-08Friction angle of NC clay from plasticityφ'
7.1.1 Background and Railroad Context

Railroad retaining walls differ from highway walls in three important ways:

  1. Live load surcharge is defined and cyclic. Cooper E-80 loading produces a dynamic, cyclic surcharge that must be treated with a dynamic load factor (DLF) and is not a simple static equivalent. AREMA MRE Chapter 8 distributes the E-80 axle loads into the backfill and computes the lateral pressure by elastic (Boussinesq-type) methods. A uniform equivalent surcharge is a simplification, and the consultant must show it is conservative for the geometry.
  2. Settlement tolerance is tight. FRA 49 CFR Part 213 Class 4 and higher track limits differential settlement at bridge approaches and wall abutments to values that drive serviceability, not strength. A wall that is structurally adequate but settles unevenly will trigger ride quality defects and progressive ballast degradation.
  3. Right-of-way is constrained. Railroad corridors through urban areas, bridge approaches, and intermodal terminals often permit no room for tieback anchors in third-party property, no room for sloped embankments, and no room for mechanically stabilized earth (MSE) fills beyond tight geometric limits. Wall selection is as much a right-of-way and constructability problem as a geotechnical one.

AREMA MRE Chapter 8, Part 5 (Retaining Walls, Abutments and Piers) provides the design basis for railroad retaining walls. Owner railroads generally require AREMA Chapter 8 compliance as a minimum, with their own modifications. Wall design calculations are normally signed and sealed by a Professional Engineer licensed in the project state. Check walls seismically where the owner railroad or the building code requires it. In cold regions, check frost penetration for all walls.

7.1.2 Lateral Earth Pressure Theory
7.1.2.1 At-Rest Earth Pressure

For walls that cannot deflect (rigid basement walls, integral abutments, braced excavations), the at-rest coefficient is used:

K₀ = 1 − sin φ' (normally consolidated soils) [Jaky, 1944]

For overconsolidated soils:

K₀(OC) = K₀(NC) × OCR^(sin φ')

The at-rest horizontal earth pressure at depth z is:

σ_h0 = K₀ × γ × z (psf)

where:

  • K₀ = at-rest lateral earth pressure coefficient (dimensionless)
  • γ = moist unit weight of retained soil (pcf)
  • z = depth below top of retained earth (ft)
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-09 At-rest earth pressure coefficient K₀Use: Uncemented soils on primary unloading. Limits: Not valid on reloading or for compacted fills, where K0 is governed by compaction stresses. Cap at passive limit.
Passive Earth Pressure
Passive Earth Pressure
Inputs for the equations in this section (6)
SymbolWhat it isComes fromHow to get itTypical range
K₀1 − sin φ' (normally consolidated soils) [Jaky, 1944]Another equationK0 = 1 − sin φ' (NC), × OCRsin φ' for OC soil (Jaky; Mayne & Kulhawy). Field: DMT or self-boring pressuremeter.0.35–0.65 NC · by USCS group
K₀(OC)K₀(NC) × OCR^(sin φ')Another equationK0 = 1 − sin φ' (NC), × OCRsin φ' for OC soil (Jaky; Mayne & Kulhawy). Field: DMT or self-boring pressuremeter.0.35–0.65 NC · by USCS group
γmoist unit weight of retained soil (pcf)Lab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
zdepth below top of retained earth (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
OCRpreconsolidation stress / OCRLab test (or correlation)Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0.OCR 1 (NC) to > 4 (heavily OC) · by USCS group
7.1.2.2 Rankine Active and Passive Pressure

Rankine theory assumes a smooth, vertical wall with a horizontal backfill surface. It is the most commonly applied method for preliminary design and is the usual starting point for walls with a vertical back and level backfill.

K_A = tan²(45° − φ'/2)

K_P = tan²(45° + φ'/2)

Active pressure at depth z:

σ_A = K_A × γ × z − 2c' × √K_A (psf)

Passive pressure at depth z:

σ_P = K_P × γ × z + 2c' × √K_P (psf)

For purely cohesionless backfill (c' = 0, the standard AREMA design assumption):

σ_A = K_A × γ × z

σ_P = K_P × γ × z

Total active force per linear foot of wall (triangular distribution):

P_A = ½ × K_A × γ × H² (lb/ft)

Acting at H/3 above the base for triangular pressure distribution.

Inputs for the equations in this section (7)
SymbolWhat it isComes fromHow to get itTypical range
KAintermediate value computed on this pageAnother equationComputed: K_A = tan²(45° − φ'/2)project-specific
KPintermediate value computed on this pageAnother equationComputed: K_P = tan²(45° + φ'/2)project-specific
σAintermediate value computed on this pageAnother equationComputed: σ_A = K_A × γ × z − 2c' × √K_A (psf)project-specific
σPintermediate value computed on this pageAnother equationComputed: σ_P = K_P × γ × z + 2c' × √K_P (psf)project-specific
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
c'effective cohesionLab testEffective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more.0–300 psf · by USCS group
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
7.1.2.3 Coulomb Active and Passive Pressure

Coulomb theory accounts for wall friction (δ) and backfill slope angle (β). Use it for sloped backfills and battered walls:

K_A(Coulomb) = sin²(α + φ') / { sin²α × sin(α − δ) × [1 + √( sin(φ' + δ) × sin(φ' − β) / (sin(α − δ) × sin(α + β)) )]² }

where:

  • α = angle of back face of wall with horizontal (= 90° for vertical wall) (degrees)
  • φ' = effective friction angle of retained soil (degrees)
  • δ = wall friction angle (degrees); δ = ⅔ φ' is a common design value
  • β = slope angle of retained fill surface (degrees)

For the common case of a vertical wall (α = 90°) retaining horizontal fill (β = 0°):

K_A(Coulomb) = cos²φ' / { cos δ × [1 + √(sin(φ' + δ) × sin φ' / cos δ)]² }

Note: Coulomb passive pressure is non-conservative for walls with significant wall friction; use Rankine passive or log-spiral methods for passive resistance calculations.

Inputs for the equations in this section (5)
SymbolWhat it isComes fromHow to get itTypical range
KA(Coulomb)intermediate value computed on this pageAnother equationComputed: K_A(Coulomb) = sin²(α + φ') / { sin²α × sin(α − δ) × [1 + √( sin(φ' + δ) × sin(φ' − β) / (sin(α − δ) × sin(α + β)) )]² }project-specific
αangle of back face of wall with horizontal (= 90° for vertical wall) (degrees)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
φ'effective friction angle of retained soil (degrees)Lab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
δwall friction angle (degrees)Lab test (or fraction of φ')Interface direct shear (ASTM D5321); otherwise δ = 0.6–1.0 φ' depending on the surface (steel, concrete, geosynthetic).0.6–1.0 φ' · by USCS group
βslope angle of retained fill surface (degrees)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
7.1.2.4 Tension Crack

In cohesive soils, tension cracking reduces the effective retained height. The tension crack depth is:

z_c = 2c' / (γ × √K_A) (ft)

For design, assume the tension crack is filled with water (worst case). The net active pressure diagram excludes the tension zone, and an additional hydrostatic pressure acts over depth z_c.

Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
c'effective cohesionLab testEffective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more.0–300 psf · by USCS group
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
7.1.3 Surcharge Loading — Cooper E-80 Train Load

AREMA MRE Chapter 8 allows train live load to be represented as an equivalent uniform surcharge on top of the retained fill for wall design:

q_LL = Cooper E-80 wheel load equivalent uniform pressure (psf)

For a rough first check of walls well away from the track, some designers use a uniform surcharge such as:

q_LL = 400 psf (simplified value; not an AREMA value)

Near the track this badly understates the load. AREMA represents the E-80 axle as a strip of about 1,882 psf (80 kips over 5 ft × 8.5 ft) and computes lateral pressure with the strip-load formula (see the box below and Section 7.1.3.1).

This is multiplied by an assumed DLF = 1.3 for dynamic effects, giving a design surcharge:

q_design = DLF × q_LL = 1.3 × 400 = 520 psf

The additional horizontal pressure from this surcharge using Rankine:

Δσ_A(surcharge) = K_A × q_design (psf, uniform with depth)

The resultant surcharge force per foot of wall:

ΔP_surcharge = K_A × q_design × H (lb/ft)

Acting at H/2 above the base (uniform pressure diagram).

For walls within 15 ft of the track centerline (measured horizontally), owner railroads may require a more detailed Boussinesq-based pressure distribution using the actual axle loads rather than the simplified equivalent surcharge.

Supplemental reference

Owner shoring criteria: much higher than a uniform equivalent surcharge

For excavation support next to active track, a Class I railroad (Public Projects Manual, 2020) requires shoring to be designed for active earth pressure plus a live-load surcharge of 1,882 psf on a continuous strip 8.5 ft wide, with lateral pressure computed by the strip-load formula in AREMA MRE Chapter 8, Part 20. (1,882 psf equals an 80-kip E-80 axle spread over 5 ft of track length and 8.5 ft of width.) This is more than three times the 400-psf uniform value in Section 7.1.3 and, as a strip load, it concentrates pressure in the upper part of the wall. Use the owner’s criterion wherever it applies, and treat the 400-psf equivalent as a preliminary-sizing number only.

Track Load Transfer
Track Load Transfer

Other Class I railroad shoring rules: shoring may be omitted only if the excavation stays outside a 1H:1V line from the bottom corner of the tie and the track is on level ground or in a cut on stable soil. Excavating the toe of an embankment carrying track is not allowed without shoring. Full cofferdams (steel sheeting, or soldier piles and lagging, with wales and struts) are preferred; partial cofferdams open on the side away from the track are allowed where conditions dictate.

Source: A Class I railroad (2020). Public Projects Manual, December 2020 (shoring requirements adjacent to track)

7.1.3.1 Earth Pressure with Railroad Surcharge

The library's notes on lateral earth pressure give the Rankine and Coulomb coefficients; the railroad problem adds a large, concentrated surcharge from the track. A wall retaining track within a few feet of the tie ends carries more load from the train than from the soil itself, and the load peaks a few feet below the top of the wall, not at the base. The manual's practice for walls retaining track is soldier piles with lagging rather than MSE walls (Chapter 7.1 and the project preferences), and the same pressure diagram is used to size the piles and lagging.

7.1.3.1.1 Method

Equation 7.1-1. Coulomb active coefficient (vertical wall back)

Ka = cos²φ / {cosδ [1 + √(sin(φ + δ) sin(φ − β) / (cosδ cosβ))]²}

with δ = 0 and β = 0 this reduces to the Rankine value tan²(45° − φ/2).

Equation 7.1-2. Lateral pressure from a strip surcharge (Boussinesq)

σh = (2qs/π)(βs − sinβs cos2α) for an unyielding wall; half this value in an elastic half-space

where βs is the angle subtended by the strip at the point and α the angle to the strip centerline.

Table 7.1-4. Railroad strip surcharge assumed in the calculator
ItemDefaultBasis
Axle load80 kipsCooper E80 design axle
Distribution along track5 ftAxle spacing of the E80 driver group
Distribution across track8.5 ftTie length
Strip pressure qsabout 1,880 psf80,000 lb / (5 ft × 8.5 ft); add impact as the governing standard requires
OffsetEnteredWall face to near end of ties

7.1.3.1.2 Worked example: soldier pile wall beside main track

Table 7.1-5. 14-ft wall, granular backfill, track 4 ft from the wall (calculator output)
Load componentThrustNotes
Soil, Coulomb Ka = 0.2753.02 kips/ftφ' = 32°, δ = 21°, γ = 120 pcf
Railroad strip surcharge7.55 kips/ft1,880 psf over 8.5 ft, unyielding-wall solution
Total10.57 kips/ftacting 6.79 ft above the base

Without the train the same wall carries only 3.02 kips/ft, acting at H/3. The surcharge raises the resultant and more than triples the thrust, so the moment in the piles is governed by the railroad load. For a flexible soldier pile wall some designers use the half-space solution (half the surcharge pressure); the calculator offers both so the choice is explicit.

Open the earth pressure calculator →
Rankine or Coulomb coefficients, water, uniform surcharge and an E80-type strip surcharge; pressure diagram, thrust, resultant height and overturning moment.

7.1.3.1.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.

  • Lateral Earth Pressure and Lateral Earth Pressure 2 (course notes): Rankine and Coulomb theory.Find source ↗Library entry
  • On the Theory of Ground Anchors (book): tieback design for anchored soldier pile walls.Find source ↗
  • Stresses in Soil due to Surface Loads and Boussinesq and Westergaard Stresses (lecture notes), Shear Stress folder: strip load solution.Find source ↗Library entry
  • Soil Retaining Structures: Development of Models for Structural Analysis (Soil Mechanics folder).Find source ↗
7.1.4 Wall Types and Selection
7.1.4.1 Gravity Walls

Gravity walls resist sliding and overturning through their own mass. Common materials include mass concrete and dry-laid or mortared stone masonry. Practical retained height limit is approximately 12–15 ft for mass concrete.

Retaining Walls
Retaining Walls
Gravity Retaining Wall
Gravity Retaining Wall

Factor of Safety Against Sliding:

FS_sliding = (W × tan δ_base + c_base × B) / P_A_total ≥ 1.5 (AREMA Ch. 8)

where:

  • W = total vertical weight of wall + retained soil on heel (lb/ft)
  • δ_base = friction angle at base (degrees); typically φ' of foundation soil or 0.9φ' for concrete-on-soil
  • c_base = base adhesion (psf)
  • B = base width (ft)
  • P_A_total = total active force including surcharge (lb/ft)
Crib Retaining Wall
Crib Retaining Wall
MSE Wall — SeaTac Airport Runway Extension
MSE Wall — SeaTac Airport Runway Extension

Factor of Safety Against Overturning:

FS_OT = ΣM_resisting / ΣM_overturning ≥ 2.0 (AREMA Ch. 8)

Resultant Eccentricity:

e = B/2 − (ΣM_resisting − ΣM_overturning) / ΣV (ft)

For no tension at the base, the middle-third rule requires:

e ≤ B/6

This is the usual requirement for gravity and cantilever walls on soil supporting track; confirm the owner railroad's criterion (rock foundations may allow more eccentricity).

Bearing Pressure at Toe:

q_toe = (ΣV/B) × (1 + 6e/B) (psf)

Bearing Pressure at Heel:

q_heel = (ΣV/B) × (1 − 6e/B) (psf)

Inputs for the equations in this section (6)
SymbolWhat it isComes fromHow to get itTypical range
Wtotal vertical weight of wall + retained soil on heel (lb/ft)Another equationArea of the slice, wedge or wall section from the cross-section geometry × unit weight γ (from lab tests).project-specific
δbasefriction angle at base (degrees)Lab test (or fraction of φ')Interface direct shear (ASTM D5321); otherwise δ = 0.6–1.0 φ' depending on the surface (steel, concrete, geosynthetic).0.6–1.0 φ' · by USCS group
cbasebase adhesion (psf)Lab testEffective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more.0–300 psf · by USCS group
Bbase width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
PAtotaltotal active force including surcharge (lb/ft)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
evoid ratio = B/2 − ( ΣM_resisting − ΣM_overturning ) / ΣV (ft)Another equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
Shored MSE Wall System — Generic Cross-Section
Shored MSE Wall System — Generic Cross-Section
Soil nail load test
Soil nail load test
7.1.4.2 Cantilever Walls

Cantilever walls use a reinforced concrete stem and footing to resist overturning. The critical design section is at the base of the stem. Retained heights of 10–25 ft are typical.

Stem base moment (per foot of wall):

M_stem = (K_A × γ × H³/6) + (K_A × q_design × H²/2) (ft·lb/ft)

Minimum embedment depth for adequate passive resistance:

d_min is determined by setting FS_sliding ≥ 1.5 with the contribution of passive resistance over the embedded depth of the footing toe.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
7.1.4.3 Mechanically Stabilized Earth (MSE) Walls

MSE walls use reinforced fill to develop internal stability. They are commonly preferred for retained heights of 10–40 ft where ROW permits adequate fill width. MSE walls are commonly designed to AASHTO LRFD Bridge Design Specifications in addition to AREMA Chapter 8.

Soil-nailed shoring wall of a shored MSE wall project under construction in Colorado
Photo 7.1.4-1. Soil-nailed shoring wall of a shored MSE wall project in Colorado, under construction. (Photo courtesy of Colorado DOT.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Completed shored MSE wall with facing, Colorado
Photo 7.1.4-2. The same shored MSE wall project, complete with facing. (Photo courtesy of Colorado DOT.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Generic cross section of an SMSE wall system
Photo 7.1.4-3. Generic cross section of an SMSE wall system, showing the shoring wall and MSE wall components. (Figure from Morrison et al., 2006.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Installation of ground anchors to stabilize the Mississippi loess at Natchez Bluff
Photo 7.1.4-4. Installation of ground anchors to stabilize the Mississippi loess, Natchez Bluff. (Photograph by Kenneth Bergeron; from Fairweather, 1997.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Typical cross section of the soil nail and MSE wall used at US Highway 26-89
Photo 7.1.4-5. Typical cross section of the soil nail and MSE wall system used at US Highway 26-89. (Turner and Jensen, 2005; with permission from ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Internal stability checks include:

  • Tensile stress in reinforcement: T_max = σ_h × S_v × S_h (lb) where S_v and S_h are vertical and horizontal reinforcement spacing (ft)
  • Reinforcement pullout: F_pullout = f × α × σ_v' × L_e × R_c × b* (lb) where L_e is the embedment length beyond the failure plane

External stability checks (sliding, overturning, bearing) use the MSE mass as an equivalent gravity wall.

Owner railroads may require a minimum cover of unreinforced structural fill between the top reinforcement layer and the ballast for MSE walls next to live track; confirm it.

7.1.4.4 Soldier Pile and Lagging Walls

Soldier pile walls use steel H-piles driven or drilled at 6–8 ft spacing with timber lagging. They are commonly used for temporary shoring during cut construction and for permanent retained cuts in urban railroad corridors where MSE fill width is unavailable.

Retaining Wall Construction
Retaining Wall Construction

Required embedment depth below excavation for cantilever soldier piles (simplified method):

Struts in Deep Excavation
Struts in Deep Excavation

(1/6) × K_p × γ × d³ = P_A × (ȳ + d),  per foot of wall, taking moments about the pile tip; ȳ = height of P_A above the excavation level. For discrete soldier piles, apply the passive resistance over an effective width of about 2–3 pile widths.

Solve iteratively for d; common practice increases d by 20–40% for design.

Size timber lagging for the span and soil type (FHWA GEC 4).

7.1.4.5 Sheet Pile Walls

Sheet pile walls (steel) are used for waterfront structures, scour protection, and temporary cofferdams. Free-earth support method for cantilever sheet piles:

Figure 7.1-17. Sheet piling protecting track along a riverbank.
Figure 7.1-17. Sheet piling protecting track along a riverbank.

d_theoretical is determined by moment equilibrium; common practice increases d_theoretical by 20–40% (USACE instead factors the passive strength; see the box below).

Anchored sheet pile walls use tie rods to reduce embedment depth and moment demand. The anchor force:

T_A = P_A − P_P (horizontal force equilibrium, free-earth support)

Owner railroads may require coated or encapsulated steel sheet piles for permanent waterfront applications where tidal or chemically aggressive conditions exist.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
7.1.4.6 Soil Nail Walls

Soil nail walls are constructed top-down and are well suited to cuts in stiff clays, dense sands, and weathered rock. Nail design:

T_design = σ_h × S_v × S_h / FS_nail (lb)

Pullout resistance per unit length: Q_u = π × d_borehole × q_s (lb/ft) where q_s is the unit skin friction (psf)

FHWA GEC 7 (FHWA-NHI-14-007, 2015) recommends a global stability FS of 1.5 for permanent soil nail walls. AREMA Chapter 1 (Section 2.3.3) lists soil nail walls among slope repair methods and says they must be designed by an experienced engineer.

Supplemental reference

Micropile and soil-nail “A-walls” built from the track

Where a ballast shoulder or fill slope has slumped away from the ties and there is no room or time for a conventional wall, a micropile–tieback facing can be built from the embankment crest within track windows. Two projects in the AREMA Committee 1 files, both by GeoStabilization International (2018), show the arrangement:

Completed shored MSE wall with facing, Colorado
Completed shored MSE wall with facing, Colorado
  • A Class I railroad, Illinois (shoulder repair, 130 LF): Class I railroad cleared and excavated the failed shoulder and handled train protection. The contractor installed self-drilling hollow-bar micropiles (about 30 ft long, 2 ft spacing) at the outer edge of the shoulder and self-drilling soil nails (about 30 ft long, 4 ft spacing), drilled back beneath the track at 20–45° below horizontal depending on obstructions. A 12-in. reinforced shotcrete facing (two layers of 4×4–W2.9 welded wire fabric, No. 4 walers, 8×8×3/8-in. nail plates) tied the heads together, with one micropile per flank returning into the embankment. Weep holes (1½–2 in. PVC) were placed at 10 ft centers. New ballast was then placed behind the facing to restore the section (Figures 16-S1 and 16-S2). Nail grout was neat Type I/II/III cement at w/c 0.50–0.60.
  • Class I railroad Yard, Virginia (culvert headwall): a failing timber lagging wall over a culvert headwall beside the track was replaced by a micropile cap beam on micropiles up to 30 ft long battered about 40° from vertical, with soil nails up to 30 ft long at 30° ± 5°.
Soil Nailing with Shotcrete Facing
Soil Nailing with Shotcrete Facing
Drilling a soil nail hole
Drilling a soil nail hole
Soil Nail Retaining Wall
Soil Nail Retaining Wall
US 26/89 Typical Section — Soil Nail / MSE Wall
US 26/89 Typical Section — Soil Nail / MSE Wall
Failed ballast shoulder before repair, Class I railroad line in Illinois.
Supplemental Figure 16-S1. Failed ballast shoulder before repair, Class I railroad line in Illinois. Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files.
Figure 7.1-21. Soil-nailed shotcrete face with bearing plates.
Figure 7.1-21. Soil-nailed shotcrete face with bearing plates.

Why micropiles fit railroad sites (SHRP2): they can be drilled through any ground, including boulders, rubble fill and old ballast, at any angle, with small rigs, low noise and little spoil (low-headroom rigs work under 10 ft clearance). Capacity comes from grout-to-ground bond (toe resistance neglected), so tension and compression capacities are about equal. At least about 40% of the load is carried by the steel. Capacities commonly exceed 200 tons in soil and 500 tons in rock, and most are under 100 ft long. Limitations: high slenderness (check buckling in very soft or liquefiable soil), and the method depends on contractor drilling and grouting skill, so load testing is essential.

Composite gabion walls (gabion facing combined with tiebacks, soil nails, reinforced concrete beams or drilled shafts) are marketed on the same principle — less excavation behind the face than a gravity gabion or cantilever wall — which matters when the excavation would otherwise undermine the track.

Retaining Wall vs Gabion Wall vs Toe Wall
Retaining Wall vs Gabion Wall vs Toe Wall
Gabion Retaining Wall
Gabion Retaining Wall
Shotcreting the wall face
Shotcreting the wall face

Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files · GeoStabilization International (2018). Class I railroad Yard Culvert Wall — Micropile Cap (drawings). AREMA Committee 1 files · SHRP2 R02 / GeoTechTools (2012). Micro-piles — fact sheet

MSE Wall Construction — MnDOT Crosstown Project
MSE Wall Construction — MnDOT Crosstown Project
Completed reinforced-shotcrete micropile/soil-nail facing along the track shoulder, before ballast was restored behind it.
Supplemental Figure 16-S2. Completed reinforced-shotcrete micropile/soil-nail facing along the track shoulder, before ballast was restored behind it. Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files.
Supplemental reference

How USACE applies safety factors to sheet pile embedment

Section 7.1.4.5 increases the theoretical embedment by 1.3. EM 1110-2-2504 takes a different approach: it applies a strength-reduction factor to the passive side only (tan φeff = tan φ/FSP; ceff = c/FSP), uses best estimates elsewhere, and usually takes FSA = 1 unless wall deformation must be limited. It then solves directly for the penetration. The two approaches do not give the same depth; do not apply both.

Table 16-S1. Minimum FS on passive pressure for penetration depth (EM 1110-2-2504, Table 5-1, retaining walls)

Loading caseFine-grained soilsFree-draining soils
Usual2.00 Q-case; 1.50 S-case1.50 S-case
Unusual1.75 Q-case; 1.25 S-case1.25 S-case
Extreme1.50 Q-case; 1.10 S-case1.10 S-case

Other USACE points relevant to track walls: in medium-dense or denser sand, the active state develops at about 0.1–0.2% of wall height (about ¼–½ in. for a 20-ft wall), while full passive needs about 2–4% (roughly 5–10 in.). This is why passive resistance should be discounted where track settlement is critical. For anchored walls, the Free Earth method gives stable walls with less penetration than Fixed Earth but overpredicts moment (use Rowe’s moment reduction). Initially place the anchor at ¼–⅓ of the exposed height below the top. Grouted anchors must lie entirely outside the active wedge and develop the tie-rod yield strength. Proof-test every anchor to 110% of required resistance and performance-test at least two to 150% of design capacity.

Source: U.S. Army Corps of Engineers (1994). Design of Sheet Pile Walls. EM 1110-2-2504

Supplemental reference

Walls and revetments protecting track along shorelines

Lines along coasts, lakes and large rivers often depend on revetments, seawalls or bulkheads. EM 1110-2-1614 sizes armor stone by Hudson’s equation:

W = γrH3 / [KD(γr/γw − 1)3 cot θ]

where W is the armor unit weight (W50 for graded riprap) and H is the design wave height. Suggested KD for breaking waves: rough angular quarrystone, two layers, random 2.0 (1.2 for smooth rounded); graded riprap 2.2 (slopes 2.0–6.0 cot θ). A single layer of randomly placed rough stone is “do not use”, and graded riprap is not recommended where waves exceed 5 ft. For irregular waves on dumped riprap, the zero-damage stability number is Nsz = 1.14 cot1/6 θ with Hs.

  • Riprap gradation (relative to W50 min): W100 max ≤ 4 W50 min (the largest economically quarried size); W100 min ≥ 2 W50 min; W50 max ≈ 1.5 W50 min; W15 min ≈ 0.4 W50 min; W15 max set by filter criteria (EM 1110-2-1901; see the filter table in Chapter 1.9) and slightly above W50 min. Graded riprap thickness is two diameters of the W50 min stone.
  • A revetment is armor + filter + toe protection. Toe scour and slope instability from poor drainage are the usual failure modes, and minimum expected water levels control toe scour. Bulkheads and seawalls retaining the track fill should be checked for low water with the fill saturated, as well as for wave overtopping and loss of fill through joints.

Source: U.S. Army Corps of Engineers (1995). Design of Coastal Revetments, Seawalls, and Bulkheads. EM 1110-2-1614

Reinforced soil vs. conventional walls on railway fills

For very tall embankment sides, Profillidis shows either a conventional retaining wall at the toe or reinforced soil: an assembly of good-quality granular backfill, metallic reinforcing bars or strips anchored in the fill, and a concrete facing. Reinforced soil is recommended particularly on poor and very poor subgrades (S1, S0) and allows very steep or vertical faces. A French cost comparison for railway projects found reinforced soil economically and technically advantageous over a retaining wall, especially at heights of 10–40 ft (Figure 7.1-13).

Soil nail load test
Photo 7.1.4-6. Soil nail load test. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Drilling a nail hole
Photo 7.1.4-7. Drilling a nail hole. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Grouting a nail hole
Photo 7.1.4-8. Grouting a nail hole. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Shotcreting the face
Photo 7.1.4-9. Shotcreting the face. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Schematic diagram of MSE wall principal elements
Photo 7.1.4-10. Mechanically stabilized earth mass — principal elements. (Figure from Berg et al. (2009).)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
MSE wall construction on MnDOT Crosstown Project, 2008
Photo 7.1.4-11. MSE wall construction on MnDOT Crosstown Project, 2008. Photograph courtesy of Ryan Berg.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
SeaTac Airport runway extension MSE wall, tiered face with workers for scale
Photo 7.1.4-12. SeaTac Airport runway extension MSE wall. Photograph courtesy of Tony Allen.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Anchored Retaining Wall
Anchored Retaining Wall
Figure 7.1-11. Retaining wall supporting a very tall embankment side. Profillidis Fig. 9.16.
Figure 7.1-11. Retaining wall supporting a very tall embankment side. Profillidis Fig. 9.16.
Figure 7.1-12. Reinforced-soil technique: concrete facing panels, metallic bars and good-quality backfill. Profillidis Fig. 9.17.
Figure 7.1-12. Reinforced-soil technique: concrete facing panels, metallic bars and good-quality backfill. Profillidis Fig. 9.17.
Figure 7.1-13. Relative construction cost of retaining wall and reinforced soil vs. height, French railway projects. Profillidis Fig. 9.18.
Figure 7.1-13. Relative construction cost of retaining wall and reinforced soil vs. height, French railway projects. Profillidis Fig. 9.18.

Caution for electrified lines. The book states that metallic-reinforced soil cannot be used on electrified railways, because return current corrodes the metal reinforcement and can lead to failure. Where a reinforced-soil wall is proposed near an electrified line or a DC transit system, address stray-current corrosion explicitly. Options include non-metallic (geosynthetic) reinforcement or a corrosion design that accounts for stray current.

After Profillidis (2014), §9.12.2, §9.13, Figs. 9.16–9.18. Full reference under Supplemental References.

Walls used to stabilize track: field practice

Use a wall when a berm cannot be placed. Driven walls isolate the track from shallow-to-medium movement below but are not efficient against deep-seated failures. H-pile walls along the shoulder use piles about 4 ft apart. If movement continues, add a whaler so the piles act together; if it still moves, add soil anchors or tie back to piles on the far side of the grade. Rule of thumb: to hold 4 ft of unstable ground, embed at least 8 ft below the slip plane. At one Atlantic Canada site, a tidal bank retrogressing toward the track was treated with a temporary riprap toe berm and then a design combining 55-ft H-piles with a 40-ft sheet-pile wall.

Ground Anchor Installation — Natchez Bluff
Ground Anchor Installation — Natchez Bluff
Figure 7.1-14. Piles must pass fully through the shear plane to hold.
Figure 7.1-14. Piles must pass fully through the shear plane to hold.
Figure 7.1-15. H-piles driven along the shoulder.
Figure 7.1-15. H-piles driven along the shoulder.
Figure 7.1-16. Driving an H-pile on a prairie main line.
Figure 7.1-16. Driving an H-pile on a prairie main line.
  • Sheet piles: interlocking steel sections, also cutting groundwater inflow; can be anchored.
  • Soldier pile and lagging / Berlin wall: H-piles with timber, steel or precast lagging; heavier anchored versions for active slides.
  • Gravity walls: precast K-blocks (typically three high, each 5 ft × 2.5 ft × 2.5 ft) on and behind geotextile, which can be raised over time; gabions and geosynthetic-reinforced walls where space or budget is tight.
  • Soil nailing: built top-down in 3–6 ft lifts with near-horizontal grouted bars at 3–6 ft centers (commonly about 20 ft long), drainage and shotcrete facing. Nails must extend beyond the slip surface.
Precast T-Wall installation
Precast T-Wall installation
Sheet Pile Retaining Wall
Sheet Pile Retaining Wall
Figure 7.1-18. Berlin wall with timber lagging approaching a trestle.
Figure 7.1-18. Berlin wall with timber lagging approaching a trestle.
Figure 7.1-19. K-block wall with geotextile beneath and behind.
Figure 7.1-19. K-block wall with geotextile beneath and behind.
Figure 7.1-20. Finished K-block wall along a river.
Figure 7.1-20. Finished K-block wall along a river.

After Geotechnology for Railroaders Program, Module 6.1; §05–07, §10. Full reference under Supplemental References.

Project management · Cretu et al. (2011)

Integrating Value Engineering with Risk Response: Function Statements

Cretu et al. argue that risk assessment and value engineering (VE) belong together, because risk analysis characterizes the problems and VE generates the solutions. VE, also called value methodology, is a facilitated multidiscipline study built on function analysis. It asks what an element must do rather than what it is, and that is what separates it from simple cost cutting. For each high or moderate risk they add a function-based step to response planning:

MSE Wall — Principal Elements
MSE Wall — Principal Elements
  1. Identify the risk object, which is the noun of the project function that the risk affects, stated in a word or two.
  2. Write response functions as verb–noun pairs. The verb comes from the response strategy: accept, avoid, mitigate or transfer for threats, and enhance, exploit or share for opportunities.
  3. Brainstorm ideas under each function statement, aiming for quantity before judgment.
  4. Screen each idea as a green check (develop it), a yellow exclamation (keep it as a fallback) or a red X (reject it).
  5. Develop action plans for the green-check ideas, each with an owner and specific steps.
Template for converting a risk description and its object into a threat or opportunity response function statement built from a response verb and an object noun.
Figure 16-PM1. Template for converting a risk description and its object into a threat or opportunity response function statement built from a response verb and an object noun. Source: Cretu et al. (2011), Figure 5.4.

Reducing a long risk narrative to a short function statement keeps the team focused on the thing that can actually be managed. It also tends to produce several candidate solutions instead of one.

For railroad work: Wall selection is a natural application. Suppose the risk is “soft clay below the planned cantilever wall may cause excessive rotation under E-80 surcharge.” The risk object is the foundation. The response functions might be “avoid foundation” (a lightweight-fill embankment or a pile-supported wall), “mitigate settlement” (ground improvement or preloading where a track window allows), “transfer design” (a performance-specified proprietary system) and “accept movement” (a flexible MSE or gabion wall with a resurfacing allowance). Screening these against track-outage limits, construction access from the right-of-way, and the railroad’s preferences for wall type gives a short list. The short list can then be ranked by weighted paired-comparison scoring and compared on a whole-life cost basis.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 157–162. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

7.1.4.7 Soldier Pile Passive Resistance, Passive Softening and Anchor Fixed Length

Soldier piles and lagging are this manual's standard wall next to track. Below the excavation the piles act as discrete elements, not a continuous wall, and the passive resistance per pile is more than the plane-strain value over the pile width. UK guidance (CIRIA C580, summarised in Pickles, 2012, pp. 995–996) gives the ultimate net resistance per pile when the spacing s is more than three pile widths b.

Equation 7.1-6. Ultimate passive resistance of a discrete pile, per unit depth

Drained:  P = Kp b p′v  (z ≤ 1.5b),  P = Kp² b p′v  (z ≥ 1.5b)
Undrained:  P = (2 + 7z/3b) su b  (z ≤ 3b),  P = 9 su b  (z ≥ 3b)

Pickles (2012), Eqs. 64.5–64.8, after Barton (1982) and Fleming et al. (1994). Divide by s for resistance per foot of wall. Kp = (1 + sinφ′)/(1 − sinφ′); valid for Kp = 3.0 to 5.3 (30° ≤ φ′ ≤ 43°). z is depth below the excavation and p′v the effective overburden there. Vol. II prints “≤” in both depth limits; the second limit of each pair is evidently ≥, where the deeper expression takes over.

Full active pressure is assumed on the retained side. The Kp² form is close to the 3Kp rule (Broms) used in many U.S. guidelines at Kp = 3 and higher at larger Kp; follow the governing railroad shoring guideline where it prescribes a method (Section 7.1.17).

Softening of the passive zone in clay

Excavation unloads the clay in front of the wall; as negative pore pressures dissipate, the clay near the excavation base softens. Take the undrained strength as zero at the excavation level, rising to the design value at a depth L (Pickles, 2012, Eq. 64.4, p. 994):

Equation 7.1-7. Depth of softened clay below an excavation

L = √(12 cv t)

cv = coefficient of consolidation; t = time the excavation is open. Use L of about 1.6 ft (0.5 m) where no groundwater recharge is possible.

For example, with cv = 0.1 ft²/day, L is about 4.1 ft after two weeks and about 10 ft after three months, which can remove much of the passive resistance a short embedment relies on. Also allow for unplanned over-excavation in front of the wall: 10% of the retained height, up to about 1.6 ft (0.5 m), in Eurocode practice (Pickles, 2012, p. 985).

Ground anchor fixed length

Equation 7.1-8. Fixed anchor length from bond (skin friction)

Tult = π d L τult;   Tdesign = Tult/F;   in clay Tult = π d L α cu

Turner (2012), Eqs. 66.1–66.6, pp. 1017–1021. d = borehole diameter; L = fixed (bond) length; τ = grout–ground bond from load tests or published values; F = global factor (Vol. II recommends retaining the BS 8081 global factors).

Example 7.1-7: Passive resistance of a soldier pile in sand

Soldier piles in 2-ft drilled holes at 8-ft spacing support an excavation beside track. Below the excavation the soil is dense sand. Find the ultimate passive resistance per pile at 5 ft below the excavation and compare it with the 3Kp rule.

Sand: φ′ 34°, γ 120 pcfRetained soilExcavationz = 5 ftPp per pile per ft = ?Plan: b = 2 ft at s = 8 fts = 8 ftResistance per ft of wall = ?Givenb = 2 ft (drilled hole)s = 8 ft (s > 3b = 6 ft)φ′ = 34°; γ = 120 pcf (dry)z = 5 ft below excavationRequiredUltimate passive resistance per pile per foot of depthResistance per foot of wallBlack = given; red = required
Given and required for Example 7.1-7.

Given

VariableValueDescription
b2 ftPile (drilled hole) width
s8 ftPile spacing (s > 3b = 6 ft)
φ′34°Sand below excavation
γ120 pcfUnit weight (above groundwater)
z5 ftDepth below excavation

Required

  • Ultimate passive resistance per pile per foot of depth
  • Resistance per foot of wall

Equations

  1. EP-02: Kp = (1 + sinφ′)/(1 − sinφ′)
  2. Eq. 7.1-6: P = Kp² b p′v for z ≥ 1.5b

Steps

Step 1 · Kp
(1 + 0.559)/(1 − 0.559)
3.54 (within 3.0 to 5.3)
↓
Step 2 · Which form
z = 5 ft ≥ 1.5b = 3 ft
Use Kp²
↓
Step 3 · p′v
120 × 5
600 psf
↓
Step 4 · P per pile
3.54² × 2 × 600 = 12.51 × 1,200
15,000 lb/ft of depth
Spot check: 3Kp rule: 3 × 3.54 × 2 × 600 = 12,700 lb/ft, about 15% lower.
↓
Step 5 · Per foot of wall
15,000 / 8
1,880 lb/ft per ft of depth
↓
Solution
Ultimate passive resistance about 15,000 lb per foot of depth per pile at 5 ft (1,880 lb/ft per foot of wall).

Solution

This is an ultimate value; apply the factor of safety or the reduced passive coefficient that the governing railroad shoring guideline requires before using it to find embedment.

In clay, replace this with the undrained form and reduce the strength near the excavation base by the softened depth L.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Pickles, A. (2012). Geotechnical design of retaining walls. Chapter 64 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 981–1000Find source ↗Library entry
  • Turner, M. (2012). Geotechnical design of ground anchors. Chapter 66 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1011–1030Find source ↗Library entry
7.1.5 Global Stability of Retaining Structures

Global stability analysis (deep-seated failure of the entire wall-soil system) should be performed for walls retaining more than about 10 ft of fill and wherever weak soil underlies the wall. Use Bishop Simplified (Chapter 6.3) or Spencer's method for complex geometries.

Minimum global FS values (Table 7.1-1):

RailroadLong-Term FS (static)Seismic FSSubmerged/Seepage FSSource
Typical1.51.11.3Common practice; confirm with owner

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

Case study: 7.1.16.1 Back-analysis of a failed wall: condemn 330 ft, or not? (Look 2023), in §16.16 Case Studies.

Stabilizing a failed road fill slope, Fergus County MT
Stabilizing a failed road fill slope, Fergus County MT
7.1.6 Drainage Behind Retaining Walls

Hydrostatic pressure behind a wall can double or triple total lateral force. Drainage is not optional — it is a fundamental design requirement.

Hydrostatic Pressure — Increase with Depth
Hydrostatic Pressure — Increase with Depth
Permeability vs Drainage
Permeability vs Drainage

Hydrostatic pressure added to active pressure:

σ_w = γ_w × h_w (psf)

where h_w = height of water behind wall (ft); γ_w = 62.4 pcf.

Design requirement: All walls retaining granular fill must include continuous granular drainage blanket (≥ 12 in. thick, AASHTO No. 57 stone or equivalent), perforated pipe collector drain at the base, and weep holes through the wall face (4 in. diameter minimum, spaced ≤ 10 ft, per AREMA Ch. 8).

For walls in cold regions where freeze-thaw cycles are severe, insulated drainage blankets or thermally protected drains are needed to prevent pipe freeze.

Supplemental reference

Why segmental (block-faced) geosynthetic walls fail: backfill and inspection

A Geosynthetic Research Institute review estimated about 35,000 geosynthetic-reinforced MSE walls, about 30% of them block-faced SRWs. It examined 26 problem walls (12 serviceability, 14 collapses). In 25 of 26 the cause was poor backfill or poor construction and/or lack of inspection, and 20 of 26 had silt or clay backfill in the reinforced zone. The collapse mechanism was hydrostatic pressure: a crack admits water, the facing bulges, a block is dislodged, and the blocks above follow progressively until the facing and drainage gravel are lost.

SieveKoerner (1994)FHWA (1998)NCMA (1997)
No. 410010020–100
No. 400–600–600–60
No. 20000–150–35

Recommended reinforced-backfill gradations, % passing (GRI compilation).

Recommendations: prefer sand in the reinforced zone (gravel is acceptable but costs more and increases installation damage). If silt or clay is used it must be drained internally and externally, with particular attention to surface drainage. Design for hydrostatic pressure from all sources and directions. Suggested construction QA presence is 67% of construction time for noncritical permanent walls and 100% for critical walls; critical walls next to track should have full-time inspection. The same survey (1998 bid prices from 40 state DOTs) found geosynthetic MSE the least-cost wall type in every height class.

Source: Geosynthetic Research Institute (c. 2000). Geosynthetic Reinforced Segmental Retaining Walls (SRWs) (presentation; cost survey after J. Koerner et al., 1998)

7.1.7 Seismic Earth Pressure — Mononobe-Okabe Method

For walls in seismically active zones where the owner railroad or the governing code requires a seismic check (commonly SDC C and D), add the seismic earth pressure increment to the static active pressure. Passenger railroads commonly require seismic design for mainline walls.

The Mononobe-Okabe (M-O) total active force:

P_AE = ½ × γ × H² × (1 − k_v) × K_AE (lb/ft)

where:

K_AE = cos²(φ' − θ − α) / { cosθ × cos²α × cos(δ + α + θ) × [1 + √(sin(φ' + δ) × sin(φ' − θ − β) / (cos(α + θ + δ) × cos(α − β)))]² }

and:

θ = arctan(k_h / (1 − k_v))

  • k_h = horizontal seismic coefficient (commonly 0.5 × A_s for walls free to move 1–2 in., where A_s = F_PGA × PGA; AASHTO LRFD, or per site-specific analysis)
  • k_v = vertical seismic coefficient (typically 0 to ½ k_h)
  • S_DS = design spectral acceleration at short periods (ASCE 7-22, g)
  • α = inclination of the wall back from vertical (0 for a vertical wall; note this differs from the Coulomb α in Section 7.1.2.3); other variables as defined there

The seismic earth pressure increment:

ΔP_AE = P_AE − P_A (lb/ft)

Per Seed and Whitman (1970), this increment is assumed to act at 0.6H above the base:

M_AE = ΔP_AE × 0.6H + P_A × H/3 (ft·lb/ft)

7.1.8 Client-Specific Requirements Summary
Table 7.1-2. Retaining Wall Design Requirements
RailroadMin. FS SlideMin. FS OTWall FrictionSurchargeSeismic Req.Drain Req.PE Seal StateGoverning Std.
AREMA1.52.0δ = ⅔φ' (common)E-80 strip load (Section 7.1.3.1)SDC per codeMandatoryPer stateAREMA MRE Ch. 8

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

7.1.9 Worked Calculation Examples
The three examples cover a cantilever wall, an MSE wall and the seismic case for a gravity wall. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution. Walls that retain track next to an operating line are usually soldier pile and lagging; Section 7.1.3.1 works that case.
Example 7.1-1: Cantilever Wall at a Rock Cut Transition

A second main track on a Class I railroad located in the Shenandoah Valley of western Virginia needs a 20-ft cantilever wall where the slope is cut back. The example computes the earth pressure with Coulomb wall friction, adds the train surcharge, and checks sliding and overturning on a trial footing.

Cantilever Retaining Wall
Cantilever Retaining Wall
RC Cantilever Retaining Wall
RC Cantilever Retaining Wall
RCC Cantilever Retaining Wall
RCC Cantilever Retaining Wall
Cantilevered Retaining Wall
Cantilevered Retaining Wall

Given

VariableValueDescription
H20 ftRetained height
Backfillφ′ = 34°, c′ = 0, γ = 120 pcfCompacted granular fill
δ22.7° (2/3 φ′)Wall friction
q520 psfTrain surcharge with DLF 1.3, simplified as uniform (Section 7.1.3.1 gives the strip load)
Baseφ′base = 30°; qallow = 4,000 psfDense sand
W≈ 24,000 lb/ftStem, footing and soil on the heel, B = 10 ft (from the wall geometry, not detailed here)
TargetsFSsliding ≥ 1.5; FSOT ≥ 2.0

Required

  • KA, forces and stem moment
  • Sliding and overturning on the trial footing

Equations

  1. Eq. 1: KA = cos²φ′ / {cosδ [1 + √(sin(φ′ + δ) sinφ′ / cosδ)]²} — Coulomb, vertical wall, level backfill
  2. Eq. 2: PA = ½KAγH² at H/3; ΔP = KAqH at H/2
  3. Eq. 3: FSsliding = W tanφ′base / P; FSOT = ΣMR/ΣMOT — about the toe

Steps

Step 1 · KA (Eq. 1)
0.687 / {0.922 × [1 + √(0.836 × 0.559/0.922)]²} = 0.687 / (0.922 × 2.930)
KA = 0.254
↓
Step 2 · Forces (Eq. 2)
½ × 0.254 × 120 × 400 = 6,096; 0.254 × 520 × 20 = 2,642
P = 8,738 lb/ft
↓
Step 3 · Stem moment
6,096 × 6.67 + 2,642 × 10.0
M ≈ 67,060 ft-lb/ft
↓
Step 4 · Sliding (Eq. 3)
24,000 × tan30° / 8,738 = 13,856 / 8,738
FS = 1.58 ≥ 1.5
↓
Step 5 · Overturning, B = 10 ft
24,000 × 4.0 / 67,060
FS = 1.43 < 2.0: revise
↓
Step 6 · Overturning, B = 14 ft
ΣMR ≈ 142,000 (from the revised geometry) / 67,060
FS = 2.12 ≥ 2.0
↓
Solution
KA = 0.254; sliding 1.58; overturning needs B = 14 ft.

Solution

KA = 0.254 and the total thrust is 8,738 lb/ft. Sliding passes at 1.58; overturning fails at B = 10 ft (1.43) and passes at B = 14 ft (2.12).

Cantilever walls usually take three to five geometry iterations; the heel is the most effective thing to lengthen because it adds both soil weight and lever arm. The uniform 520-psf surcharge understates the load where the track is close to the wall, so recheck sliding and overturning with the strip load (Section 7.1.3.1) once the track offset is fixed. Railroad walls next to track are usually soldier pile and lagging; a cantilever wall suits a cut transition like this one.

Example 7.1-2: MSE Wall at an Intermodal Yard Throat

A 30-ft MSE wall supports an approach embankment at an intermodal expansion on a Class I railroad located in Kansas City. Each geogrid layer must carry the horizontal earth pressure over its tributary spacing, and must be anchored far enough behind the failure surface not to pull out.

H = 30 ftReinforced fill φ′ = 36°, γ = 125 pcfTrain surcharge q = 520 psfTmax at z = 28 ft = ? FSpo = ?L = 22 ftBearing pressure = ?GivenH = 30 ft; L = 22 ftSv = 2.0 ft; Rc = 1.0; Le = 4.5 ft at 28 ftF* = 0.487; α = 0.8; C = 2q = 520 psf (train)qallow = 6,000 psfRequiredTmax at z = 28 ftPullout factor of safetyBearing pressureBlack = given; red = required
Given and required for Example 7.1-2.

Given

VariableValueDescription
H30 ft
Reinforced fillφ′ = 36°, γ = 125 pcf
GeogridSv = 2.0 ft; Rc = 1.0; Le = 4.5 ft at z = 28 ft
F*, α, C0.67 tanφ′ = 0.487; 0.8; 2FHWA GEC 11 defaults for geogrid
q520 psfTrain surcharge
L22 ftReinforcement length
qallow6,000 psfFoundation

Required

  • Maximum reinforcement load at z = 28 ft
  • Pullout factor of safety
  • Bearing pressure

Equations

  1. Eq. 1: KA = tan²(45° − φ′/2) — Rankine
  2. Eq. 2: σh = KA(γz + q); Tmax = σh Sv
  3. Eq. 3 (FHWA GEC 11): Pr = F* α σ′v Le C Rc — pullout resistance per unit width; C = 2 for geogrid (both faces); α = 0.8 for geogrid
  4. Eq. 4: qb = (γH + q)L / L — simple bearing check

Steps

Step 1 · KA
tan²27°
0.260
↓
Step 2 · Tmax (Eq. 2)
0.260(125 × 28 + 520) = 910 + 135 = 1,045 psf; × 2.0
Tmax = 2,090 lb/ft
↓
Step 3 · Pullout (Eq. 3)
0.487 × 0.8 × 3,500 × 4.5 × 2 × 1.0
Pr = 12,270 lb/ft; FS = 5.9 ≥ 1.5
Spot check: Without C = 2 (one face only), Pr = 6,136 lb/ft and FS = 2.9: still adequate, but understated by half.
↓
Step 4 · Bearing (Eq. 4)
(125 × 30 + 520) = 4,270 psf
4,270 < 6,000 psf
↓
Solution
Tmax = 2,090 lb/ft; pullout FS = 5.9; bearing 4,270 psf.

Solution

Tmax = 2,090 lb/ft at z = 28 ft; pullout FS = 5.9; bearing 4,270 psf against 6,000 psf allowable.

The geogrid must also have a long-term design strength Tal above 2,090 lb/ft after the reduction factors for creep, installation damage and durability (FHWA GEC 11); that comes from the product data. The final design must also check eccentricity of the base reaction, global stability and settlement.

Example 7.1-3: Seismic Earth Pressure on a Gravity Wall

A 15-ft gravity wall on a Class I railroad located near Salem, Oregon, in Seismic Design Category D. The Seed-Whitman simplification adds a seismic increment to the static thrust and applies it higher on the wall, which is why seismic overturning so often governs.

H = 15 ftBackfill φ′ = 32°, γ = 120 pcfPAE = ? ΔPAE = ?kh = 0.25, kv = 0Seismic MOT = ?GivenH = 15 ftφ′ = 32°; γ = 120 pcfkh = 0.25; kv = 0KA = 0.307 (Rankine)Coulomb, δ = 21.3°: 0.275Target FSOT ≥ 1.1RequiredSeismic thrust and incrementSeismic overturning momentBlack = given; red = required
Given and required for Example 7.1-3.

Given

VariableValueDescription
H15 ft
Backfillφ′ = 32°, γ = 120 pcf
kh, kv0.25 and 0
KA0.307 (Rankine)Coulomb with δ = 21.3° gives 0.275
TargetFSOT ≥ 1.1 seismic (assumed)

Required

  • Seismic thrust and increment
  • Seismic overturning moment

Equations

  1. Eq. 1: ΔKAE ≈ ¾ kh; KAE = KA + ΔKAE — Seed and Whitman (1970), φ′ 30° to 40°, kh < 0.3
  2. Eq. 2: P = ½KγH²
  3. Eq. 3: M = PA(H/3) + ΔPAE(0.6H)

Steps

Step 1 · KAE (Eq. 1)
0.307 + 0.75 × 0.25
0.495
Spot check: The full Mononobe-Okabe solution with δ = 21.3° gives 0.476, so the simplified value is slightly conservative.
↓
Step 2 · Forces (Eq. 2)
½ × 0.495 × 120 × 225; ½ × 0.307 × 120 × 225
PAE = 6,683; PA = 4,150; ΔPAE = 2,532 lb/ft
↓
Step 3 · Moment (Eq. 3)
4,150 × 5.0 + 2,532 × 9.0 = 20,750 + 22,790
M = 43,540 ft-lb/ft, 2.1 times the static moment
↓
Solution
Seismic overturning moment 2.1 times the static.

Solution

KAE ≈ 0.495; the seismic increment is 2,532 lb/ft, and the seismic overturning moment is about 43,500 ft-lb/ft, 2.1 times the static value.

The increment acts at 0.6H rather than H/3, so it nearly doubles the moment on its own. In Seismic Design Category D the seismic case usually governs the wall geometry; size the footing for FSOT ≥ 1.1 under this moment.

7.1.10 Representative Data Table
Table 7.1-3. Summary of Retaining Wall Parameters — Illustrative Railroad Wall Cases
ProjectClientWall TypeH (ft)Backfill φ' (°)K_AP_A (lb/ft)q_surcharge (psf)FS_slideFS_OTSeismic
Shenandoah Ext.Class ICantilever RC20340.2546,0965201.582.12*No
KC IntermodalClass IMSE Geogrid30360.26014,6255201.822.45No
Cascades Ext.Class IGravity Conc.15320.3074,1515201.521.18 seismicYes
Passenger corridor ViaductPassengerSoldier Pile25300.33312,500520N/AN/AYes
Prairie YardClass IMSE Geogrid18350.2715,2704001.922.60No
Gulf Coast Ext.Short lineCantilever RC12280.3613,1144001.652.10No
Western Div.Class IGravity Conc.10300.3332,0004001.802.50No

*After widening the base to 14 ft. The first three rows come from Examples 16-1 to 16-3; the other rows are illustrative, not project records. P_A uses γ = 120 pcf (125 pcf for the KC row).

7.1.11 Reference Photographs
Passive Earth Pressure
Passive Earth Pressure
Cantilever Retaining Wall
Cantilever Retaining Wall
Completed shored MSE wall with facing, Colorado
Completed shored MSE wall with facing, Colorado
Pile Foundation Execution Inspection
Pile Foundation Execution Inspection
photo soil nailed shoring wall under construction colorado
photo soil nailed shoring wall under construction colorado
7.1.12 Practical Recommendations
  1. Check seismic loading where it is required. Owner railroads and codes commonly require it in SDC C and D; confirm the requirement when the work is scoped.
  2. Do not use computed K_P for sliding resistance without a reduction factor. Full Rankine passive resistance is only mobilized at displacements of about 2–6% of wall height (dense to loose sand), far beyond railroad serviceability tolerances. Use 50% of K_P passive resistance in sliding checks, or mobilize passive through a properly designed shear key.
  3. Specify drainage as a contract requirement, not a recommendation. Owner railroads' engineering standards treat wall drainage as mandatory. Include perforated pipe, granular blanket, and weep holes in the Geotechnical Special Provisions (Appendix C). Make failing to install drainage a deficiency that triggers contractor correction at no cost to the railroad.
  4. Verify backfill compaction limits near walls. Heavy compaction equipment within 3 ft of a wall can generate earth pressures well above active pressure. Specify compaction equipment exclusion zones and hand-compaction zones in GSP. Confirm these exclusion zones with the owner railroad.
  5. Perform global stability analysis for all walls > 10 ft. Bearing capacity and sliding checks alone are not sufficient. A wall that passes sliding and bearing checks can still fail through a weak layer beneath the footing.
  6. For MSE walls supporting live track, confirm the owner's minimum cover requirement. Owner railroads may require a minimum thickness of unreinforced fill between the top reinforcement layer and the ballast. Confirm this geometry is met before finalizing wall face location and top of reinforcement elevation.
  7. Document wall deflection tolerance in the GDR. Railroad track geometry tolerances (FRA 49 CFR Part 213) define the acceptable deformation limits, not structural failure limits. A cantilever wall that deflects 1.5 in. at the top may be structurally fine but will cause gage or surface defects. State deflection limits explicitly in the geotechnical design report and coordinate with the track engineer.

Case study: 7.1.16.2 Design detailing and analysis input: short case notes (Look 2023), in §16.16 Case Studies.

Project management · Jacob and Müller (2017)

Estimating a Tied-Back Soldier Pile and Lagging Wall per Square Foot of Face

Jacob and Müller price a temporary anchored soldier pile wall by costing one complete bay, meaning one soldier pile and the lagging to the next pile. That bay cost is then spread over the exposed (visible) face area, which is the pay unit in their bill of quantities.

Section through the example anchored soldier pile wall, showing excavation depth, embedment, inclined tieback and soil layering used for the bay cost build-up (SI units in the original).
Figure 16-PM2. Section through the example anchored soldier pile wall, showing excavation depth, embedment, inclined tieback and soil layering used for the bay cost build-up (SI units in the original). Source: Jacob and Müller (2017), Figure 2.34.

Example geometry, converted to US units:

  • 17.4 ft clear excavation height and about 6.6 ft of embedment, for 24 ft of drilled hole per pile;
  • soldier piles at 9.8 ft centers, made of paired channels weighing about 47 lb/ft;
  • one row of tiebacks 34 ft long at 30°;
  • 4-in timber lagging;
  • a uniform surcharge of about 210 psf.

The bay cost is built from:

  • drilling, at a fraction of the drill rig’s day rate (24 ft of hole at about 197 ft/day);
  • pile extraction afterward, using a crane crew day rate at about 328 ft/day;
  • lean concrete at the toe and a sand-concrete fill above;
  • soldier steel per ton, including attrition, three months’ rent, cutting and round-trip trucking;
  • tiebacks per foot;
  • lagging per square foot, bought from a subcontractor.

Of the bay cost, lagging was about 28%, anchors about 25%, drilling about 25% and extraction about 8%. The bay cost divided by (17.4 ft × 9.8 ft) gives the cost per square foot of face. A 25% markup was applied.

The authors contrast this with sheet piling. Sheet piling is paid on the actual driven wall area rather than the exposed face. When it stays in place permanently, the full material cost is included.

For railroad work: Temporary soldier pile walls for culvert replacements, track-adjacent excavations and shoofly construction are often the largest cost of temporary works. A bay-based build-up shows the railroad how the price depends on several things:

  • the Cooper E-80 surcharge and the distance to track centerline, which drive pile section, embedment and the need for tiebacks;
  • whether tiebacks can be installed at all under the track or within the right-of-way;
  • rental duration, which is tied to the construction schedule and window availability;
  • whether piles are pulled or left in place.

The pay unit (exposed face, total wall area or lump sum) must be stated clearly in the special provision, together with who designs the system and the movement-monitoring limits.

Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 192–195. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Supplemental reference · Goswami (2015), Ch. 208

Typical Retaining Wall Damage, Inspection, and Rating Backfill

Damage patterns to look for during inspection:

  • Tilting. A tilt of about 10° can raise the lateral force on the wall by roughly 20%, so tilt tends to worsen once it starts.
  • Shifting, often from repeated freeze–thaw of wet backfill.
  • Bowing from excess lateral pressure, usually water building up behind the wall.
  • Water signs: green growth, efflorescence, mineral deposits and rust staining from ties.

Inspection. Typical codes require special inspection of walls with more than 8 ft of retained height, and of 4- to 8-ft walls that carry a surcharge or a slope steeper than 3H:1V. Periodic inspection should look for loss of backfill, open joints and movement; voids from lost backfill fill with water and raise the pressure, so fill them promptly. Walls built against freshly cut slopes may lose strength as the cut material softens with time, so design for long-term strength.

Rating granular backfill. Brown’s suitability number, developed to rate backfill for vibroflotation, compares how readily granular materials densify:

SN = 1.7 √( 3/D502 + 1/D202 + 1/D102 ) with D in mm, or SN = 0.067 √( 3/D502 + 1/D202 + 1/D102 ) with D in in.

Ratings: 0–10 excellent, 10–20 good, 20–30 fair, 30–50 poor, over 50 unsuitable.

For railroad work: Add tilt, bowing, water staining and backfill loss to the wall entries of the earthworks inventory (Chapter 7.4) and record them as defects in the risk rating (Chapter 3.8). Railroad walls carry train surcharge, so the 4- to 8-ft walls next to track normally fall in the special-inspection group. The suitability number is a quick way to compare candidate free-draining backfills and stone column or vibro backfill (Chapter 7.2, Section 7.2.4).

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 208, Retaining Walls. Full reference under Supplemental References.

7.1.13 Design Checklist

Checklist · Part VII · Stabilization Methods

Design Checklist

Pre-Design Phase0 of 7
Analysis Phase0 of 10
Deliverable Phase0 of 7
Ticks are saved in this browser.
Plain text version

Pre-Design Phase

  • [ ] Confirm retained height, train clearance envelope, and ROW constraints with railroad project engineer
  • [ ] Obtain geotechnical investigation data: borings, SPT, lab classification, shear strength for all zones
  • [ ] Confirm design train loading: Cooper E-80 + DLF per client table
  • [ ] Determine seismic zone (ASCE 7-22 SDC) from USGS NSHM
  • [ ] Review client-specific engineering standards for wall design requirements
  • [ ] Confirm frost depth for embedment design
  • [ ] Identify drainage outlet constraints (outfall location, stormwater permits)

Analysis Phase

  • [ ] Calculate K_A (Rankine or Coulomb as appropriate for geometry)
  • [ ] Calculate K₀ if wall is rigid/non-deflecting
  • [ ] Apply Cooper E-80 surcharge per Section 7.1.3
  • [ ] Check FS_sliding ≥ 1.5 (with and without shear key)
  • [ ] Check FS_OT ≥ 2.0 (moment about toe)
  • [ ] Check middle-third rule (e ≤ B/6)
  • [ ] Check bearing pressure vs. q_allow or q_ult/FS
  • [ ] Perform global stability analysis (Bishop Simplified, FS ≥ 1.5)
  • [ ] Perform seismic check if SDC ≥ B (M-O method; verify seismic FS ≥ 1.1)
  • [ ] Check MSE internal stability (tensile overstress and pullout at all reinforcement levels)

Deliverable Phase

  • [ ] Produce wall section drawing with all dimensions, loading, and resultant locations
  • [ ] Tabulate all FS values in calculation summary table
  • [ ] Specify backfill material: AASHTO No. 57 or equivalent (confirm with the owner railroad's standard)
  • [ ] Include GSP language for wall construction, backfill compaction, and drainage installation
  • [ ] PE seal calculations as required by client
  • [ ] Submit to railroad project engineer for review per client submittal protocol
  • [ ] Resolve all review comments in writing before construction
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-09 At-rest earth pressure coefficient K₀Use: Uncemented soils on primary unloading. Limits: Not valid on reloading or for compacted fills, where K0 is governed by compaction stresses. Cap at passive limit.
7.1.14 Cross-Reference Table
TopicSee Also
Bearing capacity of wall foundationChapter 6.1
Settlement of wall foundationChapter 6.2
Global slope stability of retained embankmentChapter 6.3
Seismic hazard and k_h determinationChapter 6.5
Drainage and seepage behind wallsChapter 2.8
Geotechnical Special Provisions (wall language)Appendix C
Retaining wall section in final GDRChapter 8.4
Foundation soil lab testingChapter 5.2
7.1.15 Practice Questions
Each question is worked in the same five parts as the examples.
Question 7.1-1: Rankine Thrust on a Cantilever Wall

Problem Statement

An 18-ft cantilever retaining wall will support the fill for a new main track next to an existing one, with granular backfill and the train surcharge shown. The engineer must compute the active earth pressure coefficient, the thrust from the soil and the added thrust from the train surcharge.

H = 18 ftGranular backfill φ′ = 32°, γ = 118 pcfTrain surcharge q = 520 psfKA, PA, ΔP = ?GivenH = 18 ftφ′ = 32°; γ = 118 pcfq = 520 psfRequired(a) KA (b) PA from soil(c) ΔP from surchargeBlack = given; red = required
Given and required for Question 7.1-1.

Given

VariableValueDescription
H18 ft
Backfillφ′ = 32°, γ = 118 pcf
q520 psf

Required

  • (a) KA
  • (b) PA from soil
  • (c) ΔP from surcharge

Equations

  1. Eq. 1: KA = tan²(45° − φ′/2); PA = ½KAγH²; ΔP = KAqH

Steps

Step 1 · (a)
tan²29°
0.307
↓
Step 2 · (b)
½ × 0.307 × 118 × 324
5,874 lb/ft
↓
Step 3 · (c)
0.307 × 520 × 18
2,877 lb/ft
↓
Solution
KA 0.307; 5,874 and 2,877 lb/ft.

Solution

(a) 0.307. (b) 5,874 lb/ft. (c) 2,877 lb/ft.

The surcharge adds about half as much again as the soil and acts higher on the wall (H/2), so it contributes more than half as much again to the overturning moment.

Question 7.1-2: Sliding, Toe Pressure and the Middle Third

Problem Statement

A gravity retaining wall supports a railroad embankment above a road. The wall carries the vertical load and horizontal thrust shown on an 8-ft base with no shear key. The engineer must check the wall for sliding, compute the toe pressure, and check the middle-third rule.

Gravity wallΣV = 18,000 lb/ftP = 7,200 lb/ftB = 8 fte = 1.2 ft; φ′base = 30°qtoe = ?FSsliding = ? Middle third?Railroad embankmentRoadGivenΣV = 18,000 lb/ftB = 8 ftP = 7,200 lb/fte = 1.2 ftφ′ base = 30°; no key, no adhesionRequired(a) FS sliding(b) Toe pressure(c) Middle-third checkBlack = given; red = required
Given and required for Question 7.1-2.

Given

VariableValueDescription
ΣV18,000 lb/ft
B8 ft
P7,200 lb/ft
e1.2 ft
φ′base30°No key, no adhesion

Required

  • (a) FSsliding
  • (b) Toe pressure
  • (c) Middle-third check

Equations

  1. Eq. 1: FS = ΣV tanφ′ / P
  2. Eq. 2: qtoe = (ΣV/B)(1 + 6e/B)

Steps

Step 1 · (a)
18,000 × 0.577 / 7,200
1.44 < 1.5: marginal
↓
Step 2 · (b)
2,250 × 1.9
4,275 psf
↓
Step 3 · (c)
B/6 = 1.33 ft; e = 1.2 ft
Within the middle third
↓
Solution
Sliding 1.44 (key needed); toe 4,275 psf; middle third OK.

Solution

(a) FS = 1.44, short of 1.5: add a shear key. (b) 4,275 psf. (c) e = 1.2 ft ≤ 1.33 ft: no tension at the heel.

A shear key under the base mobilizes passive resistance; it is usually cheaper than widening the base for sliding alone.

Question 7.1-3: Seismic Increment by Seed and Whitman

Problem Statement

A 16-ft railroad retaining wall in a seismic area carries the static active thrust shown, and the design horizontal seismic coefficient is 0.28. The engineer must compute the seismic increment by the Seed and Whitman method and the moment it adds to the overturning check.

The method of Example 7.1-3.

H = 16 ftBackfill γ = 120 pcf (assumed)ΔKAE, ΔPAE = ?Static PA = 5,500 lb/ftAdded MOT = ?kh = 0.28Givenkh = 0.28H = 16 ftPA = 5,500 lb/ft (static)γ = 120 pcf (assumed)Required(a) ΔKAE (b) ΔPAE (c) Added overturning momentBlack = given; red = required
Given and required for Question 7.1-3.

Given

VariableValueDescription
kh0.28
H16 ft
PA5,500 lb/ftStatic
γ120 pcf (assumed)

Required

  • (a) ΔKAE
  • (b) ΔPAE
  • (c) Added overturning moment

Equations

  1. Eq. 1: ΔKAE ≈ ¾kh; ΔPAE = ½ΔKAEγH²; ΔM = ΔPAE(0.6H)

Steps

Step 1 · (a)
0.75 × 0.28
0.210
↓
Step 2 · (b)
½ × 0.210 × 120 × 256
3,226 lb/ft
↓
Step 3 · (c)
3,226 × 9.6
30,970 ft-lb/ft
↓
Solution
ΔKAE 0.21; ΔP 3,226 lb/ft; ΔM 30,970 ft-lb/ft.

Solution

(a) 0.210. (b) 3,226 lb/ft. (c) 30,970 ft-lb/ft added to the static moment.

Compare: the static moment is 5,500 × 16/3 = 29,330 ft-lb/ft, so the seismic case slightly more than doubles it.

Question 7.1-4: Reinforcement Load and Pullout in an MSE Wall

Problem Statement

A Class I railroad needs an access road wall below its main line, and a reinforced soil wall with geogrid reinforcement has been proposed (the track itself is not carried on the wall). At 22 ft depth the fill properties, spacing, embedment and surcharge are as shown. The engineer must find the horizontal stress, the reinforcement load and the pullout factor of safety.

The method of Example 7.1-2.

z = 22 ftFill γ = 122 pcf, φ′ = 35°Surcharge q = 400 psfσh, Tmax, FSpo = ?Le = 5.0 ftAccess road wall (track not on wall)Givenγ = 122 pcf; φ′ = 35°z = 22 ftSv = 2.0 ft; Rc = 1.0Le = 5.0 ftF* = 0.80 tanφ′; α = 0.8; C = 2q = 400 psfRequired(a) σh (b) Tmax (c) Pullout capacity and FSBlack = given; red = required
Given and required for Question 7.1-4.

Given

VariableValueDescription
Fillγ = 122 pcf, φ′ = 35°
z22 ft
Sv, Rc2.0 ft; 1.0
Le5.0 ft
F*, α, C0.80 tanφ′; 0.8; 2
q400 psfSurcharge

Required

  • (a) σh
  • (b) Tmax
  • (c) Pullout capacity and FS

Equations

  1. Eq. 1: KA = tan²(45° − φ′/2); σh = KA(γz + q)
  2. Eq. 3 (FHWA GEC 11): Pr = F* α σ′v Le C Rc — pullout resistance per unit width; C = 2 for geogrid (both faces); α = 0.8 for geogrid

Steps

Step 1 · (a)
KA = 0.271; 0.271(122 × 22 + 400) = 727 + 108
835 psf
↓
Step 2 · (b)
835 × 2.0
1,670 lb/ft
↓
Step 3 · (c)
0.560 × 0.8 × 2,684 × 5.0 × 2
Pr = 12,030 lb/ft; FS = 7.2
↓
Solution
Tmax 1,670 lb/ft; pullout FS 7.2.

Solution

(a) 835 psf. (b) 1,670 lb/ft. (c) Pr ≈ 12,000 lb/ft, FS ≈ 7.2.

With both faces of the grid counted (C = 2), pullout is rarely critical at depth; it governs near the top of the wall, where σ′v is small. Check the top layers too.

Question 7.1-5: Required Resisting Moment, Static and Seismic

Problem Statement

A soldier pile wall supporting a railroad embankment has the static and seismic overturning moments shown, with required factors of safety of 2.0 and 1.15. The engineer must find the minimum resisting moment the wall must provide and say which case governs.

Railroad embankmentTrackMOT,static = 95,000 ft-lb/ft, FS 2.0MOT,seismic = 155,000 ft-lb/ft, FS 1.15Minimum ΣMR = ? Which governs?GivenMOT,static = 95,000 ft-lb/ftFS static 2.0MOT,seismic = 155,000 ft-lb/ftFS seismic 1.15RequiredMinimum resisting moment ΣMR Governing caseBlack = given; red = required
Given and required for Question 7.1-5.

Given

VariableValueDescription
MOT,static95,000 ft-lb/ftTarget FS 2.0
MOT,seismic155,000 ft-lb/ftTarget FS 1.15

Required

  • Minimum ΣMR

Equations

  1. Eq. 1: ΣMR ≥ FS × MOT

Steps

Step 1 · Static
2.0 × 95,000
190,000
↓
Step 2 · Seismic
1.15 × 155,000
178,250
↓
Step 3 · Governing
Static: 190,000 ft-lb/ft
↓
Solution
ΣMR ≥ 190,000 ft-lb/ft (static governs).

Solution

ΣMR ≥ 190,000 ft-lb/ft; the static case governs here.

The seismic moment is larger, but the lower factor of safety allowed for the rare event means static still governs. Lengthening the base, typically from about 11 to 14 ft for a 22-ft cantilever wall, provides the extra lever arm.

7.1.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S11 under Supplemental References.

Case Study 16.16.1 — Back-analysis of a failed wall: condemn 330 ft, or not?
Case study · Look (2023) §13.12

Related section: 7.1.5 Global Stability of Retaining Structures

In an extreme 2008 rainfall, 79 ft of a ten-year-old retaining wall, about 6.6 ft high, failed. The client proposed to condemn the remaining 328 ft as well, a replacement of over AU$1 million, because a back-analysis of the failure using saturated soil mechanics, a single-stage failure and a high water table gave the intact wall a factor of safety below 1.2 (Look, 2016).

The failed and intact sections were not alike:

  • The failed section was lower (under 6.6 ft against about 13 ft) but had a back slope over 20°; the analysis had assumed under 10°, which held everywhere else. The change fell on a single cross section of those drawn every 33 ft and was missed in detailing.
  • It sat in a gully with a catchment six times larger.
  • A water pipe had burst above it.
  • It had deeper colluvium.

No groundwater had ever been seen at this elevated road, and residents reported the failure developed over two days. Coupling finite element seepage with limit equilibrium showed that rainfall reduced soil suction rather than raising a water table. The three back-analyses led to three conclusions for the intact wall:

  • FS < 1.2: high water table, single-stage failure, so demolish and replace.
  • FS = 1.3: high water table, progressive failure, so acceptable for an existing wall but not a new one.
  • FS = 1.6: unsaturated soil with loss of suction, progressive failure, so the intact wall is acceptable.

The intact wall had since come through several large storms with no distress. Look’s lessons: saturated and unsaturated analyses can disagree; back-analysis carries its assumptions into the result; a factor of safety is a decision tool, not an end in itself; and analysis is not design. A slope above a wall can raise active pressure by a factor of three, so the lowest wall is not necessarily the lowest load.

For railroad work: before parameters from a failed retaining wall or cut are applied to the rest of a structure, compare catchment, back slope, water sources and soil depth section by section. Antecedent rainfall, not daily rainfall alone, is the trigger to compare.

Assumed versus actual differences between the failed and stable sections: burst pipe, catchment six times larger, back slope over 20°.
Figure 16-LK1. Assumed versus actual differences between the failed and stable sections: burst pipe, catchment six times larger, back slope over 20°. Source: Look (2023), Figure 13.12-3, p. 487.
Wall cross sections every 33 ft: the back slope exceeded the analysis assumption at the one section that failed.
Figure 16-LK2. Wall cross sections every 33 ft: the back slope exceeded the analysis assumption at the one section that failed. Source: Look (2023), Figure 13.12-5, p. 488.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §13.12, pp. 484–490. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 16.16.2 — Design detailing and analysis input: short case notes
Case study · Look (2023) §13.13

Related section: 7.1.12 Practical Recommendations

Look closes the design chapter with several short cases where the analysis was right but the detail or the input was not:

  • Unloading broke a sewer. A surcharge for ground improvement extended past the site boundary over two pipes. After 15 months, with the ground improved, the fill was being removed to build a two-level sleeper wall. An excavator working at the crest cut too steep an edge, the edge failed, and the council’s sewer, 3.3 ft from the boundary, ruptured into adjacent wetlands. Design had looked at improvement and long-term stability but not at pipe strains from loading and unloading.
  • The lower wall governed. In the back-analysis case (§16.5), the shorter section with a back slope was the critical one, not the tallest.
  • 95% density does not give one modulus. At the same density ratio, compacted fills from sandstone, interbedded siltstone/sandstone and basalt gave plate load EV2 of about 10,000, 5,800 and 9,400 psi. Typical values: well-compacted, well-graded base 29 ksi or more, subbase 100 or more, working platform 60 or more, granular subgrade 50, cohesive subgrade 25. Resilient modulus is not the same as E; for one clay, Mr was about 2E.
  • Friction angle depends on fill and roller. In-situ friction of compacted weathered-rock fill rose from about 37° at 90% density to 43° at 100%, but varied with source rock and roller type.
  • Side-long fills crack. Old “goat tracks” widened by pushing fill down the hillside develop longitudinal cracks however good the compaction. Bench the cut-to-fill interface, or use another detail where steep hard rock prevents benching.

For railroad work: side-hill fills are among the most common chronic slide sites on mountain and river-grade lines. When one is rebuilt, the benching or keying detail matters as much as the stability analysis. Surcharge and unloading near buried utilities that cross the right-of-way need their own deflection check.

Longitudinal cracking and instability at a side-long fill over weathered rock and colluvium.
Figure 16-LK3. Longitudinal cracking and instability at a side-long fill over weathered rock and colluvium. Source: Look (2023), Figure 13.13-3, p. 493.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §13.13, pp. 490–494. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

7.1.17 Temporary Shoring Next to an Operating Track

Excavations for bridge footings, culverts, utilities and grade separations often sit within the zone where train loads push on the excavation support. Two Class I railroads publish joint guidelines for temporary shoring that supplement AREMA. They cover clearances, the Cooper E80 lateral load, deflection limits, embedment and allowable stresses, and what must be submitted. Consistent with Chapter 7.1, soldier piles with lagging and sheet piles are the usual systems; trench boxes are not accepted where railroad surcharge is present, and tiebacks under the track are discouraged because they obstruct future utilities and must be removed.

7.1.17.1 Loads and criteria

Equation 7.1-3. E80 lateral pressure, resultant and point of action (Boussinesq strip)

Ps = (2q/π)(β − sinβ cos2α)   R = 2qHβ/π   z = [H²β − bH + X2²(π/2 − θ2) − X1²(π/2 − θ1)]/(2Hβ)

q = 80,000/(5 × b) psf; X1,2 = S ∓ b/2; θ = arctan(X/H); β = θ2 − θ1; α = (θ1 + θ2)/2; moment at depth H = R(H − z).

Table 7.1-6. Shoring criteria in the joint guidelines
ItemRequirement
ClearanceNo excavation closer than 12 ft to track centerline; otherwise shift or remove the track
Deflection, shoring 12 to 18 ft from centerline3/8 in. shoring; 1/4 in. rail (horizontal or vertical)
Deflection, shoring 18 to 24 ft from centerline1/2 in. shoring; 1/4 in. rail
EmbedmentEquilibrium depth × about 1.3 for temporary shoring; anchored systems at least 1.5 times calculated embedment
Cantilever sheet pilesAt least 12 ft from centerline; granular soils or stiff clays only
Other loads2 ft spoil surcharge; track 200 lb/ft; ballast 120 pcf; centrifugal force where curvature exceeds 3°
Allowable stressesSteel 0.55Fy bending, 0.35Fy shear; sheet piles 2/3 Fy; concrete f'c/3; anchor rods Fy/2; no temporary-load increase
OperationsFlagman for work within 25 ft of centerline; monitor top of rail and alignment throughout
SOIL SCREW installation equipment
Photo 7.1.17-1. SOIL SCREW® installation equipment. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
SOIL SCREW being installed
Photo 7.1.17-2. SOIL SCREW® being installed. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Screw-in soil nail wall face before shotcrete
Photo 7.1.17-3. Screw-in soil nail wall face before shotcrete. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Shotcrete application
Photo 7.1.17-4. Shotcrete application. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Table 7.1-7. AREMA backfill types and properties used when tests are not justified (Tables 8-5-1 and 8-5-2)
TypeDescriptionUnit weight (pcf)φ
1Clean sand, gravel or broken stone10533 to 42° (38° broken stone)
2Coarse-grained with silt11030°
3Fine silty sand; clayey granular; residual soil with stones12528°
4Soft clay, organic silt, soft silty clay (engineer's approval)1000 (c = 0)
5Medium or stiff clay kept dry (engineer's approval)1200 (c = 240 psf)

7.1.17.2 Worked example: the guideline sample problem

Table 7.1-8. S = 12 ft, H = 6 ft, q = 1,778 psf (b = 9 ft); type 2 soil and 2 ft spoil (calculator output)
ResultValue
E80 pressure at 6 ft558 psf
E80 resultant / moment at 6 ft2,214 lb/ft / 4,944 ft-lb/ft
Total force with earth and spoil3,314 lb/ft
Total moment at excavation base7,584 ft-lb/ft
Check against the guideline chart: S = 16 ft, H = 10 ft411 psf; 2,964 lb/ft; 11,385 ft-lb/ft

The E80 values reproduce the guideline sample (558 psf, 2,214 lb/ft, z = 3.77 ft, 4,940 ft-lb/ft) and Chart A (411 psf, 2,964 lb/ft, 11,385 ft-lb/ft at S = 16 ft, H = 10 ft).

Note that the train load contributes most of the force at this shallow depth and that the pressure peaks a few feet down rather than at the top. The deflection limit of 3/8 in. at 12 ft from the track usually governs the soldier pile size more than stress does.

Open the temporary shoring calculator →
E80 Boussinesq lateral pressure, resultant and moment, active earth and spoil pressure, and the clearance, deflection and embedment criteria for shoring next to track.

7.1.17.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • Joint guidelines for temporary shoring of two Class I railroads (2004), Carriers folder: criteria, sample problem and Chart A.Find source ↗
  • A Class I railroad's pipeline occupancy specification (2018), Carriers folder: E80 strip surcharge (q = 1,882 psf with 8.5 ft ties).Find source ↗
  • AREMA conference papers: retaining wall design for railroad infrastructure (2014); emergency and non-emergency earth retaining with pressed-in sheet piles (2019).Find source ↗
  • AREMA Committee 1 files on micropile retaining walls and tieback shoulder repairs, AREMA folder.Find source ↗
7.1.18 Cantilever Sheet Pile Walls by the Blum Method

Steel sheet piles are the usual choice where a cut next to track has to be made quickly, in soft or water-bearing ground, or where the wall will be pulled when the work is done. A cantilever wall stands on its embedment alone: the soil in front of the toe pushes back as passive resistance, and a reverse pressure develops near the tip as the wall rotates about a point a little above it. The European sheet piling handbooks in the library simplify that reverse pressure, following Blum, into a single force at the theoretical toe. Embedment comes from moment equilibrium about that point, and the depth is then increased by about 20% so the reverse pressure can actually develop. For permanent railroad walls the manual still assumes soldier piles with lagging; sheet piles are covered here for temporary shoring and for sites where soldier piles cannot be drilled or driven.

7.1.18.1 Method

Equation 7.1-4. Blum equilibrium for a cantilever wall in cohesionless soil

x3 = m·x + n,   m = 6Q0/c,   n = 6M0/c,   c = γ(Kph/γEp − γGKah)

t = u + x  (Blum allowance Δt = 0.2t, driven length 1.2t);   Mmax = M0 + 0.385·Q0·√m

Here Q0 and M0 are the shear and moment from the active pressure at the point of zero net pressure, a distance u below the dredge line, and x is the depth from that point to the theoretical toe. The handbook's worked example, in metric units, gives m = 9.90 and n = 20.14, which solve to x = 3.88 m, so the embedment is t = u + x = 4.46 m, to which Blum's driving allowance Δt = 0.2t = 0.89 m is added. The calculator does not rely on the closed form. It integrates the factored active pressure (Coulomb, with wall friction), any uniform surcharge, and the Boussinesq strip pressure from an E80 axle group (80,000 lb spread over 5 ft by the tie length) when track is behind the wall, and it solves ΣM = 0 about the toe by bisection. With no surcharge and no wall friction the numerical solution matches the Blum result to within 0.1%.

Table 7.1-9. Sheet pile design items and typical values
ItemValue usedBasis
Active pressureCoulomb Kah with δa = 2/3φHandbook practice for steel against soil
Passive pressureKph with δp = 0 (Rankine) unless test data support more, divided by 1.5Partial factor on resistance
Driving allowanceΔt = 0.2t (Blum)Allows the reverse pressure to develop
Track live loadE80 strip, BoussinesqChapter 7.1 temporary shoring sections
Clearance to trackNo excavation within 12 ft of centerlineRailroad temporary shoring guidelines
Corrosion, natural soilabout 0.01 mm (0.0004 in.) per year per exposed faceEAU 2004, as cited in the handbook

7.1.18.2 Worked example

A 10 ft cut in sand (γ = 120 pcf, φ = 32°) with a 250 psf construction surcharge and no track: Kah/Kph = 0.256 / 3.255, equilibrium embedment 11.47 ft, embedment with the Blum allowance 13.76 ft, maximum moment 19,844 ft-lb/ft and a required section modulus of 7.2 in.³/ft at 33.3 ksi. Put the same wall 13 ft from track centerline with the E80 strip in place of the 250 psf surcharge and the embedment grows to 21.35 ft, the moment to 71,179 ft-lb/ft and the section modulus to 25.7 in.³/ft. Train load, not the soil, sets the section. For a permanent wall the 50-year corrosion loss at the handbook rate is 0.040 in. of total thickness, which reduces the section modulus that remains at the end of its life.

Deflection usually governs before stress does. Railroad shoring guidelines limit cantilever sheet piles next to track to granular soils or stiff clays, and they cap shoring movement at 3/8 in. (and rail movement at 1/4 in.) for walls 12 to 18 ft from centerline, and at 1/2 in. for walls 18 to 24 ft away. Check deflection with a beam-on-springs model before accepting the section from this calculator.

Open the cantilever sheet pile calculator →
Coulomb pressures, E80 strip surcharge, numerical moment equilibrium for embedment, the Blum driving allowance, maximum moment, required section modulus and corrosion loss.

7.1.18.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads, clients and projects are not named.

  • Sheet Piling Handbook: Design (ThyssenKrupp GfT Bautechnik and HSP Hoesch), and the Sheet Piling Handbook, 3rd edition: Blum's method, the worked cantilever example, earth pressure with wall friction, partial factors, and corrosion ratesFind source ↗Library entry
  • M. Stuart, Steel Sheet Piling, PDH course S151A (2012): U.S. practice for cantilever and anchored sheet pile walls, section selection and drivingFind source ↗Library entry
  • A Class I railroad's guidelines for temporary shoring: the 12 ft clearance, the E80 surcharge, and deflection limitsFind source ↗
  • M.F. Ashby and D.R.H. Jones, Engineering Materials 1: An Introduction to Properties, Applications and Design, 3rd edition: corrosion rates and protective measures for steelFind source ↗
7.1.19 Compaction-Induced and Wetting-Induced Pressure on Walls

Compacting backfill behind a rigid wall locks in horizontal stress that can exceed the at-rest value near the top of the wall. Wetting a compacted clay backfill that cannot expand sideways raises it further. Both matter for abutments, culvert headwalls and walls that do not yield enough to reach the active state.

Compaction pressure (Ingold method)

Equation 7.1-5. Compaction-induced lateral pressure envelope

σ′h,m = √(2Pγ/π);   zcr = K0 √(2P/(πγ));   hc = (1/K0) √(2P/(πγ))

Pickles (2012), Eqs. 64.1–64.3 and Fig. 64.6, p. 985. P = effective line load per unit length of the roller (lb/ft); γ = unit weight of the fill. The envelope rises along σh = σv/K0 to σ′h,m at zcr, stays at σ′h,m to hc, then follows K0σv.

Take P from the roller manufacturer's data (static weight plus dynamic force, per unit width of drum). Light plant near the wall keeps P, and so the locked-in pressure, small.

Wetting of compacted clay backfill

  • In laterally restrained tests on compacted kaolin, wetting raised the lateral stress and so the K0 value; the rise depended on the initial density and compaction water content. K0 on normally consolidated loading was not affected by suction and matched K0 = 1 − sinφ′ (Boyd and Sivakumar, 2011, pp. 87, 101, 103).
  • The higher the compaction stress, the more a compacted clay swells on wetting (Taibi et al., 2011, p. 52).

A clay backfill compacted dry and dense behind an unyielding wall is therefore the worst case: high locked-in compaction pressure followed by swelling pressure when it gets wet. Use free-draining granular backfill behind rigid walls and drain it (Section 7.1.6), and compact the zone next to the wall with light plant.

Example 7.1-6: Compaction pressure behind a 14-ft rigid wall

A cast-in-place culvert headwall 14 ft high is backfilled with granular fill compacted by a roller whose effective line load is 2,000 lb/ft. Find the compaction pressure envelope and compare the resultant with the at-rest and active thrusts.

H = 14 ftBackfill γ = 120 pcf, φ′ = 32°Roller P = 2,000 lb/ftzcr, hc, σ′h,m = ?Thrust vs K0 and Ka = ?GivenH = 14 ft rigid wallP = 2,000 lb/ft (roller)γ = 120 pcf; φ′ = 32°Requiredzcr, hc and σ′h,m Thrust of the compaction envelope vs K0 and Ka Black = given; red = required
Given and required for Example 7.1-6.

Given

VariableValueDescription
H14 ftWall height
P2,000 lb/ftEffective roller line load
γ120 pcfBackfill unit weight
φ′32°Backfill friction angle

Required

  • zcr, hc and σ′h,m
  • Resultant thrust of the compaction envelope against K0 and Ka

Equations

  1. EP-01: K0 = 1 − sinφ′
  2. Eq. 7.1-5: σ′h,m = √(2Pγ/π), zcr, hc
  3. EP-02: Ka = tan²(45° − φ′/2)

Steps

Step 1 · K0 and Ka
1 − sin32°; tan²29°
K0 = 0.470; Ka = 0.307
↓
Step 2 · Common term
√(2 × 2,000/(π × 120)) = √10.61
3.26 ft
↓
Step 3 · Envelope
zcr = 0.470 × 3.26; hc = 3.26/0.470; σ′h,m = √(2 × 2,000 × 120/π)
zcr = 1.53 ft; hc = 6.93 ft; σ′h,m = 391 psf
Spot check: K0γhc = 0.470 × 120 × 6.93 = 391 psf, so the envelope is continuous.
↓
Step 4 · Thrusts
Compaction: ½(391)(1.53) + 391(6.93 − 1.53) + ½(391 + 790)(14 − 6.93); K0: ½(0.470)(120)(14²); Ka: ½(0.307)(120)(14²)
6,580 lb/ft; 5,530 lb/ft; 3,610 lb/ft
↓
Solution
σ′h,m = 391 psf from 1.5 to 6.9 ft; resultant about 6.6 kips/ft, 19% above at-rest and 82% above active.

Solution

The compaction envelope controls the upper half of the wall, where the at-rest pressure would be only 86 to 390 psf. For a rigid headwall that is the pressure to design the stem for.

Using lighter compaction plant within a few feet of the wall reduces P and the envelope with it. Add the railroad surcharge (Section 7.1.3.1) and water pressure separately; the earth-pressure calculator now plots this envelope.

Open the earth pressure calculator →
Now includes an optional compaction-induced pressure envelope for a roller line load.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Pickles, A. (2012). Geotechnical design of retaining walls. Chapter 64 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 981–1000Find source ↗Library entry
  • Boyd, J. L. and Sivakumar, V. (2011). Experimental observations of the stress regime in unsaturated compacted clay when laterally confined. Géotechnique 61(4); reprinted in Partial Saturation in Compacted Soils, pp. 87–108Find source ↗
  • Taibi, S., Fleureau, J. M. et al. (2011). Some aspects of the behaviour of compacted soils along wetting paths. Géotechnique 61(5), 431–437; reprinted in Partial Saturation in Compacted Soils, pp. 45–53Find source ↗
7.1.22 Cantilever Soldier Pile and Lagging Walls

Soldier piles with lagging are this manual’s standard wall for stabilizing a slope or shoring an excavation next to track: the piles are driven or set in drilled holes from the shoulder, the lagging goes in as the face is excavated, and nothing has to be built behind the wall under the track. A cantilever wall relies only on the embedment of the piles below the excavation, so it suits retained heights up to about 10 to 15 ft; above that, or where deflection limits are tight, tiebacks or rakers are added (Section 7.1.4.7 for anchor bond). The analysis differs from a sheet pile wall (Section 7.1.18) in two ways. Above the excavation the lagging collects earth and surcharge pressure over the full pile spacing and delivers it to each pile. Below the excavation the pile is a discrete element and mobilizes passive resistance over more than its own width.

7.1.22.1 Method

Driving load per pile per foot of depth is w = s(Kaγz + Kaq + σE80) above the excavation and b(Kaσv + Kaq + σE80) below it, where σE80 is the Cooper E80 strip pressure of Section 7.1.17 (Eq. 7.1-3). Passive resistance below the excavation follows Eq. 7.1-6 (discrete pile) or the arching factor below, divided by a factor of safety. The embedment D0 is found from moment equilibrium about the toe and increased by 20% (some guidelines 30%) for the reverse pressure near the toe, as for the sheet pile wall.

Equation 7.1-9. Passive resistance of a soldier pile by the arching factor

Pp = Kpγd × min(f·b, s) / FS;   f = 0.08φ′ ≤ 3.0

Caltrans Trenching and Shoring Manual; d = depth below the excavation; b = flange width or drilled-hole diameter; s = spacing. Railroad temporary shoring commonly applies FS = 1.5 to passive resistance.

Equation 7.1-10. Timber lagging thickness

M = p·l²/8;   t = √(6M / (12Fb))

p = design pressure behind the lagging (psf), reduced for soil arching where permitted; l = clear span between flanges (ft); M in lb-in. per ft of height; Fb = allowable bending stress of the timber (psi).

The maximum moment per pile occurs at the point of zero shear below the excavation; the required section modulus is M/fb. Deflection, not strength, usually governs next to track: the railroad shoring guidelines limit horizontal movement within the track influence zone, so check deflection with a beam-on-spring or p-y model, and add anchors where the cantilever is too flexible.

7.1.22.2 Worked example

Example 7.1-8: Cantilever Soldier Pile Wall Beside Track

A 10-ft cut for a drainage structure on a Class I railroad located in Georgia is shored with a cantilever soldier pile wall whose face is 16 ft from the nearest track centerline. Piles are set in 24-in. drilled holes at 8-ft centers, with timber lagging.

trackS = 16 ftH = 10 ftD = ?γ 120, φ′ 32°dense sandγ 125, φ′ 34°q = 250 psfGivenH = 10 ft; piles 24 in. at s = 8 ftφ′ = 32° above, 34° belowq = 250 psf; E80 at S = 16 ftFS passive 1.5; fb 33 ksiRequiredEmbedment D, pile lengthMmax and section modulusLagging thickness
Cantilever soldier pile wall shoring a 10-ft cut 16 ft from track centerline.

Given

VariableValueDescription
H10 ftRetained height
s, b8 ft; 24 in. = 2.0 ftSpacing; hole diameter
Retained soilγ = 120 pcf, φ′ = 32°Above the excavation
Embedment soilγ = 125 pcf, φ′ = 34°Dense sand below
q250 psfConstruction and spoil surcharge
E8080,000/(5 × 9) = 1,778 psf strip, 9 ft wideTrack centerline 16 ft from the wall
FSp1.5On passive resistance
fb, Fb33 ksi; 1,000 psiPile; timber lagging

Required

  • Embedment and pile length
  • Maximum moment and required section modulus per pile
  • Lagging thickness

Equations

  1. Rankine: Ka = tan²(45° − φ′/2); Kp = tan²(45° + φ′/2)
  2. Eq. 7.1-3: σE80 = (2q/π)(β − sinβ cos2α); R = 2qHβ/π — train surcharge
  3. Eq. 7.1-9: Pp = Kpγd × f·b/FS — passive per pile
  4. ΣMtoe = 0 → D0; D = 1.2D0 — embedment
  5. Eq. 7.1-10: t = √(6M/(12Fb)) — lagging

Steps

Step 1 · Coefficients
Ka = tan²29°; Kp = tan²62°; f = 0.08 × 34 = 2.72
Ka = 0.307; Kp = 3.54; f·b = 5.44 ft
↓
Step 2 · Load above the excavation
Earth and surcharge: 8 × (0.5 × 0.307 × 120 × 10² + 0.307 × 250 × 10) = 20.9 kips; E80: x1 = 11.5, x2 = 20.5 ft, β = 0.262 rad, R = 2 × 1,778 × 10 × 0.262/π = 2.97 kips/ft × 8 ft = 23.7 kips
44.6 kips per pile
Spot check: The calculator’s integrated shear at the excavation, 44.55 kips, matches the hand sum. The train adds more load than the soil.
↓
Step 3 · Pressure at the excavation level
0.307 × 120 × 10 + 0.307 × 250 + σE80(10 ft) = 368 + 77 + 411
856 psf; 6.85 kips/ft on the pile
↓
Step 4 · Embedment (moment about the toe)
Solve ∫(w − Pp)(H + D0 − z)dz = 0
D0 = 16.3 ft; D = 1.2 × 16.3 = 19.6 ft; pile 29.6 ft
Spot check: At 5 ft below the excavation the factored passive resistance is 3.54 × 125 × 5 × 5.44/1.5 = 8.0 kips/ft against 1.9 kips/ft of driving load; resistance builds with depth as the plot in the calculator shows.
↓
Step 5 · Moment and section
Zero shear 8.7 ft below the excavation; S = 452.6 × 12 / 33
Mmax = 452.6 kip-ft; S = 164.6 in.³
↓
Step 6 · Lagging (Eq. 7.1-10)
p = 855 psf (no arching reduction in the track zone); l = 8 − 2 = 6 ft; M = 855 × 6²/8 × 12 = 46,170 lb-in.; t = √(6 × 46,170/(12 × 1,000))
t = 4.8 in.
↓
Solution
Embed the piles 19.6 ft (about 30-ft piles); section modulus at least 165 in.³ per pile; 5-in. (nominal 6-in.) lagging, or less if arching is accepted.

Solution

A cantilever wall works in strength with 30-ft piles, a section of at least 165 in.³ (for example a W21×83 at 171 in.³ set in the drilled hole) and 5-in. lagging.

The train surcharge more than doubles the load on the wall, and the cantilever will be flexible: at 10 ft retained and 16 ft from track, expect deflection near the railroad’s limit. Run a deflection check before submitting; if it fails, a single row of tiebacks at about 3 ft below the top cuts both moment and deflection sharply. Where the railroad accepts a 0.6 arching factor on lagging pressure, the computed lagging falls to about 3.7 in., and 4-in. rough-cut boards would do.

Open the soldier pile wall calculator →
Active pressure over the spacing and the pile width, uniform and E80 strip surcharges, passive resistance by the arching factor or Eq. 7.1-6 (with softened clay), embedment by moment equilibrium, maximum moment, section modulus and lagging thickness.

7.1.22.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • Caltrans, Trenching and Shoring Manual (2011): soldier pile walls, arching capability factor, lagging design.Find source ↗
  • CIRIA C580 and Pickles (2012), as summarized in Section 7.1.4.7: discrete-pile passive resistance and softening.Find source ↗
  • Joint Class I railroad guidelines for temporary shoring: E80 Boussinesq strip method, clearance, deflection and embedment requirements (Section 7.1.17).Find source ↗
  • FHWA-RD-75-128, Lateral Support Systems and Underpinning: lagging pressure and soil arching.Find source ↗
7.1.23 Braced Excavations and Strut Loads

Trenches for pipes and culverts across or along the track, and excavations for pits, vaults and foundations, are often supported by sheeting or soldier piles with internal struts or rakers. Because the bracing is installed from the top down as the excavation deepens, the wall cannot yield enough to develop the active state near the top, and the earth pressure is not triangular. Terzaghi and Peck measured strut loads in braced cuts and drew envelopes (“apparent pressure diagrams”) that bound them. The envelopes are not true pressure distributions: they are a design device for strut loads, wales and the spans between struts.

7.1.23.1 Method

Equation 7.1-11. Apparent earth pressure envelopes (Peck, 1969)

Sand: p = 0.65KaγH, uniform;   Soft to medium clay (γH/su > 4): p = KaγH, Ka = 1 − m(4su/γH) ≥ 0.25, rising over the top 0.25H;   Stiff fissured clay (γH/su ≤ 4): p = 0.2γH to 0.4γH, trapezoidal over the middle 0.5H

H = excavation depth; m = 1.0 except where soft clay continues below the base (m = 0.4). Add surcharge pressure (uniform and the E80 strip of Section 7.1.17) and water pressure below the water table.

Strut loads are found by treating the wall as hinged at each strut below the top one, so that each span is a simple beam between struts. The cantilever above the top strut is carried by the top strut, and the span below the lowest strut is supported by the soil at the base. The strut load is the reaction per foot of wall times the horizontal strut spacing, and the wale moment is about P·s/10 for a wale continuous over several struts.

7.1.23.2 Worked example

Example 7.1-9: Strut Loads in a Braced Trench in Sand

A 20-ft trench for a culvert extension next to a Class I railroad located in Texas is supported by sheeting with three levels of struts at 4, 11 and 17 ft, spaced 12 ft apart horizontally. The soil is medium dense sand above the water table, and the contractor’s equipment surcharge is 250 psf.

4 ft11 ft17 ftH = 20 ftsandγ 120, φ′ 32°struts at s = 12 ft along trenchGivenH = 20 ft; struts at 4, 11, 17 ftStrut spacing s = 12 ftSand: γ 120 pcf, φ′ 32°q = 250 psf, Kq = 0.33RequiredApparent pressure pStrut loads P1, P2, P3Wale moment
Braced trench in sand with three strut levels.

Given

VariableValueDescription
H20 ftExcavation depth
Struts4, 11 and 17 ft; s = 12 ftDepth; horizontal spacing
Soilγ = 120 pcf, φ′ = 32°Sand
q250 psf, Kq = 0.33Uniform surcharge

Required

  • Apparent pressure
  • Strut loads at each level
  • Wale moment

Equations

  1. Eq. 7.1-11: p = 0.65KaγH + Kqq — sand, uniform
  2. Hinge method: R1 = p(z1 + (z2 − z1)/2); Rj = p(Lj−1 + Lj)/2 — uniform pressure
  3. P = R × s; Mwale ≈ P·s/10

Steps

Step 1 · Pressure
Ka = tan²29° = 0.307; 0.65 × 0.307 × 120 × 20 + 0.33 × 250 = 479 + 83
p = 562 psf
↓
Step 2 · Top strut (4 ft)
562 × (4 + 7/2) = 562 × 7.5
R1 = 4,214 lb/ft; P1 = 50.6 kips
↓
Step 3 · Middle strut (11 ft)
562 × (7/2 + 6/2) = 562 × 6.5
R2 = 3,652 lb/ft; P2 = 43.8 kips
↓
Step 4 · Bottom strut (17 ft)
562 × (6/2 + 3/2) = 562 × 4.5
R3 = 2,528 lb/ft; P3 = 30.3 kips
Spot check: Base reaction 562 × 1.5 = 843 lb/ft; total 4,214 + 3,652 + 2,528 + 843 = 11,237 lb/ft = 562 × 20. Balanced.
↓
Step 5 · Wale
50.6 × 12/10
M = 60.7 kip-ft
↓
Solution
Strut loads 50.6, 43.8 and 30.3 kips; wale moment about 61 kip-ft at the top level.

Solution

Design the top struts for about 51 kips, the middle for 44 kips and the bottom for 30 kips, and the top wale for about 61 kip-ft.

If the trench is within the track influence zone, add the E80 strip pressure (enter the track distance in the calculator); it adds most load to the upper struts. Preload the struts to about half their design load to limit movement under the track, and monitor the track surface while the trench is open.

Open the braced excavation calculator →
Apparent pressure envelopes for sand, soft clay and stiff clay with uniform and E80 surcharges, strut loads at each level by the hinge method, the base reaction and the wale moment.

7.1.23.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • R.B. Peck (1969), Deep excavations and tunneling in soft ground, Proceedings, 7th International Conference on Soil Mechanics and Foundation Engineering, Mexico City, State-of-the-Art Volume, pp. 225–290.Find source ↗
  • K. Terzaghi, R.B. Peck and G. Mesri, Soil Mechanics in Engineering Practice, 3rd ed. (1996): braced cuts.Find source ↗
  • T.G. Hicks (ed.), Handbook of Civil Engineering Calculations, McGraw-Hill (2000): Section 4, earth thrust on a timbered trench.Find source ↗Library entry
  • Joint Class I railroad guidelines for temporary shoring (Section 7.1.17).Find source ↗
Supplemental reference · Goswami (2015), Chs. 209 and 507

Bottom Heave in Clay and OSHA Sloping of Excavations

Bottom heave. In soft to medium clay, the weight of the soil beside a braced cut can push the clay up into the bottom of the excavation. Bjerrum and Eide give:

FS = cu Nc / (γ H + q) ≥ 1.5

cu = undrained strength of the clay below the base (psf); Nc = bearing capacity factor that depends on the cut depth to width and length to width (about 5.1 for a long shallow cut, rising toward 9 for deep, square cuts); γ = unit weight (pcf); H = cut depth (ft); q = surcharge beside the cut (psf). If FS is too low, drive the sheeting deeper into firmer soil or reduce the surcharge.

Secant and tangent pile walls are rows of drilled shafts that touch (tangent) or overlap (secant). Secant walls cut off groundwater; tangent walls do not.

OSHA sloping (29 CFR 1926 Subpart P). For excavations less than 20 ft deep without a designed protective system, the maximum allowable slope depends on soil type:

OSHA soil types and maximum slopes (excavations under 20 ft)
TypeUnconfined compressive strengthMaximum slope (H:V)
Stable rock—Vertical
A1.5 tsf or more¾:1
B0.5 to 1.5 tsf1:1
C0.5 tsf or less; granular, submerged or seeping soil1½:1

Deeper excavations, and any protective system outside the standard tables, must be designed by a registered professional engineer.

For railroad work: Soil that is fissured or subject to vibration from heavy traffic or similar sources cannot be classed as Type A, so excavations beside operating track are normally Type B or C and need flatter slopes or shoring designed for the train surcharge (Section 7.1.17). Check bottom heave for any braced cut in soft clay beside track, where the surcharge q includes the track and train load.

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 209 (Support of Excavation) and Chapter 507 (Excavations). Full reference under Supplemental References.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

Supplemental references

  • GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 filesFind source ↗
  • GeoStabilization International (2018). Class I railroad Yard Culvert Wall — Micropile Cap (drawings). AREMA Committee 1 filesFind source ↗
  • SHRP2 R02 / GeoTechTools (2012). Micro-piles — fact sheetFind source ↗
  • U.S. Army Corps of Engineers (1994). Design of Sheet Pile Walls. EM 1110-2-2504Official page ↗Library entry
  • U.S. Army Corps of Engineers (1995). Design of Coastal Revetments, Seawalls, and Bulkheads. EM 1110-2-1614Official page ↗Library entry
  • Geosynthetic Research Institute (c. 2000). Geosynthetic Reinforced Segmental Retaining Walls (SRWs) (presentation; cost survey after J. Koerner et al., 1998)Find source ↗
  • A Class I railroad (2020). Public Projects Manual, December 2020 (shoring requirements adjacent to track)Find source ↗
  • Craig Olden, Inc. Composite Gabion Walls (product literature; scanned, text recovered by OCR)Find source ↗
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §13.12, §13.13Find source ↗Library entry

File locations for these documents are listed under Supplemental References.

Project management sources

  • Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & SonsFind source ↗
  • Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & SohnFind source ↗
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. The Case Studies section summarizes case studies from item S11 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 filesFind source ↗
  2. GeoStabilization International (2018). Class I railroad Yard Culvert Wall — Micropile Cap (drawings). AREMA Committee 1 filesFind source ↗
  3. SHRP2 R02 / GeoTechTools (2012). Micro-piles — fact sheetFind source ↗
  4. U.S. Army Corps of Engineers (1994). Design of Sheet Pile Walls. EM 1110-2-2504Find source ↗Library entry
  5. U.S. Army Corps of Engineers (1995). Design of Coastal Revetments, Seawalls, and Bulkheads. EM 1110-2-1614Find source ↗Library entry
  6. Geosynthetic Research Institute (c. 2000). Geosynthetic Reinforced Segmental Retaining Walls (SRWs) (presentation; cost survey after J. Koerner et al., 1998)Find source ↗
  7. A Class I railroad (2020). Public Projects Manual, December 2020 (shoring requirements adjacent to track)Find source ↗
  8. Craig Olden, Inc. Composite Gabion Walls (product literature; scanned, text recovered by OCR)Find source ↗
  9. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  10. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  11. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §13.12, §13.13Find source ↗Library entry
  12. Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons. Used on this page for project-management materialFind source ↗
  13. Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn. Used on this page for project-management materialFind source ↗
  14. Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education. Used on this page: Section 7.1.12 (wall damage, inspection and backfill rating)Find source ↗

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 7.1.4-1 — Soil-nailed shoring wall of a shored MSE wall project in Colorado, under construction. (Photo courtesy of Colorado DOT.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  2. Photo 7.1.4-2 — The same shored MSE wall project, complete with facing. (Photo courtesy of Colorado DOT.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  3. Photo 7.1.4-3 — Generic cross section of an SMSE wall system, showing the shoring wall and MSE wall components. (Figure from Morrison et al., 2006.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  4. Photo 7.1.4-4 — Installation of ground anchors to stabilize the Mississippi loess, Natchez Bluff. (Photograph by Kenneth Bergeron; from Fairweather, 1997.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  5. Photo 7.1.4-5 — Typical cross section of the soil nail and MSE wall system used at US Highway 26-89. (Turner and Jensen, 2005; with permission from ASCE.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  6. Photo 7.1.4-6 — Soil nail load test. (From FHWA.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  7. Photo 7.1.4-7 — Drilling a nail hole. (From FHWA.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  8. Photo 7.1.4-8 — Grouting a nail hole. (From FHWA.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  9. Photo 7.1.4-9 — Shotcreting the face. (From FHWA.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  10. Photo 7.1.4-10 — Mechanically stabilized earth mass — principal elements. (Figure from Berg et al. (2009).) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  11. Photo 7.1.4-11 — MSE wall construction on MnDOT Crosstown Project, 2008. Photograph courtesy of Ryan Berg. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  12. Photo 7.1.4-12 — SeaTac Airport runway extension MSE wall. Photograph courtesy of Tony Allen. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  13. Photo 7.1.17-1 — SOIL SCREW® installation equipment. (From abchance.com.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  14. Photo 7.1.17-2 — SOIL SCREW® being installed. (From abchance.com.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  15. Photo 7.1.17-3 — Screw-in soil nail wall face before shotcrete. (From abchance.com.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  16. Photo 7.1.17-4 — Shotcrete application. (From abchance.com.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗