Chapter 6.2 — Settlement Analysis

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1.
Authors: Daniel P. Colwell and Mario Ruel

Railroad Geotechnical Services Manual | Primary Source: USACE EM 1110-1-1804 All equations and parameters expressed in English (Imperial) units throughout.

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Compressibility, consolidation and stiffness values for settlement estimates. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Compressibility and consolidation (60 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of volume compressibilityHard, heavily overconsolidated glacial till, stiff weathered rocks, hard claysCL-CH / OH / PtVery low compressibility0.0024ft²/kipCB T5.1, p.108
Compression indexHard, heavily overconsolidated glacial till, stiff weathered rocks, hard claysCL-CH / OH / PtVery low compressibility0.025–CB T5.1, p.108
Coefficient of volume compressibilityStiff glacial till, marls, very stiff tropical residual claysCL-CH / OH / PtLow compressibility0.00240.00360.0048ft²/kipCB T5.1, p.108
Compression indexStiff glacial till, marls, very stiff tropical residual claysCL-CH / OH / PtLow compressibility0.0250.03750.05–CB T5.1, p.108
Coefficient of volume compressibilityFirm clays, glacial outwash clays, lake deposits, NC clays at depthCL-CH / OH / PtMedium compressibility0.00480.00960.0144ft²/kipCB T5.1, p.108
Compression indexFirm clays, glacial outwash clays, lake deposits, NC clays at depthCL-CH / OH / PtMedium compressibility0.050.10.15–CB T5.1, p.108
Coefficient of volume compressibilityPoorly consolidated alluvial clays (estuarine), sensitive claysCL-CH / OH / PtHigh compressibility0.01440.04310.0718ft²/kipCB T5.1, p.108
Compression indexPoorly consolidated alluvial clays (estuarine), sensitive claysCL-CH / OH / PtHigh compressibility0.150.450.75–CB T5.1, p.108
Coefficient of volume compressibilityHighly organic alluvial clays and peatsCL-CH / OH / PtVery high compressibility0.0718ft²/kipCB T5.1, p.108
Compression indexHighly organic alluvial clays and peatsCL-CH / OH / PtVery high compressibility0.752.8755–CB T5.1, p.108
Compression indexUniform siltsML / SP0.2–USACE T3-7, p.59
Compression indexUniform sand, looseML / SP0.050.0550.06–USACE T3-7, p.59
Compression indexUniform sand, denseML / SP0.020.0250.03–USACE T3-7, p.59
Recompression indexClaysCL-CH0.0150.18250.35–CB T5.1 text, p.108
Secondary compression ratioClay0.0250.0550.085–USACE T3-14, p.79
Secondary compression ratioSilt0.030.05250.075–USACE T3-14, p.79
Secondary compression ratioPeat0.030.05750.085–USACE T3-14, p.79
Secondary compression ratioMuskeg0.090.0950.1–USACE T3-14, p.79
Secondary compression ratioInorganic soils0.0250.04250.06–USACE T3-14, p.79
Secondary compression ratioOrganic siltsOL0.0350.04750.06–CB T5.4, p.117
Secondary compression ratioAmorphous and fibrous peatPt0.0350.060.085–CB T5.4, p.117
Secondary compression ratioOrganic clays and siltsML-MH0.040.050.06–CB T5.4, p.117
Secondary compression ratioSan Francisco Bay mudCL0.040.050.06–CB T5.4, p.117
Secondary compression ratioSensitive clay, Portland MECL-CH0.0250.040.055–CB T5.4, p.117
Coefficient of consolidationLow plasticity claysCL32.29118.4204.5ft²/yrCB T5.3, p.114
Coefficient of consolidationLow plasticity glacial lake claysCL21.5326.932.29ft²/yrCB T5.3, p.114
Coefficient of consolidationLow plasticity mudCL6.469.712.92ft²/yrCB T5.3, p.114
Coefficient of consolidationMedium plasticity claysCL-CH9.69ft²/yrCB T5.3, p.114
Coefficient of consolidationVolcanic siltMH3.234.3055.38ft²/yrCB T5.3, p.114
Coefficient of consolidationOrganic siltOL6.4619.432.29ft²/yrCB T5.3, p.114
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHUndisturbed – virgin compression1,292ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHUndisturbed – virgin compression538.2ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHUndisturbed – virgin compression215.3ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHUndisturbed – virgin compression107.6ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHUndisturbed – virgin compression53.82ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHUndisturbed – virgin compression32.29ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHUndisturbed – virgin compression16.15ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHUndisturbed – virgin compression10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHUndisturbed – virgin compression9.69ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHUndisturbed – recompression215.3ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHUndisturbed – recompression107.6ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHUndisturbed – recompression53.82ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHUndisturbed – recompression32.29ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHUndisturbed – recompression21.53ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHUndisturbed – recompression10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHUndisturbed – recompression8.61ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHUndisturbed – recompression6.46ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHUndisturbed – recompression5.38ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHRemolded43.06ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHRemolded21.53ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHRemolded16.15ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHRemolded10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHRemolded6.46ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHRemolded4.31ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHRemolded3.77ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHRemolded3.23ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHRemolded2.69ft²/yrLOOK T8.14, p.122
Overconsolidation ratioClaysCL-CHNormally consolidated11.251.5–LOOK T7.10, p.108
Overconsolidation ratioClaysCL-CHLightly overconsolidated1.52.754–LOOK T7.10, p.108
Overconsolidation ratioClaysCL-CHHeavily overconsolidated4–LOOK T7.10, p.108
Open this set in the database ↗
Stiffness (73 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Young's modulus (drained)GravelGW-SPLoose522.1783.21,044ksfLOOK T11.7, p.152
Young's modulus (drained)GravelGW-SPMedium1,0441,5662,088ksfLOOK T11.7, p.152
Young's modulus (drained)GravelGW-SPDense2,0883,1334,177ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPVery loose104.4ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPLoose62.7135.8208.9ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPMedium dense167.1396.9626.6ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPDense522.1783.21,044ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPVery dense835.41,4622,088ksfLOOK T11.7, p.152
Young's modulus (drained)Fine sandGW-SPLoose104.4156.7208.9ksfLOOK T11.7, p.152
Young's modulus (drained)Fine sandGW-SPMedium208.9365.5522.1ksfLOOK T11.7, p.152
Young's modulus (drained)Fine sandGW-SPDense522.1783.21,044ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHSoft208.9ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHSoft167.1ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHStiff208.9313.3417.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHStiff167.1240.2313.3ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHHard417.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHHard313.3ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHVery soft62.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHVery soft41.8ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHSoft41.894146.2ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHSoft20.962.7104.4ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHFirm104.4177.5250.6ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHFirm83.5125.3167.1ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHStiff208.9365.5522.1ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHStiff146.2281.9417.7ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHVery stiff417.77311,044ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHVery stiff313.3522.1731ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHHard835.41,2531,671ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHHard626.6939.81,253ksfLOOK T11.7, p.152
Small-strain shear modulusSoft clays57172287ksfGEC5 T30, p.181
Small-strain shear modulusFirm clays144432.5721ksfGEC5 T30, p.181
Small-strain shear modulusSilty sands5761,7292,882ksfGEC5 T30, p.181
Small-strain shear modulusDense sands and gravels1,4414,3237,205ksfGEC5 T30, p.181
Poisson's ratio, short termSands, gravels and other cohesionless soilsShort term0.3–LOOK T11.17, p.157
Poisson's ratio, long termSands, gravels and other cohesionless soilsLong term0.3–LOOK T11.17, p.157
Poisson's ratio, short termClay, low PI (<12%)Short term0.35–LOOK T11.17, p.157
Poisson's ratio, long termClay, low PI (<12%)Long term0.25–LOOK T11.17, p.157
Poisson's ratio, short termClay, medium PI (12–22%)Short term0.4–LOOK T11.17, p.157
Poisson's ratio, long termClay, medium PI (12–22%)Long term0.3–LOOK T11.17, p.157
Poisson's ratio, short termClay, high PI (22–32%)Short term0.45–LOOK T11.17, p.157
Poisson's ratio, long termClay, high PI (22–32%)Long term0.35–LOOK T11.17, p.157
Poisson's ratio, short termClay, extremely high PI (>32%)Short term0.45–LOOK T11.17, p.157
Poisson's ratio, long termClay, extremely high PI (>32%)Long term0.4–LOOK T11.17, p.157
Poisson's ratioCohesive soil (settlement analysis)CL-CH0.4–USACE para. 3-9c, p.47
Poisson's ratioSubgrade soils0.250.3250.4–LOOK T13.28, p.192
Poisson's ratioGranular pavement materialGW / GP0.35–LOOK T13.28, p.192
Poisson's ratioWeathered rock subgradeRock0.3–LOOK T13.28, p.192
Poisson's ratioUnweathered bedrock subgradeRock0.15–LOOK T13.28, p.192
Modulus of elasticitySoft clay365472ksfDASP T11.4, p.319
Modulus of elasticityHard clay122.4205.2288ksfDASP T11.4, p.319
Modulus of elasticityLoose sand216396576ksfDASP T11.4, p.319
Modulus of elasticityDense sand7201,0801,440ksfDASP T11.4, p.319
Poisson's ratioLoose sand0.20.30.4–DASP T11.5, p.320
Poisson's ratioMedium sand0.250.3250.4–DASP T11.5, p.320
Poisson's ratioDense sand0.30.3750.45–DASP T11.5, p.320
Poisson's ratioSilty sand0.20.30.4–DASP T11.5, p.320
Poisson's ratioSoft clay0.150.20.25–DASP T11.5, p.320
Poisson's ratioMedium clay0.20.350.5–DASP T11.5, p.320
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 0–4VIICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 4–8VICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 9–15VCRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 16–25IVCRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 26–40IIICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 41–60IICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN > 60ICRAIG T8.4, p.315
Coefficient of subgrade reaction (1-ft plate)Loose sand18.438.658.9pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Medium dense sand36.8165.8294.7pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Dense sand221340.8460.5pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey sand110.5202.6294.7pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Silty sand73.7128.9184.2pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey soil, su < 1,044 psf (50 kPa)36.855.273.7pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey soil, su 1,044–2,089 psf (50–100 kPa)73.7128.9184.2pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey soil, su > 2,089 psf (100 kPa)184.2pciROB T9, p.84
Open this set in the database ↗
References (7)
  1. CB – Carter, M. & Bentley, S.P. (2016). Soil Properties and their Correlations, 2nd ed. Wiley.
  2. CRAIG – Craig, R.F. (2004). Craig's Soil Mechanics, 7th ed. Spon Press.
  3. DASP – Das, B.M. (2010). Principles of Geotechnical Engineering, 7th ed. Cengage.
  4. GEC5 – Sabatini, P.J. et al. (2002). FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017)), Geotechnical Engineering Circular No. 5: Evaluation of Soil and Rock Properties.
  5. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.
  6. ROB – Robertson, P.K. & Cabal, K.L. (2010). Guide to Cone Penetration Testing for Geotechnical Engineering, 4th ed. Gregg Drilling & Testing.
  7. USACE – U.S. Army Corps of Engineers (1990). EM 1110-1-1904, Settlement Analysis.
Correlations (15)
EstimateCorrelationLimits / notesSource
Compression index – claysCc = 0.009 (LL − 10) (organic soils, sensitivity < 4)Skempton / Terzaghi & PeckUSACE 3-7, p.59
Compression index – claysCc = 1.15 (e0 − 0.35); Cc = 0.012 wn; Cc = 0.01 (LL − 13)All claysUSACE 3-7, p.59
Compression index – organic soils, peatCc = 0.0115 wnwn in percentUSACE 3-7, p.59
Compression index – varved claysCc = (1 + e0) [0.1 + 0.006 (wn − 25)]USACE 3-7, p.59
Compression index – remolded claysCc = 0.007 (LL − 7)Azzouz et al. (1976)CB 5.2, p.109
Compression index – inorganic silt/clayCc = 0.30 (e0 − 0.27); Cc = 0.75 (e0 − 0.5)Azzouz et al. (1976)CB 5.2, p.109
Recompression indexCr ≈ 0.05–0.10 Cc (range 0.015–0.35)Roscoe et al. (1958)CB 5.1 text, p.108
Secondary compression indexCα ≈ 0.0001 wn (10 < wn < 3000%)NAVFAC DM 7.1USACE 3-14 text, p.79
Drained modulus of clay from suE′/su ≈ 270 (PI 10–30), 200 (20–30), 150 (30–40), 130 (40–50)Stroud et al. (1975)LOOK 11.13, p.155
Shear modulus at small and large strainG(large) ≈ E/2.5; G(small) ≈ 2E ≈ 5 G(large)LOOK 11.2 notes, p.148
Stiffness degradationE0.01/E0 = 0.8–0.9; E0.1/E0 = 0.4–0.5; E1.0/E0 = 0.1–0.2Heymann (1998)LOOK 11.3, p.148
Small-strain shear modulus from shear wave velocityG0 = ρ Vs² = (γ/g) Vs² (γ in pcf, g = 32.2 ft/s², Vs in ft/s → G0 in psf)Seismic CPT or other Vs measurementROB text, p.53
Subgrade reaction size effectks = ks1 [(B + 1)/(2B)]², B in ftTerzaghi (1955); large scatterROB 9 text, p.84
Overconsolidation ratio from CPTOCR = 0.25 Qt^1.25 (Robertson 2009); OCR = k Qt, k = 0.33 (0.2–0.5) (Kulhawy & Mayne 1990)Kulhawy & Mayne valid for Qt < 20ROB text, p.46
Constrained modulus from CPTM = αM (qt − σvo); Ic > 2.2: αM = Qt when Qt < 14, αM = 14 when Qt > 14; Ic < 2.2: αM = 0.0188 · 10^(0.55 Ic + 1.68)Robertson (2009); lower in organic soilsROB text, p.62
All correlations ↗

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
Executive Summary

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1. For railroad infrastructure, settlement governs more designs than bearing capacity failure — particularly embankment fills over soft alluvial soils, approach fills behind bridge abutments, and intermodal yard slabs on compressible clay. Total settlement S_total consists of three components: immediate (elastic) settlement S_i, primary consolidation settlement S_c, and secondary compression S_s. Time-rate analysis using Terzaghi's consolidation theory predicts when settlement will occur, enabling the consultant to recommend preloading, staged construction, or ground improvement to achieve acceptable geometry before track placement. This chapter develops all three settlement components in English units, cross-references FRA track geometry tolerances by track class as the acceptance criteria, and presents worked examples for a Class I railroad embankment over soft clay, a Class I railroad bridge approach fill with time-rate prediction, and a Class I railroad intermodal yard slab on overconsolidated clay. Owner railroad requirements are noted where they commonly differ.

Immediate vs. Consolidation Settlement
Immediate vs. Consolidation Settlement
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
IS-17Preconsolidation stress / OCR from CPTσ'ₚ, OCR
IX-05Secondary compression ratioC_α
IX-01Compression index from liquid limit (undisturbed)C꜀
IX-02Compression index from liquid limit (remolded)C꜀
IX-03Compression index from void ratioC꜀
IX-04Compression index from plasticity indexC꜀
IS-08Drained Young's modulus of sand from SPTE'
IS-19Constrained modulus from CPTM
6.2.1 Background and Railroad Context

FRA track geometry tolerances (49 CFR Part 213) establish the operational framework within which all settlement predictions must be evaluated. Unlike building foundations, where total settlement of 1–2 in. is routinely acceptable, railroad track geometry tolerances are measured in fractions of an inch — the structural consequence of derailment, speed restriction, or emergency slow order is immediate and measurable.

Foundation Settlement
Foundation Settlement
Table 6.2-1 — FRA Track Geometry Tolerances vs. Settlement Acceptance Criteria
Track ClassMax Speed (Freight)Cross-Level ToleranceSurface (Profile) Tolerance, 62-ft chordTotal Settlement Limit (our recommendation)Angular Distortion Limit
Class 110 mph3 in.3 in. per 62 ft≤ 3.0 in.≤ 1/200
Class 225 mph2 in.2¾ in. per 62 ft≤ 2.0 in.≤ 1/300
Class 340 mph1¾ in.2¼ in. per 62 ft≤ 1.5 in.≤ 1/400
Class 460 mph1¼ in.2 in. per 62 ft≤ 1.0 in.≤ 1/500
Class 580 mph1 in.1¼ in. per 62 ft≤ 0.75 in.≤ 1/700
Class 6110 mphsee 49 CFR 213.331see 49 CFR 213.331≤ 0.5 in.≤ 1/1,000
Class 7 (high-speed passenger corridor)125 mphsee 49 CFR 213.331see 49 CFR 213.331≤ 0.375 in.≤ 1/1,500

Angular distortion δ/L (where δ = differential settlement between two points, L = distance between them) is the critical parameter for bridge approach transitions and structure-embankment interfaces. Passenger railroads commonly impose tighter limits than FRA at structure transitions.

Owner railroads often set settlement limits tighter than the FRA minima. Confirm them when the work is scoped.

Settlement at subgrade, tie and rail level by subgrade class

Elastoplastic finite-element results reproduced by Profillidis show the settlement under a passing axle at the top of subgrade, at the tie and at the rail for subgrade classes S1, S2, S3 and rock, for track-bed thicknesses of 12–39 in.. Subgrade class dominates: moving from S1 to S3 cuts the settlement several-fold, while extra track-bed thickness gives a smaller, steady reduction. Tie type matters less than subgrade class.

Figure 6.2-11. Vertical settlement at subgrade and tie level vs. track-bed thickness e, for subgrade classes S1–S3 and rock. Profillidis Fig. 8.8.
Figure 6.2-11. Vertical settlement at subgrade and tie level vs. track-bed thickness e, for subgrade classes S1–S3 and rock. Profillidis Fig. 8.8.
Figure 6.2-12. Vertical settlement at tie and rail level vs. track-bed thickness e, by tie type and subgrade class. Profillidis Fig. 8.9.
Figure 6.2-12. Vertical settlement at tie and rail level vs. track-bed thickness e, by tie type and subgrade class. Profillidis Fig. 8.9.

For new fills, the book reminds designers to overbuild embankment width and height to allow for the fill’s own compaction after construction (Chapter 2.1, §2.1.2).

Compaction vs. Consolidation
Compaction vs. Consolidation

After Profillidis (2014), §8.4.7, Figs. 8.8–8.9. Full reference under Supplemental References.

6.2.2 Stress Increase in Soil — Boussinesq Distribution

Before computing settlement, the change in vertical stress Δσ_v at depth z due to the applied load must be determined. For a uniformly loaded rectangular area of width B and length L at the surface:

Equation 6.2-1 — Boussinesq Stress Increase Under Corner of Rectangle:

Δσ_v = q · I_σ

Where I_σ is the Boussinesq influence factor (Newmark, 1935), a function of m = B/z and n = L/z:

I_σ = (1/4π)[2mn√(m²+n²+1)/(m²+n²+1+m²n²) × (m²+n²+2)/(m²+n²+1)

+ arcsin(2mn√(m²+n²+1)/(m²+n²+1+m²n²))]

Take the arcsin term between 0 and π: when m²n² > m²+n²+1 (wide, shallow cases), use π − arcsin(…) instead of the principal value. The equivalent tangent form is tan⁻¹[2mn√(m²+n²+1)/(m²+n²+1−m²n²)], adding π when the denominator is negative. Using the principal arcsin value alone under-predicts I_σ in that range.

Source: Newmark, N.M. (1935), Simplified Computation of Vertical Pressures in Elastic Foundations, Univ. of Illinois Eng. Exp. Station Circular 24, Eq. 5; Bowles, J.E. (1996), Foundation Analysis and Design, 5th ed., McGraw-Hill.

For practical use, Boussinesq influence charts (or tables) are used; I_σ ranges from 0.25 (square footing, z = 0) to near zero at large depth. For a 2:1 stress distribution approximation, commonly used for preliminary analysis:

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Iσintermediate value computed on this pageAnother equationComputed: I_σ = (1/4π)[2mn√(m²+n²+1)/(m²+n²+1+m²n²) × (m²+n²+2)/(m²+n²+1)project-specific
Equation 6.2-2 — 2:1 Stress Distribution:

Δσ_v = Q / [(B + z)(L + z)] (psf)

Where Q = total load (lb), B and L = footing dimensions (ft), z = depth below footing base (ft). For strip loads (railroad embankments):

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Qtotal load (lb), B and L = footing dimensions (ft), z = depth below footing base (ft)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Equation 6.2-3 — Strip Load Stress Increase:

Δσ_v = (q/π)[β + sin β · cos(β + 2δ)] (psf)

Where β = the angle subtended by the load width at depth z (radians), δ = angle from load centerline, q = applied surface pressure (psf). For the centerline of a strip load:

Δσ_v,center = (q/π)[β + sin β]

Inputs: where each value comes from (2)
SymbolWhat it isComes fromHow to get itTypical range
Δσvintermediate value computed on this pageAnother equationComputed: Δσ_v = (q/π)[β + sin β · cos(β + 2δ)] (psf)project-specific
βthe angle subtended by the load width at depth z (radians), δ = angle from load centerline, q = applied surface pressure (psf)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
6.2.3 Immediate (Elastic) Settlement

Immediate settlement occurs under undrained loading conditions in saturated cohesive soils, or drained loading in granular soils. It develops essentially instantaneously upon load application.

Equation 6.2-4 — Immediate Settlement (Flexible Rectangular Footing):

Si = q · B · (1 − μ²) / Es · Iw

Where:

  • q = net contact pressure (psf)
  • B = footing width (ft)
  • μ = Poisson's ratio (0.5 for undrained clay; 0.3–0.35 for sand)
  • E_s = elastic modulus of soil (psf)
  • I_w = influence factor for shape and embedment (Bowles, 1996; I_w ≈ 0.82 for square, 1.12 for L/B = 2, 1.52 for L/B = 5; rigid-footing values, flexible-center values are higher, e.g., 1.12 for a square)
Table 6.2-2 — Typical Elastic Modulus Values for Settlement Analysis (English Units)
Soil Type (USCS)E_s (psf)Typical Source
Very soft clay (CH)10,000–25,000Unconfined compression
Soft clay (CL)25,000–75,000Unconfined compression
Medium stiff clay75,000–150,000CPTu, PMT
Stiff clay150,000–300,000CPTu, PMT
Very stiff clay300,000–500,000PMT, pressuremeter
Loose sand (SP/SM)100,000–250,000SPT correlation
Medium-dense sand250,000–500,000SPT correlation
Dense sand/gravel500,000–1,500,000SPT correlation

Immediate settlement is critical for intermodal yard slab design and for any structure where the total settlement is dominated by granular or stiff-clay subgrades. For most railroad embankment designs over soft cohesive soils, primary consolidation governs and S_i is secondary.

Inputs: where each value comes from (5)
SymbolWhat it isComes fromHow to get itTypical range
qnet contact pressure (psf)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Bfooting width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
μPoisson's ratio (0.5 for undrained clayAssumed (published values)Rarely measured; choose from published ranges. Use 0.5 for undrained clay.0.25–0.40; 0.5 undrained · by USCS group
Eselastic modulus of soil (psf)Field test, lab test or correlationPressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc.loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group
Iwinfluence factor for shape and embedment (Bowles, 1996; I_wAnother equationComputed: I_w = 0.82 for square, 1.12 for L/B = 2, 1.52 for L/B = 5; rigid-footing values, flexible-center values are higher, e.g., 1.12 for a square)≈ 0.82 for square, 1.12 for L/B = 2, 1.52 for L/B = 5
Supplemental reference

Granular soils: Schmertmann strain-influence method

Eq. 6.2-4 assumes a single modulus for the whole stressed zone. For footings, signal foundations and yard slabs on sand, USACE EM 1110-1-1904 recommends Schmertmann’s approximation, which sums strain over sublayers of thickness Δz = 0.2B using a triangular strain-influence diagram (Figure 12-S1):

Recommended strain influence factors for Schmertmann&rsquo;s approximation (Schmertmann, Hartman &amp; Brown, 1978, reproduced in EM 1110-1-1904).
Supplemental Figure 12-S1. Recommended strain influence factors for Schmertmann’s approximation (Schmertmann, Hartman & Brown, 1978, reproduced in EM 1110-1-1904). Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904, p. 3-8.

ρi = C1 · Ct · Δp · Σ (Izi / Esi) Δzi

  • C1 = 1 − 0.5 σ′od/Δp ≥ 0.5 (embedment correction); Δp = q − σ′od (net pressure).
  • Ct = 1 + 0.2 log10(t/0.1), t in years — creep of the sand; after 50 years Ct ≈ 1.54, which matters for long-life railroad structures.
  • Peak factor Izp = 0.5 + 0.1(Δp/σ′Izp)1/2, located at B/2 below the base for square/circular footings (Iz reaching zero at 2B) and at B for strip footings (zero at 4B); interpolate for 1 < L/B < 10.
  • Modulus from the cone: Es = 2.5 qc (axisymmetric) and 3.5 qc (plane strain). Where only SPT data exist, USACE converts N to qc (tsf) with qc/N = 2 (silts, sandy silts), 3.5 (clean fine–medium sand), 5 (coarse sand) and 6 (sandy gravel).

Because the method weights the stiffness of each sublayer, it captures a loose sand seam at depth B/2 that a single-modulus calculation averages away.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

Case study: 6.2.16.1 Unit weight of fill: design assumes 127 pcf, the job measures more (Look 2023), in §12.16 Case Studies.

6.2.3.1 Elastic Settlement of Shallow Foundations

Signal, catenary and communication foundations, culvert footings and small bridge spread footings on sand or stiff clay settle mostly at once, as the soil compresses elastically when the load goes on. Das's Principles of Geotechnical Engineering (Section 11.2) gives the standard method. Steinbrenner's shape factors F1 and F2 account for the foundation's proportions and the depth to a rigid layer. Fox's depth factor accounts for embedment. A weighted average modulus over the depth of influence, min(H, 5B) after Bowles, handles layered soil. The result is for the center or corner of a flexible foundation, and a rigid foundation settles about 0.93 times the flexible center value. Das gives representative moduli, and CPT correlations (Es ≈ 2qc to 3qc in sand) connect the method to the soundings in Chapter 5.1.

6.2.3.1.1 Method

Equation 6.1-22. Elastic settlement (Das Eqs. 11.1 to 11.10)

Se = Δσ(αB′)(1 − μs²)/Es × IsIf;   Is = F1 + [(1 − 2μs)/(1 − μs)]F2

Center: α = 4, B′ = B/2, m′ = L/B, n′ = H/(B/2);   corner: α = 1, B′ = B, n′ = H/B
Es = ΣEs(i)Δz / z̄, z̄ = min(H, 5B);   Se(rigid) ≈ 0.93Se(flexible, center)

Table 6.1-6. Das Example 11.1 (1 m × 2 m rigid footing, Df = 1 m, rock at 5 m, Δσ = 150 kPa, μ = 0.3), run in English units
QuantityDasCalculator
Weighted modulus Es10,400 kPa (1,508 psi)1,508 psi
F1, F2 (from tables)0.641, 0.0310.641, 0.031 (closed form)
If0.710.71
Is0.7160.658
Settlement, flexible center13.3 mm12.3 mm
Settlement, rigid12.4 mm11.4 mm

The calculator matches F1, F2, If and Es. Das's example arrives at Is = 0.716 by using (2 − μ)/(1 − μ) in place of the (1 − 2μ)/(1 − μ) of Equation 11.2. With the equation as printed, Is = 0.658 and the settlement is about 8% smaller; with 0.716 the calculator also gives 13.3 mm.

6.2.3.1.2 Worked example

Das's footing, 3.3 by 6.6 ft at 3.3 ft depth with rock 16.4 ft down, carrying 3,133 psf net over layers with moduli of 1,450, 1,160 and 1,740 psi, settles 0.48 in. at the center if flexible and 0.45 in. if rigid. The corner of a flexible footing settles 0.21 in. Most of the uncertainty is in the modulus. A factor of two in Es, well within the ranges in Das's Table 11.4, doubles the settlement. Poisson's ratio matters much less, as the calculator's chart shows.

Get the modulus from the soil that will actually be loaded: CPT qc in sands (Chapter 5.1), or the reload part of consolidation or triaxial tests in clays. For clays, add consolidation settlement (Chapter 6.2) to the elastic value; this calculator covers only the immediate part.

Open the elastic settlement calculator →
Steinbrenner shape factors in closed form, the Fox depth factor, a weighted modulus over min(H, 5B), and flexible center, flexible corner and rigid settlements, with the effect of Poisson's ratio.

6.2.3.1.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • B.M. Das, Principles of Geotechnical Engineering, 7th edition: Section 11.2, elastic settlement (Eqs. 11.1 to 11.10, Tables 11.1 to 11.5, Example 11.1), and CPT modulus correlations (Eqs. 18.23 and 18.24)Find source ↗
  • R.F. Craig, Craig's Soil Mechanics, 7th edition: immediate settlement and elastic stress distributionFind source ↗Library entry
  • B.G. Look, Handbook of Geotechnical Investigation and Design Tables (2007): soil modulus valuesFind source ↗
Supplemental reference · Carter & Bentley (2016), §5.4

Scaling a Plate Load Test to a Footing, and Which SPT N to Use

Plate to footing. A plate load test stresses the ground to a depth of only about twice the plate width, so its settlement has to be scaled up to the foundation. The usual relation for a square footing on sand (Terzaghi and Peck 1967) is:

ρB = ρ1 [2B / (1 + B)]2

where ρ1 = settlement of a 1-ft square plate, ρB = settlement of a footing of side B, and B is in feet. The ratio can never exceed 4, however large the footing. A more general relation (Ménard and Rousseau 1962) is:

ρ2 / ρ1 = (B2 / B1)α

where ρ1 and B1 are the plate settlement and width and ρ2 and B2 those of the footing. Typical α: sands and gravels 1/3 to 1/2; saturated silts 1/2; clays and dry silts 1/2 to 2/3; compacted fill 1. For example, a 1-ft plate that settles 0.25 in. under the design pressure predicts 0.25 × (12/7)2 = 0.73 in. for a 6-ft square signal-bridge footing by Terzaghi and Peck, or 0.25 × 60.4 = 0.51 in. by Ménard with α = 0.4. The spread between the two is typical. Neither relation detects a soft layer below the plate’s zone of influence, so confirm the profile with a boring to at least twice the footing width.

Do not correct N for settlement charts. The SPT-based settlement methods (Terzaghi and Peck, Meyerhof, Bowles’s adjustments and Burland and Burbidge) were all fitted to blow counts that were not corrected for overburden pressure. Applying CN to them raises the allowable bearing pressure or lowers the predicted settlement without any basis. Use the field N, corrected only for energy where the method calls for N60, and keep the overburden-corrected (N1)60 for relative density and liquefaction.

Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.4.1.4 and §5.4.2, Eqs. 5.36–5.38. Summarized and paraphrased; worked figures added. Full reference under Supplemental References.

6.2.4 Primary Consolidation Settlement
6.2.4.1 Settlement Equations

Primary consolidation settlement S_c is governed by the compressibility of the clay skeleton as excess pore pressures dissipate. Three cases apply depending on the preconsolidation stress σ'_p:

Settlement Calculation
Settlement Calculation
Equation 6.2-5 — Normally Consolidated Clay (σ'_v0 = σ'_p):

Sc = [Cc / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_v0]

Inputs: where each value comes from (3)
SymbolWhat it isComes fromHow to get itTypical range
Cccompression indexLab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
e0void ratioAnother equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
Equation 6.2-6 — Overconsolidated Clay, Stress Remains Below σ'_p:

Sc = [Cs / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_v0]

Inputs: where each value comes from (2)
SymbolWhat it isComes fromHow to get itTypical range
e0void ratioAnother equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
Equation 6.2-7 — Overconsolidated Clay, Stress Exceeds σ'_p:

Sc = [Cs / (1 + e₀)] · H · log[σ'_p / σ'_v0]

+ [Cc / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_p]

Where:

  • C_c = compression index (dimensionless)
  • C_s = swell/recompression index ≈ C_c/5 to C_c/10 (dimensionless)
  • e₀ = initial void ratio (dimensionless)
  • H = layer thickness (ft)
  • σ'_v0 = initial effective vertical stress at midpoint of layer (psf)
  • σ'_p = preconsolidation stress (psf); OCR = σ'_p / σ'_v0
  • Δσ = stress increase at midpoint of layer from applied load (psf)
Inputs: where each value comes from (8)
SymbolWhat it isComes fromHow to get itTypical range
Cccompression index (dimensionless)Lab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
Csswell/recompression index ≈ C_c/5 to C_c/10 (dimensionless)Lab testUnload–reload slope of the e–log σ' curve (ASTM D2435). Screening: Cr ≈ Cc/5 to Cc/10.0.01–0.08 (inorganic clays) · by USCS group
e₀initial void ratio (dimensionless)Another equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
Hlayer thickness (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
σ'v0initial effective vertical stress at midpoint of layer (psf)Another equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
σ'ppreconsolidation stress (psf)Lab test (or correlation)Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0.OCR 1 (NC) to > 4 (heavily OC) · by USCS group
OCRpreconsolidation stress / OCR = σ'_p / σ'_v0Lab test (or correlation)Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0.OCR 1 (NC) to > 4 (heavily OC) · by USCS group
Δσstress increase at midpoint of layer from applied load (psf)Another equationStress increase from the applied load: Boussinesq influence factor or 2:1 distribution (settlement chapter), or the track load-spread equations.project-specific
Equation 6.2-8 — Empirical C_c Estimate (Terzaghi and Peck 1967, after Skempton 1944):

Cc = 0.009 · (LL − 10)

Where LL = liquid limit (%). Valid for normally consolidated clays; use with caution for organic soils. For railroad projects, laboratory consolidation tests (ASTM D2435) should support any embankment over about 6 ft high on soft clay.

Inputs: where each value comes from (2)
SymbolWhat it isComes fromHow to get itTypical range
Cccompression index = 0.009 · (LL − 10)Lab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
LLliquid limit (%)Lab testAtterberg limits (ASTM D4318) on the minus No. 40 fraction.CL 20–50, CH 50–110 · by USCS group
Equation 6.2-9 — Void Ratio from Unit Weight:

e₀ = (Gs · γ_w / γ_d) − 1

Where G_s = specific gravity (≈ 2.70 for most clays), γ_d = dry unit weight (pcf), γ_w = 62.4 pcf.

Inputs: where each value comes from (3)
SymbolWhat it isComes fromHow to get itTypical range
e₀void ratio = (Gs · γ_w / γ_d) − 1Another equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
Gsspecific gravity (≈ 2.70 for most clays), γ_d = dry unit weight (pcf), γ_w = 62.4 pcf.Lab testSpecific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested.2.64–2.80 mineral; lower if organic · by USCS group
γddry unit weightLab or field testLab: ASTM D7263 on tube samples. Field: nuclear gauge (ASTM D6938), sand cone (D1556) or drive cylinder (D2937). Or γd = γ/(1 + w).sands 90–125, clays 80–115 pcf · by USCS group
6.2.4.2 Sublayer Method

When a compressible layer is thick (> 5 ft) or when the stress increase varies significantly with depth, the layer should be divided into sublayers of 2–4 ft thickness. Settlement is computed for each sublayer at its midpoint stress state, then summed:

Equation 6.2-10 — Sublayer Summation:

Sc,total = Σ [Cc,i / (1 + e₀,i)] · Hi · log[(σ'_v0,i + Δσ_i) / σ'_v0,i]

Use this sublayer approach for clay layers thicker than about 10 ft, where ignoring stress variation underestimates settlement at the top of the layer and overestimates at depth.

Inputs: where each value comes from (3)
SymbolWhat it isComes fromHow to get itTypical range
Cccompression indexLab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
e0void ratioAnother equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific

Settlement on organic ground: field cases

Organic soils can compress by up to about 40% (12 ft of peat can mean 5 ft of settlement). Muskeg also punches under load, and buried corduroy decays. At one Canadian swamp crossing, years of swamp ties never stopped the settlement; only a proper berm, together with draining the water driving the movement, solved it. At a peat site in northern Alberta, 400 ft of differential settlement into deep peat needed piles. In 2016 dollars, swamp ties cost about $670,000 per mile, against about $280,000 per mile for undercutting and about $6.7 million per mile for new track (course figures of $600,000, $250,000 and $6,000,000 in 2012 dollars, escalated by the ENR Construction Cost Index; see Chapter 7.2, Table 7.2-6), so diagnosing the mechanism early is the cheapest option.

Figure 6.2-14. The Lac la Biche corridor through low-lying burned forest.
Figure 6.2-14. The Lac la Biche corridor through low-lying burned forest.
Figure 6.2-15. Bedford Mile 29.8 embankment instability.
Figure 6.2-15. Bedford Mile 29.8 embankment instability.

After Geotechnology for Railroaders Program, Module 2, Module 6.1, Module 6.2; Module 2 §08; Module 6.1 §03; Module 6.2 §01, §05. Full reference under Supplemental References.

6.2.4.3 Consolidation Settlement and Time Rate Calculator

The USACE manual Settlement Analysis (EM 1110-1-1904) gives the standard one-dimensional procedure: divide the compressible layer into sublayers, compute the initial effective stress and the stress increase in each, and sum the settlement using the recompression and virgin compression indices on either side of the preconsolidation pressure. Railroad fills are a near-ideal case for this method: a widening for a siding or a raise in grade is wide compared with the clay thickness, so the stress increase is nearly uniform with depth and lateral strain is small.

6.2.4.3.1 Method

Equation 6.2-20. Primary consolidation settlement of a sublayer

S = Cr H/(1 + e0) log(σ'p/σ'v0) + Cc H/(1 + e0) log[(σ'v0 + Δσ)/σ'p]

using only the first term when σ'v0 + Δσ ≤ σ'p.

Equation 6.2-21. Time rate (Terzaghi theory)

Tv = cv t / Hdr²; U ≤ 60%: Tv = (π/4)U²; U > 60%: Tv = 1.781 − 0.933 log(100 − U%)

t50 = 0.197 Hdr²/cv; t90 = 0.848 Hdr²/cv

Table 6.2-6. Estimates of the compression index (EM 1110-1-1904, Table 3-7)
SoilCc
Clays0.01(LL − 13); 0.012 wn; 1.15(e0 − 0.35)
Soils of sensitivity below 4 (Terzaghi and Peck relation)0.009(LL − 10)
Organic soils, peat0.0115 wn
Varved clays(1 + e0)[0.1 + 0.006(wn − 25)]
Uniform silts0.20
Uniform sand, loose / dense0.05 to 0.06 / 0.02 to 0.03

Use correlations for planning only; design values come from oedometer tests on undisturbed samples (Chapter 5.2).

6.2.4.3.2 Worked example: siding embankment over soft clay

Table 6.2-7. Ten-foot embankment widening over 18 ft of soft clay (calculator output)
InputValueResultValue
Fill load q (10 ft at 125 pcf)1,250 psfPrimary settlement Sc15.34 in.
Clay: top at 4 ft, thickness, water depth18 ft, 3 ftTime to 50% consolidation6.5 months
e0, Cc (LL = 58), Cr, OCR1.20, 0.45, 0.06, 1.2Time to 90% consolidation28.2 months
cv, drainage0.08 ft²/day, doubleSecondary compression, 25 years1.88 in.
Cα0.018Total17.22 in.

A foot of settlement taking several years to complete is typical of new fill on lake-plain and coastal clays. Under track it shows up as repeated surfacing and a dip at the transition to the old embankment. The options are covered in Chapter 7.2: surcharge with or without wick drains (which shorten Hdr, cutting t90 roughly with its square), lightweight fill, or staged construction with monitoring (Chapter 5.3).

Open the settlement calculator →
Sublayered consolidation settlement under a wide fill or a footing (2:1), time to 50% and 90% consolidation, secondary compression, and a settlement-time curve.

6.2.4.3.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.

  • Settlement Analysis, USACE EM 1110-1-1904 (1990), Settlement folder: procedure, compression index table, time factors and worked examples.Find source ↗Library entry
  • Consolidation and Settlement Analysis (P. J. Fox, handbook chapter), Soil Mechanics folder: immediate, consolidation and secondary components.Find source ↗
  • Rate of Consolidation — Terzaghi Theory (course notes).Find source ↗Library entry
  • Controlling Differential Settlement of Highway Soft Soil Subgrade (book), Settlement folder: treatment of transitions.Find source ↗
Supplemental reference · Carter & Bentley (2016), §5.1, §5.5

Compressibility From SPT and CPT, and the Field Correction to Oedometer Settlement

Track and embankment projects often have many SPT or CPT soundings and only a few consolidation tests. The correlations below spread the consolidation results along the alignment. Calibrate each one against the site’s own oedometer tests before using it for design.

mv from SPT N and PI (Stroud and Butler 1975). For overconsolidated clays, stiff insensitive clays and soft rocks, the coefficient of volume compressibility falls with blow count and plasticity. The published chart is fitted by:

1 / (mv N) = 1,170 / PI2.07 + 9.1  (ksf)

so that mv (ft²/kip) = 1 / [N × (1,170/PI2.07 + 9.1)]. In SI the fit is 56,000/PI2.07 + 435 kPa. It is widely used for normally consolidated soils as well, but it was derived for overconsolidated soils and is unlikely to hold for soft clays.

Table 6.2-11. Stroud and Butler factor 1/(mvN) vs. plasticity index (from the curve fit)
PI101520304060
1/(mvN), ksf19.013.411.510.19.79.3
1/(mvN), kPa912641549484462447

Settlement from mv: S = mv Δσ H. With mv in ft²/kip, Δσ in ksf and H in ft, S is in feet.

mv from cone resistance (Meigh 1987). For normally consolidated and lightly overconsolidated clays and silts up to firm consistency, with qc up to about 25 ksf (1.2 MPa):

mv = 1 / (α qc)

With qc in ksf, mv is in ft²/kip. The coefficient α depends on soil type and cone (Table 6.2-12).

Table 6.2-12. Coefficient α for mv = 1/(α qc) (after Meigh 1987, in Carter & Bentley 2016, Table 5.5)
Soil (USCS)α, electric (reference) coneα, mechanical mantle cone
High-plasticity clays and silts (CH, MH)2.5–7.52–6
Low and intermediate plasticity clays (CL), qc < 14.6 ksf3.7–103–8
Low and intermediate plasticity clays (CL), qc > 14.6 ksf2.5–6.32–5
Low and intermediate plasticity silts (ML)3.5–7.53–6
Organic silts (OL)2.5–102–8
Peat and organic clay (Pt, OH), w = 50–100%1.9–5.01.5–4.0
Peat and organic clay, w = 100–200%1.25–1.91.0–1.5
Peat and organic clay, w > 200%0.5–1.250.4–1.0

The British “intermediate plasticity” groups (CI, MI) fall within the USCS CL and ML groups. A lower α means a more compressible soil for the same cone resistance.

Field correction to oedometer settlement (Skempton and Bjerrum 1957). Oedometer settlements overestimate field settlement in overconsolidated clays, because the pore pressure set up under a real foundation is smaller than under one-dimensional loading. Very sensitive clays are the exception: there the oedometer can slightly underestimate. The consolidation settlement is corrected by a factor μ:

Sc,field = μ × Sc,oed

Table 6.2-13. Factor μ by clay type and ratio of layer thickness H to loaded width b (after Skempton 1954, in Carter & Bentley 2016, Fig. 5.5)
ClayH/b = 0.5H/b = 1H/b = 4
Very sensitive clays (soft alluvial, estuarine, marine)1.0–1.11.0–1.11.0–1.1
Normally consolidated clays0.8–1.00.7–1.00.7–1.0
Overconsolidated clays0.6–0.80.5–0.70.4–0.7
Heavily overconsolidated clays (glacial till, marl)0.5–0.60.4–0.50.2–0.4

For a compressible layer starting at depth z below a load of width B, take b ≈ B + z (load spread at 60°). μ applies to the consolidation settlement only, not to immediate or secondary settlement.

For railroad work: Under long embankments and track widenings, H/b is usually small, which gives the largest correction in overconsolidated clay. Use μ to explain why a stiff-clay foundation settled less than predicted, but do not use it to reduce settlement in soft, sensitive or normally consolidated clay, where μ is close to 1. Where the SPT or CPT correlations are used to extend a few oedometer tests along a line, plot the correlated mv against the oedometer values at the same depths. Adopt the correlation only if the two agree within about a factor of 1.5, and say in the report which settlements rest on a correlation (Example 6.2-8).

Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.1.4–5.1.5 and §5.5.1, Eqs. 5.19, 5.20, 5.39, Table 5.5, Figs. 5.3–5.5. Summarized and paraphrased; equations converted to US units. Full reference under Supplemental References.

Example 6.2-8: Settlement of a Second-Main-Track Fill on Stiff Clay From SPT Data

A Class I railroad located in Iowa is adding a second main track on a new fill beside the existing embankment. The borings along the widening found 15 ft of stiff, overconsolidated lean-to-fat clay over dense sand. The SPT blow counts in the clay average N60 = 12, but no consolidation tests have been run yet. The engineer must estimate the settlement of the clay and how long it will take, to decide whether the new track can be surfaced at once or needs a waiting period.

existing new fill stiff OC clay, 15 ftN60 = 12, PI = 25, LL = 45 dense sand (drains) b = 40 ft H = 15 ft Δσ = 1.10 ksf S = ? GivenClay H = 15 ft, drained top and bottomN60 = 12; PI = 25; LL = 45Δσ = 1.10 ksf at mid-layerLoaded width b = 40 ftStress stays below σ′p (assumed) Requiredmv from SPT (Stroud)Oedometer and field settlementcv from LL; time to 90% Black = given; red = required
Given and required for Example 6.2-8.

Given

VariableValueDescription
H15 ftClay thickness; sand below and fill above, so drained top and bottom
N6012Average SPT blow count in the clay
PI, LL25, 45Plasticity index and liquid limit
Δσ1.10 ksfAverage stress increase at mid-layer under the new fill
b40 ftBase width of the new fill
Stress historyOverconsolidated; final stress assumed below σ′pStiff clay

Required

  • (a) mv from the SPT correlation
  • (b) Oedometer-basis consolidation settlement
  • (c) Field settlement with the Skempton–Bjerrum factor
  • (d) cv from the liquid limit and the time to 90% consolidation
  • (e) The effect if the fill pushes the clay past σ′p

Equations

  1. Eq. 1: 1/(mvN) = 1,170/PI2.07 + 9.1 — ksf; mv in ft²/kip
  2. Eq. 2: Sc,oed = mv Δσ H
  3. Eq. 3: Sc,field = μ Sc,oed — Table 6.2-13
  4. Eq. 4: cv ≈ 25,000/LL3.9 (recompression lower limit) or 80/LL2.8 (virgin) — cm²/s; × 33,950 for ft²/yr (Table 6.2-14)
  5. Eq. 5: t90 = 0.848 Hdr2/cv

Steps

Step 1 · (a) mv (Eq. 1)
252.07 = 782; 1,170/782 + 9.1 = 10.6 ksf; mv = 1/(12 × 10.6)
mv = 0.0079 ft²/kip
Spot check: SI form, 56,000/782 + 435 = 506 kPa; 1/(12 × 506) = 0.165 m²/MN = 0.0079 ft²/kip. Medium compressibility, as expected for stiff clay.
↓
Step 2 · (b) Oedometer settlement (Eq. 2)
0.0079 × 1.10 × 15 = 0.130 ft
Sc,oed = 1.6 in.
↓
Step 3 · (c) Field settlement (Eq. 3)
H/b = 15/40 = 0.38, use the H/b = 0.5 column; overconsolidated clay μ = 0.6 to 0.8, take 0.7
Sc,field = 0.7 × 1.6 = 1.1 in.
↓
Step 4 · (d) Time to 90% (Eqs. 4 and 5)
cv ≥ 25,000/453.9 = 0.0089 cm²/s = 303 ft²/yr; Hdr = 7.5 ft; t90 = 0.848 × 56.3/303
t90 ≤ 0.16 yr, about 2 months
↓
Step 5 · (e) If the clay passes σ′p
Virgin cv = 80/452.8 = 0.0019 cm²/s = 64 ft²/yr; t90 = 0.848 × 56.3/64
t90 ≈ 0.75 yr, about 9 months, and S larger (use Cc, Eq. 6.2-7)
↓
Solution
About 1.1 in., mostly within 2 months, if the clay stays overconsolidated.

Solution

(a) mv ≈ 0.0079 ft²/kip. (b) Oedometer-basis settlement 1.6 in. (c) Field settlement about 1.1 in. (d) cv ≥ 300 ft²/yr, so 90% consolidation in about 2 months or less. (e) If the new load takes the clay past its preconsolidation stress, consolidation slows to about 9 months and the settlement grows.

Settlement of about an inch over two months can be taken out by normal surfacing before the track is put to full speed. The answer rests on two things the SPT cannot confirm. First, the Stroud correlation was fitted to overconsolidated clays and is only reliable where that is true. Second, the time depends on whether the clay stays below σ′p. Both are settled by one or two consolidation tests on undisturbed samples from the widening; schedule them before the surfacing plan is fixed. If the tests show the clay is normally consolidated, μ rises toward 1, Cc governs, and a surcharge or waiting period (Section 6.2.8) may be needed. The differential between the new fill and the old embankment, which has finished settling, is what the track will feel, so check angular distortion at the transition (Section 6.2.7).

6.2.5 Time Rate of Consolidation
6.2.5.1 Terzaghi One-Dimensional Theory

The degree of consolidation U (fraction of ultimate settlement completed at time t) is governed by the dimensionless time factor T_v:

Karl Von Terzaghi
Karl Von Terzaghi
Equation 6.2-11 — Time Factor:

Tv = cv · t / H_dr²

Where:

  • c_v = coefficient of vertical consolidation (ft²/day; from ASTM D2435 consolidation test)
  • t = elapsed time (days)
  • H_dr = length of drainage path (ft): H_dr = H/2 for two-way drainage (sand above and below clay); H_dr = H for one-way drainage (clay bounded by impermeable rock)
Table 6.2-3 — Time Factor T_v vs. Average Degree of Consolidation U
U (%)T_v (simplified)T_v (exact)
100.0080.008
200.0310.031
300.0710.071
400.1260.126
500.1970.197
600.2870.287
700.4030.403
800.5670.567
900.8480.848
951.1631.129
99—1.781

For U ≤ 60%:

Tv = π/4 · (U/100)² (simplified parabolic approximation)

For U > 60%:

Tv = −0.933 · log(1 − U/100) − 0.085

Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
Tvintermediate value computed on this pageAnother equationComputed: Tv = cv · t / H_dr²project-specific
cvcoefficient of vertical consolidation (ft²/dayLab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
telapsed time (days)TimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
Hdrlength of drainage path (ft): H_drAnother equationComputed: H_dr = H/2 for two-way drainage (sand above and below clay)project-specific
Drained vs Undrained Analysis
Drained vs Undrained Analysis
Equation 6.2-12 — Settlement at Time t:

S(t) = U · Sc,total

Equation 6.2-13 — Time to Achieve Target Degree of Consolidation:

t = Tv · H_dr² / cv

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
cvcoefficient of consolidationLab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
6.2.5.2 Typical c_v Values
Table 6.2-4 — Typical Coefficient of Consolidation c_v (English Units)
Soil Typec_v (ft²/day)c_v (ft²/year)Notes
Soft organic clay0.0005–0.0050.2–2Coastal Georgia; Manitoba
Soft marine clay0.005–0.052–18Tidewater Virginia; Northeast passenger corridor
Medium clay0.05–0.218–73Kansas and Nebraska
Stiff clay0.2–1.073–365Appalachian residual soils
Very stiff clay1.0–10365–3,650Quick-draining; settle rapidly
Silty clay (CL-ML)0.1–0.537–183the Canadian Prairie provinces
Why Soil Consolidation Happens
Why Soil Consolidation Happens
Soil Consolidation Testing
Soil Consolidation Testing

Multiplying path length squared by unit conversion: if c_v in ft²/day and H_dr in ft, time t is in days.

Supplemental reference · Carter & Bentley (2016), §5.2

Estimating cv From the Liquid Limit

Before consolidation tests are available, the U.S. Navy chart of cv against liquid limit (NAVFAC DM-7, 1982) gives a first estimate of how fast a clay will drain. Carter and Bentley fitted its three trend lines with power functions that reproduce the chart within about 12% (cv in cm²/s, LL in %):

  • Undisturbed, recompression range (lower limit): cv = 25,000 / LL3.9. Values in recompression lie above this line.
  • Undisturbed, virgin compression range: cv = 80 / LL2.8.
  • Completely remolded (upper limit): cv = 1 / LL2.0. Remolded values lie below this line.

To convert cm²/s to ft²/yr multiply by 33,950 (to ft²/day, by 93).

Table 6.2-14. Coefficient of consolidation cv (ft²/yr) from liquid limit, from the curve fits to the NAVFAC chart
Liquid limit (%)3040506080100
Recompression, lower limit1,470480200993214
Virgin compression200894829136.8
Remolded, upper limit3821149.45.33.4

cv also depends strongly on structure, fissuring, sand partings and stress level, so the correlation gives only the likely order of magnitude. The virgin-compression values agree broadly with Table 6.2-4 for medium and stiff clays.

For railroad work: The roughly fivefold drop from the recompression to the virgin line is the important point. A fill that takes an overconsolidated clay past its preconsolidation stress both settles more and settles more slowly. Use the virgin line for preload and surcharge planning, and the remolded line for clay that has been disturbed by wick-drain installation (the smear zone, Section 6.2.8) or by construction traffic. Confirm the design cv with consolidation tests or CPTu dissipation tests, which also capture horizontal drainage through sand layers.

Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.2 and Fig. 5.7, after U.S. Navy (1982). Summarized; table values computed from the fitted equations and converted to ft²/yr. Full reference under Supplemental References.

6.2.6 Secondary Compression (Creep) Settlement

Secondary compression occurs after primary consolidation is essentially complete (U ≈ 95–100%) as the clay skeleton continues to creep under sustained load. It is particularly significant for organic soils (Pt) and highly plastic clays (CH) — common in coastal Georgia swamps, Manitoba peatlands and Louisiana.

Equation 6.2-14 — Secondary Compression Settlement:

Ss = Cα / (1 + ep) · H · log(t₂ / t₁)

Where:

  • C_α = secondary compression index (dimensionless); ≈ 0.04 × C_c for most clays; 0.05–0.10 for organic soils
  • e_p = void ratio at end of primary consolidation (≈ e₀ − ΔeP for primary compression)
  • H = layer thickness (ft)
  • t₁ = time at end of primary consolidation (days)
  • t₂ = design service life or evaluation time (days)
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
Inputs: where each value comes from (6)
SymbolWhat it isComes fromHow to get itTypical range
Cαsecondary compression index (dimensionless)Lab testSlope of e vs log time after primary consolidation in the consolidation test (ASTM D2435).Cα/Cc 0.03–0.08 · by USCS group
epvoid ratio at end of primary consolidation (≈ e₀ − ΔeP for primary compression)Another equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
Hlayer thickness (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
t₁time at end of primary consolidation (days)TimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
t₂design service life or evaluation time (days)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.project-specific
Cccompression indexLab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
Equation 6.2-15 — Empirical C_α (Mesri and Godlewski, 1977):

Cα/Cc ≈ 0.04 ± 0.01 (for inorganic clays)

Cα/Cc ≈ 0.05 to 0.07 (for organic clays and peats)

For a 50-year railroad service life (t₂ = 18,250 days) with primary consolidation completing at t₁ = 500 days, log(18,250/500) = log(36.5) = 1.562. Even a modest C_α = 0.010 over a 10 ft clay layer produces S_s = 0.010/(1 + 1.8) × 10 × 1.562 = 0.056 ft = 0.67 in — significant on a Class 5 mainline with a 0.75 in. tolerance.

Supplemental reference

Cα/Cc by soil type

USACE EM 1110-1-1904 (Table 3-14, after Mesri) extends the ratios in Eq. 6.2-15 to other materials encountered on railroad alignments:

Table 12-S1. Ratio of secondary compression index to compression index

SoilCα/Cc
Inorganic soils0.025–0.060
Clay0.025–0.085
Silt0.030–0.075
Peat0.030–0.085
Muskeg0.090–0.100

For a first approximation before tests are available, USACE (after NAVFAC DM-7.1) gives Cα ≈ 0.0001 wn for natural water contents 10–3,000%. The manual cautions that sample disturbance lowers the measured Cα in the virgin range and that secondary-compression predictions “have often not been reliable” — one more reason to confirm long-term behavior with settlement plates rather than rely on the calculation alone.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

Supplemental reference

Testing peat: what changes from inorganic soil

Lea and Brawner’s British Columbia highway experience gives practical guidance for the peat and muskeg crossings noted above:

  • Water content of pure peat is typically 500–1,500% (occasionally > 2,000%); values below 500% usually indicate mineral content. It can vary several-fold within 1 ft, so moisture samples should be at least 10 in.3 Research cited in the paper found the standard 220–230°F oven chars peat; about 185°F was indicated as more appropriate.
  • Specific gravity of pure peat is about 1.5–1.6, so void ratios are very high (about 18 at w = 1,000%). Gas contents of 7–10% were estimated; assuming full saturation can put e off by about 10%.
  • Unit weight of pure peat was generally 55–75 pcf (wet); dry unit weight can be as low as 4 pcf.
  • Permeability of virgin peat was about 30 to 0.3 ft/day but fell to about 0.03 ft/day under a few feet of fill — so cv measured at low stress overstates the rate under the final embankment.
  • The clay under the peat is often the real problem. Because peat is light and recently deposited, underlying clay — even 30–40 ft down — is likely to be very weak. On the Trans-Canada Highway, 6 ft of granular fill was calculated to produce about 11 ft of settlement (8 ft in peat, 3 ft in clay) and enough load to cause a base failure in the clay.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board

6.2.6.1 Long-Term Settlement of Fills: Creep and Self-Weight

A fill settles under its own weight as well as compressing the ground beneath it. A coarse fill compresses mostly as it is placed and then creeps at constant effective stress; a saturated clay fill first consolidates as construction pore pressures dissipate and then creeps (Skinner, 2012, Section 58.5, p. 905).

Equation 6.2-23. Creep compression rate of a fill

α = Δs / [H log(t2/t1)]    so    Δs = α H log(t2/t1)

Skinner (2012), Eq. 58.2. Δs = settlement between times t1 and t2 after placement; H = fill thickness; α is a strain per log cycle of time.

Table 6.2-9. Creep compression rate α for engineered and non-engineered fills
FillCompactionα (% per log cycle of time)
Sandy gravelHeavy vibrating roller0.04 σ′v
MudstoneHeavy vibrating roller0.12 σ′v
Sandstone or mudstone rockfillHeavy vibrating roller0.13 σ′v
Sandstone or mudstone rockfillNo systematic compaction0.9 to 1.5
Stiff clay fillHeavy systematic compaction0.5

Skinner (2012), Table 58.3, p. 905, from Charles and Watts (2001). For the first three rows σ′v is in MPa (1 MPa = 20.9 ksf); those rows come from embankment dam case histories.

Equation 6.2-24. Self-weight settlement of an embankment

ρi = 0.5 γ H / D*  (average strain);   settlement ≈ 0.5 γ H² / D*

Nowak (2012), Eq. 70.7, p. 1062, after Trenter (2001). D* = equivalent constrained modulus of the fill. For a 33-ft (10-m) embankment Charles (1993) gives D* of 50 for well-compacted sandy gravel and 6 for low-plasticity clay; Vol. II does not print the unit, and MPa (about 1,040 ksf and 125 ksf) gives strains consistent with the next sentence. Confirm against Charles (1993) before design use.

Charles (2008) reports self-weight settlement of less than 0.5% of the height for well-graded granular embankments and less than 1% for clay embankments (Nowak, 2012, p. 1062). Much of it happens during construction; the creep term is what continues under track.

Example 6.2-6: Creep and self-weight settlement of a new clay embankment

A 25-ft embankment of stiff clay fill is built with heavy systematic compaction for a new connection track. Estimate the creep settlement between one year and 30 years after completion, and the self-weight settlement of the fill.

Firm foundationH = 25 ftStiff clay fill, heavily compactedγ = 125 pcf; D* = 125 ksfCreep 1–30 yr = ? Self-weight = ?GivenH = 25 ft; γ = 125 pcfα = 0.5% per log cyclet1 = 1 yr; t2 = 30 yrD* = 125 ksf (6 MPa)RequiredCreep settlement, 1 to 30 yrSelf-weight settlement and its share of heightBlack = given; red = required
Given and required for Example 6.2-6.

Given

VariableValueDescription
H25 ftFill height
α0.5% per log cycleStiff clay fill, heavy compaction (Table 6.2-9)
t1, t21 yr, 30 yrPeriod after completion
γ125 pcfFill unit weight
D*125 ksfLow-plasticity clay fill (6 MPa)

Required

  • Creep settlement from 1 to 30 years
  • Self-weight settlement and its share of height

Equations

  1. Eq. 6.2-23: Δs = α H log(t2/t1)
  2. Eq. 6.2-24: S = 0.5 γ H²/D*

Steps

Step 1 · Creep
0.005 × 25 ft × log(30/1) = 0.005 × 25 × 1.477
0.185 ft = 2.2 in.
↓
Step 2 · Self-weight
0.5 × 125 × 25² / 125,000
0.31 ft = 3.75 in. (1.25% of H)
Spot check: Slightly above the 1% Charles reports for clay embankments; most occurs during construction.
↓
Solution
About 2.2 in. of creep under track between years 1 and 30; about 3.75 in. of self-weight settlement, mostly during construction.

Solution

The creep settlement continues after the track is laid and is the part that needs a surfacing allowance. It adds to any consolidation of the foundation (Section 6.2.4.3 calculator).

Build the embankment early or surcharge it if the schedule allows, and plan for one or two surfacing cycles in the first years. Use a granular fill near structures, where its creep rate is an order of magnitude lower.

Open the consolidation settlement calculator →
Now adds fill creep and self-weight settlement to the foundation consolidation result.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Skinner, H. D. (2012). Building on fills. Chapter 58 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 899–910Find source ↗Library entry
  • Nowak, P. A. (2012). Design of new earthworks. Chapter 70 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1047–1066Find source ↗Library entry
6.2.7 Total Settlement and Angular Distortion
Equation 6.2-16 — Total Settlement:

S_total = Si + Sc + Ss

Equation 6.2-17 — Angular Distortion:

α = (S_A − S_B) / L_AB

Where S_A and S_B are predicted settlements at two adjacent structures or reference points, and L_AB is the distance between them (ft). This manual recommends limiting angular distortion at bridge approach transitions to 1/500 for Class 4 track (Table 6.2-1).

Bridge Approach Transition: The most critical angular distortion check in railroad geotechnical practice is at the abutment–embankment interface. A rigid pile-supported abutment settling < 0.1 in. adjacent to an approach fill settling 3.0 in. over 30 ft produces α = 2.9/30 = 0.097 — far exceeding any FRA class limit. AREMA Chapter 8 addresses approach design; use an approach slab or engineered approach fill to limit this transition zone differential.

Supplemental reference

Settlement that consolidation theory does not predict

Repeated and dynamic loads. USACE EM 1110-1-1904 notes that loose sands compact under vibration and that this is a major cause of differential settlement. Cohesionless soils with Dr above about 75% should not settle significantly, although intense dynamic loading can still compact dense sand by 1–2% of the stratum thickness. Dynamic settlement may be insignificant if the combined static and dynamic bearing stress stays below one-half of the allowable bearing capacity. Errors in dynamic-settlement predictions can be 50% or more. For clays under repeated deviator stress (0.1–10 Hz, a typical range for traffic), the manual gives a creep-strain-rate formulation from cyclic triaxial tests but warns it may underestimate settlement because traffic loading is more complex than repeated vertical load.

Collapsible soils. Loess, some alluvial fans and cemented silts lose their bonded structure on wetting. Typical collapsible soils are light-colored, LL < 45, PI < 25, with dry unit weight 65–105 pcf; collapse rarely occurs below 40% porosity. USACE notes that dynamic loading can also break the bonds, “particularly important for roads, airfields, railways.”

Table 12-S2. Wetting that can trigger collapse (EM 1110-1-1904, Table 5-4, condensed)

Type of wettingRailroad exampleResult
Local, shallowBlocked ditch, leaking pipeline crossingSettlement in the upper layer within the wetted area
Intense localIndustry effluent, broken water main, irrigationCan saturate the whole collapsible zone in < 1 year; uneven, damaging settlement
Slow, uniform groundwater riseReservoir or regional water table riseUniform, gradual settlement
Slow increase in water contentReduced evaporation under a paved yard or slabIncomplete, progressive settlement

Collapse potential CP (Jennings and Knight, 1975) is the strain on flooding a consolidometer specimen at 2 tsf: 0–1% negligible, 1–5% moderate trouble, 5–10% trouble, 10–20% severe trouble, > 20% very severe trouble. For design, load the specimen to the anticipated field stress and then inundate it (ASTM D4546, Method B); settlement = [(eo − ec)/(1 + eo)]H. USACE cautions that lab tests can miss soil that later collapses in the field, and the amount depends on how far the wetting front travels — so drainage control is part of the design.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

How much differential settlement the track itself tolerates

Geometry limits put a practical ceiling on differential settlement under track. European intervention limits for the longitudinal (surface) defect on a 33-ft chord range from about 0.35–0.47 in. at 87–99 mph to 0.55–0.83 in. below 37 mph (Chapter 2.1, §2.1.11). Emergency speed restrictions begin at 0.71 in.. Because the chord is short, these are effectively limits on settlement differences over about 33 ft. Embankment, culvert and transition settlement predictions should be checked against that scale, not only against total settlement.

Figure 6.2-13. Definitions: theoretical vs. real track elevation after maintenance (T = 0) and after traffic T, used to define settlement and longitudinal defect. Profillidis Fig. 16.2.
Figure 6.2-13. Definitions: theoretical vs. real track elevation after maintenance (T = 0) and after traffic T, used to define settlement and longitudinal defect. Profillidis Fig. 16.2.

After any surfacing, defects grow quickly up to about 2 million tons of traffic and then slowly, roughly with log T, at a rate (0.079–0.24 in. per decade of traffic) that depends mainly on subgrade quality (Chapter 3.8, §3.8.14).

After Profillidis (2014), §16.3, §16.6–16.7, Fig. 16.2. Full reference under Supplemental References.

Settlement of the track section under traffic

Components. Total settlement is the sum of three parts:

  • Ballast strain × ballast thickness.
  • Subballast strain × subballast thickness.
  • Subgrade settlement.

On new track, more than half comes from the ballast. After each tamping the ballast share grows again, because the loosened top ballast starts over.

Use a power law, not a semilog fit. Settlement after N load cycles fits SN = S1 Nb, with b typically 0.10–0.18. A semilog fit increasingly underpredicts at large N, and so overestimates the time to the next surfacing.

Load cycles per MGT. Cm = 106 ÷ (Aa × Na), where Aa is axle load in tons and Na is axles per load cycle. Use Na = 2 per car for ballast. For example, a 39-ton axle gives about 12,800 cycles per MGT.

Table 12-SW1. Settlement relations measured at FAST (T in MGT; site-specific)
LayerRelationAt 100 MGT
Top 12 in. of ballast (strain)ε = 0.026 T0.21ε ≈ 0.068 → 0.8 in.
Subballast (strain)ε = 0.017 T0.16; about 2.6 × 10−5 per MGT beyond ~150 MGTε ≈ 0.036
Subgrade, top 10 ft of moist fine silty sandS (in.) = 0.039 T0.37 (typical); 0.054 T0.52 (worst section)≈ 0.2 in. (typical)
Subgrade, long term0.001–0.0026 in. per MGT, linear beyond ~50 MGT—

The authors evaluated the 100 MGT column from the relations. Rapid compression occurred through the first ~3 MGT, then continued at a slower rate.

Lift and settlement. After a low lift, the track settles back by about the amount it was lifted within roughly a year, so the change does not last. Lifts above about 1 in., which exceed the ballast D50, leave a residual lift. Allow about 0.16 in. of settlement even at zero lift, from wear and compaction.

After Selig & Waters (1994), chs. 8 and 15. Full reference under Supplemental References.

Supplemental reference · Feng (ed.) (2017)

Settlement of Track Over a Tunnel Crossing TN-01

Sewer, water, transit and utility tunnels are often driven beneath operating track. The empirical method of Peck (1969) describes the settlement trough across a single tunnel in open ground as a normal (Gaussian) curve (Aversa et al., in Feng 2017):

Eq. 6.2-27: w(x) = w0 exp(−x2 / 2i2), where x = horizontal distance from the tunnel centerline.

Eq. 6.2-28: w0 = 0.313 V′ D2 / i, where D = tunnel diameter and V′ = volume loss, the trough volume as a fraction of the excavated area πD2/4 per unit length.

Eq. 6.2-29: i = K z0, where i = distance from the centerline to the inflection point of the trough and z0 = depth to the tunnel axis.

Table 6.2-10. Typical volume loss and trough width parameter (after Mair and Taylor 1997 and Chiriotti et al. 2001, as summarized by Aversa et al., in Feng 2017)
Ground and methodVolume loss V′K
Open face in stiff clay1–2%0.4–0.6 (fine-grained soils)
Sprayed concrete lining (sequential excavation) in clay0.5–1.5%0.4–0.6
TBM in sandunder 0.5%about 0.25–0.45 (granular soils)
TBM in soft clay1–2%0.5 or more
Mixed soil and rock face0.5–0.8%0.3–0.7
Discontinuous or weak rockunder 0.2–0.6%0.5 to above 0.7

Ground over a TBM settles in stages: ahead of the face, over the shield, at the tail as the annular gap closes, and over time as clay consolidates. Good face pressure and prompt tail grouting keep V′ at the low end of the table. A second, parallel tunnel generally causes more volume loss than the first.

Example 6.2-7: Track Settlement Over a TBM Crossing

Problem Statement

A city is driving a 12-ft diameter sewer tunnel with an earth pressure balance TBM under a two-track main line of a Class I railroad located in Ohio. The tunnel crosses square to the tracks with its axis 36 ft below top of rail, in stiff clay. The railroad requires a prediction of the settlement of the track profile and will set monitoring triggers from it. The engineer must predict the trough for the design volume loss and for poor face control.

Track (profile along rail) w₀ = ? TBM (to scale) i = ? z₀ = 36 ft D = 12 ft 62-ft chord (Required: offset) Stiff clay Given D = 12 ft (EPB TBM)z₀ = 36 ft to tunnel axisStiff clay: K = 0.5V′ = 1.0% (design)V′ = 2.0% (poor face control)Tunnel square to track Required(a) i(b) w₀ at V′ = 1%(c) 62-ft midchord offset(d) both at V′ = 2%
Figure 6.2-17. Example 6.2-7: section along the track over a tunnel crossing beneath it, with the Gaussian settlement trough in the track profile (vertical scale exaggerated).

Given

VariableValueDescription
D12 ftExcavated tunnel diameter
z036 ftDepth to tunnel axis below top of rail
K0.5Trough width parameter, stiff clay (Table 6.2-10)
V′1.0% (design); 2.0% (poor face control)Volume loss
Chord62 ftChord used for track profile (surface) measurement, centered over the tunnel

Required

  • (a) Trough width parameter i
  • (b) Maximum settlement w0 at V′ = 1.0%
  • (c) Midchord offset of the track profile on a 62-ft chord centered over the tunnel
  • (d) w0 and the midchord offset at V′ = 2.0%

Equations

  1. Eq. 6.2-29: i = K z0
  2. Eq. 6.2-28: w0 = 0.313 V′ D2 / i
  3. Eq. 6.2-27: w(x) = w0 exp(−x2 / 2i2)
  4. Midchord offset: M = w(0) − w(31 ft) (both chord ends settle equally)

Steps

Step 1 · (a) Trough width
0.5 × 36
i = 18 ft
↓
Step 2 · (b) Maximum settlement at 1.0%
0.313 × 0.010 × 144 / 18 = 0.0250 ft
w0 = 0.30 in.
Spot check: trough volume √(2π) i w0 = 2.507 × 18 × 0.0250 = 1.13 ft3/ft; V′ × πD2/4 = 0.010 × 113.1 = 1.13 ft3/ft ✓.
↓
Step 3 · (c) Settlement at the chord ends
x = 31 ft: exp(−312 / (2 × 182)) = exp(−961/648) = exp(−1.483) = 0.227; w = 0.30 × 0.227
w(31) = 0.07 in.; M = 0.30 − 0.07 = 0.23 in.
↓
Step 4 · (d) At 2.0%
w0 doubles: 2 × 0.30; M = 0.60 × (1 − 0.227)
w0 = 0.60 in.; M = 0.46 in.
↓
Solution
i = 18 ft; about 0.3 in. maximum settlement and a 0.23-in. profile dip at design volume loss, doubling with poor face control.

Solution

(a) i = 18 ft. (b) w0 ≈ 0.30 in. (c) M ≈ 0.23 in. on a 62-ft chord. (d) w0 ≈ 0.60 in. and M ≈ 0.46 in.

Most of the trough (to about 2.5i, or 45 ft, either side) falls within a few rail lengths, so the track sees a short, sharp dip rather than a uniform drop. Both tracks settle about equally because the tunnel is square to them, so cross-level is not affected. On a skewed crossing it would be. Set the railroad’s monitoring triggers from this prediction: for example, review at half the predicted design settlement, and stop the TBM and resurface the track at the design value. Survey the rails before the TBM reaches about 2 to 3 tunnel diameters from the track, then at least daily while the face is within that distance on either side, and afterward until the readings stabilize. Clay continues to consolidate after the TBM passes, so plan follow-up surfacing. Have a tamper and crew on call during the crossing.

For railroad work: Ask the tunnel designer for the predicted trough, the assumed volume loss and the face pressure plan before the railroad agreement is signed. Require monitoring of the rails and of points on the shoulder at the tunnel centerline and at i, 2i and 3i either side, with readings tied to the TBM face position. Slow or stop the drive if the readings approach the triggers. Where track or a bridge foundation lies over a weathered rock or mixed face, volume loss can vary along the drive, so use the upper end of the range for the crossing.

Source: Aversa, Bilotta, Ferrero and Migliazza, “Settlements induced by TBM excavation,” in Feng (ed.) (2017), Ch. 23, summarizing Peck (1969), O’Reilly and New (1982), Mair and Taylor (1997) and Chiriotti et al. (2001). Summarized and paraphrased; units converted. Full reference under S11.

6.2.8 Preloading and Surcharge Design

When predicted settlement S_c exceeds the client's allowable limit, preloading with temporary surcharge fill is the most cost-effective mitigation. The concept: apply a surcharge load greater than the permanent design load, allow consolidation to occur before track placement, then remove the surcharge and install track on a pre-compressed subgrade.

Schematic of the vacuum consolidation process with PVDs, showing the impervious membrane, vacuum pumps, and peripheral trenches
Photo 6.2.8-1. Vacuum Consolidation Process with PVDs, showing the impervious membrane, vacuum gas phase booster and air/water pump, horizontal and vertical vacuum transmission pipes, and peripheral trenches filled with bentonite and polyacrylate. (Figure from Masse et al. 2001)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Sand platform and geotextile being installed at a vacuum preloading site
Photo 6.2.8-2. Sand Platform and Geotextile. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Horizontal drain connections laid in a trench
Photo 6.2.8-3. Horizontal Drain Connection. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Worker welding the vacuum preloading membrane
Photo 6.2.8-4. Installing the Membrane. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Water-filled peripheral sealing trench around a vacuum preloading site
Photo 6.2.8-5. Peripheral Trench. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Row of vacuum pumps at a preloading site
Photo 6.2.8-6. Vacuum Pumps. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Additional fill being placed for membrane protection
Photo 6.2.8-7. Additional Fill Being Placed for Membrane Protection. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
General layout drawing of the sewage treatment plant site improved by vacuum preloading
Photo 6.2.8-8. Sewage Treatment Plant General Layout, west of Pusan City, South Korea. (Figure from Masse et al. 2001.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Settlement versus time chart showing post-vacuum rebound at the Pusan case history site
Photo 6.2.8-9. Post Vacuum Rebound — recorded settlement approaching the 11.8-ft (3.61 m) target through November–December 1996, showing the brief rebound after the vacuum was stopped and the surcharge removed. (Figure from the Pusan, South Korea case history.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Equation 6.2-18 — Required Surcharge Pressure:

σ'_v0 + Δσ_p + Δσ_s = σ'_v0 × 10^[S_target(1 + e₀)/(C_c H)], where S_target = primary settlement plus expected secondary compression under the permanent load, and Δσ_s is the required surcharge (NC clay)

A simplified approach: select q_surcharge such that primary consolidation under q_surcharge equals the sum of primary consolidation + secondary compression expected under q_permanent over the service life. Make this calculation for bridge approach fills where predicted settlement exceeds about 2 in.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Cccompression indexLab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
Equation 6.2-19 — Time for Surcharge to Achieve U = 90%:

t_surcharge = 0.848 · H_dr² / cv

If t_surcharge is prohibitively long (> 6–12 months on a construction schedule), prefabricated vertical drains (PVDs) are combined with the surcharge to accelerate drainage — addressed in Chapter 7.2 (Ground Improvement).

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
cvcoefficient of consolidationLab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
Supplemental reference

Field record: preloading, drains and excavation over peat

Lea and Brawner’s case histories from the Vancouver area test the assumptions behind Eq. 6.2-18 and 6.2-19:

  • Surcharge works. At Lougheed Highway and Boundary Road (1958), about 1,200 ft of road over up to 14 ft of peat was brought to grade plus a 5-ft surcharge, carried traffic on a temporary surface for three months, then was paved. Settlement plates and piezometers controlled the rate of construction. No differential settlement or pavement failure appeared in the first four years.
  • Vertical drains in peat may not perform as calculated. At Maillardville (1954), 18-in. sand drains at 15-ft triangular spacing were calculated to raise the settlement rate at least eightfold; measured primary settlement was only about 15% faster. Check drain performance in peat with a test section before relying on it in the schedule.
  • Rigid structures in a settling fill create bumps. On the same project, culverts on piles did not settle with the grade, and severe bumps formed at every culvert within a few months. The same applies to pile-supported culverts and pipe crossings under a new railroad embankment on soft ground.
  • Excavate-and-replace is only as good as the cleanup. On the Deas Tunnel Throughway, peat 6–11 ft deep was excavated and replaced with dredged sand. Within a year pockets of peat and organic silt left in place caused up to 3 in. of differential settlement over 50 ft.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board

Supplemental reference

Lightweight fill: reducing the load instead of waiting for it

When surcharge time is not available, or added fill would cause a stability failure, the alternative is to reduce Δσ itself. Three generations of lightweight fill appear in the library:

Table 12-S3. Lightweight fill options

MaterialKey propertiesDesign notes
Sawdust (historic; Trans-Canada Highway, Burnaby)3–12 ft thick; compressed to 80–90% of placed thickness under about ½ tsf preload; lab φ = 50°Rots and can spontaneously combust above the water table, so the top must end up below groundwater after settlement. Settlement had to be predicted accurately to place it at the right grade.
Expanded shale, clay or slate (ESCS) lightweight aggregateKiln-expanded at 1,900–2,200°F; relative density 1.3–1.6 vs. 2.6–3.0 for normal aggregate (about half the mass per volume); AASHTO M 195 gradationsOpen-graded; still needs compaction (lifts ≤ 12 in. loose with vibratory roller). Density control by a one-point Proctor (modified ASTM D698) plus a method spec.
EPS geofoam (ASTM D6817)EPS 15 / 19 / 22 / 29: minimum density 0.90 / 1.15 / 1.35 / 1.80 pcf; compressive resistance at 10% strain 10.2 / 16.0 / 19.6 / 29.0 psi“Zero net load”: excavate native soil equal in weight to the geofoam plus everything placed on it. It can also replace the active wedge behind an abutment.

Case: US 17 / SC 707, Myrtle Beach, SC. At the nearby Fantasy Harbour project, embankments 10–42 ft high had settled 9 to 67 in. For the US 17 / SC 707 interchange, bridge approach fills over 30–60 ft of soft to firm clay and loose, liquefiable sands were estimated to settle 78 in. at the abutment if built with normal-weight fill (120 pcf). The design combined LWA borrow to cut the magnitude, PVDs with granular surcharge to speed it, and deep soil mixing for seismic slope stability and abutment performance.

Railroad cautions (engineering judgment, not from the sources): lightweight fills must be covered by enough ballast, subballast and soil to spread axle loads and resist buoyancy at flood stage. Geofoam must be protected from petroleum spills (hydrocarbon-resistant membrane) near fueling or derailment-prone areas. Confirm dynamic stiffness under E-80 loading before using any lightweight fill directly under track.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board · Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co. · Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)

Construction sequence using lightweight sawdust fill, sand drains and surcharge over peat and soft clay (Trans-Canada Highway, Burnaby).
Supplemental Figure 12-S2. Construction sequence using lightweight sawdust fill, sand drains and surcharge over peat and soft clay (Trans-Canada Highway, Burnaby). Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board.
Project management · Levy (2010)

Schedule Float, Change Orders and Surcharge Hold Times

Levy (2010) explains, from the owner’s side, how changes interact with the contractor’s critical path method (CPM) schedule. The critical path moves as the job proceeds, and a delay to one critical task can cascade into later tasks and push out the completion date. When a change may affect time, owners face the question of whether the delay is real. Levy advises settling time when the change is priced, not later, because once unrelated contractor delays accumulate it becomes hard to separate them from the change. Extended time matters because general conditions costs (supervision, trailers, utilities, rentals) continue, and he cites $20,000 to $40,000 per month as a typical range.

Where time cannot be agreed, he suggests two approaches: issue the change with a statement that the work proceeds while the owner reserves the right to challenge any time extension, or sign the cost proposal provisionally, reserving the right to challenge both cost and time. Change-order forms often require checking whether the change increases, decreases or does not affect the contract end date, and owners should read that box before signing.

On float, Levy notes that schedules carry a cushion of extra days for weather, late equipment or short crews. Unless the contract says otherwise, that float belongs to the contractor. If the owner wants float for its own contingencies, such as late delivery of owner-furnished items, it must reserve it in the contract; otherwise an owner-caused delay that consumes the contractor’s float can become a claim.

For railroad work: Preload and surcharge programs for embankment widening or approach fills put a waiting period directly on the critical path, and its true length depends on measured consolidation rather than on the design estimate. Specify in the contract who owns float in the hold period, how the hold may be extended or shortened on the basis of settlement plate and piezometer data, and how extended time will be paid. Write the decision rule (for example, release when the monitored settlement rate falls below a stated value) into the special provisions so that a longer hold is a defined outcome rather than a dispute.

Settlement Plate Installation
Settlement Plate Installation

Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 215–216. Summarized and paraphrased. Full reference under Supplemental References.

6.2.8.1 Precompression: Surcharging to Remove Settlement Before Track Is Built

Where a new track, siding or yard sits on soft clay, the cheapest way to avoid years of resurfacing is often to make the clay settle before the track goes down. A surcharge, extra fill above the final grade, is placed over the permanent fill. It speeds consolidation, and it is removed once the settlement the permanent load would eventually cause has occurred. Das's Advanced Soil Mechanics (Section 11.7, after Johnson) gives the design. To be safe, the degree of consolidation is taken at mid-depth of the drainage path, not as an average. If the surcharge comes off when only the average has been reached, the clay near mid-depth keeps settling while the clay near the drainage boundaries swells. Where wick drains are used (Chapter 7.2), Das replaces the mid-depth value with the average degree of consolidation for combined drainage.

6.2.8.1.1 Method

Equation 6.2-22. Degree of consolidation needed under permanent load plus surcharge (Das Eq. 11.25)

U(f+s) = log(1 + σf/σ′0) / log{1 + (σf/σ′0)[1 + σs/σf]}

σs/σf = [(1 + σf/σ′0)1/U − 1]/(σf/σ′0) − 1;   t = TvH2/cv

Das reads U from a chart; the calculator computes it from the Terzaghi series at mid-depth and solves Equation 6.2-22 directly for the surcharge ratio. For Das's Example 11.7 the calculator gives Tv = 0.497, U = 62.7% and σs/σf = 1.11. That example is 15 ft (4.5 m) of normally consolidated clay under 5 ft (1.5 m) of sand, a 1,210 psf (58 kPa) permanent load and six months available. Das, reading his charts, gets Tv = 0.497, U ≈ 0.62 and σs/σf = 1.17. The 5% difference in surcharge comes from reading the charts.

Table 6.2-8. Das Example 11.7 in English units: published and calculated
QuantityDasCalculator
σ′0 at clay mid-depth47.17 kPa (985 psf)985 psf
Tv for 6 months0.4970.497
U(f+s) at mid-depth≈ 0.62 (chart)0.627
σs/σf1.17 (chart)1.11
Surcharge σs67.86 kPa (1,417 psf)1,345 psf

6.2.8.1.2 Worked example

Applied to a siding on Das's profile, the permanent load of 1,211 psf would cause about 9.2 in. of primary settlement. To take all of it out in six months without drains takes a surcharge of 1,345 psf, about 11.2 ft of extra fill. The surcharge comes off when the settlement plates read 9.2 in., not on a calendar date. If that much fill would make the embankment unstable, combine a smaller surcharge with wick drains, or build in stages (Chapter 2.5).

The surcharge is usually the most critical stability case, because it is the heaviest load the soft clay will ever see. Check it with the Bishop calculator (Chapter 6.3), and monitor settlement plates and piezometers so the surcharge is removed on measured settlement.

Open the precompression surcharge calculator →
Effective stress at clay mid-depth, degree of consolidation in the time available (mid-depth or average), the surcharge ratio and fill height to remove primary settlement, and the settlement to wait for before removal.

6.2.8.1.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • B.M. Das, Advanced Soil Mechanics, 4th edition: Section 11.7 precompression (Eqs. 11.21 to 11.26, Example 11.7) and Section 11.8 precompression with sand drainsFind source ↗
  • R.F. Craig, Craig's Soil Mechanics, 7th edition: consolidation theory and the degree of consolidation with depthFind source ↗Library entry
  • M. Budhu, Soil Mechanics and Foundations, 3rd edition: one-dimensional consolidationFind source ↗
6.2.9 Representative Data Table
Table 6.2-5 — Sample Consolidation Test Results — Class I railroad Embankment Project located in coastal Georgia
BoringSampleDepth (ft)USCSLL (%)PIe₀C_cC_sC_αc_v (ft²/day)OCRσ'_p (psf)
B-01S-38–10CH72451.820.560.070.0220.00321.0820
B-01S-514–16CH68411.710.520.0650.0210.00511.11,080
B-02S-38–10OH105632.450.880.110.0620.00181.0750
B-02S-514–16CH74471.880.590.0740.0240.00281.01,040
B-03S-411–13CL48251.350.310.0390.0120.01201.41,750
B-03S-618–20CH69431.770.530.0660.0210.00441.01,500

Design values selected: C_c = 0.56 (average CH); C_s = 0.07; C_α = 0.022; c_v = 0.004 ft²/day; e₀ = 1.82; one-way drainage to the surface (rock below the clay); H_dr = clay thickness.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
6.2.10 Reference Photographs
Consolidation Test
Consolidation Test
Immediate vs. Consolidation Settlement
Immediate vs. Consolidation Settlement
Why Soil Consolidation Happens
Why Soil Consolidation Happens
Settlement Plate Installation
Settlement Plate Installation
6.2.11 Worked Calculation Examples
The three examples cover the three settlement cases a railroad engineer meets most often: soft normally consolidated clay under new fill, the time a preload must stay on, and a stiff overconsolidated clay under a slab. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 6.2-1: Embankment Settlement Over Soft Clay

A new siding on a Class I railroad located in coastal Georgia (Brunswick) puts 10 ft of fill on 14 ft of soft, normally consolidated fat clay over rock. The example estimates how much the clay will compress, how long it will take with drainage only upward, and how much secondary compression follows, and compares the post-construction settlement with the limit for the track.

10 ftFill 10 ft, γ = 120 pcf, B = 40 ftSp, Ss, t90 = ?CH, 14 ft: Cc = 0.56, e0 = 1.82, cv = 0.004 ft²/dRock (impervious)GWT ▽GivenFill 10 ft; γ = 120 pcf; B = 40 ftClay 14 ft CH; γ = 110 pcfCc 0.56; e0 1.82; Cα 0.022cv 0.004 ft²/day; Hdr 14 ftGWT 2 ft below original groundWick drains: primary done at 180 dLimit 1.0 in. post-construction; 50 yrRequiredPrimary and secondary settlementTime to 90% consolidationMeets the 1.0-in. limit?Black = given; red = required
Given and required for Example 6.2-1.

Given

VariableValueDescription
FillH = 10 ft; γ = 120 pcf; B = 40 ft at base
Clay14 ft CH; Cc = 0.56; e0 = 1.82; cv = 0.004 ft²/day; Cα = 0.022; γ = 110 pcfOn rock: one-way drainage, Hdr = 14 ft
zw2 ft below original ground
Limit1.0 in. post-construction (assumed, Class 4)
Wick drainsAssumed to finish primary at t1 = 180 days
Service50 years

Required

  • Primary and secondary settlement
  • Time to 90% consolidation
  • Compliance with the limit

Equations

  1. Eq. 1: Δσ = q B/(B + z) — 2:1 spread to mid-clay
  2. Eq. 6.2-5: Sc = [Cc/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — normally consolidated
  3. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848
  4. Eq. 3: Ss = [Cα/(1 + ep)] H log(t2/t1) — secondary compression
  5. Eq. 4: ep = e0 − Cc log(σ′f/σ′v0) — void ratio at end of primary

Steps

Step 1 · σ′v0 at mid-clay (7 ft)
2(110) + 5(110 − 62.4) = 220 + 238
458 psf
↓
Step 2 · Δσ (Eq. 1)
1,200 × 40/(40 + 7)
1,021 psf
↓
Step 3 · Sc (Eq. 6.2-5)
(0.56/2.82) × 14 × log(1,479/458) = 0.1986 × 14 × 0.509
Sc = 1.42 ft = 17.0 in.
↓
Step 4 · t90, no drains (Eq. 2)
0.848 × 14² / 0.004
41,500 days = 114 years
↓
Step 5 · Ss, 180 days to 50 years (Eq. 3, 4)
ep = 1.82 − 0.56 × 0.509 = 1.535; (0.022/2.535) × 14 × log(18,250/180) = 0.00868 × 14 × 2.006
Ss = 0.244 ft = 2.9 in.
↓
Step 6 · Post-construction settlement
10% of primary + secondary = 1.7 + 2.9
4.6 in. >> 1.0 in.
↓
Solution
Sc = 17 in.; 114 years undrained; 4.6 in. after construction: ground improvement required.

Solution

Primary settlement is about 17 in., which would take over a century to finish with drainage to one face. Even with wick drains finishing primary in 180 days, about 4.6 in. would remain after construction against a 1.0-in. limit.

Wick drains change the time, not the amount. The options are a surcharge preload that drives primary consolidation past the final load before track is laid, accepting the secondary settlement as maintenance, or column support (deep soil mixing or rigid inclusions) that bypasses the clay (Chapter 7.2). The 2:1 stress at mid-clay is used here as a conservative centerline value; a full analysis divides the clay into sublayers.

Example 6.2-2: Preload Duration for a Bridge Approach Fill

A bridge approach fill on a Class I railroad located in southern Manitoba sits on soft, normally consolidated silty clay drained by sand above and below. The question is how long a preload must stay in place for the remaining settlement to be within the allowable after track is laid.

18 ftFill 18 ftSc, U, t = ?CL-ML, 20 ft: Cc = 0.35, e0 = 1.25, cv = 0.08 ft²/dSand (drains)GWT ▽drain option (dashed)GivenFill 18 ft; Δσ = 1,440 psf mid-clayClay 20 ft; γsat = 115 pcfTwo-way drainage, Hdr = 10 ftGWT at original groundLimit 1.5 in. residualDrains: 5-ft triangular, de = 5.25 ftRequiredPrimary settlementU and time for 1.5 in. residualEffect of wick drainsBlack = given; red = required
Given and required for Example 6.2-2.

Given

VariableValueDescription
Fill18 ft; Δσ = 1,440 psf at mid-clay
Clay20 ft CL-ML; Cc = 0.35; e0 = 1.25; cv = 0.08 ft²/day; γsat = 115 pcfTwo-way drainage, Hdr = 10 ft
zwAt the original ground surface
Limit1.5 in. residual (assumed)
Drains option5-ft triangular spacing; de = 5.25 ft

Required

  • Primary settlement
  • Degree of consolidation and time needed for 1.5 in. residual
  • Effect of wick drains

Equations

  1. Eq. 6.2-5: Sc = [Cc/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — normally consolidated
  2. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848

Steps

Step 1 · σ′v0 at mid-clay
10 × (115 − 62.4)
526 psf
↓
Step 2 · Sc (Eq. 6.2-5)
(0.35/2.25) × 20 × log(1,966/526) = 0.1556 × 20 × 0.573
Sc = 1.78 ft = 21.4 in.
↓
Step 3 · U needed
(1 − U) × 21.4 ≤ 1.5
U ≥ 93%
↓
Step 4 · Tv and t (Eq. 2)
−0.933 log(0.070) − 0.085 = 0.993; t = 0.993 × 10²/0.08
t = 1,241 days = 3.4 years
Spot check: At 90%: t = 0.848 × 1,250 = 1,060 days, leaving 2.1 in.; 93% needs a further six months.
↓
Step 5 · With wick drains (rough)
Drainage path about de/2 = 2.6 ft; 1,241 × (2.6/10)²
About 84 days
↓
Solution
U ≥ 93%: 3.4 years without drains, about 3 months with them.

Solution

Primary settlement is about 21 in. The preload must reach 93% consolidation, which takes about 3.4 years with the natural drainage, or roughly 3 months with wick drains at 5-ft spacing.

The drain estimate is a rough analogy that ignores smear and well resistance; design the drains with Barron and Hansbo radial theory (Chapter 7.2). Tell the railroad’s project engineer the timeline early, and confirm it in the field with settlement plates at about 500-ft intervals read monthly: the plates, not the calculation, decide when the preload comes off.

Example 6.2-3: Settlement of an Overconsolidated Clay Under a Crane Slab

A crane rail pavement slab for an intermodal expansion on a Class I railroad located in Kansas City sits on stiff, overconsolidated fat clay. Because the new stress stays below the preconsolidation stress, only the stiff recompression branch is used, and the secondary compression ratio must match that branch too.

Crane slab, net Δσ = 800 psfcrane railsOC clay CH, 12 ft: Cc 0.42, Cs 0.05, e0 0.88σ′v0 = 1,850 psf; σ′p = 4,200 psfDrainage both faces, Hdr = 6 ftSp + 50-yr Ss = ? Improvement needed?GivenΔσ = 800 psfClay 12 ft; Cc 0.42; Cs 0.05; e0 0.88σ′v0 1,850; σ′p 4,200 psf (OCR 2.27)cv 1.0 ft²/d; Hdr 6 ftCα/Cr = 0.04Limit 0.125 in. per 20 ft (rail)RequiredPrimary and 50-yr secondaryIs ground improvement needed?Black = given; red = required
Given and required for Example 6.2-3.

Given

VariableValueDescription
Δσ800 psfNet load from slab and crane
Clay12 ft CH; Cc = 0.42; Cs = 0.05; e0 = 0.88
σ′v0, σ′p1,850 and 4,200 psfOCR = 2.27
cv1.0 ft²/day (assumed); Hdr = 6 ft
Cα/Cr0.04Mesri, recompression range
Limit0.125 in. per 20 ft differential (assumed)Crane rail

Required

  • Primary and 50-year secondary settlement
  • Whether ground improvement is needed

Equations

  1. Eq. 6.2-6: Sc = [Cs/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — overconsolidated, σ′f < σ′p
  2. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848
  3. Eq. 3: Ss = [Cα/(1 + ep)] H log(t2/t1) — secondary compression

Steps

Step 1 · Which case?
1,850 + 800 = 2,650 < 4,200
Recompression only (Eq. 6.2-6)
↓
Step 2 · Sc
(0.05/1.88) × 12 × log 1.432 = 0.0266 × 12 × 0.156
0.050 ft = 0.60 in.
↓
Step 3 · End of primary (Eq. 2)
0.848 × 36 / 1.0
t1 ≈ 31 days
↓
Step 4 · Ss (Eq. 3)
Cα = 0.04 × 0.05 = 0.002; ep = 0.872; (0.002/1.872) × 12 × log(18,250/31) = 0.00107 × 12 × 2.770
0.036 ft = 0.43 in.
Spot check: Using Cα = 0.04 Cc = 0.017 would give 3.6 in., an eightfold overestimate.
↓
Solution
0.60 in. primary in a month; 0.43 in. over 50 years: no improvement needed.

Solution

Primary settlement 0.60 in., essentially complete within about a month; secondary about 0.4 in. over 50 years; about 1.0 in. in all.

The primary settlement can be taken out before the crane rail is set. The long-term part is small and nearly uniform in a uniform layer, so the differential depends on lateral variation in the clay between borings; check it against the 0.125 in. per 20 ft limit and provide rail adjustment in the crane rail design. Ground improvement is not needed for settlement alone.

6.2.12 Practical Recommendations
  1. Always compute settlement before bearing capacity governs your design advice: For wide embankments over soft clay, settlement is virtually always the controlling limit state. A footing may pass bearing capacity (FS = 3.0) while the predicted settlement is 12 in. — a number that instantly triggers ground improvement requirements regardless of the bearing capacity outcome.
  2. Use the sublayer method for any clay layer > 5 ft: Treating a 20-ft clay layer as a single layer with midpoint stress overpredicts settlement for lightly loaded footings and underpredicts for heavily loaded ones. Divide clay layers thicker than about 10 ft into sublayers.
  3. Distinguish OCR carefully — it changes the settlement by a factor of C_c/C_s (5–10×): A misidentified OCR (treating lightly overconsolidated clay as NC) can produce a tenfold overestimate of settlement. Casagrande construction on every consolidation test, confirmed by the stress history from geologic context, is mandatory. Determine OCR from both the consolidation test and the CPTu (Chapter 5.1) as a cross-check.
  4. Time-rate analysis must accompany every settlement estimate: The magnitude of settlement is useless to a railroad scheduler without knowing when it will occur. A 3-in. settlement in 2 weeks (from granular fill self-weight) is handled differently from 3 in. over 20 years (secondary creep). Submit time-settlement curves with every geotechnical report for bridge approach fills.
  5. Report residual settlement explicitly: The railroad owner needs to know what settlement will remain after construction and how much will develop over the first 5–10 years of service. Give residual settlement predictions at years 1, 5, 10 and 25 as part of the geotechnical deliverable.
  6. Address approach-slab transition on every bridge project: The abutment-embankment angular distortion is a common cause of geometry exceptions on Class 4–5 mainlines. AREMA Chapter 8 approach slab design must be cross-referenced in the geotechnical report whenever the predicted embankment settlement exceeds 0.5 in. at the abutment interface.
  7. Flag secondary compression early for organic soils: In Gulf Coast territory (Pt soils common) and Manitoba peatlands, secondary compression often exceeds primary consolidation. C_α/C_c ratios of 0.05–0.08 for organic soils require explicit long-term maintenance planning; recommend periodic light tamping cycles and document the expected frequency in the geotechnical report.
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-17 Preconsolidation stress / OCR from CPT σ'ₚ, OCRUse: Intact, inorganic clays. Limits: k is higher in aged/heavily OC clays and lower in fissured clays; calibrate with oedometer tests.
  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
6.2.13 Settlement Analysis Checklist

Checklist · Part VI · Geotechnical Analysis

Settlement Analysis Checklist

Pre-Analysis0 of 6
Settlement Computation0 of 7
Time-Rate Analysis0 of 4
Deliverables0 of 6
Ticks are saved in this browser.
Plain text version

Pre-Analysis

  • [ ] Collect consolidation test results: C_c, C_s, e₀, c_v, C_α, σ'_p for all clay layers (Chapter 5.2)
  • [ ] Determine OCR from Casagrande construction; cross-check with CPTu K_D if available
  • [ ] Identify drainage boundaries (sand/gravel layers above/below clay; bedrock)
  • [ ] Confirm groundwater table: FEWL and SWL from Chapter 2.8
  • [ ] Compute effective stress profile with correct γ' = γ_sat − γ_w (γ_w = 62.4 pcf)
  • [ ] Confirm design load: DL, LL×DLF per the owner railroad's standard (Chapter 6.1)

Settlement Computation

  • [ ] Compute Δσ at midpoint of each sublayer (Boussinesq or 2:1)
  • [ ] Classify each layer as NC, OC with σ'_v0+Δσ < σ'_p, or OC crossing σ'_p
  • [ ] Apply correct equation (5.2-5, 5.2-6, or 5.2-7) for each sublayer
  • [ ] Sum sublayer settlements for S_c,total
  • [ ] Compute S_i (immediate) for granular soils or highly loaded stiff clays
  • [ ] Compute S_s (secondary) for OCR < 2 clays and all organic soils
  • [ ] Sum S_total; compare to FRA tolerance by track class (Table 6.2-1)

Time-Rate Analysis

  • [ ] Confirm H_dr (one-way or two-way); document drainage layer identification
  • [ ] Compute t_90 and t_95 using Eq. 6.2-11 and 6.2-13
  • [ ] If t_90 > project schedule, evaluate PVDs (Chapter 7.2) or surcharge preloading
  • [ ] Generate time-settlement curve; provide residual at Years 1, 5, 10, 25

Deliverables

  • [ ] Settlement calculation memorandum with all sublayer computations shown
  • [ ] Time-settlement curve (labeled with construction milestones and track placement date)
  • [ ] Residual settlement table (Years 1, 5, 10, 25 post-construction)
  • [ ] Angular distortion check at bridge approach transitions
  • [ ] Instrumentation plan if monitoring is required
  • [ ] Ground improvement recommendation (Chapter 7.2) if S_total exceeds tolerance
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-17 Preconsolidation stress / OCR from CPT σ'ₚ, OCRUse: Intact, inorganic clays. Limits: k is higher in aged/heavily OC clays and lower in fissured clays; calibrate with oedometer tests.
  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
6.2.14 Practice Questions and Full Answers
Each question is worked in the same five parts as the examples. Question 6.2-4 is a reasoning question.
Question 6.2-1: Settlement of Soft Clay Under a Footing

Problem Statement

A spread footing for a new railroad maintenance building at a Class I yard will add stress to a 10-ft layer of normally consolidated soft clay with the properties shown. The engineer must estimate the consolidation settlement and compare it with the settlement the adjacent Class 4 track can tolerate.

Maintenance building footingSc = ?NC soft clay, 10 ft: Cc = 0.45, e0 = 1.60Sand (drains)At mid-clay: σ′v0 = 500 psf, Δσ = 1,200 psfGivenH = 10 ft NC clayCc = 0.45; e0 = 1.60σ′v0 = 500 psf (mid-clay)Δσ = 1,200 psf (mid-clay)RequiredConsolidation settlement Sc Compare with Class 4 track toleranceBlack = given; red = required
Given and required for Question 6.2-1.

Given

VariableValueDescription
H10 ftClay layer
Cc, e00.45; 1.60
σ′v0500 psfMid-clay
Δσ1,200 psfMid-clay

Required

  • Sc

Equations

  1. Eq. 6.2-5: Sc = [Cc/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — normally consolidated

Steps

Step 1 · Sc
(0.45/2.60) × 10 × log(1,700/500) = 0.1731 × 10 × 0.5315
0.920 ft = 11.0 in.
↓
Solution
Sc = 11.0 in.

Solution

Sc ≈ 11 in.

That is eleven times the 1.0-in. Class 4 limit of Table 6.2-1; ground improvement or a deep foundation is required.

Question 6.2-2: Time to 90% With and Without Wick Drains

Problem Statement

A new embankment for a railroad yard expansion will sit on 15 ft of normally consolidated silty clay drained at top and bottom. The railroad wants to know how long it must wait before laying track. The engineer must compute the time to 90% consolidation without drains and with wick drains at the spacing shown.

Yard embankmentt90 with / without drains = ?NC silty clay, 15 ft: cv = 0.10 ft²/dSand (drains)Given15 ft clay, two-way: Hdr = 7.5 ftcv = 0.10 ft²/dayDrains 4.0-ft triangular; de = 4.2 ftch ≈ 2cv = 0.20 ft²/dayRequiredt90 without drainst90 with drainsBlack = given; red = required
Given and required for Question 6.2-2.

Given

VariableValueDescription
H15 ft, two-way drainageHdr = 7.5 ft
cv0.10 ft²/day
Drains4.0-ft triangular; de = 4.2 ftch ≈ 2cv = 0.20 ft²/day

Required

  • t90 without and with drains

Equations

  1. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848

Steps

Step 1 · Without drains
0.848 × 7.5² / 0.10
477 days = 1.3 years
↓
Step 2 · With drains (rough)
Path ≈ de/2 = 2.1 ft; 0.848 × 2.1² / 0.20
About 19 days
↓
Solution
477 days without drains; about 19 days with them.

Solution

About 477 days (1.3 years) without drains and about 19 days with them, roughly 25 times faster.

The drain estimate ignores smear and well resistance, which slow radial drainage; design with Barron and Hansbo (Chapter 7.2). The comparison shows why drains are specified whenever track must go on within 60 to 90 days of fill completion.

Question 6.2-3: Overconsolidated Clay Crossing the Preconsolidation Stress

Problem Statement

An embankment for a new railroad grade separation will load an overconsolidated clay past its preconsolidation stress. Laboratory tests gave the compression and swelling indices, void ratio and stresses shown. The engineer must compute the consolidation settlement and identify which settlement equation applies.

Grade separation embankmentSc = ? Which equation?OC clay, 8 ft: Cc 0.38, Cs 0.048, e0 0.95Sand (drains)σ′v0 = 1,200 psf; σ′p = 2,800 psf; Δσ = 2,000 psfGivenH = 8 ftCc 0.38; Cs 0.048; e0 0.95σ′v0 1,200; σ′p 2,800 psfΔσ = 2,000 psfRequiredSc Which settlement equation appliesBlack = given; red = required
Given and required for Question 6.2-3.

Given

VariableValueDescription
H8 ft
Cc, Cs, e00.38; 0.048; 0.95
σ′v0, σ′p1,200 and 2,800 psf
Δσ2,000 psf

Required

  • Sc, and which equation applies

Equations

  1. Eq. 6.2-7: Sc = [Cs/(1 + e0)] H log(σ′p/σ′v0) + [Cc/(1 + e0)] H log(σ′f/σ′p) — OC crossing σ′p

Steps

Step 1 · Which case?
1,200 + 2,000 = 3,200 > 2,800
Crossing σ′p: Eq. 6.2-7
↓
Step 2 · Recompression part
(0.048/1.95) × 8 × log 2.333
0.0724 ft
↓
Step 3 · Virgin part
(0.38/1.95) × 8 × log 1.143
0.0904 ft
↓
Step 4 · Total
0.163 ft = 1.95 in.
Spot check: Treated as NC: (0.38/1.95) × 8 × log 2.667 = 0.664 ft = 8.0 in., a 4.1× overestimate.
↓
Solution
Sc = 1.95 in. (Eq. 6.2-7).

Solution

Sc ≈ 1.95 in., from Eq. 6.2-7.

Missing the overconsolidation would have overestimated the settlement fourfold and could have triggered ground improvement that was not needed.

Question 6.2-4: Why Angular Distortion Governs at Bridge Approaches

Problem Statement

A pile-supported railroad bridge abutment does not settle, but the approach fill behind it has settled 1 to 3 in. within 30 ft and the track shows a dip at the bridge end. The engineer must explain why angular distortion, rather than total settlement, governs the approach and state the limit used for Class 4 track.

Abutment on pilesApproach fillas built1 to 3 in. within 30 ft30 ftWhy angular distortion governs? Class 4 limit = ?GivenAbutment on piles: settlement ≈ 0Approach fill: 1 to 3 in. in 30 ftTrack dip at the bridge endTable 6.2-1: Class 4 limitRequiredWhy angular distortion, not total settlement, is criticalThe Class 4 limitBlack = given; red = required
Given and required for Question 6.2-4.

Given

VariableValueDescription
AbutmentPile supported; settlement ≈ 0
Approach fill1 to 3 in. within 30 ft
Limit1/500 for Class 4 trackTable 6.2-1

Required

  • Why angular distortion, not total settlement, is the critical measure
  • The Class 4 limit

Equations

  1. Eq. 1: α = ΔS / L — angular distortion

Steps

Step 1 · What does the rail feel?
The change in elevation along the track: a ramp at the abutment, not the absolute settlement.
↓
Step 2 · What does FRA measure?
Surface deviation over a 62-ft chord, which a sharp ramp exceeds.
↓
Step 3 · Limit (Eq. 1)
1/500 × 25 ft = 0.05 ft; 1/500 × 62 ft = 0.124 ft
0.6 in. over 25 ft; 1.5 in. over 62 ft
↓
Solution
Distortion governs; limit 1/500 for Class 4.

Solution

Because the rail responds to the rate of elevation change, not the total. This manual limits approach distortion to 1/500 for Class 4 track, about 0.6 in. over 25 ft.

Approach slabs, sleeper slabs and geosynthetic-reinforced approach zones spread the change over a longer distance; AREMA Chapter 8 approach slab design should be cross-referenced whenever the predicted embankment settlement at the abutment exceeds 0.5 in.

Question 6.2-5: Degree of Consolidation for a Passenger Corridor Embankment

Problem Statement

A passenger corridor is adding a track on a new embankment over soft clay, and the railroad (assumed) allows only 0.375 in. of primary settlement after the track is laid. The predicted primary settlement is 8.0 in. The engineer must find the degree of consolidation required before track laying and the time to reach it with and without wick drains.

New passenger track embankmentU required = ? t = ?Soft clay: cv = 0.006 ft²/d, Hdr = 12 ftRock (impervious)GivenSc = 8.0 in. primarySs = 1.5 in. in 50 yr (maintenance)Limit 0.375 in. residual primarycv 0.006 ft²/day; Hdr 12 ftDrains: path 1.5 ft; ch ≈ 0.012 ft²/dayRequiredDegree of consolidation UTime without and with drainsBlack = given; red = required
Given and required for Question 6.2-5.

Given

VariableValueDescription
Sc8.0 in.Primary
Ss1.5 in. over 50 yearsHandled by maintenance
Limit0.375 in. residual primary (assumed)
cv, Hdr0.006 ft²/day; 12 ft
DrainsEffective path 1.5 ft; ch ≈ 0.012 ft²/day

Required

  • U required
  • Time without and with drains

Equations

  1. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848

Steps

Step 1 · U required
(1 − U) × 8.0 ≤ 0.375
U ≥ 95.3%
↓
Step 2 · Tv
−0.933 log(0.047) − 0.085
1.154
↓
Step 3 · Without drains
1.154 × 144 / 0.006
27,700 days = 76 years
↓
Step 4 · With drains
1.154 × 1.5² / 0.012
About 216 days, 7 months
↓
Solution
U ≥ 95.3%: 76 years undrained, about 7 months with drains.

Solution

U must reach 95.3%. That takes about 76 years with natural drainage, which is infeasible, and about 7 months with wick drains.

High-speed track leaves almost no room for residual settlement, so drains, a surcharge to speed the last few percent, and settlement plates to prove it are normally all required.

Question 6.2-6: How Far Short of the Sand Can the Drains Stop?

Problem Statement

A Class I railroad located in Mississippi is building a siding extension on an embankment over 50 ft of soft clay underlain by clean sand, which drains the clay from below. Vertical drains on a 4.5-ft triangular pattern are specified over a 2,000-ft by 100-ft area. The contractor asks whether the drains really need to reach the sand. The engineer must find the optimum unimproved thickness at the bottom of the clay and the drain length it would save.

Embankment and surcharge Soft clay Sand (free-draining) PVDs, triangular 4.5 ft Required: Hc 50 ft Givendw = 0.196 ftds/dw = 4kh/ks = 3ch/cv = 2Area 2,000 × 100 ft Requiredμ, Hc, drainlength saved
Figure 6.2-16. Question 6.2-6: drains in clay over sand.

Given

VariableValueDescription
H50 ftClay thickness, drained top and bottom
s4.5 ft triangularDrain spacing
dw0.196 ftEquivalent drain diameter
ds/dw, kh/ks4 and 3Smear zone size and permeability ratio
ch/cv2
Area2,000 ft × 100 ftTreated area

Required

  • (a) Drain resistance factor μ
  • (b) Optimum unimproved thickness Hc
  • (c) Total drain length saved

Equations

  1. Eq. 1: De = 1.05 s (triangular)
  2. Eq. 2: μ = ln(n/sr) + (kh/ks) ln sr − 0.75, n = De/dw, sr = ds/dw (Hansbo, Chapter 7.2, Section 7.2.3)
  3. Eq. 6.2-25: Hc = 1 / [64/H² + 2.5 ch/(μ De² cv)]0.5
  4. Eq. 3: number of drains = area / (0.866 s²)

Steps

Step 1 · De and n
1.05 × 4.5; 4.725/0.196
De = 4.73 ft; n = 24.1
↓
Step 2 · (a) μ
ln(24.1/4) + 3 ln 4 − 0.75 = 1.80 + 4.16 − 0.75
μ = 5.21
↓
Step 3 · (b) Hc
64/2,500 = 0.0256; 2.5 × 2/(5.21 × 22.3) = 0.0430; 1/(0.0686)0.5
Hc = 3.8 ft
Spot check: Units: each term is 1/ft², so the square root gives feet. Hc cannot exceed H/8 = 6.25 ft.
↓
Step 4 · (c) Drains and length saved
200,000 / (0.866 × 20.25) = 11,400 drains; 11,400 × 3.8 ft
About 43,000 ft of drain saved
↓
Solution
μ = 5.2; drains can stop about 3.8 ft above the sand; about 43,000 ft of drain saved.

Solution

(a) μ ≈ 5.2. (b) Hc ≈ 3.8 ft. (c) About 43,000 linear feet of drain.

Stopping the drains about 4 ft above the sand gives almost the same overall rate of consolidation as full penetration, because the bottom 4 ft drains quickly into the sand. The saving is about 8% of the drain length. Confirm the sand is continuous and free-draining with the borings or CPTs (a clay lens in the sand changes the answer), and if vacuum is added later, the drains must stop short of the sand anyway so the vacuum does not leak into it (Section 6.2.18).

6.2.15 Cross-References
TopicChapter
SPT N₆₀ for E_s estimation in granular soilsChapter 4.1
CPTu and DMT for E_s, M, and OCR estimation in clayChapter 5.1
Atterberg limits for C_c estimation (Skempton)Chapter 2.2
Groundwater and effective stress; seasonal WT variationChapter 2.8
Bearing capacity (companion to settlement)Chapter 6.1
Slope stability of consolidating embankmentsChapter 6.3
Seismic-induced settlement in granular soilsChapter 6.5
PVD and surcharge preloading designChapter 7.2
Bridge approach settlement mitigationChapter 7.1
Subgrade deformation under repeated train loadingChapter 2.3
Settlement plate monitoring and inclinometer readingsChapter 5.3
Settlement analysis documentation in geotechnical reportsChapter 8.4
Consolidation test (ASTM D2435) data and quality checksChapter 5.2

End of Chapter 6.2 — Settlement Analysis

Primary source: USACE EM 1110-1-1804, Geotechnical Investigations (January 2001). Settlement equations follow Terzaghi (1943), Skempton (1944), Mesri & Godlewski (1977), and FHWA GEC No. 5. FRA geometry tolerances per 49 CFR Part 213; AREMA MRE Chapter 8.

6.2.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S8 under Supplemental References.

Case Study 12.16.1 — Unit weight of fill: design assumes 127 pcf, the job measures more
Case study · Look (2023) §8.8

Related section: 6.2.3 Immediate (Elastic) Settlement

Look found that 127 pcf is used in about 70% of reports for fill unit weight. Compaction records give a large, cheap dataset to check it, and they are rarely used for that. On a Southeast Queensland project, 5,644 density tests had a 10% lower bound of 126 pcf, a median of 134 pcf and a 10% upper bound of 140 pcf. On a North Queensland road, imported fill mostly fell between 135 and 148 pcf, median 141.

On that second job the heavier fill caused more elastic settlement of a high embankment on competent ground than the bill of quantities had allowed for, and a contractual claim followed. Using the as-built 146 pcf instead of 127 pcf gives about 15% more fill settlement. Look’s suggested unit weights for well-compacted fill:

  • cut to fill, no weathered rock: 127–134 pcf
  • cut to fill with residual soil and extremely to highly weathered rock: 127–146 pcf
  • imported quarry overburden: 134–153 pcf
  • imported quarry rock fill: 140–159 pcf

For railroad work: rail embankments are often high and wide, so a 15% settlement difference becomes a real quantity of fill to pay for. Feed the density test results back into the settlement and stability checks.

Design assumes a unit weight for settlement and stability; construction measures density only to pass or fail it, and the two are rarely compared.
Figure 12-LK1. Design assumes a unit weight for settlement and stability; construction measures density only to pass or fail it, and the two are rarely compared. Source: Look (2023), Figure 8.8-1, p. 265.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §8.8, pp. 266–268. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

6.2.17 Apps and Analytical Tools18

The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this part of the analysis, gathered here from across the manual in the November 2026 restructure: 18 tools (12 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).

Apps

Each app runs in a web browser on a desktop or a phone, with nothing to install. How to use the apps (1.0.3).

Tools

Data Templates
DTData — Culvert SettlementUsed in Chapter 2.1, 2.1.5 Drainage Elements; Chapter 6.2, 6.2.7 Total Settlement and Angular DistortionCalculator ▸Guide
Field Forms & Logs
FFField Observation DataUsed in Chapter 3.8, 3.8.14 Monitoring and Early-Warning Indicators; Chapter 5.3, 5.3.6 Settlement Monitoring; Chapter 6.2, 6.2.7 Total Settlement and Angular DistortionCalculator ▸Guide
Pavements, Subgrade & Frost
PVFrost Penetration — Berggren EquationUsed in Chapter 2.3, 2.3.5 Subgrade Failure Modes; Chapter 7.3, 7.3.5 Frost DesignCalculator ▸Guide
PVFrost Penetration — Stefan EquationUsed in Chapter 2.3, 2.3.5 Subgrade Failure Modes; Chapter 7.3, 7.3.5 Frost DesignCalculator ▸Guide
PVPercent Saturation — Subgrade SamplesUsed in Chapter 2.3, 2.3.5 Subgrade Failure Modes; Chapter 5.2, 5.2.3 Test Methods — ASTM Standards and English Unit OutputsCalculator ▸Guide
PVRR Train Loads on SubgradeUsed in Chapter 2.3, 2.3.2 Load Distribution — Talbot MethodCalculator ▸Guide
Soil & Rock Properties
SPAtterberg Limits — Plasticity ChartUsed in Chapter 2.2, 2.2.3 Atterberg Limits (ASTM D4318); Chapter 5.2, 5.2.3 Test Methods — ASTM Standards and English Unit OutputsCalculator ▸Guide
SPGradationUsed in Chapter 2.2, 2.2.2 Grain-Size Analysisguide onlyGuide
Settlement & Heave
STConsolidation Index CorrelationsUsed in Chapter 2.2, 2.2.3 Atterberg Limits (ASTM D4318); Chapter 5.2, 5.2.3 Test Methods — ASTM Standards and English Unit Outputsguide onlyGuide
STConsolidation Settlement — Strip FootingUsed in Chapter 6.2, 6.2.4 Primary Consolidation SettlementCalculator ▸Guide
STHS20-44 Influence Pressuresneeds workUsed in Chapter 2.1, 2.1.7 Structural Foundations Supporting or Adjacent to the TrackCalculator ▸Guide
STHeave CalculationsUsed in Chapter 3.8, 3.8.2 Track Substructure Failure Mechanisms; Chapter 6.2, 6.2.7 Total Settlement and Angular DistortionCalculator ▸Guide
STSettlement — Fill + Cut over CulvertUsed in Chapter 2.1, 2.1.5 Drainage Elementsguide onlyGuide
STSettlement — Fill + Cut, InfiniteUsed in Chapter 6.2, 6.2.4 Primary Consolidation Settlementguide onlyGuide
STSettlement — Fill + Cut, Non-symmetric TrapezoidUsed in Chapter 2.1, 2.1.2 Embankments; Chapter 6.2, 6.2.4 Primary Consolidation Settlement; Chapter 7.2, 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged LoadingCalculator ▸Guide
STSettlement — Rectangular FootingUsed in Chapter 6.2, 6.2.3 Immediate (Elastic) Settlementguide onlyGuide
STVertical Induced Pressures (Influence Factors)Used in Chapter 2.1, 2.1.7 Structural Foundations Supporting or Adjacent to the Track; Chapter 3.9, 3.9.5 Boring Depth Planning — Criteria and Equations (English Units); Chapter 6.2, 6.2.2 Stress Increase in Soil — Boussinesq DistributionCalculator ▸Guide
STWick Drain SpacingUsed in Chapter 6.2, 6.2.8 Preloading and Surcharge Design; Chapter 7.2, 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loadingguide onlyGuide
Foundation Failure - Excessive Settlement
Foundation Failure - Excessive Settlement

Calculator: Consolidation Settlement and Time Rate (Section 6.2.4.3)

Calculator: Precompression Surcharge (Section 6.2.8.1)

6.2.18 Deformation of Embankments on Improved Soft Ground

Settlement predictions for an embankment on soft clay are only as good as the soil model, its parameters and how the construction is simulated. Chai and Carter (2011) summarize methods, checked against test embankments and case histories, for predicting deformations of soft ground improved by vertical drains, vacuum consolidation and soil-cement columns. The points below are those most useful for railroad embankments, widenings and approach fills.

6.2.18.1 Check the model against the measured strength

Before trusting a numerical model, compare the undrained shear strength profile it implies with field vane, unconfined compression or UU triaxial results. The model, its parameters and the initial stresses (including OCR) together control the strength the model uses; a mismatch here means the predicted settlement and stability will both be wrong. Correct field vane strengths for strain rate (Bjerrum).

6.2.18.2 Large settlement changes the problem

  • Fill placed to grade. When the foundation settles during construction, more fill is needed to reach grade, and that fill is extra load. A model that keeps the original fill geometry under-predicts the load; one that does not keep the fill following the settlement over-predicts it.
  • Stability. Settlement during construction lowers the effective height of the embankment, replaces some soft soil with stronger fill, and shortens drainage paths so that strength gains faster. For a test embankment built to failure in Malaysia, including these effects raised the computed factor of safety by about 0.1.
  • Buoyancy. Where the water table is near the surface, settling fill and soil move below it and become buoyant, which reduces the effective load. For a test embankment in Japan, including buoyancy reduced the predicted final settlement by about 13%.

6.2.18.3 Vertical drain parameters

  • Smear zone. Diameter ds = 2 to 3 times the equivalent mandrel diameter dm; use 3dm when there are no data. Base kh/ks on laboratory values multiplied by a field factor Cf that reflects stratification: close to 1 for a homogeneous deposit and much larger where thin sand or silt seams are present.
  • Discharge capacity. Well resistance is usually unimportant when qw exceeds about 3,500 ft³/yr (100 m³/yr), but discharge capacity drops with time from confining pressure, kinking as the clay settles, and clogging.
  • Sand mat. A drainage blanket at least about 1.6 ft thick with hydraulic conductivity above about 30 ft/day is close to free-draining. Clayey sand blankets slow consolidation.
  • Partial penetration in a two-way draining layer. Where a sand layer underlies the clay, stopping the drains short of the sand gives almost the same rate of consolidation as full penetration. The optimum unimproved thickness at the bottom is Hc = 1 / [ 64/H² + 2.5 ch / (μ De² cv) ]0.5 (Eq. 6.2-25), where H is the clay thickness, De the drain influence diameter and μ the Hansbo drain resistance factor (Chapter 7.2, Section 7.2.3). It applies to deposits up to about 65 ft thick; use thickness-weighted ch and cv in layered ground. Example: H = 40 ft, ch/cv = 2, μ = 3, De = 5 ft gives Hc = 1/(0.040 + 0.067)0.5 = 1/0.327 ≈ 3 ft, so the drains could stop about 3 ft above the sand. The first term caps Hc at H/8, so the saving is modest but free.

6.2.18.4 Vacuum consolidation

  • Vacuum adds an equal all-round consolidation stress and so tends to pull the ground inward. Inward lateral movement occurs where |σvac| > K0 σ′v0 / (1 − K0) (Eq. 6.2-26). With K0 = 0.5 and a vacuum of about 1,670 psf (11.6 psi), that is wherever the initial vertical effective stress is below about 1,670 psf, which in soft clay with a submerged unit weight of about 35 pcf extends to roughly 45 ft. Inward movement is therefore the normal case near the surface and through much of a typical soft deposit.
  • Where inward movement occurs, vacuum produces less settlement than a fill surcharge of the same pressure, and tension cracks can open near the edge of the treated area.
  • In a layer drained at both top and bottom, the vacuum cannot be held at the bottom boundary; the final vacuum distribution is triangular and settlement is less than with one-way drainage. Drains must stop short of a bottom sand layer, or the vacuum leaks into it; an optimum depth applies here too.
  • Combining vacuum with fill surcharge offsets the inward movement against the outward push of the fill and is common practice.

6.2.18.5 Soil-cement columns

  • Fully penetrating columns. Use the equilibrium method for settlement of the soil between columns, or the composite modulus method for average settlement. Because the columns are much stiffer than the clay, they also speed up consolidation even though their permeability is similar.
  • Floating columns (columns ending in the soft layer). Stress carried by the columns varies with the area ratio α, the depth ratio β and depth. Chai and Carter treat the lower part of the improved zone as effectively unimproved and calculate the soft layers below the columns as a separate layer; much of the settlement then comes from below the column tips (Section 7.2.5).
  • Installation movement. Injecting slurry or powder under pressure expands the ground like a cavity and pushes it sideways. Cavity-expansion methods predict this displacement using a soil modulus (E/Su of about 100 to 200 in soft clay) and the volume injected.

For railroad work: When soft ground under a track widening or approach fill is improved, the existing embankment and track beside it move too. Vacuum pulls the edge of the existing embankment inward and can crack it; column installation pushes it outward; both should be predicted, monitored with inclinometers and track geometry surveys, and controlled by sequence and distance from the operating track. When settlement is made up with extra fill or ballast to hold top-of-rail grade, count that fill as load, and remember that fill sinking below the water table becomes buoyant. Check that the drains stop short of an underlying sand where vacuum is used.

Source: Chai and Carter (2011), Chapters 2–5. Full reference under Supplemental References.

Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

Supplemental references

  • U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904Official page ↗Library entry
  • Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research BoardFind source ↗
  • Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co.Find source ↗
  • Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)Find source ↗
  • Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case studies §8.8Find source ↗Library entry

File locations for these documents are listed under Supplemental References.

Project management sources

  • Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier)Find source ↗
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S7 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S8 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904Find source ↗Library entry
  2. Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research BoardFind source ↗
  3. Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co.Find source ↗
  4. Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)Find source ↗
  5. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  6. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  7. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 8 and 15Find source ↗Library entry
  8. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §8.8Find source ↗Library entry
  9. Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier). Used on this page for project-management materialFind source ↗
  10. Chai, J. and Carter, J. P. (2011). Deformation Analysis in Soft Ground Improvement. Geotechnical, Geological and Earthquake Engineering, Vol. 18. Dordrecht: Springer. Used on this page: Section 6.2.18Find source ↗
  11. Feng, X.-T. (ed.) (2017). Rock Mechanics and Engineering, Volume 4: Excavation, Support and Monitoring. Leiden: CRC Press/Balkema. Used on this page: Section 6.2.7 (settlement from tunneling)Find source ↗

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 6.2.8-1 — Vacuum Consolidation Process with PVDs, showing the impervious membrane, vacuum gas phase booster and air/water pump, horizontal and vertical vacuum transmission pipes, and peripheral trenches filled with bentonite and polyacrylate. (Figure from Masse et al. 2001) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  2. Photo 6.2.8-2 — Sand Platform and Geotextile. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  3. Photo 6.2.8-3 — Horizontal Drain Connection. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  4. Photo 6.2.8-4 — Installing the Membrane. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  5. Photo 6.2.8-5 — Peripheral Trench. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  6. Photo 6.2.8-6 — Vacuum Pumps. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  7. Photo 6.2.8-7 — Additional Fill Being Placed for Membrane Protection. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  8. Photo 6.2.8-8 — Sewage Treatment Plant General Layout, west of Pusan City, South Korea. (Figure from Masse et al. 2001.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  9. Photo 6.2.8-9 — Post Vacuum Rebound — recorded settlement approaching the 11.8-ft (3.61 m) target through November–December 1996, showing the brief rebound after the vacuum was stopped and the surcharge removed. (Figure from the Pusan, South Korea case history.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗