Primary Reference: USACE EM 1110-1-1804, Geotechnical Investigations (2001), Sections 3-1 through 3-8; ASTM D2487, D3282, D4318, D6913, D7928, D1140, D7012; AREMA MRE Chapter 1, Part 1, Section 1.1 (Exploration and Testing); AASHTO M 145.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Typical index properties to check classification and boring-log descriptions against. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Undrained shear strength | Clay | CL-CH | Very soft | 251 | psf | LOOK T2.14 / 5.3, p.50 | ||
| Undrained shear strength | Clay | CL-CH | Soft | 251 | 386.5 | 522 | psf | LOOK T2.14 / 5.3, p.50 |
| Undrained shear strength | Clay | CL-CH | Firm | 522 | 783 | 1,044 | psf | LOOK T2.14 / 5.3, p.50 |
| Undrained shear strength | Clay | CL-CH | Stiff | 1,044 | 1,566 | 2,088 | psf | LOOK T2.14 / 5.3, p.50 |
| Undrained shear strength | Clay | CL-CH | Very stiff | 2,088 | 3,132 | 4,177 | psf | LOOK T2.14 / 5.3, p.50 |
| Undrained shear strength | Clay | CL-CH | Hard | 4,177 | psf | LOOK T2.14 / 5.3, p.50 | ||
| Unconfined compressive strength | Cohesive soil | CL-CH | Very soft (N < 2) | 0.25 | tsf | IDOT T4.4.6.1.2-2, p.119 | ||
| Unconfined compressive strength | Cohesive soil | CL-CH | Soft (N = 2–4) | 0.25 | 0.375 | 0.5 | tsf | IDOT T4.4.6.1.2-2, p.119 |
| Unconfined compressive strength | Cohesive soil | CL-CH | Medium stiff (N = 4–8) | 0.5 | 0.75 | 1 | tsf | IDOT T4.4.6.1.2-2, p.119 |
| Unconfined compressive strength | Cohesive soil | CL-CH | Stiff (N = 8–15) | 1 | 1.5 | 2 | tsf | IDOT T4.4.6.1.2-2, p.119 |
| Unconfined compressive strength | Cohesive soil | CL-CH | Very stiff (N = 15–30) | 2 | 3 | 4 | tsf | IDOT T4.4.6.1.2-2, p.119 |
| Unconfined compressive strength | Cohesive soil | CL-CH | Hard (N > 30) | 4 | 6 | 8 | tsf | IDOT T4.4.6.1.2-2, p.119 |
| SPT N-value | Cohesive soil | CL-CH | Very soft | 0 | 0.5 | 1 | blows/ft | GEC5 T23, p.137 |
| SPT N-value | Cohesive soil | CL-CH | Soft | 2 | 3 | 4 | blows/ft | GEC5 T23, p.137 |
| SPT N-value | Cohesive soil | CL-CH | Medium stiff | 5 | 6.5 | 8 | blows/ft | GEC5 T23, p.137 |
| SPT N-value | Cohesive soil | CL-CH | Stiff | 9 | 12 | 15 | blows/ft | GEC5 T23, p.137 |
| SPT N-value | Cohesive soil | CL-CH | Very stiff | 16 | 23 | 30 | blows/ft | GEC5 T23, p.137 |
| SPT N-value | Cohesive soil | CL-CH | Hard | 31 | 45.5 | 60 | blows/ft | GEC5 T23, p.137 |
| SPT N-value | Cohesive soil | CL-CH | Very hard | 60 | blows/ft | GEC5 T23, p.137 | ||
| SPT N-value | Granular soil | GW-SM | Very loose | 4 | blows/ft | LOOK T2.15, p.50 | ||
| Relative density | Granular soil | GW-SM | Very loose | 15 | % | LOOK T2.15, p.50 | ||
| SPT N-value | Granular soil | GW-SM | Loose | 4 | 7 | 10 | blows/ft | LOOK T2.15, p.50 |
| Relative density | Granular soil | GW-SM | Loose | 15 | 25 | 35 | % | LOOK T2.15, p.50 |
| SPT N-value | Granular soil | GW-SM | Medium dense | 10 | 20 | 30 | blows/ft | LOOK T2.15, p.50 |
| Relative density | Granular soil | GW-SM | Medium dense | 35 | 50 | 65 | % | LOOK T2.15, p.50 |
| SPT N-value | Granular soil | GW-SM | Dense | 30 | 40 | 50 | blows/ft | LOOK T2.15, p.50 |
| Relative density | Granular soil | GW-SM | Dense | 65 | 75 | 85 | % | LOOK T2.15, p.50 |
| SPT N-value | Granular soil | GW-SM | Very dense | 50 | blows/ft | LOOK T2.15, p.50 | ||
| Relative density | Granular soil | GW-SM | Very dense | 85 | % | LOOK T2.15, p.50 | ||
| Undrained shear strength | Clay | CL-CH | Very soft | 418 | psf | CRAIG T4.1, p.121 | ||
| Undrained shear strength | Clay | CL-CH | Soft | 418 | 626.5 | 835 | psf | CRAIG T4.1, p.121 |
| Undrained shear strength | Clay | CL-CH | Firm | 835 | 1,200 | 1,566 | psf | CRAIG T4.1, p.121 |
| Undrained shear strength | Clay | CL-CH | Stiff | 1,566 | 2,350 | 3,133 | psf | CRAIG T4.1, p.121 |
| Undrained shear strength | Clay | CL-CH | Very stiff | 3,133 | 4,700 | 6,266 | psf | CRAIG T4.1, p.121 |
| Undrained shear strength | Clay | CL-CH | Hard | 6,266 | psf | CRAIG T4.1, p.121 | ||
| Density index (relative density) | Sand | SP-SW | Very loose (N = 0–4) | 0 | 7.5 | 15 | % | CRAIG T8.3, p.309 |
| Normalized SPT value | Sand | SP-SW | Very loose (N = 0–4) | 0 | 1.5 | 3 | blows/ft | CRAIG T8.3, p.309 |
| Density index (relative density) | Sand | SP-SW | Loose (N = 4–10) | 15 | 25 | 35 | % | CRAIG T8.3, p.309 |
| Normalized SPT value | Sand | SP-SW | Loose (N = 4–10) | 3 | 5.5 | 8 | blows/ft | CRAIG T8.3, p.309 |
| Density index (relative density) | Sand | SP-SW | Medium dense (N = 10–30) | 35 | 50 | 65 | % | CRAIG T8.3, p.309 |
| Normalized SPT value | Sand | SP-SW | Medium dense (N = 10–30) | 8 | 16.5 | 25 | blows/ft | CRAIG T8.3, p.309 |
| Density index (relative density) | Sand | SP-SW | Dense (N = 30–50) | 65 | 75 | 85 | % | CRAIG T8.3, p.309 |
| Normalized SPT value | Sand | SP-SW | Dense (N = 30–50) | 25 | 33.5 | 42 | blows/ft | CRAIG T8.3, p.309 |
| Density index (relative density) | Sand | SP-SW | Very dense (N > 50) | 85 | 92.5 | 100 | % | CRAIG T8.3, p.309 |
| Normalized SPT value | Sand | SP-SW | Very dense (N > 50) | 42 | 50 | 58 | blows/ft | CRAIG T8.3, p.309 |
| Presumed allowable bearing value (BS 8004) | Dense gravel, or dense sand and gravel | GW, GP, SW | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 12.5 | ksf | CURTIN T1.1, p.5 | ||
| Presumed allowable bearing value (BS 8004) | Medium dense gravel, or sand and gravel | GW, GP, SW | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 4.2 | 8.3 | 12.5 | ksf | CURTIN T1.1, p.5 |
| Presumed allowable bearing value (BS 8004) | Loose gravel, or sand and gravel | GW, GP, SW | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 4.2 | ksf | CURTIN T1.1, p.5 | ||
| Presumed allowable bearing value (BS 8004) | Compact sand | SW, SP | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 6.3 | ksf | CURTIN T1.1, p.5 | ||
| Presumed allowable bearing value (BS 8004) | Medium dense sand | SW, SP | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 2.1 | 4.2 | 6.3 | ksf | CURTIN T1.1, p.5 |
| Presumed allowable bearing value (BS 8004) | Loose sand | SW, SP | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 2.1 | ksf | CURTIN T1.1, p.5 | ||
| Presumed allowable bearing value (BS 8004) | Very stiff boulder clay and hard clay | CL, CH | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 6.3 | 9.4 | 12.5 | ksf | CURTIN T1.1, p.5 |
| Presumed allowable bearing value (BS 8004) | Stiff clay | CL, CH | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 3.1 | 4.7 | 6.3 | ksf | CURTIN T1.1, p.5 |
| Presumed allowable bearing value (BS 8004) | Firm clay | CL, CH | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 1.6 | 2.35 | 3.1 | ksf | CURTIN T1.1, p.5 |
| Presumed allowable bearing value (BS 8004) | Soft clay and silt | CL, CH, ML | Footing width ≥ 3.3 ft; groundwater ≥ B below base | 1.6 | ksf | CURTIN T1.1, p.5 | ||
| Undrained strength of clay from hand-sample identification | Clay | Very soft | Extrudes between fingers | 420 | psf | ATKINSON T5.2, p.61 | ||
| Undrained strength of clay from hand-sample identification | Clay | Soft | Easily molded in fingers | 420 | 630 | 840 | psf | ATKINSON T5.2, p.61 |
| Undrained strength of clay from hand-sample identification | Clay | Firm | Molded by strong finger pressure | 840 | 1,205 | 1,570 | psf | ATKINSON T5.2, p.61 |
| Undrained strength of clay from hand-sample identification | Clay | Stiff | Cannot be molded in fingers | 1,570 | 1,830 | 2,090 | psf | ATKINSON T5.2, p.61 |
| Undrained strength of clay from hand-sample identification | Clay | Very stiff | Can be indented by thumbnail | 3,130 | psf | ATKINSON T5.2, p.61 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Specific gravity of solids | Quartz sand | SP / SW | 2.65 | – | CB T3.1, p.79 | |||
| Specific gravity of solids | Calcareous sand | SP / SW | 2.64 | 2.675 | 2.71 | – | CB T3.1, p.79 | |
| Specific gravity of solids | Most clay minerals | CL-CH | 2.67 | 2.7 | 2.73 | – | CB T3.1, p.79 | |
| Natural water content (saturated) | Loose uniform sand | Saturated, natural | 25 | 27.5 | 30 | % | DAS T2-3, p.12 | |
| Natural water content (saturated) | Dense uniform sand | Saturated, natural | 12 | 14 | 16 | % | DAS T2-3, p.12 | |
| Natural water content (saturated) | Loose angular-grained silty sand | Saturated, natural | 25 | % | DAS T2-3, p.12 | |||
| Natural water content (saturated) | Dense angular-grained silty sand | Saturated, natural | 15 | % | DAS T2-3, p.12 | |||
| Natural water content (saturated) | Stiff clay | Saturated, natural | 20 | % | DAS T2-3, p.12 | |||
| Natural water content (saturated) | Soft clay | Saturated, natural | 30 | 40 | 50 | % | DAS T2-3, p.12 | |
| Natural water content (saturated) | Soft organic clay | Saturated, natural | 80 | 105 | 130 | % | DAS T2-3, p.12 | |
| Natural water content (saturated) | Glacial till | Saturated, natural | 10 | % | DAS T2-3, p.12 | |||
| Specific gravity of soil solids | Sand | SW-SP | 2.63 | 2.65 | 2.67 | – | DAS T3-1, p.14 | |
| Specific gravity of soil solids | Silts | ML-MH | 2.65 | 2.675 | 2.7 | – | DAS T3-1, p.14 | |
| Specific gravity of soil solids | Clay and silty clay | CL-CH | 2.67 | 2.785 | 2.9 | – | DAS T3-1, p.14 | |
| Specific gravity of soil solids | Organic soil | OL / OH / Pt | 2 | – | DAS T3-1, p.14 | |||
| Void ratio (natural) | Loose uniform sand | Natural state | 0.8 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Loose uniform sand | Natural state | 30 | % | DASP T3.2, p.76 | |||
| Void ratio (natural) | Dense uniform sand | Natural state | 0.45 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Dense uniform sand | Natural state | 16 | % | DASP T3.2, p.76 | |||
| Void ratio (natural) | Loose angular-grained silty sand | Natural state | 0.65 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Loose angular-grained silty sand | Natural state | 25 | % | DASP T3.2, p.76 | |||
| Void ratio (natural) | Dense angular-grained silty sand | Natural state | 0.4 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Dense angular-grained silty sand | Natural state | 15 | % | DASP T3.2, p.76 | |||
| Void ratio (natural) | Stiff clay | Natural state | 0.6 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Stiff clay | Natural state | 21 | % | DASP T3.2, p.76 | |||
| Void ratio (natural) | Soft clay | Natural state | 0.9 | 1.15 | 1.4 | – | DASP T3.2, p.76 | |
| Natural water content (saturated) | Soft clay | Natural state | 30 | 40 | 50 | % | DASP T3.2, p.76 | |
| Void ratio (natural) | Loess | Natural state | 0.9 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Loess | Natural state | 25 | % | DASP T3.2, p.76 | |||
| Void ratio (natural) | Soft organic clay | Natural state | 2.5 | 2.85 | 3.2 | – | DASP T3.2, p.76 | |
| Natural water content (saturated) | Soft organic clay | Natural state | 90 | 105 | 120 | % | DASP T3.2, p.76 | |
| Void ratio (natural) | Glacial till | Natural state | 0.3 | – | DASP T3.2, p.76 | |||
| Natural water content (saturated) | Glacial till | Natural state | 10 | % | DASP T3.2, p.76 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Plastic limit | Montmorillonite | Clay mineral | Ca²⁺ pore water | 65 | 72 | 79 | % | CB T8.2, p.178 |
| Liquid limit | Montmorillonite | Clay mineral | Ca²⁺ pore water | 123 | 150 | 177 | % | CB T8.2, p.178 |
| Plastic limit | Montmorillonite | Clay mineral | Na⁺ pore water | 86 | 91.5 | 97 | % | CB T8.2, p.178 |
| Liquid limit | Montmorillonite | Clay mineral | Na⁺ pore water | 280 | 490 | 700 | % | CB T8.2, p.178 |
| Plastic limit | Illite | Clay mineral | Ca²⁺ pore water | 36 | 39 | 42 | % | CB T8.2, p.178 |
| Liquid limit | Illite | Clay mineral | Ca²⁺ pore water | 69 | 84.5 | 100 | % | CB T8.2, p.178 |
| Plastic limit | Illite | Clay mineral | Na⁺ pore water | 34 | 37.5 | 41 | % | CB T8.2, p.178 |
| Liquid limit | Illite | Clay mineral | Na⁺ pore water | 61 | 68 | 75 | % | CB T8.2, p.178 |
| Plastic limit | Kaolinite | Clay mineral | Ca²⁺ pore water | 26 | 31 | 36 | % | CB T8.2, p.178 |
| Liquid limit | Kaolinite | Clay mineral | Ca²⁺ pore water | 34 | 53.5 | 73 | % | CB T8.2, p.178 |
| Plastic limit | Kaolinite | Clay mineral | Na⁺ pore water | 26 | 27 | 28 | % | CB T8.2, p.178 |
| Liquid limit | Kaolinite | Clay mineral | Na⁺ pore water | 29 | 40.5 | 52 | % | CB T8.2, p.178 |
| Liquid limit | Illites | Clay mineral | Plots parallel, just above A-line | 30 | 60 | 90 | % | LOOK T7.5, p.105 |
| Liquid limit | Kaolinites | Clay mineral | Plots at or just below A-line | 30 | 50 | 70 | % | LOOK T7.5, p.105 |
| Liquid limit | Montmorillonites | Clay mineral | Plots near U-line | 30 | % | LOOK T7.5, p.105 | ||
| Plasticity index for swelling potential | Expansive clays | CL-CH | Low swell potential (Seed et al. 1962) | 0 | 7.5 | 15 | % | CB T8.4, p.180 |
| Plasticity index for swelling potential | Expansive clays | CL-CH | Medium swell potential (Seed et al. 1962) | 10 | 20 | 30 | % | CB T8.4, p.180 |
| Plasticity index for swelling potential | Expansive clays | CL-CH | High swell potential (Seed et al. 1962) | 20 | 37.5 | 55 | % | CB T8.4, p.180 |
| Plasticity index for swelling potential | Expansive clays | CL-CH | Very high swell potential (Seed et al. 1962) | 40 | % | CB T8.4, p.180 | ||
| Plasticity index for expansion potential | Expansive clays | CL-CH | Very high (probable expansion >30% of volume) | 35 | % | CB T8.6, p.185 | ||
| Plasticity index for expansion potential | Expansive clays | CL-CH | High (probable expansion 20–30% of volume) | 25 | 33 | 41 | % | CB T8.6, p.185 |
| Plasticity index for expansion potential | Expansive clays | CL-CH | Medium (probable expansion 10–30% of volume) | 15 | 21.5 | 28 | % | CB T8.6, p.185 |
| Plasticity index for expansion potential | Expansive clays | CL-CH | Low (probable expansion <10% of volume) | 18 | % | CB T8.6, p.185 | ||
| Liquid limit | Kaolinite | Clay mineral | 35 | 67.5 | 100 | % | DASP T4.1, p.96 | |
| Plastic limit | Kaolinite | Clay mineral | 20 | 30 | 40 | % | DASP T4.1, p.96 | |
| Activity | Kaolinite | Clay mineral | 0.3 | 0.4 | 0.5 | – | DASP T4.1, p.96 | |
| Liquid limit | Illite | Clay mineral | 60 | 90 | 120 | % | DASP T4.1, p.96 | |
| Plastic limit | Illite | Clay mineral | 35 | 47.5 | 60 | % | DASP T4.1, p.96 | |
| Activity | Illite | Clay mineral | 0.5 | 0.85 | 1.2 | – | DASP T4.1, p.96 | |
| Liquid limit | Montmorillonite | Clay mineral | 100 | 500 | 900 | % | DASP T4.1, p.96 | |
| Plastic limit | Montmorillonite | Clay mineral | 50 | 75 | 100 | % | DASP T4.1, p.96 | |
| Activity | Montmorillonite | Clay mineral | 1.5 | 4.25 | 7 | – | DASP T4.1, p.96 | |
| Liquid limit | Halloysite (hydrated) | Clay mineral | 50 | 60 | 70 | % | DASP T4.1, p.96 | |
| Plastic limit | Halloysite (hydrated) | Clay mineral | 40 | 50 | 60 | % | DASP T4.1, p.96 | |
| Activity | Halloysite (hydrated) | Clay mineral | 0.1 | 0.15 | 0.2 | – | DASP T4.1, p.96 | |
| Liquid limit | Halloysite (dehydrated) | Clay mineral | 40 | 47.5 | 55 | % | DASP T4.1, p.96 | |
| Plastic limit | Halloysite (dehydrated) | Clay mineral | 30 | 37.5 | 45 | % | DASP T4.1, p.96 | |
| Activity | Halloysite (dehydrated) | Clay mineral | 0.4 | 0.5 | 0.6 | – | DASP T4.1, p.96 | |
| Liquid limit | Attapulgite | Clay mineral | 150 | 200 | 250 | % | DASP T4.1, p.96 | |
| Plastic limit | Attapulgite | Clay mineral | 100 | 112.5 | 125 | % | DASP T4.1, p.96 | |
| Activity | Attapulgite | Clay mineral | 0.4 | 0.85 | 1.3 | – | DASP T4.1, p.96 | |
| Liquid limit | Allophane | Clay mineral | 200 | 225 | 250 | % | DASP T4.1, p.96 | |
| Plastic limit | Allophane | Clay mineral | 120 | 135 | 150 | % | DASP T4.1, p.96 | |
| Activity | Allophane | Clay mineral | 0.4 | 0.85 | 1.3 | – | DASP T4.1, p.96 | |
| Liquid limit | Silt | ML | 30 | 35 | 40 | % | BUDHU T4.5, p.80 | |
| Plastic limit | Silt | ML | 20 | 22.5 | 25 | % | BUDHU T4.5, p.80 | |
| Plasticity index | Silt | ML | 10 | 12.5 | 15 | % | BUDHU T4.5, p.80 | |
| Liquid limit | Clay | CL-CH | 40 | 95 | 150 | % | BUDHU T4.5, p.80 | |
| Plastic limit | Clay | CL-CH | 25 | 37.5 | 50 | % | BUDHU T4.5, p.80 | |
| Plasticity index | Clay | CL-CH | 15 | 57.5 | 100 | % | BUDHU T4.5, p.80 | |
| Liquid limit | Kaolinite | Clay mineral | 50 | 55 | 60 | % | BUDHU T4.5, p.80 | |
| Plastic limit | Kaolinite | Clay mineral | 30 | 35 | 40 | % | BUDHU T4.5, p.80 | |
| Plasticity index | Kaolinite | Clay mineral | 10 | 17.5 | 25 | % | BUDHU T4.5, p.80 | |
| Liquid limit | Illite | Clay mineral | 95 | 107.5 | 120 | % | BUDHU T4.5, p.80 | |
| Plastic limit | Illite | Clay mineral | 50 | 55 | 60 | % | BUDHU T4.5, p.80 | |
| Plasticity index | Illite | Clay mineral | 50 | 60 | 70 | % | BUDHU T4.5, p.80 | |
| Liquid limit | Montmorillonite | Clay mineral | 290 | 500 | 710 | % | BUDHU T4.5, p.80 | |
| Plastic limit | Montmorillonite | Clay mineral | 50 | 75 | 100 | % | BUDHU T4.5, p.80 | |
| Plasticity index | Montmorillonite | Clay mineral | 200 | 430 | 660 | % | BUDHU T4.5, p.80 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Soil behavior type index | Organic soils – clay | SBT zone 2 | 3.6 | – | ROB Fig. 22, p.35 | |||
| Soil behavior type index | Clays – silty clay to clay | SBT zone 3 | 2.95 | 3.275 | 3.6 | – | ROB Fig. 22, p.35 | |
| Soil behavior type index | Silt mixtures – clayey silt to silty clay | SBT zone 4 | 2.6 | 2.775 | 2.95 | – | ROB Fig. 22, p.35 | |
| Soil behavior type index | Sand mixtures – silty sand to sandy silt | SBT zone 5 | 2.05 | 2.325 | 2.6 | – | ROB Fig. 22, p.35 | |
| Soil behavior type index | Sands – clean sand to silty sand | SBT zone 6 | 1.31 | 1.68 | 2.05 | – | ROB Fig. 22, p.35 | |
| Soil behavior type index | Dense sand to gravelly sand | SBT zone 7 | 1.31 | – | ROB Fig. 22, p.35 |
| Estimate | Correlation | Limits / notes | Source |
|---|---|---|---|
| Plasticity index from linear shrinkage | PI ≈ 2.13 LS | Use where PL and LL are difficult | LOOK 2.12, p.49 |
| Liquidity and consistency index | LI = (w − PL)/PI; CI = (LL − w)/PI | CB Eq. 6.15–6.16, p.145 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
Consistent, reproducible classification of soil and rock is the common language shared between field personnel, laboratory technicians, design engineers, and railroad client reviewers. Every boring log, lab report, and geotechnical analysis submitted to Class I railroad subsidiaries relies on a classification framework that is traceable to recognized standards — principally the Unified Soil Classification System (USCS, ASTM D2487) for soils, AASHTO M 145 for pavement subgrade classification, and quantitative rock quality indices (RQD, Rock Mass Rating, and Geological Strength Index) for rock. AREMA MRE Chapter 1 references the USCS (ASTM D2487) for railroad earthwork, and AASHTO M 145 is widely used for subgrade evaluation. This chapter presents the full classification methodology for soils and rock in railroad project contexts, including Atterberg limit interpretation, gradation analysis, RQD (Chapter 4.1 cross-reference), RMR, and GSI. Three worked examples drawn from Class I railroad projects illustrate the classification process end-to-end. A representative data table, figure placeholders, practical recommendations, a field and lab checklist, and five practice questions with complete answers follow.


Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.
| ID | Correlation | Gives |
|---|---|---|
| IS-25 | Field vane strength correction | Sᵤ (field) |
| IX-10 | Undrained strength from liquidity index | Sᵤ (remolded) |
| RK-01 | Rock Mass Rating (RMR₈₉) | RMR |
| RK-02 | Rock mass quality (Q-system) | Q |
| RK-05 | GSI from RMR₈₉ | GSI |
| IX-01 | Compression index from liquid limit (undisturbed) | C꜀ |
| IX-04 | Compression index from plasticity index | C꜀ |
| RK-03 | RMR–Q conversion | RMR ↔ Q |
| RK-04 | RQD from volumetric joint count | RQD |
| RK-10 | UCS from point load index | σ꜀ |
Railroad embankment fills, subgrade soils, and foundation materials are evaluated using classification results at every project phase. Specifically:


European railways have not used a single system. The United Kingdom, France, Germany, Switzerland and others use the Unified Soil Classification System (Casagrande); Scandinavian railways rely mainly on grain size; Italy, Greece and others use the AASHO (now AASHTO) system. Profillidis calls the USCS the most generally applicable. ASTM D2487 is based on it but requires laboratory classification tests and subdivides further, whereas USCS allows a tentative visual classification. BS 5930 also derives from Casagrande but draws the sand and gravel boundaries differently, and DIN 4022 subdivides silt, sand and clay into fine, medium and coarse.

Figure 2.2-10 compares the grain-size boundaries of the main systems. They do not coincide (the silt–sand boundary, for example, falls between 0.02 mm and 0.074 mm), so check which system a historic log used before carrying its descriptions into a UIC or AREMA subgrade assessment.

After Profillidis (2014), §9.3, Fig. 9.2. Full reference under Supplemental References.
Sieve analysis separates soil particles by mechanical sieving through a standardized stack of sieves. Key sieves and particle size boundaries:


| Sieve | Opening (in.) | Particle Class Boundary |
|---|---|---|
| 3 in. | 3.00 | Coarse gravel / cobble |
| ¾ in. | 0.75 | Fine gravel / coarse gravel |
| No. 4 | 0.187 | Gravel / sand boundary |
| No. 10 | 0.079 | Coarse / medium sand |
| No. 40 | 0.0165 | Medium / fine sand |
| No. 200 | 0.0029 | Sand / fines boundary |
P_i (%) = [Mass passing sieve i / Total dry mass of specimen] × 100
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Pi (%) | [Mass passing sieve i / Total dry mass of specimen] × 100 | Lab test | Grain-size curve: sieve (ASTM D6913) plus hydrometer for fines (ASTM D7928). Read D10, D30, D50, D60, D85 from the curve. | by USCS group |
C_u = D_60 / D_10
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cu | D_60 / D_10 | Lab test | Grain-size curve: sieve (ASTM D6913) plus hydrometer for fines (ASTM D7928). Read D10, D30, D50, D60, D85 from the curve. | by USCS group |
C_c = (D_30)² / (D_10 × D_60)
Where D_10, D_30, D_60 = grain diameter (mm or in.) at which 10%, 30%, and 60% of the soil mass is finer, respectively.

Gravel classification: Well-graded gravel (GW) requires C_u ≥ 4 and 1 ≤ C_c ≤ 3. Poorly graded gravel (GP) fails either criterion. Sand classification: Well-graded sand (SW) requires C_u ≥ 6 and 1 ≤ C_c ≤ 3. Poorly graded sand (SP) fails either criterion.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | (D_30)² / (D_10 × D_60) | Lab test | Grain-size curve: sieve (ASTM D6913) plus hydrometer for fines (ASTM D7928). Read D10, D30, D50, D60, D85 from the curve. | by USCS group |
For the fines fraction (passing No. 200 sieve), hydrometer analysis gives the percent finer than each particle size, including the clay-size fraction finer than 0.002 mm (2 µm). The hydrometer reading at elapsed time t is converted to equivalent particle diameter using Stokes' Law:
D = √(18 × η × L / (G_s − 1) × γ_w × t)
Where:
Note: Hydrometer particle sizes are usually reported in mm. The USCS does not separate silt from clay by size; it uses plasticity (the A-line on the plasticity chart). The 0.002 mm size is the clay-size boundary used by AASHTO and in the activity calculation.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| η | viscosity of water at test temperature (g/cm·s) | Constant | Physical constant or standard value. | project-specific |
| L | effective hydrometer depth (cm) | Test setup | Dimension of the test equipment or specimen: from the test standard or the lab/field test record. | project-specific |
| Gs | specific gravity of solids (typically 2.65–2.72 for mineral soils | Lab test | Specific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested. | 2.64–2.80 mineral; lower if organic · by USCS group |
| γw | unit weight of water (g/cm³) = 1.0 | Constant | Physical constant or standard value. | project-specific |
| t | elapsed time (minutes × 60 = seconds) | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
Case study: 2.2.14.1 Gradings before and after compaction: the oversize that was never tested (Look 2023), in §8.14 Case Studies.
Case study: 2.2.14.2 Representative sampling from a weathered-rock stockpile (Look 2023), in §8.14 Case Studies.
Atterberg limits define the moisture content boundaries between soil behavioral states for fine-grained soils. They are measured on the fraction passing the No. 40 sieve.

No additional content.
PI = LL − PL
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| PI | plasticity index = LL − PL | Lab test | PI = LL − PL from Atterberg limits (ASTM D4318). | CL 7–30, CH 25–80 · by USCS group |
| LL | liquid limit | Lab test | Atterberg limits (ASTM D4318) on the minus No. 40 fraction. | CL 20–50, CH 50–110 · by USCS group |
LI = (w_n − PL) / PI
Where w_n = natural (field) water content (%). Interpretation:
| LI | Consistency State |
|---|---|
| < 0 | Stiff / desiccated |
| 0–0.25 | Very stiff |
| 0.25–0.50 | Stiff |
| 0.50–0.75 | Medium |
| 0.75–1.00 | Soft |
| > 1.00 | Very soft / approaching liquid state |
Activity (A) — clay mineralogy indicator:
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| wn | natural (field) water content (%) | Lab test | Oven-dry water content of samples (ASTM D2216); field check by microwave (D4643) or nuclear gauge (D6938). | gravels/sands 3–25%, clays 15–70% · by USCS group |
| PI | plasticity index | Lab test | PI = LL − PL from Atterberg limits (ASTM D4318). | CL 7–30, CH 25–80 · by USCS group |
A = PI / (% clay fraction)
Where % clay fraction = % finer than 0.002 mm from hydrometer analysis.
| A | Clay Mineral Type |
|---|---|
| < 0.75 | Inactive (kaolinite dominant) |
| 0.75–1.25 | Normal (illite dominant) |
| > 1.25 | Active (montmorillonite / smectite) |
Activity > 1.25 is a critical flag on all railroad projects: highly active clays exhibit significant swell potential when wetted after desiccation — a chronic track geometry problem along Class I railroad subdivision located in the Carolinas, Class I railroad routes located in the Texas Panhandle, and the railroad's expansive clay zones in Wyoming and Colorado. Consider swell testing (ASTM D4546) when A > 1.0.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| PI | plasticity index | Lab test | PI = LL − PL from Atterberg limits (ASTM D4318). | CL 7–30, CH 25–80 · by USCS group |
The shrinkage limit (ASTM D4943) is the water content below which further drying causes no volume change. For railroad embankments in seasonally dry climates (Class I railroad located in the Great Plains, Class I railroads located in the Southwest and the Canadian Prairies), SL data inform desiccation crack depth estimates used in slope stability models (Chapter 6.3).
Table 8-S3. Typical Atterberg limits for clay minerals (Carter & Bentley, Table 2.2.2)
| Mineral | PL (Ca++) | LL (Ca++) | PL (Na+) | LL (Na+) | Typical activity |
|---|---|---|---|---|---|
| Montmorillonite | 65–79 | 123–177 | 86–97 | 280–700 | Ca 1.5; Na 7.2 |
| Illite | 36–42 | 69–100 | 34–41 | 61–75 | 0.9 |
| Kaolinite | 26–36 | 34–73 | 26–28 | 29–52 | 0.33–0.46 |
Table 8-S4. Swelling potential from plasticity index (Carter & Bentley, Table 2.2.4)
| Swelling potential | PI (Seed et al., 1962) | PI (Krebs & Walker, 1971) |
|---|---|---|
| Low | 0–15 | 0–15 |
| Medium | 10–30 | 15–24 |
| High | 20–55 | 25–46 |
| Very high | > 40 | > 46 |
Table 8-S5. Expansion potential from shrinkage limit and linear shrinkage (after Altmeyer, 1955)
| Potential | Shrinkage limit (%) | Linear shrinkage (%) |
|---|---|---|
| Critical | < 10 | > 8 |
| Marginal | 10–12 | 5–8 |
| Non-critical | > 12 | < 5 |
Swelling potential here is the percent swell of a laterally confined specimen compacted at optimum moisture (standard Proctor) and soaked under a 1 psi surcharge: 0–1.5% low, 1.5–5% medium, 5–25% high, > 25% very high. Seed et al. (1962) related it to plasticity as S = 60K·PI2.44 with K = 3.6 × 10−5, valid for clay contents of 8–65% and accurate to about ±33% of lab values. Because each index is uncertain, Holtz and Gibbs (adopted by USBR) recommend judging expansion potential from colloid content, PI and shrinkage limit together, then confirming with an ASTM D4546 swell test where the result matters for track geometry.
Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed. Wiley
For large corridor programs, NYSDOT’s GTM-7 (based on AASHTO T 89) allows a one-point liquid limit: accept a trial that closes the groove in 15–30 drops, with at least two consistent consecutive closures, then LL = w (N/25)0.12. The factor ranges from 0.941 at 15 drops to 1.022 at 30 drops. Reserve multi-point flow curves for design-critical samples and borderline A-line soils.
Source: New York State DOT Geotechnical Engineering Bureau (2015). Test Method for Liquid Limit, Plastic Limit, and Plasticity Index, GTM-7 Rev. 2
Step 1 — Coarse or Fine?
Step 2 — For Coarse-grained soils:
Step 3 — For Fine-grained soils (plot on Casagrande Plasticity Chart):
PI = 0.73 × (LL − 20)
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| PI | plasticity index = 0.73 × (LL − 20) | Lab test | PI = LL − PL from Atterberg limits (ASTM D4318). | CL 7–30, CH 25–80 · by USCS group |
| LL | liquid limit | Lab test | Atterberg limits (ASTM D4318) on the minus No. 40 fraction. | CL 20–50, CH 50–110 · by USCS group |
PI = 0.9 × (LL − 8)
Classification matrix:
| Position on Chart | LL < 50 (Low Plasticity) | LL ≥ 50 (High Plasticity) |
|---|---|---|
| Above A-line | CL (lean clay) | CH (fat clay) |
| Below A-line or PI < 4 | ML (silt) | MH (elastic silt) |
| Organic (LL_oven < 0.75 × LL_wet) | OL | OH |
| Fibrous, very high water content | Pt (peat) | Pt |
Borderline classifications (e.g., CL-ML for soils plotting near the A-line with 4 ≤ PI ≤ 7) must be noted on boring logs submitted to the owner railroads — ASTM D2487 itself requires the dual symbol in this zone.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| PI | plasticity index = 0.9 × (LL − 8) | Lab test | PI = LL − PL from Atterberg limits (ASTM D4318). | CL 7–30, CH 25–80 · by USCS group |
| LL | liquid limit | Lab test | Atterberg limits (ASTM D4318) on the minus No. 40 fraction. | CL 20–50, CH 50–110 · by USCS group |
Field logs use the visual-manual procedure (ASTM D2488). The USACE field tests, run on the minus No. 40 fraction:
| Test | Procedure | Interpretation |
|---|---|---|
| Dilatancy | Shake a 1-in. pat of moist soil in the palm, then squeeze it | Very fine clean sand: quick, distinct water and gloss. Inorganic silt: moderately quick. Plastic clay: no reaction. |
| Dry strength | Dry a putty-consistency pat and crumble it between the fingers | Strength increases with plasticity; high for fat clay. Silts and silty sands are slight — sand feels gritty, silt feels like flour. Break on a fresh surface, not a shrinkage crack. |
| Toughness | Roll a 1/8-in. thread repeatedly until it crumbles at the plastic limit, then knead the pieces | Stiffer threads and tougher lumps at the PL indicate higher clay content. |
| Ribbon | Flatten a 1/2–3/4 in. roll to 1/8–1/4 in. thick | High-plasticity clay: 8–10 in. ribbon; shorter for lower plasticity; non-plastic soil will not ribbon. |





USACE also lists quick checks for organic matter (odor), calcium carbonate cementation (dilute HCl), and whether a “rock-like” material is shale (slaking in water). Record color with Munsell soil color charts — color reflects mineralogy, drainage, and organic content.
Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804
Coarse vs. fine follows the 50-50 rule: more than 50% passing the No. 200 sieve is fine-grained, and in coarse soils the No. 4 sieve separates sand from gravel. In a name like “silty sand,” the second word is the predominant material. Clay particles carry a charge that gives cohesion and plasticity; silt does not. Dry silt blows away as dust, wet silt feels slippery and wet clay feels sticky. The distinction matters operationally, because silts and fine sands can fail very rapidly while deep clay embankments tend to creep.

| Test | Silt | Low-plasticity clay | High-plasticity clay |
|---|---|---|---|
| Dilatancy (shake a wet pat) | Water appears quickly; pat loses shape | Water appears slowly; holds shape | No change |
| Toughness (roll a 1/8-in. thread) | Difficult to roll any thread | Easy, moderately plastic thread | Possible but difficult; very stiff |
| Dry strength (crush a dry 1/8-in. piece) | Crumbles with little pressure | Moderate | Cannot be broken with fingers |
Plasticity index guide used in the course: 0 non-plastic, 1–5 slightly plastic, 5–10 low, 10–20 medium, 20–40 high, and 40+ very high. Organic soils (topsoil, peat) are identified by fiber, color and odor and should be avoided as subgrade.
After Geotechnology for Railroaders Program, Module 2; §08, §10. Full reference under Supplemental References.

After Selig & Waters (1994), ch. 3. Full reference under Supplemental References.
ASTM D2487 (in the library's Soil Mechanics folder) defines the Unified Soil Classification System as a fixed sequence of decisions: fines content first, then the predominant coarse fraction or the plasticity chart, then gradation, and finally the modifiers that make up the group name. Getting the name right matters on railroad work because the name carries the behavior: a CL subgrade pumps when wet, an ML is frost susceptible and erodible, and an SP-SM may be suitable subballast while an SC is not.
| Step | Test | Outcome |
|---|---|---|
| 1 | Fines (passing No. 200) ≥ 50%? | Yes: fine-grained (CL, ML, CH, MH, OL, OH). No: coarse-grained. |
| 2 | Coarse: gravel > sand? | Gravel (G) or sand (S) |
| 3 | Coarse with fines < 5% | Well graded (Cu ≥ 4 gravel or ≥ 6 sand and 1 ≤ Cc ≤ 3): GW/SW; otherwise GP/SP |
| 4 | Coarse with fines 5 to 12% | Dual symbol, e.g. SP-SM, SW-SC |
| 5 | Coarse with fines > 12% | GM, GC, SM, SC (or GC-GM, SC-SM if fines are CL-ML) |
| 6 | Plasticity chart | A-line PI = 0.73(LL − 20); CL-ML band PI 4 to 7; LL 50 divides low and high plasticity |
| 7 | Modifiers | “with sand/gravel” at 15% or more; “sandy/gravelly” when the coarse fraction of a fine-grained soil is 30% or more |
Equation 2.2-15. Gradation coefficients
| Sample | Data | Classification |
|---|---|---|
| Embankment fill | 18% gravel, 55% sand, 27% fines; LL 34, PL 19 | SC, clayey sand with gravel |
| Soft subgrade under a pumping joint | 2% gravel, 10% sand, 88% fines; LL 63, PL 25 | CH, fat clay |
Open the USCS classification calculator →
Group symbol and group name from gradation and Atterberg limits per ASTM D2487, with a plasticity chart and a railroad note for the group.
These are the two samples of Table 2.2-5, classified by hand so the calculator output can be checked. One is a sandy embankment fill; the other is the soft subgrade under a pumping joint.
| Variable | Value | Description |
|---|---|---|
| Sample A | 18% gravel, 55% sand, 27% fines; LL = 34, PL = 19 | Embankment fill |
| Sample B | 2% gravel, 10% sand, 88% fines; LL = 63, PL = 25 | Soft subgrade under a pumping joint |
Sample A: SC, clayey sand with gravel. Sample B: CH, fat clay.
The fat clay under the pumping joint is the classic pumping material: high plasticity, weak when wet, and fine enough to be carried up into the ballast. The clayey sand fill is serviceable but its plastic fines make it sensitive to drainage. Checking calculator output by hand like this once per project catches data entry errors early.
These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.
Many older boring logs, especially in the northeastern United States, use the Burmister system instead of USCS. It describes soil by its principal component in capitals and the minor components with proportion terms:
| Term | Percent by weight | Example |
|---|---|---|
| (principal, in capitals) | over 50 | SAND |
| and | 35 to 50 | SAND and GRAVEL |
| some | 20 to 35 | SAND, some silt |
| little | 10 to 20 | SAND, little gravel |
| trace | 1 to 10 | SAND, trace silt |
Gradation of the principal component is shown by size terms (coarse, medium, fine), for example “c-f SAND” for coarse-to-fine sand. Plasticity of fines is described separately, so a Burmister description alone does not give a USCS group.
For railroad work: Railroad files often hold decades-old logs written in Burmister terms. Translate them to approximate USCS groups for the desktop study (Chapter 3.2), treating the result as provisional until confirmed by new samples and index tests. “Some silt” (20% to 35%) can mean a fines content that changes the soil from SM-type behavior to frost-susceptible and pumping-prone subgrade (Section 2.2.7).
Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 203, Burmister Soil Classification System. Full reference under Supplemental References.
The AASHTO classification (AASHTO M 145) is used specifically for pavement subgrade evaluation and is the primary soil classification system referenced by many owner railroads for track subgrade rehabilitation projects. It classifies soils into Groups A-1 through A-7 based on gradation and Atterberg limits.
| Group | % Pass No. 200 | LL | PI | Typical USCS | Subgrade Rating |
|---|---|---|---|---|---|
| A-1-a | ≤ 15 | — | ≤ 6 | GW, GP | Excellent |
| A-1-b | ≤ 25 | — | ≤ 6 | SW, SP, GM | Excellent |
| A-2-4 | ≤ 35 | ≤ 40 | ≤ 10 | GM, GC, SM | Good |
| A-2-6 | ≤ 35 | ≤ 40 | > 10 | GC, SC | Good-Fair |
| A-3 | ≤ 10 | NP | NP | SP | Good |
| A-4 | > 36 | ≤ 40 | ≤ 10 | ML, OL | Fair |
| A-5 | > 36 | > 40 | ≤ 10 | MH, OH | Fair-Poor |
| A-6 | > 36 | ≤ 40 | > 10 | CL | Poor |
| A-7-5 | > 36 | > 40 | ≤ LL − 30 | MH, CH | Poor |
| A-7-6 | > 36 | > 40 | > LL − 30 | CH | Very Poor |
Group Index (GI) — quantifies subgrade quality within a group:
GI = (F − 35) × [0.2 + 0.005(LL − 40)] + 0.01(F − 15)(PI − 10)
Where:
GI = 0 indicates good subgrade material, and higher values indicate poorer material. AASHTO M 145 sets no upper limit; highly plastic clays can exceed 20. A high group index (GI ≥ 12 is a common trigger) warrants a ground improvement evaluation (Chapter 7.2) for track subgrade.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| GI | intermediate value computed on this page | Another equation | Computed: GI = (F − 35) × [0.2 + 0.005(LL − 40)] + 0.01(F − 15)(PI − 10) | project-specific |
| F | percent passing No | Lab test | Percent passing No. 200 sieve: washed sieve analysis (ASTM D1140 / D6913). | clean < 5%; with fines > 12% · by USCS group |
| LL | liquid limit (%) | Lab test | Atterberg limits (ASTM D4318) on the minus No. 40 fraction. | CL 20–50, CH 50–110 · by USCS group |
| PI | plasticity index (%) | Lab test | PI = LL − PL from Atterberg limits (ASTM D4318). | CL 7–30, CH 25–80 · by USCS group |
RQD is calculated from rock core runs per the procedure established in Chapter 4.1. To summarize:




RQD (%) = [Σ length of sound core pieces ≥ 4 in.] / [Total core run length] × 100
| RQD (%) | Rock Quality |
|---|---|
| 0–25 | Very Poor |
| 25–50 | Poor |
| 50–75 | Fair |
| 75–90 | Good |
| 90–100 | Excellent |
Calculate and record RQD on every core run. Confirm any owner-specific uses of RQD, such as rock acceptance criteria, against the owner railroad's current standards.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| RQD (%) | [Σ length of intact core pieces ≥ 2 in.] / [Total core run length] × 100 | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
RMR classifies the overall rock mass quality using six parameters, each assigned a rating:

RMR = R₁ + R₂ + R₃ + R₄ + R₅ + R₆
| Parameter | Rating Range | Description |
|---|---|---|
| R₁ — UCS (psi) | 0–15 | UCS < 145 psi (1 MPa) → 0; UCS > 36,000 psi (250 MPa) → 15 |
| R₂ — RQD (%) | 3–20 | RQD 0–25% → 3; RQD 90–100% → 20 |
| R₃ — Spacing of discontinuities | 5–20 | < 2.4 in. → 5; > 6.6 ft → 20 |
| R₄ — Condition of discontinuities | 0–30 | Soft infill > 0.2 in. → 0; very rough, unweathered → 30 |
| R₅ — Groundwater | 0–15 | Flowing water → 0; dry → 15 |
| R₆ — Discontinuity orientation | 0 to −60 | Adjustment for orientation: 0 to −12 for tunnels, 0 to −25 for foundations, 0 to −60 for slopes |
| RMR | Rock Class | Description |
|---|---|---|
| 81–100 | I | Very good rock |
| 61–80 | II | Good rock |
| 41–60 | III | Fair rock |
| 21–40 | IV | Poor rock |
| 0–20 | V | Very poor rock |
RMR is used on Class I railroad tunnel feasibility studies and on Class I railroad bridge pier excavation designs in the Canadian Shield. RMR is a common basis for classifying rock cut stability.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| RMR | R₁ + R₂ + R₃ + R₄ + R₅ + R₆ | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
GSI provides a rock mass characterization input for the Hoek-Brown failure criterion, used in rock slope stability analyses (Chapter 6.3) for Class I railroad projects. GSI is estimated from field observation of structure and surface condition of discontinuities:
σ'₁ = σ'₃ + UCS × (m_b × σ'₃/UCS + s)^a
Where:
Include the GSI estimation chart used (Marinos and Hoek 2000), with the selected value marked, as a figure in the geotechnical data report (Chapter 8.4).
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| UCS | uniaxial compressive strength of intact rock (psi) | Lab test | Uniaxial compression of rock core (ASTM D7012); point load index (D5731) for screening. | shale 1,000–15,000; sandstone 5,000–25,000; granite 15,000–40,000 psi |
| mb | reduced Hoek-Brown constant = m_i × exp((GSI − 100)/(28 − 14D)) | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
| s | intermediate value computed on this page | Another equation | Computed: s = exp((GSI − 100)/(9 − 3D)) | project-specific |
| a | intermediate value computed on this page | Another equation | Computed: a = 0.5 + (1/6)(exp(−GSI/15) − exp(−20/3)) | project-specific |
| D | disturbance factor (0 = undisturbed | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
| mi | intact rock constant (from Hoek-Brown tables | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |

The Q-system (Tunneling Quality Index) is used when Class I railroad projects involve tunnel or large underground excavation design:
Q = (RQD / J_n) × (J_r / J_a) × (J_w / SRF)
Where:
| Q | Rock Class | Support Category |
|---|---|---|
| > 40 | Very good or better | Spot bolting |
| 10–40 | Good | Systematic bolting |
| 1–10 | Fair to poor | Shotcrete + bolts |
| 0.1–1 | Very poor | Multiple passes |
| < 0.1 | Extremely poor | Heavy support |
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Q | (RQD / J_n) × (J_r / J_a) × (J_w / SRF) | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
| Jn | joint set number (3 for one set | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
| Jr | joint roughness number (1 = smooth planar | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
| Ja | joint alteration number (1 = unaltered | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
| Jw | joint water reduction factor (1 = dry | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
| SRF | stress reduction factor (1 = low stress | Field mapping / core logging | From core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water). | see rating tables |
ASTM D6032, FHWA GEC 5 and the USBR field manual all define RQD using sound core pieces 4 in. or longer, measured along the core centerline, as Chapter 4.1 (Section 4.1.5.2) states. GEC 5 adds two rules often missed: pieces that are not hard and sound are excluded even if longer than 4 in. (so weathered rock is downgraded), and RQD is not appropriate for BQ/BX core — NQ/NX is optimal.
Table 8-S1. Rock material strength grades (GEC 5, Table 37)
| Grade | Description | Field identification | UCS range (psi) |
|---|---|---|---|
| R0 | Extremely weak | Indented by thumbnail | 36–145 |
| R1 | Very weak | Crumbles under firm blows of hammer point; peeled by pocket knife | 145–725 |
| R2 | Weak | Peeled by knife with difficulty; shallow indentations with firm hammer blow | 725–3,600 |
| R3 | Medium strong | Cannot be scraped or peeled with knife; fractured with single firm blow | 3,600–7,250 |
| R4 | Strong | More than one blow needed to fracture | 7,250–14,500 |
| R5 | Very strong | Many blows needed to fracture | 14,500–36,000 |
| R6 | Extremely strong | Can only be chipped | > 36,000 |
Table 8-S2. Weathering grades (GEC 5, Table 38)
| Grade | Term | Description |
|---|---|---|
| I | Fresh | No visible weathering; slight discoloration on major discontinuities possible |
| II | Slightly weathered | Discoloration of rock material and discontinuity surfaces; surface may be somewhat weaker |
| III | Moderately weathered | Less than half decomposed/disintegrated to soil; fresh or discolored rock as framework or corestones |
| IV | Highly weathered | More than half decomposed/disintegrated to soil; rock as framework or corestones |
| V | Completely weathered | All decomposed to soil; original mass structure largely intact |
| VI | Residual soil | All converted to soil; structure and fabric destroyed; not significantly transported |
A complete rock description strings these together in a set order, e.g. “slightly weathered, crystalline, gray, fine-grained, medium strong (R3) basalt,” followed by a rock-mass description of joint sets, spacing, persistence, infilling, roughness and seepage (GEC 5, after Wyllie). The strength grade gives the R1 input to RMR when no UCS test is available.
Source: Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017)) · U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I

If an excavator can dig it, treat it as soil; once rock breaks apart, it behaves like soil. Igneous extrusive rock cooled quickly (basalt) is fine-grained and dark, and it is the preferred ballast family: the darker and finer, the better. Slowly cooled granite is coarser and less suitable. Sedimentary rock (sandstone, limestone) and metamorphic rock are generally not recommended for ballast; soft rock can grind into a mud spot within a few years.

After Geotechnology for Railroaders Program, Module 2, Module 3; Module 2 §07; Module 3 §05. Full reference under Supplemental References.
For Class I railroad mainline located in the prairies and Class I railroad operations located in Canada, frost susceptibility is a primary classification criterion. The U.S. Army Corps of Engineers frost susceptibility classification:
| FS Class | Description | Frost Heave Risk |
|---|---|---|
| FS-0 | Non-frost-susceptible | Negligible |
| FS-1 | Slightly frost-susceptible | Slight |
| FS-2 | Moderately frost-susceptible | Moderate |
| FS-3 | Moderately to highly frost-susceptible | High |
| FS-4 | Very highly frost-susceptible | Very High |
This manual labels the USACE frost groups FS-0 (NFS) and FS-1 to FS-4 (F1 to F4). Key criteria: GW, GP, SW, SP with < 3% finer than 0.02 mm = FS-0. All silts (ML, MH) = FS-4. Clays with PI > 12 = FS-3; lean clays with PI < 12 and varved clays = FS-4. In cold regions, assign a frost susceptibility class to all subgrade materials; Use a frost index analysis (freezing degree-days) together with the frost susceptibility class to set the minimum non-frost-susceptible ballast and subballast thickness.
The standard USACE groups (1965), which the FS classes above correspond to, are defined by the percent finer than 0.02 mm (20 μm), not the No. 200 sieve:
| Group | Soils |
|---|---|
| NFS | All soils with < 3% finer than 0.02 mm |
| F1 | Gravelly soils with 3–10% finer than 0.02 mm |
| F2 | Gravelly soils with 10–20% finer; sands with 3–15% finer than 0.02 mm |
| F3 | Gravelly soils > 20% finer; sands (except very fine silty sands) > 15% finer; clays with PI > 12 |
| F4 | All silts; very fine silty sands > 15% finer; lean clays with PI < 12; varved clays and other banded fine-grained sediments |
Susceptibility increases from F1 to F4. Carter and Bentley note that kaolinitic clays tend to heave more than montmorillonitic clays because water is more mobile in non-expanding clay structures — a counter-intuitive point when CH subgrade is assumed to be low frost risk. A quick screen (TRRL, 1970): granular soil with < 10% passing No. 200 is not susceptible; granular soil with > 10% fines or cohesive soil with PI < 20 is susceptible; cohesive soil with PI > 20 is not.
Confirm the frost-susceptibility classification with a hydrometer test, because the percent finer than 0.02 mm cannot be read from a sieve analysis.
Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed. Wiley
Profillidis ranks silt as very frost-susceptible, clay as susceptible, and sand and gravel as not susceptible. Frost susceptibility is the third subgrade parameter, after soil class and hydrogeology, in climates where freezing is frequent. Protection is sized with the frost index ( Chapter 2.3, Section 2.3.5.3 ).
After Profillidis (2014), §9.4, §9.11.1. Full reference under Supplemental References.
| Sample ID | Depth (ft) | % Pass No. 200 | LL (%) | PL (%) | PI (%) | USCS | AASHTO | GI | LI | Notes |
|---|---|---|---|---|---|---|---|---|---|---|
| B-1, S-2 | 3–5 | 68 | 52 | 22 | 30 | CH | A-7-6 | 19 | 0.83 | Fat clay; soft consistency; swell concern |
| B-1, S-4 | 8–10 | 44 | 38 | 19 | 19 | CL | A-6 | 4 | 0.47 | Lean clay; medium stiff |
| B-2, S-1 | 1–3 | 22 | 28 | 14 | 14 | SC | A-2-6 | 0 | 0.21 | Clayey sand; fill material suspected |
| B-2, S-3 | 6–8 | 78 | 61 | 27 | 34 | CH | A-7-6 | 28 | 1.05 | Fat clay; LI > 1.0 indicates near-liquid state |
| B-3, S-2 | 4–6 | 12 | NP | NP | NP | SP-SM | A-2-4 | 0 | — | Fine sand with silt; non-plastic |
| B-3, S-5 | 14–16 | 55 | 44 | 21 | 23 | CL | A-7-6 | 10 | 0.63 | Lean clay; plots above the A-line |
B-2, S-3 at 6–8 ft: LI = 1.05 and GI = 28 indicate very poor subgrade.
A sample from a bridge approach on a Class I railroad located in the Appalachians was recovered at 12 to 14 ft. Classification is the first thing done with any sample, because the group symbol tells the engineer which strength, compressibility and frost behavior to expect before any other test is run. This example takes the sample through both systems the manual uses: USCS for engineering behavior and AASHTO M 145 for subgrade rating.
| Variable | Value | Description |
|---|---|---|
| F | 62% | Percent passing the No. 200 sieve |
| LL | 48% | Liquid limit |
| PL | 21% | Plastic limit |
| wn | 33% | Natural water content |
USCS: CL, lean clay. AASHTO: A-7-6 with GI = 14. LI = 0.44, stiff to medium.
Both systems say the same thing in different words: a plastic, fine-grained soil that will lose strength when wet and make a poor subgrade. A group index of 14 places it near the bottom of the AASHTO rating. On a bridge approach this sample sets up a CBR evaluation (Chapter 7.3) and a check of whether ground improvement is needed (Chapter 7.2).
Subgrade fill is being evaluated for a new intermodal yard on a Class I railroad located in the Midwest. For coarse-grained soils the classification rests on the shape of the grain-size curve, so the sieve results are read at three points, D10, D30 and D60, to decide whether the sand is well or poorly graded.
| Variable | Value | Description |
|---|---|---|
| % passing 1 in., No. 4, No. 10, No. 40, No. 200 | 100, 88, 74, 42, 7 | Sieve analysis |
| D10 | 0.087 mm (0.0034 in.) | Interpolated on a log scale from the sieve data |
| D30 | 0.23 mm (0.0092 in.) | As above |
| D60 | 1.02 mm (0.040 in.) | As above |
| LL, PL | Non-plastic (NP) | Atterberg limits of the fines |
USCS: SP-SM, poorly graded sand with silt. AASHTO: A-1-b, GI = 0.
Poorly graded here means the curve has a gap or a flat step in the middle (Cc below 1), not that the sand is unsuitable. It drains, it is non-plastic and it rates at the top of the AASHTO scale. It is generally acceptable as yard subgrade without ground improvement, subject to proof-roll acceptance during construction (Chapter 5.3).
A rock cut on a Class I railroad located in the mountains of British Columbia is being evaluated from NQ core and face mapping. The Rock Mass Rating (Bieniawski 1989) adds six ratings: five for the rock and its joints, and one adjustment for how the joints are oriented relative to the cut. The example shows how much that last term can matter.
| Variable | Value | Description |
|---|---|---|
| UCS | 14,500 psi (100 MPa) | Uniaxial compressive strength, laboratory (Chapter 5.2) |
| RQD | 68% | Rock quality designation from the core log (Chapter 4.1) |
| s | 6 in. (152 mm) | Average discontinuity spacing |
| Condition | Slightly rough; separation under 0.04 in. (1 mm); slightly weathered walls | Discontinuity condition |
| Water | Damp, no free water | Groundwater condition |
| Orientation | Fair for a slope | Joint orientation relative to the cut face |
Basic RMR = 63, Class II (good rock). With the slope orientation adjustment, RMR = 38, Class IV (poor rock).
The 25-point adjustment is larger than any single rock property rating except joint condition, so the cut is controlled by how its joints are oriented, not by the quality of the rock. That points the next step toward a kinematic analysis (Chapter 6.3) and the Slope Mass Rating (Romana), which treats the slope orientation in more detail, and toward pattern bolting as a likely remedy. Production blasting damages the rock near the face; a disturbance factor D = 0.7 should be used in any Hoek-Brown strength estimate.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
Checklist · Part V · Subsurface Exploration
Field (During Drilling and Sampling)
Laboratory
A sample from the foundation of a Class I railroad embankment that is to be raised for a new grade has the gradation, Atterberg limits and water content shown. The engineer must classify the soil in both the USCS and AASHTO systems, find its liquidity index, and say what the results mean for carrying the added embankment load.
| Variable | Value | Description |
|---|---|---|
| F | 71% | Percent passing No. 200 |
| LL | 56% | Liquid limit |
| PL | 24% | Plastic limit |
| wn | 41% | Natural water content |
(a) CH, fat clay. (b) A-7-6, GI = 22. (c) LI = 0.53, medium consistency.
The soil is highly plastic but not near its liquid limit, so it is not in an unstable state today. A GI of 22 is a very poor subgrade rating, and a fat clay foundation will consolidate under fill. Any embankment load over about 3 ft of fill warrants a settlement and ground improvement assessment (Chapters 6.2 and 7.2).
A Class I railroad is building a new yard lead and wants to know whether the sand exposed at subgrade level can stay in place. A gradation test gave the grain sizes shown, with 9% non-plastic fines. The engineer must find the gradation coefficients, assign the USCS symbol, and comment on the sand as a track subgrade.
| Variable | Value | Description |
|---|---|---|
| D10 | 0.003 in. | Grain size at 10% passing |
| D30 | 0.019 in. | Grain size at 30% passing |
| D60 | 0.090 in. | Grain size at 60% passing |
| F | 9% | Fines content |
| LL | NP | Fines are non-plastic |
Cu = 30.0 and Cc = 1.34; the sand is well graded. With 9% non-plastic fines it is SW-SM, well-graded sand with silt.
SW-SM is generally a suitable subgrade material. Its performance depends on compaction, so density is verified during construction (Chapter 5.3).
A railroad embankment over soft plastic clay is to be checked for stability before a speed increase. Field vane tests gave the strength shown, and laboratory tests gave the plasticity index and clay fraction. The engineer must correct the vane strength for use in the stability analysis and screen the clay for swell potential.
Field vane shear tests overestimate the strength of plastic clays mobilized in an embankment failure, so the vane value is reduced by Bjerrum’s factor. The same sample’s activity screens it for swell.
| Variable | Value | Description |
|---|---|---|
| su,VST | 0.22 tsf | Field vane shear strength |
| PI | 48% | Plasticity index |
| Clay fraction | 35% | Percent finer than 0.002 mm |
| μ | 0.85 at PI = 40%; 0.75 at PI = 60% | Bjerrum correction factors read from the chart |
(a) Corrected su = 0.178 tsf (356 psf). (b) A = 1.37, an active clay.
Using the uncorrected vane value would overstate the strength by about 19%. The activity says the clay mineral is probably smectite, so swell testing (ASTM D4546) is warranted before the subgrade or any structure is designed. Both the corrected strength and the swell data belong in the geotechnical report (Chapter 8.4).
A passenger rail corridor is studying a short tunnel to replace a sharp curve around a ridge. A 10-ft core run from the feasibility boring gave the rock strength, RQD, joint spacing and condition shown, in a dry hole with joints favorably oriented for tunneling. The engineer must compute the rock mass rating and class for the tunnel feasibility report.
A 10-ft core run from a tunnel feasibility study on a passenger corridor. The same six RMR ratings are used as for a slope, but the orientation adjustment is taken from the table for tunnels.
| Variable | Value | Description |
|---|---|---|
| UCS | 22,000 psi (152 MPa) | Uniaxial compressive strength |
| RQD | 74% | Rock quality designation |
| s | 1.5 ft (457 mm) | Average joint spacing |
| Condition | Slightly rough, no infill, unweathered | Joint condition |
| Water | Dry borehole | Groundwater |
| Orientation | Favorable for tunneling | Joint orientation |
RMR = 73, Class II (good rock).
For a tunnel the orientation adjustment is small when the joints are favorable, so the rating is governed by the rock itself. If the owner’s criterion for unsupported spans is, say, RMR of 60 or more, this rock meets it. A Q-system check is still recommended before tunnel support recommendations are finalized, because the two systems weigh joint sets and stress differently.
A Class I railroad located in Manitoba is rebuilding a main track that heaves every winter. The subgrade is a silt with the fines content shown, in a climate with deep seasonal frost. The engineer must assign the frost susceptibility group and explain what it means for the depth of non-frost-susceptible material above the subgrade.
A subgrade sample from a Class I railroad located in Manitoba. Frost susceptibility is assigned from the soil type and the percentage finer than 0.02 mm, and it decides how much non-frost-susceptible material must sit above the subgrade.
| Variable | Value | Description |
|---|---|---|
| USCS | ML | Silt |
| % finer than 0.02 mm | 18% | Fines in the frost-critical size range |
| Climate | About 50°N | Deep seasonal frost |
No equation is needed; the answer follows from the criteria listed under Given.
USACE group F4, the most frost-susceptible group.
Silt with water available is the material that heaves most and loses most strength on thaw (Section 3.8.8). Document the frost group in the geotechnical data report, determine the site freezing index, and provide a non-frost-susceptible (NFS) granular subballast over the subgrade with its thickness set by a site-specific freeze-depth calculation, such as the modified Berggren equation (Chapter 7.3). Track geometry should be monitored (Chapter 5.3) through the first few freeze-thaw cycles after construction.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S13 under Supplemental References.
Related section: 2.2.2 Grain-Size Analysis
On a cut-to-fill earthworks job, rocks up to 24 in were visible and many particles exceeded 10 in, yet four of five grading certificates gave 6 in as the maximum size. Look calls this survivorship bias: the large pieces are left behind when the sample is taken, so they never appear in the result. Visual observation should always be part of the assessment.
Averaged gradings before and after compaction with two 19-ton vibrating rollers were similar to each other but clearly different from the pre-compaction gradings, because rolling breaks the material down. A specification limiting fines to 7% passing the No. 200 sieve would pass this material before compaction and fail it after. Since performance depends on the compacted state there is a case for post-compaction testing; since roller type and size change the result there is a case for pre-compaction testing. Either way, the specification has to say which.
For railroad work: the same question arises for subballast and granular fill acceptance. State in the special provision whether gradation is tested at the source, on the stockpile, or after placement and compaction.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §4.6, pp. 114. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 2.2.2 Grain-Size Analysis
Four stockpile samples of extremely to slightly weathered sandstone/siltstone all reported 100% passing 1½ in., yet rocks up to 12 in were visible in the pile. After rolling, 24 post-compaction gradings gave a maximum particle size under 3 in for both roller types, while the embankment surface still showed 12 in. pieces. The “increase” in coarse fraction after compaction is an artefact of the biased pre-compaction samples. Fines rose only slightly, from 10% to about 11%, although rolling visibly broke down the large weathered particles.
Look’s conclusion is that the industry places misplaced confidence in test certificates as proof that a material specification has been met.
Table 8-LK1. Average gradings of XW–SW sandstone/siltstone, % passing (after Look 2023, Table 5.7)
| Sieve | Pre-compaction (n = 4) | Smooth drum (n = 12) | Padfoot (n = 12) |
|---|---|---|---|
| 3 in. | 100.0 | 100.0 | 100.0 |
| 1½ in. | 100.0 | 82.8 | 80.3 |
| ¾ in. | 75.5 | 65.4 | 61.8 |
| No. 8 | 33.0 | 25.0 | 23.9 |
| No. 40 | 27.0 | 21.6 | 20.4 |
| No. 200 | 10.0 | 11.1 | 10.8 |

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §5.9, pp. 142–144. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Expansive clay subgrades produce some of the most persistent track geometry problems: seasonal heave and shrinkage under the track, and loss of support along culverts and wall footings. The FHWA's Evaluation of Soil and Rock Properties (GEC 5, Section 7.3) sets out the approach. Clays with PI below 15 generally do not swell. Above that, clay content and activity are checked, then undisturbed samples are tested in the oedometer for swell and swell pressure (ASTM D4546). Volume change is limited to the active zone, the depth over which moisture changes with the seasons. Skempton's activity, PI divided by the percentage finer than 0.002 mm, points to the clay mineral: about 0.3 to 0.5 for kaolinite, 0.5 to 1.2 for illite and 1.5 to 7 for montmorillonite (Das Table 4.1). Das notes that compaction moisture can be chosen to limit swelling and shrinkage.
Equation 2.2-16. Activity and heave
| Limitation | Consequence |
|---|---|
| Lateral swell and lateral confinement are not reproduced | Vertical swell may misstate expansion where the soil is not laterally confined, for example behind abutments |
| Laboratory swell rate does not reflect field water availability | Field heave may develop more slowly, or more completely, than in the test |
| Long-term swell may continue after primary swell | Add it where the design will have long-term access to water |
A track subgrade has four clay layers extending through a 10 ft active zone. The PIs are 38, 42, 30 and 18, and clay contents are 30 to 50%, giving activities up to 0.84, in the illite range. These inputs are illustrative, not data from a real site. Swell tests at the expected load gave 4.5, 3.2 and 1.5% for the upper three layers. Beneath 2 ft of ballast and subballast, the estimated heave is 2.77 in. Doubling the non-expansive cover to 4 ft takes more clay out of the active zone and lowers it to 2.41 in. Keeping moisture constant also helps: drainage away from the track, sealing ditches, and avoiding trees near the line.
Open the expansive clay heave calculator →
Activity and likely clay mineral for each layer, the PI screen, heave within the active zone from swell test results, and the effect of non-expansive cover thickness.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.
A boring log is only as useful as its soil descriptions. Laboratory classification (USCS, Section 2.2.4.2) is done on a few samples; every other sample is described in the field from what the driller and the engineer can see and feel. A consistent “word picture” lets the reader of the log, often years later, picture the soil and its behavior: what is the main soil, what else is in it in amounts that change its behavior, how dense or stiff it is, and whether it is natural ground or fill. The system summarized here, a modified Unified description used by a state DOT, is simple enough to apply on the drill rig and maps directly onto the USCS group names.
Primary constituent. If more than half the sample passes the #200 sieve it is fine-grained, and the primary constituent is clay or silt by behavior: clay is plastic, rolls to a 1/8-in. thread and is strong when dry; silt is non-plastic, crumbles, and shows water on its surface when the sample is jolted in the hand. Otherwise the soil is coarse-grained and the primary constituent is sand or gravel, whichever is larger, with its size range (fine, medium, coarse) and, where useful, its shape (rounded, angular) written immediately before it. Peat, muck and marl are organic primaries.
Secondary and tertiary constituents. A constituent present in enough quantity to change the behavior is secondary and becomes an adjective before the primary (Silty, Sandy, Gravelly), listed in ascending order of importance. A constituent that is readily seen but does not change the behavior is tertiary and is added at the end as “with ___”. Smaller amounts may be noted as “Trace of ___”.
| Constituent | Secondary (adjective before primary) | Tertiary (“with ___”) | Trace |
|---|---|---|---|
| Fine-grained (silt, clay) | more than 12% | 5 to 12% | less than 5% |
| Coarse-grained (sand, gravel) | more than 30% | 15 to 29% | less than 15% |
Strength and descriptors. The strength term comes first: relative density for sand, gravel and silt, consistency for clay. Color, moisture (dry, moist, saturated, judged before the sample is handled) and structure (fissured, laminated, varved, blocky, mottled) follow in ascending order of significance, then the secondary constituents, the size and the primary. “Fill” follows the primary; inclusions such as lenses or layers of another soil are added after the complete description.
| Granular term | SPT N | Relative density | Cohesive term | Cohesion (psf) | SPT N | Manual index |
|---|---|---|---|---|---|---|
| Very Loose | < 4 | 0–15% | Very Soft | 0–250 | < 2 | Extrudes between fingers |
| Loose | 4–10 | 15–35% | Soft | 250–500 | 2–4 | Molded by light finger pressure |
| Medium Dense | 10–30 | 35–65% | Medium Stiff | 500–1,000 | 4–8 | Molded by firm finger pressure |
| Dense | 30–50 | 65–85% | Stiff | 1,000–2,000 | 8–15 | Readily indented by thumb |
| Very Dense | > 50 | 85–100% | Very Stiff | 2,000–4,000 | 15–30 | Readily indented by thumbnail |
| Hard | 4,000–8,000 | > 30 | Indented by thumbnail with difficulty |
Where no SPT is taken, the system gives a field check for granular soils with a 4-ft, 1.5-in. pigtail auger (pushed in by body weight: very loose; turned in full length easily: loose; stalls near 2.5 ft: medium dense; tight at about 1 ft: dense; only to the length of the spiral: very dense).
A boring through an embankment on a Class I railroad located in Michigan recovers a split-spoon sample at 12 ft. The engineer estimates the composition by eye and feel, records the blow count and checks plasticity with the thread test.
| Variable | Value | Description |
|---|---|---|
| Fines | about 60%; rolls to a 1/8-in. thread, strong when dry | Clay behavior |
| Sand | about 32% | |
| Gravel | about 8% | |
| N | 9 blows/ft | SPT, 140-lb hammer |
| Color | Gray-Brown | |
| Moisture | Moist | Before handling |
Field description: Stiff Gray-Brown Moist Sandy Clay, Trace of Gravel.
The lab will probably classify this sample CL, sandy lean clay (Section 2.2.4.2), consistent with the field description. In railroad embankments, also note cinders, ballast, slag or tie fragments when they appear: they mark old track raises and are the clue to where the original ground surface and the past fouled ballast layers are.
Open the field soil description builder →
Builds the word picture from estimated gravel, sand and fines, fines behavior, size and shape, color, moisture, structure, fill and inclusions, with the strength term from N, su or the manual index tests.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.
Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.
Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.
File locations for these documents are listed under Supplemental References.
Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S12 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S13 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual.