5.1.9 Worked Examples

In situ testing provides continuous or near-continuous soil and rock characterization without the inherent sample disturbance associated with laboratory testing.
Authors: Daniel P. Colwell and Mario Ruel
5.1.9 Worked Examples
The four examples reduce four common in situ tests to design values: CPTu strength in soft clay, vane strength with Bjerrum’s correction, site class from MASW, and subgrade CBR and modulus from a DCP test. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 5.1-1: CPTu Characterization of a Soft Clay

A CPTu sounding supports an embankment widening on a Class I railroad located near Savannah, Georgia. In soft clay the pore pressure acting behind the cone tip is a large share of the measured resistance, so the tip value must be corrected before anything is computed from it.

CrustSoft clay, γ = 108 pcf0510152025303540Depth (ft)GWT 4 ftqc = 4.20 tsf, u2 = 1.80 tsfqt, su, Bq = ?Piezocone soundingGivenAt 22 ft: qc = 4.20 tsf; u2 = 1.80 tsfa = 0.80; Nkt = 14γ = 108 pcf; GWT 4 ftRequiredCorrected tip resistance qt Undrained strength su Pore pressure ratio Bq Black = given; red = required
Given and required for Example 5.1-1.

Given

VariableValueDescription
qc4.20 tsfMeasured tip resistance at 22 ft
u21.80 tsfPore pressure at the shoulder
a0.80Net area ratio
γ108 pcfSoil unit weight
zw4 ftWater table
Nkt14Cone factor

Required

  • Corrected tip resistance qt
  • Undrained strength su
  • Pore pressure ratio Bq

Equations

  1. Eq. 5.1-1: qt = qc + u2(1 − a) — corrected tip resistance
  2. Eq. 5.1-3: su = (qt − σv) / Nkt — undrained strength
  3. Eq. 2: σv = γz; u0 = γw(z − zw)
  4. Eq. 5.1-4: Bq = (u2 − u0) / (qt − σv)

Steps

Step 1 · qt (Eq. 5.1-1)
4.20 + 1.80 × 0.20
qt = 4.56 tsf
↓
Step 2 · Stresses (Eq. 2)
σv = 108 × 22 = 2,376 psf; u0 = 62.4 × 18 = 1,123 psf
σv = 1.188 tsf; u0 = 0.562 tsf; σ′v = 0.626 tsf
↓
Step 3 · su (Eq. 5.1-3)
(4.56 − 1.188) / 14 = 3.372 / 14
su = 0.241 tsf = 482 psf
↓
Step 4 · Bq (Eq. 5.1-4)
(1.80 − 0.562) / 3.372
Bq = 0.37
Spot check: su/σ′v = 0.241/0.626 = 0.38, in the usual range for a normally to lightly overconsolidated clay.
↓
Solution
qt = 4.56 tsf; su = 482 psf; Bq = 0.37.

Solution

qt = 4.56 tsf, su ≈ 480 psf and Bq = 0.37: a soft, normally to lightly overconsolidated clay.

The correction added 0.36 tsf, about 8% of qt but 11% of the net resistance that su comes from; skipping it would overstate the strength. The value goes into the embankment stability analysis (Chapter 6.3). Nkt should be calibrated against vane or laboratory tests on the same clay before design.

Example 5.1-2: Vane Shear Test With Bjerrum’s Correction

Vane tests near the south shore of Lake Erie support an embankment stability check in soft lacustrine clay. The peak and remolded torques give strength and sensitivity; Bjerrum’s correction converts the vane strength to the strength mobilized in an embankment failure.

CrustSoft clay051015202530Depth (ft)Tpeak / Trem = 12.4 / 3.1 lb·ftsu, St, design su = ?Field vane, D = 2.24 in., H/D = 2GivenTpeak = 12.4; Trem = 3.1 lb·ftD = 0.187 ft; H/D = 2PI = 55%Trigger St > 8RequiredPeak and remolded su SensitivityDesign su (Bjerrum)Black = given; red = required
Given and required for Example 5.1-2.

Given

VariableValueDescription
Tpeak, Trem12.4 and 3.1 lb·ftTorques at 18 ft
D2.24 in. = 0.187 ft; H/D = 2Standard vane
PI55%Plasticity index (Chapter 5.2)
ThresholdSt > 8This manual’s trigger for enhanced seismic review

Required

  • Peak and remolded su; sensitivity
  • Design su

Equations

  1. Eq. 5.1-6: su = 6T / (7πD³) — vane strength, H/D = 2
  2. Eq. 5.1-8: St = su,peak / su,remolded — sensitivity
  3. Eq. 5.1-7: su,design = μ su,peak — Bjerrum; μ = 0.85 at PI 40, 0.75 at PI 60, 0.65 at PI 80

Steps

Step 1 · Vane constant
7π × 0.187³ = 7π × 0.00654
0.1438 ft³
↓
Step 2 · Peak and remolded (Eq. 5.1-6)
6 × 12.4 / 0.1438; 6 × 3.1 / 0.1438
517 psf and 129 psf
↓
Step 3 · St (Eq. 5.1-8)
517 / 129
St = 4.0: medium sensitivity, below 8
↓
Step 4 · μ at PI 55% and design su (Eq. 5.1-7)
0.75 + (5/20)(0.10) = 0.78; 0.78 × 517
su,design = 402 psf
Spot check: 517 / 402 = 1.29: the raw vane overstates the strength by about 29%.
↓
Solution
su,design = 402 psf; St = 4.0.

Solution

Peak 517 psf, remolded 129 psf, St = 4.0, and design su = 402 psf.

Using the uncorrected vane strength would overstate the embankment’s stability by nearly 30%. Apply the Bjerrum correction to all vane data used in embankment design. The sensitivity does not reach the enhanced seismic review threshold, but it is high enough that the clay will lose most of its strength if disturbed.

Example 5.1-3: Site Class From an MASW Profile

An MASW survey for a new intermodal facility on a Class I railroad located in the Mid-Continent gives a layered shear wave velocity profile. The site class comes from the time-averaged velocity over the top 100 ft, not the simple average.

Vs = 480 ft/s, γ = 120 pcfVs = 920 ft/sVs = 1,650 ft/sVs = 3,200 ft/s0102030405060708090100Depth (ft)Vs,30 = ? Site class?MASW profile (upper 100 ft)Gmax = ?Given12 ft at 480 ft/s28 ft at 920 ft/s35 ft at 1,650 ft/s25 ft at 3,200 ft/sγ = 120 pcf (upper layer)D: 600–1,200; C: 1,200–2,500 ft/sRequiredVs,30 Site classGmax of the upper layerBlack = given; red = required
Given and required for Example 5.1-3.

Given

VariableValueDescription
Layers12 ft at 480; 28 ft at 920; 35 ft at 1,650; 25 ft at 3,200 ft/sdi and Vsi
γ120 pcfUpper layer, for Gmax
ClassesD: 600 to 1,200 ft/s; C: 1,200 to 2,500 ft/sAASHTO

Required

  • Vs,30 and site class
  • Gmax of the upper layer

Equations

  1. Eq. 5.1-16: Vs,30 = Σdi / Σ(di/Vsi) — time-averaged velocity
  2. Eq. 2: Gmax = (γ/g) Vs²

Steps

Step 1 · Travel times
12/480 + 28/920 + 35/1,650 + 25/3,200 = 0.02500 + 0.03043 + 0.02121 + 0.00781
0.08445 s
↓
Step 2 · Vs,30 (Eq. 5.1-16)
100 / 0.08445
1,185 ft/s: Site Class D, near the C boundary
Spot check: A simple average of the four velocities would give 1,560 ft/s and Class C; the time average gives the soft layers their proper weight.
↓
Step 3 · Gmax (Eq. 2)
(120/32.2) × 480² = 3.727 × 230,400
858,900 psf ≈ 429 tsf
↓
Solution
Vs,30 = 1,185 ft/s, Site Class D.

Solution

Vs,30 = 1,185 ft/s, Site Class D; Gmax of the upper layer ≈ 429 tsf.

Class D calls for the site amplification factors Fa and Fv in seismic design (AREMA Chapter 9; AASHTO). Being within 2% of the Class C boundary, the result is sensitive to the soft top layer; a second MASW line or a downhole test would confirm it before the class is fixed. Gmax is the small-strain stiffness; the operating stiffness under heavy axle loads is lower.

Example 5.1-4: Subgrade Strength from a DCP Test in a Crib Dig

A section of main track on a Class I railroad located in the Ohio Valley needs surfacing every few months, and the ballast at the shoulder is stained with clay. During a track window the ballast is removed from one crib and a DCP is driven through the subballast into the subgrade. The example shows how a DCP record becomes the CBR and modulus values that the trackbed design uses, and why the subgrade soil type must be known before the correlation is chosen.

TieTie BallastBallast Crib dig(ballast removed) Subballast (sand and gravel) Subgrade (lean clay, CL) 17.6-lb hammer, 22.6-in. drop 8 in.16 blows 12 in.8 blows GIVEN Subballast: 8 in. in 16 blows Subgrade (CL): 12 in. in 8 blows ASTM D6951 DPI–CBR correlations Design assumed subgrade Mr = 6,000 psi REQUIRED DPI of each layer (in./blow) CBR of each layer Resilient modulus Mr of each layer Is the design subgrade modulus met? Figure 5.1-16. DCP test at the bottom of a crib dig: the Given (layer penetrations and blows) and the Required.

Given

VariableValueDescription
Layer 18 in. in 16 blowsSubballast, well-graded sand and gravel
Layer 212 in. in 8 blowsSubgrade, lean clay (CL), from a hand-auger sample
Mr,design6,000 psiSubgrade modulus assumed in the original granular layer design

Required

  • DCP index of each layer
  • CBR of each layer
  • Resilient modulus of each layer, and whether the subgrade meets the design value

Equations

  1. Eq. 5.1-20: DPI = penetration / blows — in./blow
  2. Eq. 5.1-21: CBR = 7.80 / DPI1.12 (IS-26) — ASTM D6951 general correlation (written for DPI in in./blow); all soils except CH, and CL with CBR below 10
  3. Eq. 5.1-22: CBR = 5.35 / DPI2 (IS-27) — ASTM D6951 correlation for CL with CBR below 10 (DPI in in./blow)
  4. Eq. 5.1-23: Mr = 2,555 × CBR0.64 (IS-28) — psi (AASHTO mechanistic-empirical design guide)

Steps

Step 1 · DPI (Eq. 5.1-20)
Subballast 8 / 16; subgrade 12 / 8
0.50 and 1.50 in./blow
↓
Step 2 · Subballast CBR (Eq. 5.1-21)
0.501.12 = 0.460; 7.80 / 0.460
CBR = 17
↓
Step 3 · Subgrade CBR: which equation?
General equation: 1.501.12 = 1.575; 7.80 / 1.575 = 4.95. Below 10 in CL, so Eq. 5.1-22 governs: 5.35 / 1.502 = 5.35 / 2.25
CBR = 2.4
Spot check: the general equation would have doubled the subgrade CBR. Classifying the subgrade changed the answer more than any other input.
↓
Step 4 · Moduli (Eq. 5.1-23)
Subballast: 170.64 = 6.12; 2,555 × 6.12. Subgrade: 2.40.64 = 1.75; 2,555 × 1.75
15,600 psi and 4,450 psi
Spot check: the older rule Mr ≈ 1,500 × CBR gives 3,600 psi for the subgrade, the same order. Both are well below 6,000 psi.
↓
Solution
Subballast CBR 17, Mr ≈ 15,600 psi; subgrade CBR 2.4, Mr ≈ 4,500 psi, below the 6,000 psi design value.

Solution

The subballast is adequate (CBR about 17); the subgrade is not (CBR about 2.4, Mr about 4,500 psi against 6,000 psi assumed).

The test points to the subgrade, not the ballast, as the cause of the repeated surfacing. That changes the fix: cleaning or replacing ballast would not last. The low modulus goes into the granular layer thickness check (Chapter 2.1, Section 2.1.17) to find the subballast thickness that keeps subgrade stress within its allowable value, and into the track substructure assessment (Chapter 2.3). One crib is one point: repeat the test at several cribs, chosen from GPR or track geometry records, and check the CBR of the clay in the laboratory before a design is fixed. Because CBR here is a correlated value, record it as such in the risk rating.

Empirical equation note · this example

Equations 5.1-21 to 5.1-23 are correlations. The DCP–CBR equations are converted from ASTM D6951 (which uses mm/blow) to in./blow; the modulus equation is from the AASHTO mechanistic-empirical pavement design guide. Use them for soils within their range and confirm with laboratory CBR or resilient modulus tests.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-12 Corrected cone resistance qₜUse: All piezocone (CPTu) soundings; essential in soft clays and silts. Limits: Correction negligible in clean sands; critical in soft fine-grained soils. Requires u2 filter position.
  • IS-14 Undrained shear strength from CPT SᵤUse: Fine-grained soils penetrated undrained (Ic > ~2.6). Limits: Nkt depends on reference test (vane, CIUC, DSS) and plasticity; calibrate locally. Use Nkt toward upper end for conservative Su.