Surface geophysics measures a physical property of the ground from the surface: magnetization, electrical conductivity, seismic velocity, density or natural voltage. It works only where the target differs from its surroundings in that property, so the first step is always to ask what the target is and what property contrast it makes (Everett; ASTM D6429). Seismic refraction, MASW, ERT, GPR and microgravity are summarized in the catalogue in Section 5.1.0. This section adds magnetics, electromagnetic induction, resistivity arrays and self-potential, and the inversion and uncertainty that apply to all of them.
| Target | Property contrast | Methods to consider | Problems near track |
|---|---|---|---|
| Buried steel pipe, abandoned well casing, old steel culvert, drums | Magnetization; electrical conductivity | Magnetics (gradiometer), EM induction, GPR | Rails, fences, vehicles and signal equipment give large magnetic and EM noise |
| Clay layer, saline or contaminated groundwater, landfill | Conductivity | EM induction, ERT, IP | Traction power and buried cables affect EM and ERT |
| Voids, sinkholes, mine workings | Density; resistivity (air-filled high, water- or clay-filled low) | Microgravity, ERT, GPR, seismic | Track vibration affects gravity readings; terrain corrections on embankments |
| Seepage through an embankment or into a sinkhole | Natural voltage from water flow (streaming potential); resistivity | Self-potential, time-lapse ERT | Stray currents from traction power and cathodic protection |
| Depth to bedrock, rippability | Seismic velocity; resistivity | Seismic refraction, MASW, ERT | Train noise; schedule shots between trains |
| Faults, shear zones | Velocity, resistivity, magnetization | Refraction, ERT, magnetics | Interpret with geologic mapping |
Magnetometers (proton precession, cesium vapor or fluxgate) measure the Earth’s total field, and buried steel shows as a local anomaly of tens to thousands of nanotesla (nT). A gradiometer measures the difference between two sensors one above the other, which removes the slowly varying regional field and the daily (diurnal) variation and sharpens shallow targets. For single-sensor surveys, read a base station during the survey to correct for diurnal change.
Eq. 5.1-29: for a long magnetized pipe, with the anomaly reduced to the pole, the depth from the sensor to the pipe is approximately equal to the full width of the total-field anomaly at half its maximum value (FWHM): d ≈ FWHM. Depth rules for other shapes differ. At mid-latitudes an anomaly that has not been reduced to the pole is lopsided, with a positive and a negative lobe, so the peak may not sit exactly over the pipe.
A transmitter coil induces currents in the ground and a receiver coil measures the secondary field. At low induction numbers the reading is proportional to the apparent conductivity of the ground (mS/m). The Geonics EM31 has a coil spacing of 3.66 m (12 ft); the EM34 has spacings of 10, 20 and 40 m (33, 66 and 131 ft). The effective depth is about 1.5 times the coil spacing with the coils horizontal (vertical dipole) and about 0.75 times with the coils vertical (horizontal dipole) (McNeill 1980). EM induction is fast, needs no ground contact, and maps clay, saline water, landfill edges and buried metal. Metal fences, rails, pipelines and power lines distort the readings, so keep lines well away from them or note them on the map.
Current I is passed between two electrodes and the voltage V is measured between two others. The apparent resistivity is Eq. 5.1-30: ρa = κ V / I, where κ is the geometric factor of the array: κ = 2πa for the Wenner array with electrode spacing a, and κ = πn(n + 1)(n + 2)a for the dipole-dipole array with dipole length a and separation na. Wenner gives good signal and lateral profiles; Schlumberger suits depth soundings; dipole-dipole resolves lateral changes and vertical structures best but has weaker signal at large n. Multi-electrode systems record many combinations as a pseudosection, which is inverted to a resistivity section (ERT).
Self-potential (SP) measures natural voltages between a fixed reference electrode and a roving electrode, using non-polarizing electrodes and a high-impedance voltmeter. Water flowing through soil generates a streaming potential, so SP maps seepage paths: in embankments and dams, around sinkholes, and along leaking pipes. Readings must be corrected for drift and topography, because SP tends to increase downhill along the hydraulic gradient, and they are noisier in heavy vegetation. Induced polarization (IP) measures how the ground stores charge after the current is switched off; it helps tell clay from sand where both have similar resistivity, and responds to some contaminants and disseminated sulfides.
ERT, EM and gravity sections are produced by inversion: the software finds a model whose computed response matches the measured data. Many different models can fit the same data (non-uniqueness), so inversions add constraints that favor smooth or simple models (regularization). The resulting section is one plausible picture, smoother than the real ground, and less reliable at depth and at the ends of the line. Repeating the same survey over time (time-lapse ERT or microgravity) removes much of this ambiguity, because the change between surveys shows where something is happening, such as a void growing or water moving.
For railroad work: State the target and the property contrast in the scope before asking for a geophysical survey, and ask the contractor to explain why the method will see it. Run lines across the expected target, not along the track; keep away from rails, fences and power lines, or measure their effect with a test line. Ask for the raw data, the inversion settings and a statement of uncertainty, and plan borings, test pits or potholes to check the anomalies. Geophysics shows where to drill; it does not replace drilling. Before drilling or driving piles near suspected buried pipes, confirm locations by vacuum excavation even if the geophysics looks clear.
A Class I railroad located in Ohio plans a 3-ft diameter drilled shaft for a new signal mast. Old right-of-way maps show an abandoned steel water line crossing the railroad near the site, but not its exact location or depth. The utility locator could not trace it. A magnetometer profile was run across the right-of-way, well away from the rails, square to the expected pipe line. The railroad requires 5 ft of horizontal clearance between the shaft and any buried pipe. The engineer must estimate the pipe location and depth and decide whether the shaft must be moved.
| Variable | Value | Description |
|---|---|---|
| Tmax | 118 nT at station 52.0 ft | Peak of the total-field anomaly (regional field removed) |
| x1, x2 | 47.2 ft and 56.8 ft | Stations where the anomaly equals half the peak (59 nT) |
| h | 1.0 ft | Sensor height above ground |
| Shaft | 3.0 ft diameter, center at station 49.0 ft | Planned signal foundation |
| c | 5.0 ft | Required horizontal clearance from shaft edge to pipe |
(a) About 8.6 ft below ground at station 52.0. (b) 1.5 ft clear, which fails the 5-ft requirement. (c) Move the shaft center to station 45.5 ft or less, or 58.5 ft or more.
The 15-ft shaft would pass the pipe depth, so drilling at station 49 risks hitting it. The depth rule is approximate: it assumes a long pipe and an anomaly reduced to the pole, and a lopsided anomaly at this latitude can shift the peak by a few feet. The symmetric half-maximum points here suggest the shift is small, but confirm the pipe by vacuum excavation at station 52 before drilling, and add a second profile 20 to 30 ft along the pipe line to check its direction. If the pipe is found shallower or offset, recompute the clearance. Moving the shaft to station 45 keeps it on the same side of the pipe and avoids a crossing of the signal cable trench over the pipe.
Source: Everett (2013), Chs. 1, 3, 4, 5, 8, 10 and 11–12; McNeill (1980); ASTM D6429. Summarized and paraphrased; units converted. Full references under S13, S14, S15.