↑ Parent Menu⌂ Main Menu
← Chapter 3.8 Risk Ratings and Ground Hazard Risk Assessment
GHRM
Railway Ground Hazard Risk Management · 3.0 · Risk Management
Sections · open a dropdown to go to a section or subsection

3.8.15 Worked Calculation Examples

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.15 Worked Calculation Examples
The two examples show how a trigger changes the margin of safety at a site. Each is laid out in five parts: what is known (Given), what is wanted (Required), the equations, a flow chart of the steps in the order they are solved with a spot check at each step, and the solution with what it means for the track.
Example 3.8-1: Effect of a Rising Water Table on an Embankment Side Slope

A 2H:1V embankment side slope of silty sand fill carries a main track, and shallow sloughing has been reported after heavy rain. The question is how much of the margin of safety the water takes away. The infinite-slope model (Chapter 6.3) suits this case because the sloughs are shallow and long compared with their depth, and seepage parallel to the slope is the condition that develops in a long wet spell.

slip surfacez = 6 ft (vertical, arrow)β = 26.6° (2H:1V)water table at height m·z above slip, m = 0, 0.5, 1.0FS (dry, half, full) = ?Givenβ = 26.6°; z = 6 ftγ = 120 pcf; γw = 62.4 pcfc′ = 50 psf; φ′ = 32°m = 0, 0.5, 1.0RequiredFS for dry, half and full saturationMeets 1.5 target? Meaning for the triggerBlack = given; red = required
Given and required for Example 3.8-1.

Given

VariableValueDescription
β26.6° (2H:1V)Slope angle
z6 ftVertical depth to the slip surface
γ120 pcfTotal unit weight of the fill
γw62.4 pcfUnit weight of water
c′50 psfEffective cohesion
φ′32°Effective friction angle
m0, 0.5 and 1.0Saturated fraction: height of the water table above the slip surface divided by z

Required

  • Factor of safety FS for dry, half-saturated and fully saturated conditions
  • Whether the slope meets the 1.5 target, and what the result means for the trigger

Equations

  1. Eq. 1: τd = γ z sinβ cosβ — driving shear stress on the slip plane
  2. Eq. 2: σ = γ z cos²β — total normal stress on the slip plane
  3. Eq. 3: u = m γw z cos²β — pore pressure for seepage parallel to the slope
  4. Eq. 4 (Equation 3.8-19): FS = [c′ + (σ − u) tanφ′] / τd — infinite-slope factor of safety

Steps

Step 1 · Trigonometric terms
cos²β and sinβ cosβ for β = 26.6°
cosβ = 0.894, sinβ = 0.447
cos²β = 0.800; sinβ cosβ = 0.400; tanφ′ = tan 32° = 0.625
Spot check: For a 2H:1V slope tanβ = 0.5, so cos²β = 1/(1 + 0.25) = 0.800 exactly.
↓
Step 2 · Driving stress τd (Eq. 1)
Uses: γ, z, sinβ cosβ
τd = 120 × 6 × 0.400
τd = 288 psf
Spot check: 120 × 6 = 720; 720 × 0.4 = 288.
↓
Step 3 · Normal stress σ (Eq. 2)
Uses: γ, z, cos²β
σ = 120 × 6 × 0.800
σ = 576 psf
Spot check: σ is exactly twice τd, because cos²β / (sinβ cosβ) = 1/tanβ = 2.
↓
Step 4 · Pore pressure u for each condition (Eq. 3)
Uses: m, γw, z, cos²β
u = m × 62.4 × 6 × 0.800 = 299.5 m
u = 0, 150 and 300 psf for m = 0, 0.5 and 1.0
Spot check: At m = 1.0, u / σ = 299.5 / 576 = 0.52, close to γw/γ = 0.52, as it must be.
↓
Step 5 · Factor of safety for each condition (Eq. 4)
Uses: c′, σ, u, tanφ′, τd
Dry: [50 + 576 × 0.625] / 288 = 410 / 288
Half: [50 + 426 × 0.625] / 288 = 316 / 288
Full: [50 + 276 × 0.625] / 288 = 223 / 288
FS = 1.42 (dry), 1.10 (half saturated), 0.77 (fully saturated)
Spot check: Each step of 0.5 in m removes 150 × 0.625 = 94 psf of resistance, or 0.33 in FS; 1.42 − 0.33 = 1.09 and 1.09 − 0.33 = 0.76, matching within rounding.
↓
Solution
FS falls from 1.42 (dry) to 1.10 (half saturated) to 0.77 (saturated).

Solution

FS = 1.42 dry, 1.10 half saturated and 0.77 fully saturated. The slope is marginal even when dry, below the 1.5 target. A storm that saturates half the slipping depth brings it close to failure, and full saturation fails it.

The example separates the three parts of the story that Section 3.8.1 asks for. The mechanism is shallow translational sliding of the fill. The condition that makes it possible is a steep slope in a weak, permeable fill. The trigger is rainfall infiltration that builds pore pressure. Controls that act on the mechanism are flattening the slope, a drained rock buttress, or surface drainage and vegetation. Until one is built, a rainfall-based patrol (Section 3.8.12) manages the exposure, because it watches the trigger the example shows is decisive.

Example 3.8-2: Checking a Storm Against the Caine Threshold

A rain gauge near a debris-flow channel above the track records a storm. Rainfall thresholds turn a forecast or a gauge reading into a decision, so the check is whether this storm is intense enough, for its length, to be in the range where shallow landslides and debris flows have started worldwide.

0.1110100Duration D (hr, log)Intensity I (in./hr, log)0.010.1110Caine (1980): I = 0.58 D−0.39D = 6 hr: I = ? Exceeds?GivenP = 2.0 in.D = 6 hrI = 0.58 D−0.39 (in./hr)RequiredAverage storm intensity IThreshold at 6 hr; exceeded?Black = given; red = required
Given and required for Example 3.8-2.

Given

VariableValueDescription
P2.0 in.Storm rainfall at the gauge
D6 hrStorm duration
ThresholdI = 0.58 D−0.39Caine (1980) global threshold in in./hr, valid for 10 minutes to 10 days

Required

  • Average storm intensity I
  • Threshold intensity for a 6-hour storm, and whether the storm exceeds it

Equations

  1. Eq. 1: I = P / D — average intensity
  2. Eq. 2 (Equation 3.8-18): It = 0.58 D−0.39 — threshold intensity (in./hr, D in hours)

Steps

Step 1 · Storm intensity I (Eq. 1)
Uses: P, D
I = 2.0 / 6
I = 0.333 in./hr
Spot check: One-third of an inch an hour: 6 × 0.333 = 2.0 in.
↓
Step 2 · Threshold intensity It (Eq. 2)
Uses: D
60.39 = 2.01; It = 0.58 / 2.01
It = 0.29 in./hr
Spot check: ln 6 = 1.79; 0.39 × 1.79 = 0.70; e0.70 = 2.01.
↓
Step 3 · Compare
Uses: I, It
0.333 in./hr against 0.29 in./hr
I > It: the storm exceeds the global threshold
Spot check: The ratio is 0.333 / 0.29 = 1.15, a 15% exceedance.
↓
Solution
The storm exceeds the threshold (0.333 > 0.29 in./hr).

Solution

Yes. The storm, at 0.333 in./hr over 6 hours, exceeds the Caine threshold of 0.29 in./hr.

Under a protocol calibrated to this threshold, the site would move to its heightened-response level, such as a patrol before the next train or a speed restriction, depending on its risk rating. The global threshold is a lower bound drawn from worldwide data and ignores antecedent moisture, so it is a starting point. Calibrate it against the territory’s own event record before relying on it (Sections 3.8.12 and 3.8.23.7).

← Previous · 3.0 Risk Management Chapter 3.7 — Cost Estimates
Next · 3.0 Risk Management → Chapter 3.9 — Geotechnical Investigation Planning and Scope