5.1.0 In Situ Test Catalogue: What Each Test Provides and How It Is Used

In situ testing provides continuous or near-continuous soil and rock characterization without the inherent sample disturbance associated with laboratory testing.
Authors: Daniel P. Colwell and Mario Ruel
5.1.0 In Situ Test Catalogue: What Each Test Provides and How It Is Used

An in situ test is any test run on the ground where it lies, rather than on a sample taken to a laboratory. The value of a test lies in the decision it supports, so each test in this catalogue is described in the same way:

  • The test: what is done and with what equipment.
  • Information provided: what is measured directly, and what is derived from it by calculation or correlation.
  • How the information is used: which analysis or decision in this manual the result feeds.
  • Limitations: where the test gives poor or misleading results.

Tests that have their own detailed section in this chapter (CPT, vane, pressuremeter, dilatometer, MASW, seismic refraction and GPR) are summarized here and linked to that section. The others are described in full here.

Measured, derived or correlated? Every parameter taken from an in situ test falls into one of three classes. Measured values (blow count, cone resistance, vane torque, water level, travel time) are facts about the test. Derived values come from them through mechanics with few assumptions (su from vane torque, Gmax from Vs, k from a slug test). Correlated values come from empirical relationships (φ′ from N, su from qt and Nkt, CBR from DPI) and carry the scatter of the data set behind them. Record which class each design parameter is in. A design that rests on correlated values should be checked against a second test type or against laboratory tests, and the uncertainty should be reflected in the risk rating (Chapter 3.8). The correlations used in this chapter are listed in the Empirical Equations card above.
5.1.0.1 Summary of Tests, Outputs and Uses

Table 5.1-10 lists every test in the catalogue on one page. The last column gives the section where it is described.

Table 5.1-10. In situ tests: what they measure and how the results are used
TestASTMMeasuresGives (derived or correlated)Main usesSection
SPTD1586N, sampleDr, φ′, consistency, EBearing, piles, liquefaction, site classCh. 4.1
CPT / CPTuD5778qt, fs, u2SBT, su, OCR, φ′, M, kStratigraphy, stability, settlement, liquefaction, piles5.1.2
SCPTuD7400CPTu + VsGmax, Vs,30Site class, dynamic stiffness5.1.0.4
DCPD6951DPICBR, MrTrackbed and pavement subgrade5.1.0.5
Becker—NBEquivalent N60Gravel liquefaction and density5.1.0.6
Field vaneD2573Torquesu, StSoft clay stability, Nkt calibration5.1.3
PMTD4719Pressure–volumeEPMT, pL, σh0Foundations, lateral piles5.1.4
DMT / SDMTD6635A and B pressuresID, KD, M, OCR, K0Settlement, stress history, slip surfaces5.1.5
BST—Shear vs normal stressc′, φ′Slopes in silt, loess, residual soil5.1.0.10
Plate load / LWDD1196, E2583Load–settlementk, ESlabs, formation acceptance, QC5.1.0.11
Pocket pen. / Torvane—Index readingqu, su (index)Logging, sample selection5.1.0.12
PiezometersD5092Water level, pressurePore pressure with timeEffective stress, monitoring, live rating5.1.0.13
Slug testD4044Head recoverykSeepage, drains, dewatering5.1.0.14
Packer testD4630Flow vs pressureLugeon, k of rockRock seepage, grouting, karst5.1.0.15
Pumping testD4050Drawdown vs timeT, S, k, radiusLarge dewatering5.1.0.16
InfiltrationD3385Inflow rateInfiltration rateStormwater, ditches5.1.0.17
Point loadD5731Breaking loadIs(50), UCSRippability, rock sockets5.1.0.18
Schmidt hammerD5873Rebound RUCS, JCSJoint shear strength, weathering5.1.0.19
TeleviewerD5753Wall imageJoint orientation, voidsRock cut kinematics, anchors5.1.0.20
Borehole jackD4971Pressure–displacementRock mass modulusFoundations on rock5.1.0.21
MASW—Surface-wave dispersionVs, Gmax, Vs,30Site class, soft-ground screening5.1.6
Seismic refractionD5777First arrivalsVp, depth to rockRock depth, rippability5.1.7
Downhole / crossholeD7400, D4428Travel timesVs, Vp, νSite response at major structures5.1.0.24
ERID6431, G57Voltage / currentResistivity sectionKarst, seepage, corrosion5.1.0.25
GPRD6432ReflectionsLayer thickness, foulingBallast and subballast condition5.1.15
MicrogravityD6430GravityMass deficitsSinkholes, mine voids5.1.0.27
Borehole geophysical logsD5753Gamma, conductivity, density, neutron, caliper, sonic, radarClay content, density, water content, fracture zones, VpCorrelating layers between borings; voids and weak zones at piers5.1.16
Magnetics (total field, gradiometer)D6429Total magnetic field or vertical gradientBuried steel: pipes, well casings, culverts, drumsClearing drilling and pile locations; old wells5.1.17
EM induction (terrain conductivity)D6429, D6639Apparent conductivityClay, saline water, landfill edges, buried metalFast mapping along a corridor before drilling5.1.17
Self-potentialD6429Natural voltage from water flowSeepage pathsEmbankment and sinkhole seepage5.1.17
Field densityD1556, D6938Density, moisture% compactionFill acceptanceCh. 5.3
A. Penetration Tests

Penetration tests push or drive a probe into the ground and record how hard it is to advance. They are the backbone of most railroad programs because they are fast, give a profile with depth and are tied to large published databases of correlations.

5.1.0.2 Standard Penetration Test (SPT)

Standard: ASTM D1586; hammer energy by ASTM D4633 (withdrawn 2025)

The test

A 2-in. outside-diameter split-spoon sampler is driven 18 in. at the bottom of a boring by a 140-lb hammer falling 30 in. The blows for each 6-in. increment are recorded; the blow count N is the sum of the second and third increments. Refusal is normally 50 blows for less than 6 in. of advance. The test is usually run every 2.5 ft in the upper 10 ft and every 5 ft below that, and it is the default test on nearly every railroad boring.

Information provided
  • Field blow count N (blows/ft) and refusal depth
  • A disturbed sample from every test for visual classification, moisture content and Atterberg limits (Chapter 5.2)
  • Corrected values N60 (hammer energy) and (N1)60 (overburden), computed as shown in Chapter 4.1, Section 4.1.3
  • By correlation: relative density and friction angle of sands, consistency of clays, elastic modulus, and typical property ranges by soil type (Appendix D)
How the information is used
  • Bearing capacity and settlement of footings on sand, and side and tip resistance of driven piles (Chapter 6.1, Chapter 6.2)
  • Liquefaction triggering with (N1)60,cs (Chapter 6.5)
  • Seismic site class from the average blow count over the upper 100 ft where shear wave velocity has not been measured (Chapter 6.5)
  • Locating soft or loose zones under the track and setting the depth of borings and undercuts
Limitations

Results depend on hammer energy, borehole cleanout and the crew. N is unreliable in soft clay (use the vane or CPTu instead) and is inflated by gravel. Below the water table, sand can heave into the hole and give low counts unless the hole is kept full of water or drilling fluid.

Detailed procedure, energy corrections and Example 6-1 are in Chapter 4.1, Section 4.1.3. The reliability of SPT–CPT conversions is discussed in Section 5.1.8.

5.1.0.3 Cone and Piezocone Penetration Test (CPT and CPTu)

Standard: ASTM D5778

The test

A 1.41-in.-diameter, 60° cone is pushed at 0.8 in./s by a truck- or track-mounted rig. Sensors record tip resistance, sleeve friction and, on a piezocone, pore pressure behind the tip about every 2 in. A sounding to 60 ft takes well under an hour. No sample is recovered.

Information provided
  • Measured: tip resistance qc (corrected to qt), sleeve friction fs, pore pressure u2
  • Soil behavior type and the index Ic, giving a continuous stratigraphic log that picks up layers as thin as about 4 in.
  • By correlation: undrained strength su, OCR and preconsolidation stress, friction angle and relative density of sand, constrained modulus, unit weight
  • Dissipation tests: coefficient of consolidation ch, hydraulic conductivity, and the static water level
How the information is used
  • Filling in the stratigraphy between borings along a corridor, and finding thin soft or loose layers that SPT spacing misses
  • Undrained strength for embankment stability (Chapter 6.3) and consolidation settlement inputs (Chapter 6.2)
  • Direct pile capacity methods that use qt and fs (Chapter 6.1)
  • Liquefaction triggering with qc1N (Chapter 6.5)
  • Subgrade modulus for track (Chapter 2.3, Section 2.3.6)
Limitations

Will not penetrate gravel, cobbles, dense cemented soil or old riprap in embankments; pair it with borings to confirm soil type, since the log is a behavior type, not a classification.

Full treatment in Section 5.1.2 and Example 5.1-1.

5.1.0.4 Seismic Cone (SCPTu)

Standard: ASTM D7400 (downhole method)

The test

A piezocone with one or two geophones behind the tip. At each rod break, usually every 3.3 ft, pushing stops and a shear wave is generated at the surface by striking a beam held down by the rig. The arrival time at the geophone gives the interval shear wave velocity. A compression-wave source can be added.

Information provided
  • All CPTu outputs, plus a measured shear wave velocity Vs profile (and P-wave velocity Vp if recorded)
  • Small-strain shear modulus Gmax = ρVs2 at the same location as the strength profile
  • Vp near 4,900 ft/s marks full saturation, which matters for liquefaction
How the information is used
  • Seismic site class from Vs,30 (Chapter 6.5)
  • A second, independent liquefaction check based on Vs
  • Small-strain stiffness of the trackbed and foundation soils for dynamic analysis; the small cyclic strains under train loads are closer to Gmax than to a resilient modulus
  • Detecting aging or cementation: a Vs much higher than the CPT correlation predicts means the correlations will understate strength and stiffness
Limitations

Depth is limited to where the cone can be pushed. Velocities in the upper 5 to 10 ft are less reliable because of the short travel path.

5.1.0.5 Dynamic Cone Penetrometer (DCP)

Standard: ASTM D6951

The test

A hand-portable probe: a 17.6-lb hammer dropped 22.6 in. drives a 60° cone of about 0.79-in. diameter. The penetration per blow, the DCP index (DPI), is recorded to about 3 ft, and deeper with extension rods. Two people can run a test in 15 minutes from the shoulder, a crib window or the bottom of a test pit, which suits track time limits.

Information provided
  • Penetration index DPI (in./blow) with depth, and the depth at which it changes (layer boundaries)
  • California Bearing Ratio (CBR) of each layer from ASTM D6951 correlations
  • Resilient modulus Mr from CBR
How the information is used
  • Subgrade strength under existing track at mud-pumping, ballast-pocket and soft-spot locations (Chapter 2.3)
  • Thickness and strength of subballast and subgrade for granular layer design (Chapter 2.1, Section 2.1.17)
  • Pavement subgrade CBR at yards and intermodal facilities (Chapter 7.3)
  • Quick acceptance checks on subgrade and fill alongside proof rolling (Chapter 5.3)
Limitations

Cannot penetrate ballast or coarse gravel; remove ballast first. The correlations change with soil type, so the subgrade must be classified. A rock or cobble gives a false high resistance; repeat the test a short distance away.

Applied in Example 5.1-4.

5.1.0.6 Becker Penetration Test and Dynamic Probing

Standard: No ASTM standard for the Becker test; dynamic probing by EN ISO 22476-2

The test

The Becker hammer drill drives a closed-end, 6.6-in. double-walled casing with a diesel hammer and counts the blows per foot. It is the usual tool for penetration resistance in gravel and cobbles, where the SPT sampler is too small. Blow counts are corrected for hammer energy (measured by instrumenting the casing) and converted to an equivalent SPT N60. Lighter continuous dynamic probes, driven without a borehole, are a cheaper screening tool in sand and fine gravel.

Information provided
  • Becker blow count NB and its equivalent N60 in gravelly soils
  • A continuous resistance profile, but no sample
How the information is used
  • Liquefaction and strength of gravelly alluvium at bridge and embankment sites in seismic areas (Chapter 6.5)
  • Density of coarse fill and gravel foundations where SPT counts would be inflated
Limitations

Specialized equipment with few operators. The conversion to N60 carries much more uncertainty than an SPT; use a range, not a single value.

B. Shear Strength and Stiffness Tests

These tests load the ground in a controlled way to measure strength or stiffness directly, rather than inferring them from penetration resistance. They are used where the design depends on one parameter and a correlation is not good enough.

5.1.0.7 Field Vane Shear Test (VST)

Standard: ASTM D2573

The test

A four-bladed vane is pushed into undisturbed clay below the bottom of a boring, or from the surface inside a protective casing, and rotated slowly. The peak torque gives the peak undrained strength. After ten or more rapid turns, the residual torque gives the remolded strength.

Information provided
  • Peak and remolded undrained shear strength su
  • Sensitivity St = peak / remolded
  • Design su after Bjerrum’s correction for plasticity index
How the information is used
  • Undrained strength of soft clay for embankment stability, widening and staged construction (Chapter 6.3, Chapter 7.2)
  • Calibrating the CPTu cone factor Nkt for a site
  • Screening sensitive and quick clays, which lose most of their strength when disturbed by vibration or excavation
  • Undrained bearing capacity of footings and pile tips in soft clay (Chapter 6.1)
Limitations

Only for soft to firm clay (about su below 2,000 psf). Silt and sand drain during the test and give meaningless results; shells, roots and fibers in peat overstate strength.

Full treatment in Section 5.1.3 and Example 5.1-2.

5.1.0.8 Pressuremeter Test (PMT)

Standard: ASTM D4719

The test

A cylindrical probe is lowered into a carefully drilled hole and a rubber membrane is expanded against the borehole wall in pressure steps. The volume change at each step gives a pressure–volume curve. An unload–reload loop gives a stiffness closer to working loads. Self-boring versions drill themselves into place and avoid most disturbance.

Information provided
  • Pressuremeter modulus EPMT and unload–reload modulus
  • Limit pressure pL and creep pressure
  • In situ horizontal stress (most reliable with the self-boring probe)
  • By correlation: undrained strength of clay, friction angle of sand
How the information is used
  • Bearing capacity and settlement of footings by direct pressuremeter methods (Chapter 6.1, Chapter 6.2)
  • Lateral load response (p–y curves) of piles and drilled shafts supporting bridges, signal masts and catenary poles
  • Stiffness of soils that are hard to sample: stiff fissured clay, residual soil, weathered rock and dense glacial till
Limitations

Results depend heavily on borehole quality; an oversized or smeared hole ruins the test. Slower and more expensive than penetration tests, so it is used at specific foundation locations, not along a corridor.

Full treatment in Section 5.1.4.

5.1.0.9 Flat Dilatometer Test (DMT and SDMT)

Standard: ASTM D6635 (withdrawn 2024)

The test

A flat steel blade about 3.7 in. wide and 0.6 in. thick is pushed into the ground, usually by a CPT rig. At every 8 in. a circular membrane on one face is inflated; the pressure to start moving it (A) and to move it 0.04 in. (B) are recorded. The seismic dilatometer adds geophones for shear wave velocity.

Information provided
  • Intermediate indices: material index ID (soil type), horizontal stress index KD, dilatometer modulus ED
  • Constrained modulus MDMT, OCR, K0, undrained strength of clay and friction angle of sand
  • Vs and Gmax from the seismic version
How the information is used
  • Settlement of embankments and footings: MDMT is one of the better field estimates of one-dimensional modulus (Chapter 6.2)
  • Stress history (OCR) of clay layers, which decides whether settlement is recompression or virgin consolidation
  • Locating existing slip surfaces in clay slopes, where KD close to 2 marks remolded material (Chapter 6.3)
  • Before-and-after checks of densification and ground improvement (Chapter 7.2)
Limitations

Same push limits as the CPT. The blade can bend in dense or gravelly layers. The correlations are for uncemented soils.

Full treatment in Section 5.1.5.

5.1.0.10 Borehole Shear Test (BST)

Standard: No ASTM standard; Iowa borehole shear tester procedure

The test

Two serrated plates are expanded against the wall of a 3-in. borehole under a set normal stress, left to consolidate for about 5 to 15 minutes, then pulled upward to shear the soil. The test is repeated at increasing normal stresses at the same depth, giving several points on a failure envelope from one location in about an hour.

Information provided
  • Drained or near-drained cohesion c′ and friction angle φ′ at a known depth, without sampling
  • Several envelope points from one hole, so scatter between samples is removed
How the information is used
  • Effective-stress strength of silty soils, loess and residual soils for slope stability and cut design (Chapter 6.3)
  • Quick strength data for back-analysis of slides where sampling is difficult
Limitations

Drainage in clays is not certain, so results in plastic clay may be partly undrained. Does not work in gravel or in holes that will not stay open.

5.1.0.11 Plate Load Test and Light Weight Deflectometer (LWD)

Standard: ASTM D1196 (static plate load); LWD by ASTM E2583 and E2835

The test

A rigid steel plate, typically 12 to 30 in. in diameter, is loaded in steps against a reaction (a loaded truck or rail equipment) and its settlement measured. Unloading and reloading gives a second modulus. The light weight deflectometer is a portable version: a 22-lb weight dropped onto a 12-in. plate, with the deflection recorded in seconds.

Information provided
  • Load–settlement curve and the modulus of subgrade reaction k (pci)
  • Surface elastic modulus of the layers under the plate (first loading and reloading)
  • LWD: a dynamic surface modulus for fast comparison along a section
How the information is used
  • Modulus of subgrade reaction for rigid pavements and slabs at yards (Chapter 7.3)
  • Stiffness of formation, subballast and subgrade for track design and acceptance; the ratio of reload to first-load modulus is used as a compaction check
  • Field verification of bearing assumptions for shallow foundations
  • LWD as a quick quality-control test on fill lifts and subgrade (Chapter 5.3)
Limitations

The plate tests only to a depth of about 1.5 to 2 plate diameters, so a soft layer deeper down is missed; scale results to the real footing carefully. The LWD modulus is not the same as a static or resilient modulus; correlate it with site tests.

5.1.0.12 Pocket Penetrometer and Torvane

Standard: Field index tests; no ASTM standard

The test

Hand tools used on the ends of tube samples, split-spoon samples, test-pit walls and cut faces. The pocket penetrometer is pushed 1/4 in. into the soil and reads unconfined compressive strength directly in tsf. The Torvane is a small vane pressed against a flat surface and turned by hand; it reads undrained strength.

Information provided
  • Estimated unconfined strength qu (pocket penetrometer) and undrained strength su (Torvane)
How the information is used
  • Consistency descriptions on boring logs (very soft to hard)
  • Choosing which tube samples go to the laboratory, and spotting disturbed samples
  • Screening strength of exposed clay in cuts and failed slopes during reconnaissance
Limitations

Index values only. They test a tiny volume, often of disturbed soil, and should not be used alone for design.

C. Groundwater and Hydraulic Conductivity Tests

Water is involved in most railroad ground hazards. These tests establish where the water is, what pressure it is under, and how easily it moves through the ground.

5.1.0.13 Groundwater Levels and Piezometers

Standard: ASTM D5092 (monitoring wells)

The test

Water levels are recorded during drilling, at completion and at least 24 hours later. Open standpipe piezometers (a screened pipe sealed at a chosen depth) and vibrating-wire piezometers (a pressure sensor grouted in place, read by a data logger) give water pressure over time at specific depths.

Information provided
  • Depth of the water table and any perched or artesian water
  • Pore water pressure at a given depth, and how it changes with season, rainfall and river stage
  • Response time of the ground to storms, which shows how quickly a slope can lose strength
How the information is used
  • Effective stress in every strength, settlement and liquefaction calculation (Chapter 6.2, Chapter 6.3, Chapter 6.5)
  • Pore pressure conditions in slope stability, including the high-water design case
  • Dewatering and drainage design for culverts, underpasses and cuts (Chapter 2.8)
  • Trigger levels for monitoring and the live risk rating (Chapter 3.8)
Limitations

A water level read during or right after drilling is often wrong, especially in clay or where drilling fluid was used. Piezometers must be sealed so they read one layer, not a mixture.

Installation details are in Chapter 2.8.

5.1.0.14 Slug (Rising- and Falling-Head) Tests

Standard: ASTM D4044 (withdrawn 2024)

The test

The water level in a well or piezometer is suddenly raised or lowered, by adding or removing water or by dropping in a solid rod (a slug), and the return to the static level is timed. The rate of recovery and the geometry of the screen give the hydraulic conductivity of the soil around it (Hvorslev or Bouwer–Rice methods).

Information provided
  • Hydraulic conductivity k (ft/day) of the soil or rock around the well screen
How the information is used
  • Seepage analysis through and beneath embankments (Chapter 6.4)
  • First estimates of dewatering inflow for excavations
  • Checking consolidation rates: k from the field is often higher than the laboratory value because of sand seams and fissures (Chapter 6.2)
  • Design of underdrains and edge drains
Limitations

Tests only a small volume around the screen and is sensitive to a smeared or clogged well. Treat it as a local value, and test several wells.

5.1.0.15 Packer (Lugeon) Tests

Standard: ASTM D4630

The test

One or two inflatable packers seal off a length of a rock borehole, typically 5 to 10 ft, and water is pumped in at a series of rising and then falling pressures. The flow rate at each step is measured. One Lugeon is a take of about 0.08 gal/min per foot of test section at 145 psi, roughly equal to a hydraulic conductivity of 0.04 ft/day.

Information provided
  • Hydraulic conductivity of a rock interval, in Lugeons
  • The pattern of flow with pressure, which shows whether joints are open, washing out, filling or being jacked open
  • Intervals that take water without building pressure, a sign of open voids or karst
How the information is used
  • Seepage and uplift beneath embankments and structures founded on rock
  • Inflow to rock cuts, culverts and tunnels, and grouting design
  • Confirming karst or mine voids found by geophysics (Chapter 6.4)
Limitations

Packers can leak or be bypassed through joints around them. Use pressures low enough not to open the joints unless that is the purpose.

5.1.0.16 Pumping Tests

Standard: ASTM D4050

The test

A well is pumped at a constant rate for hours to days while the drawdown is recorded in it and in nearby observation wells. The drawdown–time and drawdown–distance data are fitted to aquifer models (Theis, Cooper–Jacob).

Information provided
  • Transmissivity, storage coefficient and average hydraulic conductivity of a large volume of ground
  • Radius of influence and the presence of recharge or barrier boundaries
How the information is used
  • Dewatering design for large excavations such as underpasses, pump stations and bridge foundations (Chapter 2.8)
  • Predicting effects of dewatering on nearby wells, wetlands and settlement-sensitive structures
Limitations

Expensive and slow, and needs a permit to discharge water in many places. Worth it only where dewatering is a large part of the cost or risk.

The Cooper–Jacob method is worked in Chapter 2.8.

5.1.0.17 Infiltration Tests

Standard: ASTM D3385 (double-ring infiltrometer)

The test

Two concentric rings, typically 12 and 24 in. in diameter, are driven into the surface and kept filled with water. The rate at which water level falls in the inner ring, once steady, is the infiltration rate. Borehole permeameters do the same at depth.

Information provided
  • Steady infiltration rate (in./hr) of the surface soil
How the information is used
  • Sizing stormwater basins, infiltration trenches and ditches at yards and terminals (Chapter 6.4)
  • Runoff estimates for slopes and cut faces, and the erosion potential of the surface
Limitations

Represents only the surface layer at that spot; compaction from equipment changes it greatly. Run several tests across the area.

D. Rock Tests in the Field

Rock strength and the orientation of discontinuities decide how cuts fail, how much it costs to excavate, and how foundations on rock behave. These tests are run on outcrops, on core at the rig, or in the borehole.

5.1.0.18 Point Load Test

Standard: ASTM D5731 (withdrawn 2025)

The test

A piece of core or an irregular rock lump is broken between two cone-shaped points in a portable frame. The breaking load, corrected to a 2-in. equivalent core diameter, gives the point load index Is(50). Dozens of tests can be run at the rig in an hour.

Information provided
  • Point load index Is(50) and the strength anisotropy index for layered rock
  • By correlation: unconfined compressive strength, roughly 20 to 25 times Is(50) for many rocks, but from about 15 to 50 times depending on rock type
How the information is used
  • Rock strength for excavatability and rippability (with seismic refraction)
  • Rock socket design for drilled shafts (Chapter 6.1)
  • Strength rating in the rock mass classification (Chapter 2.2)
  • Showing how strength varies along the core so laboratory tests can be chosen well
Limitations

Calibrate the conversion factor with a few laboratory unconfined compression tests (Chapter 5.2). Results on weak, clayey rock are scattered.

5.1.0.19 Schmidt (Rebound) Hammer

Standard: ASTM D5873 (withdrawn 2023) (rock); ASTM C805 (concrete)

The test

A spring-loaded plunger strikes the rock surface and the rebound number R is read. At least 20 readings are taken on a clean, flat surface and the high values averaged.

Information provided
  • Rebound number R
  • By correlation: unconfined strength of intact rock, and the joint wall compressive strength (JCS) used in joint shear strength
How the information is used
  • Shear strength of joints for rock slope stability (Barton–Bandis), together with joint roughness (Chapter 6.3)
  • Mapping weathering grade across a cut face and identifying weak beds that undercut rock fall sources
  • Condition screening of old masonry and concrete culverts, abutments and walls
Limitations

Very sensitive to surface condition, weathering rind, moisture and the direction of the hammer. Use it to compare, not as a measured strength.

5.1.0.20 Borehole Imaging (Optical and Acoustic Televiewer)

Standard: ASTM D5753 (borehole geophysical logging)

The test

A probe lowered down an open or water-filled rock hole records a continuous, oriented image of the borehole wall, either a photograph (optical) or a map of acoustic reflection (acoustic). Caliper, natural gamma and other logs can be run in the same visit.

Information provided
  • Depth, dip and dip direction of every joint, bedding plane and fault
  • Aperture, infilling and spacing of discontinuities
  • Voids, solution features and zones of lost core
How the information is used
  • Kinematic checks for planar, wedge and toppling failure in rock cuts (Chapter 6.3)
  • Orienting rock bolts and anchors (Chapter 7.1)
  • Locating and sizing karst or mine voids for grouting
Limitations

Needs a stable, uncased hole; muddy water blinds the optical camera. Images must be interpreted by someone who has seen the core.

Televiewer logs are usually run with the other borehole geophysical logs; see Section 5.1.16.

5.1.0.21 Borehole Jack and Rock Dilatometer

Standard: ASTM D4971 (withdrawn 2025) (borehole jack)

The test

Two curved steel plates (the borehole jack) or an expanding membrane (the rock dilatometer) load the wall of an NX-size rock hole. Pressure against wall displacement gives the deformation modulus of the rock mass at that depth.

Information provided
  • In situ deformation modulus of the rock mass, which includes the effect of joints that a core test misses
How the information is used
  • Settlement of foundations and drilled shaft sockets on fractured or weathered rock (Chapter 6.1, Chapter 6.2)
  • Checking modulus values estimated from rock mass classification
Limitations

Specialized and seldom used on railroad work except at major bridges. Tests a small volume, so several depths are needed.

E. Geophysical Methods

Geophysics measures a physical property of the ground over a large area from the surface or from boreholes. It never replaces borings, but it shows where to put them and fills the gaps between them, which is valuable along a long, narrow corridor.

5.1.0.22 Multichannel Analysis of Surface Waves (MASW)

Standard: No ASTM standard; see Park, Miller and Xia (1999)

The test

A line of 24 or more geophones records surface waves from a sledgehammer or weight drop. Because longer waves reach deeper, their speed at each frequency gives a shear wave velocity profile, typically to 60 to 100 ft. Passive versions record traffic and other background vibration to reach deeper.

Information provided
  • Shear wave velocity Vs with depth, in 1D soundings or 2D sections
  • Gmax and Vs,30
  • Low-velocity zones that may be soft soil, loose fill or voids
How the information is used
  • Seismic site class (Chapter 6.5)
  • Corridor screening for soft ground and muskeg thickness before borings are placed
  • Before-and-after checks of ground improvement (Chapter 7.2)
  • Stiffness of the trackbed and foundation for dynamic track modulus
Limitations

Resolution decreases with depth, and a stiff layer over a soft one can hide the soft one. Calibrate against at least one boring or SCPTu.

Full treatment in Section 5.1.6 and Example 5.1-3.

5.1.0.23 Seismic Refraction

Standard: ASTM D5777

The test

Compression waves from a surface source are recorded on a line of geophones. Waves bent along faster, deeper layers arrive first at long distances, and the arrival times give layer depths and P-wave velocities. Refraction tomography gives a 2D velocity section.

Information provided
  • P-wave velocity of each layer and the depth to faster layers, usually the top of rock or the water table
  • Lateral variation in rock surface along the line
How the information is used
  • Depth to rock along proposed cuts and foundations, so borings can be fewer and better placed
  • Rippability and excavation cost: velocity is compared with equipment manufacturers’ rippability charts, supported by point load tests
  • Saturated soil, with Vp about 4,900 ft/s
Limitations

Cannot see a slower layer beneath a faster one (a velocity inversion), such as soft clay under a stiff crust or a weathered seam within rock.

Full treatment in Section 5.1.7.

5.1.0.24 Downhole and Crosshole Seismic Tests

Standard: ASTM D7400 (downhole); ASTM D4428 (crosshole)

The test

Downhole: a source at the surface and a receiver lowered in a cased boring. Crosshole: a source in one cased boring and receivers in one or two others, 10 to 20 ft away, at the same depths. Both measure travel times layer by layer.

Information provided
  • Interval Vs and Vp at each depth; crosshole gives the most accurate values available
  • Poisson’s ratio from Vp/Vs above the water table
How the information is used
  • Site response analysis for major bridges and structures (Chapter 6.5)
  • Checking MASW profiles where the site class is near a boundary
  • Vibration and dynamic foundation analysis
Limitations

Needs borings cased and grouted correctly, and borehole deviation surveys for crosshole. Costly; reserved for major structures.

Crosshole tomography, the velocity index and the other borehole logs are in Section 5.1.16.

5.1.0.25 Electrical Resistivity Imaging (ERI)

Standard: ASTM D6431; soil resistivity for corrosion by ASTM G57

The test

Current is passed between pairs of electrodes along a line and the voltage between other pairs is measured. Inversion gives a 2D or 3D section of resistivity. Clay and salty water conduct well (low resistivity); clean sand, gravel, dry fill, air-filled voids and rock do not (high resistivity).

Information provided
  • A section showing clay versus granular soil, wet versus dry zones, depth to rock, and anomalies such as voids or buried debris
  • Soil resistivity (ohm-cm) at a point for corrosion assessment
How the information is used
  • Karst and mine void screening, and choosing where to drill (Chapter 3.8)
  • Finding seepage paths and wet zones through embankments and the moisture conditions behind slides (Chapter 6.3, Chapter 6.4)
  • Corrosion potential of the soil for steel piles, pipe culverts and soil nails (Chapter 6.1, Chapter 7.1)
  • Repeat surveys to track seasonal wetting of a slope
Limitations

Many different conditions can give the same resistivity, and rails, fences, pipelines and other metal nearby distort the data. Always interpret with borings.

5.1.0.26 Ground Penetrating Radar (GPR)

Standard: ASTM D6432

The test

Radar pulses are sent into the ground from an antenna dragged along the surface or mounted on a hi-rail vehicle, and reflections from boundaries in dielectric constant are recorded. On track, 1 to 2 GHz antennas image the ballast and subballast; lower frequencies reach deeper with less detail.

Information provided
  • Thickness of clean ballast, fouled ballast and subballast along the track
  • Ballast pockets, wet zones and changes in the subgrade surface
  • Buried utilities, voids beneath slabs and culverts, and shallow rock
How the information is used
  • Planning undercutting, shoulder cleaning and drainage work (Chapter 2.3)
  • Placing crib digs and DCP tests at the worst locations
  • Clearing utilities before drilling
Limitations

Clay and wet ground absorb the signal and limit depth to a few feet. Depth depends on an assumed dielectric constant, so calibrate at test pits.

Full treatment in Section 5.1.15.

5.1.0.27 Microgravity

Standard: ASTM D6430

The test

A sensitive gravity meter is read on a close grid of surveyed points. After correcting for elevation, terrain, latitude and drift, small negative anomalies show where mass is missing below the surface.

Information provided
  • Map of gravity anomalies showing mass deficits: voids, solution cavities, loose infill and old mine workings
How the information is used
  • Screening for sinkholes and abandoned mine workings beneath the track (Chapter 3.8)
  • Targeting borings and grout holes, and checking that grouting filled the void
Limitations

Needs precise elevations and a quiet site; passing trains and heavy equipment disturb readings. Resolves only voids that are large relative to their depth.

F. Field Density and Compaction Tests

These tests check fill placed during construction rather than natural ground. They are listed here for completeness and covered in Chapter 5.3.

5.1.0.28 Sand Cone, Nuclear Gauge and Drive Cylinder

Standard: ASTM D1556, D6938 and D2937

The test

The sand cone measures the volume of a small hole by filling it with calibrated sand; the nuclear gauge measures density and moisture from radiation passing through the soil; the drive cylinder cuts out a known volume of fine-grained soil.

Information provided
  • In-place dry unit weight and moisture content
  • Percent compaction relative to the laboratory maximum dry unit weight (Chapter 5.2)
How the information is used
  • Acceptance of embankment fill, subgrade and backfill against the specification (Chapter 5.3)
  • Checking existing fill density where an old embankment is being widened
Limitations

Tests a small volume at the surface of each lift; the nuclear gauge needs a licensed operator and calibration against sand cone tests on the same soil.

Procedures and worked examples are in Chapter 5.3.

5.1.0.29 Choosing Tests by the Design Question

Start from the question the investigation has to answer, not from the tests the driller has available. Table 5.1-11 gives a first choice and the tests that confirm or extend it. The method comparison in Section 5.1.8 adds suitability ratings by soil type.

Table 5.1-11. First-choice and supporting in situ tests by design question
Design questionFirst choiceSupporting testsAnalysis in
How strong is the soft clay under an embankment?CPTu with field vane calibrationDMT; laboratory triaxial tests on tube samplesChapter 6.3
How much will a new fill or widening settle, and how fast?CPTu with dissipation tests; DMTLaboratory consolidation tests; piezometers and settlement plates during constructionChapter 6.2
Will the ground liquefy?CPTu or SPTSCPTu or MASW for Vs; Becker in gravelChapter 6.5
What is the seismic site class?MASW or SCPTuDownhole or crosshole near a class boundaryChapter 6.5
What will support a footing or pile?SPT and CPTPMT for lateral loads and stiff soils; plate load to verifyChapter 6.1
Why is this track section pumping or losing surface?GPR along the track, then DCP in crib digsPiezometers; laboratory index tests of fouling and subgradeChapter 2.3
Where is the top of rock and can it be ripped?Seismic refractionBorings with point load testsChapter 6.3
What controls the stability of a rock cut?Discontinuity mapping and televiewerSchmidt hammer for JCS; point load for intact strengthChapter 6.3
Are there voids from karst or old mines?ERI or microgravityBorings and packer tests at the anomalies; televiewerChapter 3.8
What will the water do?Piezometers with timeSlug or packer tests; pumping test for large dewateringChapter 2.8
Will the soil corrode steel?Soil resistivity, pH, sulfates and chloridesERI for extentChapter 7.1
Is the new fill compacted?Nuclear gauge or sand coneLWD, DCP and proof rollingChapter 5.3

Three rules apply in almost every case:

  • Pair a profiling test with a sampling test. CPT, DMT and geophysics show where layers change; borings show what the layers are. Neither is complete alone.
  • Calibrate correlations on site. A few side-by-side tests (vane beside CPTu, SPT beside CPT, a boring on a geophysical line) turn regional correlations into site-specific ones.
  • Measure water. Nearly every analysis needs the pore pressure, and a single reading at the end of drilling is rarely enough.