3.8.40 Life-Cycle Cost of Ground Hazard Mitigation
A risk rating says which sites matter. It does not say whether fixing a site is worth more than living with it. Sullivan, Wicks and Koelling's Engineering Economy supplies the tools: present worth, equivalent uniform annual cost and the benefit-cost ratio, all at the owner's discount rate over a fixed analysis period. For ground hazards the recurring cost has two parts. One is routine maintenance, such as surfacing, ditch cleaning and slow orders. The other is the annual risk cost, the probability of a failure in any year times what one failure costs in repair, outage and exposure. Mitigation buys down the second part. The Construction Materials and Engineering Materials 1 texts are the basis for the service life chosen for each alternative, whether that is corrosion of steel, deterioration of concrete or decay of timber.
3.8.40.1 Method
Equation 3.8-17. Present worth, annual cost and benefit-cost ratio
Example 3.8-13: Life-Cycle Cost of Two Mitigation Alternatives
A soft-ground embankment is costing $60,000 a year in surfacing and has an estimated 5% annual chance of a $1.5 million failure. Two mitigation alternatives are compared with continuing to maintain it, using the risk cost (probability times consequence) as an annual cost alongside maintenance.
Given and required for Example 3.8-13.
Given
Variable
Value
Description
C
$1,500,000
Cost of a failure (repair, outage and claims)
A0
K = 0; M = $60,000/yr; p = 0.05
Continue surfacing
A1
K = $450,000; M = $8,000/yr; p = 0.01
Toe berm
A2
K = $900,000; M = $3,000/yr; p = 0.005
Sheet pile reinforcement
i, N
7%; 30 years
Discount rate and analysis period
Required
Present worth of each alternative
Benefit-cost ratio of A1 and A2 against A0
The better buy, and whether the choice holds when p is halved or doubled
Continuing to maintain the embankment has a present worth of $1,675,221. The toe berm comes to $735,408 (B/C = 3.09) and sheet pile reinforcement to $1,030,295 (B/C = 1.72). Both pay for themselves, and the berm is the better buy.
The answer turns on the probability and the consequence, which come from the risk assessment, so the calculator is meant to be run across a range of values.
Present the result as a range, not a single number: run the probability at half and double the estimate. If the preferred alternative holds across that range, the recommendation is robust; if it flips, the decision rests on the risk estimate and more investigation may be the best investment.
Open the life-cycle cost calculator → Present worth, equivalent uniform annual cost and benefit-cost ratio of mitigation alternatives, with annual risk cost as probability times consequence, and a cumulative present-worth chart.
3.8.40.3 Sources in the library
Paraphrased from these documents in the reference library.
O. Cretu, R. Stewart and T. Berends, Risk Management for Design and Construction (Wiley, 2011): probability and consequence in project riskFind source ↗
P. Domone and J. Illston (eds.), Construction Materials: Their Nature and Behaviour, 4th edition: service life and deterioration of concrete, steel, timber and masonry (Current edition: M. Soutsos and P. Domone (eds.), 5th edition, CRC Press, 2018; this section cites the edition held in the library.)Find source ↗
Where the Present Worth Factor Comes From: Geometric Series
The present worth factor in Equation 3.8-17 is the sum of a geometric series. An annual cost A paid at the end of each of N years, discounted at rate i, has present worth A[v + v² + … + vN] with v = 1/(1 + i). The finite geometric series a + ar + … + arN−1 sums to a(1 − rN)/(1 − r), which gives (P/A) = [1 − (1 + i)−N]/i, the same as the form in Equation 3.8-17.
Perpetual cost. Because v < 1, the series converges as N grows: (P/A) → 1/i. At 7%, an annual risk cost carried forever is worth 1/0.07 = 14.3 years of that cost; over 30 years it is already 12.4 years. A cost avoided permanently is therefore worth only about 15% more than one avoided for 30 years, which is why the analysis period matters less than the probability and consequence.
Growing cost. If the annual cost grows at rate g (deteriorating slope, rising traffic), the ratio becomes (1 + g)/(1 + i), and the series still converges if g < i: (P/A) = [1 − ((1 + g)/(1 + i))N]/(i − g). With g ≥ i the sum grows without limit, a warning that deferring work on a site that worsens faster than the discount rate is never the cheaper choice.
Series approximations. The exposure formula of Section 3.8.30 uses (1 − p)n ≈ e−np, from the series ln(1 − p) = −p − p²/2 − …. The relative error in the exponent is about p/2, so the approximation is within 1% for annual probabilities below about 0.02 (return periods longer than 50 years) and about 12% at p = 0.2 (a 5-year return period).
For railroad work: Use the growing-cost form when a site is visibly getting worse; a constant annual risk cost understates the case for early repair.
Source: Hirst, K. E. (1995). Numbers, Sequences and Series. Modular Mathematics Series. London: Arnold (Butterworth-Heinemann) Find source ↗ (Ch. on sequences and series: geometric series, convergence, and series expansions).