3.9.15 Selecting Design Parameters and Estimating Probability of Failure

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
3.9.15 Selecting Design Parameters and Estimating Probability of Failure

An investigation ends with a number chosen for each property, and the scatter in the data is as important as the average. The FHWA's Evaluation of Soil and Rock Properties (GEC 5) sets out a three-step selection. First, judge the data and remove values that reflect disturbance or a different material. Second, estimate variability, either from the tests themselves, from published coefficients of variation (Duncan 2000), or from the three-sigma rule using the highest and lowest conceivable values. Third, test the design at the mean and at the mean minus one standard deviation. Duncan, Wright and Brandon carry this to the probability that the factor of safety is less than 1.0 by the Taylor series method. One railroad's investigation requirements ask for the same end product: design strength parameters for every layer, from borings placed off the track where possible, preferably at the embankment toe.

3.9.15.1 Variability and the Taylor series method

Table 3.9-9. Coefficients of variation (Duncan 2000, in GEC 5 Table 52)
PropertyCOV (%)PropertyCOV (%)
Unit weight3 to 7Compression index10 to 37
Effective friction angle2 to 13Preconsolidation stress10 to 35
Undrained shear strength13 to 40Coefficient of consolidation33 to 68
Undrained strength ratio5 to 15Hydraulic conductivity, saturated clay68 to 90
SPT blow count15 to 45Electric CPT qc5 to 15
Vane shear strength10 to 20Mechanical CPT qc15 to 37

Equation 3.9-4. Standard deviation, reliability index and probability of failure

s = (HCV − LCV)/6  (three-sigma rule)

σF = √Σ[(Fi+ − Fi−)/2]²;   COVF = σF/FMLV
β = (FMLV − 1)/σF (normal);   βLN = ln[FMLV/√(1 + COVF²)]/√ln(1 + COVF²) (lognormal)

Fi+ and Fi− come from rerunning the stability analysis (for example with the Chapter 6.3 Bishop calculator) with one parameter at a time raised and lowered by one standard deviation. The probabilities agree with Duncan, Wright and Brandon's Tables 13.5 and 13.6. At FMLV = 1.5 and COVF = 20%, the calculator gives 4.8% (normal) and 2.6% (lognormal), against the tabulated 4.8% and 3%. At 1.2 and 10%, it gives 4.8% and 3.8%, against 4.8% and 4%.

3.9.15.2 Worked example

GEC 5's Piedmont example has a mean friction angle of 35.2°, a highest conceivable value of 53.8° and a lowest of 27.3°. The three-sigma rule gives s = 4.42, a COV of 12.5% (at the top of the published 2 to 13% range), and a mean minus one standard deviation of 30.78°. For an illustrative slope with FMLV = 1.5 and four uncertain parameters, the Taylor series gives COVF = 16.5% and a probability of failure of 2.18% (normal) or 0.84% (lognormal). The clay's undrained strength contributes most of the variance, so more strength testing of the clay is the investigation money best spent.

Engineers almost always set the highest and lowest conceivable values too close together. Widen them deliberately. Report the probability of failure alongside the factor of safety in the risk assessment (Chapter 3.8), and judge it against the consequence, not against a fixed number.

Open the design parameter reliability calculator →
Mean, standard deviation and COV from tests or the three-sigma rule, comparison with published COV ranges, mean minus one standard deviation, and probability of failure by the Taylor series method.

3.9.15.3 Using probability of failure in a decision

Duncan, Wright and Brandon show why a probability of failure can say more than a factor of safety. Two slope designs are compared. Design A has steep slopes, costs $100,000 for construction and land, and has Pf = 0.1. Design B has flatter slopes, costs $400,000, and has Pf = 0.01. If either failure would cost $5 million in primary and secondary consequences, the expected total cost is $100,000 + 0.1 × $5,000,000 = $600,000 for A and $400,000 + 0.01 × $5,000,000 = $450,000 for B. The design that costs more to build is cheaper overall. They also note that most people understand "1 chance in 10" against "1 chance in 100" more readily than 1.3 against 1.5. Putting a probability in front of an owner also makes clear that no factor of safety above 1.0 guarantees the slope will stand. The same arithmetic underlies the life-cycle comparison in Chapter 3.8.

Table 3.9-10. Expected total cost of two slope designs (Duncan, Wright and Brandon, Section 13.5.5)
DesignConstruction and landPfExpected failure cost ($5 million consequence)Expected total
A, steep slopes$100,0000.10$500,000$600,000
B, flatter slopes$400,0000.01$50,000$450,000

3.9.15.4 Checks against the published tables

The calculator's lognormal probabilities match Duncan, Wright and Brandon's Table 13.6, which is rounded, at the combinations below. Read across a row and the probability rises steeply with COVF. Reducing uncertainty through more testing can lower Pf as much as a higher factor of safety does.

Table 3.9-11. Probability that F < 1, lognormal distribution: published (Table 13.6) / calculated
FMLVCOVF = 10%COVF = 20%COVF = 30%
1.30.5% / 0.49%11% / 11.01%23% / 22.75%
1.50.00% / 0.00%3% / 2.57%11% / 10.85%
2.00.00% / 0.00%0.03% / 0.03%1.3% / 1.34%
11.522.501020304050Most likely factor of safetyProbability of failure (%), lognormalCOVF = 10%COVF = 20%COVF = 30%
Figure 3.9-11. Probability of failure against the most likely factor of safety for three coefficients of variation of F. The grey line marks 1%.

3.9.15.5 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • P.J. Sabatini and others, Evaluation of Soil and Rock Properties, FHWA Geotechnical Engineering Circular No. 5: selection of design parameters, variability, Table 52 and the Piedmont exampleFind source ↗Library entry
  • J.M. Duncan, S.G. Wright and T.L. Brandon, Soil Strength and Slope Stability, 2nd edition: Chapter 13, reliability, the Taylor series method and probability tablesFind source ↗
  • N. Simons, B. Menzies and M. Matthews, A Short Course in Geotechnical Site Investigation: the value of site investigationFind source ↗
  • U.S. Army Corps of Engineers, Geotechnical Investigations, EM 1110-1-1804 (2001): investigation planningOfficial page ↗
  • A Class I railroad's general requirements for geotechnical investigations for bridge projects: boring location, depth and reporting of design parametersFind source ↗

Probability and statistics behind the ratings: combining probabilities and updating them with Bayes’ theorem in Section 3.8.31; event counts, Poisson rates and annual maxima in Section 3.8.32; confidence limits, number of tests and records with no failures in Section 3.8.33.