Railroad Geotechnical Services Manual | Primary Source: USACE EM 1110-1-1804 All equations and parameters expressed in English (Imperial) units throughout.
Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database
Compressibility, consolidation and stiffness values for settlement estimates. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Coefficient of volume compressibility | Hard, heavily overconsolidated glacial till, stiff weathered rocks, hard clays | CL-CH / OH / Pt | Very low compressibility | 0.0024 | ft²/kip | CB T5.1, p.108 | ||
| Compression index | Hard, heavily overconsolidated glacial till, stiff weathered rocks, hard clays | CL-CH / OH / Pt | Very low compressibility | 0.025 | – | CB T5.1, p.108 | ||
| Coefficient of volume compressibility | Stiff glacial till, marls, very stiff tropical residual clays | CL-CH / OH / Pt | Low compressibility | 0.0024 | 0.0036 | 0.0048 | ft²/kip | CB T5.1, p.108 |
| Compression index | Stiff glacial till, marls, very stiff tropical residual clays | CL-CH / OH / Pt | Low compressibility | 0.025 | 0.0375 | 0.05 | – | CB T5.1, p.108 |
| Coefficient of volume compressibility | Firm clays, glacial outwash clays, lake deposits, NC clays at depth | CL-CH / OH / Pt | Medium compressibility | 0.0048 | 0.0096 | 0.0144 | ft²/kip | CB T5.1, p.108 |
| Compression index | Firm clays, glacial outwash clays, lake deposits, NC clays at depth | CL-CH / OH / Pt | Medium compressibility | 0.05 | 0.1 | 0.15 | – | CB T5.1, p.108 |
| Coefficient of volume compressibility | Poorly consolidated alluvial clays (estuarine), sensitive clays | CL-CH / OH / Pt | High compressibility | 0.0144 | 0.0431 | 0.0718 | ft²/kip | CB T5.1, p.108 |
| Compression index | Poorly consolidated alluvial clays (estuarine), sensitive clays | CL-CH / OH / Pt | High compressibility | 0.15 | 0.45 | 0.75 | – | CB T5.1, p.108 |
| Coefficient of volume compressibility | Highly organic alluvial clays and peats | CL-CH / OH / Pt | Very high compressibility | 0.0718 | ft²/kip | CB T5.1, p.108 | ||
| Compression index | Highly organic alluvial clays and peats | CL-CH / OH / Pt | Very high compressibility | 0.75 | 2.875 | 5 | – | CB T5.1, p.108 |
| Compression index | Uniform silts | ML / SP | 0.2 | – | USACE T3-7, p.59 | |||
| Compression index | Uniform sand, loose | ML / SP | 0.05 | 0.055 | 0.06 | – | USACE T3-7, p.59 | |
| Compression index | Uniform sand, dense | ML / SP | 0.02 | 0.025 | 0.03 | – | USACE T3-7, p.59 | |
| Recompression index | Clays | CL-CH | 0.015 | 0.1825 | 0.35 | – | CB T5.1 text, p.108 | |
| Secondary compression ratio | Clay | 0.025 | 0.055 | 0.085 | – | USACE T3-14, p.79 | ||
| Secondary compression ratio | Silt | 0.03 | 0.0525 | 0.075 | – | USACE T3-14, p.79 | ||
| Secondary compression ratio | Peat | 0.03 | 0.0575 | 0.085 | – | USACE T3-14, p.79 | ||
| Secondary compression ratio | Muskeg | 0.09 | 0.095 | 0.1 | – | USACE T3-14, p.79 | ||
| Secondary compression ratio | Inorganic soils | 0.025 | 0.0425 | 0.06 | – | USACE T3-14, p.79 | ||
| Secondary compression ratio | Organic silts | OL | 0.035 | 0.0475 | 0.06 | – | CB T5.4, p.117 | |
| Secondary compression ratio | Amorphous and fibrous peat | Pt | 0.035 | 0.06 | 0.085 | – | CB T5.4, p.117 | |
| Secondary compression ratio | Organic clays and silts | ML-MH | 0.04 | 0.05 | 0.06 | – | CB T5.4, p.117 | |
| Secondary compression ratio | San Francisco Bay mud | CL | 0.04 | 0.05 | 0.06 | – | CB T5.4, p.117 | |
| Secondary compression ratio | Sensitive clay, Portland ME | CL-CH | 0.025 | 0.04 | 0.055 | – | CB T5.4, p.117 | |
| Coefficient of consolidation | Low plasticity clays | CL | 32.29 | 118.4 | 204.5 | ft²/yr | CB T5.3, p.114 | |
| Coefficient of consolidation | Low plasticity glacial lake clays | CL | 21.53 | 26.9 | 32.29 | ft²/yr | CB T5.3, p.114 | |
| Coefficient of consolidation | Low plasticity mud | CL | 6.46 | 9.7 | 12.92 | ft²/yr | CB T5.3, p.114 | |
| Coefficient of consolidation | Medium plasticity clays | CL-CH | 9.69 | ft²/yr | CB T5.3, p.114 | |||
| Coefficient of consolidation | Volcanic silt | MH | 3.23 | 4.305 | 5.38 | ft²/yr | CB T5.3, p.114 | |
| Coefficient of consolidation | Organic silt | OL | 6.46 | 19.4 | 32.29 | ft²/yr | CB T5.3, p.114 | |
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 30% | ML-CH | Undisturbed – virgin compression | 1,292 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 40% | ML-CH | Undisturbed – virgin compression | 538.2 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 50% | ML-CH | Undisturbed – virgin compression | 215.3 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 60% | ML-CH | Undisturbed – virgin compression | 107.6 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 70% | ML-CH | Undisturbed – virgin compression | 53.82 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 80% | ML-CH | Undisturbed – virgin compression | 32.29 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 90% | ML-CH | Undisturbed – virgin compression | 16.15 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 100% | ML-CH | Undisturbed – virgin compression | 10.76 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 110% | ML-CH | Undisturbed – virgin compression | 9.69 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 30% | ML-CH | Undisturbed – recompression | 215.3 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 40% | ML-CH | Undisturbed – recompression | 107.6 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 50% | ML-CH | Undisturbed – recompression | 53.82 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 60% | ML-CH | Undisturbed – recompression | 32.29 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 70% | ML-CH | Undisturbed – recompression | 21.53 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 80% | ML-CH | Undisturbed – recompression | 10.76 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 90% | ML-CH | Undisturbed – recompression | 8.61 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 100% | ML-CH | Undisturbed – recompression | 6.46 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 110% | ML-CH | Undisturbed – recompression | 5.38 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 30% | ML-CH | Remolded | 43.06 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 40% | ML-CH | Remolded | 21.53 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 50% | ML-CH | Remolded | 16.15 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 60% | ML-CH | Remolded | 10.76 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 70% | ML-CH | Remolded | 6.46 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 80% | ML-CH | Remolded | 4.31 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 90% | ML-CH | Remolded | 3.77 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 100% | ML-CH | Remolded | 3.23 | ft²/yr | LOOK T8.14, p.122 | ||
| Coefficient of consolidation vs liquid limit | Fine-grained soil, LL = 110% | ML-CH | Remolded | 2.69 | ft²/yr | LOOK T8.14, p.122 | ||
| Overconsolidation ratio | Clays | CL-CH | Normally consolidated | 1 | 1.25 | 1.5 | – | LOOK T7.10, p.108 |
| Overconsolidation ratio | Clays | CL-CH | Lightly overconsolidated | 1.5 | 2.75 | 4 | – | LOOK T7.10, p.108 |
| Overconsolidation ratio | Clays | CL-CH | Heavily overconsolidated | 4 | – | LOOK T7.10, p.108 |
| Property | Soil / material | Class | Condition | Low | Typical | High | Units | Source |
|---|---|---|---|---|---|---|---|---|
| Young's modulus (drained) | Gravel | GW-SP | Loose | 522.1 | 783.2 | 1,044 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Gravel | GW-SP | Medium | 1,044 | 1,566 | 2,088 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Gravel | GW-SP | Dense | 2,088 | 3,133 | 4,177 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Medium to coarse sand | GW-SP | Very loose | 104.4 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus (drained) | Medium to coarse sand | GW-SP | Loose | 62.7 | 135.8 | 208.9 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Medium to coarse sand | GW-SP | Medium dense | 167.1 | 396.9 | 626.6 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Medium to coarse sand | GW-SP | Dense | 522.1 | 783.2 | 1,044 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Medium to coarse sand | GW-SP | Very dense | 835.4 | 1,462 | 2,088 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Fine sand | GW-SP | Loose | 104.4 | 156.7 | 208.9 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Fine sand | GW-SP | Medium | 208.9 | 365.5 | 522.1 | ksf | LOOK T11.7, p.152 |
| Young's modulus (drained) | Fine sand | GW-SP | Dense | 522.1 | 783.2 | 1,044 | ksf | LOOK T11.7, p.152 |
| Young's modulus, short term (undrained) | Silt | ML-CH | Soft | 208.9 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus, long term (drained) | Silt | ML-CH | Soft | 167.1 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus, short term (undrained) | Silt | ML-CH | Stiff | 208.9 | 313.3 | 417.7 | ksf | LOOK T11.7, p.152 |
| Young's modulus, long term (drained) | Silt | ML-CH | Stiff | 167.1 | 240.2 | 313.3 | ksf | LOOK T11.7, p.152 |
| Young's modulus, short term (undrained) | Silt | ML-CH | Hard | 417.7 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus, long term (drained) | Silt | ML-CH | Hard | 313.3 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus, short term (undrained) | Clay | ML-CH | Very soft | 62.7 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus, long term (drained) | Clay | ML-CH | Very soft | 41.8 | ksf | LOOK T11.7, p.152 | ||
| Young's modulus, short term (undrained) | Clay | ML-CH | Soft | 41.8 | 94 | 146.2 | ksf | LOOK T11.7, p.152 |
| Young's modulus, long term (drained) | Clay | ML-CH | Soft | 20.9 | 62.7 | 104.4 | ksf | LOOK T11.7, p.152 |
| Young's modulus, short term (undrained) | Clay | ML-CH | Firm | 104.4 | 177.5 | 250.6 | ksf | LOOK T11.7, p.152 |
| Young's modulus, long term (drained) | Clay | ML-CH | Firm | 83.5 | 125.3 | 167.1 | ksf | LOOK T11.7, p.152 |
| Young's modulus, short term (undrained) | Clay | ML-CH | Stiff | 208.9 | 365.5 | 522.1 | ksf | LOOK T11.7, p.152 |
| Young's modulus, long term (drained) | Clay | ML-CH | Stiff | 146.2 | 281.9 | 417.7 | ksf | LOOK T11.7, p.152 |
| Young's modulus, short term (undrained) | Clay | ML-CH | Very stiff | 417.7 | 731 | 1,044 | ksf | LOOK T11.7, p.152 |
| Young's modulus, long term (drained) | Clay | ML-CH | Very stiff | 313.3 | 522.1 | 731 | ksf | LOOK T11.7, p.152 |
| Young's modulus, short term (undrained) | Clay | ML-CH | Hard | 835.4 | 1,253 | 1,671 | ksf | LOOK T11.7, p.152 |
| Young's modulus, long term (drained) | Clay | ML-CH | Hard | 626.6 | 939.8 | 1,253 | ksf | LOOK T11.7, p.152 |
| Small-strain shear modulus | Soft clays | 57 | 172 | 287 | ksf | GEC5 T30, p.181 | ||
| Small-strain shear modulus | Firm clays | 144 | 432.5 | 721 | ksf | GEC5 T30, p.181 | ||
| Small-strain shear modulus | Silty sands | 576 | 1,729 | 2,882 | ksf | GEC5 T30, p.181 | ||
| Small-strain shear modulus | Dense sands and gravels | 1,441 | 4,323 | 7,205 | ksf | GEC5 T30, p.181 | ||
| Poisson's ratio, short term | Sands, gravels and other cohesionless soils | Short term | 0.3 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, long term | Sands, gravels and other cohesionless soils | Long term | 0.3 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, short term | Clay, low PI (<12%) | Short term | 0.35 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, long term | Clay, low PI (<12%) | Long term | 0.25 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, short term | Clay, medium PI (12–22%) | Short term | 0.4 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, long term | Clay, medium PI (12–22%) | Long term | 0.3 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, short term | Clay, high PI (22–32%) | Short term | 0.45 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, long term | Clay, high PI (22–32%) | Long term | 0.35 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, short term | Clay, extremely high PI (>32%) | Short term | 0.45 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio, long term | Clay, extremely high PI (>32%) | Long term | 0.4 | – | LOOK T11.17, p.157 | |||
| Poisson's ratio | Cohesive soil (settlement analysis) | CL-CH | 0.4 | – | USACE para. 3-9c, p.47 | |||
| Poisson's ratio | Subgrade soils | 0.25 | 0.325 | 0.4 | – | LOOK T13.28, p.192 | ||
| Poisson's ratio | Granular pavement material | GW / GP | 0.35 | – | LOOK T13.28, p.192 | |||
| Poisson's ratio | Weathered rock subgrade | Rock | 0.3 | – | LOOK T13.28, p.192 | |||
| Poisson's ratio | Unweathered bedrock subgrade | Rock | 0.15 | – | LOOK T13.28, p.192 | |||
| Modulus of elasticity | Soft clay | 36 | 54 | 72 | ksf | DASP T11.4, p.319 | ||
| Modulus of elasticity | Hard clay | 122.4 | 205.2 | 288 | ksf | DASP T11.4, p.319 | ||
| Modulus of elasticity | Loose sand | 216 | 396 | 576 | ksf | DASP T11.4, p.319 | ||
| Modulus of elasticity | Dense sand | 720 | 1,080 | 1,440 | ksf | DASP T11.4, p.319 | ||
| Poisson's ratio | Loose sand | 0.2 | 0.3 | 0.4 | – | DASP T11.5, p.320 | ||
| Poisson's ratio | Medium sand | 0.25 | 0.325 | 0.4 | – | DASP T11.5, p.320 | ||
| Poisson's ratio | Dense sand | 0.3 | 0.375 | 0.45 | – | DASP T11.5, p.320 | ||
| Poisson's ratio | Silty sand | 0.2 | 0.3 | 0.4 | – | DASP T11.5, p.320 | ||
| Poisson's ratio | Soft clay | 0.15 | 0.2 | 0.25 | – | DASP T11.5, p.320 | ||
| Poisson's ratio | Medium clay | 0.2 | 0.35 | 0.5 | – | DASP T11.5, p.320 | ||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N = 0–4 | VII | CRAIG T8.4, p.315 | |||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N = 4–8 | VI | CRAIG T8.4, p.315 | |||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N = 9–15 | V | CRAIG T8.4, p.315 | |||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N = 16–25 | IV | CRAIG T8.4, p.315 | |||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N = 26–40 | III | CRAIG T8.4, p.315 | |||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N = 41–60 | II | CRAIG T8.4, p.315 | |||
| Compressibility grade (Burland & Burbidge) | Normally consolidated sands and gravels | GW-SP | N > 60 | I | CRAIG T8.4, p.315 | |||
| Coefficient of subgrade reaction (1-ft plate) | Loose sand | 18.4 | 38.6 | 58.9 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Medium dense sand | 36.8 | 165.8 | 294.7 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Dense sand | 221 | 340.8 | 460.5 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Clayey sand | 110.5 | 202.6 | 294.7 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Silty sand | 73.7 | 128.9 | 184.2 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Clayey soil, su < 1,044 psf (50 kPa) | 36.8 | 55.2 | 73.7 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Clayey soil, su 1,044–2,089 psf (50–100 kPa) | 73.7 | 128.9 | 184.2 | pci | ROB T9, p.84 | ||
| Coefficient of subgrade reaction (1-ft plate) | Clayey soil, su > 2,089 psf (100 kPa) | 184.2 | pci | ROB T9, p.84 |
| Estimate | Correlation | Limits / notes | Source |
|---|---|---|---|
| Compression index – clays | Cc = 0.009 (LL − 10) (organic soils, sensitivity < 4) | Skempton / Terzaghi & Peck | USACE 3-7, p.59 |
| Compression index – clays | Cc = 1.15 (e0 − 0.35); Cc = 0.012 wn; Cc = 0.01 (LL − 13) | All clays | USACE 3-7, p.59 |
| Compression index – organic soils, peat | Cc = 0.0115 wn | wn in percent | USACE 3-7, p.59 |
| Compression index – varved clays | Cc = (1 + e0) [0.1 + 0.006 (wn − 25)] | USACE 3-7, p.59 | |
| Compression index – remolded clays | Cc = 0.007 (LL − 7) | Azzouz et al. (1976) | CB 5.2, p.109 |
| Compression index – inorganic silt/clay | Cc = 0.30 (e0 − 0.27); Cc = 0.75 (e0 − 0.5) | Azzouz et al. (1976) | CB 5.2, p.109 |
| Recompression index | Cr ≈ 0.05–0.10 Cc (range 0.015–0.35) | Roscoe et al. (1958) | CB 5.1 text, p.108 |
| Secondary compression index | Cα ≈ 0.0001 wn (10 < wn < 3000%) | NAVFAC DM 7.1 | USACE 3-14 text, p.79 |
| Drained modulus of clay from su | E′/su ≈ 270 (PI 10–30), 200 (20–30), 150 (30–40), 130 (40–50) | Stroud et al. (1975) | LOOK 11.13, p.155 |
| Shear modulus at small and large strain | G(large) ≈ E/2.5; G(small) ≈ 2E ≈ 5 G(large) | LOOK 11.2 notes, p.148 | |
| Stiffness degradation | E0.01/E0 = 0.8–0.9; E0.1/E0 = 0.4–0.5; E1.0/E0 = 0.1–0.2 | Heymann (1998) | LOOK 11.3, p.148 |
| Small-strain shear modulus from shear wave velocity | G0 = ρ Vs² = (γ/g) Vs² (γ in pcf, g = 32.2 ft/s², Vs in ft/s → G0 in psf) | Seismic CPT or other Vs measurement | ROB text, p.53 |
| Subgrade reaction size effect | ks = ks1 [(B + 1)/(2B)]², B in ft | Terzaghi (1955); large scatter | ROB 9 text, p.84 |
| Overconsolidation ratio from CPT | OCR = 0.25 Qt^1.25 (Robertson 2009); OCR = k Qt, k = 0.33 (0.2–0.5) (Kulhawy & Mayne 1990) | Kulhawy & Mayne valid for Qt < 20 | ROB text, p.46 |
| Constrained modulus from CPT | M = αM (qt − σvo); Ic > 2.2: αM = Qt when Qt < 14, αM = 14 when Qt > 14; Ic < 2.2: αM = 0.0188 · 10^(0.55 Ic + 1.68) | Robertson (2009); lower in organic soils | ROB text, p.62 |
Full database · Laboratory tests · Download Excel · Library documents for this chapter · Calculators for this chapter
Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1. For railroad infrastructure, settlement governs more designs than bearing capacity failure — particularly embankment fills over soft alluvial soils, approach fills behind bridge abutments, and intermodal yard slabs on compressible clay. Total settlement S_total consists of three components: immediate (elastic) settlement S_i, primary consolidation settlement S_c, and secondary compression S_s. Time-rate analysis using Terzaghi's consolidation theory predicts when settlement will occur, enabling the consultant to recommend preloading, staged construction, or ground improvement to achieve acceptable geometry before track placement. This chapter develops all three settlement components in English units, cross-references FRA track geometry tolerances by track class as the acceptance criteria, and presents worked examples for a Class I railroad embankment over soft clay, a Class I railroad bridge approach fill with time-rate prediction, and a Class I railroad intermodal yard slab on overconsolidated clay. Owner railroad requirements are noted where they commonly differ.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.
| ID | Correlation | Gives |
|---|---|---|
| IS-17 | Preconsolidation stress / OCR from CPT | σ'ₚ, OCR |
| IX-05 | Secondary compression ratio | C_α |
| IX-01 | Compression index from liquid limit (undisturbed) | C꜀ |
| IX-02 | Compression index from liquid limit (remolded) | C꜀ |
| IX-03 | Compression index from void ratio | C꜀ |
| IX-04 | Compression index from plasticity index | C꜀ |
| IS-08 | Drained Young's modulus of sand from SPT | E' |
| IS-19 | Constrained modulus from CPT | M |
FRA track geometry tolerances (49 CFR Part 213) establish the operational framework within which all settlement predictions must be evaluated. Unlike building foundations, where total settlement of 1–2 in. is routinely acceptable, railroad track geometry tolerances are measured in fractions of an inch — the structural consequence of derailment, speed restriction, or emergency slow order is immediate and measurable.

| Track Class | Max Speed (Freight) | Cross-Level Tolerance | Surface (Profile) Tolerance, 62-ft chord | Total Settlement Limit (our recommendation) | Angular Distortion Limit |
|---|---|---|---|---|---|
| Class 1 | 10 mph | 3 in. | 3 in. per 62 ft | ≤ 3.0 in. | ≤ 1/200 |
| Class 2 | 25 mph | 2 in. | 2¾ in. per 62 ft | ≤ 2.0 in. | ≤ 1/300 |
| Class 3 | 40 mph | 1¾ in. | 2¼ in. per 62 ft | ≤ 1.5 in. | ≤ 1/400 |
| Class 4 | 60 mph | 1¼ in. | 2 in. per 62 ft | ≤ 1.0 in. | ≤ 1/500 |
| Class 5 | 80 mph | 1 in. | 1¼ in. per 62 ft | ≤ 0.75 in. | ≤ 1/700 |
| Class 6 | 110 mph | see 49 CFR 213.331 | see 49 CFR 213.331 | ≤ 0.5 in. | ≤ 1/1,000 |
| Class 7 (high-speed passenger corridor) | 125 mph | see 49 CFR 213.331 | see 49 CFR 213.331 | ≤ 0.375 in. | ≤ 1/1,500 |
Angular distortion δ/L (where δ = differential settlement between two points, L = distance between them) is the critical parameter for bridge approach transitions and structure-embankment interfaces. Passenger railroads commonly impose tighter limits than FRA at structure transitions.
Owner railroads often set settlement limits tighter than the FRA minima. Confirm them when the work is scoped.
Elastoplastic finite-element results reproduced by Profillidis show the settlement under a passing axle at the top of subgrade, at the tie and at the rail for subgrade classes S1, S2, S3 and rock, for track-bed thicknesses of 12–39 in.. Subgrade class dominates: moving from S1 to S3 cuts the settlement several-fold, while extra track-bed thickness gives a smaller, steady reduction. Tie type matters less than subgrade class.


For new fills, the book reminds designers to overbuild embankment width and height to allow for the fill’s own compaction after construction (Chapter 2.1, §2.1.2).
After Profillidis (2014), §8.4.7, Figs. 8.8–8.9. Full reference under Supplemental References.
Before computing settlement, the change in vertical stress Δσ_v at depth z due to the applied load must be determined. For a uniformly loaded rectangular area of width B and length L at the surface:
Δσ_v = q · I_σ
Where I_σ is the Boussinesq influence factor (Newmark, 1935), a function of m = B/z and n = L/z:
I_σ = (1/4π)[2mn√(m²+n²+1)/(m²+n²+1+m²n²) × (m²+n²+2)/(m²+n²+1)
+ arcsin(2mn√(m²+n²+1)/(m²+n²+1+m²n²))]
Take the arcsin term between 0 and π: when m²n² > m²+n²+1 (wide, shallow cases), use π − arcsin(…) instead of the principal value. The equivalent tangent form is tan⁻¹[2mn√(m²+n²+1)/(m²+n²+1−m²n²)], adding π when the denominator is negative. Using the principal arcsin value alone under-predicts I_σ in that range.
Source: Newmark, N.M. (1935), Simplified Computation of Vertical Pressures in Elastic Foundations, Univ. of Illinois Eng. Exp. Station Circular 24, Eq. 5; Bowles, J.E. (1996), Foundation Analysis and Design, 5th ed., McGraw-Hill.
For practical use, Boussinesq influence charts (or tables) are used; I_σ ranges from 0.25 (square footing, z = 0) to near zero at large depth. For a 2:1 stress distribution approximation, commonly used for preliminary analysis:
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Iσ | intermediate value computed on this page | Another equation | Computed: I_σ = (1/4π)[2mn√(m²+n²+1)/(m²+n²+1+m²n²) × (m²+n²+2)/(m²+n²+1) | project-specific |
Δσ_v = Q / [(B + z)(L + z)] (psf)
Where Q = total load (lb), B and L = footing dimensions (ft), z = depth below footing base (ft). For strip loads (railroad embankments):
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Q | total load (lb), B and L = footing dimensions (ft), z = depth below footing base (ft) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
Δσ_v = (q/π)[β + sin β · cos(β + 2δ)] (psf)
Where β = the angle subtended by the load width at depth z (radians), δ = angle from load centerline, q = applied surface pressure (psf). For the centerline of a strip load:
Δσ_v,center = (q/π)[β + sin β]
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Δσv | intermediate value computed on this page | Another equation | Computed: Δσ_v = (q/π)[β + sin β · cos(β + 2δ)] (psf) | project-specific |
| β | the angle subtended by the load width at depth z (radians), δ = angle from load centerline, q = applied surface pressure (psf) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
Immediate settlement occurs under undrained loading conditions in saturated cohesive soils, or drained loading in granular soils. It develops essentially instantaneously upon load application.
Si = q · B · (1 − μ²) / Es · Iw
Where:
| Soil Type (USCS) | E_s (psf) | Typical Source |
|---|---|---|
| Very soft clay (CH) | 10,000–25,000 | Unconfined compression |
| Soft clay (CL) | 25,000–75,000 | Unconfined compression |
| Medium stiff clay | 75,000–150,000 | CPTu, PMT |
| Stiff clay | 150,000–300,000 | CPTu, PMT |
| Very stiff clay | 300,000–500,000 | PMT, pressuremeter |
| Loose sand (SP/SM) | 100,000–250,000 | SPT correlation |
| Medium-dense sand | 250,000–500,000 | SPT correlation |
| Dense sand/gravel | 500,000–1,500,000 | SPT correlation |
Immediate settlement is critical for intermodal yard slab design and for any structure where the total settlement is dominated by granular or stiff-clay subgrades. For most railroad embankment designs over soft cohesive soils, primary consolidation governs and S_i is secondary.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| q | net contact pressure (psf) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| B | footing width (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| μ | Poisson's ratio (0.5 for undrained clay | Assumed (published values) | Rarely measured; choose from published ranges. Use 0.5 for undrained clay. | 0.25–0.40; 0.5 undrained · by USCS group |
| Es | elastic modulus of soil (psf) | Field test, lab test or correlation | Pressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc. | loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group |
| Iw | influence factor for shape and embedment (Bowles, 1996; I_w | Another equation | Computed: I_w = 0.82 for square, 1.12 for L/B = 2, 1.52 for L/B = 5; rigid-footing values, flexible-center values are higher, e.g., 1.12 for a square) | ≈ 0.82 for square, 1.12 for L/B = 2, 1.52 for L/B = 5 |
Eq. 6.2-4 assumes a single modulus for the whole stressed zone. For footings, signal foundations and yard slabs on sand, USACE EM 1110-1-1904 recommends Schmertmann’s approximation, which sums strain over sublayers of thickness Δz = 0.2B using a triangular strain-influence diagram (Figure 12-S1):

ρi = C1 · Ct · Δp · Σ (Izi / Esi) Δzi
Because the method weights the stiffness of each sublayer, it captures a loose sand seam at depth B/2 that a single-modulus calculation averages away.
Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904
Case study: 6.2.16.1 Unit weight of fill: design assumes 127 pcf, the job measures more (Look 2023), in §12.16 Case Studies.
Signal, catenary and communication foundations, culvert footings and small bridge spread footings on sand or stiff clay settle mostly at once, as the soil compresses elastically when the load goes on. Das's Principles of Geotechnical Engineering (Section 11.2) gives the standard method. Steinbrenner's shape factors F1 and F2 account for the foundation's proportions and the depth to a rigid layer. Fox's depth factor accounts for embedment. A weighted average modulus over the depth of influence, min(H, 5B) after Bowles, handles layered soil. The result is for the center or corner of a flexible foundation, and a rigid foundation settles about 0.93 times the flexible center value. Das gives representative moduli, and CPT correlations (Es ≈ 2qc to 3qc in sand) connect the method to the soundings in Chapter 5.1.
Equation 6.1-22. Elastic settlement (Das Eqs. 11.1 to 11.10)
Center: α = 4, B′ = B/2, m′ = L/B, n′ = H/(B/2); corner: α = 1, B′ = B, n′ = H/B
Es = ΣEs(i)Δz / z̄, z̄ = min(H, 5B); Se(rigid) ≈ 0.93Se(flexible, center)
| Quantity | Das | Calculator |
|---|---|---|
| Weighted modulus Es | 10,400 kPa (1,508 psi) | 1,508 psi |
| F1, F2 (from tables) | 0.641, 0.031 | 0.641, 0.031 (closed form) |
| If | 0.71 | 0.71 |
| Is | 0.716 | 0.658 |
| Settlement, flexible center | 13.3 mm | 12.3 mm |
| Settlement, rigid | 12.4 mm | 11.4 mm |
The calculator matches F1, F2, If and Es. Das's example arrives at Is = 0.716 by using (2 − μ)/(1 − μ) in place of the (1 − 2μ)/(1 − μ) of Equation 11.2. With the equation as printed, Is = 0.658 and the settlement is about 8% smaller; with 0.716 the calculator also gives 13.3 mm.
Das's footing, 3.3 by 6.6 ft at 3.3 ft depth with rock 16.4 ft down, carrying 3,133 psf net over layers with moduli of 1,450, 1,160 and 1,740 psi, settles 0.48 in. at the center if flexible and 0.45 in. if rigid. The corner of a flexible footing settles 0.21 in. Most of the uncertainty is in the modulus. A factor of two in Es, well within the ranges in Das's Table 11.4, doubles the settlement. Poisson's ratio matters much less, as the calculator's chart shows.
Open the elastic settlement calculator →
Steinbrenner shape factors in closed form, the Fox depth factor, a weighted modulus over min(H, 5B), and flexible center, flexible corner and rigid settlements, with the effect of Poisson's ratio.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.
Plate to footing. A plate load test stresses the ground to a depth of only about twice the plate width, so its settlement has to be scaled up to the foundation. The usual relation for a square footing on sand (Terzaghi and Peck 1967) is:
ρB = ρ1 [2B / (1 + B)]2
where ρ1 = settlement of a 1-ft square plate, ρB = settlement of a footing of side B, and B is in feet. The ratio can never exceed 4, however large the footing. A more general relation (Ménard and Rousseau 1962) is:
ρ2 / ρ1 = (B2 / B1)α
where ρ1 and B1 are the plate settlement and width and ρ2 and B2 those of the footing. Typical α: sands and gravels 1/3 to 1/2; saturated silts 1/2; clays and dry silts 1/2 to 2/3; compacted fill 1. For example, a 1-ft plate that settles 0.25 in. under the design pressure predicts 0.25 × (12/7)2 = 0.73 in. for a 6-ft square signal-bridge footing by Terzaghi and Peck, or 0.25 × 60.4 = 0.51 in. by Ménard with α = 0.4. The spread between the two is typical. Neither relation detects a soft layer below the plate’s zone of influence, so confirm the profile with a boring to at least twice the footing width.
Do not correct N for settlement charts. The SPT-based settlement methods (Terzaghi and Peck, Meyerhof, Bowles’s adjustments and Burland and Burbidge) were all fitted to blow counts that were not corrected for overburden pressure. Applying CN to them raises the allowable bearing pressure or lowers the predicted settlement without any basis. Use the field N, corrected only for energy where the method calls for N60, and keep the overburden-corrected (N1)60 for relative density and liquefaction.
Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.4.1.4 and §5.4.2, Eqs. 5.36–5.38. Summarized and paraphrased; worked figures added. Full reference under Supplemental References.
Primary consolidation settlement S_c is governed by the compressibility of the clay skeleton as excess pore pressures dissipate. Three cases apply depending on the preconsolidation stress σ'_p:
Sc = [Cc / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_v0]
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | compression index | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
| e0 | void ratio | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| σ'v | vertical stress / pore pressure | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
Sc = [Cs / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_v0]
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| e0 | void ratio | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| σ'v | vertical stress / pore pressure | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
Sc = [Cs / (1 + e₀)] · H · log[σ'_p / σ'_v0]
+ [Cc / (1 + e₀)] · H · log[(σ'_v0 + Δσ) / σ'_p]
Where:
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | compression index (dimensionless) | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
| Cs | swell/recompression index ≈ C_c/5 to C_c/10 (dimensionless) | Lab test | Unload–reload slope of the e–log σ' curve (ASTM D2435). Screening: Cr ≈ Cc/5 to Cc/10. | 0.01–0.08 (inorganic clays) · by USCS group |
| e₀ | initial void ratio (dimensionless) | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| H | layer thickness (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| σ'v0 | initial effective vertical stress at midpoint of layer (psf) | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
| σ'p | preconsolidation stress (psf) | Lab test (or correlation) | Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0. | OCR 1 (NC) to > 4 (heavily OC) · by USCS group |
| OCR | preconsolidation stress / OCR = σ'_p / σ'_v0 | Lab test (or correlation) | Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0. | OCR 1 (NC) to > 4 (heavily OC) · by USCS group |
| Δσ | stress increase at midpoint of layer from applied load (psf) | Another equation | Stress increase from the applied load: Boussinesq influence factor or 2:1 distribution (settlement chapter), or the track load-spread equations. | project-specific |
Cc = 0.009 · (LL − 10)
Where LL = liquid limit (%). Valid for normally consolidated clays; use with caution for organic soils. For railroad projects, laboratory consolidation tests (ASTM D2435) should support any embankment over about 6 ft high on soft clay.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | compression index = 0.009 · (LL − 10) | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
| LL | liquid limit (%) | Lab test | Atterberg limits (ASTM D4318) on the minus No. 40 fraction. | CL 20–50, CH 50–110 · by USCS group |
e₀ = (Gs · γ_w / γ_d) − 1
Where G_s = specific gravity (≈ 2.70 for most clays), γ_d = dry unit weight (pcf), γ_w = 62.4 pcf.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| e₀ | void ratio = (Gs · γ_w / γ_d) − 1 | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| Gs | specific gravity (≈ 2.70 for most clays), γ_d = dry unit weight (pcf), γ_w = 62.4 pcf. | Lab test | Specific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested. | 2.64–2.80 mineral; lower if organic · by USCS group |
| γd | dry unit weight | Lab or field test | Lab: ASTM D7263 on tube samples. Field: nuclear gauge (ASTM D6938), sand cone (D1556) or drive cylinder (D2937). Or γd = γ/(1 + w). | sands 90–125, clays 80–115 pcf · by USCS group |
When a compressible layer is thick (> 5 ft) or when the stress increase varies significantly with depth, the layer should be divided into sublayers of 2–4 ft thickness. Settlement is computed for each sublayer at its midpoint stress state, then summed:
Sc,total = Σ [Cc,i / (1 + e₀,i)] · Hi · log[(σ'_v0,i + Δσ_i) / σ'_v0,i]
Use this sublayer approach for clay layers thicker than about 10 ft, where ignoring stress variation underestimates settlement at the top of the layer and overestimates at depth.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | compression index | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
| e0 | void ratio | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| σ'v | vertical stress / pore pressure | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
Organic soils can compress by up to about 40% (12 ft of peat can mean 5 ft of settlement). Muskeg also punches under load, and buried corduroy decays. At one Canadian swamp crossing, years of swamp ties never stopped the settlement; only a proper berm, together with draining the water driving the movement, solved it. At a peat site in northern Alberta, 400 ft of differential settlement into deep peat needed piles. In 2016 dollars, swamp ties cost about $670,000 per mile, against about $280,000 per mile for undercutting and about $6.7 million per mile for new track (course figures of $600,000, $250,000 and $6,000,000 in 2012 dollars, escalated by the ENR Construction Cost Index; see Chapter 7.2, Table 7.2-6), so diagnosing the mechanism early is the cheapest option.


After Geotechnology for Railroaders Program, Module 2, Module 6.1, Module 6.2; Module 2 §08; Module 6.1 §03; Module 6.2 §01, §05. Full reference under Supplemental References.
The USACE manual Settlement Analysis (EM 1110-1-1904) gives the standard one-dimensional procedure: divide the compressible layer into sublayers, compute the initial effective stress and the stress increase in each, and sum the settlement using the recompression and virgin compression indices on either side of the preconsolidation pressure. Railroad fills are a near-ideal case for this method: a widening for a siding or a raise in grade is wide compared with the clay thickness, so the stress increase is nearly uniform with depth and lateral strain is small.
Equation 6.2-20. Primary consolidation settlement of a sublayer
using only the first term when σ'v0 + Δσ ≤ σ'p.
Equation 6.2-21. Time rate (Terzaghi theory)
t50 = 0.197 Hdr²/cv; t90 = 0.848 Hdr²/cv
| Soil | Cc |
|---|---|
| Clays | 0.01(LL − 13); 0.012 wn; 1.15(e0 − 0.35) |
| Soils of sensitivity below 4 (Terzaghi and Peck relation) | 0.009(LL − 10) |
| Organic soils, peat | 0.0115 wn |
| Varved clays | (1 + e0)[0.1 + 0.006(wn − 25)] |
| Uniform silts | 0.20 |
| Uniform sand, loose / dense | 0.05 to 0.06 / 0.02 to 0.03 |
Use correlations for planning only; design values come from oedometer tests on undisturbed samples (Chapter 5.2).
| Input | Value | Result | Value |
|---|---|---|---|
| Fill load q (10 ft at 125 pcf) | 1,250 psf | Primary settlement Sc | 15.34 in. |
| Clay: top at 4 ft, thickness, water depth | 18 ft, 3 ft | Time to 50% consolidation | 6.5 months |
| e0, Cc (LL = 58), Cr, OCR | 1.20, 0.45, 0.06, 1.2 | Time to 90% consolidation | 28.2 months |
| cv, drainage | 0.08 ft²/day, double | Secondary compression, 25 years | 1.88 in. |
| Cα | 0.018 | Total | 17.22 in. |
A foot of settlement taking several years to complete is typical of new fill on lake-plain and coastal clays. Under track it shows up as repeated surfacing and a dip at the transition to the old embankment. The options are covered in Chapter 7.2: surcharge with or without wick drains (which shorten Hdr, cutting t90 roughly with its square), lightweight fill, or staged construction with monitoring (Chapter 5.3).
Open the settlement calculator →
Sublayered consolidation settlement under a wide fill or a footing (2:1), time to 50% and 90% consolidation, secondary compression, and a settlement-time curve.
These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.
Track and embankment projects often have many SPT or CPT soundings and only a few consolidation tests. The correlations below spread the consolidation results along the alignment. Calibrate each one against the site’s own oedometer tests before using it for design.
mv from SPT N and PI (Stroud and Butler 1975). For overconsolidated clays, stiff insensitive clays and soft rocks, the coefficient of volume compressibility falls with blow count and plasticity. The published chart is fitted by:
1 / (mv N) = 1,170 / PI2.07 + 9.1 (ksf)
so that mv (ft²/kip) = 1 / [N × (1,170/PI2.07 + 9.1)]. In SI the fit is 56,000/PI2.07 + 435 kPa. It is widely used for normally consolidated soils as well, but it was derived for overconsolidated soils and is unlikely to hold for soft clays.
| PI | 10 | 15 | 20 | 30 | 40 | 60 |
|---|---|---|---|---|---|---|
| 1/(mvN), ksf | 19.0 | 13.4 | 11.5 | 10.1 | 9.7 | 9.3 |
| 1/(mvN), kPa | 912 | 641 | 549 | 484 | 462 | 447 |
Settlement from mv: S = mv Δσ H. With mv in ft²/kip, Δσ in ksf and H in ft, S is in feet.
mv from cone resistance (Meigh 1987). For normally consolidated and lightly overconsolidated clays and silts up to firm consistency, with qc up to about 25 ksf (1.2 MPa):
mv = 1 / (α qc)
With qc in ksf, mv is in ft²/kip. The coefficient α depends on soil type and cone (Table 6.2-12).
| Soil (USCS) | α, electric (reference) cone | α, mechanical mantle cone |
|---|---|---|
| High-plasticity clays and silts (CH, MH) | 2.5–7.5 | 2–6 |
| Low and intermediate plasticity clays (CL), qc < 14.6 ksf | 3.7–10 | 3–8 |
| Low and intermediate plasticity clays (CL), qc > 14.6 ksf | 2.5–6.3 | 2–5 |
| Low and intermediate plasticity silts (ML) | 3.5–7.5 | 3–6 |
| Organic silts (OL) | 2.5–10 | 2–8 |
| Peat and organic clay (Pt, OH), w = 50–100% | 1.9–5.0 | 1.5–4.0 |
| Peat and organic clay, w = 100–200% | 1.25–1.9 | 1.0–1.5 |
| Peat and organic clay, w > 200% | 0.5–1.25 | 0.4–1.0 |
The British “intermediate plasticity” groups (CI, MI) fall within the USCS CL and ML groups. A lower α means a more compressible soil for the same cone resistance.
Field correction to oedometer settlement (Skempton and Bjerrum 1957). Oedometer settlements overestimate field settlement in overconsolidated clays, because the pore pressure set up under a real foundation is smaller than under one-dimensional loading. Very sensitive clays are the exception: there the oedometer can slightly underestimate. The consolidation settlement is corrected by a factor μ:
Sc,field = μ × Sc,oed
| Clay | H/b = 0.5 | H/b = 1 | H/b = 4 |
|---|---|---|---|
| Very sensitive clays (soft alluvial, estuarine, marine) | 1.0–1.1 | 1.0–1.1 | 1.0–1.1 |
| Normally consolidated clays | 0.8–1.0 | 0.7–1.0 | 0.7–1.0 |
| Overconsolidated clays | 0.6–0.8 | 0.5–0.7 | 0.4–0.7 |
| Heavily overconsolidated clays (glacial till, marl) | 0.5–0.6 | 0.4–0.5 | 0.2–0.4 |
For a compressible layer starting at depth z below a load of width B, take b ≈ B + z (load spread at 60°). μ applies to the consolidation settlement only, not to immediate or secondary settlement.
For railroad work: Under long embankments and track widenings, H/b is usually small, which gives the largest correction in overconsolidated clay. Use μ to explain why a stiff-clay foundation settled less than predicted, but do not use it to reduce settlement in soft, sensitive or normally consolidated clay, where μ is close to 1. Where the SPT or CPT correlations are used to extend a few oedometer tests along a line, plot the correlated mv against the oedometer values at the same depths. Adopt the correlation only if the two agree within about a factor of 1.5, and say in the report which settlements rest on a correlation (Example 6.2-8).
Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.1.4–5.1.5 and §5.5.1, Eqs. 5.19, 5.20, 5.39, Table 5.5, Figs. 5.3–5.5. Summarized and paraphrased; equations converted to US units. Full reference under Supplemental References.
A Class I railroad located in Iowa is adding a second main track on a new fill beside the existing embankment. The borings along the widening found 15 ft of stiff, overconsolidated lean-to-fat clay over dense sand. The SPT blow counts in the clay average N60 = 12, but no consolidation tests have been run yet. The engineer must estimate the settlement of the clay and how long it will take, to decide whether the new track can be surfaced at once or needs a waiting period.
| Variable | Value | Description |
|---|---|---|
| H | 15 ft | Clay thickness; sand below and fill above, so drained top and bottom |
| N60 | 12 | Average SPT blow count in the clay |
| PI, LL | 25, 45 | Plasticity index and liquid limit |
| Δσ | 1.10 ksf | Average stress increase at mid-layer under the new fill |
| b | 40 ft | Base width of the new fill |
| Stress history | Overconsolidated; final stress assumed below σ′p | Stiff clay |
(a) mv ≈ 0.0079 ft²/kip. (b) Oedometer-basis settlement 1.6 in. (c) Field settlement about 1.1 in. (d) cv ≥ 300 ft²/yr, so 90% consolidation in about 2 months or less. (e) If the new load takes the clay past its preconsolidation stress, consolidation slows to about 9 months and the settlement grows.
Settlement of about an inch over two months can be taken out by normal surfacing before the track is put to full speed. The answer rests on two things the SPT cannot confirm. First, the Stroud correlation was fitted to overconsolidated clays and is only reliable where that is true. Second, the time depends on whether the clay stays below σ′p. Both are settled by one or two consolidation tests on undisturbed samples from the widening; schedule them before the surfacing plan is fixed. If the tests show the clay is normally consolidated, μ rises toward 1, Cc governs, and a surcharge or waiting period (Section 6.2.8) may be needed. The differential between the new fill and the old embankment, which has finished settling, is what the track will feel, so check angular distortion at the transition (Section 6.2.7).
The degree of consolidation U (fraction of ultimate settlement completed at time t) is governed by the dimensionless time factor T_v:
Tv = cv · t / H_dr²
Where:
| U (%) | T_v (simplified) | T_v (exact) |
|---|---|---|
| 10 | 0.008 | 0.008 |
| 20 | 0.031 | 0.031 |
| 30 | 0.071 | 0.071 |
| 40 | 0.126 | 0.126 |
| 50 | 0.197 | 0.197 |
| 60 | 0.287 | 0.287 |
| 70 | 0.403 | 0.403 |
| 80 | 0.567 | 0.567 |
| 90 | 0.848 | 0.848 |
| 95 | 1.163 | 1.129 |
| 99 | — | 1.781 |
For U ≤ 60%:
Tv = π/4 · (U/100)² (simplified parabolic approximation)
For U > 60%:
Tv = −0.933 · log(1 − U/100) − 0.085
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Tv | intermediate value computed on this page | Another equation | Computed: Tv = cv · t / H_dr² | project-specific |
| cv | coefficient of vertical consolidation (ft²/day | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
| t | elapsed time (days) | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| Hdr | length of drainage path (ft): H_dr | Another equation | Computed: H_dr = H/2 for two-way drainage (sand above and below clay) | project-specific |
S(t) = U · Sc,total
t = Tv · H_dr² / cv
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| cv | coefficient of consolidation | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
| Soil Type | c_v (ft²/day) | c_v (ft²/year) | Notes |
|---|---|---|---|
| Soft organic clay | 0.0005–0.005 | 0.2–2 | Coastal Georgia; Manitoba |
| Soft marine clay | 0.005–0.05 | 2–18 | Tidewater Virginia; Northeast passenger corridor |
| Medium clay | 0.05–0.2 | 18–73 | Kansas and Nebraska |
| Stiff clay | 0.2–1.0 | 73–365 | Appalachian residual soils |
| Very stiff clay | 1.0–10 | 365–3,650 | Quick-draining; settle rapidly |
| Silty clay (CL-ML) | 0.1–0.5 | 37–183 | the Canadian Prairie provinces |
Multiplying path length squared by unit conversion: if c_v in ft²/day and H_dr in ft, time t is in days.
Before consolidation tests are available, the U.S. Navy chart of cv against liquid limit (NAVFAC DM-7, 1982) gives a first estimate of how fast a clay will drain. Carter and Bentley fitted its three trend lines with power functions that reproduce the chart within about 12% (cv in cm²/s, LL in %):
To convert cm²/s to ft²/yr multiply by 33,950 (to ft²/day, by 93).
| Liquid limit (%) | 30 | 40 | 50 | 60 | 80 | 100 |
|---|---|---|---|---|---|---|
| Recompression, lower limit | 1,470 | 480 | 200 | 99 | 32 | 14 |
| Virgin compression | 200 | 89 | 48 | 29 | 13 | 6.8 |
| Remolded, upper limit | 38 | 21 | 14 | 9.4 | 5.3 | 3.4 |
cv also depends strongly on structure, fissuring, sand partings and stress level, so the correlation gives only the likely order of magnitude. The virgin-compression values agree broadly with Table 6.2-4 for medium and stiff clays.
For railroad work: The roughly fivefold drop from the recompression to the virgin line is the important point. A fill that takes an overconsolidated clay past its preconsolidation stress both settles more and settles more slowly. Use the virgin line for preload and surcharge planning, and the remolded line for clay that has been disturbed by wick-drain installation (the smear zone, Section 6.2.8) or by construction traffic. Confirm the design cv with consolidation tests or CPTu dissipation tests, which also capture horizontal drainage through sand layers.
Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.2 and Fig. 5.7, after U.S. Navy (1982). Summarized; table values computed from the fitted equations and converted to ft²/yr. Full reference under Supplemental References.
Secondary compression occurs after primary consolidation is essentially complete (U ≈ 95–100%) as the clay skeleton continues to creep under sustained load. It is particularly significant for organic soils (Pt) and highly plastic clays (CH) — common in coastal Georgia swamps, Manitoba peatlands and Louisiana.
Ss = Cα / (1 + ep) · H · log(t₂ / t₁)
Where:
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cα | secondary compression index (dimensionless) | Lab test | Slope of e vs log time after primary consolidation in the consolidation test (ASTM D2435). | Cα/Cc 0.03–0.08 · by USCS group |
| ep | void ratio at end of primary consolidation (≈ e₀ − ΔeP for primary compression) | Another equation | e = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435). | sands 0.35–0.85, clays 0.5–2.0 · by USCS group |
| H | layer thickness (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| t₁ | time at end of primary consolidation (days) | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| t₂ | design service life or evaluation time (days) | Design criterion | Set by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification. | project-specific |
| Cc | compression index | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
Cα/Cc ≈ 0.04 ± 0.01 (for inorganic clays)
Cα/Cc ≈ 0.05 to 0.07 (for organic clays and peats)
For a 50-year railroad service life (t₂ = 18,250 days) with primary consolidation completing at t₁ = 500 days, log(18,250/500) = log(36.5) = 1.562. Even a modest C_α = 0.010 over a 10 ft clay layer produces S_s = 0.010/(1 + 1.8) × 10 × 1.562 = 0.056 ft = 0.67 in — significant on a Class 5 mainline with a 0.75 in. tolerance.
USACE EM 1110-1-1904 (Table 3-14, after Mesri) extends the ratios in Eq. 6.2-15 to other materials encountered on railroad alignments:
Table 12-S1. Ratio of secondary compression index to compression index
| Soil | Cα/Cc |
|---|---|
| Inorganic soils | 0.025–0.060 |
| Clay | 0.025–0.085 |
| Silt | 0.030–0.075 |
| Peat | 0.030–0.085 |
| Muskeg | 0.090–0.100 |
For a first approximation before tests are available, USACE (after NAVFAC DM-7.1) gives Cα ≈ 0.0001 wn for natural water contents 10–3,000%. The manual cautions that sample disturbance lowers the measured Cα in the virgin range and that secondary-compression predictions “have often not been reliable” — one more reason to confirm long-term behavior with settlement plates rather than rely on the calculation alone.
Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904
Lea and Brawner’s British Columbia highway experience gives practical guidance for the peat and muskeg crossings noted above:
Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board
A fill settles under its own weight as well as compressing the ground beneath it. A coarse fill compresses mostly as it is placed and then creeps at constant effective stress; a saturated clay fill first consolidates as construction pore pressures dissipate and then creeps (Skinner, 2012, Section 58.5, p. 905).
Equation 6.2-23. Creep compression rate of a fill
Skinner (2012), Eq. 58.2. Δs = settlement between times t1 and t2 after placement; H = fill thickness; α is a strain per log cycle of time.
| Fill | Compaction | α (% per log cycle of time) |
|---|---|---|
| Sandy gravel | Heavy vibrating roller | 0.04 σ′v |
| Mudstone | Heavy vibrating roller | 0.12 σ′v |
| Sandstone or mudstone rockfill | Heavy vibrating roller | 0.13 σ′v |
| Sandstone or mudstone rockfill | No systematic compaction | 0.9 to 1.5 |
| Stiff clay fill | Heavy systematic compaction | 0.5 |
Skinner (2012), Table 58.3, p. 905, from Charles and Watts (2001). For the first three rows σ′v is in MPa (1 MPa = 20.9 ksf); those rows come from embankment dam case histories.
Equation 6.2-24. Self-weight settlement of an embankment
Nowak (2012), Eq. 70.7, p. 1062, after Trenter (2001). D* = equivalent constrained modulus of the fill. For a 33-ft (10-m) embankment Charles (1993) gives D* of 50 for well-compacted sandy gravel and 6 for low-plasticity clay; Vol. II does not print the unit, and MPa (about 1,040 ksf and 125 ksf) gives strains consistent with the next sentence. Confirm against Charles (1993) before design use.
Charles (2008) reports self-weight settlement of less than 0.5% of the height for well-graded granular embankments and less than 1% for clay embankments (Nowak, 2012, p. 1062). Much of it happens during construction; the creep term is what continues under track.
A 25-ft embankment of stiff clay fill is built with heavy systematic compaction for a new connection track. Estimate the creep settlement between one year and 30 years after completion, and the self-weight settlement of the fill.
| Variable | Value | Description |
|---|---|---|
| H | 25 ft | Fill height |
| α | 0.5% per log cycle | Stiff clay fill, heavy compaction (Table 6.2-9) |
| t1, t2 | 1 yr, 30 yr | Period after completion |
| γ | 125 pcf | Fill unit weight |
| D* | 125 ksf | Low-plasticity clay fill (6 MPa) |
The creep settlement continues after the track is laid and is the part that needs a surfacing allowance. It adds to any consolidation of the foundation (Section 6.2.4.3 calculator).
Build the embankment early or surcharge it if the schedule allows, and plan for one or two surfacing cycles in the first years. Use a granular fill near structures, where its creep rate is an order of magnitude lower.
Open the consolidation settlement calculator →
Now adds fill creep and self-weight settlement to the foundation consolidation result.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
S_total = Si + Sc + Ss
α = (S_A − S_B) / L_AB
Where S_A and S_B are predicted settlements at two adjacent structures or reference points, and L_AB is the distance between them (ft). This manual recommends limiting angular distortion at bridge approach transitions to 1/500 for Class 4 track (Table 6.2-1).
Bridge Approach Transition: The most critical angular distortion check in railroad geotechnical practice is at the abutment–embankment interface. A rigid pile-supported abutment settling < 0.1 in. adjacent to an approach fill settling 3.0 in. over 30 ft produces α = 2.9/30 = 0.097 — far exceeding any FRA class limit. AREMA Chapter 8 addresses approach design; use an approach slab or engineered approach fill to limit this transition zone differential.
Repeated and dynamic loads. USACE EM 1110-1-1904 notes that loose sands compact under vibration and that this is a major cause of differential settlement. Cohesionless soils with Dr above about 75% should not settle significantly, although intense dynamic loading can still compact dense sand by 1–2% of the stratum thickness. Dynamic settlement may be insignificant if the combined static and dynamic bearing stress stays below one-half of the allowable bearing capacity. Errors in dynamic-settlement predictions can be 50% or more. For clays under repeated deviator stress (0.1–10 Hz, a typical range for traffic), the manual gives a creep-strain-rate formulation from cyclic triaxial tests but warns it may underestimate settlement because traffic loading is more complex than repeated vertical load.
Collapsible soils. Loess, some alluvial fans and cemented silts lose their bonded structure on wetting. Typical collapsible soils are light-colored, LL < 45, PI < 25, with dry unit weight 65–105 pcf; collapse rarely occurs below 40% porosity. USACE notes that dynamic loading can also break the bonds, “particularly important for roads, airfields, railways.”
Table 12-S2. Wetting that can trigger collapse (EM 1110-1-1904, Table 5-4, condensed)
| Type of wetting | Railroad example | Result |
|---|---|---|
| Local, shallow | Blocked ditch, leaking pipeline crossing | Settlement in the upper layer within the wetted area |
| Intense local | Industry effluent, broken water main, irrigation | Can saturate the whole collapsible zone in < 1 year; uneven, damaging settlement |
| Slow, uniform groundwater rise | Reservoir or regional water table rise | Uniform, gradual settlement |
| Slow increase in water content | Reduced evaporation under a paved yard or slab | Incomplete, progressive settlement |
Collapse potential CP (Jennings and Knight, 1975) is the strain on flooding a consolidometer specimen at 2 tsf: 0–1% negligible, 1–5% moderate trouble, 5–10% trouble, 10–20% severe trouble, > 20% very severe trouble. For design, load the specimen to the anticipated field stress and then inundate it (ASTM D4546, Method B); settlement = [(eo − ec)/(1 + eo)]H. USACE cautions that lab tests can miss soil that later collapses in the field, and the amount depends on how far the wetting front travels — so drainage control is part of the design.
Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904
Geometry limits put a practical ceiling on differential settlement under track. European intervention limits for the longitudinal (surface) defect on a 33-ft chord range from about 0.35–0.47 in. at 87–99 mph to 0.55–0.83 in. below 37 mph (Chapter 2.1, §2.1.11). Emergency speed restrictions begin at 0.71 in.. Because the chord is short, these are effectively limits on settlement differences over about 33 ft. Embankment, culvert and transition settlement predictions should be checked against that scale, not only against total settlement.

After any surfacing, defects grow quickly up to about 2 million tons of traffic and then slowly, roughly with log T, at a rate (0.079–0.24 in. per decade of traffic) that depends mainly on subgrade quality (Chapter 3.8, §3.8.14).
After Profillidis (2014), §16.3, §16.6–16.7, Fig. 16.2. Full reference under Supplemental References.
Components. Total settlement is the sum of three parts:
On new track, more than half comes from the ballast. After each tamping the ballast share grows again, because the loosened top ballast starts over.
Use a power law, not a semilog fit. Settlement after N load cycles fits SN = S1 Nb, with b typically 0.10–0.18. A semilog fit increasingly underpredicts at large N, and so overestimates the time to the next surfacing.
Load cycles per MGT. Cm = 106 ÷ (Aa × Na), where Aa is axle load in tons and Na is axles per load cycle. Use Na = 2 per car for ballast. For example, a 39-ton axle gives about 12,800 cycles per MGT.
| Layer | Relation | At 100 MGT |
|---|---|---|
| Top 12 in. of ballast (strain) | ε = 0.026 T0.21 | ε ≈ 0.068 → 0.8 in. |
| Subballast (strain) | ε = 0.017 T0.16; about 2.6 × 10−5 per MGT beyond ~150 MGT | ε ≈ 0.036 |
| Subgrade, top 10 ft of moist fine silty sand | S (in.) = 0.039 T0.37 (typical); 0.054 T0.52 (worst section) | ≈ 0.2 in. (typical) |
| Subgrade, long term | 0.001–0.0026 in. per MGT, linear beyond ~50 MGT | — |
The authors evaluated the 100 MGT column from the relations. Rapid compression occurred through the first ~3 MGT, then continued at a slower rate.
Lift and settlement. After a low lift, the track settles back by about the amount it was lifted within roughly a year, so the change does not last. Lifts above about 1 in., which exceed the ballast D50, leave a residual lift. Allow about 0.16 in. of settlement even at zero lift, from wear and compaction.
After Selig & Waters (1994), chs. 8 and 15. Full reference under Supplemental References.
Sewer, water, transit and utility tunnels are often driven beneath operating track. The empirical method of Peck (1969) describes the settlement trough across a single tunnel in open ground as a normal (Gaussian) curve (Aversa et al., in Feng 2017):
Eq. 6.2-27: w(x) = w0 exp(−x2 / 2i2), where x = horizontal distance from the tunnel centerline.
Eq. 6.2-28: w0 = 0.313 V′ D2 / i, where D = tunnel diameter and V′ = volume loss, the trough volume as a fraction of the excavated area πD2/4 per unit length.
Eq. 6.2-29: i = K z0, where i = distance from the centerline to the inflection point of the trough and z0 = depth to the tunnel axis.
| Ground and method | Volume loss V′ | K |
|---|---|---|
| Open face in stiff clay | 1–2% | 0.4–0.6 (fine-grained soils) |
| Sprayed concrete lining (sequential excavation) in clay | 0.5–1.5% | 0.4–0.6 |
| TBM in sand | under 0.5% | about 0.25–0.45 (granular soils) |
| TBM in soft clay | 1–2% | 0.5 or more |
| Mixed soil and rock face | 0.5–0.8% | 0.3–0.7 |
| Discontinuous or weak rock | under 0.2–0.6% | 0.5 to above 0.7 |
Ground over a TBM settles in stages: ahead of the face, over the shield, at the tail as the annular gap closes, and over time as clay consolidates. Good face pressure and prompt tail grouting keep V′ at the low end of the table. A second, parallel tunnel generally causes more volume loss than the first.
A city is driving a 12-ft diameter sewer tunnel with an earth pressure balance TBM under a two-track main line of a Class I railroad located in Ohio. The tunnel crosses square to the tracks with its axis 36 ft below top of rail, in stiff clay. The railroad requires a prediction of the settlement of the track profile and will set monitoring triggers from it. The engineer must predict the trough for the design volume loss and for poor face control.
| Variable | Value | Description |
|---|---|---|
| D | 12 ft | Excavated tunnel diameter |
| z0 | 36 ft | Depth to tunnel axis below top of rail |
| K | 0.5 | Trough width parameter, stiff clay (Table 6.2-10) |
| V′ | 1.0% (design); 2.0% (poor face control) | Volume loss |
| Chord | 62 ft | Chord used for track profile (surface) measurement, centered over the tunnel |
(a) i = 18 ft. (b) w0 ≈ 0.30 in. (c) M ≈ 0.23 in. on a 62-ft chord. (d) w0 ≈ 0.60 in. and M ≈ 0.46 in.
Most of the trough (to about 2.5i, or 45 ft, either side) falls within a few rail lengths, so the track sees a short, sharp dip rather than a uniform drop. Both tracks settle about equally because the tunnel is square to them, so cross-level is not affected. On a skewed crossing it would be. Set the railroad’s monitoring triggers from this prediction: for example, review at half the predicted design settlement, and stop the TBM and resurface the track at the design value. Survey the rails before the TBM reaches about 2 to 3 tunnel diameters from the track, then at least daily while the face is within that distance on either side, and afterward until the readings stabilize. Clay continues to consolidate after the TBM passes, so plan follow-up surfacing. Have a tamper and crew on call during the crossing.
For railroad work: Ask the tunnel designer for the predicted trough, the assumed volume loss and the face pressure plan before the railroad agreement is signed. Require monitoring of the rails and of points on the shoulder at the tunnel centerline and at i, 2i and 3i either side, with readings tied to the TBM face position. Slow or stop the drive if the readings approach the triggers. Where track or a bridge foundation lies over a weathered rock or mixed face, volume loss can vary along the drive, so use the upper end of the range for the crossing.
Source: Aversa, Bilotta, Ferrero and Migliazza, “Settlements induced by TBM excavation,” in Feng (ed.) (2017), Ch. 23, summarizing Peck (1969), O’Reilly and New (1982), Mair and Taylor (1997) and Chiriotti et al. (2001). Summarized and paraphrased; units converted. Full reference under S11.
When predicted settlement S_c exceeds the client's allowable limit, preloading with temporary surcharge fill is the most cost-effective mitigation. The concept: apply a surcharge load greater than the permanent design load, allow consolidation to occur before track placement, then remove the surcharge and install track on a pre-compressed subgrade.









σ'_v0 + Δσ_p + Δσ_s = σ'_v0 × 10^[S_target(1 + e₀)/(C_c H)], where S_target = primary settlement plus expected secondary compression under the permanent load, and Δσ_s is the required surcharge (NC clay)
A simplified approach: select q_surcharge such that primary consolidation under q_surcharge equals the sum of primary consolidation + secondary compression expected under q_permanent over the service life. Make this calculation for bridge approach fills where predicted settlement exceeds about 2 in.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Cc | compression index | Lab test | Slope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10). | CL 0.10–0.40, CH 0.35–0.90 · by USCS group |
t_surcharge = 0.848 · H_dr² / cv
If t_surcharge is prohibitively long (> 6–12 months on a construction schedule), prefabricated vertical drains (PVDs) are combined with the surcharge to accelerate drainage — addressed in Chapter 7.2 (Ground Improvement).
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| cv | coefficient of consolidation | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
Lea and Brawner’s case histories from the Vancouver area test the assumptions behind Eq. 6.2-18 and 6.2-19:
Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board
When surcharge time is not available, or added fill would cause a stability failure, the alternative is to reduce Δσ itself. Three generations of lightweight fill appear in the library:
Table 12-S3. Lightweight fill options
| Material | Key properties | Design notes |
|---|---|---|
| Sawdust (historic; Trans-Canada Highway, Burnaby) | 3–12 ft thick; compressed to 80–90% of placed thickness under about ½ tsf preload; lab φ = 50° | Rots and can spontaneously combust above the water table, so the top must end up below groundwater after settlement. Settlement had to be predicted accurately to place it at the right grade. |
| Expanded shale, clay or slate (ESCS) lightweight aggregate | Kiln-expanded at 1,900–2,200°F; relative density 1.3–1.6 vs. 2.6–3.0 for normal aggregate (about half the mass per volume); AASHTO M 195 gradations | Open-graded; still needs compaction (lifts ≤ 12 in. loose with vibratory roller). Density control by a one-point Proctor (modified ASTM D698) plus a method spec. |
| EPS geofoam (ASTM D6817) | EPS 15 / 19 / 22 / 29: minimum density 0.90 / 1.15 / 1.35 / 1.80 pcf; compressive resistance at 10% strain 10.2 / 16.0 / 19.6 / 29.0 psi | “Zero net load”: excavate native soil equal in weight to the geofoam plus everything placed on it. It can also replace the active wedge behind an abutment. |
Case: US 17 / SC 707, Myrtle Beach, SC. At the nearby Fantasy Harbour project, embankments 10–42 ft high had settled 9 to 67 in. For the US 17 / SC 707 interchange, bridge approach fills over 30–60 ft of soft to firm clay and loose, liquefiable sands were estimated to settle 78 in. at the abutment if built with normal-weight fill (120 pcf). The design combined LWA borrow to cut the magnitude, PVDs with granular surcharge to speed it, and deep soil mixing for seismic slope stability and abutment performance.
Railroad cautions (engineering judgment, not from the sources): lightweight fills must be covered by enough ballast, subballast and soil to spread axle loads and resist buoyancy at flood stage. Geofoam must be protected from petroleum spills (hydrocarbon-resistant membrane) near fueling or derailment-prone areas. Confirm dynamic stiffness under E-80 loading before using any lightweight fill directly under track.
Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board · Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co. · Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)

Levy (2010) explains, from the owner’s side, how changes interact with the contractor’s critical path method (CPM) schedule. The critical path moves as the job proceeds, and a delay to one critical task can cascade into later tasks and push out the completion date. When a change may affect time, owners face the question of whether the delay is real. Levy advises settling time when the change is priced, not later, because once unrelated contractor delays accumulate it becomes hard to separate them from the change. Extended time matters because general conditions costs (supervision, trailers, utilities, rentals) continue, and he cites $20,000 to $40,000 per month as a typical range.
Where time cannot be agreed, he suggests two approaches: issue the change with a statement that the work proceeds while the owner reserves the right to challenge any time extension, or sign the cost proposal provisionally, reserving the right to challenge both cost and time. Change-order forms often require checking whether the change increases, decreases or does not affect the contract end date, and owners should read that box before signing.
On float, Levy notes that schedules carry a cushion of extra days for weather, late equipment or short crews. Unless the contract says otherwise, that float belongs to the contractor. If the owner wants float for its own contingencies, such as late delivery of owner-furnished items, it must reserve it in the contract; otherwise an owner-caused delay that consumes the contractor’s float can become a claim.
For railroad work: Preload and surcharge programs for embankment widening or approach fills put a waiting period directly on the critical path, and its true length depends on measured consolidation rather than on the design estimate. Specify in the contract who owns float in the hold period, how the hold may be extended or shortened on the basis of settlement plate and piezometer data, and how extended time will be paid. Write the decision rule (for example, release when the monitored settlement rate falls below a stated value) into the special provisions so that a longer hold is a defined outcome rather than a dispute.

Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 215–216. Summarized and paraphrased. Full reference under Supplemental References.
Where a new track, siding or yard sits on soft clay, the cheapest way to avoid years of resurfacing is often to make the clay settle before the track goes down. A surcharge, extra fill above the final grade, is placed over the permanent fill. It speeds consolidation, and it is removed once the settlement the permanent load would eventually cause has occurred. Das's Advanced Soil Mechanics (Section 11.7, after Johnson) gives the design. To be safe, the degree of consolidation is taken at mid-depth of the drainage path, not as an average. If the surcharge comes off when only the average has been reached, the clay near mid-depth keeps settling while the clay near the drainage boundaries swells. Where wick drains are used (Chapter 7.2), Das replaces the mid-depth value with the average degree of consolidation for combined drainage.
Equation 6.2-22. Degree of consolidation needed under permanent load plus surcharge (Das Eq. 11.25)
σs/σf = [(1 + σf/σ′0)1/U − 1]/(σf/σ′0) − 1; t = TvH2/cv
Das reads U from a chart; the calculator computes it from the Terzaghi series at mid-depth and solves Equation 6.2-22 directly for the surcharge ratio. For Das's Example 11.7 the calculator gives Tv = 0.497, U = 62.7% and σs/σf = 1.11. That example is 15 ft (4.5 m) of normally consolidated clay under 5 ft (1.5 m) of sand, a 1,210 psf (58 kPa) permanent load and six months available. Das, reading his charts, gets Tv = 0.497, U ≈ 0.62 and σs/σf = 1.17. The 5% difference in surcharge comes from reading the charts.
| Quantity | Das | Calculator |
|---|---|---|
| σ′0 at clay mid-depth | 47.17 kPa (985 psf) | 985 psf |
| Tv for 6 months | 0.497 | 0.497 |
| U(f+s) at mid-depth | ≈ 0.62 (chart) | 0.627 |
| σs/σf | 1.17 (chart) | 1.11 |
| Surcharge σs | 67.86 kPa (1,417 psf) | 1,345 psf |
Applied to a siding on Das's profile, the permanent load of 1,211 psf would cause about 9.2 in. of primary settlement. To take all of it out in six months without drains takes a surcharge of 1,345 psf, about 11.2 ft of extra fill. The surcharge comes off when the settlement plates read 9.2 in., not on a calendar date. If that much fill would make the embankment unstable, combine a smaller surcharge with wick drains, or build in stages (Chapter 2.5).
Open the precompression surcharge calculator →
Effective stress at clay mid-depth, degree of consolidation in the time available (mid-depth or average), the surcharge ratio and fill height to remove primary settlement, and the settlement to wait for before removal.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.
| Boring | Sample | Depth (ft) | USCS | LL (%) | PI | e₀ | C_c | C_s | C_α | c_v (ft²/day) | OCR | σ'_p (psf) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B-01 | S-3 | 8–10 | CH | 72 | 45 | 1.82 | 0.56 | 0.07 | 0.022 | 0.0032 | 1.0 | 820 |
| B-01 | S-5 | 14–16 | CH | 68 | 41 | 1.71 | 0.52 | 0.065 | 0.021 | 0.0051 | 1.1 | 1,080 |
| B-02 | S-3 | 8–10 | OH | 105 | 63 | 2.45 | 0.88 | 0.11 | 0.062 | 0.0018 | 1.0 | 750 |
| B-02 | S-5 | 14–16 | CH | 74 | 47 | 1.88 | 0.59 | 0.074 | 0.024 | 0.0028 | 1.0 | 1,040 |
| B-03 | S-4 | 11–13 | CL | 48 | 25 | 1.35 | 0.31 | 0.039 | 0.012 | 0.0120 | 1.4 | 1,750 |
| B-03 | S-6 | 18–20 | CH | 69 | 43 | 1.77 | 0.53 | 0.066 | 0.021 | 0.0044 | 1.0 | 1,500 |
Design values selected: C_c = 0.56 (average CH); C_s = 0.07; C_α = 0.022; c_v = 0.004 ft²/day; e₀ = 1.82; one-way drainage to the surface (rock below the clay); H_dr = clay thickness.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

A new siding on a Class I railroad located in coastal Georgia (Brunswick) puts 10 ft of fill on 14 ft of soft, normally consolidated fat clay over rock. The example estimates how much the clay will compress, how long it will take with drainage only upward, and how much secondary compression follows, and compares the post-construction settlement with the limit for the track.
| Variable | Value | Description |
|---|---|---|
| Fill | H = 10 ft; γ = 120 pcf; B = 40 ft at base | |
| Clay | 14 ft CH; Cc = 0.56; e0 = 1.82; cv = 0.004 ft²/day; Cα = 0.022; γ = 110 pcf | On rock: one-way drainage, Hdr = 14 ft |
| zw | 2 ft below original ground | |
| Limit | 1.0 in. post-construction (assumed, Class 4) | |
| Wick drains | Assumed to finish primary at t1 = 180 days | |
| Service | 50 years |
Primary settlement is about 17 in., which would take over a century to finish with drainage to one face. Even with wick drains finishing primary in 180 days, about 4.6 in. would remain after construction against a 1.0-in. limit.
Wick drains change the time, not the amount. The options are a surcharge preload that drives primary consolidation past the final load before track is laid, accepting the secondary settlement as maintenance, or column support (deep soil mixing or rigid inclusions) that bypasses the clay (Chapter 7.2). The 2:1 stress at mid-clay is used here as a conservative centerline value; a full analysis divides the clay into sublayers.
A bridge approach fill on a Class I railroad located in southern Manitoba sits on soft, normally consolidated silty clay drained by sand above and below. The question is how long a preload must stay in place for the remaining settlement to be within the allowable after track is laid.
| Variable | Value | Description |
|---|---|---|
| Fill | 18 ft; Δσ = 1,440 psf at mid-clay | |
| Clay | 20 ft CL-ML; Cc = 0.35; e0 = 1.25; cv = 0.08 ft²/day; γsat = 115 pcf | Two-way drainage, Hdr = 10 ft |
| zw | At the original ground surface | |
| Limit | 1.5 in. residual (assumed) | |
| Drains option | 5-ft triangular spacing; de = 5.25 ft |
Primary settlement is about 21 in. The preload must reach 93% consolidation, which takes about 3.4 years with the natural drainage, or roughly 3 months with wick drains at 5-ft spacing.
The drain estimate is a rough analogy that ignores smear and well resistance; design the drains with Barron and Hansbo radial theory (Chapter 7.2). Tell the railroad’s project engineer the timeline early, and confirm it in the field with settlement plates at about 500-ft intervals read monthly: the plates, not the calculation, decide when the preload comes off.
A crane rail pavement slab for an intermodal expansion on a Class I railroad located in Kansas City sits on stiff, overconsolidated fat clay. Because the new stress stays below the preconsolidation stress, only the stiff recompression branch is used, and the secondary compression ratio must match that branch too.
| Variable | Value | Description |
|---|---|---|
| Δσ | 800 psf | Net load from slab and crane |
| Clay | 12 ft CH; Cc = 0.42; Cs = 0.05; e0 = 0.88 | |
| σ′v0, σ′p | 1,850 and 4,200 psf | OCR = 2.27 |
| cv | 1.0 ft²/day (assumed); Hdr = 6 ft | |
| Cα/Cr | 0.04 | Mesri, recompression range |
| Limit | 0.125 in. per 20 ft differential (assumed) | Crane rail |
Primary settlement 0.60 in., essentially complete within about a month; secondary about 0.4 in. over 50 years; about 1.0 in. in all.
The primary settlement can be taken out before the crane rail is set. The long-term part is small and nearly uniform in a uniform layer, so the differential depends on lateral variation in the clay between borings; check it against the 0.125 in. per 20 ft limit and provide rail adjustment in the crane rail design. Ground improvement is not needed for settlement alone.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
Checklist · Part VI · Geotechnical Analysis
Pre-Analysis
Settlement Computation
Time-Rate Analysis
Deliverables
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
A spread footing for a new railroad maintenance building at a Class I yard will add stress to a 10-ft layer of normally consolidated soft clay with the properties shown. The engineer must estimate the consolidation settlement and compare it with the settlement the adjacent Class 4 track can tolerate.
| Variable | Value | Description |
|---|---|---|
| H | 10 ft | Clay layer |
| Cc, e0 | 0.45; 1.60 | |
| σ′v0 | 500 psf | Mid-clay |
| Δσ | 1,200 psf | Mid-clay |
Sc ≈ 11 in.
That is eleven times the 1.0-in. Class 4 limit of Table 6.2-1; ground improvement or a deep foundation is required.
A new embankment for a railroad yard expansion will sit on 15 ft of normally consolidated silty clay drained at top and bottom. The railroad wants to know how long it must wait before laying track. The engineer must compute the time to 90% consolidation without drains and with wick drains at the spacing shown.
| Variable | Value | Description |
|---|---|---|
| H | 15 ft, two-way drainage | Hdr = 7.5 ft |
| cv | 0.10 ft²/day | |
| Drains | 4.0-ft triangular; de = 4.2 ft | ch ≈ 2cv = 0.20 ft²/day |
About 477 days (1.3 years) without drains and about 19 days with them, roughly 25 times faster.
The drain estimate ignores smear and well resistance, which slow radial drainage; design with Barron and Hansbo (Chapter 7.2). The comparison shows why drains are specified whenever track must go on within 60 to 90 days of fill completion.
An embankment for a new railroad grade separation will load an overconsolidated clay past its preconsolidation stress. Laboratory tests gave the compression and swelling indices, void ratio and stresses shown. The engineer must compute the consolidation settlement and identify which settlement equation applies.
| Variable | Value | Description |
|---|---|---|
| H | 8 ft | |
| Cc, Cs, e0 | 0.38; 0.048; 0.95 | |
| σ′v0, σ′p | 1,200 and 2,800 psf | |
| Δσ | 2,000 psf |
Sc ≈ 1.95 in., from Eq. 6.2-7.
Missing the overconsolidation would have overestimated the settlement fourfold and could have triggered ground improvement that was not needed.
A pile-supported railroad bridge abutment does not settle, but the approach fill behind it has settled 1 to 3 in. within 30 ft and the track shows a dip at the bridge end. The engineer must explain why angular distortion, rather than total settlement, governs the approach and state the limit used for Class 4 track.
| Variable | Value | Description |
|---|---|---|
| Abutment | Pile supported; settlement ≈ 0 | |
| Approach fill | 1 to 3 in. within 30 ft | |
| Limit | 1/500 for Class 4 track | Table 6.2-1 |
Because the rail responds to the rate of elevation change, not the total. This manual limits approach distortion to 1/500 for Class 4 track, about 0.6 in. over 25 ft.
Approach slabs, sleeper slabs and geosynthetic-reinforced approach zones spread the change over a longer distance; AREMA Chapter 8 approach slab design should be cross-referenced whenever the predicted embankment settlement at the abutment exceeds 0.5 in.
A passenger corridor is adding a track on a new embankment over soft clay, and the railroad (assumed) allows only 0.375 in. of primary settlement after the track is laid. The predicted primary settlement is 8.0 in. The engineer must find the degree of consolidation required before track laying and the time to reach it with and without wick drains.
| Variable | Value | Description |
|---|---|---|
| Sc | 8.0 in. | Primary |
| Ss | 1.5 in. over 50 years | Handled by maintenance |
| Limit | 0.375 in. residual primary (assumed) | |
| cv, Hdr | 0.006 ft²/day; 12 ft | |
| Drains | Effective path 1.5 ft; ch ≈ 0.012 ft²/day |
U must reach 95.3%. That takes about 76 years with natural drainage, which is infeasible, and about 7 months with wick drains.
High-speed track leaves almost no room for residual settlement, so drains, a surcharge to speed the last few percent, and settlement plates to prove it are normally all required.
A Class I railroad located in Mississippi is building a siding extension on an embankment over 50 ft of soft clay underlain by clean sand, which drains the clay from below. Vertical drains on a 4.5-ft triangular pattern are specified over a 2,000-ft by 100-ft area. The contractor asks whether the drains really need to reach the sand. The engineer must find the optimum unimproved thickness at the bottom of the clay and the drain length it would save.
| Variable | Value | Description |
|---|---|---|
| H | 50 ft | Clay thickness, drained top and bottom |
| s | 4.5 ft triangular | Drain spacing |
| dw | 0.196 ft | Equivalent drain diameter |
| ds/dw, kh/ks | 4 and 3 | Smear zone size and permeability ratio |
| ch/cv | 2 | |
| Area | 2,000 ft × 100 ft | Treated area |
(a) μ ≈ 5.2. (b) Hc ≈ 3.8 ft. (c) About 43,000 linear feet of drain.
Stopping the drains about 4 ft above the sand gives almost the same overall rate of consolidation as full penetration, because the bottom 4 ft drains quickly into the sand. The saving is about 8% of the drain length. Confirm the sand is continuous and free-draining with the borings or CPTs (a clay lens in the sand changes the answer), and if vacuum is added later, the drains must stop short of the sand anyway so the vacuum does not leak into it (Section 6.2.18).
| Topic | Chapter |
|---|---|
| SPT N₆₀ for E_s estimation in granular soils | Chapter 4.1 |
| CPTu and DMT for E_s, M, and OCR estimation in clay | Chapter 5.1 |
| Atterberg limits for C_c estimation (Skempton) | Chapter 2.2 |
| Groundwater and effective stress; seasonal WT variation | Chapter 2.8 |
| Bearing capacity (companion to settlement) | Chapter 6.1 |
| Slope stability of consolidating embankments | Chapter 6.3 |
| Seismic-induced settlement in granular soils | Chapter 6.5 |
| PVD and surcharge preloading design | Chapter 7.2 |
| Bridge approach settlement mitigation | Chapter 7.1 |
| Subgrade deformation under repeated train loading | Chapter 2.3 |
| Settlement plate monitoring and inclinometer readings | Chapter 5.3 |
| Settlement analysis documentation in geotechnical reports | Chapter 8.4 |
| Consolidation test (ASTM D2435) data and quality checks | Chapter 5.2 |
End of Chapter 6.2 — Settlement Analysis
Primary source: USACE EM 1110-1-1804, Geotechnical Investigations (January 2001). Settlement equations follow Terzaghi (1943), Skempton (1944), Mesri & Godlewski (1977), and FHWA GEC No. 5. FRA geometry tolerances per 49 CFR Part 213; AREMA MRE Chapter 8.
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S8 under Supplemental References.
Related section: 6.2.3 Immediate (Elastic) Settlement
Look found that 127 pcf is used in about 70% of reports for fill unit weight. Compaction records give a large, cheap dataset to check it, and they are rarely used for that. On a Southeast Queensland project, 5,644 density tests had a 10% lower bound of 126 pcf, a median of 134 pcf and a 10% upper bound of 140 pcf. On a North Queensland road, imported fill mostly fell between 135 and 148 pcf, median 141.
On that second job the heavier fill caused more elastic settlement of a high embankment on competent ground than the bill of quantities had allowed for, and a contractual claim followed. Using the as-built 146 pcf instead of 127 pcf gives about 15% more fill settlement. Look’s suggested unit weights for well-compacted fill:
For railroad work: rail embankments are often high and wide, so a 15% settlement difference becomes a real quantity of fill to pay for. Feed the density test results back into the settlement and stability checks.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §8.8, pp. 266–268. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this part of the analysis, gathered here from across the manual in the November 2026 restructure: 18 tools (12 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).
Each app runs in a web browser on a desktop or a phone, with nothing to install. How to use the apps (1.0.3).
| Data Templates | |||
|---|---|---|---|
| DT | Data — Culvert SettlementUsed in Chapter 2.1, 2.1.5 Drainage Elements; Chapter 6.2, 6.2.7 Total Settlement and Angular Distortion | Calculator ▸ | Guide |
| Field Forms & Logs | |||
| FF | Field Observation DataUsed in Chapter 3.8, 3.8.14 Monitoring and Early-Warning Indicators; Chapter 5.3, 5.3.6 Settlement Monitoring; Chapter 6.2, 6.2.7 Total Settlement and Angular Distortion | Calculator ▸ | Guide |
| Pavements, Subgrade & Frost | |||
| PV | Frost Penetration — Berggren EquationUsed in Chapter 2.3, 2.3.5 Subgrade Failure Modes; Chapter 7.3, 7.3.5 Frost Design | Calculator ▸ | Guide |
| PV | Frost Penetration — Stefan EquationUsed in Chapter 2.3, 2.3.5 Subgrade Failure Modes; Chapter 7.3, 7.3.5 Frost Design | Calculator ▸ | Guide |
| PV | Percent Saturation — Subgrade SamplesUsed in Chapter 2.3, 2.3.5 Subgrade Failure Modes; Chapter 5.2, 5.2.3 Test Methods — ASTM Standards and English Unit Outputs | Calculator ▸ | Guide |
| PV | RR Train Loads on SubgradeUsed in Chapter 2.3, 2.3.2 Load Distribution — Talbot Method | Calculator ▸ | Guide |
| Soil & Rock Properties | |||
| SP | Atterberg Limits — Plasticity ChartUsed in Chapter 2.2, 2.2.3 Atterberg Limits (ASTM D4318); Chapter 5.2, 5.2.3 Test Methods — ASTM Standards and English Unit Outputs | Calculator ▸ | Guide |
| SP | GradationUsed in Chapter 2.2, 2.2.2 Grain-Size Analysis | guide only | Guide |
| Settlement & Heave | |||
| ST | Consolidation Index CorrelationsUsed in Chapter 2.2, 2.2.3 Atterberg Limits (ASTM D4318); Chapter 5.2, 5.2.3 Test Methods — ASTM Standards and English Unit Outputs | guide only | Guide |
| ST | Consolidation Settlement — Strip FootingUsed in Chapter 6.2, 6.2.4 Primary Consolidation Settlement | Calculator ▸ | Guide |
| ST | HS20-44 Influence Pressuresneeds workUsed in Chapter 2.1, 2.1.7 Structural Foundations Supporting or Adjacent to the Track | Calculator ▸ | Guide |
| ST | Heave CalculationsUsed in Chapter 3.8, 3.8.2 Track Substructure Failure Mechanisms; Chapter 6.2, 6.2.7 Total Settlement and Angular Distortion | Calculator ▸ | Guide |
| ST | Settlement — Fill + Cut over CulvertUsed in Chapter 2.1, 2.1.5 Drainage Elements | guide only | Guide |
| ST | Settlement — Fill + Cut, InfiniteUsed in Chapter 6.2, 6.2.4 Primary Consolidation Settlement | guide only | Guide |
| ST | Settlement — Fill + Cut, Non-symmetric TrapezoidUsed in Chapter 2.1, 2.1.2 Embankments; Chapter 6.2, 6.2.4 Primary Consolidation Settlement; Chapter 7.2, 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading | Calculator ▸ | Guide |
| ST | Settlement — Rectangular FootingUsed in Chapter 6.2, 6.2.3 Immediate (Elastic) Settlement | guide only | Guide |
| ST | Vertical Induced Pressures (Influence Factors)Used in Chapter 2.1, 2.1.7 Structural Foundations Supporting or Adjacent to the Track; Chapter 3.9, 3.9.5 Boring Depth Planning — Criteria and Equations (English Units); Chapter 6.2, 6.2.2 Stress Increase in Soil — Boussinesq Distribution | Calculator ▸ | Guide |
| ST | Wick Drain SpacingUsed in Chapter 6.2, 6.2.8 Preloading and Surcharge Design; Chapter 7.2, 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading | guide only | Guide |
Calculator: Consolidation Settlement and Time Rate (Section 6.2.4.3)
Calculator: Precompression Surcharge (Section 6.2.8.1)
Settlement predictions for an embankment on soft clay are only as good as the soil model, its parameters and how the construction is simulated. Chai and Carter (2011) summarize methods, checked against test embankments and case histories, for predicting deformations of soft ground improved by vertical drains, vacuum consolidation and soil-cement columns. The points below are those most useful for railroad embankments, widenings and approach fills.
Before trusting a numerical model, compare the undrained shear strength profile it implies with field vane, unconfined compression or UU triaxial results. The model, its parameters and the initial stresses (including OCR) together control the strength the model uses; a mismatch here means the predicted settlement and stability will both be wrong. Correct field vane strengths for strain rate (Bjerrum).
For railroad work: When soft ground under a track widening or approach fill is improved, the existing embankment and track beside it move too. Vacuum pulls the edge of the existing embankment inward and can crack it; column installation pushes it outward; both should be predicted, monitored with inclinometers and track geometry surveys, and controlled by sequence and distance from the operating track. When settlement is made up with extra fill or ballast to hold top-of-rail grade, count that fill as load, and remember that fill sinking below the water table becomes buoyant. Check that the drains stop short of an underlying sand where vacuum is used.
Source: Chai and Carter (2011), Chapters 2–5. Full reference under Supplemental References.
Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.
Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.
File locations for these documents are listed under Supplemental References.
Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S7 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S8 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.
The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.