5.1.6 Multichannel Analysis of Surface Waves (MASW)

In situ testing provides continuous or near-continuous soil and rock characterization without the inherent sample disturbance associated with laboratory testing.
Authors: Daniel P. Colwell and Mario Ruel
5.1.6 Multichannel Analysis of Surface Waves (MASW)
At a glance. Provides: Shear wave velocity profile, Gmax and Vs,30. Used for: Seismic site class, corridor screening for soft ground, and dynamic stiffness. Catalogue entry
5.1.6.1 Principle and Equipment

MASW (no dedicated ASTM standard; see Park, Miller and Xia 1999) measures the dispersion of Rayleigh surface waves to derive a shear-wave velocity (V_s) profile with depth. A linear array of 24 or more 4.5-Hz vertical geophones spaced 3.3–9.8 ft apart is deployed at the surface. An impact source (sledgehammer, weight drop) generates surface waves. The dispersion curve is inverted to yield V_s versus depth.

In Situ & Geophysical Methods — SPT, MASW, SRT, ERT, CHST, DHST, PIT
In Situ & Geophysical Methods — SPT, MASW, SRT, ERT, CHST, DHST, PIT

MASW is a non-invasive option for mainline subgrade rehabilitation projects where track occupancy windows limit drilling. It is also used for track-structure interaction studies, for permafrost boundary mapping and for muskeg (peat bog) thickness profiling.

5.1.6.2 Small-Strain Shear Modulus

No additional content.

Equation 5.1-15 — Small-Strain Shear Modulus:

G_max = ρ × V_s²

Where:

  • G_max = small-strain shear modulus (psf)
  • ρ = soil mass density (slug/ft³) = γ / g = γ (pcf) / 32.2 (ft/s²)
  • V_s = shear-wave velocity (ft/s)

Example: For a sand with γ = 120 pcf and V_s = 820 ft/s:

  • ρ = 120 / 32.2 = 3.727 slug/ft³
  • G_max = 3.727 × (820)² = 3.727 × 672,400 ≈ 2,506,000 psf ≈ 1,253 tsf

G_max is the input stiffness for dynamic track-subgrade interaction models commonly used for high-axle-load corridors (315K GRL).

Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
Gmaxρ × V_s²Another equationGmax = ρVs2 = (γ/g)Vs2, from measured Vs.by USCS group
ρsoil mass density (slug/ft³)Another equationComputed: ρ = γ / g = γ (pcf) / 32.2 (ft/s²)project-specific
Vsshear-wave velocity (ft/s)Field testSeismic CPT, downhole or crosshole (ASTM D4428 / D7400), or MASW surface waves.soft clay 250–500, dense sand 800–1,600 ft/s · by USCS group
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
Cross-hole Seismic Test (chst)
Cross-hole Seismic Test (chst)
5.1.6.3 AASHTO / AREMA Site Class from V_s,30

The AASHTO seismic site classification is based on the time-averaged shear-wave velocity in the upper 100 ft, V_s,30:

Equation 5.1-16 — Time-Averaged V_s in Upper 100 ft:

V_s,30 = Σd_i / Σ(d_i / V_si)

Where d_i and V_si are thickness (ft) and shear-wave velocity (ft/s) of each layer in the upper 100 ft.

Site ClassV_s,30 (ft/s)Description
A> 5,000Hard rock
B2,500–5,000Rock
C1,200–2,500Very dense soil / soft rock
D600–1,200Stiff soil
E< 600Soft clay
F—Special study required

AREMA MRE Chapter 9 (Seismic Design for Railway Structures) uses site classes of the same AASHTO/NEHRP form. MASW is the most practical tool for establishing site class when bedrock is too deep for refraction and borings are not available at every bridge location.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Vsshear-wave velocityField testSeismic CPT, downhole or crosshole (ASTM D4428 / D7400), or MASW surface waves.soft clay 250–500, dense sand 800–1,600 ft/s · by USCS group