3.8.21 Current Risk Rating

Rating ground hazard risk now, and how much each solution will reduce it: triggering mechanisms, current risk, and risk reduction ratings.
Author: Daniel P. Colwell
3.8.21 Current Risk Rating
Equation 3.8-4. Current risk
Rc = Fc × S (1 to 25); the current risk rating is read from the risk matrix, Table 3.8-16

The current risk rating carries the required response of Table 3.8-17 (Severe: act now; High: act soon; Elevated: plan; Guarded: watch; Low: routine inspection). It is reported with the trigger narrative and with each of its inputs, so a reviewer can see whether the rating is driven by the location (Fg), by the track (D) or by the consequence (S).

Table 3.8-12. Record of the current risk
ItemValueOne-line reason
Primary trigger and Te.g. culvert overtopping, T = 4Ponding against the fill recorded about every 3 years
Situational and historic score L1–5Weighted L1–L6 per Section 3.8.24.3
Geospatial frequency Fglesser of L and T
Defect rating D1–5Defect measurements and frequency; indicators
Current frequency FcTable 3.8-11
Severity S1–5Traffic, setting, what lies below
Current risk Rc and ratingFc × S; Table 3.8-16
Check the narrative against the numbers. A High rating driven by D = 4 should read as a site that is moving; one driven by Fg with D = 1 cannot be above Forming and should read as a susceptible site awaiting its trigger.